Method and system for determining contribution value of air conditioning load participating in stabilizing new energy fluctuation
Calculating the contribution value of air conditioning load through continuous grading probability scoring method solves the problem that the existing evaluation system cannot accurately evaluate air conditioning load, encourages it to participate in power regulation, and improves the safety and economics of the power system.
Patent Information
- Application Number
- CN202411002947.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-11-12
AI Technical Summary
The existing evaluation system is difficult to ensure the comprehensiveness and accuracy of the air conditioner load evaluation, which has led to the failure to fully explore and study its contribution to curbing new energy fluctuations, affecting the safety and stability of the power system.
The continuous grading probability scoring method is used to calculate the air conditioner prediction accuracy score and marginal contribution score by obtaining the actual output and predicted output of the air conditioner, the actual output and predicted output of the power plant, and determine the contribution value of the air conditioner load participating in the suppression of new energy fluctuations.
Accurately determine the contribution value of the air conditioner load, stimulate it to perform power regulation, and improve the safety and economicality of the power system.
Smart Images

Figure CN118944076A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of power systems, and in particular to a method and system for determining the contribution value of air-conditioning load in smoothing fluctuations in new energy sources. Background Art
[0002] In recent years, as the proportion of renewable energy in the power system continues to increase, the randomness, intermittency and volatility of its power generation have posed a great threat to the security and reliability of power supply. Effective control of these renewable energy sources is crucial to meeting the challenges of the power system. However, the wide distribution range and small scale of renewable energy make it difficult for the power system to manage them directly. To solve this problem, renewable energy can be aggregated into virtual power plants for management. Virtual power plants can effectively use their internal flexible and adjustable resources to offset the variability and unpredictability brought by renewable energy. Air conditioning load is one of the resources that can be effectively utilized.
[0003] At present, the technology of air conditioning load participating in virtual power plants and regulating them has been deeply explored. Scholars from Southeast University proposed an innovative air conditioning load modeling method aimed at playing a role in demand response applications, and designed an effective control algorithm to adjust air conditioning loads in response to grid demand. Scholars from the University of Kentucky proposed a novel control method that uses HVAC systems in large residential communities as energy storage and developed a set of coordinated control strategies to achieve efficient integration of distributed energy resources and promote the smooth operation of virtual power plants. This type of method effectively alleviates the peak and valley load differences of the power system by using air conditioning as a demand response resource, and explores the scheduling strategy of air conditioning loads within virtual power plants. However, the potential of using air conditioning to minimize the deviation between predicted and actual power output has not been fully explored and studied. There is a lack of a fair and reasonable evaluation system for the contribution of using the flexibility of air conditioning loads to smooth the volatility of new energy, which inhibits the enthusiasm of air conditioning loads to participate in power regulation and poses a major challenge to the safety and stability of the power system. Given that air conditioning loads have the characteristics of both output stability and power flexibility, they should be distinguished from other distributed energy sources when evaluating air conditioning loads. The existing evaluation system is no longer fully applicable and it is difficult to ensure the comprehensiveness and accuracy of air conditioning load evaluation. Summary of the invention
[0004] The present application provides a method and system for determining the contribution value of air-conditioning load in smoothing the fluctuation of new energy, so as to at least solve the technical problem that the existing evaluation system is no longer fully applicable and it is difficult to ensure the comprehensiveness and accuracy of the air-conditioning load evaluation.
[0005] The first embodiment of the present application proposes a method for determining the contribution value of air conditioning load in smoothing the fluctuation of new energy sources, the method comprising:
[0006] Obtain the actual output and predicted output of the air conditioner at each moment within the preset time;
[0007] According to the actual output of the air conditioner at each moment within the preset time and the predicted output of the air conditioner, a prediction accuracy score of the air conditioner at each moment within the preset time is determined by using a continuous graded probability scoring method;
[0008] Obtain the actual output of the power plant and the predicted output of the power plant at each moment within the preset duration, and determine the difference between the actual output of the power plant and the predicted output of the power plant at each moment within the preset duration, and determine the marginal contribution score of the air conditioner at each moment within the preset duration based on the difference between the actual output of the power plant and the predicted output of the power plant at each moment;
[0009] The contribution value of the air conditioning load at each moment in smoothing the fluctuation of new energy is determined according to the air conditioning prediction accuracy score and the air conditioning marginal contribution score.
