Valve well system

By setting up drainage and ventilation wells inside the working well, a valve well system with both drainage and ventilation functions is formed, which solves the problem of resource waste caused by the backfilling and abandonment of the working well, realizes the reuse and safe maintenance of the working well, and reduces construction costs.

CN118911202APending Publication Date: 2024-11-08BEIJING INST OF WATER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411177127.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

After the water pipeline is laid, the working wells, which used a lot of high-quality building materials, are backfilled and abandoned, resulting in a waste of resources.

Method used

A drainage well and two venting wells are installed inside the working well. The water supply pipe is connected to the drainage well through the drainage pipe equipped with a shut-off valve. The venting wells are connected to the water supply pipes respectively. Backfill soil is used to fill the vacant area not occupied by the facilities, forming a valve well system that combines drainage and venting functions.

Benefits of technology

This approach enables the reuse of working wells, prevents resource waste, meets the functional requirements of the valve well system while also taking into account the operational and maintenance needs of the project, ensures project safety, and saves investment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911202A_ABST
    Figure CN118911202A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of working well recycling, in particular to a valve well system. The valve well system comprises a working well, backfill soil, a drainage well, two water conveying pipes and two exhaust wells. The working well comprises a working well wall and a mounting chamber, the working well wall comprises a working well bottom wall and a working well peripheral wall, the two water conveying pipes penetrate through the working well peripheral wall in a sealed mode in the width direction of the working well, and the water conveying pipes are located above the working well bottom wall and fixedly connected with the working well bottom wall; the two exhaust wells are respectively communicated with the two water conveying pipes so as to exhaust air in the water conveying pipes; the drainage well is arranged in the mounting chamber and located between the two water conveying pipes and between the two exhaust wells, and the water conveying pipes are communicated with the drainage well through a drainage pipe provided with a stop valve; and the backfill soil is filled in all the free areas of the mounting chamber. The working well is transformed into a valve well system which has drainage and exhaust functions and is compact in structure, the working well is reused, and resource waste is prevented.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of working well recycling, and in particular to a valve well system. Background Art

[0002] With the development of cities, there are more and more ground buildings and facilities. Water pipes can no longer be laid in cities by excavating the ground. Otherwise, it will cause damage to the ground buildings and facilities, and may also have a great impact on traffic and the surrounding environment. Therefore, trenchless construction is usually used to lay water pipes in cities.

[0003] The most commonly used trenchless construction method is pipe jacking, which requires the construction of multiple working wells in sequence along the pipeline design route, and then the water pipes are passed through the working wells; after the water pipes are laid, the working wells are completely backfilled.

[0004] Since the high-thrust jacking cylinder used for pipe jacking construction needs to be installed on the side wall of the working well, high-quality reinforced concrete materials are needed to build a solid and firm working well wall (the working well wall includes the working well perimeter wall and the working well bottom wall) when building the working well. However, after the water pipes are laid, these working wells that use a large amount of high-quality building materials will be backfilled and abandoned, resulting in a waste of resources. Therefore, industry personnel are currently researching and exploring the reuse of working wells. Summary of the invention

[0005] One problem to be solved by the present invention is that after the water pipes are laid, the working wells in which a large amount of high-quality building materials are used will be backfilled and abandoned, resulting in a waste of resources.

[0006] In order to at least partially solve the above problems, the present invention provides a valve well system, which includes a working well, backfill soil, a drainage well, two water pipes and two exhaust wells; the working well includes a working well wall and an installation chamber, the working well wall includes a working well bottom wall and a square cylindrical working well peripheral wall, the working well peripheral wall circumferentially surrounds the installation chamber, and the working well bottom wall is fixedly connected to the bottom of the working well peripheral wall; the two water pipes are sealed and pass through the working well peripheral wall along the width direction of the working well, and the two water pipes are spaced apart along the length direction of the working well, the water pipes are located above the working well bottom wall and are fixedly connected to the working well bottom wall; the exhaust well is arranged in the installation chamber, the two exhaust wells are spaced apart along the length direction of the working well, and the two exhaust wells are respectively connected to the two water pipes so as to be able to discharge the air in the water pipes; the drainage well is arranged in the installation chamber, the drainage well is located between the two water pipes and between the two exhaust wells, and the water pipe is connected to the drainage well through a drainage pipe provided with a stop valve; the backfill soil is filled in all the idle areas of the installation chamber.

[0007] In some embodiments, the drainage well includes a first well chamber, a second well chamber, a well bottom wall, a well cover and a square cylindrical well peripheral wall; the well bottom wall is fixedly installed on the top surface of the working well bottom wall, the bottom of the well peripheral wall is sealed and fixedly connected to the well bottom wall, the bottom of the well peripheral wall is sealed and fixedly connected to the well cover, the well peripheral wall surrounds the first well chamber and the second well chamber, the first well chamber and the second well chamber are distributed in sequence along the width direction of the working well, and the first well chamber and the second well chamber are isolated from each other by a partition wall; the well cover covers the top of the well peripheral wall, the well cover is provided with two first manhole structures and two first ventilation structures, the two first manhole structures are respectively connected to the first well chamber and the second well chamber, and the two first ventilation structures are respectively connected to the first well chamber and the second well chamber; the drainage pipe passes through the well peripheral wall, the first well chamber and the partition wall in sequence, and the drainage pipe is connected to the second well chamber, and the stop valve is located in the first well chamber.

