Settlement monitoring device for roadbed and pavement engineering construction
By using a combination device of drilling barrel, auger drill bit and deep monitoring mechanism in roadbed construction, the problem that the existing technology cannot monitor the settlement of the deep and below the roadbed in real time is solved, real-time monitoring and continuous early warning of soil layers at different depths is achieved , ensuring construction quality and safety.
Patent Information
- Application Number
- CN202411223910.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-02
- Publication Date
- 2024-11-12
AI Technical Summary
The existing roadbed settlement monitoring device is difficult to continuously monitor after construction, especially under geographical conditions such as mountain roads and goaf roads, which cannot accurately detect the settlement of deep and below roadbeds in real time, affecting the quality and safety of road construction.
A settlement monitoring device for roadbed construction is designed, including drilling barrels and columns that can drill into the ground, equipped with auger drill bits, deep monitoring mechanisms and multi-section gear rod structures, which can monitor the settlement of soil layers at different depths in real time. The multi-section settlement plate monitoring mechanism is horizontally embedded under the road for real-time monitoring.
The device can monitor the settlement of soil on both sides of the roadbed and the road surface in real time and accurately, improve monitoring accuracy and early warning effect, and ensure construction quality and safety of passing vehicles and pedestrians.
Smart Images

Figure CN118936410A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of roadbed settlement monitoring, and in particular to a settlement monitoring device for roadbed and pavement engineering construction. Background Art
[0002] During the construction of roadbed and pavement, settlement monitoring of soft roadbed is an indispensable link. The main purpose of settlement monitoring is to monitor the stability of the roadbed during fill construction on the one hand, and to ensure that the post-construction settlement of the project meets the design requirements by analyzing the settlement monitoring data on the other hand.
[0003] At present, in the process of roadbed and pavement construction, most of the methods of setting monitoring points and reference points are adopted to manually observe the settlement data of the monitoring points. This monitoring method wastes manpower and has a poor effect on the settlement monitoring of the roadbed. In addition, the existing settlement monitoring device for roadbed construction is only suitable for monitoring during construction, and it is not convenient to continue to monitor the settlement of the roadbed and pavement after the construction is completed. Especially for mountain roads and goaf roads, due to their unique geographical factors, real-time and accurate detection and monitoring of settlement are more needed. In addition, in some settlement situations, the road surface does not settle, but the deep soil layer below will settle and collapse inside the deep soil layer after being washed by rainwater. The existing settlement detection device cannot accurately detect the settlement of the deep layer on both sides of the highway and the roadbed below in real time, and it is not convenient to monitor the settlement of soil layers at different depths, which will affect the road construction quality and subsequent settlement warning, and affect the safety of passing vehicles and pedestrians.
[0004] In view of the above, we provide a settlement monitoring device for roadbed and pavement construction to solve the above problems. Summary of the invention
[0005] In view of the above situation, the present invention provides a settlement monitoring device for roadbed and pavement construction, which is convenient for real-time settlement monitoring of soil layers at different depths on both sides of the roadbed, and a multi-section settlement plate monitoring mechanism can be horizontally pre-buried under the paved road surface, so as to monitor the settlement of the road surface and the roadbed below in real time, and facilitate real-time settlement monitoring of the roadbed and road surface as well as the soil layers on both sides of the road.
[0006] A settlement monitoring device for roadbed and pavement construction, comprising a drill barrel and a column that can be drilled into the ground, the column is fixedly installed on the top of the drill barrel, the outer surface of the drill barrel is fixedly connected to a spiral rotating plate, the bottom of the drill barrel is plugged with a spiral drill bit structure that can be easily drilled into the ground, and the spiral drill bit structure is vertically slidably connected to the bottom of the drill barrel, the upper surface of the spiral drill bit structure is provided with a deep monitoring mechanism that can monitor the settlement of deep soil layers, and the deep monitoring mechanism is penetrated into the inside of the drill barrel and the column, the top of the outer surface of the column is provided with an observation component that can cooperate with the deep monitoring mechanism, the inside of the drill barrel is vertically penetrated with a rotatable multi-section gear rod structure, and the two sides of the outside of the multi-section gear rod structure are respectively connected with a first monitoring mechanism and a second monitoring mechanism, the first monitoring mechanism and the second monitoring mechanism are respectively penetrated on both sides of the drill barrel, the number of the drill barrels is two, and the tops of the outsides of the two drill barrels are both sleeved with a detachable clamping ring structure, and a multi-section settlement plate monitoring mechanism that can improve the accuracy of road surface settlement monitoring is provided between the two clamping ring structures.
