Curing monitoring mechanism of photovoltaic junction box potting machine

By designing a monitoring, adjustment and positioning mechanism in the photovoltaic junction box filling machine, the overall limit and calibration of the junction box after filling is realized, and the excess colloid is recovered through the air pump and contact plate, the junction box transmission process is solved. The problems of flatness and colloid flow improve the accuracy of curing monitoring and resource utilization.

CN118937394APending Publication Date: 2024-11-12ANHUI TIANDA NEW ENERGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411120080.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the prior art, unevenness is easily caused during the transmission process after the junction box is filled with glue and cured, which affects the monitoring efficiency. The colloid after the glue is filled with glue may flow or remain, causing waste of resources and difficulty in cleaning.

Method used

A photovoltaic junction box glue filling machine curing monitoring mechanism is designed, including monitoring mechanism, adjustment mechanism and positioning mechanism. Through the drive motor, rodent plate, shrink plate and air pump, the overall limit of the junction box after glue filling is achieved. , calibration and curing monitoring, and recover excess colloids through contact plates and guide grooves to ensure parallel placement of the junction box and colloid recovery.

Benefits of technology

It improves the accuracy of glue filling and curing monitoring, avoids colloid waste and difficulty in cleaning, and ensures the integrity of the colloid on the surface of the junction box and the cleanliness of the conveyor belt.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118937394A_ABST
    Figure CN118937394A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of curing monitoring of junction box potting machines, in particular to a curing monitoring mechanism of a photovoltaic junction box potting machine. Comprising a monitoring mechanism, an adjusting mechanism and positioning mechanisms, the monitoring mechanism is arranged on the upper surface of the adjusting mechanism, the positioning mechanisms are movably installed on the front side and the rear side of the upper surface of the adjusting mechanism, and the positioning mechanisms are telescopically adjusted on the surface of the monitoring mechanism through the adjusting mechanism; shrinkage plates are mounted on the two sides of the outer surface of the monitoring plate, meshing plates are mounted on the front side and the rear side of the surface of the adjusting mechanism, the shrinkage plates are subjected to shrinkage adjustment on the two sides of the upper surface of the adjusting mechanism through the meshing plates, and the meshing plates are subjected to meshing movement on the front side and the rear side of the lower surface of the monitoring plate through the adjusting mechanism; one side of the surface of the contact plate telescopically contacts with the surface of the monitoring plate. And the surface of the junction box after glue pouring is parallel and corresponds to the surface position of the monitoring plate, so that the accuracy of curing monitoring of the junction box after glue pouring is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of curing monitoring of a junction box glue potting machine, and in particular to a curing monitoring mechanism of a photovoltaic junction box glue potting machine. Background Art

[0002] In the photovoltaic industry, the curing of junction box glue filling is a key step to ensure the stable performance and reliability of photovoltaic modules. The junction box after glue filling and curing not only serves as an electrical connection, but also effectively protects the internal circuit from erosion by the external environment. Therefore, it is crucial to effectively monitor and evaluate the glue filling and curing process.

[0003] At present, after the junction box is glued and cured, it is transported on a conveyor belt, which may make the placement of the junction box uneven, affecting the efficiency of monitoring the glue curing of the junction box. After the junction box is glued, a small amount of glue will flow from the glue filling position of the junction box and remain on the surface of the junction box or fall onto the surface of the conveyor belt, causing waste of glue and difficulty in cleaning.

[0004] Therefore, there is an urgent need for a photovoltaic junction box glue filling machine curing monitoring mechanism to solve the existing technical problems. Summary of the invention

[0005] The object of the present invention is to provide a curing monitoring mechanism for a photovoltaic junction box glue filling machine to solve the problems raised in the above-mentioned background technology.