[0008] In some embodiments, a concrete platform fixedly connected to the bottom wall of the well is provided in the first well chamber, a drainage pipe passes through the concrete platform, a stop valve is located between the concrete platform and the partition wall, and the drainage pipe is connected to the bottom of the second well chamber; an outlet pipe is provided at the top of the peripheral wall of the well, the bottom end of the outlet pipe is connected to the top of the second well chamber, and the top of the outlet pipe is used to connect to an external sewage pipe.

[0009] In some embodiments, a sump is provided at the top of the bottom wall of the water well, the sump is located between the concrete platform and the partition wall, the opening of the sump is directly opposite to the stop valve, and a grate is provided at the top of the sump.

[0010] In some embodiments, in the width direction of the working well, the outer side surface of the water well peripheral wall is connected and fit with the inner side surface of the working well peripheral wall; and / or, the first well chamber and the second well chamber are respectively provided with vertically extending escalators, and the escalators are fixedly connected to the water well peripheral wall; and / or, the top surface of the water well cover is lower than the top surface of the working well.

[0011] In some embodiments, the exhaust well includes a vertically extending exhaust pipe, which is arranged in the installation room. The exhaust pipe is separated from the drainage well in the length direction of the working well; the bottom end of the exhaust pipe is connected to the top of the water pipe, and the top end of the exhaust pipe is provided with an exhaust valve that only allows gas to be discharged.

[0012] In some embodiments, the water well peripheral wall includes two first water well wall panels spaced apart in the length direction of the working well; the valve well system also includes two encapsulation walls, the two encapsulation walls are respectively connected and fitted with the outer side surfaces of the two first water well wall panels, the encapsulation walls are spaced apart from the portion of the working well peripheral wall in the length direction of the working well, and the two sides of the encapsulation walls in the width direction of the working well are respectively fixedly connected to the working well peripheral wall; the top surface of the encapsulation wall is lower than the top surface of the first water well wall panel, two water pipes respectively pass through the two encapsulation walls horizontally, two exhaust pipes respectively pass through the two encapsulation walls vertically, the exhaust valve is located above the encapsulation wall, and the thickness of the encapsulation wall is greater than the outer diameter of the water pipe and the outer diameter of the exhaust pipe.

[0013] In some embodiments, the valve well system also includes two inspection wells, which are located in the installation room. The two inspection wells are fixedly connected to the top of the two enclosing walls, and the two exhaust valves are respectively located inside the two inspection wells; the inspection well is provided with a second manhole structure and a second ventilation structure connected to the interior thereof.

[0014] In some embodiments, the inspection well includes an inspection room, an inspection well bottom wall, an inspection well cover and an inspection well peripheral wall; the inspection well bottom wall is fixedly connected to the top of the enclosing wall, the bottom of the inspection well peripheral wall is fixedly connected to the inspection well bottom wall, and the inspection well peripheral wall surrounds the inspection room; the inspection well cover covers the top of the inspection well peripheral wall, and the inspection well cover is provided with a second manhole structure and a second ventilation structure, and the second manhole structure and the second ventilation structure are respectively connected to the inspection room; the exhaust pipe runs through the corresponding inspection well bottom wall, and the exhaust valve is located in the corresponding inspection room, and the inspection room is provided with a ladder fixedly connected to the inspection well peripheral wall.

[0015] In some embodiments, the side of the inspection well wall facing the drainage well is fixedly connected to the first water well wall panel and fits together, the side of the inspection well wall facing away from the drainage well is fixedly connected to the working well wall and fits together, and backfill soil is filled between the bottom wall of the inspection well and the bottom wall of the working well.

[0016] The above technical solution of the present invention has the following beneficial effects:

[0017] A drainage well and two exhaust wells are arranged in the installation room of the working well. The water pipe is connected to the drainage well through a drainage pipe provided with a stop valve, and the water in the water pipe can be discharged into the drainage well through the drainage pipe, so that the staff can inspect and repair the emptied water pipe. The two exhaust wells are respectively connected to the two water pipes, and the air in the water pipe can enter the exhaust well and be discharged, so that the water in the water pipe can flow stably. The idle areas of the installation room that are not occupied by various facilities are all filled with backfill soil, and the top surface of the backfill soil is flush with the ground, so that the valve well system is integrated into the surrounding land. Therefore, the present invention makes full use of the original structure of the working well, and sets a drainage well and two exhaust wells connected to the water pipe in the working well, thereby transforming the working well into a valve well system with both drainage and exhaust functions and a compact structure, so as to reuse the working well and prevent waste of resources. Moreover, on the premise of meeting the functions of the valve well system, the requirements for engineering operation and maintenance are taken into account, the safety of the project is guaranteed, and investment is saved. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 is a schematic top view of a valve well system in one embodiment of the present invention;

