Power distribution network fault early warning method under comprehensive multiple factors
Through multi-source fault information acquisition and feature extraction, combined with time series prediction and FCM clustering algorithm, considering human and meteorological factors, the problem of low warning accuracy in the existing technology is solved, and a more accurate distribution network fault warning is achieved. Ensure the safety and stability of the distribution network.
Patent Information
- Application Number
- CN202410967617.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-18
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-07-18
AI Technical Summary
The existing distribution network fault warning methods ignore human factors and external weather factors, resulting in low warning accuracy and inability to effectively evaluate possible faults in real-time status information.
Multi-source fault information acquisition, feature extraction and time series prediction algorithms are used, combined with FCM clustering algorithm and LSTM network, fault trigger values are calculated, human factors and meteorological factors are considered, and comprehensive early warning is conducted.
It improves the accuracy and universality of the distribution network fault warning, ensures the safe and stable operation of the distribution network, and can effectively evaluate the impact of human and weather factors on the fault.
Smart Images

Figure CN118917468A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of distribution network fault early warning, and in particular relates to a distribution network fault early warning method under comprehensive multi-factors. Background Art
[0002] The power system is a leading industry in the national economic system. As an important part of the power system, the distribution network is used to connect the main grid and users, and bears the heavy responsibility of transmitting electricity to users. The quality of its operation directly affects the user's experience of electricity consumption. In addition, power outages not only bring huge economic losses to society, but also affect people's lives, disrupt social order, and even endanger national defense security. According to statistics, more than 80% of power outages are caused by distribution network failures, so it is of great significance to carry out fault warning for distribution network.
[0003] Most of the existing distribution network fault warning methods are based on distribution network operation information (for example, load, voltage and current, etc.), which do not take into account the real-time status of the distribution network and ignore the image of external factors such as weather. At the same time, in the later fault tracing, it was found that a large number of distribution network failures were caused by human factors, such as personnel in the distribution network area ignoring safety distances and illegal theft. However, the existing fault warning methods do not consider the impact of human factors, ignore the real-time status information of the distribution network, and cannot evaluate the possibility of inducing faults during the development of real-time status information, resulting in the low accuracy of fault warning of the existing fault warning model. Summary of the invention
[0004] In order to solve the problems existing in the background technology, one aspect of the present invention provides a distribution network fault early warning method under comprehensive multi-factors, comprising:
[0005] S1: Acquire multi-source fault information of the distribution network after preprocessing; wherein the multi-source fault information includes: human factor information, meteorological factor information and power equipment factor information;
[0006] S2: extracting the power equipment factor information to obtain the power equipment factor features;
[0007] S3: Based on the historical power equipment factor characteristics, use the time series prediction algorithm to predict the power equipment factor characteristics from the current time t0 to the next time period t0+t′;
[0008] S4: extracting the power equipment factor features when the power equipment is operating normally and when it fails according to the historical power equipment factor information, and using the FCM clustering algorithm to calculate the membership degree of the power equipment factor features in the time period [t0, t0+t′] belonging to the failure;
[0009] S5: Calculate the accidental fault triggering factor at the current time t0 according to the human factor information and the meteorological factor information;
[0010] S6: Calculate the fault trigger value at time t0 based on the degree of membership of the power equipment factor characteristics in the time period [t0, t0+t′] when the fault occurs and the accidental fault trigger factor at time t0; determine whether the fault trigger value at time t0 is greater than the set threshold, and if so, issue a fault warning.
[0011] Preferably, the power equipment factor information includes but is not limited to: voltage, current, frequency, and temperature of the power equipment during operation;
[0012] The feature extraction of the power equipment factor information includes:
[0013] S21: Obtain the power equipment factor information at time t, and input the power equipment factor information at time t into the encoder of the deep autoencoder network for encoding to obtain the encoded intermediate features;
[0014] S22: The intermediate features from time tt″ to time t are combined into a feature sequence, and the context information of the feature sequence is fused using the LSTM network to obtain the power equipment factor features at time t; steps S21-S22 are repeated to obtain the power equipment factor features at the current time t0 and all times before the current time t0.
[0015] Preferably, the prediction of the power equipment factor characteristics starting from the current time t0 to the subsequent time period t0+t′ includes:
[0016] S31: extracting the power equipment factor characteristics in the time period from t0-T to t0;
[0017] S32: Based on the power equipment factor characteristics in the time period from t0-T to t0, the power equipment factor characteristics in the time period from the current time t0 to the next time period t0+t′ are predicted using a time series prediction algorithm.
