Building construction monitoring method and system based on BIM
By constructing BIM models in construction and dividing segmented information, analyzing dynamic data differences, and combining historical data, the problem of inaccurate construction progress prediction in the existing technology is solved, and more accurate construction progress monitoring and delay control are achieved. .
Patent Information
- Application Number
- CN202410936572.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2024-11-12
AI Technical Summary
The existing construction monitoring methods rely on the single BIM three-dimensional model analysis, and cannot intuitively display the construction status of different stages, resulting in inaccurate construction progress prediction and ineffective control of construction progress delays.
By constructing the BIM model of the target building, dividing segmented information, collecting dynamic data, analyzing data differences, making non-uniform division of construction progress adjustments, and referring to historical data, to improve the accuracy of construction progress monitoring.
It realizes more intuitive monitoring and accurate prediction of building construction progress, effectively controls construction progress delays, and improves the accuracy of construction monitoring.
Smart Images

Figure CN118940938A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, and in particular to a building construction monitoring method and system based on BIM. Background Art
[0002] Building Information Modeling (BIM) is a new tool for architecture, engineering and civil engineering. BIM was created by Autodesk and is essentially a method of designing through computers. BIM is mainly based on three-dimensional graphics, so when it is applied to the construction industry, it has a very intuitive visual experience.
[0003] Referring to the Chinese patent, a BIM-based construction monitoring method and system (announcement number: CN113378274B, announcement date: 2023-12-01) This patent uses BIM technology to establish a three-dimensional model of the construction project, and then performs real-time position information measurement at the measurement control point of each construction process. By using the real-time position information data to determine whether there are construction quality problems at each current point, and being able to provide early warning for the occurrence of risks, the safety of construction is improved.
[0004] However, the existing construction monitoring process still has other defects, such as: only relying on the BIM three-dimensional model to analyze the construction status, the model display method is single, and it cannot be combined and analyzed according to the construction status of different stages, the expected construction progress display is not intuitive enough, and when the construction data is compared with the BIM building model, due to the difference in construction direction and the error in data collection, it is not accurate to analyze the construction progress only by data comparison, resulting in inaccurate construction progress prediction and analysis results, and the construction progress cannot be adjusted in time, and the construction progress delay cannot be effectively controlled. For this reason, the present invention proposes a BIM-based construction monitoring method and system to solve the above-mentioned problems. Summary of the invention
[0005] 1. Technical issues to be solved
[0006] In view of the deficiencies in the prior art, the present invention provides a BIM-based building construction monitoring method and system, which solves the problems mentioned in the above background technology.
[0007] (II) Technical solution
[0008] To achieve the above objectives, the present invention is implemented through the following technical solutions: a BIM-based construction monitoring method, specifically comprising the following steps:
[0009] Step 1: construct basic information of the target building, set a vertical central axis for the target building, and construct a BIM model of the target building in a computer, divide the BIM model data, and display segmented information of the target building according to the division result of the BIM model data, wherein the basic information is specifically a construction drawing;
[0010] Step 2: Collect dynamic data of the target building, analyze the dynamic data, obtain marking points of the dynamic data, and determine the construction progress of the target building according to the dynamic data, wherein the dynamic data is specifically construction data;
[0011] Step 3: Analyze the data difference between the dynamic data and the corresponding BIM model, and then divide the construction progress, and adjust the construction progress according to the size of the data difference, wherein the construction progress is divided in a non-uniform manner.
[0012] Preferably, the specific method of displaying the segmented information of the target building according to the division result of the BIM model data in step 1 is:
[0013] S1: First, the finished model state of the BIM model is recorded as H, and then the BIM model is divided into several display units, recorded as j. At this time, the BIM model state corresponding to each unit j is Hj. At this time, the BIM model state corresponding to the first unit is H1, the BIM model state corresponding to the second unit is H1+H2, and the BIM model state corresponding to the nth unit is H1+H2+...+Hn;
[0014] S2: Then enter the management system of the platform, determine the BIM model status according to the input unit j, and perform multimodal analysis on the BIM model status. The specific method is as follows:
[0015] S21: Create a multimodal display window, and set the number of units input for the first time as display mode A1, the number of units input for the second time as display mode A2, and the number of units input for the nth time as display mode An, wherein A1, A2, ...An are displayed separately, and the span time between A1, A2, ...An is recorded as Tn.
