Integral lifting construction method for large steel truss

By assembling and welding steel mesh on the ground, and using multi-point synchronous lifting equipment and real-time monitoring technology, the safety risks and accuracy problems of high-altitude operations in large steel mesh construction are solved, achieving efficient and safe overall improvement , ensuring the stability and accuracy of the structure.

CN118933365APending Publication Date: 2024-11-12CHINA RAILWAY SIXTH GROUP CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411087195.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

Large steel mesh frames face problems that are difficult to ensure safety risks, accuracy and quality of high altitude operations during construction, especially in environments with a height of more than 30 meters, and the overall lifting process requires synchronous control and stress monitoring, so the existing technology is difficult to be effective. solve.

Method used

The steel mesh frame is assembled and welded on the ground, and the multi-point synchronous lifting equipment is slowly and evenly lifted, and the stress distribution and deformation are monitored in real time. Hydraulic or electric lifters and stress sensors are used to ensure the stability and safety of the lifting process. Finally, the connection is highly fixed in the design.

Benefits of technology

It improves construction efficiency and quality, reduces the safety risks of high-altitude operations, ensures the stability and accuracy of the steel mesh structure, and reduces construction costs and time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933365A_ABST
    Figure CN118933365A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building steel net rack lifting, in particular to a large steel net rack overall lifting construction method. The method comprises the following steps: S1, splicing, welding and inspecting the steel net rack on the ground; s2, lifting equipment is installed on the periphery of the building, and lifting hanging points are installed at key joints of the steel net frame; and S3, the lifting equipment is started, and the steel grid structure is slowly and evenly lifted at the speed of 1-2 meters per minute. The steel net rack is spliced and welded on the ground, the whole steel net rack is lifted through multi-point synchronous lifting equipment, the stability and safety of the lifting process are ensured by monitoring and adjusting the stress distribution and deformation conditions in the lifting process in real time, the construction efficiency and quality are improved, the safety risk of high-altitude operation is reduced, and the construction cost is reduced. And meanwhile, the stability and accuracy of the steel grid structure are ensured, the method is suitable for the large-span and heavy-weight steel grid structure, and the construction cost and time are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building steel grid lifting, and in particular to a large-scale steel grid integral lifting construction method. Background Art

[0002] In modern construction projects, large steel grid structures are widely used in various large public buildings, such as stadiums, airport terminals, exhibition halls and large industrial plants, due to their excellent mechanical properties, light weight, high strength and beautiful appearance. Steel grid structures are usually composed of multiple rods connected by nodes to form a spatial grid. Its geometric shape and connection method can form a variety of complex architectural shapes. This structure can not only cover a large span space, but also has good seismic resistance and stability.

[0003] However, large steel grid structures face many challenges during construction. First, because steel grid structures are usually large in size and weight, traditional construction methods require the erection of a large number of support frames and high-altitude operations, which not only increases the complexity and cost of construction, but also poses a greater safety risk. Especially in high-altitude working environments with a height of more than 30 meters, the operating difficulty and risk of construction workers are greatly increased. Once an accident occurs, the consequences are disastrous.

[0004] Secondly, the node connection and rod assembly process of the steel grid structure requires highly accurate positioning and welding technology. Traditional high-altitude assembly and welding operations are not only inefficient, but also difficult to ensure construction quality. The stress characteristics of the steel grid structure require that the connections between each node and rod have high precision and high strength. Once there is a deviation or welding quality problem, it will seriously affect the safety and stability of the overall structure.

[0005] Thirdly, the overall lifting process of the steel grid requires strict synchronous control and monitoring. Since the steel grid structure has a large span and weight, if the lifting points are not synchronized or the stress distribution is uneven during the lifting process, it will cause structural deformation or even damage. Therefore, how to achieve multi-point synchronous lifting and real-time monitoring and adjustment of the stress state of the steel grid during the lifting process is a key problem in the overall lifting construction technology of the steel grid.