[0018] Preferably, the time series prediction algorithm includes but is not limited to: LSTM algorithm and TCN algorithm.
[0019] Preferably, the calculation of the degree of membership of the power equipment factor feature in the time period [t0, t0+t′] when it belongs to a fault by using the FCM clustering algorithm includes:
[0020] S41: using the FCM clustering algorithm to divide the power equipment factor characteristics when the power equipment is in normal operation and when it is faulty into two groups: normal operation data and faulty operation data, and finding the cluster center of each group;
[0021] S42: Calculate the degree of membership of the power equipment factor feature in the time period [t0, t0+t′] belonging to the fault according to the cluster centers of the two groups of normal operation data and fault operation data.
[0022] Preferably, the degree of membership of the power equipment factor feature in the time period [t0, t0+t′] when it belongs to a fault includes:
[0023]
[0024] Among them, u2 represents the degree of membership of the power equipment factor characteristics in the time period [t0, t0+t′] belonging to the fault; x represents the power equipment factor characteristics in the time period [t0, t0+t′]; c2 represents the cluster center of the fault operation data group; m represents the fuzziness index; c=2 represents the number of groups; c1 represents the cluster center of the normal operation data group; ||xc k || represents x and c k The Euclidean distance of .
[0025] Preferably, step S5 comprises:
[0026] S51: extracting personnel information of the distribution network area at time t0 from the human factor information and calculating the human factor correction coefficient, wherein the personnel information includes the type of personnel, the body temperature of the personnel, and the shortest distance between the personnel and the distribution network equipment;
[0027] The human factor correction coefficient P includes:
[0028]
[0029] Where N represents the total number of people in the distribution network area; P i represents the fault inducing factor of the ith person in the distribution network area; C i Indicates the category of person i; C i =0 means that person i is an internal staff member; C i =1 indicates that person i belongs to the rest of the personnel; ε indicates the set temperature threshold; φ indicates the set safety distance threshold; represents the body temperature of person i; a represents the weight parameter; It indicates the shortest distance between person i and the distribution network equipment;
[0030] S52: Obtain the weather conditions in the time period [t0, t0+t′] according to the weather forecast, and determine whether extreme weather will occur in the time period [t0, t0+t′]; if so, obtain the number of extreme weather events in history based on historical meteorological factor information and the number of failures that occurred during extreme weather conditions Calculate the weather correction factor
[0031]
[0032] S53: The accidental fault trigger factor α=P×W is calculated based on the human factor correction coefficient and the weather factor correction coefficient.
[0033] Preferably, the fault trigger value at time t0 includes:
[0034] β=u2×α
[0035] Among them, β represents the fault trigger value, α represents the accidental fault trigger factor, and u2 represents the membership degree of the power equipment factor characteristics in the time period [t0, t0+t′] belonging to the fault.
[0036] Another aspect of the present invention provides a distribution network fault early warning device under comprehensive multiple factors, characterized in that it includes a processor and a memory; the memory is used to store a computer program; the processor is connected to the memory, and is used to execute the computer program stored in the memory, so that the distribution network fault early warning device under comprehensive multiple factors executes the distribution network fault early warning method under comprehensive multiple factors.
[0037] Another aspect of the present invention provides a computer-readable storage medium storing a program, characterized in that when the program is executed by a processor, the distribution network fault early warning method under comprehensive multi-factors is implemented.
[0038] The present invention has at least the following beneficial effects
[0039] The present invention obtains information including human factors, meteorological factors and factors of the power equipment itself, calculates the fault trigger value in each time period through an early warning method, and issues an early warning for each time period. The present invention comprehensively considers the equipment factor information, extracts the power equipment factor characteristics when the power equipment is operating normally and when it fails according to the historical power equipment factor information, and calculates the fault trigger value considering the human factor information and the meteorological factor information. The early warning method of the present invention integrates multi-source fault information, considers the accidental fault triggering under human factors and weather factors, has universal applicability to distribution network fault early warning, and is of great significance to ensuring the safe and stable operation of the distribution network. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] Figure 1 It is a schematic diagram of the method flow of the present invention;
[0041] Figure 2 This is a schematic diagram of the training of the time series prediction algorithm of this embodiment. DETAILED DESCRIPTION
[0042] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the illustrations provided in the following embodiments only illustrate the basic concept of the present invention in a schematic manner, and the following embodiments and features in the embodiments can be combined with each other without conflict.