[0006] To achieve the above-mentioned purpose, the present invention aims to provide a curing monitoring mechanism for a photovoltaic junction box glue filling machine, including a monitoring mechanism, an adjusting mechanism and a positioning mechanism, the monitoring mechanism is arranged on the upper surface of the adjusting mechanism, the positioning mechanism is movably installed on the front and rear sides of the upper surface of the adjusting mechanism, and the positioning mechanism is telescopically adjusted on the surface of the monitoring mechanism through the adjusting mechanism, a monitoring plate is installed at the center position of the lower surface of the monitoring mechanism, a contraction plate is installed on both sides of the outer surface of the monitoring plate, a toothed plate is installed on the front and rear sides of the surface of the adjusting mechanism, the contraction plate is contracted and adjusted on both sides of the upper surface of the adjusting mechanism through the toothed plate, and the toothed plate meshes and moves on the front and rear sides of the lower surface of the monitoring plate through the adjusting mechanism, and contact plates are installed around the surface of the positioning mechanism, and one side of the contact plate surface is in telescopic contact with the surface of the monitoring plate.

[0007] As a further improvement of the present technical solution, the monitoring mechanism includes a retraction plate, a fixed block is installed on the top of the retraction plate, a splint is installed on one side of the surface of the fixed block, a top plate is clamped on the surface of the splint, an air pump is installed at the center position of the top of the top plate, a bottom plate is installed on the bottom surface of the top plate, a monitoring plate is installed on the lower surface of the bottom plate, slots are opened around the bottom surface of the monitoring plate, a connecting piece is connected to one side of the bottom surface of the retraction plate, a guide rail is arranged on one side of the surface of the connecting piece, a control panel is arranged on the right side of the surface of the retraction plate, the bottom of the guide rail corresponds to the surface position of the adjustment mechanism, and the retraction plate is retracted and adjusted on the front and rear sides of the surface of the monitoring mechanism through the connecting piece and the guide rail.

[0008] As a further improvement of the present technical solution, the adjustment mechanism includes a driving motor, a rotating rod is fixedly connected to the top of the driving motor, racks are arranged around the outer surface of the rotating rod, geared plates are meshed on both sides of the outer surface of the rack, a ring is fixedly sleeved on the top surface of the rotating rod, a sleeve rod is sleeved on the inner wall of the ring, the top surface of the gear plate corresponds to the position of the guide rail, and the connecting piece passes through the guide rail and is connected to the top surface of the gear plate.

[0009] As a further improvement of the present technical solution, the positioning mechanism includes a bearing, a seesaw is connected to one side of the bearing surface, telescopic parts are connected on both sides of the seesaw surface, a buffer spring is installed on the surface of the telescopic part, a positioning plate is connected to one side of the surface of the telescopic part, and a total of four positioning plates are provided, and the four positioning plates are symmetrically distributed around the surface of the retractable plate.

[0010] As a further improvement of the present technical solution, a support rod is installed on the top of the positioning plate, a contact plate is connected to one side of the surface of the support rod, a recovery groove is installed on the bottom surface of the contact plate, a guide groove is opened on one side of the top surface of the contact plate, the guide groove corresponds to the surface position of the monitoring plate, and the bottom surface of the guide groove is connected to the corresponding surface position of the recovery groove.

[0011] As a further improvement of the technical solution, through grooves are opened at the center positions of the corners on both sides of the surface of the retractable plate, the through grooves correspond to the positions of the telescopic parts, and the telescopic parts are telescopically adjusted at the positions of the through grooves through bearings and rocker plates.

[0012] As a further improvement of the technical solution, the four positioning plates are telescopically adjusted around the bottom surface of the monitoring plate through the retraction plate, the seesaw shape is V-shaped, and the four positioning plates are adjusted on the bearing surface through the seesaw.

[0013] As a further improvement of the technical solution, threads are provided around the inner wall of the collar, and the sleeve rod is rotated and lifted inside the collar through the threads.

[0014] Compared with the prior art, the present invention has the following beneficial effects: 1. The photovoltaic junction box glue filling machine solidifies the monitoring mechanism. The junction box after glue filling is transmitted to the monitoring mechanism, and the driving motor is started to drive the rotating rod to rotate. Under the meshing action of the rack, the toothed plate slides back and forth on the surface of the rotating rod. Since the positions of the toothed plate and the guide rail correspond, the connecting piece penetrates the guide rail and is connected to the toothed plate. Therefore, the shrinkage plate can be driven to shrink and adjust on both sides of the upper surface of the monitoring mechanism. First, the overall limit adjustment of the junction box after glue filling is performed to ensure that the junction box after glue filling is placed parallel to the center position inside the monitoring mechanism.

