Underground soil bearing capacity uniformity analysis method based on drill rod detection record

Through machine vision and genetic algorithms, the problem of low degree of brazing automation in the existing technology is solved, the efficiency and accuracy of brazing are improved, and real-time sharing of brazing data and automated reporting generation are realized.

CN118937201AActive Publication Date: 2024-11-12DEZHOU DINGWANG TIANCHENG CONSTR ENG CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202410940708.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-11-12
Estimated Expiration
2044-07-15

AI Technical Summary

Technical Problem

The existing brazing technology has low degree of automation, and requires manual operation of the brazing probe and recording the brazing results, resulting in insufficient efficiency and accuracy.

Method used

Using methods based on machine vision and genetic algorithms, we automatically generate the cracking path, collect and analyze the cracking data in real time, including automatically adjusting the drop hammer height and counting the number of hammers, and generating a cracking analysis report.

Benefits of technology

It improves the efficiency and accuracy of the cracking operation, reduces manual recording errors, and realizes real-time sharing of cracking data and automated analysis report generation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118937201A_ABST
    Figure CN118937201A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of foundation testing, in particular to an underground soil bearing capacity uniformity analysis method based on drill rod detection records, which comprises the following steps: S1, generating a foundation pit profile diagram, constructing a cross coordinate system by taking the center of a foundation pit as an original point, and determining coordinates and numbers of drill rod detection point positions; s2, generating a drill rod detection path of the drill rod detection machine according to the coordinate information of each drill rod detection point; s3, guiding the drill rod detection machine to perform drill rod detection on each drill rod detection point position in sequence according to the drill rod detection path; when drilling detection is carried out on any drilling detection point position, the distance between the bottom of the drop hammer and the top of the probe rod is adjusted to be maintained at a preset distance; whether each round of hammering is finished or not is recognized based on machine vision, and the number of hammering times of each round is automatically counted; and S4, after drill rod detection of all drill rod detection points is completed, drill rod detection data are shared to a client, and a drill rod detection analysis report for all drill rod detection points of the current foundation pit is generated according to a preset template. According to the invention, path guiding, drilling and drilling detection recording processes of the drilling detection machine can be automatically completed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation testing, and more particularly to an analysis method for the uniformity of underground soil bearing capacity based on drilling records. Background Art

[0002] The drilling test, also known as the light dynamic penetration test, refers to the exploration of the soil layer below the bottom of the foundation pit after the excavation reaches the design elevation to determine the hardness of the soil. At present, in the drilling test, it is usually necessary to manually operate the drilling machine to the designated location for drilling, and manually record the drilling results, and the degree of automation is low. Summary of the invention

[0003] In view of this, the present invention provides an analysis method for the uniformity of underground soil bearing capacity based on the drilling record, which can automatically complete the path guidance, drilling and drilling recording processes of the drilling machine.

[0004] In order to achieve the above object, the present invention adopts the following technical solution:

[0005] A method for analyzing the uniformity of underground soil bearing capacity based on drilling records comprises the following steps:

[0006] S1. Generate a foundation pit outline map, take the center of the foundation pit as the origin, construct a cross coordinate system, and determine the coordinates and numbers of each drilling point;

[0007] S2, generating the drilling path of the drilling machine according to the coordinate information of each drilling point;

[0008] S3, guide the drilling probe machine to perform drilling on each drilling point in turn according to the drilling path; when drilling on any drilling point, each time the probe rod is hammered, the height of the hammer is adjusted once, so that before each hammering, the distance between the bottom of the hammer and the top of the probe rod is maintained at a preset distance; and the image information of the probe rod is collected in real time, and when the first scale mark on the probe rod is flush with the ground, it is regarded as the end of the first round of hammering;

[0009] After the probe rod has been hammered for a preset number of rounds, the drilling test for the drilling point is deemed to be completed, and the number of hammering times in each round for the drilling point number is recorded;

[0010] S4. When all the drilling points are completed, the drilling data is shared with the client, and a drilling analysis report for each drilling point in the current foundation pit is generated according to the preset template.

[0011] Furthermore, S2 includes:

[0012] S21, determining a fitness function;

[0013] S22, initialize according to the coordinate information of each drilling point to obtain an initial drilling path population;

[0014] S23, selecting individuals with high fitness ranking from the initial drilling path population and performing crossover, mutation, and reversal operations;

[0015] S24. When the individual with the best fitness in the population does not change for several consecutive generations starting from a certain generation, the iterative process is terminated and the optimal solution in the population at this time is output as the result of the drilling path planning.