[0019] Figure 2 yes Figure 1 A schematic diagram of a vertical section along line AA;

[0020] Figure 3 yes Figure 1 A schematic diagram of a vertical section along line BB;

[0021] Figure 4 yes Figure 1 A schematic diagram of a vertical section along line CC;

[0022] Figure 5 yes Figure 1 A schematic diagram of a vertical section along line DD;

[0023] Figure 6 yes Figure 1 Schematic diagram of the vertical section along line EE.

[0024] Description of Reference Numerals

[0025] 1. working well; 11. installation room; 12. bottom wall of working well; 13. peripheral wall of working well; 131. first working well wall panel; 132. second working well wall panel;

[0026] 2. Backfill soil;

[0027] 3. Drainage well; 31. First well chamber; 311. Sump; 32. Second well chamber; 321. Outlet pipe; 33. Bottom wall of well; 34. Well cover; 341. First manhole structure; 342. First ventilation structure; 35. Peripheral wall of well; 351. First well wall panel; 352. Second well wall panel; 36. Partition wall; 37. Concrete platform; 38. Escalator;

[0028] 4. Water pipe; 41. Drain pipe; 42. Stop valve;

[0029] 5. Exhaust well; 51. Exhaust pipe; 52. Exhaust valve;

[0030] 6. Encapsulation wall;

[0031] 7. Inspection shaft; 71. Inspection room; 72. Inspection shaft bottom wall; 73. Inspection shaft cover; 731. Second manhole structure; 732. Second ventilation structure; 74. Inspection shaft peripheral wall; 75. Ladder. DETAILED DESCRIPTION

[0032] The features and exemplary embodiments of various aspects of the present invention will be described in detail below. In order to make the purpose, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be understood that the specific embodiments described herein are only intended to explain the present invention, rather than to limit the present invention. For those skilled in the art, the present invention can be implemented without the need for some of these specific details. The following description of the embodiments is only to provide a better understanding of the present invention by illustrating examples of the present invention.

[0033] like Figures 1 to 6 As shown, the present invention provides a valve well system, which includes a working well 1, backfill soil 2, a drainage well 3, two water pipes 4 and two exhaust wells 5. The working well 1 includes a well wall of the working well 1 and an installation room 11. The well wall of the working well 1 includes a working well bottom wall 12 and a square cylindrical working well peripheral wall 13. The working well peripheral wall 13 surrounds the installation room 11 in a circumferential direction. The working well bottom wall 12 is fixedly connected to the bottom of the working well peripheral wall 13. The two water pipes 4 pass through the working well peripheral wall 13 in a sealed manner along the width direction W of the working well 1, and the two water pipes 4 are spaced apart along the length direction L of the working well 1. The water pipes 4 are located above the working well bottom wall 12 and are fixedly connected to the working well bottom wall 12. An exhaust well 5 is arranged in the installation room 11, and two exhaust wells 5 are spaced apart along the length direction L of the working well 1. The two exhaust wells 5 are respectively connected to two water pipes 4 so as to discharge the air in the water pipes 4; a drainage well 3 is arranged in the installation room 11, and the drainage well 3 is located between the two water pipes 4 and between the two exhaust wells 5. The water pipe 4 is connected to the drainage well 3 through a drainage pipe 41 provided with a stop valve 42; backfill soil 2 is filled in all the vacant areas of the installation room 11.

[0034] Specifically, a drainage well 3 and two exhaust wells 5 are arranged in the installation room 11 of the working well 1. The water pipe 4 is connected to the drainage well 3 through a drainage pipe 41 provided with a stop valve 42, and the water in the water pipe 4 can be discharged into the drainage well 3 through the drainage pipe 41, so that the staff can inspect and repair the emptied water pipe 4. The two exhaust wells 5 are respectively connected to the two water pipes 4, and the air in the water pipe 4 can enter the exhaust well 5 and be discharged, so that the water in the water pipe 4 can flow stably. The idle area of ​​the installation room 11 that is not occupied by various facilities is completely filled with backfill soil 2, and the top surface of the backfill soil 2 is flush with the ground, so that the valve well system is integrated into the surrounding land. Therefore, the present invention makes full use of the original structure of the working well 1, and sets a drainage well 3 and two exhaust wells 5 connected to the water pipe 4 in the working well 1, thereby transforming the working well 1 into a valve well system with both drainage and exhaust functions and a compact structure, so that the working well 1 can be reused to prevent waste of resources. Moreover, on the premise of meeting the functions of the valve well system, it also takes into account the project operation and maintenance requirements, ensures project safety and saves investment.

