Power grid frequency safety online checking method, system and equipment and storage medium
Through the multi-time scale online verification method for grid frequency safety, combined with the adjustable space of the power grid unit and the secondary frequency modulation climbing rate, the problem that traditional grid disturbance simulation methods are difficult to meet the complex operation needs of high proportion new energy systems is realized. The accurate and reliable verification of power grid frequency reduces the risk of power grid operation.
Patent Information
- Application Number
- CN202410835032.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-26
- Publication Date
- 2024-11-12
AI Technical Summary
The traditional grid disturbance simulation method is only applicable to a single time scale, and it is difficult to meet the reliability and sensitivity requirements of online early warning under the complex operation mode of high proportion of new energy power systems, resulting in difficulty in maintaining the power grid frequency within the safe range and the risk of large power outages.
The online verification method of grid frequency safety of multiple time scales is adopted. By collecting active disturbance measurement data from each station, it is divided into disturbance events of different time scales, integrating and superimposing it to obtain extreme disturbance signals, combining the unit adjustable space and secondary Frequency modulation climbing rate, conduct safety verification of grid frequency based on electromechanical transient time domain simulation, judge and perform primary or secondary frequency modulation response.
It improves the accuracy and reliability of multi-time scale frequency calibration in the power grid, reduces the risk of grid operation, provides an analysis and decision-making basis for grid frequency safety, and ensures the frequency safety of the power grid under multi-time scale disturbances.
Smart Images

Figure CN118941129A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power system automation, and in particular to a method, system, device and storage medium for online verification of power grid frequency safety. Background Art
[0002] With the deepening development of new power systems, thermal power units in power systems with a high proportion of new energy continue to be retired, traditional frequency regulation resources are gradually scarce, and the frequency regulation capacity that synchronous machines in the system can provide is significantly reduced. Affected by multi-time scale disturbance factors such as fluctuations in primary energy supply, low output of new energy during peak load periods, and AC and DC faults in power grids, the existing frequency regulation resources are difficult to ensure that the system frequency remains within a safe range when the load continues to grow. There is a risk of continuous frequency decline triggering low-frequency load reduction and causing a major blackout. Therefore, it is necessary to simulate the multi-time scale frequency disturbances of the power grid and provide technical support for comprehensive defense measures for the safety and stability of the power grid.
[0003] Traditional grid disturbance simulation methods are only for a single time scale, which is difficult to meet the requirements of online warning reliability and sensitivity for complex and changeable operation modes of high-proportion renewable energy power systems. Therefore, a method for online verification of grid frequency security that considers multiple time scales is needed. Summary of the invention
[0004] Purpose of the invention: The purpose of the present invention is to provide a method, system, device and storage medium for online frequency safety verification of power grid, which improves the accuracy and reliability of multi-time scale frequency verification of power grid.
[0005] Technical solution: The method for online verification of power grid frequency safety described in the present invention comprises:
[0006] Collect active disturbance measurement data of each station, divide the active disturbance measurement data of each station into disturbance data of each station under the target disturbance event according to the decrease and increase of active change in unit time, and continuously integrate the disturbance data of each station under the target disturbance event to obtain the disturbance signal of each station under the target disturbance event. Each station includes historical wind farms, photovoltaic power stations and substations;
[0007] Analyze the target disturbance events of historical wind farms, photovoltaic power stations and substations, obtain the disturbance events and corresponding disturbance signals corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations, and superimpose the disturbance signals corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations into extreme disturbance signals through the linear superposition method;
[0008] Divide the superimposed extreme disturbance signal into n time windows according to preset time intervals;
[0009] Perform online verification of grid frequency security at multiple time scales in each time window.
[0010] Further, the active disturbance measurement data of each station includes active disturbance measurement data of historical wind farms, active disturbance measurement data of photovoltaic power stations, and active disturbance measurement data of substation loads. The target disturbance event includes a sudden rise disturbance event and a sudden drop disturbance event. The active disturbance measurement data of each station is divided into disturbance data of each station under the target disturbance event, and the disturbance data of each station under the target disturbance event is continuously integrated to obtain the disturbance signal of each station under the target disturbance event, including:
[0011] The active disturbance measurement data of historical wind farms, photovoltaic power stations and substation loads are divided into disturbance data of each station under a sudden rise disturbance event and disturbance data of each station under a sudden drop disturbance event. The disturbance data of each station under a sudden drop disturbance event and the disturbance data under a sudden rise disturbance event are continuously integrated to obtain the sudden drop disturbance signals of historical wind farms, photovoltaic power stations and substations under a sudden drop disturbance event and the sudden rise disturbance signals under a sudden rise disturbance event.