[0016] Further, in S21, the fitness function is the inverse of the total length of the probe path, expressed as:

[0017] F i =1 / L i

[0018] Among them, F i Indicates the fitness value of the drilling path numbered i, L i Indicates the length of the probe path numbered i.

[0019] Furthermore, S22 includes:

[0020] S221, using a linear regression method to fit the coordinates of each probe in the foundation pit area to obtain a linear regression line H1;

[0021] S222, calculating the center point of the regression line H1 in the foundation pit area, and determining the perpendicular line H2 passing through the regression line H1, and dividing the foundation pit area into four sub-areas by the regression line H1 and the perpendicular line H2;

[0022] S223, recursively execute S221-S222 in each probe sub-region, further divide each sub-region, when the probe point digit in a certain sub-region is less than or equal to 3, be regarded as this sub-region division and end, until the probe point digit contained in all sub-regions is less than or equal to 3, be regarded as the whole foundation pit area division and end, obtain multiple minimum probe areas;

[0023] S224, randomly select a minimum probe area as the initial minimum probe area, randomly select a probe point in the initial minimum probe area as the starting probe point, and add the nearest probe point as the new starting probe point until all probe points are connected;

[0024] Then the initial minimum probe area is connected to a nearest probe point in other nearest minimum probe areas until all the probe points in all the minimum probe areas are connected to generate a probe path;

[0025] S225. Loop through S221-S224 m times to obtain m initial drilling paths, forming an initial drilling path population.

[0026] Furthermore, in S3, the process of adjusting the height of the drop hammer includes:

[0027] The distance between the drop weight and the probe rod is adjusted to a preset distance in advance, and an image of the drop weight and the probe rod is taken in advance by a camera installed at a designated position of the drilling probe machine, and the pixel distance between the drop weight and the probe rod in the image is calibrated as the standard pixel distance;

[0028] When probing any probing point, keep the camera installation position unchanged. Before hammering the probe rod each time, collect images of the drop hammer and the probe rod in real time, calculate the current pixel distance between the two images, and determine whether the current pixel distance is equal to the standard pixel spacing. If so, control the drop hammer to perform this hammering. Otherwise, adjust the drop hammer height until the spacing between the bottom of the drop hammer and the top of the probe rod in the image is the standard pixel spacing, and then control the drop hammer to perform this hammering.

[0029] Furthermore, in S3, the method for determining whether each round of hammering is completed is:

[0030] The scales on the probe rod are color-marked in advance so that the color of the mark is clearly different from the ground color and the probe rod color; the probe rod is hammered into the ground so that the bottom of the scale mark is flush with the ground, and the image of the bottom of the probe rod is collected by a camera installed at the bottom of the drilling probe, and the pixel width of the scale line in the image is calculated as the standard pixel width;

[0031] Keep the camera installation position unchanged, hammer each pair of probes once, and collect an image of the bottom of the probes once;

[0032] If after a certain hammering, the scale line in the image at the bottom of the probe rod touches the ground, and the pixel width of the scale line is less than or equal to the standard pixel width, then this round of hammering is considered to be over.

[0033] Furthermore, the method for determining whether each round of hammering is completed also includes:

[0034] If after a certain hammering, the scale mark on the lowest side of the probe rod bottom image disappears, but the scale mark on the lowest side of the probe rod bottom image after the previous hammering exists, and there is a certain distance between the lowest side scale line and the ground, then this round of hammering is considered to be over.

[0035] Furthermore, in S3, machine vision is used to count the number of hammer strikes in each round, including:

[0036] The video stream of each round of hammering is collected and frame-by-frame processed to obtain a set of sequentially arranged single-frame images;

[0037] Perform edge detection on each frame of image to identify the falling hammer area and probe rod area;

[0038] Binarize each frame of the image, assign the value of 0 to the pixels in the hammer area and the probe area, and turn them black, and assign the value of 1 to the pixels in the rest of the background area, and turn them white;

[0039] The dynamic change process of the drop hammer area and the probe rod area from contact to separation is counted as one hammer strike;

[0040] The number of dynamic changes of the hammer drop area and the probe rod area from contact to separation in the entire video stream is counted and saved as the number of hammer strikes in this round.