[0006] In order to solve the above problems, in recent years, a variety of improved and innovative construction methods have emerged in the field of construction engineering. For example, some methods use segmented assembly and segmented lifting, by dividing the steel grid into several small sections, assembling and lifting them separately, and then connecting them at high altitude. This method can reduce the weight and difficulty of a single lift, but it still requires a lot of high-altitude work and support frame erection, the construction period is long, and the accuracy and quality of the high-altitude connection are difficult to guarantee. For this reason, we propose a large-scale steel grid overall lifting construction method. Summary of the invention

[0007] The purpose of the present invention is to provide a large-scale steel grid integral lifting construction method to solve the problems raised in the above-mentioned background technology.

[0008] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0009] A large steel grid overall lifting construction method comprises the following steps:

[0010] S1: Assemble, weld and inspect the steel grid on the ground;

[0011] S2: Install lifting equipment around the building and install lifting points at key nodes of the steel grid;

[0012] S3: Start the lifting equipment, slowly and evenly lift the steel grid structure at a speed of 1-2 meters per minute, and monitor the stress distribution and deformation in real time;

[0013] S4: After lifting to the designed height, the steel grid is fixedly connected to the embedded parts of the building;

[0014] S5: Adjust the horizontality and verticality of the steel grid to ensure that the error does not exceed ±5 mm, and finally fix the connection.

[0015] Preferably, the lifting equipment comprises a hydraulic lifter or an electric lifter, and the rated lifting force of each lifting equipment is 10 tons to 20 tons.

[0016] Preferably, the assembling of the steel grid on the ground comprises the following steps:

[0017] Step 1: Build a temporary assembly platform on the ground with a height of 0.5m to 1.5m;

[0018] Step 2: Assemble and weld the components of the steel grid on the platform;

[0019] Step 3: Inspect the welding quality and structural stability, and upgrade after passing the inspection.

[0020] Preferably, the installation of lifting equipment around the building comprises the following steps:

[0021] Step 1: Set up a lifting equipment installation base around the building. The base is cast in concrete with a strength grade of C30 and a size of 1.5 meters long, 1.5 meters wide and 1 meter high;

[0022] Step 2: Set up several lifting points around the building and in the center area, with the distance between each lifting point being 12 to 15 meters. The specific distance is determined according to the weight of the steel grid and the structural characteristics of the building;

[0023] Step 3: Install a hydraulic lifter or electric lifter at the lifting point. The installation height of the lifting equipment should be 1 to 1.5 meters to ensure the stability and operating space of the lifting equipment.

[0024] Step 4: Set a horizontal support beam between the lifting equipment and the building. The support beam is made of H-shaped steel with a specification of H300×300×10×15mm to enhance the stability of the lifting equipment;

[0025] Step 5: After the lifting equipment is installed, a loading test is carried out. The loading weight of each lifting equipment is 1.25 times its rated lifting force and the duration is 30 minutes to ensure the safety and reliability of the equipment and the installation base.

[0026] Preferably, the lifting device is connected to the lifting hanging point of the steel grid via a steel cable with a diameter of 16 mm to 24 mm.

[0027] Preferably, the real-time monitoring of stress distribution and deformation includes using stress sensors and deformation monitoring equipment to collect and analyze data, with a monitoring frequency of 10 times per second.

[0028] Preferably, after being lifted to the designed height, the steel grid is fixedly connected to the embedded parts of the building by bolts of M20 to M30 specifications.

[0029] Preferably, the adjustment of the horizontality and verticality of the steel grid includes precise measurement and adjustment using a laser leveler and a total station, and the error of the horizontality and verticality does not exceed ±3 mm.

[0030] Preferably, during the lifting process, the synchronization of the lifting equipment is coordinated through a computer control system to ensure the smoothness of the steel grid lifting, and the synchronization control accuracy is ±2 mm.

[0031] Preferably, the lifting points installed at the key nodes of the steel grid include:

[0032] Weld lifting points at the main stress nodes of the steel grid;

[0033] A reinforcing plate with a thickness of 10 mm to 15 mm is set at the lifting hanging point to enhance the bearing capacity of the node.