[0012] Furthermore, the online verification of the power grid frequency safety at multiple time scales for each time window is specifically implemented by:
[0013] Integrate the frequency modulation response area of all time windows in the time series of extreme disturbance signals, considering the adjustable space P of the unit Space and the secondary frequency regulation ramp rate θ SFC , according to the frequency modulation response status of each time window, the detailed model and parameters of the current power grid are checked for power grid frequency safety based on electromechanical transient time domain simulation;
[0014] For the i-th time window, determine the adjustable space P corresponding to the i-th time window of the previous round of power grid units Space,i-1 The adjustment space ΔP corresponding to the turbine unit in the i-th time window Gen,i , if P Space,i-1 ≥ΔP Gen,i When , the frequency of the i-th time window is modulated;
[0015] After this round of frequency regulation, the grid frequency changes by Δf i , the remaining adjustable space of the adjustable unit is P Space_res,i , then:
[0016] P Space_res,i =P Space_res,i-1 -ΔP Gen,i
[0017] When the adjustable space P of the previous round of the power grid unitSpace,i-1 Smaller than the adjustment space ΔP of the frequency response of this turbine unit Gen,i When , the remaining time window of the disturbance time series stops the frequency modulation response;
[0018] The simulation results of frequency modulation in n time windows are superimposed to obtain the maximum frequency offset of the disturbance event under the current operation mode of the power grid:
[0019]
[0020] By comparing the frequency change of the maximum disturbance event under the current operation mode of the power grid with the frequency safety constraint of the power grid, if the frequency change is greater than the frequency safety constraint of the power grid, an alarm is issued to achieve frequency safety simulation verification.
[0021] Furthermore, the frequency modulation of the i-th time window is specifically to determine whether the i-th time window is a primary frequency modulation response area or a secondary frequency modulation response area;
[0022] When the i-th time window is a frequency modulation response area, a frequency modulation is performed on the i-th time window in this round;
[0023] When the i-th time window is a secondary frequency modulation response area, secondary frequency modulation is performed on the i-th time window in this round.
[0024] Further, judging whether the i-th time window is a primary frequency modulation response region or a secondary frequency modulation response region includes: calculating the equivalent slope θ of the integrated electrical quantity of the disturbance signal in each time window respectively. n ;
[0025] According to the equivalent slope θ of the integrated power of the disturbance signal in each time window n and the secondary frequency regulation ramp rate θ SFC , the disturbance signal area in each time window is divided into the primary frequency modulation response area or the secondary frequency modulation response area.
[0026] Furthermore, the equivalent slope θ of the integrated electrical quantity of the disturbance signal in each time window is calculated respectively. n , specifically:
[0027] Using a constant slope instead of the changing slope of the serialized disturbance signal in each time window, the equivalent slope θ of the disturbance signal in the nth time window n The calculation method is as follows:
[0028]
[0029] Among them, t n is the starting time of the disturbance sequence in the nth time window, t n+1 is the starting time of the disturbance sequence in the n+1th time window, Pn (t) is the active power curve corresponding to the disturbance sequence in the nth time window, P s,n The corresponding initial active power in the disturbance sequence in the nth time window, dt represents the integration operation on the corresponding function curve of the nth time window.
[0030] Furthermore, the secondary frequency regulation ramp rate θ SFC The specific determination methods include:
[0031] Statistics of the secondary frequency regulation climbing rate θ of the whole network generator set Gen_SFC,q , calculate the secondary frequency regulation climbing rate of the power grid according to the secondary frequency regulation climbing rate of the whole network generator set θ SFC , grid secondary frequency regulation ramp rate θ SFC The calculation formula is as follows:
[0032]
[0033] Among them, N is the number of generators participating in secondary frequency regulation in the entire network.
[0034] Furthermore, the disturbance signal area in each time window is divided into the primary frequency modulation response area or the secondary frequency modulation response area, specifically, by comparing the equivalent slope of the integrated power of the disturbance sequence in the nth time window with the secondary frequency modulation ramp rate of the power grid. If θ n ≤θ SFC , then the disturbance signal area in the nth time window is divided into the secondary frequency modulation response area of the disturbance, otherwise it is divided into the primary frequency modulation response area of the disturbance.
[0035] Based on the same inventive concept, the present invention also provides a power grid frequency safety online verification system, comprising:
[0036] The disturbance signal acquisition module is used to collect the active disturbance measurement data of each station, and divide the active disturbance measurement data of each station into disturbance data of each station under the target disturbance event according to the decrease and increase of the active change in unit time, and continuously integrate the disturbance data of each station under the target disturbance event to obtain the disturbance signal of each station under the target disturbance event. Each station includes a historical wind farm, a photovoltaic power station and a substation;
[0037] The extreme disturbance signal generation module is used to analyze the target disturbance events of historical wind farms, photovoltaic power stations and substations, obtain the disturbance events corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations, and superimpose the disturbance signals corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations into extreme disturbance signals by linear superposition method;
[0038] A serialization module is used to divide the superimposed extreme disturbance signal into n time windows according to a preset time interval;
[0039] The safety verification module is used to perform online safety verification of the power grid frequency at multiple time scales in each time window.