[0041] Furthermore, in S4, the sounding analysis report includes the time, foundation pit name, sounding point number, the number of hammer blows in each round and the total number of hammer blows for each sounding point number, the scale of each round of hammer blows, the staff and the underground soil bearing capacity analysis results, among which the underground soil bearing capacity uniformity analysis results are obtained based on a pre-trained neural network model.

[0042] Furthermore, S4 also includes: gridding the foundation pit contour map, converting the total number of hammer strikes at each drilling point into pseudo-color, and displaying it in the grid area of ​​the corresponding drilling point in the foundation pit contour map to obtain a pseudo-color map of the bearing capacity of the underground soil of the foundation pit.

[0043] It can be seen from the above technical solutions that, compared with the prior art, the present invention has the following beneficial effects:

[0044] 1. The present invention predetermines the coordinates of each drilling point in the foundation pit and generates a drilling path, thereby guiding the drilling machine to perform drilling operations on each point in the optimal path sequence, without the need for real-time participation of staff, thereby greatly improving work efficiency.

[0045] 2. The present invention automatically identifies whether each round of hammering operation is completed and the number of hammering times in each round based on machine vision, without the need for manual recording, thus reducing recording errors.

[0046] 3. Before hammering the probe rod each time, the present invention automatically identifies the distance between the drop hammer and the probe rod based on machine vision, and automatically adjusts the drop hammer height to ensure that the hammer force is the same each time, further improving the accuracy of the probe test.

[0047] 4. The present invention can realize the real-time sharing of on-site drilling data and automatically generate a drilling analysis report for the foundation pit without manual one-to-one comparison. The results are intuitive and highly automated. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0049] Figure 1 A flow chart of a method for analyzing the uniformity of underground soil bearing capacity based on drilling records provided by the present invention;

[0050] Figure 2 A flow chart of generating a drilling path provided by the present invention;

[0051] Figure 3 The present invention provides a schematic diagram of dividing the foundation pit area into four sub-areas by the regression line H1 and the vertical line H2. DETAILED DESCRIPTION

[0052] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0053] like Figure 1 As shown, an embodiment of the present invention discloses a method for analyzing the uniformity of underground soil bearing capacity based on drilling records, comprising the following steps:

[0054] S1. Generate a foundation pit outline map, take the center of the foundation pit as the origin, construct a cross coordinate system, and determine the coordinates and numbers of each drilling point;

[0055] S2, generating the drilling path of the drilling machine according to the coordinate information of each drilling point;

[0056] S3, guide the drilling probe machine to perform drilling on each drilling point in turn according to the drilling path; when drilling on any drilling point, each time the probe rod is hammered, the height of the hammer is adjusted once, so that before each hammering, the distance between the bottom of the hammer and the top of the probe rod is maintained at a preset distance; and the image information of the probe rod is collected in real time, and when the first scale mark on the probe rod is flush with the ground, it is regarded as the end of the first round of hammering;

[0057] After the probe rod has been hammered for a preset number of rounds, the drilling test for the drilling point is deemed to be completed, and the number of hammering times in each round for the drilling point number is recorded;

[0058] S4. When all the drilling points are completed, the drilling data is shared with the client, and a drilling analysis report for each drilling point in the current foundation pit is generated according to the preset template.

[0059] The above steps are further explained below.

[0060] S1. Draw the foundation pit outline according to a certain ratio based on the actual size. Take the center of the foundation pit as the origin, construct a cross coordinate system, and determine the coordinates and numbers of each drilling point.

[0061] S2, generate the drilling path of the drilling machine according to the coordinate information of each drilling point, such as Figure 2 As shown, specifically including:

[0062] S21, determine the fitness function; the fitness function is the inverse of the total length of the probe path, expressed as:

[0063] F i =1 / L i

[0064] Among them, F i Indicates the fitness value of the drilling path numbered i, L i Indicates the length of the probe path numbered i.