[0015] 2. The curing monitoring mechanism of the photovoltaic junction box glue filling machine is that after the junction box after glue filling is placed parallel to the center position inside the monitoring mechanism, the sleeve rod is extended from the inside of the sleeve ring under the action of the thread, and the junction box after glue filling can be lifted up. At the same time, the shrinkage plate is still contracted toward the inside of the monitoring mechanism, so that the surface of the positioning plate is in contact with the corners of the outer surface of the junction box after glue filling. When the corners of the outer surface of the junction box after glue filling are squeezed, the set seesaw and the bearing are adjusted under the action of the squeezing force, and the positioning plate is effectively telescopically adjusted to keep the positioning plates on the same side parallel. The junction box after glue filling can be further calibrated, so that the surface of the junction box after glue filling is parallel to the surface position of the monitoring plate, thereby improving the accuracy of the curing monitoring of the junction box after glue filling.

[0016] 3. The curing monitoring mechanism of the photovoltaic junction box glue filling machine calibrates the junction box after glue filling so that it is parallel to the surface position of the monitoring board, and the card slot is connected to the four sides of the upper surface of the junction box. The compressed air is transmitted to the card slot position through the monitoring board through the operation of the air pump to monitor the curing of the junction box glue filling position.

[0017] 4. The curing monitoring mechanism of the photovoltaic junction box glue filling machine can scrape off the excess colloid on the junction box surface after being connected to the junction box surface through the card slot. Because one side of the contact plate surface is in parallel contact with the junction box surface, and the excess colloid can be conducted through the opened guide groove and finally concentrated in the recovery groove position, the excess colloid can be recycled, and the colloid will not drip from the junction box surface to the conveyor belt surface, avoiding waste of resources and difficulty in cleaning. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the connection structure of the monitoring mechanism and the regulating mechanism of the present invention; Figure 2 It is a schematic diagram of the connection structure between the toothed plate and the positioning mechanism of the present invention; Figure 3 It is a schematic diagram of the connection structure of the shrinkage plate and the seesaw plate of the present invention; Figure 4 It is a schematic diagram of the connection structure between the shrinkage plate and the monitoring plate of the present invention; Figure 5 for Figure 4A schematic diagram of the enlarged structure at A in the middle; Figure 6 It is a schematic diagram of the connection structure of the contraction plate and the toothed plate of the present invention; Figure 7 for Figure 6 Schematic diagram of the enlarged structure at point B in the middle.

[0019] The meaning of each number in the figure is: Monitoring mechanism; 101, retractable plate; 102, fixing block; 103, clamping plate; 104, top plate; 105, air pump; 106, bottom plate; 107, connecting piece; 108, guide rail; 109, monitoring board; 110, card slot; 111, control panel; Adjusting mechanism; 201, driving motor; 202, rotating rod; 203, rack; 204, toothed plate; 205, sleeve ring; 206, sleeve rod.

[0020] 300, positioning mechanism; 301, bearing; 302, seesaw; 303, telescopic member; 304, buffer spring; 305, positioning plate; 306, support rod; 307, contact plate; 308, recovery slot. DETAILED DESCRIPTION

[0021] The following will be combined with the accompanying drawings in the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Example