[0007] Preferably, the number of the spiral turning plates is four and the four spiral turning plates are equidistantly fixedly connected to the outer surface of the drill tube, the four spiral turning plates are spaced apart from each other, and an alarm is fixedly installed on the top of the column.
[0008] Preferably, the spiral drill bit structure includes a spiral drill bit, a sealing ring and a limit rod, the sealing ring is fixedly connected to the upper surface of the spiral drill bit and inserted into the bottom of the drill barrel, a slot is provided at the bottom of the drill barrel and the sealing ring is inserted into the inside of the slot, both sides of the bottom of the inner wall of the drill barrel are fixedly connected with fixed blocks, the number of the limit rods is two and the two limit rods are respectively fixedly connected to the two sides of the upper surface of the spiral drill bit, and the two limit rods are respectively penetrated into the inside of the two fixed blocks.
[0009] Preferably, the deep monitoring mechanism includes a wire rope, a sliding disc and a spring, the bottom end of the wire rope is fixedly connected to the center of the upper surface of the spiral drill bit and is passed through the inside of the drill barrel and the column, the sliding disc is vertically slidably connected to the top of the inside of the column and the top end of the wire rope is fixedly connected to the center of the lower surface of the sliding disc, the number of springs is four and the four springs are fixedly connected to the inner bottom wall of the sliding disc in the form of a circular array, and the top ends of the four springs are fixedly connected to the inner top wall of the column.
[0010] Preferably, the observation component includes a first sensor and an observation window, the number of the first sensors is several and the several first sensors are evenly divided into two groups, the two groups of first sensors are respectively arranged vertically and fixedly installed on the top of both sides of the column and can correspond to the sliding disc, and the observation window is arranged at the top of the side of the column and between the first sensors on both sides.
[0011] Preferably, the multi-section gear rod structure includes a gear rod, a spur gear, a first bevel gear, a second bevel gear and a rotating handle. The gear rod is rotatably connected to the inside of the drill barrel through a bearing. The number of the spur gears is four and the four spur gears are equidistantly fixedly connected to the rod body of the gear rod that passes through the drill barrel. The first bevel gear is fixedly connected to the top of the gear rod, the second bevel gear is fixedly connected to the rotating handle and rotatably connected to the side of the column. The first bevel gear and the second bevel gear are both arranged inside the column and mesh with each other. The gear rod and the first bevel gear are both provided with through holes at the center of the circle, and the wire rope is passed through the through holes of the gear rod and the first bevel gear.
[0012] Preferably, the first monitoring mechanism includes a first arc plug plate, a first rack, a second arc plug plate, a push-out rope body, a retrieval rope body and a second sensor, the first arc plug plate is penetrated into the side of the drill barrel and the first rack is fixedly connected to a side of the first arc plug plate close to the gear rod, the first rack is transmission-connected to a side of the spur gear corresponding thereto, the second arc plug plate is penetrated into the interior of the first arc plug plate, one end of the push-out rope body is fixedly connected to one side of the second arc plug plate close to one end of the gear rod, and the other end of the push-out rope body passes through the first arc plug plate close to one side and one end away from the gear rod and is fixedly connected to the inner surface of the drill barrel, one end of the retrieval rope body is fixedly connected to the other side of the second arc plug plate close to one end of the gear rod, and the other end of the retrieval rope body passes through the first arc plug plate close to one side and one end close to the gear rod and is fixedly connected to the inner surface of the drill barrel, and the second sensor is fixedly installed in the middle of the second arc plug plate close to the gear rod.
[0013] Preferably, the second monitoring mechanism includes a third arc plug plate, a second rack, a fourth arc plug plate, a push-out rope body, a retracting rope body and a second sensor, the third arc plug plate is penetrated at a side of the drill barrel away from the first arc plug plate and the second rack is fixedly connected to a side of the third arc plug plate close to the gear rod, the first rack and the second rack are both penetrated inside the drill barrel and will be respectively meshed with the two sides of the spur gear corresponding thereto, the fourth arc plug plate is penetrated inside the third arc plug plate, one end of the push-out rope body is fixedly connected to one side of the fourth arc plug plate close to one end of the gear rod, and the other end of the push-out rope body passes through the third arc plug plate close to one side and one end away from the gear rod and is fixedly connected to the inner surface of the drill barrel, one end of the retracting rope body is fixedly connected to the other side of the fourth arc plug plate close to one end of the gear rod, and the other end of the retracting rope body passes through the third arc plug plate close to one side and one end close to the gear rod and is fixedly connected to the inner surface of the drill barrel, and the second sensor is fixedly installed in the middle of the side of the fourth arc plug plate away from the gear rod.