[0065] S22, initialize according to the coordinate information of each drilling point, and obtain the initial drilling path population, specifically including:

[0066] S221, using a linear regression method to fit the coordinates of each probe in the foundation pit area to obtain a linear regression line H1;

[0067] S222, calculate the center point of the regression line H1 in the foundation pit area, and determine the vertical line H2 passing through the regression line H1, and divide the foundation pit area into four sub-areas by the regression line H1 and the vertical line H2, such as Figure 3 As shown;

[0068] S223, recursively execute S221-S222 in each probe sub-region, further divide each sub-region, when the probe point digit in a certain sub-region is less than or equal to 3, be regarded as this sub-region division and end, until the probe point digit contained in all sub-regions is less than or equal to 3, be regarded as the whole foundation pit area division and end, obtain multiple minimum probe areas;

[0069] S224, randomly select a minimum probe area as the initial minimum probe area, randomly select a probe point in the initial minimum probe area as the starting probe point, and add the nearest probe point as the new starting probe point until all probe points are connected;

[0070] Then the initial minimum probe area is connected to a nearest probe point in other nearest minimum probe areas until all the probe points in all the minimum probe areas are connected to generate a probe path;

[0071] S225. Loop through S221-S224 m times to obtain m initial drilling paths, forming an initial drilling path population.

[0072] S23. Select individuals with high fitness ranking from the initial exploration path population and perform crossover, mutation and reversal operations.

[0073] S24. When the individual with the best fitness in the population does not change for several consecutive generations starting from a certain generation, the iterative process is terminated and the optimal solution in the population at this time is output as the result of the drilling path planning. At this time, the output drilling path is the shortest, which can maximize the saving of drilling time.

[0074] S3. Guide the probe machine to probe each probe point in turn according to the probe path; when probing any probe point, adjust the height of the drop hammer every time the probe rod is hit, so that before each hammering, the distance between the bottom of the drop hammer and the top of the probe rod is maintained at a preset distance, so that the hammering force each time is as similar as possible to ensure the experimental accuracy.

[0075] Specifically, the process of adjusting the drop weight height includes:

[0076] The distance between the drop weight and the probe rod is adjusted to a preset distance in advance, and an image of the drop weight and the probe rod is taken in advance by a camera installed at a designated position of the drilling probe machine, and the pixel distance between the drop weight and the probe rod in the image is calibrated as the standard pixel distance;

[0077] When probing any probing point, keep the camera installation position unchanged. Before hammering the probe rod each time, collect images of the drop hammer and the probe rod in real time, calculate the current pixel distance between the two images, and determine whether the current pixel distance is equal to the standard pixel spacing. If so, control the drop hammer to perform this hammering. Otherwise, adjust the drop hammer height until the spacing between the bottom of the drop hammer and the top of the probe rod in the image is the standard pixel spacing, and then control the drop hammer to perform this hammering.

[0078] In addition, when performing the drilling operation, the drilling data needs to be automatically recorded. At this time, the key is to identify whether a round of hammering is completed and count the number of hammering in each round.

[0079] Specifically, the method for determining whether each round of hammering is completed is:

[0080] The scales on the probe rod are color-marked in advance so that the color of the mark is clearly different from the ground color and the probe rod color; the probe rod is hammered into the ground so that the bottom of the scale mark is flush with the ground, and the image of the bottom of the probe rod is collected by a camera installed at the bottom of the drilling probe, and the pixel width of the scale line in the image is calculated as the standard pixel width;

[0081] Keep the camera installation position unchanged, hammer each pair of probes once, and collect an image of the bottom of the probes once;

[0082] If after a certain hammering, the scale line in the image at the bottom of the probe rod touches the ground, and the pixel width of the scale line is less than or equal to the standard pixel width, then this round of hammering is considered to be over.

[0083] or:

[0084] If after a certain hammering, the scale mark on the lowest side of the probe rod bottom image disappears, but the scale mark on the lowest side of the probe rod bottom image after the previous hammering exists, and there is a certain distance between the lowest side scale line and the ground, then this round of hammering is considered to be over.

[0085] The present invention uses machine vision to count the number of hammer strikes in each round, and the specific steps include:

[0086] The video stream of each round of hammering is collected and frame-by-frame processed to obtain a set of sequentially arranged single-frame images;

[0087] Perform edge detection on each frame of image to identify the falling hammer area and probe rod area;

[0088] Binarize each frame of the image, assign the value of 0 to the pixels in the hammer area and the probe area, and turn them black, and assign the value of 1 to the pixels in the rest of the background area, and turn them white;

[0089] The dynamic change process of the drop hammer area and the probe rod area from contact to separation is counted as one hammer strike;

[0090] The number of dynamic changes of the hammer drop area and the probe rod area from contact to separation in the entire video stream is counted and saved as the number of hammer strikes in this round.

[0091] In general, the present invention can identify the height of the falling hammer based on machine vision and automatically count the number of hammer strikes in each round, which can greatly reduce the work intensity of the staff and ensure the accuracy of the drilling operation.