[0022] See also Figure 1-Figure 7 As shown, the purpose of this embodiment is to provide a curing monitoring mechanism for a photovoltaic junction box glue filling machine, including a monitoring mechanism 100, an adjusting mechanism 200 and a positioning mechanism 300, wherein the monitoring mechanism 100 is arranged on the upper surface of the adjusting mechanism 200, the positioning mechanism 300 is movably installed on the front and rear sides of the upper surface of the adjusting mechanism 200, and the positioning mechanism 300 is telescopically adjusted on the surface of the monitoring mechanism 100 through the adjusting mechanism 200, a monitoring plate 109 is installed at the center of the lower surface of the monitoring mechanism 100, and a contraction plate 101 is installed on both sides of the outer surface of the monitoring plate 109, and a toothed plate 204 is installed on the front and rear sides of the surface of the adjusting mechanism 200, and the contraction plate 101 is contracted and adjusted on both sides of the upper surface of the adjusting mechanism 200 through the toothed plate 204, and the toothed plate 204 is meshed and moved on the front and rear sides of the lower surface of the monitoring plate 109 through the adjusting mechanism 200, and a contact plate 307 is installed around the surface of the positioning mechanism 300, and one side of the surface of the contact plate 307 is in telescopic contact with the surface of the monitoring plate 109; By operating the adjusting mechanism 200, the toothed plate 204 slides, thereby driving the shrinkage plate 101 to shrink and adjust on the front and rear sides of the upper surface of the monitoring mechanism 100, and the initial limit adjustment can be performed on the junction box after glue filling, so that the junction box after glue filling can be transmitted in parallel to the center position of the upper surface of the monitoring mechanism 100, and the positioning mechanism 300 can squeeze the corners around the junction box after glue filling while the adjusting mechanism 200 continues to operate, and further calibrate the junction box after glue filling, so that the surrounding areas of the upper surface of the junction box after glue filling correspond to the position of the lower surface of the monitoring plate 109, which is used for curing monitoring of the glue filling position of the junction box, and at the same time, the excess colloid on the surface of the junction box is also recovered, so as to avoid the waste of excess colloid and the difficulty of cleaning.

[0023] Considering the need to realize the regulating function of the regulating mechanism 200, in this embodiment, the regulating mechanism 200 includes a driving motor 201, a rotating rod 202 is fixedly connected to the top of the driving motor 201, a rack 203 is arranged around the outer surface of the rotating rod 202, and a toothed plate 204 is meshed on both sides of the outer surface of the rack 203, a collar 205 is fixedly sleeved on the top surface of the rotating rod 202, a sleeve rod 206 is sleeved on the inner wall of the collar 205, the top surface of the toothed plate 204 corresponds to the position of the guide rail 108, and the connecting member 107 penetrates the guide rail 108 and is connected to the top surface of the toothed plate 204; Furthermore, the driving motor 201 is started, and the rotating rod 202 rotates to make the rack 203 operate synchronously. Under the meshing action of the rack 203, the toothed plate 204 can slide on both sides of the surface of the rack 203. The surface of the guide rail 108 corresponds to the position of the toothed plate 204. One end of the connecting piece 107 passes through the guide rail 108 and is connected to the toothed plate 204. Therefore, the shrinkage plate 101 and the toothed plate 204 can be made to slide synchronously through the connecting piece 107, and the rotation of the rotating rod 202 can drive the ring 205 to rotate synchronously. The positive rotation of the ring 205 under the action of the thread can effectively make the sleeve rod 206 extend from the surface of the sleeve rod 205, lift up the junction box after the glue is poured, and clamp with the surface of the positioning mechanism 300 around, play a clamping role on the junction box after the glue is poured, and ensure that the curing monitoring of the junction box after the glue is poured is carried out normally; The improvement lies in that the toothed plate 204 is driven by the rack 203 to slide and adjust on the surface of the rotating rod 202, and the shrinkage plate 101 is synchronously slid and adjusted under the action of the guide rail 108 and the connecting piece 107, so that the two sides of the surface of the junction box after glue filling can be initially limited to ensure that the junction box after glue filling is horizontally transmitted to the central position inside the monitoring mechanism 100. At the same time, the rotating rod 202 drives the ring 205 to rotate synchronously, and under the action of the threaded connection, drives the sleeve rod 206 to telescope and connect from the surface of the ring 205, which can effectively lift the junction box after glue filling and connect the corners of the junction box after glue filling with the positioning mechanism 300.

