Anti-seepage repairing method for post-cast top plate of tower crane foundation
By opening a construction groove on the tower crane foundation roof, implanting anchor steel bars and rectangular steel frames, and covering the concrete cover plate and waterproof coil, the crack extension and durability problems in the construction of the tower crane foundation back-poured roof plate are solved, and one-time repair is achieved and long-term anti-seepage effect.
Patent Information
- Application Number
- CN202411110659.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-08
AI Technical Summary
During the construction of the post-pouring roof panel of the tower crane foundation, the existing grouting and repair methods are prone to cause crack extension and durability problems, which cannot be completed at one time and the repair effect gradually decreases, resulting in re-seepage of water.
A rectangular construction groove is opened on the tower crane foundation roof, anchor steel bars are implanted and rectangular steel frames are set up, and filled with cement grouting material is used to cover the rectangular steel plate and concrete cover plate, and waterproof coils are laid to form a fully covered repair structure.
One-time repair is achieved to prevent cracks from extending, and provide long-term anti-seepage effect, good material durability, simple construction and easy operation to ensure construction quality.
Smart Images

Figure CN118911215A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of concrete anti-seepage, in particular to an anti-seepage repair method for a post-cast top plate of a tower crane foundation. Background Art
[0002] A construction tower crane is a lifting and transportation equipment used in high-rise and super-high-rise buildings, and is mainly used in the structural construction stage of the building. In the process of construction, the part of the tower crane foundation that passes through the concrete top plate is often constructed after the tower crane is dismantled. At present, the construction plan for the post-cast top plate of the tower crane foundation usually adopts the construction plan for the top plate post-cast strip. Cracks are often prone to appear at the junction of the new and old concrete, resulting in concrete seepage. In the past, if water seepage occurred in the post-cast top plate of the tower crane foundation, the grouting repair method was usually adopted. The grouting material is polyurethane foaming agent. The following problems exist in the grouting repair: 1) During the grouting process to repair existing cracks, the old cracks may extend and need to be repaired further, and the repair cannot be completed in one go; 2) Due to the durability limitations of grouting materials, the grouting repair effect will gradually decrease over time, eventually leading to water seepage at the repaired site again. Summary of the invention
[0003] The purpose of the present invention is to provide a tower crane foundation post-cast top plate anti-seepage repair method based on the above-mentioned deficiencies of the prior art, to repair the top plate part of the tower crane foundation. This method will not produce new extended cracks during the repair process, the repair is completed in one go, and the repair method has a long-term anti-seepage effect.
[0004] The purpose of the present invention is achieved by the following technical solutions: A tower crane foundation post-cast roof anti-seepage repair method is used to repair the gap between the tower crane foundation post-cast roof and the top plate that are constructed successively, and is characterized by comprising the following steps: A rectangular construction groove is provided on the top plate outside the post-cast top plate of the tower crane foundation; Along the rectangular circumferential direction of the construction trench, a plurality of anchoring steel bars are evenly spaced and implanted inside the construction trench, and a rectangular steel frame is arranged at the anchoring steel bars, wherein the rectangular steel frame connects the plurality of anchoring steel bars to form an integral structure; Filling the construction groove with cement grouting material, wherein the anchoring steel bars and the rectangular steel frame are buried in the cement grouting material; A rectangular steel plate is arranged on the top surface of the rectangular steel frame and the anchoring steel bar, wherein the rectangular steel plate; Cast a concrete cover plate in a rectangular range extending a certain distance around the rectangular steel plate, wherein the concrete cover plate completely covers the rectangular steel plate; The waterproofing membrane is laid, and the waterproofing membrane completely covers the top plate and the concrete cover plate.
[0005] The top plane of the anchoring steel bar is flush with the top plane of the post-cast top plate of the tower crane foundation; the top plane of the rectangular steel frame is flush with the top plane of the anchoring steel bar.
[0006] The anchor steel bars are installed at the four corners and the midpoints of the four sides of the construction groove.
[0007] The rectangular steel frame and the anchoring steel bars are fixedly connected by welding.
[0008] The rectangular steel plate and the rectangular steel frame are fixedly connected by welding.
[0009] The concrete cover slab is constructed by cast-in-place method.
[0010] The waterproof membrane is constructed by wet pasting with cement slurry.
[0011] The advantages of the present invention are: (1) The top plate of the tower crane foundation is fully covered and repaired with steel plates, concrete cover plates and waterproof membranes, which has a better anti-seepage effect. The construction is completed in one go, and there is no need for subsequent repair work on extended cracks.
[0012] (2) The materials used are more durable and can maintain their anti-seepage functionality for a longer period of time, thus maintaining a long-term anti-seepage effect.
[0013] (3) The construction method is simple and easy to operate. The entire construction process is visible, making it easy to monitor the construction quality and ensure the completion effect of the construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a structural schematic diagram of the present invention; Figure 2 It is a schematic diagram of the construction groove in the present invention; Figure 3 It is a schematic diagram of anchoring steel bars in the present invention; Figure 4 It is a schematic diagram of the connection between the new anchoring steel bar and the L-shaped rectangular steel frame in the present invention; Figure 5 It is a schematic diagram of the connection between the L-shaped rectangular steel frame and the rectangular steel plate in the present invention. DETAILED DESCRIPTION
[0015] The features of the present invention and other related features are further described in detail below through embodiments in conjunction with the accompanying drawings to facilitate understanding by those skilled in the art: like Figure 1-5As shown, the marks 1-9 in the figure respectively represent: construction trench 1, anchor steel bar 2, rectangular steel frame 3, cement grouting material 4, rectangular steel plate 5, concrete cover plate 6, waterproof membrane 7, tower crane foundation top plate 8, tower crane foundation post-cast top plate 9.