[0092] In S4, the drilling data is shared to the client in real time, and a drilling analysis report for each drilling point of the current foundation pit is generated on the client according to a preset template. The drilling analysis report includes the time, foundation pit name, drilling point number, the number of hammer blows per round and the total number of hammer blows under each drilling point number, the scale of each round of hammer blows, the staff and the underground soil bearing capacity analysis results, among which the underground soil bearing capacity uniformity analysis results are obtained based on a pre-trained neural network model.

[0093] Specifically, previous drilling test data and corresponding analysis results can be used as training sets to train the neural network model in order to learn the corresponding relationship between the number of hammer blows and the soil bearing capacity under the relevant scale, and at the same time learn the relationship between the distribution of the number of hammer blows at the drilling point and the uniformity of the soil bearing capacity. The present invention no longer requires manual one-to-one comparison of the drilling records, and can quickly obtain the soil bearing capacity distribution results of the foundation pit, thereby greatly improving work efficiency.

[0094] More advantageously, S4 further includes: gridding the foundation pit outline on the client so that each drilling point is surrounded by a grid, converting the total number of hammer strikes at each drilling point into pseudo-color and displaying it in the grid area of ​​the corresponding drilling point in the foundation pit outline to obtain a pseudo-color map of the bearing capacity of the underground soil in the foundation pit. In this way, the bearing capacity of the soil at different locations of the foundation pit can be intuitively expressed.

[0095] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.

[0096] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A method for analyzing the uniformity of underground soil bearing capacity based on drilling records, characterized in that: The following steps are involved: S1. Generate a foundation pit outline map, take the center of the foundation pit as the origin, construct a cross coordinate system, and determine the coordinates and numbers of each drilling point; S2, generating the drilling path of the drilling machine according to the coordinate information of each drilling point; S3, guide the drilling probe machine to perform drilling on each drilling point in turn according to the drilling path; when drilling on any drilling point, each time the probe rod is hammered, the height of the hammer is adjusted once, so that before each hammering, the distance between the bottom of the hammer and the top of the probe rod is maintained at a preset distance; and the image information of the probe rod is collected in real time, and when the first scale mark on the probe rod is flush with the ground, it is regarded as the end of the first round of hammering; After the probe rod has been hammered for a preset number of rounds, the drilling test for the drilling point is deemed to be completed, and the number of hammering times in each round for the drilling point number is recorded; S4. When all the drilling points are completed, the drilling data is shared with the client, and a drilling analysis report for each drilling point in the current foundation pit is generated according to the preset template.

2. The method for analyzing the uniformity of underground soil bearing capacity based on the drilling record according to claim 1, wherein S2 include: S21, determining the fitness function; S22, initialize according to the coordinate information of each drilling point to obtain an initial drilling path population; S23, selecting individuals with high fitness ranking from the initial drilling path population and performing crossover, mutation, and reversal operations; S24. When the individual with the best fitness in the population does not change for several consecutive generations starting from a certain generation, the iterative process is terminated and the optimal solution in the population at this time is output as the result of the drilling path planning.

3. The method for analyzing the uniformity of underground soil bearing capacity based on the drilling record according to claim 2, characterized in that, In S21, the fitness function is the inverse of the total length of the probe path, expressed as: F i =1 / L i Among them, F i Indicates the fitness value of the drilling path numbered i, L i Indicates the length of the probe path numbered i.

4. The method for analyzing the uniformity of underground soil bearing capacity based on the drilling record according to claim 2, characterized in that, S22 includes: S221, using a linear regression method to fit the coordinates of each probe in the foundation pit area to obtain a linear regression line H1; S222, calculating the center point of the regression line H1 in the foundation pit area, and determining the perpendicular line H2 passing through the regression line H1, and dividing the foundation pit area into four sub-areas by the regression line H1 and the perpendicular line H2; S223, recursively execute S221-S222 in each probe sub-region, further divide each sub-region, when the probe point digit in a certain sub-region is less than or equal to 3, be regarded as this sub-region division and end, until the probe point digit contained in all sub-regions is less than or equal to 3, be regarded as the whole foundation pit area division and end, obtain multiple minimum probe areas; S224, randomly select a minimum probe area as the initial minimum probe area, randomly select a probe point in the initial minimum probe area as the starting probe point, and add the nearest probe point as the new starting probe point until all probe points are connected; Then the initial minimum probe area is connected to a nearest probe point in other nearest minimum probe areas until all the probe points in all the minimum probe areas are connected to generate a probe path; S225. Loop through S221-S224 m times to obtain m initial drilling paths, forming an initial drilling path population.