[0040] Furthermore, the specific implementation method of the safety verification module is as follows:
[0041] Integrate the frequency modulation response area of all time windows in the time series of extreme disturbance signals, considering the adjustable space P of the unit Space and the secondary frequency regulation ramp rate θ SFC , according to the frequency modulation response status of each time window, the detailed model and parameters of the current power grid are checked for power grid frequency safety based on electromechanical transient time domain simulation;
[0042] For the i-th time window, determine the adjustable space P corresponding to the i-th time window of the previous round of power grid units Space,i-1 The adjustment space ΔP corresponding to the turbine unit in the i-th time window Gen,i , if P Space,i-1 ≥ΔP Gen,i When , the frequency of the i-th time window is modulated;
[0043] After this round of frequency regulation, the grid frequency changes by Δf i , the remaining adjustable space of the adjustable unit is P Space_res,i , then:
[0044] P Space_res,i =P Space_res,i-1 -ΔP Gen,i
[0045] When the adjustable space P of the previous round of the power grid unit Space,i-1 Smaller than the adjustment space ΔP of the frequency response of this turbine unit Gen,i When , the remaining time window of the disturbance time series stops the frequency modulation response;
[0046] The simulation results of frequency modulation in n time windows are superimposed to obtain the maximum frequency offset of the disturbance event under the current operation mode of the power grid:
[0047]
[0048] By comparing the frequency change of the maximum disturbance event under the current operation mode of the power grid with the frequency safety constraint of the power grid, if the frequency change is greater than the frequency safety constraint of the power grid, an alarm is issued to achieve frequency safety simulation verification.
[0049] Based on the same inventive concept, the present invention also provides a computing device, comprising: one or more processors, one or more memories and one or more programs, wherein the programs are stored in the memories and configured to be executed by the processors, and when the programs are loaded into the processors, the steps of the method for online verification of grid frequency safety according to any one of the above items are implemented.
[0050] Based on the same inventive concept, the present invention also provides a storage medium, which stores a computer program, and the computer program includes program instructions. When the program instructions are executed by a processor, the processor executes the steps of the online verification method for power grid frequency safety according to any one of the above items.
[0051] Beneficial effect: Compared with the prior art, the present invention can perform multi-time-scale online verification of power grid frequency safety. By adopting a multi-time-scale online verification scheme for power grid frequency safety, it realizes the simulation of secondary frequency modulation and primary frequency modulation of multi-time-scale disturbances in the power grid, improves the accuracy and reliability of multi-time-scale frequency verification of the power grid, reduces the risk of power grid operation, and provides an analysis and decision-making basis for ensuring the safety of power grid frequency. BRIEF DESCRIPTION OF THE DRAWINGS
[0052] Figure 1 is a flow chart of the method of the present invention;
[0053] Figure 2 The figure is a flow chart of a method according to an embodiment of the present invention. DETAILED DESCRIPTION
[0054] The technical solution of the present invention is further described below in conjunction with the accompanying drawings and embodiments. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present invention.
[0055] Embodiment 1: As attached Figure 1 As shown, the power grid frequency safety online verification method of the embodiment of the present invention includes:
[0056] Collect active disturbance measurement data of each station, divide the active disturbance measurement data of each station into disturbance data of each station under the target disturbance event according to the decrease and increase of active change in unit time, and continuously integrate the disturbance data of each station under the target disturbance event to obtain the disturbance signal of each station under the target disturbance event. Each station includes historical wind farms, photovoltaic power stations and substations;
[0057] Analyze the target disturbance events of historical wind farms, photovoltaic power stations and substations, obtain the disturbance events and corresponding disturbance signals corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations, and superimpose the disturbance signals corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations into extreme disturbance signals through the linear superposition method;
[0058] Divide the superimposed extreme disturbance signal into n time windows according to preset time intervals;
[0059] Perform online verification of grid frequency security at multiple time scales in each time window.
