Management system and method based on GIL ontology data analysis
Through the analysis of GIL ontology data, electromagnetic signal processing and sensor monitoring are used to solve the problem that traditional systems cannot identify and locate internal local discharge activities, providing accurate fault information, and improving grid stability.
Patent Information
- Application Number
- CN202410955480.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-07-17
AI Technical Summary
Traditional transmission line management systems are unable to locate and identify the specific location and type of internal local discharge activities in GIL, resulting in a lack of accurate information on maintenance work and affecting the stability of the power grid.
Using a management system based on GIL ontological data analysis, the abnormal characteristics of internal localized activity are extracted by collecting and analyzing electromagnetic signals, using discrete Fourier transform and energy spectral density analysis, and the activity position and type are determined through electromagnetic sensor monitoring and matching. .
It realizes accurate positioning and type identification of GIL internal local discharge activities, provides maintenance personnel with accurate troubleshooting and repair information, and improves grid stability.
Smart Images

Figure CN118914768A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of data analysis, and in particular to a management system and method based on GIL ontology data analysis. Background Art
[0002] GIL (Gas Insulated Line) is a high-voltage transmission line. The core is to use special insulating gases, such as hydrogen sulfide gas or sulfur fluoride gas, in the transmission line to replace air as the insulating medium. These special gases have high insulation capacity, allowing the transmission line to operate at a higher voltage, thereby achieving a larger transmission capacity; internal partial discharge is a local discharge phenomenon that occurs inside the gas-insulated transmission line, which can cause insulation damage, trigger equipment failures, and affect the stability of power grid operation;
[0003] Traditional transmission line management systems cannot locate the specific location and type of internal partial discharge activities, and cannot provide accurate information on internal partial discharge activities for relevant maintenance personnel to perform troubleshooting and maintenance work;
[0004] Therefore, people are in urgent need of a management system based on GIL ontology data analysis to solve the above problems. Summary of the invention
[0005] The object of the present invention is to provide a management system based on GIL ontology data analysis to solve the problems raised in the above background technology.
[0006] In order to solve the above technical problems, the present invention provides the following technical solutions:
[0007] A management method based on GIL ontology data analysis, the method comprising the following steps:
[0008] S1. Set a time length, and collect electromagnetic signals of the time length when the GIL works normally and when various types of internal partial discharge activities occur according to the types of internal partial discharge activities in the historical GIL; set a sampling interval according to each electromagnetic signal, sample each electromagnetic signal, perform discrete Fourier transform on each sampled electromagnetic signal, and obtain a transformation sequence of each electromagnetic signal;
[0009] Through Fourier transform, the signal is converted from the time domain to the frequency domain, which has the effect of denoising. At the same time, the frequency components of the signal and the energy distribution of different frequency components in the frequency domain are clearly displayed, which is convenient for extracting the characteristics of the signal;
[0010] S2. Calculate the energy spectrum density of each transformation sequence according to the transformation sequence of each electromagnetic signal, analyze the energy spectrum density, and obtain the corresponding comprehensive energy spectrum density when the GIL works normally and when various types of internal partial discharge activities occur;
[0011] S3. Analyze the difference between the comprehensive energy spectrum density of the electromagnetic signal when various types of internal partial discharge activities of the GIL occur and the comprehensive energy spectrum density of the electromagnetic signal when the GIL works normally, and obtain the abnormal feature set of different types of internal partial discharge activities;
[0012] By analyzing the energy spectrum density, the abnormal characteristics of different types of internal partial discharge activities are extracted to provide a theoretical basis for subsequent matching;
[0013] S4. Collect the line layout of the line to be supervised, establish a line map, mark the branch points in the line map, and set electromagnetic sensors at the locations of the branch points;
[0014] S5. According to the line map, the actual distance between two adjacent branch points in the same line is obtained, the effective monitoring radius of the electromagnetic sensor is collected, and the increase of the electromagnetic sensor is analyzed in combination with the actual distance between two adjacent branch points in the same line, and the added electromagnetic sensor is marked in the line map;
[0015] S6. Monitor the electromagnetic signal of the line to be supervised by electromagnetic sensors. If the radiation intensity of the electromagnetic signal in the line to be supervised detected by two adjacent electromagnetic sensors exceeds a threshold value, it indicates that internal partial discharge activity occurs; according to the moment when the radiation intensity of the electromagnetic signal in the line to be supervised detected by two adjacent electromagnetic sensors exceeds the threshold value, analyze the occurrence position of the current internal partial discharge activity;
[0016] S7. Collect abnormal electromagnetic signals, process the abnormal electromagnetic signals, and obtain an abnormal feature set of the current internal partial discharge activity; match the abnormal feature set of the current electromagnetic signal with abnormal feature sets of different types of internal partial discharge activities to obtain the type of the current internal partial discharge activity.