[0024] Considering the need to realize the sliding effect of the monitoring mechanism 100, in this embodiment, the monitoring mechanism 100 includes a retractable plate 101, a fixed block 102 is installed on the top of the retractable plate 101, a clamping plate 103 is installed on one side of the surface of the fixed block 102, a top plate 104 is clamped on the surface of the clamping plate 103, an air pump 105 is installed at the center of the top of the top plate 104, a bottom plate 106 is installed on the bottom surface of the top plate 104, a monitoring plate 109 is installed on the lower surface of the bottom plate 106, and a card slot 110 is opened around the bottom surface of the monitoring plate 109. A connecting piece 107 is connected to one side of the bottom surface of the retractable plate 101, a guide rail 108 is arranged on one side of the surface of the connecting piece 107, and a control panel 111 is arranged on the right side of the surface of the retractable plate 101. The bottom of the guide rail 108 corresponds to the surface position of the adjustment mechanism 200, and the retractable plate 101 is retracted and adjusted on the front and rear sides of the surface of the monitoring mechanism 100 through the connecting piece 107 and the guide rail 108; Further, the toothed plate 204 drives the retracting plate 101 to position the junction box after the glue filling, and is clamped in the center position inside the monitoring mechanism 100. At the same time, the junction box after the glue filling is lifted up by the sleeve rod 206, so that the corners of the junction box after the glue filling correspond to the lower surface of the monitoring plate 109, and is clamped in the card slot 110. The air pump 105 is started to transmit compressed air to the card slot 110 to monitor the curing of the glue filling position of the junction box. At the same time, a high-precision sensor will be set at the monitoring plate 109 position to monitor the key parameters in the glue filling curing process in real time to determine whether the curing degree meets the standard (the high-precision sensor includes a temperature sensor, a humidity sensor and a pressure sensor, which are existing technologies and are therefore not described in detail); The improvement lies in that the junction box after glue filling is lifted up by the sleeve rod 206 and connected with the monitoring board 109 accordingly, and the compressed air generated by the air pump 105 is transmitted to the position of the card slot 110 to monitor the curing of the glue filling position of the junction box, which is convenient and simple to operate.

[0025] Considering the need to realize the positioning function of the positioning mechanism 300, in this embodiment, the positioning mechanism 300 includes a bearing 301, a seesaw 302 is connected to one side of the surface of the bearing 301, telescopic members 303 are connected to both sides of the surface of the seesaw 302, a buffer spring 304 is installed on the surface of the telescopic member 303, and a positioning plate 305 is connected to one side of the surface of the telescopic member 303. There are four positioning plates 305 in total, and the four positioning plates 305 are symmetrically distributed around the surface of the contraction plate 101; Furthermore, after the sleeve rod 206 is set to lift up the junction box after glue filling, the shrinking plate 101 continues to shrink toward the inside of the monitoring mechanism 100, so that the surface of the positioning plate 305 contacts the corners of the junction box after glue filling, and generates an extrusion force to calibrate the junction box that still has an inclined angle. At the same time, the buffer spring 304 can play the role of buffering the extrusion force, and the set seesaw 302 adjusts the positioning plate 305 on the other side under the linkage action of the bearing 301, ensuring that the positioning plates 305 on both sides remain parallel after squeezing the junction box after glue filling, and accurately dock with the surface of the monitoring plate 109; The improvement lies in that: by shrinking the shrinking plate 101 towards the inside of the monitoring mechanism 100, one side of the surface of the positioning plate 305 is in contact with the surface of the junction box after glue filling. Since the positioning plate 305 is arranged at the corners around the junction box, it can calibrate the corners around the junction box to ensure that the glue filling position of the junction box is connected to the surface of the monitoring plate 109, and the result of the monitoring of the glue filling and curing of the junction box is more accurate. At the same time, the buffer spring 304 provided can buffer the extrusion force to avoid the problem of damage to the corners around the junction box during the calibration process of the junction box. The set rocker 302 and bearing 301 can synchronize the calibration of the corners around the junction box, thereby improving the work efficiency of the calibration of the junction box.

[0026] Considering the need to realize the recovery function of the positioning mechanism 300, in this embodiment, a support rod 306 is installed on the top of the positioning plate 305, a contact plate 307 is connected to one side of the surface of the support rod 306, a recovery groove 308 is installed on the bottom surface of the contact plate 307, a guide groove is opened on one side of the top surface of the contact plate 307, the guide groove corresponds to the surface position of the monitoring plate 109, and the bottom surface of the guide groove is connected to the surface position of the recovery groove 308; Furthermore, after the junction box after the filling of glue is calibrated, the surface of the contact plate 307 is in contact with the surrounding surfaces of the junction box, and after the upper surface of the junction box is engaged with the card slot 110, excess colloid flows downward from the surrounding of the junction box and can be directly transferred to the surface of the contact plate 307. The guide groove opened on the surface of the contact plate 307 can effectively and quickly transfer the excess colloid to the inside of the recovery groove 308, which has the effect of centralized collection of the excess colloid, avoiding the waste of colloid and the difficulty of cleaning; The improvement lies in that: by setting the contact plate 307 around the surface of the junction box, after the card slot 110 is connected with the junction box, the curing monitoring process of the glue filling position of the junction box is carried out, and the excess colloid can be directly transferred to the recovery groove 308 through the guide groove opened by the contact plate 307, which effectively prevents the excess colloid from flowing around the surface of the junction box and finally dripping on the surface of the conveyor belt, thereby reducing the waste of colloid and the work required for staff to clean up the colloid.