[0060] Further, the active disturbance measurement data of each station includes active disturbance measurement data of historical wind farms, active disturbance measurement data of photovoltaic power stations, and active disturbance measurement data of substation loads. The target disturbance event includes a sudden rise disturbance event and a sudden drop disturbance event. The active disturbance measurement data of each station is divided into disturbance data of each station under the target disturbance event, and the disturbance data of each station under the target disturbance event is continuously integrated to obtain the disturbance signal of each station under the target disturbance event, including:
[0061] The active disturbance measurement data of historical wind farms, photovoltaic power stations and substation loads are divided into disturbance data of each station under a sudden rise disturbance event and disturbance data of each station under a sudden drop disturbance event. The disturbance data of each station under a sudden drop disturbance event and the disturbance data under a sudden rise disturbance event are continuously integrated to obtain the sudden drop disturbance signals of historical wind farms, photovoltaic power stations and substations under a sudden drop disturbance event and the sudden rise disturbance signals under a sudden rise disturbance event.
[0062] Furthermore, the online verification of the power grid frequency safety at multiple time scales for each time window is specifically implemented by:
[0063] Integrate the frequency modulation response area of all time windows in the time series of extreme disturbance signals, considering the adjustable space P of the unit Space and the secondary frequency regulation ramp rate θ SFC , according to the frequency modulation response status of each time window, the detailed model and parameters of the current power grid are checked for power grid frequency safety based on electromechanical transient time domain simulation;
[0064] For the i-th time window, determine the adjustable space P corresponding to the i-th time window of the previous round of power grid units Space,i-1 The adjustment space ΔP corresponding to the turbine unit in the i-th time window Gen,i , if P Space,i-1 ≥ΔP Gen,i When , the frequency of the i-th time window is modulated;
[0065] After this round of frequency regulation, the grid frequency changes by Δf i , the remaining adjustable space of the adjustable unit is P Space_res,i , then:
[0066] P Space_res,i =P Space_res,i-1 -ΔP Gen,i
[0067] When the adjustable space P of the previous round of the power grid unit Space,i-1 Smaller than the adjustment space ΔP of the frequency response of this turbine unit Gen,i When , the remaining time window of the disturbance time series stops the frequency modulation response;
[0068] The simulation results of frequency modulation in n time windows are superimposed to obtain the maximum frequency offset of the disturbance event under the current operation mode of the power grid:
[0069]
[0070] By comparing the frequency change of the maximum disturbance event under the current operation mode of the power grid with the frequency safety constraint of the power grid, if the frequency change is greater than the frequency safety constraint of the power grid, an alarm is issued to achieve frequency safety simulation verification.
[0071] Furthermore, the frequency modulation of the i-th time window is specifically to determine whether the i-th time window is a primary frequency modulation response area or a secondary frequency modulation response area;
[0072] When the i-th time window is a frequency modulation response area, a frequency modulation is performed on the i-th time window in this round;
[0073] When the i-th time window is a secondary frequency modulation response area, secondary frequency modulation is performed on the i-th time window in this round.
[0074] Further, judging whether the i-th time window is a primary frequency modulation response region or a secondary frequency modulation response region includes: calculating the equivalent slope θ of the integrated electrical quantity of the disturbance signal in each time window respectively. n ;
[0075] According to the equivalent slope θ of the integrated power of the disturbance signal in each time window n and the secondary frequency regulation ramp rate θ SFC , the disturbance signal area in each time window is divided into the primary frequency modulation response area or the secondary frequency modulation response area.
[0076] Furthermore, the equivalent slope θ of the integrated electrical quantity of the disturbance signal in each time window is calculated respectively. n , specifically:
[0077] Using a constant slope instead of the changing slope of the serialized disturbance signal in each time window, the equivalent slope θ of the disturbance signal in the nth time window n The calculation method is as follows:
[0078]
[0079] Among them, t n is the starting time of the disturbance sequence in the nth time window, t n+1 is the starting time of the disturbance sequence in the n+1th time window, P n (t) is the active power curve corresponding to the disturbance sequence in the nth time window, P s,n The corresponding initial active power in the disturbance sequence in the nth time window, dt represents the integration operation on the corresponding function curve of the nth time window.
[0080] Furthermore, the secondary frequency regulation ramp rate θ SFC The specific determination methods include:
[0081] Statistics of the secondary frequency regulation climbing rate θ of the whole network generator set Gen_SFC,q , calculate the secondary frequency regulation climbing rate of the power grid according to the secondary frequency regulation climbing rate of the whole network generator set θ SFC , grid secondary frequency regulation ramp rate θ SFC The calculation formula is as follows:
[0082]
[0083] Among them, N is the number of generators participating in secondary frequency regulation in the entire network.
[0084] Furthermore, the disturbance signal area in each time window is divided into the primary frequency modulation response area or the secondary frequency modulation response area, specifically, by comparing the equivalent slope of the integrated power of the disturbance sequence in the nth time window with the secondary frequency modulation ramp rate of the power grid. If θ n ≤θ SFC , then the disturbance signal area in the nth time window is divided into the secondary frequency modulation response area of the disturbance, otherwise it is divided into the primary frequency modulation response area of the disturbance.