[0034] It can be seen without a doubt that the above-mentioned technical solution of the present application can definitely solve the technical problem to be solved by the present application.

[0035] At the same time, through the above technical solutions, the present invention has at least the following beneficial effects:

[0036] The present invention assembles and welds the steel grid on the ground, utilizes multi-point synchronous lifting equipment to realize the overall lifting of the steel grid, and ensures the stability and safety of the lifting process by real-time monitoring and adjusting the stress distribution and deformation during the lifting process, thereby improving the construction efficiency and quality and reducing the safety risks of high-altitude operations. At the same time, the present invention ensures the stability and accuracy of the steel grid structure, is suitable for large-span and heavy-weight steel grid structures, and reduces construction costs and time. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying any creative work.

[0038] Figure 1 It is a structural schematic diagram of the present invention;

[0039] Figure 2 It is a schematic diagram of the assembly process of the steel grid of the present invention;

[0040] Figure 3 It is a schematic diagram of the process of installing the lifting equipment of the present invention. DETAILED DESCRIPTION

[0041] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0042] Example 1

[0043] Reference Figure 1-2 A large steel grid overall lifting construction method comprises the following steps:

[0044] S1: Assemble, weld and inspect the steel grid on the ground;

[0045] S2: Install lifting equipment around the building and install lifting points at key nodes of the steel grid;

[0046] S3: Start the lifting equipment, slowly and evenly lift the steel grid structure at a speed of 1-2 meters per minute, and monitor the stress distribution and deformation in real time;

[0047] S4: After lifting to the designed height, the steel grid is fixedly connected to the embedded parts of the building;

[0048] S5: Adjust the horizontality and verticality of the steel grid to ensure that the error does not exceed ±5 mm, and finally fix the connection. This method improves the construction quality and efficiency and reduces the safety risks of high-altitude operations by assembling and welding the steel grid on the ground. The slow and uniform lifting speed and real-time monitoring of stress distribution ensure the stability of the structure, and the final precise adjustment ensures the installation accuracy of the steel grid.

[0049] The lifting equipment includes hydraulic lifters or electric lifters. The rated lifting capacity of each lifting equipment is 10 tons to 20 tons. Selecting appropriate lifting equipment and rated lifting capacity ensures the safety and reliability of the lifting process and can adapt to steel grid structures of different weights and sizes.

[0050] The assembly of the steel grid on the ground includes the following steps:

[0051] Step 1: Build a temporary assembly platform on the ground with a height of 0.5m to 1.5m;

[0052] Step 2: Assemble and weld the components of the steel grid on the platform;

[0053] Step 3: Inspect the welding quality and structural stability. After passing the inspection, lift it and build a temporary assembly platform on the ground to facilitate construction operations. The weld quality and structural inspection that meet the standards improve the overall quality and safety of the steel grid.

[0054] The lifting equipment is connected to the lifting hanging points of the steel grid through steel cables with a diameter of 16 mm to 24 mm. Using steel cables of appropriate diameter to connect the lifting equipment and the steel grid ensures the load-bearing capacity and safety during the lifting process and reduces the risk of steel cable breakage or slippage.

[0055] Real-time monitoring of stress distribution and deformation includes the use of stress sensors and deformation monitoring equipment for data collection and analysis, with a monitoring frequency of 10 times per second. High-frequency real-time monitoring can promptly detect and correct stress concentration and deformation problems that occur during the lifting process, ensuring the stability and safety of the steel grid structure.

[0056] After lifting to the designed height, the steel grid is fixedly connected to the embedded parts of the building through bolts of M20 to M30 specifications. The appropriate specifications of bolts or standard welding methods are used for fixing the connection, ensuring the firm connection between the steel grid and the building and improving the safety and stability of the overall structure.

[0057] Adjustments to the horizontality and verticality of the steel grid include precise measurement and adjustment using a laser leveler and total station. The error in horizontality and verticality does not exceed ±3 mm. Adjustments are made using precise measuring instruments, ensuring the installation accuracy of the steel grid. This ensures that the overall structure meets design requirements and avoids deformation and displacement problems in subsequent use.