[0016] Preferably, when entering the management system of the platform in S2, identity authentication is required, and after the identity authentication is completed, the model name is entered, and the set BIM model is displayed in the form of a finished product.
[0017] Preferably, the specific method of obtaining the marking points of the dynamic data in step 2 and determining the construction progress of the target building according to the dynamic data is:
[0018] P1: First, set the time node t, and display the status of the BIM model at time t. At this time, the status data of the BIM model is recorded as Yj. Then, collect the on-site construction data and record it as Sj. The data higher than Yj in the data Sj is recorded as GSj, and the data lower than Yj in the data Sj is recorded as DSj.
[0019] P2: Then set the floating threshold ER of the data. If DSj<Yj-ER, the construction progress is judged to be slow. If DSj≥Yj-ER, further analysis of the construction progress is required. The specific method is as follows:
[0020] P21: Let the number of GSj be FA, and the number of DSj be FB. If FA≥2FB, the construction progress is judged to be normal. If FA<2FB, the construction progress is judged to be slow.
[0021] Preferably, when analyzing the construction progress in P2, if only FA occurs, the construction progress is determined to be normal; if only FB occurs, the construction progress is determined to be slow.
[0022] Preferably, the specific method of dividing the construction progress in step 3 and adjusting the construction progress according to the size of the data difference is:
[0023] M1: First, the construction progress is divided into n parts, and the expected construction progress of each part is Rn. Then the actual construction progress SRn is obtained. If two or more consecutive SRn fail to reach the expected construction progress Rn, a construction progress warning is required, and the subsequent construction progress is adjusted until the next actual construction progress SRn reaches the expected construction progress Rn;
[0024] M2: Then set the threshold number WY. When the actual construction progress SRn fails to reach the expected construction progress Rn for WY times, a construction progress warning is issued and the subsequent construction progress is adjusted until the next actual construction progress SRn reaches the expected construction progress Rn.
[0025] Preferably, when the construction progress is divided into n parts in M1, the parts before n-1 are equally divided, and the n-1 part is larger than the n part.
[0026] Preferably, the method further includes step 4: acquiring historical construction data of the same target building, using the construction data as reference data for the construction progress of the building, and storing the reference data and the actual construction data shown.
[0027] The present invention also discloses a BIM-based building construction monitoring system, comprising:
[0028] Model building unit: construct basic information of the target building, set a vertical central axis for the target building, build a BIM model of the target building in a computer, divide the BIM model data, and display segmented information of the target building according to the division result of the BIM model data;
[0029] Construction analysis unit: collects dynamic data of the target building, analyzes the dynamic data, obtains marking points of the dynamic data, and determines the construction progress of the target building according to the dynamic data, wherein the dynamic data is specifically construction data;
[0030] Construction adjustment unit: Analyze the data difference between the dynamic data and the corresponding BIM model, then divide the construction progress, and adjust the construction progress according to the size of the data difference, wherein the construction progress is divided in a non-uniform manner;
[0031] Reference data unit: obtains the historical construction data of the same target building, uses the construction data as reference data for the construction progress of the building, and stores the reference data and the actual construction data.