[0085] Embodiment 2: As attached Figure 2 As shown, the power grid frequency safety online verification method of the embodiment of the present invention includes:
[0086] Step 1: Acquisition of new energy and load disturbance events: Collect historical active disturbance measurement data of wind farms, active disturbance measurement data of photovoltaic power stations, and load disturbance data of substations, and divide them into two types of disturbance events: sudden drop and sudden rise. For the same type of disturbance events, the discrete disturbance data are continuously integrated to obtain the sudden drop or sudden rise disturbance signals corresponding to wind power, photovoltaic power and load respectively;
[0087] Step 2: Generation of extreme disturbance signals: Analyze the disturbance events of wind power, photovoltaic power and load, obtain the disturbance events corresponding to the maximum disturbance amplitudes of wind power, photovoltaic power and load respectively, and superimpose the disturbance signals corresponding to the maximum disturbance amplitudes of wind power, photovoltaic power and load into extreme disturbance signals by linear superposition method;
[0088] Step 3: Disturbance signal serialization: Perform time serialization processing and divide the superimposed disturbance signal into n time windows at a fixed time interval of 1 minute;
[0089] Step 4: Calculation of equivalent slope of disturbance sequence time window: Calculate the equivalent slope θ of the integrated power of the disturbance signal in each time window n ;
[0090] Step 5: Determine the primary frequency modulation response area or secondary frequency modulation response area of the disturbance: Determine the primary and secondary frequency modulation response areas of the disturbance, specifically when the secondary frequency modulation ramp rate θ SFC Greater than or equal to the equivalent slope θ of the disturbance signal in the nth time window n When , the disturbance signal region in the nth time window is divided into the secondary frequency modulation response region of the disturbance, otherwise it is divided into the primary frequency modulation response region of the disturbance;
[0091] Step 6: Generate a primary frequency modulation disturbance scenario: Calculate the disturbance change according to the active integrated power and equivalent slope in the primary frequency modulation response area, and generate a primary frequency modulation power disturbance scenario;
[0092] Step 7: Integrate the multi-time scale frequency safety simulation scenarios, integrating the primary frequency modulation response area or the secondary frequency modulation response area of all time windows in the time series of the extreme disturbance signal;
[0093] Step 8: Multi-time scale grid frequency safety check: Specifically, integrate the primary frequency modulation response area or secondary frequency modulation response area of all time windows in the time series of the extreme disturbance signal, perform primary and secondary frequency modulation safety checks on all time windows in turn, consider the adjustable space and ramp rate of the unit, calculate the frequency change of the disturbance signal after the primary and secondary frequency modulation response in each time window, and superimpose the calculation of the frequency change of the disturbance signal after the primary and secondary frequency modulation response in the entire disturbance event time series.
[0094] Step 9: Determine the frequency security problem, and determine the frequency change of the maximum disturbance event under the current grid operation mode;
[0095] Step 10: Frequency safety alarm. If the frequency change is greater than the frequency safety constraint of the power grid, an alarm is issued. If there is no frequency safety problem, the next round of rolling calculation is performed.
[0096] Specifically, in step 4, the calculation process of the equivalent slope calculation of the disturbance sequence time window is as follows:
[0097] Step 4.1: The equivalent slope of the disturbance is replaced by the slope of the hypotenuse of the triangle corresponding to the integrated power of the disturbance in the time window, and the slope of the disturbance sequence signal that changes continuously in the time window is replaced by a constant slope. The equivalent slope calculation method for the nth disturbance sequence is as follows:
[0098]
[0099] Step 4.2: Where θ n is the equivalent slope in the nth time window of the disturbance sequence, t n is the starting time of the nth time series, P n (t) is the active power curve corresponding to the nth time series, P s,n The corresponding initial active power in the nth time series.
[0100] In step 5, the calculation process for determining the primary frequency modulation response area or the secondary frequency modulation response area of the disturbance is as follows:
[0101] Step 5.1: Divide the secondary frequency regulation response area of the disturbance by considering the limitation of the secondary frequency regulation ramp rate of the power grid, and calculate the secondary frequency regulation ramp rate θ of the power grid SFC , by counting the secondary frequency ramp rate of the whole network generator set θ Gen_SFC,q The calculation can be obtained:
[0102]
[0103] Step 5.2: Compare the equivalent slope of the nth disturbance time series with the secondary frequency regulation ramp rate of the power grid. If θ n ≤θ SFC It is divided into the secondary FM response area, otherwise it is divided into the primary FM response area.
