Cabin travelling crane full-stroke overhaul channel and overhaul method thereof
By using an elliptical ring plate and lubricating brake mechanism in the cabin driving maintenance channel, the problem of lag in the roller operation is solved, the smooth operation of the rollers in the maintenance channel is achieved, and the maintenance efficiency and safety are improved.
Patent Information
- Application Number
- CN202410999111.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-11-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The traditional cabin driving maintenance channel is in a humid environment for a long time, causing the roller operation to stutter, affecting the maintenance efficiency and safety.
A full-travel maintenance channel for cabin driving is designed, using an elliptical ring plate, an adjustment cylinder, a limit ring plate, a placement platform, a baffle and a lubricating brake mechanism. Through the combination of lubricating fluid and adsorption sponge, the rollers can be ensured to run smoothly, and Provides regular lubrication and replenishment mechanisms to reduce rust ash accumulation.
It effectively reduces the lag in the roller operation in the maintenance channel, ensures the safety maintenance of the cabin by staff, and improves maintenance efficiency and safety.
Smart Images

Figure CN118954293A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of maintenance passages, in particular to a full-travel maintenance passage for a cabin crane and a maintenance method thereof. Background Art
[0002] The engine room crane, also known as the ship mark engine room crane, is a device specially used for cargo logistics inside ships. It improves the efficiency of cargo unloading and ensures safety, thereby shortening cargo loading and unloading time, reducing the impact on the environment and the ship, and providing strong support for the ship's cargo loading and unloading work.
[0003] Since the engine room crane is a heavy industrial machinery, the staff needs to regularly inspect and maintain the engine room crane. Usually, the staff is transported to the gantry crane of the engine room crane through the maintenance passage to inspect and maintain the engine room crane.
[0004] For example, the national patent publication number CN115675791A discloses a special hanging basket for repairing the engine room crane, including a mobile trolley, a hanging basket fixedly connected below the mobile trolley, the mobile trolley including a left and a right frame, the left and right frames are connected and fixed by a connecting shaft, the left and right frames are respectively provided with symmetrical rollers, the rollers are respectively located on both sides of the top surface of the engine room crane I-beam, the bottom surface of the I-beam is provided with a toothed track, a reduction device is fixedly connected to the outer side of the right frame, the reduction device is a worm gear reducer, including a hand chain wheel and an iron chain sleeved on the outer peripheral surface of the hand chain wheel, the hand chain wheel is fixedly connected to the input shaft end of the reduction device, the output shaft of the reduction device is sleeved with a transmission gear, and the transmission gear is meshed with the toothed track. The hanging basket can move at a uniform speed along the I-beam, and can be braked to stop at any time. When stopped, the position is locked and it will not be displaced due to the shaking of the ship, making the maintenance work safer.
[0005] However, the traditional engine room crane is placed on the sea surface for a long time during shipping. The sea breeze contains high water vapor, which makes the engine room crane in a humid environment for a long time, making it easy to rust in the maintenance channel, causing the rollers in the channel to jam and affecting the staff's maintenance of the engine room crane. Therefore, we need a mechanism that can ensure the smooth operation of the rollers in the maintenance channel. Summary of the invention
[0006] The object of the present invention is to provide a full-travel maintenance passage for a cabin vehicle and a maintenance method thereof, so as to solve the problems raised in the above-mentioned background technology.
[0007] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: A full-stroke maintenance passage for a cabin crane comprises a gantry hanger, a bottom outer wall of the gantry hanger is provided with an maintenance passage, a bottom outer wall of the gantry hanger is provided with a load-bearing hanging basket, both sides of the top outer wall of the load-bearing hanging basket are fixedly connected with pulley blocks, the gantry hanger is rotatably connected with a steel cable through the pulley blocks, a connecting holder is provided with a connecting holder on the bottom outer wall, an electric-controlled winding roller is fixedly installed on the inner wall of the connecting holder, the outer wall of one end of the steel cable away from the gantry hanger is fixedly wound around the outer wall position of the electric-controlled winding roller, a connecting hinge is fixedly installed on the top inner wall of the connecting holder, the connecting holder is fixedly connected with a supporting adjustment plate through a connecting hinge, the outer wall of one end of the supporting adjustment plate away from the connecting holder is rotatably connected with a load-bearing shaft rod, the outer walls of both ends of the load-bearing shaft rod are fixedly connected with elliptical ring plates, the outer wall of the elliptical ring plate is movably connected to the inner wall of the maintenance passage, and the outer wall of the load-bearing shaft rod is provided with a regular lubrication mechanism and a replenishing mechanism.