[0032] (III) Beneficial effects
[0033] The present invention provides a BIM-based construction monitoring method and system. Compared with the prior art, it has the following beneficial effects:
[0034] This BIM-based construction monitoring method and system uses BIM technology to establish a three-dimensional model of the construction project and display information in a segmented manner. It can intuitively view the expected progress of the construction, and through the display of the cross-progress model set, analyze the time of the progress of each model, and have a more intuitive monitoring of the construction progress. Then, the construction data is compared with the BIM building model, and high and low quantity analysis is performed in the form of data marking points. Prediction analysis of the construction progress is provided, and the construction progress is adjusted in conjunction with the division of the construction progress. This can effectively control the problem of construction progress delays and significantly improve the accuracy of construction monitoring. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 A flow chart of a BIM-based construction monitoring method for an embodiment of the present application;
[0036] Figure 2 A schematic diagram of the structure of an electronic device shown in an embodiment of the present application;
[0037] Figure 3 A block diagram of a BIM-based construction monitoring system shown in an embodiment of the present application. DETAILED DESCRIPTION
[0038] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0039] See also Figure 1 - Figure 3 , the embodiment of the present invention provides five technical solutions:
[0040] Embodiment 1
[0041] A building construction monitoring method based on BIM, comprising:
[0042] Step 1: construct the basic information of the target building, set a vertical central axis for the target building, and construct the BIM model of the target building in the computer, divide the BIM model data, and display the segmented information of the target building according to the division result of the BIM model data, wherein the basic information is specifically the construction drawing; the specific method of displaying the segmented information of the target building according to the division result of the BIM model data in step 1 is:
[0043] S1: First, the finished model state of the BIM model is recorded as H, and then the BIM model is divided into several display units, recorded as j. At this time, the BIM model state corresponding to each unit j is Hj. At this time, the BIM model state corresponding to the first unit is H1, the BIM model state corresponding to the second unit is H1+H2, and the BIM model state corresponding to the nth unit is H1+H2+...+Hn;
[0044] Combined with the specific example analysis, if unit j is 5, then the finished model state H of the BIM model is divided into 5 states, corresponding to H1, H2, H3, H4 and H5 respectively. When 3 is input, it is the superposition state of H1, H2 and H3.
[0045] S2: Then enter the management system of the platform. When entering the management system of the platform, identity authentication is required. After identity authentication is completed, enter the model name. The set BIM model is displayed in the form of a finished product. The BIM model status is determined according to the input unit j. When performing multimodal analysis of the BIM model status, the specific method is as follows:
[0046] S21: Create a multimodal display window, and set the number of units input for the first time as display mode A1, the number of units input for the second time as display mode A2, and the number of units input for the nth time as display mode An, wherein A1, A2, ...An are displayed separately, and the span time between A1, A2, ...An is recorded as Tn.
[0047] Combined with the analysis of specific examples, the management personnel want to check the status of the BIM model and analyze the time spans reached by several statuses. Taking three of the statuses as an example, a window is created in the system. The first unit quantity entered in the window is display mode A1, the second unit quantity entered is display mode A2, and the third unit quantity entered is display mode A3. A1, A2 and A3 correspond to three statuses of the BIM model. These three statuses can be continuous or discontinuous. The span from A1 to A2 is 10 days, the span from A1 to A3 is 30 days, and the span from A2 to A3 is 20 days.
[0048] Step 2: Collect dynamic data of the target building, analyze the dynamic data, obtain marking points of the dynamic data, and judge the construction progress of the target building according to the dynamic data, wherein the dynamic data is specifically construction data; the specific method of obtaining marking points of the dynamic data in step 2 and judging the construction progress of the target building according to the dynamic data is:
[0049] P1: First, set the time node t, and display the status of the BIM model at time t. At this time, the status data of the BIM model is recorded as Yj. Then, collect the on-site construction data and record it as Sj. The data higher than Yj in the data Sj is recorded as GSj, and the data lower than Yj in the data Sj is recorded as DSj.
[0050] P2: Then set the floating threshold ER of the data. If DSj<Yj-ER, the construction progress is judged to be slow. If DSj≥Yj-ER, further analysis of the construction progress is required. The specific method is as follows:
[0051] P21: Let the number of GSj be FA, and the number of DSj be FB. If FA≥2FB, the construction progress is judged to be normal. If FA<2FB, the construction progress is judged to be slow.
[0052] When analyzing the construction progress in P2, if only FA occurs, the construction progress is judged to be normal. If only FB occurs, the construction progress is judged to be slow.
[0053] Combined with the analysis of specific examples, taking the expected construction progress of three months as an example, when the time node t is one month, the status of the preset BIM model is displayed, the status data Yj of the BIM model is collected, and then the data Sj is collected at the construction site. At this time, according to DSj<Yj-ER, it is judged that one data is too low, and the construction progress is slow. Taking the number of GSj as 10 and the number of DSj as 5 as an example, at this time FA≥2FB is established, and the construction progress is normal.
