Intelligent detection ventilation system and ventilation method for gas tunnel
Through the cooperation of setting up an intelligent control room in the gas tunnel and using air booster devices, gas detectors and small fans, the gas return problem caused by the inability of traditional ventilation systems to regulate the airflow in real time is solved, and the adaptability and efficiency of the ventilation system are improved. Prevent gas backflow and ensure good condition of the ventilation system.
Patent Information
- Application Number
- CN202411184797.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-11-12
AI Technical Summary
Traditional tunnel ventilation systems cannot monitor and regulate airflow in real time, resulting in gas return problems caused by pedestrians and vehicles, affecting the working efficiency and air quality of the ventilation system.
An intelligent detection and ventilation system for gas tunnels was designed. By setting up an intelligent control room in the inlet tunnel, using the cooperation of air booster devices, gas detectors and small fans, the air pressure in the intelligent control room is always greater than the air pressure in the tunnel body. It also ensures that the gas concentration is lower than the preset value to prevent gas reflux.
It improves the adaptability and flexibility of the ventilation system, effectively prevents gas backflow, ensures good ventilation, and reduces construction cycle and health risks to construction personnel.
Smart Images

Figure CN118934061A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel ventilation, and in particular to an intelligent detection ventilation system and a ventilation method for a gas tunnel. Background Art
[0002] A gas tunnel refers to a tunnel in which a coal-bearing layer appears in some parts during tunnel construction, with gas exposed. The ventilation system of a gas tunnel is a vital safety facility in underground projects such as mines and subways. Its function is to control and regulate the airflow in the tunnel to ensure that the air quality and temperature in the working environment meet the requirements of safety and comfort. However, with the acceleration of urbanization and the increase in transportation demand, the ventilation system of a gas tunnel faces increasingly serious challenges, one of the main problems being the gas backflow caused by pedestrians and vehicles.
[0003] The current tunnel ventilation system has a significant effect on the ventilation of double-hole tunnels, but it uses a fixed ventilation plan and equipment configuration for double-hole gas tunnels, and cannot flexibly adjust the airflow distribution according to the actual situation. Construction after ventilation is completed will greatly increase the construction period, and even if the gas is not completely removed, it will affect the health of the construction workers. During the construction process, the movement of pedestrians and vehicles will also drive a large amount of harmful gas back to the gas-free area in the tunnel, polluting the originally clean airflow, thereby affecting the working efficiency and air quality of the ventilation system.
[0004] For double-hole tunnels, the current ventilation system for gas tunnels needs to be further improved. The traditional tunnel ventilation system cannot monitor and adjust the airflow in real time to deal with the gas reflux problem caused by pedestrians and vehicles. Summary of the invention
[0005] In order to solve the technical problem that the traditional laneway ventilation system of a double-hole tunnel cannot monitor and adjust the airflow in real time to cope with the gas reflux caused by pedestrians and vehicles, the present invention provides an intelligent detection ventilation system for a gas tunnel on the one hand, and provides an intelligent detection ventilation method for a gas tunnel on the other hand.
[0006] To achieve the above purpose, the technical solution adopted by the intelligent detection and ventilation system of the gas tunnel in the present invention is: A gas tunnel intelligent detection ventilation system comprises a tunnel body, the tunnel body comprises an air inlet tunnel and a return air tunnel arranged in parallel, a communication channel is connected between the air inlet tunnel and the return air tunnel, an intelligent control room is arranged between the air inlet of the air inlet tunnel and the connecting port between the air inlet tunnel and the communication channel, the intelligent control room is provided with a first air door and a second air door, the first air door and the second air door are arranged in parallel in the air inlet tunnel, the first air door is closer to the air inlet, a small fan is arranged in the intelligent control room, the small fan is installed on the top of the air inlet tunnel, the small fan is connected to one end of the air supply pipe, and the other end of the air supply pipe passes through the intelligent control room toward the second air door; a gas detector and an air booster are arranged in the intelligent control room, both of which are installed on the side wall of the air inlet tunnel; the gas detector, the small fan and the air booster are all electrically connected to a controller; the air pressure in the intelligent control room is always greater than the air pressure in the tunnel body.