[0043] Among them, the drawings are only used for illustrative explanations, and they only represent schematic diagrams rather than actual pictures, and should not be understood as limitations on the present invention. In order to better illustrate the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of actual products. For those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.
[0044] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right", "front", "rear", etc. indicate the orientation or position relationship, they are based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the terms describing the position relationship in the drawings are only used for illustrative purposes and cannot be understood as limiting the present invention. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0045] See also Figure 1 One aspect of the present invention provides a distribution network fault early warning method under comprehensive multi-factors, comprising:
[0046] S1: Acquire multi-source fault information of the distribution network after preprocessing; wherein the multi-source fault information includes: human factor information, meteorological factor information and power equipment factor information;
[0047] In this embodiment, multi-source fault information is obtained by information collection devices installed at distribution network terminals, equipment management information and other related information channels. The multi-source fault information includes human factor information, meteorological factor information and power equipment factor information. The human factor information includes: the type of personnel in the distribution network area, the number of personnel, the body temperature of personnel, and the distance between personnel and distribution network equipment; wherein the body temperature of personnel can be monitored by infrared thermal imaging sensing cameras for all personnel in the area, and the distance between personnel and power grid equipment in the power grid area can be monitored by cameras and other equipment; meteorological factors include: temperature, humidity, wind force, and weather categories, such as thunderstorms, haze, and tornadoes; and equipment factor information includes: voltage, current, and temperature when the equipment is running; the power equipment in the distribution network mainly includes: transformers and overhead lines.
[0048] In this embodiment, the multi-source fault information needs to be preprocessed, and the preprocessing includes: using zero mean to normalize the multi-source fault information for normalization; and using linear function normalization to normalize different types of data.
[0049] S2: extracting the power equipment factor information to obtain the power equipment factor features;
[0050] The feature extraction of the power equipment factor information includes:
[0051] S21: Obtain the power equipment factor information at time t, and input the power equipment factor information at time t into the encoder of the deep autoencoder network for encoding to obtain the encoded intermediate features;
[0052] S22: The intermediate features from time tt″ to time t are combined into a feature sequence, and the context information of the feature sequence is fused using the LSTM network to obtain the power equipment factor features at time t; steps S21-S22 are repeated to obtain the power equipment factor features at the current time t0 and all times before the current time t0.
[0053] Preferably, the power equipment factor information includes but is not limited to: voltage, current, frequency, and temperature of the power equipment during operation;
[0054] In this embodiment, the deep autoencoder network is composed of an encoder part and a decoder part. The encoding part is used to encode the input features into a low-dimensional space representation, and the decoder is used to reconstruct the low-dimensional space representation into input features. By using the encoder of the deep autoencoder network to encode the power equipment factor information into a low-dimensional space to obtain intermediate features, the amount of computational effort in subsequent calculations is reduced, thereby improving the timeliness of the early warning.
[0055] In this embodiment, the context information of the feature sequence is fused through the LSTM network to obtain the power equipment factor feature at time t, that is, the intermediate features from time tt″ to time t are combined into a feature sequence, and the context information of the feature sequence is fused using the LSTM network to obtain the power equipment factor feature at time t. The power equipment factor feature at time t integrates the information of the [tt″, t] time period. The voltage, current and other information of the power equipment have a certain correlation in time series. The LSTM network can learn this correlation and then obtain the power equipment factor feature at time t, which can improve the accuracy of subsequent warnings. The LSTM network is composed of multiple unit modules, each of which is composed of an input gate, a forget gate and an output gate. The input of each unit module is the hidden state h output by the previous unit module. t-1 and feature c t-1 , the output is h t and c t , then the feature c output by the last unit module is last That is the characteristic of power equipment factors.
[0056] S3: Based on the historical power equipment factor characteristics, use the time series prediction algorithm to predict the power equipment factor characteristics from the current time t0 to the next time period t0+t′;
[0057] Preferably, the prediction of the power equipment factor characteristics starting from the current time t0 to the subsequent time period t0+t′ includes:
[0058] S31: extracting the power equipment factor characteristics in the time period from t0-T to t0;
[0059] S32: Based on the power equipment factor characteristics in the time period from t0-T to t0, the power equipment factor characteristics in the time period from the current time t0 to the next time period t0+t′ are predicted using a time series prediction algorithm.