[0104] In step 6, the calculation process of generating the primary frequency modulation disturbance scenario is as follows:
[0105] Step 6.1: In the mth time window of the divided primary frequency modulation response area, calculate the disturbance amplitude ΔP in the time window according to the active integrated power in the current time window PFC,m :
[0106]
[0107] Step 6.2: According to the disturbance amplitude ΔP in the mth time window PFC,m and the disturbance equivalent slope θ m , generate a frequency modulation disturbance scenario;
[0108] In step 8, the multi-time scale grid frequency security verification calculation process is:
[0109] Step 8.1: Perform electromechanical transient time domain simulation on the detailed model and parameters of the current power grid, considering the adjustable space P of the unit Space and the secondary frequency regulation ramp rate θ SFC , and perform frequency safety verification of primary and secondary frequency regulation of power grids in turn according to the primary and secondary frequency regulation response states of the power grid in each time window;
[0110] Step 8.2: In the i-th time window, consider the primary or secondary frequency regulation response type of the time window, when the adjustable space P of the previous round of the power grid unit Space,i-1 Adjustment space ΔP with the primary or secondary frequency response of this turbine unit Gen,i Compared to: P Space,i-1 ≥ΔP Gen,i When the frequency is adjusted once or twice,
[0111] Step 8.3: After the first or second frequency adjustment in this round, the grid frequency changes by Δf i , the remaining adjustable space of the adjustable unit is P Space_res,i :
[0112] P Space_res,i =P Space_res,i-1 -ΔP Gen,i (4)
[0113] Step 8.4: When the adjustable space P of the previous round of the grid unit Space,i-1 Smaller than the adjustment space ΔP of the primary or secondary frequency response of the turbine unit Gen,i When , the remaining disturbance time series stops the primary or secondary frequency modulation response;
[0114] Step 8.5: Superimpose the simulation results of the primary or secondary frequency modulation in n time windows to obtain the maximum frequency offset of the disturbance event under the current operation mode of the power grid:
[0115]
[0116] Based on the same inventive concept, this embodiment also provides a power grid frequency safety online verification system, including:
[0117] The disturbance signal acquisition module is used to collect the active disturbance measurement data of each station, and divide the active disturbance measurement data of each station into disturbance data of each station under the target disturbance event according to the decrease and increase of the active change in unit time, and continuously integrate the disturbance data of each station under the target disturbance event to obtain the disturbance signal of each station under the target disturbance event. Each station includes a historical wind farm, a photovoltaic power station and a substation;
[0118] The extreme disturbance signal generation module is used to analyze the target disturbance events of historical wind farms, photovoltaic power stations and substations, obtain the disturbance events corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations, and superimpose the disturbance signals corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations into extreme disturbance signals by linear superposition method;
[0119] A serialization module is used to divide the superimposed extreme disturbance signal into n time windows according to a preset time interval;
[0120] The safety verification module is used to perform online safety verification of the power grid frequency at multiple time scales in each time window.
[0121] Furthermore, the specific implementation method of the safety verification module is as follows:
[0122] Integrate the frequency modulation response area of all time windows in the time series of extreme disturbance signals, considering the adjustable space P of the unit Space and the secondary frequency regulation ramp rate θ SFC , according to the frequency modulation response status of each time window, the detailed model and parameters of the current power grid are checked for power grid frequency safety based on electromechanical transient time domain simulation;
[0123] For the i-th time window, determine the adjustable space P corresponding to the i-th time window of the previous round of power grid units Space,i-1 The adjustment space ΔP corresponding to the turbine unit in the i-th time window Gen,i , if P Space,i-1 ≥ΔP Gen,i When , the frequency of the i-th time window is modulated;
[0124] After this round of frequency regulation, the grid frequency changes by Δf i , the remaining adjustable space of the adjustable unit is P Space_res,i , then:
[0125] P Space_res,i =P Space_res,i-1 -ΔP Gen,i
[0126] When the adjustable space P of the previous round of the power grid unit Space,i-1Smaller than the adjustment space ΔP of the frequency response of this turbine unit Gen,i When , the remaining time window of the disturbance time series stops the frequency modulation response;
[0127] The simulation results of frequency modulation in n time windows are superimposed to obtain the maximum frequency offset of the disturbance event under the current operation mode of the power grid:
[0128]
[0129] By comparing the frequency change of the maximum disturbance event under the current operation mode of the power grid with the frequency safety constraint of the power grid, if the frequency change is greater than the frequency safety constraint of the power grid, an alarm is issued to implement frequency safety simulation verification. Based on the same inventive concept, this embodiment also provides a computing device, including: one or more processors, one or more memories, and one or more programs, the programs are stored in the memories and are configured to be executed by the processors, and when the programs are loaded into the processors, the steps of the online verification method for power grid frequency safety according to any of the above items are implemented.