[0017] According to the above technical solution, in step S1, electromagnetic signals are collected and discrete Fourier transform is performed to obtain the transformation sequence of each electromagnetic signal. The specific process is as follows:
[0018] S1-1, the time length is set to T, and the electromagnetic signal of time length T is collected when M segments of GIL are working normally; according to the type of internal partial discharge activity in the historical GIL, starting from the moment when the electromagnetic signal changes, for each type of internal partial discharge activity, M segments of electromagnetic signals of time length T are collected respectively; wherein T and M are both preset fixed parameters;
[0019] S1-2. According to each electromagnetic signal, collect the highest frequency of each electromagnetic signal, recorded as Said represents the highest frequency of the electromagnetic signal in the i-th segment, i∈[1,(I+1)M], where (I+1)M represents the total number of electromagnetic signals collected, and I represents the number of types of internal partial discharge activities; the sampling interval is set to Said represents the sampling interval of the i-th segment of the electromagnetic signal;
[0020] S1-3, according to Each electromagnetic signal is sampled, and the total number of samples after sampling of each electromagnetic signal is The N i represents the total number of samples of the electromagnetic signal in the i-th segment, Express Round down;
[0021] The sampled electromagnetic signals are subjected to discrete Fourier transform to obtain the transformation sequence of each electromagnetic signal. The formula is as follows:
[0022]
[0023] Among them, the X i [k i ] represents the kth in the transformation sequence corresponding to the i-th segment of the electromagnetic signal i elements, the x i [n i ] represents the nth segment in the original sequence corresponding to the i-th segment of electromagnetic signal i elements, the is the rotation factor, e represents the base of the natural logarithm, j is the imaginary unit, and k i is the frequency parameter and k i ∈[0,N i -1], the n i is the time parameter and n i ∈[0,N i -1].
[0024] According to the above technical solution, in step S2, the comprehensive energy spectrum density is obtained, and the specific process is as follows:
[0025] S2-1. Calculate the energy spectral density of each transformation sequence according to the following formula:
[0026]
[0027]
[0028] Among them, the The kth transformation sequence corresponding to the i-th electromagnetic signal is represented by i The frequency corresponding to the elements, Represents the frequency in the transformation sequence corresponding to the i-th segment of the electromagnetic signal The corresponding energy spectral density, the |X i [k i ]| 2 Represents X i [k i ] is the square of the modulus;
[0029] Obtain the energy spectrum density of the signal to more intuitively distinguish the strength of the frequency in the signal, which is convenient for subsequent screening and conducive to signal identification and classification;
[0030] S2-2, the M-segment electromagnetic signals when the GIL is working normally, and the M-segment electromagnetic signals corresponding to different types of internal partial discharge activities; the same type of electromagnetic signals are frequency matched, and the common frequencies in the M-segment electromagnetic signals of the same type are screened out, and the comprehensive energy spectrum density is calculated according to the following formula:
[0031]
[0032] Among them, the represents the bth electromagnetic signal in the ath category a common frequencies, the categories include electromagnetic signals when the GIL is working normally and electromagnetic signals when the GIL has internal partial discharge activity. Represents the frequency of the electromagnetic signal of the ath category The comprehensive energy spectral density is Indicates the frequency of the electromagnetic signal in segment c The energy spectral density of a∈[1,I+1], b a ∈[1,M a ], c∈[1,M], the M a Represents the number of common frequencies in the electromagnetic signals of the ath category.
[0033] According to the above technical solution, in step S3, the abnormal characteristics of different types of internal partial discharge activities are obtained, and the specific process is as follows:
[0034] S3-1. Based on the comprehensive energy spectrum density, filter out the frequencies where the electromagnetic signal is present when the GIL has internal partial discharge activity but not when it is working normally, and the frequencies where the electromagnetic signal is present when the GIL is working normally and has internal partial discharge activity but does not satisfy the following relationship:
[0035]
[0036] Among them, the Indicates the bth electromagnetic signal in the a category when the GIL has internal partial discharge activity. a(局放)The frequency corresponding to the comprehensive energy spectral density is Indicates the bth electromagnetic signal in the a category representing the normal operation of the GIL a(正常) The frequency corresponding to the comprehensive energy spectral density is Indicates the frequency of the electromagnetic signal when the GIL is working normally The modulus of the integrated energy spectral density is Indicates the frequency of the electromagnetic signal when the GIL has internal partial discharge activity The modulus of the comprehensive energy spectral density, and at this time The α represents a preset fixed parameter;
[0037] S3-2. Filter out the frequencies of different types of internal partial discharge activities and the comprehensive energy spectrum densities corresponding to the frequencies, and form a set of I comprehensive energy spectrum densities as the abnormal feature set of different types of internal partial discharge activities, recorded as set A x , the set A x represents the set of abnormal features of the x-th type of internal partial discharge activity, x∈[1,I];
[0038] Based on comparative analysis, the abnormal characteristics of different types of internal partial discharge activities are obtained, which include the frequency and energy characteristics of the signal. The abnormal characteristics of different partial discharge activities are different.
[0039] According to the above technical solution, the specific process of step S4 is as follows:
[0040] Collect the route layout of the route to be supervised, establish a route map, and mark the branch points in the route map, denoted as P d , the P d represents the d-th branch point in the route map, d∈[1,D] and D is a positive integer;
[0041] In P d Position setting electromagnetic sensor.