[0054] It should be noted that FA≥2FB is not absolute. In some construction sites, there are situations where FA≥FB is used to determine that the construction progress is normal. The specific judgment formula should be analyzed based on specific circumstances.
[0055] Step 3: Analyze the data difference between the dynamic data and the corresponding BIM model, then divide the construction progress, and adjust the construction progress according to the size of the data difference. The construction progress is divided in a non-uniform manner. The specific method of dividing the construction progress in step 3 and adjusting the construction progress according to the size of the data difference is as follows:
[0056] M1: First, the construction progress is divided into n parts. The parts before n-1 are equally divided, and the n-1 part is larger than the n part. This design is to avoid the last construction progress line being too long and to avoid delays in the construction period as much as possible. The expected construction progress of each part is Rn, and then the actual construction progress SRn is obtained. If two or more consecutive SRn fail to reach the expected construction progress Rn, a construction progress warning is required, and the subsequent construction progress is adjusted until the next actual construction progress SRn reaches the expected construction progress Rn;
[0057] M2: Then set the threshold number WY. When the actual construction progress SRn fails to reach the expected construction progress Rn for WY times, a construction progress warning is issued and the subsequent construction progress is adjusted until the next actual construction progress SRn reaches the expected construction progress Rn.
[0058] Combined with the analysis of specific examples, taking the construction progress divided into 10 parts as an example, if the actual construction progress SRn of construction progress 1 and 2 fails to reach the expected construction progress Rn continuously, construction progress 3 begins to be adjusted so that construction progress 3 completes the progress of this interval and completes the delayed part of construction progress 1 and 2. If construction progress 3 is not completed, construction progress 4 will continue to make up for it until it is completed. Taking WY as 3 as an example, if construction progress 1 is delayed, construction progress 2 is normal, construction progress 3 is delayed, construction progress 4 is normal, and construction progress 5 is delayed, then construction progress 1, 3 and 5 are all delayed, reaching 3 times. At this time, construction progress 6 is accelerated and completes the delayed part of construction progress 1, 3 and 5. If construction progress 6 is not completed, construction progress 7 will continue to make up for it until it is completed.
[0059] Embodiment 2
[0060] This embodiment is based on the first embodiment, and differs from the first embodiment in that it also includes step four: obtaining the historical construction data of the same target building, and using the construction data as reference data for the construction progress of the building, and storing the reference data and the actual construction data shown.
[0061] Embodiment 3
[0062] Compared with the first and second embodiments, the technical solution of this embodiment is to combine the solutions of the first and second embodiments for implementation.
[0063] Embodiment 4
[0064] A BIM-based building construction monitoring system, comprising:
[0065] Model building unit: construct basic information of the target building, set a vertical central axis for the target building, build a BIM model of the target building in a computer, divide the BIM model data, and display segmented information of the target building according to the division result of the BIM model data;
[0066] Construction analysis unit: collects dynamic data of the target building, analyzes the dynamic data, obtains marking points of the dynamic data, and determines the construction progress of the target building according to the dynamic data, wherein the dynamic data is specifically construction data;
[0067] Construction adjustment unit: Analyze the data difference between the dynamic data and the corresponding BIM model, then divide the construction progress, and adjust the construction progress according to the size of the data difference, wherein the construction progress is divided in a non-uniform manner;
[0068] Reference data unit: obtains the historical construction data of the same target building, uses the construction data as reference data for the construction progress of the building, and stores the reference data and the actual construction data.
[0069] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.
[0070] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0071] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
[0072] Embodiment 5
[0073] Corresponding to the aforementioned application function implementation method embodiment, the present application also provides an electronic device and corresponding embodiments.
[0074] See also Figure 2 , the electronic device 1000 includes a memory 1010 and a processor 1020 .
[0075] The processor 1020 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or the processor may be any conventional processor, etc.