[0130] Based on the same inventive concept, this embodiment also provides a storage medium, which stores a computer program, and the computer program includes program instructions. When the program instructions are executed by a processor, the processor executes the steps of the power grid frequency safety online verification method according to any one of the above items.
[0131] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0132] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0133] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0134] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 A step that specifies a function in one or more boxes.
[0135] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents. Any modification or equivalent replacement that does not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.
Claims
1. A method for online verification of power grid frequency security, characterized in that: include: Collect active disturbance measurement data of each station, divide the active disturbance measurement data of each station into disturbance data of each station under the target disturbance event according to the decrease and increase of active change in unit time, and continuously integrate the disturbance data of each station under the target disturbance event to obtain the disturbance signal of each station under the target disturbance event. Each station includes historical wind farms, photovoltaic power stations and substations; Analyze the target disturbance events of historical wind farms, photovoltaic power stations and substations, obtain the disturbance events and corresponding disturbance signals corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations, and superimpose the disturbance signals corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations into extreme disturbance signals through the linear superposition method; Divide the superimposed extreme disturbance signal into n time windows according to preset time intervals; Perform online verification of grid frequency security at multiple time scales in each time window.
2. The method for online verification of power grid frequency safety according to claim 1, characterized in that: The active disturbance measurement data of each station includes active disturbance measurement data of historical wind farms, active disturbance measurement data of photovoltaic power stations, and active disturbance measurement data of substation loads. The target disturbance event includes a sudden rise disturbance event and a sudden drop disturbance event. The active disturbance measurement data of each station is divided into disturbance data of each station under the target disturbance event, and the disturbance data of each station under the target disturbance event are continuously integrated to obtain the disturbance signal of each station under the target disturbance event, including: The active disturbance measurement data of historical wind farms, photovoltaic power stations and substation loads are divided into disturbance data of each station under a sudden rise disturbance event and disturbance data of each station under a sudden drop disturbance event. The disturbance data of each station under a sudden drop disturbance event and the disturbance data under a sudden rise disturbance event are continuously integrated to obtain the sudden drop disturbance signals of historical wind farms, photovoltaic power stations and substations under a sudden drop disturbance event and the sudden rise disturbance signals under a sudden rise disturbance event.
3. The method for online verification of power grid frequency safety according to claim 1, characterized in that: The specific implementation method of performing multi-time-scale online verification of power grid frequency safety in each time window includes: Integrate the frequency modulation response area of all time windows in the time series of extreme disturbance signals, considering the adjustable space P of the unit Space and the secondary frequency regulation ramp rate θ SFC , according to the frequency modulation response status of each time window, the detailed model and parameters of the current power grid are checked for power grid frequency safety based on electromechanical transient time domain simulation; For the i-th time window, determine the adjustable space P corresponding to the i-th time window of the previous round of power grid units Space,i-1 The adjustment space ΔP corresponding to the turbine unit in the i-th time window Gen,i , if P Space,i-1 ≥ΔP Gen,i When , the frequency of the i-th time window is modulated; After this round of frequency regulation, the grid frequency changes by Δf i , the remaining adjustable space of the adjustable unit is P Space_res,i , then: P Space_res,i =P Space_res,i-1 -ΔP Gen,i When the adjustable space P of the previous round of the power grid unit Space,i-1 Smaller than the adjustment space ΔP of the frequency response of this turbine unit Gen,i When , the remaining time window of the disturbance time series stops the frequency modulation response; The simulation results of frequency modulation in n time windows are superimposed to obtain the maximum frequency offset of the disturbance event under the current operation mode of the power grid: By comparing the frequency change of the maximum disturbance event under the current operation mode of the power grid with the frequency safety constraint of the power grid, if the frequency change is greater than the frequency safety constraint of the power grid, an alarm is issued to achieve frequency safety simulation verification.
4. The method for online verification of power grid frequency safety according to claim 3, characterized in that: The frequency modulation of the i-th time window is specifically to determine whether the i-th time window is a primary frequency modulation response area or a secondary frequency modulation response area; When the i-th time window is a frequency modulation response area, a frequency modulation is performed on the i-th time window in this round; When the i-th time window is a secondary frequency modulation response area, secondary frequency modulation is performed on the i-th time window in this round.
5. The method for online verification of power grid frequency safety according to claim 4, characterized in that: Determine whether the i-th time window is a primary frequency modulation response area or a secondary frequency modulation response area, including: calculating the equivalent slope θ of the integrated electrical quantity of the disturbance signal in each time window respectively n ; According to the equivalent slope θ of the integrated power of the disturbance signal in each time window n and the secondary frequency regulation ramp rate θ SFC , the disturbance signal area in each time window is divided into the primary frequency modulation response area or the secondary frequency modulation response area.