[0014] Preferably, the clamping ring structure includes a first ring, a second ring and a threaded sleeve, one side of the first ring and the second ring are hinged to each other and the other side is threaded with a locking bolt, the first ring and the second ring are sleeved on the top of the drill barrel, and the first ring and the second ring are fixedly connected to a threaded sleeve on one side close to the other drill barrel.
[0015] Preferably, the multi-section settlement plate monitoring mechanism includes an elastic rope, a settlement plate, a flexible belt, a third sensor and an electronic level. The number of the settlement plates is several and the several settlement plates are interconnected by flexible belts. The two ends of the settlement plates at both ends that are away from each other are fixedly connected with elastic ropes and the end of the elastic rope away from the settlement plate is fixedly connected with a connector that can be threadedly connected to a threaded sleeve. The connectors on both sides are respectively threadedly connected in the threaded sleeves corresponding to them, and the third sensor and the electronic level are fixedly installed on the upper surface of the settlement plate.
[0016] The above technical solution has the following beneficial effects:
[0017] The settlement monitoring device for roadbed and pavement construction is provided with a drill tube, a spiral drill bit structure, a deep monitoring mechanism, a first detection mechanism, a second monitoring mechanism and a multi-section settlement plate monitoring mechanism. Construction personnel can respectively drill two drill tubes into the deep soil on both sides of the roadbed through the drill tube and the spiral drill bit structure. The spiral drill bit structure can not only facilitate drilling the device into the ground, but also monitor the settlement of the soil layer at the corresponding depth. When the soil layer around the spiral drill bit structure settles, the spiral drill bit structure will fall with it, and can monitor the settlement data of the deep soil layer in real time through the observation component and the deep monitoring mechanism, so that construction personnel can obtain the settlement data in time. and through the multi-section gear rod structure, multiple groups of first monitoring mechanisms and second monitoring mechanisms can be inserted into soil layers of different depths, so that the device can conduct real-time settlement monitoring of soil layers of different depths on both sides of the roadbed, and the multi-section settlement plate monitoring mechanism can be pre-buried horizontally under the paved road surface, so as to monitor the settlement of the road surface and the roadbed below in real time, which is convenient for real-time settlement monitoring of the roadbed and the road surface and the soil layers on both sides of the road, greatly improving the accuracy of the device for settlement monitoring and improving the prevention effect, and the device can continuously monitor the settlement of the roadbed and road surface and give early warning, which can ensure the safety of passing vehicles and pedestrians. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0019] Figure 2 It is a schematic diagram of the disassembly of the drill tube and the column of the present invention;
[0020] Figure 3 It is a schematic diagram of a multi-section settlement plate monitoring mechanism of the present invention;
[0021] Figure 4 It is a cross section of the drill tube and a schematic diagram of the internal structure of the drill tube of the present invention;
[0022] Figure 5 It is a cross-sectional schematic diagram of a column of the present invention;
[0023] Figure 6 It is a schematic diagram of the first detection mechanism and the second monitoring mechanism of the present invention;
[0024] Figure 7 This is a schematic diagram of the split state of the first monitoring mechanism and the second monitoring mechanism of the present invention;
[0025] Figure 8 It is a schematic diagram of the top cross-sectional structure of the first monitoring mechanism and the second monitoring mechanism of the present invention.
[0026] In the figure: 1, drill tube; 2, column; 3, spiral rotating plate; 4, alarm; 5, spiral drill bit; 6, sealing ring; 7, limit rod; 8, slot; 9, fixed block; 10, wire rope; 11, sliding disc; 12, spring; 13, first sensor; 14, observation window; 15, gear rod; 16, spur gear; 17, first bevel gear; 18, second bevel gear; 19, turning handle; 20, first arc plug plate; 21, first rack; 22, second arc plug plate; 23, push out rope body; 24, retract rope body; 25, second sensor; 26, third arc plug plate; 27, second rack; 28, fourth arc plug plate; 29, first ring; 30, second ring; 31, threaded casing; 32, elastic rope; 33, settlement plate; 34, flexible belt; 35, third sensor; 36, electronic level; 37, connector. DETAILED DESCRIPTION
[0027] The above and other technical contents, features and effects of the present invention are described in detail below with reference to the attached Figures 1 to 8 It can be clearly presented in the detailed description of the embodiments that the structural contents mentioned in the following embodiments are all referenced to the drawings in the specification.