[0076] The memory 1010 may include various types of storage units, such as system memory, read-only memory (ROM), and permanent storage devices. Among them, ROM can store static data or instructions required by the processor 1020 or other modules of the computer. The permanent storage device may be a readable and writable storage device. The permanent storage device may be a non-volatile storage device that does not lose the stored instructions and data even after the computer is powered off. In some embodiments, the permanent storage device uses a large-capacity storage device (such as a magnetic or optical disk, flash memory) as a permanent storage device. In some other embodiments, the permanent storage device may be a removable storage device (such as a floppy disk, optical drive). The system memory may be a readable and writable storage device or a volatile readable and writable storage device, such as a dynamic random access memory. The system memory may store some or all instructions and data required by the processor at run time. In addition, the memory 1010 may include any combination of computer-readable storage media, including various types of semiconductor memory chips (DRAM, SRAM, SDRAM, flash memory, programmable read-only memory), and disks and / or optical disks may also be used. In some embodiments, the memory 1010 may include a readable and / or writable removable storage device, such as a laser disc (CD), a read-only digital versatile disc (such as a DVD-ROM, a double-layer DVD-ROM), a read-only Blu-ray disc, an ultra-density optical disc, a flash memory card (such as an SD card, a mini SD card, a Micro-SD card, etc.), a magnetic floppy disk, etc. The computer-readable storage medium does not include carrier waves and transient electronic signals transmitted wirelessly or wired.
[0077] The memory 1010 stores executable codes, and when the executable codes are processed by the processor 1020 , the processor 1020 can execute part or all of the methods described above.
[0078] The scheme of the present application has been described in detail above with reference to the accompanying drawings. In the above embodiments, the description of each embodiment has its own emphasis. For the part that is not described in detail in a certain embodiment, refer to the relevant description of other embodiments. Those skilled in the art should also know that the actions and modules involved in the description are not necessarily required for the present application. In addition, it can be understood that the steps in the method of the embodiment of the present application can be adjusted in order, merged and deleted according to actual needs, and the modules in the device of the embodiment of the present application can be merged, divided and deleted according to actual needs.
[0079] In addition, the method according to the present application may also be implemented as a computer program or a computer program product, which includes computer program code instructions for executing some or all of the steps in the above method of the present application.
[0080] Alternatively, the present application can also be implemented as a non-temporary machine-readable storage medium (or computer-readable storage medium, or machine-readable storage medium) on which executable code (or computer program, or computer instruction code) is stored. When the executable code (or computer program, or computer instruction code) is executed by a processor of an electronic device (or electronic device, server, etc.), the processor executes part or all of the steps of the above-mentioned method according to the present application.
[0081] Those skilled in the art will further appreciate that the various illustrative logical blocks, modules, circuits, and algorithm steps described in connection with the application herein may be implemented as electronic hardware, computer software, or combinations of both.
[0082] The flow chart and block diagram in the accompanying drawings show the possible architecture, function and operation of the system and method according to multiple embodiments of the present application. In this regard, each square box in the flow chart or block diagram can represent a part of a module, a program segment or a code, and the part of the module, the program segment or the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the square box can also occur in a sequence different from that marked in the accompanying drawings. For example, two continuous square boxes can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each square box in the block diagram and / or the flow chart, and the combination of the square boxes in the block diagram and / or the flow chart can be implemented with a dedicated hardware-based system that performs the specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.
[0083] The embodiments of the present application have been described above, and the above description is exemplary, not exhaustive, and is not limited to the disclosed embodiments. Many modifications and changes will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments. The selection of terms used herein is intended to best explain the principles of the embodiments, practical applications, or improvements to the technology in the market, or to enable other persons of ordinary skill in the art to understand the embodiments disclosed herein.
Claims
1. A BIM-based construction monitoring method, characterized in that: The specific steps include: Step 1: construct basic information of the target building, set a vertical central axis for the target building, and construct a BIM model of the target building in a computer, divide the BIM model data, and display segmented information of the target building according to the division result of the BIM model data, wherein the basic information is specifically a construction drawing; Step 2: Collect dynamic data of the target building, analyze the dynamic data, obtain marking points of the dynamic data, and determine the construction progress of the target building according to the dynamic data, wherein the dynamic data is specifically construction data; Step 3: Analyze the data difference between the dynamic data and the corresponding BIM model, and then divide the construction progress, and adjust the construction progress according to the size of the data difference, wherein the construction progress is divided in a non-uniform manner.