[0060] Preferably, the time series prediction algorithm includes but is not limited to: LSTM algorithm and TCN algorithm. In this embodiment, the time series prediction algorithm can adopt a more traditional time series modeling method, such as naive prediction method, simple average method, moving average method, AR, MA, ARMA, etc.; it can also be based on machine learning methods, such as random forest, Xgboost, LightGBM, RNN, LSTM algorithm, and TCN algorithm. In this embodiment, the LSTM algorithm and TCN algorithm are preferred. As an improved recurrent neural network structure, LSTM overcomes the defect of only short-term memory, selectively forgets or retains historical information, avoids gradient disappearance, and is conducive to the modeling of long time series; TCN algorithm uses a time convolutional network to predict, which balances short-term burst memory and long-term memory, and the prediction result is more accurate.
[0061] See also Figure 2 , taking the LSTM algorithm as an example, Figure 2 As shown. Data_model_i (i = 1, 2, 3, 4) is the historical data collected within Δt1 as the training data of LSTM, and Data_test_i (i = 1, 2, 3, 4) represents the data to be predicted within Δt2. After each model training, both slide back Δt2 to continue the next round of training and prediction. In order to ensure the accuracy of the prediction, the step size of Δt2 should be much smaller than Δt1.
[0062] S4: extracting the power equipment factor features when the power equipment is operating normally and when it fails according to the historical power equipment factor information, and using the FCM clustering algorithm to calculate the membership degree of the power equipment factor features in the time period [t0, t0+t′] belonging to the failure;
[0063] Preferably, the calculation of the degree of membership of the power equipment factor feature in the time period [t0, t0+t′] when it belongs to a fault by using the FCM clustering algorithm includes:
[0064] S41: using the FCM clustering algorithm to divide the power equipment factor characteristics when the power equipment is in normal operation and when it is faulty into two groups: normal operation data and faulty operation data, and finding the cluster center of each group;
[0065] S42: Calculate the degree of membership of the power equipment factor feature in the time period [t0, t0+t′] belonging to the fault according to the cluster centers of the two groups of normal operation data and fault operation data.
[0066] Preferably, the degree of membership of the power equipment factor feature in the time period [t0, t0+t′] when it belongs to a fault includes:
[0067]
[0068] Among them, u2 represents the degree of membership of the power equipment factor characteristics in the time period [t0, t0+t′] belonging to the fault; x represents the power equipment factor characteristics in the time period [t0, t0+t′]; c2 represents the cluster center of the fault operation data group; m represents the fuzziness index; c=2 represents the number of groups; c1 represents the cluster center of the normal operation data group; ||xc k || represents x and c k The Euclidean distance of .
[0069] When a fault occurs in the distribution network, the fault data at this moment will mostly change compared to the normal operating state. In the time series, the characteristic information at the time of the fault is different from that when the system is operating normally, which is called an anomaly point and can be used as the main basis for determining whether a fault has occurred. The FCM clustering algorithm can use the membership degree to determine the degree to which each feature quantity belongs to the normal operating state or the fault state, and construct an objective function based on distance and membership degree to find its optimal value. As the sampling data changes, the membership degree also changes accordingly, which can characterize the changing trend of the distribution network operating state and then determine the distribution network fault boundary conditions.
[0070] S5: Calculate the accidental fault triggering factor at the current time t0 according to the human factor information and the meteorological factor information;
[0071] Preferably, the step S5 comprises:
[0072] S51: extracting personnel information of the distribution network area at time t0 from the human factor information and calculating the human factor correction coefficient, wherein the personnel information includes the type of personnel, the body temperature of the personnel, and the shortest distance between the personnel and the distribution network equipment;
[0073] The human factor correction coefficient P includes:
[0074]
[0075] Where N represents the total number of people in the distribution network area; P i represents the fault inducing factor of the ith person in the distribution network area; C i Indicates the category of person i; C i =0 means that person i is an internal staff member; C i =1 indicates that person i belongs to the rest of the personnel; ε indicates the set temperature threshold; φ indicates the set safety distance threshold; represents the body temperature of person i; a represents the weight parameter; It indicates the shortest distance between person i and the distribution network equipment;
[0076] S52: Obtain the weather conditions in the time period [t0, t0+t′] according to the weather forecast, and determine whether extreme weather will occur in the time period [t0, t0+t′]; if so, obtain the number of extreme weather events in history based on historical meteorological factor information and the number of failures that occurred during extreme weather conditions Calculate the weather correction factor
[0077] S53: The accidental fault trigger factor α=P×W is calculated based on the human factor correction coefficient and the weather factor correction coefficient.