[0035] In addition, it is usually necessary to separately set up a drainage device and an exhaust device on the pipeline of the water pipe 4. The water in the water pipe 4 can be discharged into the drainage device to facilitate the inspection of the emptied water pipe 4. The air in the water pipe 4 can enter the exhaust device and be discharged by the exhaust device. The drainage device and the exhaust device are made of steel and reinforced concrete materials. The present invention integrates the drainage well 3 and the exhaust well 5 in the working well 1 to form a valve well system, and the overall structure of the valve well system is relatively simple, and the overall construction cost is not actually increased. Since the original structure of the working well 1 is fully utilized, the overall construction cost can be reduced to a certain extent and resources can be prevented from being wasted.

[0036] like Figure 1 and Figure 5 As shown, in some embodiments of the present invention, the drainage well 3 includes a first well chamber 31, a second well chamber 32, a well bottom wall 33, a well cover 34 and a square cylindrical well peripheral wall 35. The well bottom wall 33 is fixedly mounted on the top surface of the working well bottom wall 12, the bottom of the well peripheral wall 35 is sealed and fixedly connected to the well bottom wall 33, the bottom of the well peripheral wall 35 is sealed and fixedly connected to the well cover, the well peripheral wall 35 surrounds the first well chamber 31 and the second well chamber 32, the first well chamber 31 and the second well chamber 32 are sequentially distributed along the width direction W of the working well 1, and the first well chamber 31 and the second well chamber 32 are isolated from each other by a partition wall 36. The water well cover 34 covers the top of the water well peripheral wall 35, and is provided with two first manhole structures 341 and two first ventilation structures 342. The two first manhole structures 341 are respectively connected to the first well chamber 31 and the second well chamber 32, and the two first ventilation structures 342 are respectively connected to the first well chamber 31 and the second well chamber 32. The drainage pipe 41 passes through the water well peripheral wall 35, the first well chamber 31 and the partition wall 36 in sequence, and the drainage pipe 41 is connected to the second well chamber 32, and the stop valve 42 is located in the first well chamber 31.

[0037] Specifically, when the water pipe 4 needs to be inspected, the staff enters the first well chamber 31 through the first manhole structure 341, opens the stop valve 42, and the water in the water pipe 4 flows into the second well chamber 32 under the action of its own weight, and then temporarily stores in the second well chamber 32; then the staff can enter the second well chamber 32 through another first manhole structure 341, and then put the sewage pump into the second well chamber 32, so that the water outlet end of the water pipe of the sewage pump is connected to the external sewage pipe; then the sewage pump can pump the water in the second well chamber 32 to the external sewage pipe. The first well chamber 31 and the second well chamber 32 are isolated from each other to prevent the water in the second well chamber 32 from entering the first well chamber 31. When the water pipe 4 is inspected, the staff enters the first well chamber 31 through the first manhole structure 341 and closes the stop valve 42. Therefore, the first well chamber 31 can provide protection for the staff and provide installation space for the stop valve 42. The first ventilation structure 342 can realize ventilation between the first well chamber 31 and the second well chamber 32 and the outside, and prevent the harmful gas from gradually accumulating in the first well chamber 31 and the second well chamber 32. In addition, the first well chamber 31 and the second well chamber 32 are sequentially distributed along the width direction W of the working well 1, the structure layout of the drainage well 3 is compact, and sufficient space is reserved in the installation room 11 to set the exhaust well 5. Therefore, the overall structure of the valve well system is compact and functional.

[0038] It should be noted that the first manhole structure 341 can be any structure that facilitates the staff to enter and exit the first well chamber 31 and the second well chamber 32, and the present invention does not limit it. For example, a manhole structure with a publication number of CN216784499U can be used. In addition, the first ventilation structure 342 can be any structure that can achieve a ventilation function, and the present invention does not limit it. For example, the first ventilation structure 342 can be a ventilation pipe, a filter, or a ventilation manhole cover.

[0039] like Figure 1 , Figure 2 and Figure 5 As shown, in some embodiments of the present invention, a concrete platform 37 fixedly connected to the bottom wall 33 of the water well is provided in the first well chamber 31, a drain pipe 41 passes through the concrete platform 37, a stop valve 42 is located between the concrete platform 37 and the partition wall 36, and the drain pipe 41 is connected to the bottom of the second well chamber 32; a water outlet pipe 321 is provided at the top of the water well peripheral wall 35, the bottom end of the water outlet pipe 321 is connected to the top of the second well chamber 32, and the top of the water outlet pipe 321 is used to connect to an external sewage pipe.

[0040] Specifically, the concrete platform 37 is made of reinforced concrete material. The concrete platform 37 can be a rectangular parallelepiped, and the length, width and height of the concrete platform 37 are greater than the outer diameter of the drain pipe 41. The outlet end of the drain pipe 41 passes through the partition wall 36 and is sealed with the partition wall 36 to prevent water from entering the first well chamber 31. For example, a water stop ring is provided between the outlet end of the drain pipe 41 and the partition wall 36. Preferably, two stop valves 42 are arranged at intervals on the drain pipe 41. In addition, the outlet end of the drain pipe 41 is higher than the bottom wall 33 of the water well to prevent the sludge in the second well chamber 32 from entering the drain pipe 41.