[0027] In summary, the working principle of this solution is as follows: the staff operates the control panel 111, and when the junction box after glue filling is transmitted to the monitoring mechanism 100, the driving motor 201 is started to drive the rotating rod 202 to rotate, and under the meshing action of the rack 203, the toothed plate 204 slides back and forth on the surface of the rotating rod 202. Since the positions of the toothed plate 204 and the guide rail 108 correspond, the connecting member 107 penetrates the guide rail 108 and is connected to the toothed plate 204, so that the retractable plate 101 can be retracted on both sides of the upper surface of the monitoring mechanism 100. The overall limit adjustment of the junction box after glue filling is first performed to ensure that the junction box after glue filling is placed parallel to the center position inside the monitoring mechanism 100. After the junction box after glue filling is placed parallel to the center position inside the monitoring mechanism 100, the sleeve rod 206 is extended from the inside of the sleeve ring 205 under the action of the thread, and the junction box after glue filling can be lifted up. At the same time, the shrink plate 101 is still retracted to the inside of the monitoring mechanism 100, so that the surface of the positioning plate 305 is in contact with the corners of the outer surface of the junction box after glue filling, and squeezed around the corners of the outer surface of the junction box after glue filling. When the pressure is pressed, the set seesaw 302 and the bearing 301 are adjusted under the action of the squeezing force, and the positioning plate 305 is effectively telescopically adjusted, so that the positioning plate 305 on the same side remains in a parallel state, and the junction box after the glue filling can be further calibrated, so that the surface of the junction box after the glue filling is parallel to the surface position of the monitoring board 109, thereby improving the accuracy of the curing monitoring of the junction box after the glue filling. After the junction box after the glue filling is calibrated, it is parallel to the surface position of the monitoring board 109, and the card slot 110 is clamped around the upper surface of the junction box, and the air pump 10 5 operation, the compressed air is transmitted to the position of the card slot 110 through the monitoring board 109, and the curing monitoring of the glue filling position of the junction box is performed. After the card slot 110 is clamped on the surface of the junction box, the excess colloid on the surface of the junction box can be scraped off, because one side of the surface of the contact plate 307 is parallel to the surface of the junction box, and the excess colloid can be conducted through the opened guide groove, and finally concentrated at the recovery groove 308, the excess colloid can be recovered, and the colloid will not drip from the surface of the junction box to the surface of the conveyor belt, avoiding the waste of resources and the difficulty of cleaning.

[0028] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited by the above embodiments. The above embodiments and descriptions are only preferred examples of the present invention and are not intended to limit the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A curing monitoring mechanism for a photovoltaic junction box glue filling machine, characterized in that: The invention comprises a monitoring mechanism (100), an adjusting mechanism (200) and a positioning mechanism (300), wherein the monitoring mechanism (100) is arranged on the upper surface of the adjusting mechanism (200), the positioning mechanism (300) is movably mounted on the front and rear sides of the upper surface of the adjusting mechanism (200), and the positioning mechanism (300) is telescopically adjusted on the surface of the monitoring mechanism (100) through the adjusting mechanism (200), a monitoring plate (109) is mounted at the center of the lower surface of the monitoring mechanism (100), and retractable and retractable plates are mounted on both sides of the outer surface of the monitoring plate (109). The retractable plate (101) is provided with toothed plates (204) on both sides of the surface of the adjustment mechanism (200); the retractable plate (101) is retracted and adjusted on both sides of the upper surface of the adjustment mechanism (200) through the toothed plates (204); and the toothed plates (204) are meshed and moved on both sides of the lower surface of the monitoring plate (109) through the adjustment mechanism (200); contact plates (307) are provided around the surface of the positioning mechanism (300); and one side of the surface of the contact plate (307) is in telescopic contact with the surface of the monitoring plate (109).