[0010] Preferably, the calculation formula for the actual output of the air conditioner at each moment within the preset time is as follows:
[0011]
[0012] In the formula, is the actual output of air conditioner i at time t, is the cooling effect value of air conditioner i at time t, COP i is the coefficient of performance of air conditioner i.
[0013] Furthermore, the air conditioner prediction accuracy score at each moment within the preset time length is determined according to the actual air conditioner output and the predicted air conditioner output at each moment within the preset time length by using a continuous hierarchical probability scoring method, including:
[0014] Obtain the predicted distribution curve of air conditioning load within a preset time, the day-ahead market electricity price and the real-time market electricity price, and determine the difference between the actual output of the air conditioner and the predicted output of the air conditioner at each time;
[0015] Determine the continuous graded probability score corresponding to each moment according to the predicted distribution curve of the air conditioning load within the preset time and the difference between the actual output of the air conditioning at each moment and the predicted output of the air conditioning;
[0016] Determine the price difference coefficient at each time according to the difference between the actual output of the air conditioner at each time and the predicted output of the air conditioner, the day-ahead market electricity price, and the real-time market electricity price;
[0017] The air conditioning prediction accuracy score at each moment within the preset time period is determined according to the continuous graded probability score corresponding to each moment and the price difference coefficient at each moment.
[0018] Furthermore, the calculation formula for the air conditioning prediction accuracy score at each moment within the preset time period is as follows:
[0019]
[0020] In the formula, is the prediction accuracy score of air conditioner i at time t, g(e i,t ) is the price difference coefficient corresponding to air conditioner i at time t, CRPS(F i ,e i,t ) is the continuous graded probability score corresponding to air conditioner i at time t, where
[0021] F i (X) is the predicted distribution curve of air conditioner i load within the preset time period, F i is the cumulative distribution of the prediction error reported by air conditioner i, Π s is the real-time market electricity price, Π da is the day-ahead market electricity price, e i,t is the difference between the actual output and the predicted output of the i-th air conditioner at time t, p i,t is the actual output of air conditioner i at time t, is the predicted output of air conditioner i at time t.
[0022] Furthermore, the air conditioning marginal contribution score at each moment within the preset time period is determined based on the difference between the actual output of the power plant at each moment and the predicted output of the power plant, including:
[0023] Get the target temperature range, upper and lower limits of operating power, and actual output of the air conditioner at each moment;
[0024] Determining the initial power value required for adjusting the air conditioner at each moment based on the difference between the actual output of the power plant at each moment and the predicted output of the power plant;
[0025] Taking the target temperature range and the upper and lower limits of the operating power corresponding to the air conditioner at each moment as constraints, the initial power value required to be adjusted for the air conditioner at each moment is optimized to obtain the optimized power value required to be adjusted for the air conditioner at each moment;
[0026] The marginal contribution score of the air conditioner at each moment within the preset duration is determined according to the optimized power value that needs to be adjusted for the air conditioner at each moment.
[0027] Furthermore, the calculation formula of the marginal contribution score of the air conditioner at each moment within the preset time is as follows:
[0028]
[0029] In the formula, is the marginal contribution score of air conditioner i at time t, V(N) is the benefit of alliance N participating in the virtual power plant as a whole, and V(Ni) is the overall benefit of the alliance composed of N except air conditioner i, where N is a power plant forming an alliance.
[0030] Furthermore, the calculation formula of the contribution value of the air conditioning load at each moment to smoothing the fluctuation of new energy is as follows:
[0031]
[0032] In the formula, S i,t is the contribution value of air conditioning load i in smoothing the fluctuation of new energy at time t.
[0033] The second embodiment of the present application proposes a system for determining the contribution value of air conditioning load in smoothing the fluctuation of new energy, including:
[0034] An acquisition module is used to obtain the actual output of the air conditioner and the predicted output of the air conditioner at each moment within a preset time;
[0035] A first determination module is used to determine the air conditioner prediction accuracy score at each moment within the preset time length according to the actual air conditioner output and the air conditioner predicted output at each moment within the preset time length, and using a continuous hierarchical probability scoring method;
[0036] The second determination module is used to obtain the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determine the difference between the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determine the marginal contribution score of the air conditioner at each moment within the preset time based on the difference between the actual output of the power plant and the predicted output of the power plant at each moment;
[0037] The third determination module is used to determine the contribution value of the air-conditioning load at each moment in smoothing the fluctuation of new energy according to the air-conditioning prediction accuracy score and the air-conditioning marginal contribution score.