[0041] In this embodiment, the concrete platform 37 can support the drain pipe 41 to a certain height, so as to facilitate the operation of the stop valve 42. In addition, the top surface of the concrete platform 37 is higher than the bottom wall 33 of the water well, so the top surface of the concrete platform 37 can be used as a safe position for the staff. The staff entering the first well chamber 31 can first reach the top surface of the concrete platform 37 to make corresponding work preparations, and then go to the target position to work. In addition, when discharging the water in the second well chamber 32, the staff puts the sewage pump into the bottom of the second well chamber 32, and the water outlet end of the water guide pipe of the sewage pump is connected to the bottom end of the water outlet pipe 321.

[0042] like Figure 5 As shown, in some embodiments of the present invention, a sump 311 is provided on the top of the bottom wall 33 of the water well, the sump 311 is located between the concrete platform 37 and the partition wall 36, the opening of the sump 311 faces the stop valve 42, and a grate is provided on the top of the sump 311.

[0043] Specifically, water leaking from the stop valve 42 or the drain pipe 41 can flow into the sump 311, so that the ground of the first well chamber 31 remains dry. Since a grate is provided on the top of the sump 311, the staff will not step into the sump 311 by mistake after entering the first well chamber 31, thereby preventing danger. When it is necessary to discharge the accumulated water in the sump 311, the grate is removed, and a sewage pump is placed in the sump 311, and the accumulated water in the sump 311 is pumped to the outside of the first well chamber 31 by the sewage pump.

[0044] like Figures 1 to 6 As shown, in some embodiments of the present invention, in the width direction W of the working well 1, the outer side surface of the water well peripheral wall 35 is connected and fitted with the inner side surface of the working well peripheral wall 13.

[0045] Specifically, the water well peripheral wall 35 includes second water well wall panels 352 spaced apart along the width direction W of the working well 1, and the two second water well wall panels 352 are respectively connected to and fitted with the working well peripheral wall 13. At this time, the water well peripheral wall 35 can support the working well peripheral wall 13 to prevent the working well peripheral wall 13 from bending and deforming inward due to the compression of the surrounding soil; and the working well peripheral wall 13 can also strengthen the second water well wall panels 352 of the water well peripheral wall 35, without increasing the thickness of the second water well wall panels 352 by increasing the amount of reinforced concrete, saving building materials and reducing construction costs.

[0046] like Figure 2 , Figure 4 and Figure 5 As shown, in some embodiments of the present invention, vertically extending ladders 38 are respectively provided in the first well chamber 31 and the second well chamber 32 , and the ladders 38 are fixedly connected to the peripheral wall 35 of the water well.

[0047] Specifically, for the first well chamber 31, the top end of the escalator 38 is located at the first manhole structure 341, and the bottom end of the escalator 38 is located at the top surface of the concrete platform 37, so that the staff can enter and exit the first well chamber 31. Therefore, the staff can enter the first well chamber 31 through the first manhole structure 341 and the escalator 38 to switch or overhaul the stop valve 42. The staff can enter the second well chamber 32 through the first manhole structure 341 and the escalator 38, and then place a sewage pump in the second well chamber 32 or clean the sludge in the second well chamber 32.

[0048] In some implementation examples, a concrete platform 37 fixedly connected to the water well bottom wall 33 is also provided in the second well chamber 32. For the second well chamber 32, the top end of the escalator 38 is located at the first manhole structure 341, and the bottom end of the escalator 38 is located at the top surface of the concrete platform 37.

[0049] like Figure 5 As shown, in some embodiments of the present invention, the top surface of the well cover 34 is lower than the top surface of the working well 1, so as to cover the original soil above the well cover 34. Of course, the first manhole structure 341 and the first ventilation structure 342 are higher than the ground to facilitate their functions.

[0050] like Figure 3 and Figure 6 As shown, in some embodiments of the present invention, the exhaust well 5 includes a vertically extending exhaust pipe 51, which is arranged in the installation room 11, and the exhaust pipe 51 is separated from the drainage well 3 in the length direction L of the working well 1; the bottom end of the exhaust pipe 51 is connected to the top of the water pipe 4, and the top end of the exhaust pipe 51 is provided with an exhaust valve 52 that only allows gas to be discharged.

[0051] Specifically, during the process of conveying water in the water pipe 4, a large amount of air may exist in the water due to the water supply source, and the air will gradually gather at the top of the inside of the water pipe 4. If the air accumulates more and more, it will reduce the unit time flow of the water pipe 4 and hinder the stable flow of water, so it is necessary to discharge the air in time to maintain the normal flow of water. Therefore, the bottom end of the exhaust pipe 51 is connected to the top of the water pipe 4 so that the air in the water pipe 4 can enter the exhaust pipe 51 and be discharged from the exhaust valve 52. To prevent water leakage, the exhaust valve 52 only allows gas to be discharged but does not allow water to flow out.