[0007] By adopting the above-mentioned structural scheme, an intelligent control room is set up in the air intake tunnel to prevent gas backflow, and through the cooperation between the air booster, the gas detector and the small fan, the air inside the intelligent control room is adjusted according to the on-site implementation situation to keep the air pressure in the intelligent control room always greater than the air pressure in the tunnel body, and to ensure that the gas concentration in the intelligent control room is lower than the preset value, thereby ensuring good ventilation, improving the adaptability and flexibility of the ventilation system, and better preventing gas backflow.
[0008] As a preferred implementation method of an intelligent detection ventilation system for a gas tunnel, the air boosting device includes a booster and a pressure gauge, the booster is electrically connected to the pressure gauge, the pressure gauge is electrically connected to the controller, the booster is connected to one end of the air inlet duct, the other end of the air inlet duct passes through the intelligent control room toward the first air gate, the booster is connected to one end of the air outlet duct, and the other end of the air outlet duct is located in the intelligent control room.
[0009] With the above structural solution, when the air pressure in the intelligent control room is lower than the air pressure in the tunnel, the controller controls the air pressurization device to automatically work, and draws fresh air from the air inlet of the air inlet tunnel into the intelligent control room, so as to keep the air pressure in the intelligent control room always higher than the air pressure in the tunnel. Therefore, when pedestrians or vehicles enter the intelligent control room from the second air door toward the side of the face, the amount of air flowing into the intelligent control room is reduced, and the degree of gas backflow is reduced.
[0010] As a preferred implementation method of an intelligent detection ventilation system for a gas tunnel, the first damper and the second damper are both connected to door frames, the door frames are connected to the side walls of the air inlet tunnel, and rubber sealing strips are provided between the frames of the first damper and the second damper and their respective door frames.
[0011] The above structural solution is adopted to further ensure the airtightness of the intelligent control room.
[0012] As a preferred implementation of a gas tunnel intelligent detection ventilation system, the distance between the first damper and the second damper is 30 meters.
[0013] The above structural solution is adopted to leave enough space for pedestrians and passing vehicles.
[0014] As a preferred implementation method of an intelligent detection ventilation system for a gas tunnel, a fan device is also provided in the air inlet tunnel, and the fan device includes an air supply fan, which is installed at the top of the air inlet tunnel. The air supply fan is located on the side of the first air gate facing the air inlet, and the side of the air supply fan facing the first air gate is connected to one end of the wind tube, and the other end of the wind tube passes through the intelligent control room.
[0015] As a preferred implementation method of an intelligent detection and ventilation system for a gas tunnel, two groups of fan devices are provided. The wind ducts of the first group of fan devices pass through the intelligent control room and extend toward the face of the air inlet tunnel. The wind ducts of the second group of fan devices pass through the intelligent control room and the communication channel in turn and extend toward the face of the air outlet tunnel.
[0016] With the above structural solution, fresh air is delivered by two blowers through their respective air ducts to the vicinity of the face of the air inlet tunnel and the face of the return air tunnel. After reaching the vicinity of the face, the fresh air will be mixed with the pollution source (dust and harmful gases), and will flow into the return air tunnel through the connecting channel and be discharged uniformly from the air outlet of the return air tunnel.
[0017] As a preferred implementation method of an intelligent detection ventilation system for a gas tunnel, the wind tube between the blower and the first air gate is made of a rigid air duct, and the wind tube in the direction of the first air gate away from the air inlet is made of a flexible air duct, and the rigid air duct and the flexible air duct are sealed at the joint.
[0018] With the above structural solution, when the rigid air duct passes through the top of the intelligent control room, the connection with the top of the intelligent control room can be more properly sealed. The flexible air duct improves the durability, explosion-proof performance and service life of the air duct.
[0019] As a preferred implementation method of an intelligent detection ventilation system for a gas tunnel, a first one-way ventilation valve is provided in the air supply pipe, and the first one-way ventilation valve only allows air to flow out of the intelligent control room.