[0042] According to the above technical solution, in step S5, the increase in the electromagnetic sensor is analyzed, and the specific process is as follows:
[0043] S5-1. According to the route map, obtain the actual distance between two adjacent branch points on the same route, and convert P d With P d' The actual distance between d' , the P d' Indicates the d'th and P d Adjacent branch points, d'∈[1,D'] and D' is a positive integer; the effective monitoring radius of the electromagnetic sensor is recorded as r; P d With P d' The increase in the electromagnetic sensor between Said Express Round up
[0044] S5-2, if is 1, then it is not in P d With P d' Add an electromagnetic sensor between d The electromagnetic sensor adjacent to the electromagnetic sensor at position P d' Electromagnetic sensors for position;
[0045] like If it is not 1, then in P d With P d' Add an electromagnetic sensor between the two lines and mark the added electromagnetic sensor on the line, denoted as P g , At this time, P d The electromagnetic sensor adjacent to the electromagnetic sensor at position P g Electromagnetic sensors for position;
[0046] P d The adjacent distance between the electromagnetic sensor at the position and the adjacent electromagnetic sensor is recorded as
[0047] According to the above technical solution, in step S6, the occurrence position of the current internal partial discharge activity is analyzed, and the specific process is as follows:
[0048] S6-1. Monitor the electromagnetic signal of the line to be supervised by electromagnetic sensors, collect the radiation intensity of the electromagnetic signal monitored by each electromagnetic sensor during normal operation, take the average value, record it as E, and preset the threshold of the radiation intensity of the electromagnetic signal as E+β, where β is a preset fixed parameter;
[0049] If P d If the radiation intensity of the electromagnetic signal monitored by the electromagnetic sensors at the position and its adjacent positions exceeds E+β, it indicates that internal partial discharge activity occurs;
[0050] S6-2, P d The moment when the electromagnetic sensor at the position detects that the radiation intensity of the electromagnetic signal in the line to be supervised exceeds E+β is recorded as time t0; d The electromagnetic sensor adjacent to the electromagnetic sensor at the position detects that the radiation intensity of the electromagnetic signal in the line to be supervised exceeds E+β, which is recorded as time t1. The occurrence position of the current internal partial discharge activity and P are calculated according to the following formula d The distance between the electromagnetic sensors of the position:
[0051]
[0052] Wherein, l represents the location of the current internal partial discharge activity and P d The distance between the electromagnetic sensors of the position, the v 光 represents the speed of light;
[0053] S6-3, according to l, obtain the occurrence position of the current internal partial discharge activity, in P d The electromagnetic sensors at the position and its adjacent positions are d The electromagnetic sensor distance of the position is l.
[0054] According to the above technical solution, in step S7, the type of the current internal partial discharge activity is obtained, and the specific process is as follows:
[0055] S7-1, according to P d The electromagnetic sensor at the position collects electromagnetic signals of time length T from time t0 as abnormal electromagnetic signals, processes the abnormal electromagnetic signals, and obtains the abnormal feature set of the current internal partial discharge activity, which is recorded as set A 异 ;
[0056] S7-2. According to set A 异 , respectively with the set A x Make a match;
[0057] Filter set A 异 With set A x Satisfied The frequency condition element, the The first in the set of abnormal features representing the xth type of internal partial discharge activity The frequency of the elements, Indicates the first in the abnormal feature set of the current internal partial discharge activity The frequency of the elements, γ is a preset fixed parameter, x∈[1,I], Said Represents the set A x The number of elements in Represents the set A 异 The number of elements of
[0058] The selected elements are calculated according to the following formula:
[0059]
[0060] Among them, the η x Represents the set A 异 With set A x similarity; Indicates the bth x frequencies, and the set A x middle Set A 异 middle Said Represents the set A 异 Medium frequency The corresponding integrated energy spectral density modulus; Represents the set A x Medium frequency The corresponding integrated energy spectral density modulus; the Q x Indicates the number of frequencies screened; b x ∈[1,Q x ];
[0061] According to the calculation results, select η x The type of internal PD activity that corresponds to the value closest to 1 is used as the type of current internal PD activity.
[0062] A management system based on GIL ontology data analysis, the system includes an information collection module, an information processing module and an information display module;
[0063] The information acquisition module is used to acquire various information required by the system; the information processing module is used to store, analyze and transmit various information of each module; and the information display module is used to display various information of the information processing module.
[0064] According to the above technical solution, the information acquisition module includes a historical information unit and a current information unit; the information processing module includes an information storage unit, an information analysis unit and an information transmission unit; the information display module includes an alarm unit and a remote display unit;
[0065] The historical information unit is used to collect historical data information of the GIL, and the current information unit is used to collect current data information of the line to be supervised;
[0066] The information storage unit is used to store various information acquired by the information acquisition module; the information analysis unit is used to analyze various information acquired by the information acquisition module; the information transmission unit is used for information transmission of various modules in the system;
[0067] The alarm unit is used to send out a reminder message when an internal partial discharge activity occurs, and the remote display unit is used to display the location and type of the internal partial discharge activity of the line to be supervised.