[0052] It is to be noted that the exhaust valve 52 may be any structure capable of achieving the above functions, and the present invention does not limit this. For example, the automatic exhaust valve 52 with publication number CN218761740U may be used.

[0053] like Figures 1 to 4 As shown, in some embodiments of the present invention, the water well peripheral wall 35 includes two first water well wall panels 351 spaced apart in the length direction L of the working well 1. The valve well system also includes two enclosing walls 6, the two enclosing walls 6 are respectively connected and fitted to the outer side surfaces of the two first water well wall panels 351, the enclosing walls 6 are spaced apart from the part of the working well peripheral wall 13 in the length direction L of the working well 1, and the two sides of the enclosing walls 6 in the width direction W of the working well 1 are respectively fixedly connected to the working well peripheral wall 13; the top surface of the enclosing wall 6 is lower than the top surface of the first water well wall panel 351, the two water pipes 4 respectively pass through the two enclosing walls 6 horizontally, the two exhaust pipes 51 respectively pass through the two enclosing walls 6 vertically, the exhaust valve 52 is located above the enclosing wall 6, and the thickness of the enclosing wall 6 is greater than the outer diameter of the water pipe 4 and the outer diameter of the exhaust pipe 51.

[0054] Specifically, the encapsulating wall 6 can be a T-shaped wall, and in the width direction W of the working well 1, the size of the bottom of the encapsulating wall 6 is the same as the size of the first water well wallboard 351, so the two ends of the bottom of the encapsulating wall 6 are respectively fixedly connected to the wall of the working well 1. Of course, the encapsulating wall 6 can also be a wall in a rectangular or trapezoidal shape. Except for the top of the exhaust pipe 51 and the exhaust valve 52, the other parts of the exhaust pipe 51 are completely encapsulated in the encapsulating wall 6, and the encapsulating wall 6 is connected and fitted with the first water well wallboard 351. On the one hand, the encapsulating wall 6 can protect the exhaust pipe 51, and on the other hand, the encapsulating wall 6 can enhance the strength of the first water well wallboard 351, making the water well peripheral wall 35 stronger and firmer. Moreover, the thickness of the encapsulating wall 6 is less than the distance between the first water well wallboard 351 and the working well peripheral wall 13, which can save building materials, and the unoccupied idle area can be filled with backfill soil 2.

[0055] In some embodiments, the working well peripheral wall 13 includes two first working well wall panels 131 spaced apart in the length direction L of the working well 1 and two second working well wall panels 132 spaced apart in the width direction W of the working well 1. The water well peripheral wall 35 includes two first water well wall panels 351 spaced apart in the length direction L of the working well 1 and two second water well wall panels 352 spaced apart in the width direction of the working well 1. The first water well wall panel 351 is spaced apart from the adjacent first working well wall panel 131. The two second water well wall panels 352 are respectively connected and fitted to the two second working well wall panels 132.

[0056] like Figure 1 and Figure 3 As shown, in some embodiments of the present invention, the valve well system further includes two inspection wells 7, the inspection wells 7 are located in the installation room 11, the two inspection wells 7 are respectively fixedly connected to the tops of the two enclosing walls 6, and the two exhaust valves 52 are respectively located inside the two inspection wells 7. The inspection well 7 is provided with a second manhole structure 731 and a second ventilation structure 732 communicated with the inside thereof.

[0057] Specifically, the staff can enter the inspection well 7 through the second manhole structure 731 to inspect the exhaust valve 52. The second ventilation structure 732 is connected to the inside of the inspection well 7, and the inside of the inspection well 7 can be ventilated to the outside. The provision of the inspection well 7 can further fully utilize the space of the installation room 11, making the entire valve well system more integrated and more functional.

[0058] It should be noted that the second manhole structure 731 can be any structural form that facilitates the staff to enter and exit the interior of the inspection well 7, and the present invention does not limit it. For example, the manhole structure with publication number CN216784499U can be used. In addition, the second ventilation structure 732 can be any structural form that can achieve the ventilation function, and the present invention does not limit it. For example, the second ventilation structure 732 can be a ventilation pipe, a filter or a ventilation well cover.

[0059] like Figure 3 and Figure 6 As shown, in some embodiments of the present invention, the inspection well 7 includes an inspection room 71, an inspection well bottom wall 72, an inspection well cover 73 and an inspection well peripheral wall 74. The inspection well bottom wall 72 is fixedly connected to the top of the enclosure wall 6, the bottom of the inspection well peripheral wall 74 is fixedly connected to the inspection well bottom wall 72, and the inspection well peripheral wall 74 surrounds the inspection room 71; the inspection well cover 73 covers the top of the inspection well peripheral wall 74, and the inspection well cover 73 is provided with a second manhole structure 731 and a second ventilation structure 732, and the second manhole structure 731 and the second ventilation structure 732 are respectively connected to the inspection room 71; the exhaust pipe 51 passes through the corresponding inspection well bottom wall 72, and the exhaust valve 52 is located in the corresponding inspection room 71, and the inspection room 71 is provided with a ladder 75 fixedly connected to the inspection well peripheral wall 74.