[0058] During the lifting process, the synchronization of the lifting equipment is coordinated through the computer control system to ensure the smooth lifting of the steel grid. The synchronization control accuracy is ±2 mm. The computer control system ensures the synchronization of the lifting equipment, improves the smoothness and safety of the lifting process, and avoids deformation or damage to the steel grid structure due to asynchrony.

[0059] The lifting points installed at the key nodes of the steel grid include:

[0060] Weld lifting points at the main stress nodes of the steel grid;

[0061] Reinforcement plates with a thickness of 10 mm to 15 mm are set at the lifting and hanging points to enhance the bearing capacity of the nodes. Lifting and hanging points are set at the main stress nodes and reinforcement plates are used to improve the bearing capacity and safety of the nodes and ensure the stability of the steel grid during the lifting process and after fixation.

[0062] Example 2

[0063] Embodiment 1 is further optimized, specifically, as Figure 3 As shown, installing the lifting equipment around the building includes the following steps:

[0064] Step 1: Set up a lifting equipment installation base around the building. The base is cast in concrete with a strength grade of C30 and a size of 1.5 meters long, 1.5 meters wide and 1 meter high;

[0065] Step 2: Set up several lifting points around the building and in the center area, with the distance between each lifting point being 12 to 15 meters. The specific distance is determined according to the weight of the steel grid and the structural characteristics of the building;

[0066] Step 3: Install a hydraulic lifter or electric lifter at the lifting point. The installation height of the lifting equipment should be 1 to 1.5 meters to ensure the stability and operating space of the lifting equipment.

[0067] Step 4: Set a horizontal support beam between the lifting equipment and the building. The support beam is made of H-shaped steel with a specification of H300×300×10×15mm to enhance the stability of the lifting equipment;

[0068] Step 5: After the lifting equipment is installed, a loading test is carried out. Each lifting equipment is loaded with 1.25 times its rated lifting force for 30 minutes to ensure the safety and reliability of the equipment and the installation base. The detailed lifting equipment installation steps and standardized base size, lifting point spacing and installation height ensure the stability and reliability of the lifting equipment. The safety of the lifting equipment and base is verified through the loading test, reducing the risks during the construction process.

[0069] From the above, we can know that:

[0070] The present invention is directed to the following technical problems: the existing technology adopts the method of segmented assembly and segmented lifting, by dividing the steel grid into several small segments, assembling and lifting them separately, and then connecting them at high altitude. This method can reduce the weight and difficulty of a single lift, but still requires a lot of high-altitude operations and support frame erection, the construction period is long, and the accuracy and quality of high-altitude connections are difficult to guarantee; the technical solutions of the above embodiments are adopted.

[0071] By setting the above technical solution, the present application can certainly solve the above technical problems and achieve the following technical effects:

[0072] The present invention assembles and welds the steel grid on the ground, utilizes multi-point synchronous lifting equipment to realize the overall lifting of the steel grid, and ensures the stability and safety of the lifting process by real-time monitoring and adjusting the stress distribution and deformation during the lifting process, thereby improving the construction efficiency and quality and reducing the safety risks of high-altitude operations. At the same time, the present invention ensures the stability and accuracy of the steel grid structure, is suitable for large-span and heavy-weight steel grid structures, and reduces construction costs and time.

[0073] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0074] Obviously, the embodiments described above are only some embodiments of the present invention, rather than all embodiments. The preferred embodiments of the present invention are given in the accompanying drawings, but they do not limit the patent scope of the present invention. The present invention can be implemented in many different forms. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosure of the present invention more thorough and comprehensive. Although the present invention has been described in detail with reference to the aforementioned embodiments, for those skilled in the art, it is still possible to modify the technical solutions recorded in the aforementioned specific embodiments, or to perform equivalent replacements for some of the technical features therein. Any equivalent structure made using the contents of the specification and drawings of the present invention, directly or indirectly used in other related technical fields, is also within the scope of patent protection of the present invention.