[0068] Compared with the prior art, the beneficial effects achieved by the present invention are:
[0069] By analyzing the electromagnetic signals in the GIL body, the present invention not only locates the internal partial discharge activities occurring in the GIL body, but also identifies the types of the internal partial discharge activities, thereby providing accurate information for the troubleshooting and maintenance work of relevant maintenance personnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0070] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0071] Figure 1 It is a flow chart of a management method based on GIL ontology data analysis of the present invention;
[0072] Figure 2 It is a structural schematic diagram of a management system based on GIL ontology data analysis of the present invention. DETAILED DESCRIPTION
[0073] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0074] See also Figure 1 , the present invention provides a technical solution:
[0075] A management method based on GIL ontology data analysis, the method comprising the following steps:
[0076] S1. Set a time length, and collect electromagnetic signals of the time length when the GIL works normally and when various types of internal partial discharge activities occur according to the types of internal partial discharge activities in the historical GIL; set a sampling interval according to each electromagnetic signal, sample each electromagnetic signal, perform discrete Fourier transform on each sampled electromagnetic signal, and obtain a transformation sequence of each electromagnetic signal;
[0077] Through Fourier transform, the signal is converted from the time domain to the frequency domain, which has the effect of denoising. At the same time, the frequency components of the signal and the energy distribution of different frequency components in the frequency domain are clearly displayed, which is convenient for extracting the characteristics of the signal;
[0078] In step S1, electromagnetic signals are collected and discrete Fourier transform is performed to obtain a transformation sequence of each electromagnetic signal. The specific process is as follows:
[0079] S1-1, the time length is set to T, and the electromagnetic signal of time length T is collected when M segments of GIL are working normally; according to the type of internal partial discharge activity in the historical GIL, starting from the moment when the electromagnetic signal changes, for each type of internal partial discharge activity, M segments of electromagnetic signals of time length T are collected respectively; wherein T and M are both preset fixed parameters;
[0080] Collect historical data and conduct data analysis;
[0081] S1-2. According to each electromagnetic signal, collect the highest frequency of each electromagnetic signal, recorded as Said represents the highest frequency of the electromagnetic signal in the i-th segment, i∈[1,(I+1)M], where (I+1)M represents the total number of electromagnetic signals collected, and I represents the number of types of internal partial discharge activities; the sampling interval is set to Said represents the sampling interval of the i-th segment of the electromagnetic signal;
[0082] S1-3, according to Each electromagnetic signal is sampled, and the total number of samples after sampling of each electromagnetic signal is The N i represents the total number of samples of the electromagnetic signal in the i-th segment, Express Round down;
[0083] The sampled electromagnetic signals are subjected to discrete Fourier transform to obtain the transformation sequence of each electromagnetic signal, which is as follows:
[0084]
[0085] Among them, the X i [k i ] represents the kth in the transformation sequence corresponding to the i-th segment of the electromagnetic signal i elements, the x i [n i ] represents the nth segment in the original sequence corresponding to the i-th segment of electromagnetic signal i elements, the is the rotation factor, e represents the base of the natural logarithm, j is the imaginary unit, and k i is the frequency parameter and k i ∈[0,N i -1], the n i is the time parameter and n i ∈[0,N i -1];
[0086] All collected electromagnetic signals are Fourier transformed.
[0087] S2. Calculate the energy spectrum density of each transformation sequence according to the transformation sequence of each electromagnetic signal, analyze the energy spectrum density, and obtain the corresponding comprehensive energy spectrum density when the GIL works normally and when various types of internal partial discharge activities occur;
[0088] In step S2, the comprehensive energy spectrum density is obtained, and the specific process is as follows:
[0089] S2-1. Calculate the energy spectral density of each transformation sequence according to the following formula:
[0090]
[0091] Among them, the The kth transformation sequence corresponding to the i-th electromagnetic signal is represented by i The frequency corresponding to the elements, Represents the frequency in the transformation sequence corresponding to the i-th segment of the electromagnetic signal The corresponding energy spectral density, the |X i [k i ]| 2 Represents X i [k i ] is the square of the modulus;
[0092] Obtain the energy spectrum density of the signal to more intuitively distinguish the strength of the frequency in the signal, which is convenient for subsequent screening and conducive to signal identification and classification;
[0093] S2-2, the M-segment electromagnetic signals when the GIL is working normally, and the M-segment electromagnetic signals corresponding to different types of internal partial discharge activities; the same type of electromagnetic signals are frequency matched, and the common frequencies in the M-segment electromagnetic signals of the same type are screened out, and the comprehensive energy spectrum density is calculated according to the following formula:
[0094]
[0095] Among them, the represents the bth electromagnetic signal in the ath category a common frequencies, the categories include electromagnetic signals when the GIL is working normally and electromagnetic signals when the GIL has internal partial discharge activity. Represents the frequency of the electromagnetic signal of the ath category The comprehensive energy spectral density is Indicates the frequency of the electromagnetic signal in segment c The energy spectral density of a∈[1,I+1], b a ∈[1,M a ], c∈[1,M], the M a represents the number of common frequencies in the electromagnetic signals of the ath category;
[0096] According to the category, M segments of electromagnetic signals corresponding to the same category are integrated to obtain I+1 comprehensive energy spectrum densities.