[0028] This embodiment provides a settlement monitoring device for roadbed and pavement construction, as shown in the attached Figure 1-8 As shown, it comprises a drill tube 1 and a column 2 that can be drilled into the ground, the column 2 is fixedly installed on the top of the drill tube 1, and a spiral rotating plate 3 is fixedly connected to the outer surface of the drill tube 1. The number of the spiral rotating plates 3 is four and the four spiral rotating plates 3 are fixedly connected to the outer surface of the drill tube 1 at equal distances. The four spiral rotating plates 3 are arranged at intervals from each other, which can facilitate the drill tube 1 to drill into the deep soil layer as a whole;
[0029] The bottom of the drill tube 1 is plugged with an auger drill bit structure that can be easily drilled into the ground, and the auger drill bit structure is vertically slidably connected to the bottom of the drill tube 1. The auger drill bit structure includes an auger drill bit 5, a sealing ring 6 and a limiting rod 7. The sealing ring 6 is fixedly connected to the upper surface of the auger drill bit 5 and plugged into the bottom of the drill tube 1. A slot 8 is provided at the bottom of the drill tube 1 and the sealing ring 6 is plugged into the inside of the slot 8. When the auger drill bit 5 falls, the sealing ring 6 can ensure the sealing of the bottom of the drill tube 1 to prevent the auger drill bit 5 from being generated between the auger drill bit 5 and the bottom of the drill tube. The inner wall of the drill tube 1 is fixed with fixed blocks 9 on both sides of the bottom, and the number of the limiting rods 7 is two, and the two limiting rods 7 are respectively fixedly connected to the two sides of the upper surface of the spiral drill bit 5. The two limiting rods 7 are respectively passed through the inside of the two fixing blocks 9. The fixing blocks 9 can limit the limiting rods 7, so that the limiting rods 7 and the spiral drill bit 5 at the bottom can only move up and down relative to the drill tube 1. Therefore, the spiral drill bit 5 and the drill tube 1 can be drilled into the ground by rotating the drill tube 1.
[0030] The upper surface of the spiral drill bit structure is provided with a deep monitoring mechanism that can monitor the settlement of the deep soil layer, and the deep monitoring mechanism is arranged inside the drill tube 1 and the column 2. The deep monitoring mechanism includes a wire rope 10, a sliding disc 11 and a spring 12. The bottom end of the wire rope 10 is fixedly connected to the center of the upper surface of the spiral drill bit 5 and is arranged inside the drill tube 1 and the column 2. The sliding disc 11 is vertically slidably connected to the top of the inside of the column 2 and the top of the wire rope 10 is fixedly connected to the center of the lower surface of the sliding disc 11. There are four springs 12 and the four springs 12 are fixedly connected to the inner bottom wall of the sliding disc 11 in the form of a circular array, and the top ends of the four springs 12 are fixedly connected to the inner top wall of the column 2. The spring 12 can make the bottom of the sliding disc 11 be at the top of the inside of the column 2 when there is no force.
[0031] An observation component that can cooperate with the deep monitoring mechanism is arranged at the top of the outer surface of the column 2. The observation component includes a first sensor 13 and an observation window 14. The number of the first sensors 13 is several and the several first sensors 13 are evenly divided into two groups. The two groups of first sensors 13 are respectively arranged vertically and fixedly installed on the tops of both sides of the column 2 and can correspond to the sliding disc 11. The observation window 14 is arranged at the top of the side of the column 2 and is between the first sensors 13 on both sides. When the deep soil layer around the spiral drill bit 5 settles and drives the sliding disc 11 to fall, not only can its falling state be detected by the first sensor 13, but pedestrians passing by can also see the falling state of the sliding disc 11 through the observation window 14. Reminder content can be set on the column so that pedestrians can be informed of the settlement of the current road section in time to ensure the safety of pedestrians;
[0032] After the drill tube 1 and the auger 5 are vertically drilled into the ground, the auger 5 is in the deep soil layer. When the deep soil layer settles, the auger 5 will fall with the settled part, so that the sliding disc 11 can be pulled downward by the wire rope 10. The gravity of the auger 5 itself is much greater than the pulling force of the four springs 12 on the sliding disc 11, so it will not affect the sliding disc 11 moving downward with the auger 5. When the sliding disc 11 falls, it will correspond to the first sensors 13 on both sides of the column 2 from high to low. When the first sensors at different heights detect the sliding disc 11, they will feed back the data to the external terminal device, so that the relevant personnel can timely know the settlement of the deep soil layer in the current drill tube 1.