[0078] In this embodiment, the correction of the fault trigger value is achieved by calculating the accidental fault trigger factor taking into account human factors, which can improve the universality and accuracy of the distribution network fault warning. For the staff of the distribution network, by monitoring the body temperature and distance from the power equipment of the distribution network staff, it can prevent the staff from operating the distribution network under abnormal physical conditions, resulting in faults. For non-internal staff, by monitoring the distance between non-internal staff and power grid equipment, it can prevent non-staff from ignoring the safety distance and causing faults; weather factors mainly consider the impact of extreme weather conditions on the distribution network. Extreme weather includes: temperature greater than 40 degrees Celsius, strong wind (greater than level 5), extremely heavy rainfall (rainfall reaches 50 mm), humidity greater than (80% RH), lightning, frost and blizzards, etc. The above situations are all extreme weather. The specific situation can be determined by experts in this field based on the investigation of the impact of different weather on the distribution network.
[0079] S6: Calculate the fault trigger value at time t0 based on the degree of membership of the power equipment factor characteristics in the time period [t0, t0+t′] when the fault occurs and the accidental fault trigger factor at time t0; determine whether the fault trigger value at time t0 is greater than the set threshold, and if so, issue a fault warning.
[0080] Preferably, the fault trigger value at time t0 includes:
[0081] β=u2×α
[0082] Among them, β represents the fault trigger value, α represents the accidental fault trigger factor, and u2 represents the membership degree of the power equipment factor characteristics in the time period [t0, t0+t′] belonging to the fault.
[0083] Another aspect of the present invention provides a distribution network fault early warning device under comprehensive multiple factors, characterized in that it includes a processor and a memory; the memory is used to store a computer program; the processor is connected to the memory, and is used to execute the computer program stored in the memory, so that the distribution network fault early warning device under comprehensive multiple factors executes the distribution network fault early warning method under comprehensive multiple factors.
[0084] Another aspect of the present invention provides a computer-readable storage medium storing a program, characterized in that when the program is executed by a processor, the distribution network fault early warning method under comprehensive multi-factors is implemented.
[0085] In summary, the present invention obtains information including human factors, meteorological factors and factors of the power equipment itself, calculates the fault trigger value in each time period through an early warning method, and issues an early warning for each time period. The present invention comprehensively considers the equipment factor information, extracts the power equipment factor characteristics during normal operation and failure of the power equipment according to the historical power equipment factor information, and calculates the fault trigger value considering the human factor information and the meteorological factor information. The early warning method of the present invention integrates multi-source fault information, considers the accidental fault triggering under human factors and weather factors, has universal applicability to distribution network fault early warning, and is of great significance to ensuring the safe and stable operation of the distribution network.
[0086] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the program can be stored in a non-volatile computer-readable storage medium. When the program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application can include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).
[0087] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
[0088] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution, which should be included in the scope of the claims of the present invention.
Claims
1. A distribution network fault early warning method based on multiple factors, characterized in that: include: S1: Acquire multi-source fault information of the distribution network after preprocessing; wherein the multi-source fault information includes: human factor information, meteorological factor information and power equipment factor information; S2: extracting the power equipment factor information to obtain the power equipment factor features; S3: Based on the historical power equipment factor characteristics, use the time series prediction algorithm to predict the power equipment factor characteristics from the current time t0 to the next time period t0+t′; S4: extracting the power equipment factor features when the power equipment is operating normally and when it fails according to the historical power equipment factor information, and using the FCM clustering algorithm to calculate the membership degree of the power equipment factor features in the time period [t0, t0+t′] belonging to the failure; S5: Calculate the accidental fault triggering factor at the current time t0 according to the human factor information and the meteorological factor information; S6: Calculate the fault trigger value at time t0 based on the degree of membership of the power equipment factor characteristics in the time period [t0, t0+t′] when the fault occurs and the accidental fault trigger factor at time t0; determine whether the fault trigger value at time t0 is greater than the set threshold, and if so, issue a fault warning.
2. The distribution network fault early warning method based on comprehensive multi-factors according to claim 1 is characterized in that: The power equipment factor information includes but is not limited to: voltage, current, frequency, and temperature of the power equipment during operation; The feature extraction of the power equipment factor information includes: S21: Obtain the power equipment factor information at time t, and input the power equipment factor information at time t into the encoder of the deep autoencoder network for encoding to obtain the encoded intermediate features; S22: The intermediate features from time tt″ to time t are combined into a feature sequence, and the context information of the feature sequence is fused using the LSTM network to obtain the power equipment factor features at time t; steps S21-S22 are repeated to obtain the power equipment factor features at the current time t0 and all times before the current time t0.