[0038] Preferably, the calculation formula for the actual output of the air conditioner at each moment within the preset time is as follows:
[0039]
[0040] In the formula, is the actual output of air conditioner i at time t, is the cooling effect value of air conditioner i at time t, COP i is the coefficient of performance of air conditioner i.
[0041] Furthermore, the first determining module includes:
[0042] The first acquisition unit is used to obtain the predicted distribution curve of the air conditioning load within a preset time, the day-ahead market electricity price and the real-time market electricity price, and determine the difference between the actual output of the air conditioner and the predicted output of the air conditioner at each time;
[0043] A first determination unit is used to determine the continuous graded probability score corresponding to each moment according to the predicted distribution curve of the air conditioning load within the preset time period and the difference between the actual output of the air conditioner at each moment and the predicted output of the air conditioner;
[0044] The second determining unit is used to determine the price difference coefficient at each moment according to the difference between the actual output of the air conditioner and the predicted output of the air conditioner at each moment, the day-ahead market electricity price, and the real-time market electricity price;
[0045] The third determination unit is used to determine the air conditioning prediction accuracy score at each moment within a preset time period according to the continuous graded probability score corresponding to each moment and the price difference coefficient at each moment.
[0046] The technical solution provided by the embodiments of the present application brings at least the following beneficial effects:
[0047] The present application proposes a method and system for determining the contribution value of air conditioning load in smoothing out new energy fluctuations, wherein the method includes: obtaining the actual output of air conditioning and the predicted output of air conditioning at each moment within a preset time; according to the actual output of air conditioning and the predicted output of air conditioning at each moment within the preset time, and using a continuous graded probability scoring method to determine the air conditioning prediction accuracy score at each moment within the preset time; obtaining the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determining the difference between the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determining the air conditioning marginal contribution score at each moment within the preset time based on the difference between the actual output of the power plant and the predicted output of the power plant at each moment; determining the contribution value of the air conditioning load in smoothing out new energy fluctuations at each moment according to the air conditioning prediction accuracy score and the air conditioning marginal contribution score. The technical solution proposed in the present application can accurately determine the contribution value of the air conditioning load in smoothing out new energy fluctuations, thereby encouraging the air conditioning load to perform power regulation and improve the safety and economy of power system operation.
[0048] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0049] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0050] Figure 1 A flow chart of a method for determining a contribution value of air conditioning load to smoothing new energy fluctuations provided according to an embodiment of the present application;
[0051] Figure 2 A structural diagram of a system for determining a contribution value of air conditioning load to smoothing new energy fluctuations provided according to an embodiment of the present application;
[0052] Figure 3 It is a structural diagram of a first determination module provided according to an embodiment of the present application. DETAILED DESCRIPTION
[0053] Embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application.
[0054] The present application proposes a method and system for determining the contribution value of air conditioning load in smoothing out new energy fluctuations, wherein the method includes: obtaining the actual output of the air conditioner and the predicted output of the air conditioner at each moment within a preset time; determining the air conditioning prediction accuracy score at each moment within the preset time according to the actual output of the air conditioner and the predicted output of the air conditioner at each moment within the preset time by using a continuous graded probability scoring method; obtaining the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determining the difference between the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determining the air conditioning marginal contribution score at each moment within the preset time based on the difference between the actual output of the power plant and the predicted output of the power plant at each moment; determining the contribution value of the air conditioning load in smoothing out new energy fluctuations at each moment according to the air conditioning prediction accuracy score and the air conditioning marginal contribution score. The technical solution proposed in the present application can accurately determine the contribution value of the air conditioning load in smoothing out new energy fluctuations, thereby encouraging the air conditioning load to perform power regulation and improve the safety and economy of power system operation.
[0055] The following describes a method and system for determining the contribution value of air conditioning load in smoothing new energy fluctuations in an embodiment of the present application with reference to the accompanying drawings.