[0008] Preferably, the periodic lubrication mechanism includes an elliptical ring plate, an adjusting cylinder, a limiting ring plate, a placing platform and a baffle, the inner wall of the elliptical ring plate is movably connected to the outer wall of the load-bearing shaft, the bottom outer wall of the adjusting cylinder is fixedly connected to the top outer wall of the elliptical ring plate, the inner wall of the limiting ring plate is rotatably connected to the outer wall of the load-bearing shaft, one side of the bottom outer wall of the placing platform is fixedly connected to the top outer wall of the limiting ring plate, the bottom outer wall of the baffle is fixedly connected to the side of the top outer wall of the placing platform away from the limiting ring plate, the outer walls at both ends of the adjusting cylinder are movably connected to the outer walls of one side of the two baffles respectively, the bottom outer walls at both ends of the adjusting cylinder are movably connected to the top outer walls of the two placing platforms respectively, a connecting opening is provided on the bottom outer wall of the baffle, and a lubrication braking mechanism is arranged inside the adjusting cylinder.
[0009] Preferably, the lubricating brake mechanism includes a triangular pressure block, a mounting plate, a connecting spring and a lubricating cotton sheet, the adjusting cylinder is provided with two ends connected, and movable grooves connected to the adjusting cylinder are provided on both sides of the top outer wall, the outer wall of one end of the triangular pressure block is fixedly connected to the top of the outer wall of one side of the baffle, the outer wall of the triangular pressure block is movably connected to the inner wall of the movable groove, the outer wall of the mounting plate is fixedly connected to the inner wall, the two connecting springs are respectively fixedly connected to the outer walls of both sides of the mounting plate, the outer wall of the connecting spring at one end away from the mounting plate is fixedly connected to the outer wall of one side of the lubricating cotton sheet, the outer walls around the lubricating cotton sheet are movably connected to the inner wall, and the top outer wall of the lubricating cotton sheet is movably connected to the inclined side outer wall of the triangular pressure block.
[0010] Preferably, the bottom outer wall of the limiting ring plate is fixedly connected to the limiting retaining frame, the bottom outer wall of the elliptical ring plate is fixedly connected to an adjusting card plate, the two ends of the outer wall of the adjusting card plate are respectively slidably connected to the inner walls of the two limiting retaining frames, the bottom inner wall of the limiting retaining frame is fixedly connected to a resist spring, the top outer wall of the resist spring is fixedly connected to the bottom outer wall of the adjusting card plate, one side outer wall of the support adjustment plate is movably connected to one side of the top outer wall of the adjusting card plate, one side outer walls of the two support adjustment plates are fixedly connected to a retaining hinge, and the two support adjustment plates are fixedly connected to the same pressure rod through the retaining hinge.
[0011] Preferably, one side outer wall of the limit retaining frame and the outer wall of the load-bearing shaft are fixedly connected with a wheel disc, and the two wheel discs are rotatably connected with the same connecting belt. An adsorption sponge is provided on one side outer wall of the wheel disc located at the limit retaining frame, and the outer wall of the adsorption sponge is movably connected to the bottom outer wall of the inspection channel.
[0012] Preferably, a connecting rod is fixedly connected to the outer wall of one side of the wheel disc located at the limit retaining frame, and the outer walls around the connecting rod and the inner wall of the adsorption sponge are fixedly connected with Velcro, and the adsorption sponge is adhered to the connecting rod by the Velcro, and a plurality of overflow holes connected to the inner cavity are opened on the bottom outer wall of the inspection channel.