[0033] A rotatable multi-section gear rod structure is vertically penetrated inside the drill barrel 1, and the multi-section gear rod structure includes a gear rod 15, a spur gear 16, a first bevel gear 17, a second bevel gear 18 and a rotating handle 19. The gear rod 15 is rotatably connected to the inside of the drill barrel 1 through a bearing. There are four spur gears 16, and the four spur gears 16 are equidistantly fixedly connected to the rod body of the gear rod 15 penetrated in the drill barrel 1. The first bevel gear 17 is fixedly connected to the top of the gear rod 15, and the second bevel gear 18 is fixedly connected to the rotating handle 19 and rotatably connected to the side of the column 2. The first bevel gear 17 and the second bevel gear 18 are both arranged inside the column 2 and mesh with each other. A through hole is opened at the center of the gear rod 15 and the first bevel gear 17. The wire rope 10 is penetrated in the through holes of the gear rod 15 and the first bevel gear 17. By rotating the handle 19, the second bevel gear 18 can drive the first bevel gear 17 and the gear rod 15 to rotate;
[0034] The first monitoring mechanism and the second monitoring mechanism are respectively connected to the two sides of the outside of the multi-section gear rod structure, and the first monitoring mechanism and the second monitoring mechanism are respectively arranged on the two sides of the drill tube 1. The first monitoring mechanism includes a first arc plug plate 20, a first rack 21, a second arc plug plate 22, a push rope body 23, a retracting rope body 24 and a second sensor 25. The first arc plug plate 20 is arranged on the side of the drill tube 1 and the first rack 21 is fixedly connected to the side of the first arc plug plate 20 close to the gear rod 15. The first rack 21 is connected to the side of the spur gear 16 corresponding to it. The second arc plug plate 22 is arranged on the side of the first arc plug plate 20. Inside, one end of the push rope body 23 is fixedly connected to one side of the second arc plug plate 22 close to the gear rod 15, and the other end of the push rope body 23 passes through the first arc plug plate 20 close to the side and away from the gear rod 15 and is fixedly connected to the inner surface of the drill tube 1, one end of the retracting rope body 24 is fixedly connected to the other side of the second arc plug plate 22 close to the gear rod 15, and the other end passes through the first arc plug plate 20 close to the side and close to the gear rod 15 and is fixedly connected to the inner surface of the drill tube 1, and the second sensor 25 is fixedly installed in the middle of the second arc plug plate 22 away from the gear rod 15;
[0035] The second monitoring mechanism includes a third arc plug plate 26, a second rack 27, a fourth arc plug plate 28, a push rope 23, a retracting rope 24 and a second sensor 25. The third arc plug plate 26 is inserted into the drill tube 1 on a side away from the first arc plug plate 20 and the second rack 27 is fixedly connected to a side of the third arc plug plate 26 close to the gear rod 15. The first rack 21 and the second rack 27 are both inserted into the drill tube 1 and are respectively meshed with the two sides of the corresponding spur gear 16. The fourth arc plug plate 28 is inserted into the third arc plug plate 26. One end of the push rope 23 is fixedly connected to the first arc plug plate 20. The fourth arc plug plate 28 is close to one side of one end of the gear rod 15, and the other end of the push rope body 23 passes through the third arc plug plate 26 close to the side and away from the end of the gear rod 15 and is fixedly connected to the inner surface of the drill tube 1, and one end of the retracting rope body 24 is fixedly connected to the other side of the fourth arc plug plate 28 close to the end of the gear rod 15, and the other end of the retracting rope body 24 passes through the third arc plug plate 26 close to the side and close to the end of the gear rod 15 and is fixedly connected to the inner surface of the drill tube 1, and the second sensor 25 is fixedly installed in the middle of the fourth arc plug plate 28 away from the gear rod 15.