[0016] Example: Figures 1 to 5 As shown, the anti-seepage repair method for the post-cast top slab of the tower crane foundation in this embodiment is used to carry out anti-seepage repair on the gap between the post-cast top slab 9 of the tower crane foundation and the top slab 8 of the tower crane foundation; in this embodiment, the tower crane foundation top slab 8 and the post-cast top slab 9 of the tower crane foundation refer to the top slabs constructed in the previous and subsequent stages, and both of them serve together as the top slab of the tower crane foundation.
[0017] Specifically, this embodiment includes the following construction steps: 1) A rectangular construction groove 1 is opened on the top plate 8 of the tower crane foundation at a corresponding distance around the post-cast top plate 9 of the tower crane foundation, and the cross section of the construction groove 1 is rectangular.
[0018] 2) Anchor steel bars 2 are implanted in the four corners and the midpoints of each side of the construction trench 1 by planting steel bars. The top plane of the anchor steel bars 2 is flush with the top surface of the tower crane foundation top plate 8, and the anchor steel bars 2 are at a certain distance from the inner wall of the construction trench 1 in the horizontal direction. The inner opening of the rectangular steel frame 3 is welded to the anchor steel bars 2. The anchor steel bars 2 are distributed at the four corners and the midpoints of the four sides of the rectangular steel frame 2, and the top of the rectangular steel frame 2 is flush with the top plane of the anchor steel bars. Cement grouting material 4 is used to fill the construction trench 1. After filling, the filling surface of the construction trench 1 is flush with the top surface of the tower crane foundation top plate 8. The rectangular steel plate 5 covers the inner opening area of the rectangular steel frame 3, and the four sides of the rectangular steel plate 5 correspond to the four sides of the top surface of the rectangular steel frame 3. The rectangular steel plate 5 and the rectangular steel frame 3 are welded by full welding.
[0019] 3) A concrete cover plate 6 is cast within a rectangular range extending a certain distance around the rectangular steel plate 5 , and the concrete cover plate 6 completely covers the rectangular steel plate 5 .
[0020] 4) The waterproof membrane 7 is laid by wet cement pasting, and the waterproof membrane 7 completely covers the tower crane foundation top plate 8 and the concrete cover plate 6.
[0021] In the specific implementation of this embodiment: the cross-section of the rectangular steel frame 5 is L-shaped, and its size is customized according to the position of the anchor steel bar 2. After the inner opening of the rectangular steel frame 5 is welded to the anchor steel bar 2, the top surface of the rectangular steel frame 5 is flush with the top plane of the anchor steel bar 2.
[0022] Although the above embodiments have described in detail the concepts and embodiments of the present invention with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and changes can still be made to the present invention without departing from the scope of the claims, so they are not described one by one here.
Claims
1. A tower crane foundation post-cast roof anti-seepage repair method, used for anti-seepage repair of the gap between the tower crane foundation post-cast roof and the top plate constructed successively, characterized in that: The steps include: A rectangular construction groove is provided on the top plate outside the post-cast top plate of the tower crane foundation; Along the rectangular circumferential direction of the construction trench, a plurality of anchoring steel bars are evenly implanted inside the construction trench, and a rectangular steel frame is arranged at the anchoring steel bars, wherein the rectangular steel frame connects the plurality of anchoring steel bars to form an integral structure; Filling the construction groove with cement grouting material, wherein the anchoring steel bars and the rectangular steel frame are buried in the cement grouting material; A rectangular steel plate is arranged on the top surface of the rectangular steel frame and the anchoring steel bar, wherein the rectangular steel plate; Cast a concrete cover plate in a rectangular range extending a certain distance around the rectangular steel plate, wherein the concrete cover plate completely covers the rectangular steel plate; The waterproofing membrane is laid, and the waterproofing membrane completely covers the top plate and the concrete cover plate.
2. The anti-seepage repair method of the post-cast top plate of a tower crane foundation according to claim 1, characterized in that: The top plane of the anchoring steel bar is flush with the top plane of the post-cast top plate of the tower crane foundation; the top plane of the rectangular steel frame is flush with the top plane of the anchoring steel bar.
3. The anti-seepage repair method of the post-cast top plate of a tower crane foundation according to claim 1, characterized in that: The anchor steel bars are installed at the four corners and the midpoints of the four sides of the construction groove.
4. The anti-seepage repair method of the post-cast top plate of a tower crane foundation according to claim 1, characterized in that: The rectangular steel frame and the anchoring steel bars are fixedly connected by welding.
5. The anti-seepage repair method of the post-cast top plate of a tower crane foundation according to claim 1, characterized in that: The rectangular steel plate and the rectangular steel frame are fixedly connected by welding.
6. The anti-seepage repair method of the post-cast top plate of a tower crane foundation according to claim 1, characterized in that: The concrete cover slab is constructed by cast-in-place method.
7. The anti-seepage repair method of the post-cast top plate of a tower crane foundation according to claim 1, characterized in that: The waterproof membrane is constructed by wet pasting with cement slurry.