3. The distribution network fault early warning method under comprehensive multi-factors according to claim 1 is characterized in that: The prediction starts from the current time t0 and ends in the time period t0+t′, and the power equipment factor characteristics include: S31: extracting the power equipment factor characteristics in the time period from t0-T to t0; S32: Based on the power equipment factor characteristics in the time period from t0-T to t0, the power equipment factor characteristics in the time period from the current time t0 to the next time period t0+t′ are predicted using a time series prediction algorithm.
4. The distribution network fault early warning method based on comprehensive multi-factors according to claim 3 is characterized in that: The time series prediction algorithm includes but is not limited to: LSTM algorithm and TCN algorithm.
5. The distribution network fault early warning method based on comprehensive multi-factors according to claim 1 is characterized in that: The method of using the FCM clustering algorithm to calculate the degree of membership of the power equipment factor characteristics in the time period [t0, t0+t′] when the power equipment factor characteristics belong to a fault includes: S41: using the FCM clustering algorithm to divide the power equipment factor characteristics when the power equipment is in normal operation and when it is faulty into two groups: normal operation data and faulty operation data, and finding the cluster center of each group; S42: Calculate the degree of membership of the power equipment factor feature in the time period [t0, t0+t′] belonging to the fault according to the cluster centers of the two groups of normal operation data and fault operation data.
6. The distribution network fault early warning method based on comprehensive multi-factors according to claim 1 is characterized in that: The membership degree of the power equipment factor characteristics in the time period [t0, t0+t′] when it belongs to a fault includes: Among them, u2 represents the degree of membership of the power equipment factor characteristics in the time period [t0, t0+t′] belonging to the fault; x represents the power equipment factor characteristics in the time period [t0, t0+t′]; c2 represents the cluster center of the fault operation data group; m represents the fuzziness index; c=2 represents the number of groups; c1 represents the cluster center of the normal operation data group; ||xc k || represents x and c k The Euclidean distance of .
7. The distribution network fault early warning method based on comprehensive multi-factors according to claim 1 is characterized in that: The step S5 comprises: S51: extracting personnel information of the distribution network area at time t0 from the human factor information and calculating the human factor correction coefficient, wherein the personnel information includes the type of personnel, the body temperature of the personnel, and the shortest distance between the personnel and the distribution network equipment; The human factor correction coefficient P includes: Where N represents the total number of people in the distribution network area; P i represents the fault inducing factor of the ith person in the distribution network area; C i Indicates the category of person i; C i =0 means that person i is an internal staff member; C i =1 means that person i belongs to the rest of the people; ε represents the set temperature threshold; φ represents the set safety distance threshold; represents the body temperature of person i; a represents the weight parameter; It indicates the shortest distance between person i and the distribution network equipment; S52: Obtain the weather conditions in the time period [t0, t0+t′] according to the weather forecast, and determine whether extreme weather will occur in the time period [t0, t0+t′]; if so, obtain the number of extreme weather events in history based on historical meteorological factor information and the number of failures that occurred during extreme weather conditions Calculate the weather correction factor S53: The accidental fault trigger factor α=P×W is calculated based on the human factor correction coefficient and the weather factor correction coefficient.
8. The distribution network fault early warning method based on comprehensive multi-factors according to claim 1 is characterized in that: The fault trigger value at time t0 includes: β=u2×α Among them, β represents the fault trigger value, α represents the accidental fault trigger factor, and u2 represents the membership degree of the power equipment factor characteristics in the time period [t0, t0+t′] belonging to the fault.
9. A distribution network fault early warning device based on comprehensive multi-factors, characterized in that: It comprises a processor and a memory; the memory is used to store a computer program; the processor is connected to the memory and is used to execute the computer program stored in the memory, so that the distribution network fault early warning device under comprehensive multiple factors executes the distribution network fault early warning method under comprehensive multiple factors described in any one of claims 1 to 8.
10. A computer-readable storage medium storing a program, characterized in that: When the program is executed by the processor, a distribution network fault early warning method based on comprehensive multiple factors as described in any one of claims 1 to 8 is implemented.
Citation Information
Patent Citations
Bearing fault diagnosis method based on fuzzy support vector machine
CN104502103A
Fault prediction method for adaptive threshold of refrigeration equipment based on multi-algorithm fusion
CN110689075A
Power distribution network fault risk early warning method and system based on deep learning
CN112749904A
Power distribution network area early warning method and system, terminal equipment and readable storage medium
CN113536206A
Botnet detection method based on CNN and LSTM-DAE