[0036] Before the drill tube 1 and the auger 5 are screwed into the ground, the first monitoring mechanism and the second monitoring mechanism on both sides are retracted in the drill tube 1. After the drill tube 1 and the auger 5 are screwed into the ground, the gear rod 15 can be driven to rotate clockwise by rotating the rotation handle 19, and the spur gear 16 on the gear rod 15 can drive the first rack 21 and the second rack 27 to move away from each other, so that the first arc plug plate 20 and the third arc plug plate 26 on both sides can be pushed out of the drill tube 1 and inserted into the soil layer of corresponding depth. At the same time, driven by the pushing rope body 23, the second arc plug plate 22 and the fourth arc plug plate 28 in the first arc plug plate 20 and the third arc plug plate 26 on both sides can be pushed out synchronously, and the retracting rope body 24 on the other side will not cause the second arc plug plate 22 and the fourth arc plug plate 28 to be pushed out when the second arc plug plate 22 and the fourth arc plug plate 28 are pushed out. The second arc plug plate 22 and the fourth arc plug plate 28 can increase the overall extension length of the first monitoring mechanism and the second monitoring mechanism, making the horizontal insertion length longer, so that the area of the soil layer that can be monitored below is larger; when the device needs to be taken out, by turning the handle 19 to drive the gear rod to rotate counterclockwise, the spur gear 16 on the gear rod 15 can drive the first rack 21 and the second rack 27 to approach each other, so that the first arc plug plate 20 and the third arc plug plate 26 on both sides can be retracted into the drill tube 1, and under the drive of the retracting rope body 24, the second arc plug plate 22 and the fourth arc plug plate 28 on both sides can be synchronously retracted into the first arc plug plate 20 and the third arc plug plate 26, and the pushing rope body 23 at this time will not affect the activities of the second arc plug plate 22 and the fourth arc plug plate 28;
[0037] A second sensor 25 is fixedly mounted on the surface of each second arc plug plate 22 and the fourth arc plug plate 28. The second sensor 25 can monitor the soil layer under the second arc plug plate 22 or the fourth arc plug plate 28. When the soil layer under the second arc plug plate 22 and the fourth arc plug plate 28 sinks and falls, a gap will be generated between the corresponding second arc plug plate 22 and the fourth arc plug plate 28. The corresponding second sensor 25 can monitor the settlement of the corresponding part, so that the monitoring personnel can quickly know the settlement and the location where the settlement occurs and respond in time. The setting of multiple first monitoring mechanisms and second monitoring mechanisms at different depths can facilitate the device to monitor the settlement of soil layers at different depths, and the monitoring results do not affect each other, which is more conducive to real-time monitoring of local settlement in the soil layer and enables the monitoring personnel to respond in time.
[0038] There are two drill tubes 1 and the top ends of the two drill tubes 1 are sleeved with a detachable clamping ring structure, which includes a first sleeve 29, a second sleeve 30 and a threaded sleeve 31. One side of the first sleeve 29 and the second sleeve 39 is hinged to each other and a locking bolt is threaded through the other side. The first sleeve 29 and the second sleeve 30 are sleeved on the top of the drill tube 1, and the first sleeve 29 and the second sleeve 30 are fixedly connected with the threaded sleeve 31 on one side close to the other drill tube.
[0039] A multi-section settlement plate monitoring mechanism that can improve the accuracy of road surface settlement monitoring is arranged between the two clamping ring structures. The multi-section settlement plate monitoring mechanism includes an elastic rope 32, a settlement plate 33, a flexible belt 34, a third sensor 35 and an electronic level 36. The number of settlement plates 33 is several and the settlement plates 33 are interconnected by the flexible belt 34. The two ends of the settlement plates 33 at both ends are fixedly connected with elastic ropes 32 on the side away from each other, and the end of the elastic rope 32 away from the settlement plate 33 is fixedly connected with a connector 37 that can be threadedly connected to the threaded sleeve 31. The elastic rope 32 can ensure that the two ends of the settlement plate 33 will not be tightened, so that the settlement plate 33 can fall or tilt accordingly when settlement occurs, thereby ensuring the accuracy of the monitoring results; the connectors 37 on both sides are respectively threadedly connected in the corresponding threaded sleeves 31, and the upper surface of the settlement plate 33 is fixedly installed with the third sensor 35 and the electronic level. Level meter 36, monitoring personnel can drill two drill tubes 1 on both sides of the roadbed respectively, and can pre-bury the multi-section settlement plate detection mechanism horizontally under the road surface, the lower surface of the multi-section settlement plate monitoring mechanism is in contact with the compacted roadbed and the upper surface is under the paved road surface, and the multiple settlement plates 33 in the multi-section settlement monitoring mechanism are in a horizontal state when buried on the roadbed, and the multi-section settlement monitoring mechanisms are connected by a flexible belt 34, so each settlement plate 33 can independently perform settlement detection on the corresponding roadbed part below it, when the detection data of the third sensor 35 on a settlement plate 33 changes or the horizontal state of the electronic level meter 36 changes, it can prove that the state of the roadbed below has changed, which can remind the detection personnel, and then the settlement of the corresponding part can be further accurately detected to confirm whether settlement has occurred, which can play a good preventive effect;
[0040] An alarm 4 is fixedly installed on the top of the column 2. The alarm 4, the first sensor 13, the second sensor 25, the third sensor 35 and the electronic level 36 are all electrically connected to the control unit, and the control unit can transmit the monitoring data to the terminal device, which can facilitate the monitoring personnel to know the monitoring situation in time. When the settlement change data detected by any one of the first sensor 13, the second sensor 25, the third sensor 35 and the electronic level 36 is greater than the pre-set safe settlement range, the terminal device is immediately reminded through the control unit and the alarm 4 is controlled to sound an alarm to remind passers-by that the current road section has great safety hazards, which can effectively prevent pedestrians from passing through dangerous sections without knowing it, thereby ensuring the safety of pedestrians.