[0020] The above structural solution is adopted to further ensure the airtightness of the intelligent control room.
[0021] As a preferred implementation of an intelligent detection ventilation system for a gas tunnel, a second one-way ventilation valve is provided in the air inlet duct, and the second one-way ventilation valve only allows airflow to flow toward the supercharger.
[0022] The above structural solution is adopted to further ensure the airtightness of the intelligent control room.
[0023] The technical solution adopted by the intelligent detection and ventilation method of the gas tunnel in the present invention is: A gas tunnel intelligent detection ventilation method, which is used for a gas tunnel intelligent detection ventilation system as described in any one of the preceding claims, comprising the following steps: When a person or a vehicle needs to enter the intelligent control room through the air inlet, the first air door is opened and the second air door is closed. After the person or vehicle enters the intelligent control room, the first air door is closed. When the person or vehicle leaves the intelligent control room, the second air door is opened. When a person or a passing vehicle needs to enter the intelligent control room from the second damper toward the side of the face, the second damper is opened and the first damper is closed. After the person or the passing vehicle enters the intelligent control room, the second damper is closed. When the person or the passing vehicle leaves the intelligent control room, the first damper is opened. When the air pressure in the intelligent control room is lower than the air pressure in the tunnel, the controller controls the air pressurizing device to work automatically, extracting fresh air in the air intake tunnel into the intelligent control room, so as to keep the air pressure in the intelligent control room always higher than the air pressure in the tunnel; When the gas detector detects that the gas concentration in the intelligent control room is greater than the preset value, the controller controls the small fan to work automatically and discharge the air in the intelligent control room along the air supply pipe to the outside of the intelligent control room.
[0024] The beneficial effects of the present invention include: An intelligent control room is set up in the air intake tunnel to prevent gas backflow, and through the cooperation between the air booster, gas detector and small fan, the air inside the intelligent control room is adjusted according to the on-site implementation situation to keep the air pressure in the intelligent control room always greater than the air pressure in the tunnel body, and to ensure that the gas concentration in the intelligent control room is lower than the preset value, to ensure good ventilation, improve the adaptability and flexibility of the ventilation system, and better prevent gas backflow. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the technical solution of the present invention, the drawings required for use in the description will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0026] Figure 1 It is a structural schematic diagram of the intelligent detection ventilation system of a gas tunnel in a specific implementation manner of the present invention; Figure 2 It is a structural schematic diagram of the intelligent control room in a specific implementation mode of the present invention; Figure 3 It is a structural schematic diagram of an air boosting device in a specific embodiment of the present invention; Figure 4 It is a schematic diagram of the structure of a gas detector in a specific implementation manner of the present invention.
[0027] List of parts and reference numerals: 1. Tunnel body; 101. Return air tunnel; 102. Inlet air tunnel; 103. Communication passage; 104. Heading face; 105. Air inlet; 106. Air outlet; 2. Fan device; 201. Air blower; 202. Air duct; 203. Assembled fan frame; 204. Expansion screw; 301, first damper; 302, second damper; 303, door frame; 4. Air booster device; 401. Pressure gauge; 402. Supercharger; 403. Air inlet duct; 404. Air outlet duct; 405. Box handle; 5. Gas detector; 501. Gas detection contact; 502. Gas concentration display screen; 6. Small fan; 601. Fan suspension frame; 602. Small fan body; 603. Air supply pipe; 7. Passing vehicles; 8. Intelligent control room. DETAILED DESCRIPTION
[0028] In order to make the purpose, features and advantages of the present invention more obvious and easy to understand, the technical scheme of the present invention will be clearly and completely described below in conjunction with the drawings in this specific embodiment. Obviously, the embodiments described below are only part of the embodiments of the present invention, not all of them. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0029] Reference Figure 1-4 This embodiment proposes a gas tunnel intelligent detection ventilation system, including a tunnel body 1, the tunnel body 1 includes an air inlet tunnel 102 and a return air tunnel 101 arranged in parallel, and a connecting channel 103 is connected between the air inlet tunnel 102 and the return air tunnel 101. Those skilled in the art should understand that in a double-hole tunnel, fresh air enters from the air inlet 105 of the air inlet tunnel 102, enters the return air tunnel 101 from the connecting channel 103, and is then discharged from the air outlet 106 of the return air tunnel 101, and the air inlet 105 and the air outlet 106 are arranged on the same side. In this embodiment, pedestrians or passing vehicles 7 enter and exit the air inlet tunnel 102 through the air inlet 105.