2. A BIM-based construction monitoring method according to claim 1, characterized in that: The specific method of displaying the segmented information of the target building according to the division result of the BIM model data in the step 1 is: S1: First, the finished model state of the BIM model is recorded as H, and then the BIM model is divided into several display units, recorded as j. At this time, the BIM model state corresponding to each unit j is Hj. At this time, the BIM model state corresponding to the first unit is H1, the BIM model state corresponding to the second unit is H1+H2, and the BIM model state corresponding to the nth unit is H1+H2+...+Hn; S2: Then enter the management system of the platform, determine the BIM model status according to the input unit j, and perform multimodal analysis on the BIM model status. The specific method is as follows: S21: Create a multimodal display window, and set the number of units input for the first time as display mode A1, the number of units input for the second time as display mode A2, and the number of units input for the nth time as display mode An, wherein A1, A2, ...An are displayed separately, and the span time between A1, A2, ...An is recorded as Tn.
3. A BIM-based construction monitoring method according to claim 2, characterized in that: When entering the management system of the platform in S2, identity authentication is required. After the identity authentication is completed, the model name is entered, and the set BIM model is displayed in the form of a finished product.
4. A BIM-based construction monitoring method according to claim 1, characterized in that: The specific method of obtaining the marking points of the dynamic data in step 2 and determining the construction progress of the target building according to the dynamic data is as follows: P1: First, set the time node t, and display the status of the BIM model at time t. At this time, the status data of the BIM model is recorded as Yj. Then, collect the on-site construction data and record it as Sj. The data higher than Yj in the data Sj is recorded as GSj, and the data lower than Yj in the data Sj is recorded as DSj. P2: Then set the floating threshold ER of the data. If DSj<Yj-ER, the construction progress is judged to be slow. If DSj≥Yj-ER, the construction progress needs to be further analyzed. The specific method is as follows: P21: Let the number of GSj be FA, and the number of DSj be FB. If FA≥2FB, the construction progress is judged to be normal. If FA<2FB, the construction progress is judged to be slow.
5. A BIM-based construction monitoring method according to claim 4, characterized in that: When analyzing the construction progress in P2, if only FA occurs, the construction progress is determined to be normal; if only FB occurs, the construction progress is determined to be slow.
6. A BIM-based construction monitoring method according to claim 1, characterized in that: The specific method of dividing the construction progress in step 3 and adjusting the construction progress according to the size of the data difference is: M1: First, the construction progress is divided into n parts, and the expected construction progress of each part is Rn. Then the actual construction progress SRn is obtained. If two or more consecutive SRn fail to reach the expected construction progress Rn, a construction progress warning is required, and the subsequent construction progress is adjusted until the next actual construction progress SRn reaches the expected construction progress Rn; M2: Then set the threshold number WY. When the actual construction progress SRn fails to reach the expected construction progress Rn for WY times, a construction progress warning is issued and the subsequent construction progress is adjusted until the next actual construction progress SRn reaches the expected construction progress Rn.
7. A BIM-based construction monitoring method according to claim 6, characterized in that: When the construction progress is divided into n parts in M1, the parts before n-1 are equally divided, and the n-1 part is larger than the n part.
8. The method for monitoring construction based on BIM according to claim 1, characterized in that: The method also includes step 4: obtaining the historical construction data of the same target building, using the construction data as reference data for the construction progress of the building, and storing the reference data and the actual construction data shown.
9. A BIM-based building construction monitoring system, characterized in that: include: Model building unit: construct basic information of the target building, set a vertical central axis for the target building, build a BIM model of the target building in a computer, divide the BIM model data, and display segmented information of the target building according to the division result of the BIM model data; Construction analysis unit: collects dynamic data of the target building, analyzes the dynamic data, obtains marking points of the dynamic data, and determines the construction progress of the target building according to the dynamic data, wherein the dynamic data is specifically construction data; Construction adjustment unit: Analyze the data difference between the dynamic data and the corresponding BIM model, then divide the construction progress, and adjust the construction progress according to the size of the data difference, wherein the construction progress is divided in a non-uniform manner; Reference data unit: obtains the historical construction data of the same target building, uses the construction data as reference data for the construction progress of the building, and stores the reference data and the actual construction data.