[0041] The above description is only for illustrating the present invention. It should be understood that the present invention is not limited to the above embodiments, and various variations that conform to the concept of the present invention are within the protection scope of the present invention.
Claims
1. A settlement monitoring device for roadbed and pavement construction, comprising a drill tube (1) and a column (2) that can be drilled into the ground, characterized in that: The column (2) is fixedly mounted on the top of the drill tube (1); the outer surface of the drill tube (1) is fixedly connected with a spiral rotating plate (3); the bottom of the drill tube (1) is plugged with a spiral drill bit structure that can be easily drilled into the ground, and the spiral drill bit structure is vertically slidably connected to the bottom of the drill tube (1); the upper surface of the spiral drill bit structure is provided with a deep monitoring mechanism that can monitor the settlement of the deep soil layer, and the deep monitoring mechanism is inserted into the inside of the drill tube (1) and the column (2); the top of the outer surface of the column (2) is provided with a deep monitoring mechanism that can be connected with the deep monitoring mechanism. The drill barrel (1) is provided with an observation component that cooperates with a monitoring mechanism, wherein a rotatable multi-section gear rod structure is vertically penetrated inside the drill barrel (1), and the two sides of the outside of the multi-section gear rod structure are respectively connected to a first monitoring mechanism and a second monitoring mechanism, the first monitoring mechanism and the second monitoring mechanism are respectively penetrated on both sides of the drill barrel (1), the number of the drill barrels (1) is two, and the top ends of the outsides of the two drill barrels (1) are both sleeved with a detachable clamping ring structure, and a multi-section settlement plate monitoring mechanism that can improve the accuracy of road surface settlement monitoring is arranged between the two clamping ring structures.
2. A settlement monitoring device for roadbed and pavement construction according to claim 1, characterized in that: The number of the spiral turning plates (3) is four and the four spiral turning plates (3) are fixedly connected to the outer surface of the drill tube (1) at equal distances. The four spiral turning plates (3) are arranged at intervals from each other, and an alarm (4) is fixedly installed on the top of the column (2).
3. A settlement monitoring device for roadbed and pavement construction according to claim 1, characterized in that: The spiral drill bit structure comprises a spiral drill bit (5), a sealing ring (6) and a limiting rod (7); the sealing ring (6) is fixedly connected to the upper surface of the spiral drill bit (5) and inserted into the bottom of the drill tube (1); a slot (8) is provided at the bottom of the drill tube (1) and the sealing ring (6) is inserted into the inside of the slot (8); both sides of the bottom of the inner wall of the drill tube (1) are fixedly connected with fixing blocks (9); there are two limiting rods (7) and the two limiting rods (7) are respectively fixedly connected to the two sides of the upper surface of the spiral drill bit (5); the two limiting rods (7) are respectively inserted into the inside of the two fixing blocks (9).
4. A settlement monitoring device for roadbed and pavement construction according to claim 3, characterized in that: The deep layer monitoring mechanism comprises a steel wire rope (10), a sliding disc (11) and a spring (12); the bottom end of the steel wire rope (10) is fixedly connected to the center of the upper surface of the spiral drill bit (5) and is passed through the inside of the drill tube (1) and the column (2); the sliding disc (11) is vertically slidably connected to the top of the inside of the column (2) and the top end of the steel wire rope (10) is fixedly connected to the center of the lower surface of the sliding disc (11); the number of the springs (12) is four and the four springs (12) are fixedly connected to the inner bottom wall of the sliding disc (11) in the form of a circular array, and the top ends of the four springs (12) are fixedly connected to the inner top wall of the column (2).
5. A settlement monitoring device for roadbed and pavement construction according to claim 4, characterized in that: The observation component comprises a first sensor (13) and an observation window (14); the number of the first sensors (13) is a plurality and the plurality of first sensors (13) are evenly divided into two groups; the two groups of first sensors (13) are respectively arranged vertically and fixedly mounted on the tops of both sides of the column (2) and can correspond to the sliding disc (11); the observation window (14) is arranged on the top of the side of the column (2) and between the first sensors (13) on both sides.
6. A settlement monitoring device for roadbed and pavement construction according to claim 4, characterized in that: The multi-section gear rod structure comprises a gear rod (15), a spur gear (16), a first bevel gear (17), a second bevel gear (18) and a rotating handle (19); the gear rod (15) is rotatably connected to the inside of a drill tube (1) through a bearing; the number of the spur gears (16) is four and the four spur gears (16) are equidistantly fixedly connected to a rod body of the gear rod (15) which is arranged inside the drill tube (1); the first bevel gear (17) is fixedly connected to the top of the gear rod (15); the second bevel gear (18) is fixedly connected to the rotating handle (19) and rotatably connected to the side of a column (2); the first bevel gear (17) and the second bevel gear (18) are both arranged inside the column (2) and mesh with each other; a through hole is opened at the center of the gear rod (15) and the first bevel gear (17); the steel wire rope (10) is passed through the through holes of the gear rod (15) and the first bevel gear (17).