5. The method for analyzing the uniformity of underground soil bearing capacity based on the drilling record according to claim 1, characterized in that, In S3, the process of adjusting the drop weight height includes: The distance between the drop weight and the probe rod is adjusted to a preset distance in advance, and an image of the drop weight and the probe rod is taken in advance by a camera installed at a designated position of the drilling probe machine, and the pixel distance between the drop weight and the probe rod in the image is calibrated as the standard pixel distance; When probing any probing point, keep the camera installation position unchanged. Before hammering the probe rod each time, collect images of the drop hammer and the probe rod in real time, calculate the current pixel distance between the two images, and determine whether the current pixel distance is equal to the standard pixel spacing. If so, control the drop hammer to perform this hammering. Otherwise, adjust the drop hammer height until the spacing between the bottom of the drop hammer and the top of the probe rod in the image is the standard pixel spacing, and then control the drop hammer to perform this hammering.

6. The method for analyzing the uniformity of underground soil bearing capacity based on the drilling record according to claim 1, characterized in that: In S3, the method for determining whether each round of hammering is completed is: The scales on the probe rod are color-marked in advance so that the color of the mark is clearly different from the ground color and the probe rod color; the probe rod is hammered into the ground so that the bottom of the scale mark is flush with the ground, and the image of the bottom of the probe rod is collected by a camera installed at the bottom of the drilling probe, and the pixel width of the scale line in the image is calculated as the standard pixel width; Keep the camera installation position unchanged, hammer each pair of probes once, and collect an image of the bottom of the probes once; If after a certain hammering, the scale line in the image at the bottom of the probe rod touches the ground, and the pixel width of the scale line is less than or equal to the standard pixel width, then this round of hammering is considered to be over.

7. The method for analyzing the uniformity of underground soil bearing capacity based on the drilling record according to claim 6, characterized in that: The method for judging whether each round of hammering is finished also includes: If after a certain hammering, the scale mark on the lowest side of the probe rod bottom image disappears, but the scale mark on the lowest side of the probe rod bottom image after the previous hammering exists, and there is a certain distance between the lowest side scale line and the ground, then this round of hammering is considered to be over.

8. The method for analyzing the uniformity of underground soil bearing capacity based on the drilling record according to claim 1, characterized in that: In S3, machine vision is used to count the number of hammer blows in each round, including: The video stream of each round of hammering is collected and frame-by-frame processed to obtain a set of sequentially arranged single-frame images; Perform edge detection on each frame of image to identify the falling hammer area and probe rod area; Binarize each frame of the image, assign the value of 0 to the pixels in the hammer area and the probe area, and turn them black, and assign the value of 1 to the pixels in the rest of the background area, and turn them white; The dynamic change process of the drop hammer area and the probe rod area from contact to separation is counted as one hammer strike; The number of dynamic changes of the hammer drop area and the probe rod area from contact to separation in the entire video stream is counted and saved as the number of hammer strikes in this round.

9. The method for analyzing the uniformity of underground soil bearing capacity based on the drilling record according to claim 1, characterized in that, In S4, the sounding analysis report includes the time, foundation pit name, sounding point number, the number of hammer blows in each round and the total number of hammer blows for each sounding point number, the scale of each round of hammer blows, the staff and the underground soil bearing capacity analysis results, among which the underground soil bearing capacity uniformity analysis results are obtained based on a pre-trained neural network model.

10. The method for analyzing the uniformity of underground soil bearing capacity based on the drilling record according to claim 1, characterized in that: S4 also includes: gridding the foundation pit contour map, converting the total number of hammer strikes at each drilling point into pseudo-color, and displaying it in the grid area of ​​the corresponding drilling point in the foundation pit contour map to obtain a pseudo-color map of the bearing capacity of the underground soil of the foundation pit.

Citation Information

Patent Citations

  • Method for performing distribution, numbering and operation control on drill rod detection points by utilizing computer program

    CN102359127A

  • Display system and marking method for geological digital map

    CN109342226A

  • Underground pipeline monitoring method based on CT method

    CN110873232A

  • Power pipe jacking detection method and probe rod

    CN115453611A

  • Regional soft soil testing method

    CN117629784A