[0056] Embodiment 1
[0057] Figure 1 A flow chart of a method for determining the contribution value of air conditioning load to smoothing new energy fluctuations provided according to an embodiment of the present application, such as Figure 1 As shown, the method includes:
[0058] Step 1: Obtain the actual output and predicted output of the air conditioner at each time within the preset time.
[0059] In the embodiment of the present disclosure, the calculation formula for the actual output of the air conditioner at each moment within the preset time period is as follows:
[0060]
[0061] In the formula, is the actual output of air conditioner i at time t, is the cooling effect value of air conditioner i at time t, COP i is the coefficient of performance of air conditioner i.
[0062] It should be noted that before determining the contribution of air conditioning load to smoothing the fluctuation of new energy, key data of all buildings in the area, including heat capacity, thermal response characteristics, indoor and outdoor temperature, indoor heat load and cooling effect of air conditioning system, are obtained to achieve precise control of indoor temperature. The indoor temperature at the current time point is estimated by analyzing the indoor temperature, indoor heat load, cooling performance of air conditioner and outdoor temperature at the previous time point; the effective load of air conditioner is calculated based on its cooling capacity and performance coefficient; the indoor temperature and air conditioning power are maintained within a given reasonable range to achieve efficient use of energy and environmental comfort.
[0063] Each building contains only one air conditioning system, and each air conditioning system is regarded as a user in a virtual power plant. Collect the thermal characteristic data, temperature and heat load of the building, and calculate the current indoor temperature and air conditioning power: Let t be the time point for evaluation, and let the heat capacity of the building be C i , whose thermal response is R i , indoor temperature and the outdoor temperature is The indoor heat load is and the cooling effect provided by the air conditioner is The indoor temperature at time t can be calculated according to the following formula:
[0064]
[0065] In the formula, α i =1-Δt / (R i C i ),β i =Δt / C i ,γ i =Δt / (R i C i ), I is the virtual power plant, i.e., the set of all air conditioning loads in the power plant;
[0066] Output power of air conditioner It can be calculated as follows:
[0067]
[0068] It should be noted that the indoor temperature should be kept within a reasonable range to maintain a comfortable temperature, and the air conditioner has power limits and needs to meet the following constraints:
[0069]
[0070] Among them, θ i,low and θ i,high are the minimum and maximum temperature limits of building i, respectively, i,high is the maximum power of air conditioner i.
[0071] Step 2: According to the actual output of the air conditioner at each moment within the preset time and the predicted output of the air conditioner, a continuous graded probability scoring method is used to determine the air conditioner prediction accuracy score at each moment within the preset time.
[0072] In the embodiment of the present disclosure, step 2 specifically includes:
[0073] Step 2-1: Obtain the forecast distribution curve of the air conditioning load within a preset time period, the day-ahead market electricity price and the real-time market electricity price, and determine the difference between the actual output of the air conditioner and the forecast output of the air conditioner at each time;
[0074] Step 2-2: Determine the continuous graded probability score corresponding to each moment according to the predicted distribution curve of the air conditioning load within the preset time period and the difference between the actual output of the air conditioner at each moment and the predicted output of the air conditioner;
[0075] Step 2-3: determining the price difference coefficient at each time according to the difference between the actual output of the air conditioner at each time and the predicted output of the air conditioner, the day-ahead market electricity price, and the real-time market electricity price;
[0076] Step 2-4: Determine the air conditioning prediction accuracy score at each moment within the preset time period according to the continuous graded probability score corresponding to each moment and the price difference coefficient at each moment.
[0077] The calculation formula for the air conditioning prediction accuracy score at each moment within the preset time period is as follows:
[0078]
[0079] In the formula, is the prediction accuracy score of air conditioner i at time t, g(e i,t ) is the price difference coefficient corresponding to air conditioner i at time t, CRPS(F i ,e i,t ) is the continuous graded probability score corresponding to air conditioner i at time t, where
[0080] F i (X) is the predicted distribution curve of air conditioner i load within the preset time period, F i is the cumulative distribution of the prediction error reported by air conditioner i, Π s is the real-time market electricity price, Π dais the day-ahead market electricity price, e i,t is the difference between the actual output and the predicted output of the i-th air conditioner at time t, p i,t is the actual output of air conditioner i at time t, is the predicted output of air conditioner i at time t.