[0097] S3. Analyze the difference between the comprehensive energy spectrum density of the electromagnetic signal when various types of internal partial discharge activities of the GIL occur and the comprehensive energy spectrum density of the electromagnetic signal when the GIL works normally, and obtain the abnormal feature set of different types of internal partial discharge activities;
[0098] By analyzing the energy spectrum density, the abnormal characteristics of different types of internal partial discharge activities are extracted to provide a theoretical basis for subsequent matching;
[0099] In step S3, the abnormal characteristics of different types of internal partial discharge activities are obtained, and the specific process is as follows:
[0100] S3-1. Based on the comprehensive energy spectrum density, filter out the frequencies where the electromagnetic signal is present when the GIL has internal partial discharge activity but not when it is working normally, and the frequencies where the electromagnetic signal is present when the GIL is working normally and has internal partial discharge activity but does not satisfy the following relationship:
[0101]
[0102] Among them, the Indicates the bth electromagnetic signal in the a category when the GIL has internal partial discharge activity. a The frequency corresponding to the integrated energy spectrum density (partial discharge) is Indicates the bth electromagnetic signal in the a category representing the normal operation of the GIL a(正常) The frequency corresponding to the comprehensive energy spectral density is Indicates the frequency of the electromagnetic signal when the GIL is working normally The modulus of the integrated energy spectral density is Indicates the frequency of the electromagnetic signal when the GIL has internal partial discharge activity The modulus of the comprehensive energy spectral density, and at this time The α represents a preset fixed parameter;
[0103] The comprehensive energy spectrum density of the electromagnetic signal representing the internal partial discharge activity of the GIL is screened with the comprehensive energy spectrum density of the electromagnetic signal representing the normal operation of the GIL to select the abnormal characteristics of different types of internal partial discharge activities;
[0104] S3-2. Filter out the frequencies of different types of internal partial discharge activities and the comprehensive energy spectrum densities corresponding to the frequencies, and form a set of I comprehensive energy spectrum densities as the abnormal feature set of different types of internal partial discharge activities, recorded as set A x , the set A x represents the set of abnormal features of the x-th type of internal partial discharge activity, x∈[1,I];
[0105] Based on comparative analysis, the abnormal characteristics of different types of internal partial discharge activities are obtained, which include the frequency and energy characteristics of the signal. The abnormal characteristics of different partial discharge activities are different.
[0106] S4. Collect the line layout of the line to be supervised, establish a line map, mark the branch points in the line map, and set electromagnetic sensors at the locations of the branch points;
[0107] The specific process of step S4 is as follows:
[0108] Collect the route layout of the route to be supervised, establish a route map, and mark the branch points in the route map, denoted as P d , the P d represents the d-th branch point in the route map, d∈[1,D] and D is a positive integer;
[0109] In P d Position setting electromagnetic sensor.
[0110] S5. According to the line map, the actual distance between two adjacent branch points in the same line is obtained, the effective monitoring radius of the electromagnetic sensor is collected, and the increase of the electromagnetic sensor is analyzed in combination with the actual distance between two adjacent branch points in the same line, and the added electromagnetic sensor is marked in the line map;
[0111] In step S5, the increase in the electromagnetic sensor is analyzed, and the specific process is as follows:
[0112] S5-1. According to the route map, obtain the actual distance between two adjacent branch points on the same route, and convert P d With P d' The actual distance between d' , the P d' Indicates the d'th and P d Adjacent branch points, d'∈[1,D'] and D' is a positive integer; the effective monitoring radius of the electromagnetic sensor is recorded as r; P d With P d' The increase in the electromagnetic sensor between Said Express Round up
[0113] S5-2, if is 1, then it is not in P d With P d' Add an electromagnetic sensor between d The electromagnetic sensor adjacent to the electromagnetic sensor at position P d' Electromagnetic sensors for position;
[0114] like If it is not 1, then in Pd With P d' Add an electromagnetic sensor between the two lines and mark the added electromagnetic sensor on the line, denoted as P g , At this time, P d The electromagnetic sensor adjacent to the electromagnetic sensor at position P g Electromagnetic sensors for position;
[0115] P d The adjacent distance between the electromagnetic sensor at the position and the adjacent electromagnetic sensor is recorded as
[0116] S6. Monitor the electromagnetic signal of the line to be supervised by electromagnetic sensors. If the radiation intensity of the electromagnetic signal in the line to be supervised detected by two adjacent electromagnetic sensors exceeds a threshold value, it indicates that internal partial discharge activity occurs; according to the moment when the radiation intensity of the electromagnetic signal in the line to be supervised detected by two adjacent electromagnetic sensors exceeds the threshold value, analyze the occurrence position of the current internal partial discharge activity;
[0117] In step S6, the occurrence position of the current internal partial discharge activity is analyzed, and the specific process is as follows:
[0118] S6-1. Monitor the electromagnetic signal of the line to be supervised by electromagnetic sensors, collect the radiation intensity of the electromagnetic signal monitored by each electromagnetic sensor during normal operation, take the average value, record it as E, and preset the threshold of the radiation intensity of the electromagnetic signal as E+β, where β is a preset fixed parameter;
[0119] If P d If the radiation intensity of the electromagnetic signal monitored by the electromagnetic sensors at the position and its adjacent positions exceeds E+β, it indicates that internal partial discharge activity occurs;
[0120] S6-2, P d The moment when the electromagnetic sensor at the position detects that the radiation intensity of the electromagnetic signal in the line to be supervised exceeds E+β is recorded as time t0; d The electromagnetic sensor adjacent to the electromagnetic sensor at the position detects that the radiation intensity of the electromagnetic signal in the line to be supervised exceeds E+β, which is recorded as time t1. The occurrence position of the current internal partial discharge activity and P are calculated according to the following formula d The distance between the electromagnetic sensors of the position:
[0121]
[0122] Wherein, l represents the location of the current internal partial discharge activity and P d The distance between the electromagnetic sensors of the position, the v 光 represents the speed of light;
[0123] S6-3, according to l, obtain the occurrence position of the current internal partial discharge activity, in P d The electromagnetic sensors at the position and its adjacent positions are d The electromagnetic sensor distance of the position is l.
[0124] S7. Collect abnormal electromagnetic signals, process the abnormal electromagnetic signals, and obtain an abnormal feature set of the current internal partial discharge activity; match the abnormal feature set of the current electromagnetic signal with abnormal feature sets of different types of internal partial discharge activities to obtain the type of the current internal partial discharge activity.