[0013] Preferably, the replenishing mechanism includes a lubricating oil filling box, a connecting channel, a slider, a return spring, a first magnet and a second magnet. The lubricating oil filling box is fixedly installed inside the gantry hanger, the top outer wall of the connecting channel is fixedly connected to the output end of the lubricating oil filling box, the outer wall of the slider is movably connected to the inner wall of the connecting channel, the top outer wall of the return spring is fixedly connected to the top inner wall of the connecting channel, the bottom outer wall of the return spring is fixedly connected to the top outer wall of the slider, the top outer wall of the slider is provided with a flow hole connected to the outer walls on both sides, the top outer wall of the first magnet is fixedly connected to the bottom outer wall of the slider, the bottom outer wall of the second magnet is fixedly connected to the top outer wall of the mounting plate, the top outer wall of the adjusting cylinder is provided with a through groove connected to the first magnet, and the first magnet is magnetically connected to the second magnet via the through groove.
[0014] Preferably, a maintenance method for a full-stroke maintenance passage of a cabin crane comprises any one of the full-stroke maintenance passages of a cabin crane described in the above invention, and the maintenance method comprises: Step 1: The staff enters the load-bearing hanging basket and lifts the load-bearing hanging basket to the bottom of the gantry hanger through the electric-controlled winding roller, so that the staff can inspect and repair the gantry hanger; Step 2: Use the moving roller to slide in the maintenance channel to drive the staff to move horizontally outside the gantry hanger; Step 3: The staff regularly adds lubricating oil to the lubricating oil filling box and replaces the adsorption sponge.
[0015] Compared with the prior art, the present invention has the following beneficial effects: In the present invention, a worker enters the load-bearing hanging basket and lifts the load-bearing hanging basket to the bottom of the gantry hanger through the electrically controlled winding roller, and then uses the moving roller to slide in the maintenance channel to drive the worker to move laterally outside the gantry hanger, so that the worker can inspect the gantry hanger conveniently. In the present invention, the special shape of the elliptical ring plate is utilized to enable the elliptical ring plate to slide a certain distance on the outer wall of the load-bearing shaft. When the elliptical ring plate drives the adjusting cylinder to move downward, the adjusting cylinder will be placed on the placement platform. At this time, the outer walls at both ends of the adjusting cylinder lose the resistance of the baffle plate, and the lubrication device arranged inside the adjusting cylinder can lubricate the moving roller through the connecting opening, and the lubricating liquid is driven to the full-platform maintenance channel through the rolling of the moving roller. The device reduces the running jam of the moving roller in the maintenance channel, ensures the smooth operation of the elliptical ring plate, and avoids affecting the maintenance of the cabin driving by the worker. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the overall structure of the present invention.
[0017] Figure 2 It is a schematic diagram of the upper right structure of the present invention.
[0018] Figure 3 It is a schematic diagram of the lower left structure of the present invention.
[0019] Figure 4 It is a front view structural schematic diagram of the present invention.
[0020] Figure 5 It is a schematic diagram of the internal structure of the inspection channel of the present invention.
[0021] Figure 6 for Figure 5 A schematic diagram of the enlarged structure at point A in the middle.
[0022] Figure 7 It is a schematic diagram of the structure of the load-bearing hanging basket of the present invention.
[0023] Figure 8 It is a schematic diagram of the side structure of the load-bearing hanging basket of the present invention.
[0024] Fig. 9 for Figure 8 A magnified schematic diagram of the structure at point B in the middle.
[0025] Fig.10 It is a schematic diagram of the internal structure of the connection retainer of the present invention.
[0026] Fig.11It is a schematic diagram of the supplementary mechanism structure of the present invention.
[0027] Fig.12 for Fig.11 Enlarged schematic diagram of the structure at C in the middle.
[0028] Fig.13 It is a schematic diagram of the internal structure of the connecting channel of the present invention.
[0029] Fig.14 It is a schematic diagram of the structure of the periodic lubrication mechanism of the present invention.
[0030] Fig.15 for Fig.14 Enlarged schematic diagram of the structure at C in the middle.