[0081] It should be noted that the continuous ranked probability scoring method CRPS (Continuous Ranked Probability Score) can be used to quantify the performance of distributed energy output forecasting, which can effectively evaluate the output forecasting level of distributed energy and motivate them to form an alliance. The distributed energy can be new energy, air conditioning, etc.
[0082] For each air-conditioning user i, i = 1, 2, ..., n, let the predicted distribution curve be F i (x), the actual and predicted (bid) outputs are Define its continuous level probability score as:
[0083]
[0084] in, Function in When 1 is taken, When 0.
[0085] Due to the price difference in the deviation settlement market, the prediction accuracy score of distributed energy is calculated by the following formula
[0086]
[0087]
[0088] Among them, π da is the electricity price in the day-ahead market, π s is the real-time market electricity price, I ei,t≥0 Function in e i,t ≥0, take 1, in e i,t When <0, take 0.
[0089] Step 3: Obtain the actual output of the power plant and the predicted output of the power plant at each moment within the preset duration, and determine the difference between the actual output of the power plant and the predicted output of the power plant at each moment within the preset duration, and determine the air conditioning marginal contribution score at each moment within the preset duration based on the difference between the actual output of the power plant and the predicted output of the power plant at each moment.
[0090] In the embodiment of the present disclosure, the step of determining the marginal contribution score of the air conditioner at each moment within the preset time period based on the difference between the actual output of the power plant at each moment and the predicted output of the power plant specifically includes:
[0091] Get the target temperature range, upper and lower limits of operating power, and actual output of the air conditioner at each moment;
[0092] Determining the initial power value required for adjusting the air conditioner at each moment based on the difference between the actual output of the power plant at each moment and the predicted output of the power plant;
[0093] Taking the target temperature range and the upper and lower limits of the operating power corresponding to the air conditioner at each moment as constraints, the initial power value required to be adjusted for the air conditioner at each moment is optimized to obtain the optimized power value required to be adjusted for the air conditioner at each moment;
[0094] Among them, the target temperature range constraint corresponding to the air conditioner can be The upper and lower limits of the operating power can be:
[0095] The marginal contribution score of the air conditioner at each moment within the preset duration is determined according to the optimized power value that needs to be adjusted for the air conditioner at each moment.
[0096] The calculation formula of the marginal contribution score of the air conditioner at each moment within the preset time is as follows:
[0097]
[0098] In the formula, is the marginal contribution score of air conditioner i at time t, V(N) is the benefit of alliance N participating in the virtual power plant as a whole, and V(Ni) is the overall benefit of the alliance composed of N except air conditioner i, where N is a power plant forming an alliance.
[0099] It should be noted that the air conditioners are optimized and scheduled according to the power consumption and target temperature range settings of the air-conditioning system, combined with the upper and lower limits of the operating power, so as to minimize the temperature changes and costs caused by changes in the air-conditioning power, and obtain the power that needs to be adjusted for each air conditioner. The difference between the predicted output and the actual output in the virtual power plant is smoothed based on the power that needs to be adjusted, and the margin for smoothing the difference between the predicted output and the actual output in the virtual power plant is determined. The marginal contribution score of the air conditioner is calculated based on the margin.
[0100] The entire virtual power plant forms an alliance N, and the profit equation is v(), where v(i) represents the profit of member i, i.e. air conditioner i, participating in the electricity market alone, which is calculated by multiplying the difference between the marginal electricity price and the power generation cost by the power generation, and v(N) represents the profit of alliance N as a whole participating in the virtual power plant. According to the definition of marginal contribution, the marginal contribution score of air conditioner It can be calculated by the following formula:
[0101]
[0102] Where v(Ni) represents the overall benefit of the alliance in N excluding member i.
[0103] Step 4: Determine the contribution value of the air conditioning load at each moment in smoothing the fluctuation of new energy according to the air conditioning prediction accuracy score and the air conditioning marginal contribution score.
[0104] In the embodiment of the present disclosure, the calculation formula of the contribution value of the air conditioning load at each moment to smoothing the fluctuation of new energy is as follows:
[0105]
[0106] In the formula, S i,t is the contribution value of air conditioning load i in smoothing the fluctuation of new energy at time t.