[0030] An intelligent control room 8 is provided between the air inlet 105 of the air inlet tunnel 102 and the connecting port between the air inlet tunnel 102 and the communication channel 103. The intelligent control room 8 is provided with a first damper 301 and a second damper 302. The first damper 301 and the second damper 302 are arranged in parallel in the air inlet tunnel 102. The distance between the first damper 301 and the second damper 302 is 30 meters, and the first damper 301 is closer to the air inlet 105. The first damper 301 and the second damper 302 are both connected to a door frame 303, and the door frame 303 is tightly welded to the side wall of the air inlet tunnel 102. A rubber sealing strip is provided between the frame of the first damper 301 and the second damper 302 and their respective door frames 303. After the first damper 301 and the second damper 302 are closed, they remain tightly connected to their respective door frames 303 to prevent air permeability, thereby improving the airtightness of the intelligent control room 8. The first damper 301 and the second damper 302 are both of the left-right telescopic push-pull type or the up-down telescopic push-pull type.
[0031] A small fan 6 is provided in the intelligent control room 8, and the small fan 6 includes a small fan body 602. The top of the small fan body 602 is connected to the fan suspension frame 601, and the fan suspension frame 601 is fixedly installed on the top of the air inlet channel 102 by expansion screws 204. The small fan body 602 is connected to one end of the air supply pipe 603. The air supply pipe 603 is provided with a first one-way ventilation valve, which only allows air to flow out of the intelligent control room 8. The other end of the air supply pipe 603 passes through the intelligent control room 8 toward the second air gate 302. Furthermore, the air supply pipe 603 can extend into the communication channel 103.
[0032] A gas detector 5 and an air booster 4 are provided in the intelligent control room 8 , and both the gas detector 5 and the air booster 4 are installed on the side wall of the air inlet tunnel 102 .
[0033] The gas detector 5 is fixedly installed on the side wall of the air inlet tunnel 102 by means of expansion screws 204 . The gas detector 5 includes a detector body, a gas concentration display screen 502 and a gas detection contact 501 .
[0034] The air boosting device 4 is fixedly installed on the side wall of the air inlet alley 102 by means of expansion screws 204. The air boosting device 4 is a box-shaped object. The air boosting device 4 includes a supercharger 402 and a pressure gauge 401. The supercharger 402 is electrically connected to the pressure gauge 401, and the pressure gauge 401 is electrically connected to the controller. The supercharger 402 is connected to one end of the air inlet duct 403. A second one-way ventilation valve is provided in the air inlet duct 403. The second one-way ventilation valve only allows airflow to flow to the supercharger 402. The other end of the air inlet duct 403 passes through the intelligent control room 8 toward the first damper 301. The supercharger 402 is connected to one end of the air outlet duct 404, and the other end of the air outlet duct 404 is located in the intelligent control room 8. The press 401 has multiple detection points, which can detect the air pressure in the intelligent control room 8 and the air pressure in the tunnel body 1. When the pressure gauge 401 detects that the air pressure in the intelligent control room 8 is lower than the air pressure in the tunnel body 1, the booster 402 automatically works to draw clean air from the air inlet tunnel 102 through the air inlet duct 403 and discharge it into the intelligent control room 8, so that the air pressure in the intelligent control room 8 is greater than the air pressure in the tunnel body 1.
[0035] The gas detector 5, the small fan body 602 and the air pressure booster 4 are all electrically connected to the controller. The air pressure in the intelligent control room 8 is always greater than the air pressure in the tunnel body 1.