[0125] In step S7, the type of the current internal partial discharge activity is obtained, and the specific process is as follows:
[0126] S7-1, according to The electromagnetic sensor at the position collects electromagnetic signals of time length T from time t0 as abnormal electromagnetic signals, processes the abnormal electromagnetic signals, and obtains the abnormal feature set of the current internal partial discharge activity, which is recorded as set A 异 ;
[0127] S7-2. According to set A 异 , respectively with the set A x Make a match;
[0128] Filter set A 异 With set A x Satisfied The frequency condition element, the The first in the set of abnormal features representing the xth type of internal partial discharge activity The frequency of the elements, Indicates the first in the abnormal feature set of the current internal partial discharge activity The frequency of the elements, γ is a preset fixed parameter, x∈[1,I], Said Represents the set A x The number of elements in Represents the set A 异 The number of elements of
[0129] The selected elements are calculated according to the following formula:
[0130]
[0131] Among them, the η x Represents the set A 异 With set A x similarity; Indicates the bth x frequencies, and the set A xmiddle Set A 异 middle Said Represents the set A 异 Medium frequency The corresponding integrated energy spectral density modulus; Represents the set A x Medium frequency The corresponding integrated energy spectral density modulus; the Q x Indicates the number of frequencies screened; b x ∈[1,Q x ];
[0132] According to the calculation results, select η x The type of internal PD activity that corresponds to the value closest to 1 is used as the type of current internal PD activity.
[0133] See also Figure 2 , a management system based on GIL ontology data analysis, the system includes an information collection module, an information processing module and an information display module;
[0134] The information acquisition module is used to acquire various information required by the system; the information processing module is used to store, analyze and transmit various information of each module; and the information display module is used to display various information of the information processing module.
[0135] The information acquisition module includes a historical information unit and a current information unit; the information processing module includes an information storage unit, an information analysis unit and an information transmission unit; the information display module includes an alarm unit and a remote display unit;
[0136] The historical information unit is used to collect historical data information of the GIL, and the current information unit is used to collect current data information of the line to be supervised;
[0137] The information storage unit is used to store various information acquired by the information acquisition module; the information analysis unit is used to analyze various information acquired by the information acquisition module; the information transmission unit is used for information transmission of various modules in the system;
[0138] The alarm unit is used to send out a reminder message when an internal partial discharge activity occurs, and the remote display unit is used to display the location and type of the internal partial discharge activity of the line to be supervised.
[0139] Example:
[0140] A GIL is currently using this method to monitor internal partial discharge activities. Two continuous electromagnetic sensors are located at P d Position and P gPosition, the two electromagnetic sensors detect that the radiation intensity of the electromagnetic signal between them exceeds the threshold. It is known that the effective monitoring radius of the electromagnetic sensor is r = 500, P d With P d' The distance between d' =1500, the time difference between the two electromagnetic sensors is t0-t1=0.001, and the location of the current internal partial discharge activity and P d The distance between the electromagnetic sensors of the position:
[0141]
[0142] The current location of the internal partial discharge activity is at P d Position and P g The electromagnetic sensor between the position and P d The electromagnetic sensor distance of the position is l = 625;
[0143] Now filter collection A 异 With set A x ;
[0144] and The corresponding set
[0145] and The corresponding set
[0146] The selected elements are calculated according to the following formula:
[0147]
[0148] Calculate η x=1 =1.3,η x=2 =1;
[0149] According to the calculation results, η x=2 =1 is used as the type of internal partial discharge activity corresponding to the current internal partial discharge activity.
[0150] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0151] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A management method based on GIL ontology data analysis, characterized in that: The method comprises the following steps: S1. Set a time length, and collect electromagnetic signals of the time length when the GIL works normally and when various types of internal partial discharge activities occur according to the types of internal partial discharge activities in the historical GIL; set a sampling interval according to each electromagnetic signal, sample each electromagnetic signal, perform discrete Fourier transform on each sampled electromagnetic signal, and obtain a transformation sequence of each electromagnetic signal; S2. Calculate the energy spectrum density of each transformation sequence according to the transformation sequence of each electromagnetic signal, analyze the energy spectrum density, and obtain the corresponding comprehensive energy spectrum density when the GIL works normally and when various types of internal partial discharge activities occur; S3. Analyze the difference between the comprehensive energy spectrum density of the electromagnetic signal when various types of internal partial discharge activities of the GIL occur and the comprehensive energy spectrum density of the electromagnetic signal when the GIL works normally, and obtain the abnormal feature set of different types of internal partial discharge activities; S4. Collect the line layout of the line to be supervised, establish a line map, mark the branch points in the line map, and set electromagnetic sensors at the locations of the branch points; S5. According to the line map, the actual distance between two adjacent branch points in the same line is obtained, the effective monitoring radius of the electromagnetic sensor is collected, and the increase of the electromagnetic sensor is analyzed in combination with the actual distance between two adjacent branch points in the same line, and the added electromagnetic sensor is marked in the line map; S6. Monitor the electromagnetic signal of the line to be supervised by electromagnetic sensors. If the radiation intensity of the electromagnetic signal in the line to be supervised detected by two adjacent electromagnetic sensors exceeds a threshold value, it indicates that internal partial discharge activity occurs; according to the moment when the radiation intensity of the electromagnetic signal in the line to be supervised detected by two adjacent electromagnetic sensors exceeds the threshold value, analyze the occurrence position of the current internal partial discharge activity; S7. Collect abnormal electromagnetic signals, process the abnormal electromagnetic signals, and obtain an abnormal feature set of the current internal partial discharge activity; match the abnormal feature set of the current electromagnetic signal with abnormal feature sets of different types of internal partial discharge activities to obtain the type of the current internal partial discharge activity.