[0107] It should be noted that by combining the forecast accuracy score and marginal contribution score of air conditioning load, we comprehensively evaluate the market contribution of air conditioning in smoothing the fluctuation of new energy. While considering the accuracy of the forecast, we also consider the actual role of air conditioning in the balance of the power system, providing quantitative indicators for the stable operation of the power market and the effective integration of new energy.
[0108] In summary, the method for determining the contribution value of air-conditioning load in smoothing the fluctuation of renewable energy proposed in this embodiment makes more flexible use of the adjustability of air-conditioning output power given by building thermal inertia, and ensures that the temperature in the building is comfortable and the air-conditioning power is within the constraint range. In addition, this method can evaluate the contribution of air-conditioning load in smoothing the fluctuation of renewable energy from multiple dimensions. The application of this method can motivate air-conditioning load to adjust power, thereby improving the safety and economy of power system operation, which is conducive to improving the operating efficiency of virtual power plants. It has important practical significance and good application prospects.
[0109] Embodiment 2
[0110] Figure 2 This is a structural diagram of a system for determining the contribution value of air conditioning load to smoothing new energy fluctuations according to an embodiment of the present application, such as Figure 2 As shown, the system comprises:
[0111] An acquisition module 100 is used to acquire the actual output of the air conditioner and the predicted output of the air conditioner at each moment within a preset time period;
[0112] The calculation formula for the actual output of the air conditioner at each moment within the preset time is as follows:
[0113]
[0114] In the formula, is the actual output of air conditioner i at time t, is the cooling effect value of air conditioner i at time t, COP iis the coefficient of performance of air conditioner i.
[0115] The first determination module 200 is used to determine the air conditioner prediction accuracy score at each moment within the preset time length according to the actual air conditioner output and the air conditioner predicted output at each moment within the preset time length, and using a continuous hierarchical probability scoring method;
[0116] The second determination module 300 is used to obtain the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determine the difference between the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determine the marginal contribution score of the air conditioner at each moment within the preset time based on the difference between the actual output of the power plant and the predicted output of the power plant at each moment;
[0117] The third determination module 400 is used to determine the contribution value of the air conditioning load at each moment in smoothing the fluctuation of new energy according to the air conditioning prediction accuracy score and the air conditioning marginal contribution score.
[0118] The calculation formula for the contribution value of the air conditioning load at each moment to smoothing the fluctuation of new energy is as follows:
[0119]
[0120] In the formula, S i,t is the contribution value of air conditioning load i in smoothing the fluctuation of new energy at time t.
[0121] In the embodiments of the present disclosure, Figure 3 As shown, the first determination module 200 includes:
[0122] The first acquisition unit 201 is used to obtain the predicted distribution curve of the air conditioning load within a preset time, the day-ahead market electricity price and the real-time market electricity price, and determine the difference between the actual output of the air conditioner and the predicted output of the air conditioner at each time;
[0123] The first determination unit 202 is used to determine the continuous graded probability score corresponding to each moment according to the predicted distribution curve of the air conditioning load within the preset time period and the difference between the actual output of the air conditioner at each moment and the predicted output of the air conditioner;
[0124] The second determining unit 203 is used to determine the price difference coefficient at each moment according to the difference between the actual output of the air conditioner and the predicted output of the air conditioner at each moment, the day-ahead market electricity price, and the real-time market electricity price;
[0125] The third determining unit 204 is used to determine the air conditioning prediction accuracy score at each moment within a preset time period according to the continuous hierarchical probability score corresponding to each moment and the price difference coefficient at each moment.
[0126] The calculation formula for the air conditioning prediction accuracy score at each moment within the preset time period is as follows:
[0127]
[0128] In the formula, is the prediction accuracy score of air conditioner i at time t, g(e i,t ) is the price difference coefficient corresponding to air conditioner i at time t, CRPS(F i ,e i,t ) is the continuous graded probability score corresponding to air conditioner i at time t, where
[0129] F i (X) is the predicted distribution curve of air conditioner i load within the preset time period, F i is the cumulative distribution of the prediction error reported by air conditioner i, Π s is the real-time market electricity price, Π da is the day-ahead market electricity price, e i,t is the difference between the actual output and the predicted output of the i-th air conditioner at time t, p i,t is the actual output of air conditioner i at time t, is the predicted output of air conditioner i at time t.