6. The method for online verification of power grid frequency safety according to claim 5, characterized in that: The equivalent slope θ of the integrated electrical quantity of the disturbance signal in each time window is calculated respectively. n , specifically: Using a constant slope instead of the changing slope of the serialized disturbance signal in each time window, the equivalent slope θ of the disturbance signal in the nth time window n The calculation method is as follows: Among them, t n is the starting time of the disturbance sequence in the nth time window, t n+1 is the starting time of the disturbance sequence in the n+1th time window, P n (t) is the active power curve corresponding to the disturbance sequence in the nth time window, P s,n The corresponding initial active power in the disturbance sequence in the nth time window, Indicates that the integration operation is performed on the corresponding function curve of the nth time window.
7. The method for online verification of power grid frequency safety according to claim 5, characterized in that: The grid secondary frequency regulation climbing rate θ SFC The specific determination methods include: Statistics of the secondary frequency regulation climbing rate θ of the whole network generator set Gen_SFC,q , calculate the secondary frequency regulation climbing rate of the power grid according to the secondary frequency regulation climbing rate of the whole network generator set θ SFC , grid secondary frequency regulation ramp rate θ SFC The calculation formula is as follows: Among them, N is the number of generators participating in secondary frequency regulation in the entire network.
8. The method for online verification of power grid frequency safety according to claim 5, characterized in that: The disturbance signal area in each time window is divided into the primary frequency modulation response area or the secondary frequency modulation response area, specifically, by comparing the equivalent slope of the integrated power of the disturbance sequence in the nth time window with the secondary frequency modulation ramp rate of the power grid, if θ n ≤θ SFC , then the disturbance signal area in the nth time window is divided into the secondary frequency modulation response area of the disturbance, otherwise it is divided into the primary frequency modulation response area of the disturbance.
9. A power grid frequency safety online verification system, characterized in that: include: The disturbance signal acquisition module is used to collect the active disturbance measurement data of each station, and divide the active disturbance measurement data of each station into disturbance data of each station under the target disturbance event according to the decrease and increase of the active change in unit time, and continuously integrate the disturbance data of each station under the target disturbance event to obtain the disturbance signal of each station under the target disturbance event. Each station includes a historical wind farm, a photovoltaic power station and a substation; The extreme disturbance signal generation module is used to analyze the target disturbance events of historical wind farms, photovoltaic power stations and substations, obtain the disturbance events corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations, and superimpose the disturbance signals corresponding to the maximum disturbance amplitudes of historical wind farms, photovoltaic power stations and substations into extreme disturbance signals by linear superposition method; A serialization module is used to divide the superimposed extreme disturbance signal into n time windows according to a preset time interval; The safety verification module is used to perform online safety verification of the power grid frequency at multiple time scales in each time window.
10. The method for online verification of power grid frequency safety according to claim 9, characterized in that: The specific implementation method of the safety verification module is as follows: Integrate the frequency modulation response area of all time windows in the time series of extreme disturbance signals, considering the adjustable space P of the unit Space and the secondary frequency regulation ramp rate θ SFC , according to the frequency modulation response status of each time window, the detailed model and parameters of the current power grid are checked for power grid frequency safety based on electromechanical transient time domain simulation; For the i-th time window, determine the adjustable space P corresponding to the i-th time window of the previous round of power grid units Space,i-1 The adjustment space ΔP corresponding to the turbine unit in the i-th time window Gen,i , if P Space,i-1 ≥ΔP Gen,i When , the frequency of the i-th time window is modulated; After this round of frequency regulation, the grid frequency changes by Δf i , the remaining adjustable space of the adjustable unit is P Space_res,i , then: P Space_res,i =P Space_res,i-1 -ΔP Gen,i When the adjustable space P of the previous round of the power grid unit Space,i-1 Smaller than the adjustment space ΔP of the frequency response of this turbine unit Gen,i When , the remaining time window of the disturbance time series stops the frequency modulation response; The simulation results of frequency modulation in n time windows are superimposed to obtain the maximum frequency offset of the disturbance event under the current operation mode of the power grid: By comparing the frequency change of the maximum disturbance event under the current operation mode of the power grid with the frequency safety constraint of the power grid, if the frequency change is greater than the frequency safety constraint of the power grid, an alarm is issued to achieve frequency safety simulation verification.
11. A computing device, characterized in that: include: One or more processors, one or more memories and one or more programs, wherein the programs are stored in the memories and are configured to be executed by the processors, and when the programs are loaded into the processors, the steps of the method for online verification of power grid frequency security according to any one of claims 1 to 6 are implemented.
12. A storage medium, characterized in that: The storage medium stores a computer program, which includes program instructions. When the program instructions are executed by a processor, the processor executes the steps of the method for online verification of power grid frequency security according to any one of claims 1 to 6.