[0036] A fan device 2 is also provided in the air inlet tunnel 102, and the fan device 2 includes an air supply fan 201. The top of the air supply fan 201 is connected to an assembled fan frame 203. The assembled fan frame 203 is fixedly installed on the top of the air inlet tunnel 102 by expansion screws 204. The air supply fan 201 is located on the side of the first damper 301 facing the air inlet 105. The side of the air supply fan 201 facing the first damper 301 is connected to one end of the wind tube 202, and the other end of the wind tube 202 passes through the intelligent control room 8. The diameter of the wind tube 202 is 1.8m. The air duct 202 between the blower 201 and the first air gate 301 is made of a rigid air duct, so that when the rigid air duct passes through the top of the intelligent control room 8, the connection with the top of the intelligent control room 8 can be more properly sealed. The air duct 202 in the direction of the first air gate 301 away from the air inlet 105 is made of a flexible air duct, which improves the durability, explosion-proofness and service life of the air duct 202. The rigid air duct and the flexible air duct are sealed at the joint. The fan device 2 is provided with two groups. The air duct 202 of the first group of fan devices 2 extends toward the face 104 of the air inlet tunnel 102 after passing through the intelligent control room 8 to ensure that fresh air directly reaches the face 104 of the air inlet tunnel 102. The wind duct 202 of the second group of fan devices 2 passes through the intelligent control room 8 and the communication channel 103 in sequence and then extends toward the heading face 104 of the air outlet tunnel to ensure that fresh air reaches the heading face 104 of the air outlet tunnel directly. The diameter of the wind duct 202 at the turning point is thickened by 20 cm, and the wind duct 202 is provided with a waterproof and explosion-proof layer at the turning point for reinforcement, which greatly improves the durability, explosion-proofness and service life of the wind duct 202 and enhances the safety of construction.
[0037] This embodiment also provides a gas tunnel intelligent detection and ventilation method, which is used in the gas tunnel intelligent detection and ventilation system described above, and includes the following steps: Fresh air continuously flows into the air inlet tunnel 102 from the air inlet 105, and is respectively delivered by two blowers 201 through respective air ducts 202 to the vicinity of the tunnel face 104 of the air inlet tunnel 102 and the vicinity of the tunnel face 104 of the return air tunnel 101. After reaching the vicinity of the tunnel face 104, the fresh air will be mixed with the pollution source (dust and harmful gases), and will be merged into the return air tunnel 101 through the connecting channel 103, and will be uniformly discharged from the air outlet 106 of the return air tunnel 101.
[0038] When a person or a passing vehicle 7 needs to enter the intelligent control room 8 through the air inlet 105, the first damper 301 is opened and the second damper 302 is closed. After the person or the passing vehicle 7 enters the intelligent control room 8, the first damper 301 is closed. When the person or the passing vehicle 7 leaves the intelligent control room 8, the second damper 302 is opened.
[0039] When a person or a passing vehicle 7 needs to enter the intelligent control room 8 from the second damper 302 toward the side of the tunnel face 104, the second damper 302 is opened and the first damper 301 is closed. After the person or the passing vehicle 7 enters the intelligent control room 8, the second damper 302 is closed. When the person or the passing vehicle 7 leaves the intelligent control room 8, the first damper 301 is opened.
[0040] When the air pressure in the intelligent control room 8 is lower than the air pressure in the tunnel body 1, the controller controls the air booster device 4 to automatically work, and draws fresh air from the air inlet 105 of the air inlet tunnel 102 into the intelligent control room 8, so as to keep the air pressure in the intelligent control room 8 always higher than the air pressure in the tunnel body 1. Therefore, when pedestrians or vehicles enter the intelligent control room 8 from the second air door 302 toward the side of the tunnel face 104, the amount of air flowing into the intelligent control room 8 is reduced, and the degree of gas backflow is reduced.