[0060] Specifically, the staff can enter the inspection room 71 through the second manhole structure 731 and the ladder 75. The inspection room 71 provides a certain inspection space for the staff, which is convenient for the staff to inspect or repair the exhaust valve 52. Moreover, the inspection room 71 is located close to the ground, which is convenient for the staff to enter and exit the inspection room 71.

[0061] In some embodiments of the present invention, the top surface of the inspection well cover 73 is lower than the top surface of the working well 1, so as to cover the original soil above the inspection well cover 73. Of course, the second manhole structure 731 and the second ventilation structure 732 are higher than the ground to facilitate their functions.

[0062] like Figure 3 As shown, in some embodiments of the present invention, the side of the inspection well wall 74 facing the drainage well 3 is fixedly connected to the first water well wall panel 351 and fits together, the side of the inspection well wall 74 facing away from the drainage well 3 is fixedly connected to the working well wall 13 and fits together, and backfill soil 2 is filled between the inspection well bottom wall 72 and the working well bottom wall 12.

[0063] Specifically, the length of the inspection well 7 is greater than the thickness of the first water well wallboard 351, one side of the inspection well 7 is connected and fitted with the first water well wallboard 351 of the water well peripheral wall 35, and the other side of the inspection well 7 is connected and fitted with the first working well wallboard 131 of the working well peripheral wall 13, so that the inspection well 7 is firm. Since the length of the inspection well 7 is relatively large, the inspection space of the inspection well 7 will also be relatively large, which is convenient for the staff to inspect or repair the exhaust valve 52. In addition, the bottom of the inspection well bottom wall 72 is filled with backfill soil 2, which can support the inspection well 7 and make the inspection well 7 more stable.

[0064] This article uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core ideas of the present invention. The above are only preferred implementation methods of the present invention. It should be pointed out that due to the limitations of textual expression, there are objectively infinite specific structures. For ordinary technicians in this technical field, without departing from the principles of the present invention, they can make several improvements, modifications or changes, and can also combine the above technical features in an appropriate manner; these improvements, modifications, changes or combinations, or the direct application of the concept and technical solution of the present invention to other occasions without improvement, should be regarded as the protection scope of the present invention.

Claims

1. A valve well system, characterized in that: It includes a working well (1), backfill soil (2), a drainage well (3), two water pipes (4) and two exhaust wells (5); The working well (1) comprises a working well wall and an installation room (11), wherein the working well wall comprises a working well bottom wall (12) and a square cylindrical working well peripheral wall (13), wherein the working well peripheral wall (13) circumferentially surrounds the installation room (11), and the working well bottom wall (12) is fixedly connected to the bottom of the working well peripheral wall (13); the two water pipes (4) are sealed and pass through the working well peripheral wall (13) along the width direction of the working well (1), and the two water pipes (4) are spaced apart along the length direction of the working well (1), and the water pipes (4) are located above the working well bottom wall (12) and are fixedly connected to the working well bottom wall (12); The exhaust well (5) is arranged in the installation room (11), and the two exhaust wells (5) are spaced apart along the length direction of the working well (1), and the two exhaust wells (5) are respectively connected to the two water pipes (4) so ​​as to be able to discharge the air in the water pipes (4); the drainage well (3) is arranged in the installation room (11), and the drainage well (3) is located between the two water pipes (4) and between the two exhaust wells (5), and the water pipe (4) is connected to the drainage well (3) through a drainage pipe (41) provided with a stop valve (42); the backfill soil (2) is filled in all the vacant areas of the installation room (11).

2. The valve well system according to claim 1, characterized in that: The drainage well (3) comprises a first well chamber (31), a second well chamber (32), a well bottom wall (33), a well cover (34) and a square cylindrical well peripheral wall (35); The water well bottom wall (33) is fixedly mounted on the top surface of the working well bottom wall (12); the bottom of the water well peripheral wall (35) is sealed and fixedly connected to the water well bottom wall (33); the bottom of the water well peripheral wall (35) is sealed and fixedly connected to the well cover; the water well peripheral wall (35) surrounds the first well chamber (31) and the second well chamber (32); the first well chamber (31) and the second well chamber (32) are sequentially distributed along the width direction of the working well (1); and the first well chamber (31) is ) and the second well chamber (32) are isolated from each other by a partition wall (36); the well cover (34) covers the top of the well peripheral wall (35), and the well cover (34) is provided with two first manhole structures (341) and two first ventilation structures (342), the two first manhole structures (341) are respectively connected to the first well chamber (31) and the second well chamber (32), and the two first ventilation structures (342) are respectively connected to the first well chamber (31) and the second well chamber (32); The drainage pipe (41) passes through the water well peripheral wall (35), the first well chamber (31) and the partition wall (36) in sequence, and the drainage pipe (41) is connected to the second well chamber (32), and the stop valve (42) is located in the first well chamber (31).