2. The curing monitoring mechanism of the photovoltaic junction box glue filling machine according to claim 1 is characterized in that: The monitoring mechanism (100) comprises a contraction plate (101), a fixing block (102) being mounted on the top of the contraction plate (101), a clamping plate (103) being mounted on one side of the surface of the fixing block (102), a top plate (104) being clamped on the surface of the clamping plate (103), an air pump (105) being mounted at the top center of the top plate (104), a bottom plate (106) being mounted on the bottom surface of the top plate (104), a monitoring plate (109) being mounted on the lower surface of the bottom plate (106), and a bottom surface of the monitoring plate (109) being clamped on the bottom of the clamping plate (103). The surface of the part is provided with card slots (110) around the periphery, one side of the bottom surface of the retractable plate (101) is connected to a connecting piece (107), one side of the surface of the connecting piece (107) is provided with a guide rail (108), a control panel (111) is provided on the right side of the surface of the retractable plate (101), the bottom of the guide rail (108) corresponds to the position of the surface of the adjustment mechanism (200), and the retractable plate (101) is retracted and adjusted on the front and rear sides of the surface of the monitoring mechanism (100) through the connecting piece (107) and the guide rail (108).

3. The curing monitoring mechanism of the photovoltaic junction box glue filling machine according to claim 2 is characterized in that: The adjustment mechanism (200) comprises a driving motor (201), a rotating rod (202) being fixedly connected to the top of the driving motor (201), racks (203) being arranged around the outer surface of the rotating rod (202), toothed plates (204) being meshed on both sides of the outer surface of the rack (203), a sleeve ring (205) being fixedly sleeved on the top surface of the rotating rod (202), a sleeve rod (206) being sleeved on the inner wall of the sleeve ring (205), the top surface of the toothed plate (204) corresponding to the position of the guide rail (108), and the connecting member (107) penetrating the guide rail (108) and connected to the top surface of the toothed plate (204).

4. The curing monitoring mechanism of the photovoltaic junction box glue filling machine according to claim 2 is characterized in that: The positioning mechanism (300) comprises a bearing (301), a seesaw (302) connected to one side of the surface of the bearing (301), telescopic parts (303) connected to both sides of the surface of the seesaw (302), a buffer spring (304) installed on the surface of the telescopic part (303), and a positioning plate (305) connected to one side of the surface of the telescopic part (303), wherein four positioning plates (305) are provided in total, and the four positioning plates (305) are symmetrically distributed around the surface of the contraction plate (101).

5. The curing monitoring mechanism of the photovoltaic junction box glue filling machine according to claim 4 is characterized in that: A support rod (306) is installed on the top of the positioning plate (305), a contact plate (307) is connected to one side of the surface of the support rod (306), a recovery groove (308) is installed on the bottom surface of the contact plate (307), a guide groove is opened on one side of the top surface of the contact plate (307), the guide groove corresponds to the surface position of the monitoring plate (109), and the bottom surface of the guide groove is connected to the surface position of the recovery groove (308) in a corresponding manner.

6. The curing monitoring mechanism of the photovoltaic junction box glue filling machine according to claim 5 is characterized in that: Through slots are provided at the center positions of the corners on both sides of the surface of the retractable plate (101), the through slots corresponding to the positions of the telescopic members (303), and the telescopic members (303) are telescopically adjusted at the positions of the through slots through the bearings (301) and the rocker plate (302).

7. The curing monitoring mechanism of the photovoltaic junction box glue filling machine according to claim 4 is characterized in that: The four positioning plates (305) are telescopically adjusted around the bottom surface of the monitoring plate (109) via the contraction plate (101); the seesaw (302) is V-shaped, and the four positioning plates (305) are adjusted on the surface of the bearing (301) via the seesaw (302).

8. The curing monitoring mechanism of the photovoltaic junction box glue filling machine according to claim 3 is characterized by: The inner wall of the sleeve ring (205) is provided with threads around its periphery, and the sleeve rod (206) is rotated and lifted inside the sleeve ring (205) through the threads.