[0041] The gas detector 5 will detect the gas concentration in the intelligent control room 8 in real time. When the gas detector 5 detects that the gas concentration in the intelligent control room 8 is greater than the preset value, the controller controls the small fan body 602 to work automatically, and discharges the air in the intelligent control room 8 along the air supply pipe 603 to the outside of the intelligent control room 8. The preset value can be 0.5%.
[0042] In this embodiment, in order to improve the continuous supply of fresh air, the air supply fan 201 adopts a high-power fan, and the air duct 202 directly reaches the vicinity of the tunnel face 104 of the tunnel body 1. In order to solve the gas backflow problem, an intelligent control room 8 is set in the air intake tunnel 102 to block the gas backflow, and through the cooperation between the air booster 4, the gas detector 5 and the small fan 6, the air inside the intelligent control room 8 is adjusted according to the on-site implementation situation, so that the air pressure in the intelligent control room 8 is always greater than the air pressure in the tunnel body 1, and the gas concentration in the intelligent control room 8 is ensured to be lower than the preset value, so as to ensure a good ventilation state, improve the adaptability and flexibility of the ventilation system, and better prevent gas backflow.
[0043] In this embodiment, the intelligent control room 8 is provided to improve the ventilation efficiency and ventilation effect, and reduce the gas backflow caused by the reciprocating movement of pedestrians and passing vehicles 7.
[0044] In this embodiment, the air duct 202 will pass through the intelligent control room 8, the air supply pipe 603 will pass through the second damper 302, and the air inlet duct 403 will pass through the first damper 301. The air duct 202, the air supply pipe 603 and the air inlet duct 403 can be arranged above the first damper 301 and the second damper 302. The air duct 202, the air supply pipe 603 and the air inlet duct 403 pass through the gap between the first damper 301 and the second damper 302 and the top surface of the air inlet lane 102, and the sealing operation of the gap is done well. The air duct 202, the air supply pipe 603 and the air inlet duct 403 can also directly pass through the parts of the first damper 301 and the second damper 302 that will not move. In short, the arrangement of the air duct 202, the air supply pipe 603 and the air inlet duct 403 will not affect the opening and closing of the first damper 301 and the second damper 302.
[0045] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A gas tunnel intelligent detection ventilation system, comprising a tunnel body (1), the tunnel body (1) comprising an air inlet tunnel (102) and a return air tunnel (101) arranged in parallel, a communication channel (103) connecting the air inlet tunnel (102) and the return air tunnel (101), characterized in that: An intelligent control room (8) is provided between an air inlet (105) of the air inlet tunnel (102) and a connecting port between the air inlet tunnel (102) and the communication channel (103). The intelligent control room (8) is provided with a first air door (301) and a second air door (302). The first air door (301) and the second air door (302) are arranged in parallel in the air inlet tunnel (102). The first air door (301) is closer to the air inlet (105). A small fan (6) is provided in the intelligent control room (8). The small fan (6) is installed at the top of the air inlet tunnel (102). The small fan (6) is connected to one end of the air supply pipe (603), and the other end of the air supply pipe (603) passes through the intelligent control room (8) toward the second air door (302); a gas detector (5) and an air booster (4) are arranged in the intelligent control room (8), and the gas detector (5) and the air booster (4) are both installed on the side wall of the air inlet tunnel (102); the gas detector (5), the small fan (6) and the air booster (4) are all electrically connected to the controller; the air pressure in the intelligent control room (8) is always greater than the air pressure in the tunnel body (1).
2. The intelligent detection and ventilation system for a gas tunnel according to claim 1 is characterized in that: The air boosting device (4) comprises a booster (402) and a pressure gauge (401), the booster (402) being electrically connected to the pressure gauge (401), the pressure gauge (401) being electrically connected to the controller, the booster (402) being connected to one end of an air inlet duct (403), the other end of the air inlet duct (403) passing through the intelligent control room (8) toward the first air door (301), the booster (402) being connected to one end of an air outlet duct (404), the other end of the air outlet duct (404) being located in the intelligent control room (8).