7. A settlement monitoring device for roadbed and pavement construction according to claim 6, characterized in that: The first monitoring mechanism comprises a first arc plug plate (20), a first rack (21), a second arc plug plate (22), a push rope body (23), a retracting rope body (24) and a second sensor (25); the first arc plug plate (20) is arranged on the side of the drill tube (1) and the first rack (21) is fixedly connected to a side of the first arc plug plate (20) close to the gear rod (15); the first rack (21) is transmission-connected to a side of the spur gear (16) corresponding thereto; the second arc plug plate (22) is arranged inside the first arc plug plate (20); one end of the push rope body (23) is fixedly connected to a side of the second arc plug plate (22) close to the gear rod (15); One side of one end of the gear rod (15), and the other end of the pushing rope body (23) passes through the first arc plug plate (20) on the side close to it and away from the end of the gear rod (15) and is fixedly connected to the inner surface of the drill tube (1); one end of the retracting rope body (24) is fixedly connected to the other side of the second arc plug plate (22) close to the end of the gear rod (15), and the other end of the retracting rope body (24) passes through the first arc plug plate (20) on the side close to it and close to the end of the gear rod (15) and is fixedly connected to the inner surface of the drill tube (1); the second sensor (25) is fixedly installed in the middle of the second arc plug plate (22) on the side away from the gear rod (15).
8. A settlement monitoring device for roadbed and pavement construction according to claim 7, characterized in that: The second monitoring mechanism comprises a third arc plug plate (26), a second rack (27), a fourth arc plug plate (28), a push rope body (23), a retracting rope body (24) and a second sensor (25); the third arc plug plate (26) is arranged on a side of the drill tube (1) away from the first arc plug plate (20), and the second rack (27) is fixedly connected to a side of the third arc plug plate (26) close to the gear rod (15); the first rack (21) and the second rack (27) are both arranged inside the drill tube (1) and are respectively meshed with two sides of the corresponding spur gears (16); the fourth arc plug plate (28) is arranged inside the third arc plug plate (26); one end of the push rope body (23) is The first embodiment of the present invention is a first embodiment of the present invention which is fixedly connected to one side of the fourth arc plug plate (28) close to one end of the gear rod (15), and the other end of the push rope body (23) passes through the third arc plug plate (26) close to one side of the third arc plug plate (26) and one end away from the gear rod (15) and is fixedly connected to the inner surface of the drill tube (1); one end of the retracting rope body (24) is fixedly connected to the other side of the fourth arc plug plate (28) close to one end of the gear rod (15), and the other end of the retracting rope body (24) passes through the third arc plug plate (26) close to one side of the third arc plug plate (26) and one end close to the gear rod (15) and is fixedly connected to the inner surface of the drill tube (1); the second sensor (25) is fixedly mounted in the middle of the fourth arc plug plate (28) away from the gear rod (15).
9. A settlement monitoring device for roadbed and pavement construction according to claim 1, characterized in that: The clamping ring structure comprises a first sleeve (29), a second sleeve (30) and a threaded sleeve (31); one side of the first sleeve (29) and the second sleeve (39) are hinged to each other and a locking bolt is threadedly penetrated on the other side; the first sleeve (29) and the second sleeve (30) are sleeved on the top of the drill tube (1); and the first sleeve (29) and the second sleeve (30) are fixedly connected to the threaded sleeve (31) on one side close to the other drill tube.
10. A settlement monitoring device for roadbed and pavement construction according to claim 1, characterized in that: The multi-section settlement plate monitoring mechanism comprises an elastic rope (32), a settlement plate (33), a flexible belt (34), a third sensor (35) and an electronic level (36); the number of the settlement plates (33) is several and the several settlement plates (33) are connected to each other through the flexible belt (34); the two ends of the settlement plates (33) at both ends are fixedly connected to the elastic rope (32) at one end away from each other, and the end of the elastic rope (32) away from the settlement plate (33) is fixedly connected to a connector (37) that can be threadedly connected to a threaded sleeve (31); the connectors (37) on both sides are respectively threadedly connected in the threaded sleeve (31) corresponding thereto; and the third sensor (35) and the electronic level (36) are fixedly installed on the upper surface of the settlement plate (33).