[0130] In the embodiment of the present disclosure, the second determining module 300 is further configured to:
[0131] Get the target temperature range, upper and lower limits of operating power, and actual output of the air conditioner at each moment;
[0132] Determining the initial power value required for adjusting the air conditioner at each moment based on the difference between the actual output of the power plant at each moment and the predicted output of the power plant;
[0133] Taking the target temperature range and the upper and lower limits of the operating power corresponding to the air conditioner at each moment as constraints, the initial power value required to be adjusted for the air conditioner at each moment is optimized to obtain the optimized power value required to be adjusted for the air conditioner at each moment;
[0134] The marginal contribution score of the air conditioner at each moment within the preset duration is determined according to the optimized power value that needs to be adjusted for the air conditioner at each moment.
[0135] The calculation formula of the marginal contribution score of the air conditioner at each moment within the preset time is as follows:
[0136]
[0137] In the formula, is the marginal contribution score of air conditioner i at time t, V(N) is the benefit of alliance N participating in the virtual power plant as a whole, and V(Ni) is the overall benefit of the alliance composed of N except air conditioner i, where N is a power plant forming an alliance.
[0138] To sum up, the contribution value determination system of the air-conditioning load in smoothing the fluctuation of renewable energy proposed in this embodiment can accurately determine the contribution value of the air-conditioning load in smoothing the fluctuation of renewable energy, thereby stimulating the air-conditioning load to perform power regulation and improving the safety and economy of the power system operation.
[0139] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0140] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, fragment or portion of code comprising one or more executable instructions for implementing the steps of a custom logical function or process, and the scope of the preferred embodiments of the present application includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in the reverse order depending on the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present application belong.
[0141] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in this field can change, modify, replace and modify the above embodiments within the scope of the present application.
Claims
1. A method for determining the contribution value of air conditioning load in smoothing the fluctuation of new energy, characterized in that: The method comprises: Obtain the actual output and predicted output of the air conditioner at each moment within the preset time; According to the actual output of the air conditioner at each moment within the preset time and the predicted output of the air conditioner, a prediction accuracy score of the air conditioner at each moment within the preset time is determined by using a continuous graded probability scoring method; Obtain the actual output of the power plant and the predicted output of the power plant at each moment within the preset duration, and determine the difference between the actual output of the power plant and the predicted output of the power plant at each moment within the preset duration, and determine the marginal contribution score of the air conditioner at each moment within the preset duration based on the difference between the actual output of the power plant and the predicted output of the power plant at each moment; The contribution value of the air conditioning load at each moment in smoothing the fluctuation of new energy is determined according to the air conditioning prediction accuracy score and the air conditioning marginal contribution score.
2. The method according to claim 1, characterized in that The calculation formula for the actual output of the air conditioner at each moment within the preset time is as follows: In the formula, is the actual output of air conditioner i at time t, is the cooling effect value of air conditioner i at time t, COP i is the coefficient of performance of air conditioner i.
3. The method according to claim 2, characterized in that The method of determining the air conditioner prediction accuracy score at each moment within the preset time length according to the actual air conditioner output and the air conditioner predicted output at each moment within the preset time length and using a continuous hierarchical probability scoring method includes: Obtain the predicted distribution curve of air conditioning load within a preset time, the day-ahead market electricity price and the real-time market electricity price, and determine the difference between the actual output of the air conditioner and the predicted output of the air conditioner at each time; Determine the continuous graded probability score corresponding to each moment according to the predicted distribution curve of the air conditioning load within the preset time and the difference between the actual output of the air conditioning at each moment and the predicted output of the air conditioning; Determine the price difference coefficient at each time according to the difference between the actual output of the air conditioner at each time and the predicted output of the air conditioner, the day-ahead market electricity price, and the real-time market electricity price; The air conditioning prediction accuracy score at each moment within the preset time period is determined according to the continuous graded probability score corresponding to each moment and the price difference coefficient at each moment.