3. The intelligent detection and ventilation system for a gas tunnel according to claim 1 is characterized in that: The first damper (301) and the second damper (302) are both connected to a door frame (303), the door frame (303) is connected to the side wall of the air inlet tunnel (102), and rubber sealing strips are provided between the frames of the first damper (301) and the second damper (302) and their respective door frames (303).
4. The intelligent detection and ventilation system for a gas tunnel according to claim 1 is characterized in that: The distance between the first damper (301) and the second damper (302) is 30 meters.
5. The intelligent detection and ventilation system for a gas tunnel according to claim 1 is characterized in that: A fan device (2) is also provided in the air inlet tunnel (102), and the fan device (2) comprises an air supply fan (201). The air supply fan (201) is installed at the top of the air inlet tunnel (102), and the air supply fan (201) is located on the side of the first air door (301) facing the air inlet (105). The side of the air supply fan (201) facing the first air door (301) is connected to one end of the air duct (202), and the other end of the air duct (202) passes through the intelligent control room (8).
6. The intelligent detection and ventilation system for a gas tunnel according to claim 5 is characterized in that: The fan devices (2) are provided with two groups. The wind tubes (202) of the first group of fan devices (2) extend toward the face (104) of the air inlet tunnel (102) after passing through the intelligent control room (8). The wind tubes (202) of the second group of fan devices (2) extend toward the face (104) of the air outlet tunnel after passing through the intelligent control room (8) and the communication channel (103) in sequence.
7. The intelligent detection and ventilation system for a gas tunnel according to claim 5 is characterized in that: The air duct (202) between the air supply fan (201) and the first air door (301) is made of a rigid air duct, and the air duct (202) in the direction away from the first air door (301) and away from the air inlet (105) is made of a flexible air duct, and the rigid air duct and the flexible air duct are sealed at the joint.
8. The intelligent detection and ventilation system for a gas tunnel according to claim 1 is characterized in that: A first one-way ventilation valve is provided in the air supply pipe (603), and the first one-way ventilation valve only allows air to flow out of the intelligent control room (8).
9. The intelligent detection and ventilation system for a gas tunnel according to claim 2, characterized in that: A second one-way ventilation valve is provided in the air inlet duct (403), and the second one-way ventilation valve only allows airflow to flow toward the supercharger (402).
10. A gas tunnel intelligent detection ventilation method, used in a gas tunnel intelligent detection ventilation system according to any one of claims 1 to 9, characterized in that: When a person or a passing vehicle (7) needs to enter the intelligent control room (8) through the air inlet (105), the first air door (301) is opened and the second air door (302) is closed. After the person or the passing vehicle (7) enters the intelligent control room (8), the first air door (301) is closed. When the person or the passing vehicle (7) leaves the intelligent control room (8), the second air door (302) is opened. When a person or a passing vehicle (7) needs to enter the intelligent control room (8) from the second damper (302) toward the side of the tunnel face (104), the second damper (302) is opened and the first damper (301) is closed. After the person or the passing vehicle (7) enters the intelligent control room (8), the second damper (302) is closed. When the person or the passing vehicle (7) leaves the intelligent control room (8), the first damper (301) is opened. When the air pressure in the intelligent control room (8) is lower than the air pressure in the tunnel body (1), the controller controls the air pressurizing device (4) to automatically operate, so as to draw fresh air in the air inlet tunnel (102) into the intelligent control room (8), thereby keeping the air pressure in the intelligent control room (8) always higher than the air pressure in the tunnel body (1); When the gas detector (5) detects that the gas concentration in the intelligent control room (8) is greater than a preset value, the controller controls the small fan (6) to automatically operate, and discharges the air in the intelligent control room (8) along the air supply pipe (603) to the outside of the intelligent control room (8).
Citation Information
Cited By
Pressurizing, oxygenating and ventilating system and method for high-altitude construction tunnel
CN119664416A
A high-altitude construction tunnel pressurization and oxygenation ventilation system and method
CN119664416B
Tunnel intelligent air door system, control method, terminal and storage medium
CN119933773A