3. The valve well system according to claim 2, characterized in that: The first well chamber (31) is provided with a concrete platform (37) fixedly connected to the bottom wall (33) of the water well, the drainage pipe (41) passes through the concrete platform (37), the stop valve (42) is located between the concrete platform (37) and the partition wall (36), and the drainage pipe (41) is connected to the bottom of the second well chamber (32); the top of the water well peripheral wall (35) is provided with a water outlet pipe (321), the bottom end of the water outlet pipe (321) is connected to the top of the second well chamber (32), and the top of the water outlet pipe (321) is used to be connected to an external sewage pipe.

4. The valve well system according to claim 3, characterized in that: A sump (311) is provided on the top of the bottom wall (33) of the water well. The sump (311) is located between the concrete platform (37) and the partition wall (36). The opening of the sump (311) faces the stop valve (42). A grate is provided on the top of the sump (311).

5. The valve well system according to claim 3, characterized in that: In the width direction of the working well (1), the outer side surface of the water well peripheral wall (35) is connected and abutted to the inner side surface of the working well peripheral wall (13); And / or, the first well chamber (31) and the second well chamber (32) are respectively provided with vertically extending escalators (38), and the escalators (38) are fixedly connected to the peripheral wall (35) of the water well; And / or, the top surface of the water well cover (34) is lower than the top surface of the working well (1).

6. The valve well system according to claim 2, characterized in that: The exhaust shaft (5) comprises an exhaust pipe (51) extending vertically, the exhaust pipe (51) being arranged in the installation room (11), the exhaust pipe (51) being spaced apart from the drainage shaft (3) in the length direction of the working shaft (1); the bottom end of the exhaust pipe (51) is connected to the top of the water pipe (4), and the top end of the exhaust pipe (51) is provided with an exhaust valve (52) that only allows gas to be discharged.

7. The valve well system according to claim 6, characterized in that: The water well peripheral wall (35) comprises two first water well wall panels (351) spaced apart in the length direction of the working well (1); The valve well system further comprises two enclosing walls (6), the two enclosing walls (6) are respectively connected to and fitted with the outer side surfaces of the two first water well wall panels (351), the enclosing walls (6) are spaced apart from the portion of the working well peripheral wall (13) in the length direction of the working well (1), and the two sides of the enclosing walls (6) in the width direction of the working well (1) are respectively fixedly connected to the working well peripheral wall (13); the top surface of the enclosing wall (6) is lower than the top surface of the first water well wall panel (351), the two water pipes (4) respectively pass through the two enclosing walls (6) horizontally, the two exhaust pipes (51) respectively pass through the two enclosing walls (6) vertically, the exhaust valve (52) is located above the enclosing wall (6), and the thickness of the enclosing wall (6) is greater than the outer diameter of the water pipe (4) and the outer diameter of the exhaust pipe (51).

8. The valve well system according to claim 7, characterized in that: The valve well system further comprises two inspection wells (7), wherein the inspection wells (7) are located in the installation room (11), the two inspection wells (7) are respectively fixedly connected to the tops of the two enclosing walls (6), and the two exhaust valves (52) are respectively located inside the two inspection wells (7); the inspection well (7) is provided with a second manhole structure (731) and a second ventilation structure (732) which are connected to the inside thereof.

9. The valve well system according to claim 8, characterized in that: The inspection well (7) comprises an inspection room (71), an inspection well bottom wall (72), an inspection well cover (73) and an inspection well peripheral wall (74); The bottom wall (72) of the inspection shaft is fixedly connected to the top of the enclosure wall (6); the bottom of the peripheral wall (74) of the inspection shaft is fixedly connected to the bottom wall (72) of the inspection shaft; the peripheral wall (74) of the inspection shaft surrounds the inspection room (71); the inspection shaft cover (73) covers the top of the peripheral wall (74) of the inspection shaft; the inspection shaft cover (73) is provided with the second manhole structure (731) and the second ventilation structure (732); the second manhole structure (731) and the second ventilation structure (732) are respectively connected to the inspection room (71); the exhaust pipe (51) passes through the corresponding bottom wall (72) of the inspection shaft; the exhaust valve (52) is located in the corresponding inspection room (71); the inspection room (71) is provided with a ladder (75) fixedly connected to the peripheral wall (74) of the inspection shaft.

10. The valve well system according to claim 9, characterized in that: The side of the inspection well peripheral wall (74) facing the drainage well (3) is fixedly connected to the first water well wall panel (351) and fits together, and the side of the inspection well peripheral wall (74) facing away from the drainage well (3) is fixedly connected to the working well peripheral wall (13) and fits together, and the backfill soil (2) is filled between the inspection well bottom wall (72) and the working well bottom wall (12).