4. The method according to claim 3, characterized in that The calculation formula of the air conditioning prediction accuracy score at each moment within the preset time period is as follows: In the formula, is the prediction accuracy score of air conditioner i at time t, g(e i,t ) is the price difference coefficient corresponding to air conditioner i at time t, CRPS(F i ,e i,t ) is the continuous graded probability score corresponding to air conditioner i at time t, where F i (X) is the predicted distribution curve of air conditioner i load within the preset time period, F i is the cumulative distribution of the prediction error reported by air conditioner i, Π s is the real-time market electricity price, Π da is the day-ahead market electricity price, e i,t is the difference between the actual output and the predicted output of the i-th air conditioner at time t, p i,t is the actual output of air conditioner i at time t, is the predicted output of air conditioner i at time t.
5. The method according to claim 4, characterized in that The determining of the air conditioning marginal contribution score at each moment within the preset time period based on the difference between the actual output of the power plant at each moment and the predicted output of the power plant includes: Get the target temperature range, upper and lower limits of operating power, and actual output of the air conditioner at each moment; Determining the initial power value required for adjusting the air conditioner at each moment based on the difference between the actual output of the power plant at each moment and the predicted output of the power plant; Taking the target temperature range and the upper and lower limits of the operating power corresponding to the air conditioner at each moment as constraints, the initial power value required to be adjusted for the air conditioner at each moment is optimized to obtain the optimized power value required to be adjusted for the air conditioner at each moment; The marginal contribution score of the air conditioner at each moment within the preset duration is determined according to the optimized power value that needs to be adjusted for the air conditioner at each moment.
6. The method according to claim 5, characterized in that The calculation formula of the air conditioning marginal contribution score at each moment within the preset time is as follows: In the formula, is the marginal contribution score of air conditioner i at time t, V(N) is the benefit of alliance N participating in the virtual power plant as a whole, and V(Ni) is the overall benefit of the alliance composed of N except air conditioner i, where N is a power plant forming an alliance.
7. The method according to claim 6, characterized in that The calculation formula for the contribution value of the air conditioning load at each moment to smoothing the fluctuation of new energy is as follows: In the formula, S i,t is the contribution value of air conditioning load i in smoothing the fluctuation of new energy at time t.
8. A system for determining the contribution value of air conditioning load in smoothing the fluctuation of new energy, characterized in that: The system comprises: An acquisition module is used to obtain the actual output of the air conditioner and the predicted output of the air conditioner at each moment within a preset time; A first determination module is used to determine the air conditioner prediction accuracy score at each moment within the preset time length according to the actual air conditioner output and the air conditioner predicted output at each moment within the preset time length, and using a continuous hierarchical probability scoring method; The second determination module is used to obtain the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determine the difference between the actual output of the power plant and the predicted output of the power plant at each moment within the preset time, and determine the marginal contribution score of the air conditioner at each moment within the preset time based on the difference between the actual output of the power plant and the predicted output of the power plant at each moment; The third determination module is used to determine the contribution value of the air-conditioning load at each moment in smoothing the fluctuation of new energy according to the air-conditioning prediction accuracy score and the air-conditioning marginal contribution score.
9. The system according to claim 8, characterized in that The calculation formula for the actual output of the air conditioner at each moment within the preset time is as follows: In the formula, is the actual output of air conditioner i at time t, is the cooling effect value of air conditioner i at time t, COP i is the coefficient of performance of air conditioner i.
10. The system according to claim 9, characterized in that The first determining module includes: The first acquisition unit is used to obtain the predicted distribution curve of the air conditioning load within a preset time, the day-ahead market electricity price and the real-time market electricity price, and determine the difference between the actual output of the air conditioner and the predicted output of the air conditioner at each time; A first determination unit is used to determine the continuous graded probability score corresponding to each moment according to the predicted distribution curve of the air conditioning load within the preset time period and the difference between the actual output of the air conditioner at each moment and the predicted output of the air conditioner; The second determining unit is used to determine the price difference coefficient at each moment according to the difference between the actual output of the air conditioner and the predicted output of the air conditioner at each moment, the day-ahead market electricity price, and the real-time market electricity price; The third determination unit is used to determine the air conditioning prediction accuracy score at each moment within a preset time period according to the continuous graded probability score corresponding to each moment and the price difference coefficient at each moment.