2. A management method based on GIL ontology data analysis according to claim 1, characterized in that: In step S1, electromagnetic signals are collected and discrete Fourier transform is performed to obtain a transformation sequence of each electromagnetic signal. The specific process is as follows: S1-1, the time length is set to T, and the electromagnetic signal of time length T is collected when M segments of GIL are working normally; according to the type of internal partial discharge activity in the historical GIL, starting from the moment when the electromagnetic signal changes, for each type of internal partial discharge activity, M segments of electromagnetic signals of time length T are collected respectively; wherein T and M are both preset fixed parameters; S1-2. According to each electromagnetic signal, collect the highest frequency of each electromagnetic signal, recorded as Said represents the highest frequency of the electromagnetic signal in the i-th segment, i∈[1,(I+1)M], where (I+1)M represents the total number of electromagnetic signals collected, and I represents the number of types of internal partial discharge activities; the sampling interval is set to Said represents the sampling interval of the i-th segment of the electromagnetic signal; S1-3, according to Each electromagnetic signal is sampled, and the total number of samples after sampling of each electromagnetic signal is The N i represents the total number of samples of the electromagnetic signal in the i-th segment, Express Round down; The sampled electromagnetic signals are subjected to discrete Fourier transform to obtain the transformation sequence of each electromagnetic signal. The formula is as follows: Among them, the X i [k i ] represents the kth in the transformation sequence corresponding to the i-th segment of the electromagnetic signal i elements, the x i [n i ] represents the nth segment in the original sequence corresponding to the i-th segment of electromagnetic signal i elements, the is the rotation factor, e represents the base of the natural logarithm, j is the imaginary unit, and k i is the frequency parameter and k i ∈[0,N i -1], the n i is the time parameter and n i ∈[0,N i -1].
3. A management method based on GIL ontology data analysis according to claim 2, characterized in that: In step S2, the comprehensive energy spectrum density is obtained, and the specific process is as follows: S2-1. Calculate the energy spectral density of each transformation sequence according to the following formula: Among them, the The kth transformation sequence corresponding to the i-th electromagnetic signal is represented by i The frequency corresponding to the elements, Represents the frequency in the transformation sequence corresponding to the i-th segment of the electromagnetic signal The corresponding energy spectral density, the |X i [k i ]| 2 Represents X i [k i ] is the square of the modulus; S2-2, the M-segment electromagnetic signals when the GIL is working normally, and the M-segment electromagnetic signals corresponding to different types of internal partial discharge activities; the same type of electromagnetic signals are frequency matched, and the common frequencies in the M-segment electromagnetic signals of the same type are screened out, and the comprehensive energy spectrum density is calculated according to the following formula: Among them, the represents the bth electromagnetic signal in the ath category a A common frequency, the Represents the frequency of the electromagnetic signal of the ath category The comprehensive energy spectral density is Indicates the frequency of the electromagnetic signal in segment c The energy spectral density of a∈[1,I+1], b a ∈[1,a], c∈[1,M], where a represents the number of common frequencies in the electromagnetic signals of the ath category.
4. A management method based on GIL ontology data analysis according to claim 3, characterized in that: In step S3, the abnormal characteristics of different types of internal partial discharge activities are obtained, and the specific process is as follows: S3-1. Based on the comprehensive energy spectrum density, filter out the frequencies where the electromagnetic signal is present when the GIL has internal partial discharge activity but not when it is working normally, and the frequencies where the electromagnetic signal is present when the GIL is working normally and has internal partial discharge activity but does not satisfy the following relationship: Among them, the Indicates the bth electromagnetic signal in the a category when the GIL has internal partial discharge activity. a(局放) The frequency corresponding to the comprehensive energy spectral density is Indicates the bth electromagnetic signal in the a category representing the normal operation of the GIL a(正常) The frequency corresponding to the comprehensive energy spectral density is Indicates the frequency of the electromagnetic signal when the GIL is working normally The modulus of the integrated energy spectral density is Indicates the frequency of the electromagnetic signal when the GIL has internal partial discharge activity The modulus of the comprehensive energy spectral density, and at this time The α represents a preset fixed parameter; S3-2. Filter out the frequencies of different types of internal partial discharge activities and the comprehensive energy spectrum densities corresponding to the frequencies, and form a set of I comprehensive energy spectrum densities as the abnormal feature set of different types of internal partial discharge activities, recorded as set A x , the set A x The set of abnormal features representing the x-th type of internal partial discharge activity, x∈[1,I].
5. A management method based on GIL ontology data analysis according to claim 4, characterized in that: The specific process of step S4 is as follows: Collect the route layout of the route to be supervised, establish a route map, and mark the branch points in the route map, denoted as P d , the P d represents the d-th branch point in the route map, d∈[1,D] and D is a positive integer; In P d Position setting electromagnetic sensor.