Claims

1. A large steel grid overall lifting construction method, characterized in that: The following steps are involved: S1: Assemble, weld and inspect the steel grid on the ground; S2: Install lifting equipment around the building and install lifting points at key nodes of the steel grid; S3: Start the lifting equipment, slowly and evenly lift the steel grid structure at a speed of 1-2 meters per minute, and monitor the stress distribution and deformation in real time; S4: After lifting to the designed height, the steel grid is fixedly connected to the embedded parts of the building; S5: Adjust the horizontality and verticality of the steel grid to ensure that the error does not exceed ±5 mm, and finally fix the connection.

2. A large steel grid overall lifting construction method according to claim 1, characterized in that: The lifting equipment includes a hydraulic lifter or an electric lifter, and the rated lifting force of each lifting equipment is 10 tons to 20 tons.

3. A large steel grid overall lifting construction method according to claim 1, characterized in that: The assembly of the steel grid on the ground comprises the following steps: Step 1: Build a temporary assembly platform on the ground with a height of 0.5m to 1.5m; Step 2: Assemble and weld the components of the steel grid on the platform; Step 3: Inspect the welding quality and structural stability, and upgrade after passing the inspection.

4. A large steel grid overall lifting construction method according to claim 2, characterized in that: The installation of the lifting equipment around the building comprises the following steps: Step 1: Set up a lifting equipment installation base around the building. The base is cast in concrete with a strength grade of C30 and a size of 1.5 meters long, 1.5 meters wide and 1 meter high; Step 2: Set up several lifting points around the building and in the center area, with the distance between each lifting point being 12 to 15 meters. The specific distance is determined according to the weight of the steel grid and the structural characteristics of the building; Step 3: Install a hydraulic lifter or electric lifter at the lifting point. The installation height of the lifting equipment should be 1 to 1.5 meters to ensure the stability and operating space of the lifting equipment. Step 4: Set a horizontal support beam between the lifting equipment and the building. The support beam is made of H-shaped steel with a specification of H300×300×10×15mm to enhance the stability of the lifting equipment; Step 5: After the lifting equipment is installed, a loading test is carried out. The loading weight of each lifting equipment is 1.25 times its rated lifting force and the duration is 30 minutes to ensure the safety and reliability of the equipment and the installation base.

5. A large steel grid overall lifting construction method according to claim 4, characterized in that: The lifting device is connected to the lifting hanging point of the steel grid through a steel cable with a diameter of 16 mm to 24 mm.

6. A large steel grid overall lifting construction method according to claim 1, characterized in that: The real-time monitoring of stress distribution and deformation includes using stress sensors and deformation monitoring equipment to collect and analyze data, with a monitoring frequency of 10 times per second.

7. A large steel grid overall lifting construction method according to claim 1, characterized in that: After being lifted to the designed height, the steel grid is fixedly connected to the embedded parts of the building by bolts of M20 to M30 specifications.

8. A large steel grid overall lifting construction method according to claim 7, characterized in that: The adjustment of the horizontality and verticality of the steel grid includes precise measurement and adjustment using a laser leveler and a total station, and the error of the horizontality and verticality does not exceed ±3 mm.

9. A large steel grid overall lifting construction method according to claim 8, characterized in that: During the lifting process, the synchronization of the lifting equipment is coordinated through a computer control system to ensure the smooth lifting of the steel grid, with a synchronization control accuracy of ±2 mm.

10. A large steel grid overall lifting construction method according to claim 8, characterized in that: The lifting points installed at the key nodes of the steel grid include: Weld lifting points at the main stress nodes of the steel grid; A reinforcing plate with a thickness of 10 mm to 15 mm is set at the lifting hanging point to enhance the bearing capacity of the node.

Citation Information

Patent Citations

  • Reverse cumulative lifting construction method for single-layer spherical reticulated shell structure

    CN106836507A

  • Steel grid frame installation construction method based on BIM

    CN111636693A

  • Large-span steel structure net rack lifting construction method

    CN113738124A

  • Method for entire removal of space truss and assistive support mechanism

    US20220213705A1