6. A management method based on GIL ontology data analysis according to claim 5, characterized in that: In step S5, the increase in the electromagnetic sensor is analyzed, and the specific process is as follows: S5-1. According to the route map, obtain the actual distance between two adjacent branch points on the same route, and convert P d With P d' The actual distance between d' , the P d' Indicates the d'th and P d Adjacent branch points, d'∈[1,D'] and D' is a positive integer; the effective monitoring radius of the electromagnetic sensor is recorded as r; P d With P d' The increase in the electromagnetic sensor between Said Express Round up S5-2, if is 1, then it is not in P d With P d' Add an electromagnetic sensor between d The electromagnetic sensor adjacent to the electromagnetic sensor at position P d' Electromagnetic sensors for position; like If it is not 1, then in P d With P d' Add an electromagnetic sensor between the two lines and mark the added electromagnetic sensor on the line, denoted as P g , At this time, P d The electromagnetic sensor adjacent to the electromagnetic sensor at position P g Electromagnetic sensors for position; P d The adjacent distance between the electromagnetic sensor at the position and the adjacent electromagnetic sensor is recorded as 7. A management method based on GIL ontology data analysis according to claim 6, characterized in that: In step S6, the occurrence position of the current internal partial discharge activity is analyzed, and the specific process is as follows: S6-1. Monitor the electromagnetic signal of the line to be supervised by electromagnetic sensors, collect the radiation intensity of the electromagnetic signal monitored by each electromagnetic sensor during normal operation, take the average value, record it as E, and preset the threshold of the radiation intensity of the electromagnetic signal as E+β, where β is a preset fixed parameter; If P d If the radiation intensity of the electromagnetic signal monitored by the electromagnetic sensors at the position and its adjacent positions exceeds E+β, it indicates that internal partial discharge activity occurs; S6-2, P d The moment when the electromagnetic sensor at the position detects that the radiation intensity of the electromagnetic signal in the line to be supervised exceeds E+β is recorded as time t0; d The electromagnetic sensor adjacent to the electromagnetic sensor at the position detects that the radiation intensity of the electromagnetic signal in the line to be supervised exceeds E+β, which is recorded as time t1. The occurrence position of the current internal partial discharge activity and P are calculated according to the following formula d The distance between the electromagnetic sensors of the position: Wherein, l represents the location of the current internal partial discharge activity and P d The distance between the electromagnetic sensors of the position, the v 光 represents the speed of light; S6-3, according to l, obtain the occurrence position of the current internal partial discharge activity, in P d The electromagnetic sensors at the position and its adjacent positions are d The electromagnetic sensor distance of the position is l.
8. A management method based on GIL ontology data analysis according to claim 7, characterized in that: In step S7, the type of the current internal partial discharge activity is obtained, and the specific process is as follows: S7-1, according to P d The electromagnetic sensor at the position collects electromagnetic signals of time length T from time t0 as abnormal electromagnetic signals, processes the abnormal electromagnetic signals, and obtains the abnormal feature set of the current internal partial discharge activity, which is recorded as set A 异 ; S7-2. According to set A 异 , respectively with the set A x Make a match; Filter set A 异 With set A x Satisfied The frequency condition element, the The first in the set of abnormal features representing the xth type of internal partial discharge activity The frequency of the elements, Indicates the first in the abnormal feature set of the current internal partial discharge activity The frequency of the elements, γ is a preset fixed parameter, x∈[1,I], Said Represents the set A x The number of elements in Represents the set A 异 The number of elements of The selected elements are calculated according to the following formula: Among them, the η x Represents the set A 异 With set A x similarity; Indicates the bth x frequencies, and the set A x middle Set A 异 middle Said Represents the set A 异 Medium frequency The corresponding integrated energy spectral density modulus; Represents the set A x Medium frequency The corresponding integrated energy spectral density modulus; the Q x Indicates the number of frequencies screened; b x ∈[1,Q x ]; According to the calculation results, select η x The type of internal PD activity that corresponds to the value closest to 1 is used as the type of current internal PD activity.
9. A management system based on GIL ontology data analysis, such as using a management method based on GIL ontology data analysis according to any one of claims 1 to 8, characterized in that: The system includes an information acquisition module, an information processing module and an information display module; The information acquisition module is used to acquire various information required by the system; the information processing module is used to store, analyze and transmit various information of each module; and the information display module is used to display various information of the information processing module.
10. A management system based on GIL ontology data analysis according to claim 9, characterized in that: The information acquisition module includes a historical information unit and a current information unit; the information processing module includes an information storage unit, an information analysis unit and an information transmission unit; the information display module includes an alarm unit and a remote display unit; The historical information unit is used to collect historical data information of the GIL, and the current information unit is used to collect current data information of the line to be supervised; The information storage unit is used to store various information acquired by the information acquisition module; The information analysis unit is used to analyze the information acquired by the information acquisition module; the information transmission unit is used for information transmission of each module in the system; The alarm unit is used to send out a reminder message when an internal partial discharge activity occurs, and the remote display unit is used to display the location and type of the internal partial discharge activity of the line to be supervised.
Citation Information
Patent Citations
Device and method for locating partial discharge source
CN106841950A
Urban integration pipe gallery intelligent monitoring system
CN109407594A
Cable partial discharge abnormity intelligent monitoring method and system
CN118209830A
System and process
GB201601134D0
Instrument and method for measuring partial electrical discharges in an electrical system
US20090248327A1