[0031] In the figure: 1. gantry hanger; 2. maintenance channel; 3. load-bearing hanging basket; 4. pulley block; 5. steel cable; 6. connecting cage; 7. electric control winding roller; 8. support adjustment plate; 9. pressure rod; 10. holding hinge; 11. moving roller; 12. load-bearing shaft rod; 13. elliptical ring plate; 14. adjustment cylinder; 15. limit ring plate; 16. placement platform; 17. baffle; 18. connecting opening; 19. triangular pressure block; 20. movable groove; 21. limit cage; 22. adjustment card plate; 23. resist spring; 24. wheel; 25. connecting belt; 26. adsorption sponge; 27. Velcro; 28. connecting rod; 29. mounting plate; 30. connecting spring; 31. lubricating cotton sheet; 32. lubricating oil filling box; 33. connecting channel; 34. slider; 35. reset spring; 36. first magnet; 37. second magnet. DETAILED DESCRIPTION
[0032] In order to make the purpose and technical solution of the present invention clearly and completely described, and the advantages more clearly understood, the embodiments of the present invention are further described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are part of the embodiments of the present invention, rather than all of the embodiments, and are only used to explain the embodiments of the present invention, and are not used to limit the embodiments of the present invention. All other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] Embodiment 1 See also Figure 1-Figure 15The present invention provides a technical solution: a full-stroke maintenance channel for a cabin crane and a maintenance method thereof, comprising a gantry hanger 1, a maintenance channel 2 is opened on the bottom outer wall of the gantry hanger 1, a load-bearing hanging basket 3 is arranged on the bottom outer wall of the gantry hanger 1, pulley blocks 4 are fixedly connected to both sides of the top outer wall of the load-bearing hanging basket 3, the gantry hanger 1 is rotatably connected to a steel cable 5 through the pulley blocks 4, a connecting holder 6 is arranged on the bottom outer wall of the gantry hanger 1, an electric-controlled winding roller 7 is fixedly installed on the inner wall of the connecting holder 6, the outer wall of one end of the steel cable 5 away from the gantry hanger 1 is fixedly wound around the outer wall position of the electric-controlled winding roller 7, a connecting hinge is fixedly installed on the top inner wall of the connecting holder 6, the connecting holder 6 is fixedly connected to a supporting adjustment plate 8 through a connecting hinge, the outer wall of the end of the supporting adjustment plate 8 away from the connecting holder 6 is rotatably connected to a load-bearing shaft rod 12, the outer walls of both ends of the load-bearing shaft rod 12 are fixedly connected to elliptical ring plates 13, the outer wall of the elliptical ring plate 13 is connected to the inner wall of the maintenance channel 2 The wall is movably connected, and the outer wall of the load-bearing shaft rod 12 is provided with a regular lubrication mechanism and a replenishing mechanism. The regular lubrication mechanism includes an elliptical ring plate 13, an adjusting cylinder 14, a limiting ring plate 15, a placement platform 16 and a baffle 17. The inner wall of the elliptical ring plate 13 is movably connected to the outer wall of the load-bearing shaft rod 12, the bottom outer wall of the adjusting cylinder 14 is fixedly connected to the top outer wall of the elliptical ring plate 13, the inner wall of the limiting ring plate 15 is rotatably connected to the outer wall of the load-bearing shaft rod 12, one side of the bottom outer wall of the placement platform 16 is fixedly connected to the top outer wall of the limiting ring plate 15, the bottom outer wall of the baffle 17 is fixedly connected to the side of the top outer wall of the placement platform 16 away from the limiting ring plate 15, the outer walls at both ends of the adjusting cylinder 14 are respectively movably connected to the outer walls of one side of the two baffles 17, the bottom outer walls at both ends of the adjusting cylinder 14 are respectively movably connected to the top outer walls of the two placement platforms 16, a connecting opening 18 is opened on the bottom outer wall of the baffle 17, and a lubrication braking mechanism is provided inside the adjusting cylinder 14.
[0034] In the present invention, the staff enters the load-bearing hanging basket 3 and lifts the load-bearing hanging basket 3 to the bottom of the gantry hanger 1 through the electrically controlled winding roller 7, and then uses the moving roller 11 to slide in the maintenance channel 2 to drive the staff to move horizontally outside the gantry hanger 1, so that the staff can inspect the gantry hanger 1. In the present invention, the special shape of the elliptical ring plate 13 is used to enable the elliptical ring plate 13 to slide a certain distance on the outer wall of the load-bearing shaft 12. When the elliptical ring plate 13 drives the adjusting cylinder 14 to move downward, the adjusting cylinder 14 will be placed on the placement platform 16. At this time, the outer walls at both ends of the adjusting cylinder 14 lose the resistance of the baffle 17. The lubricating device arranged inside the adjusting cylinder 14 can lubricate the moving roller 11 through the connecting opening 18, and the lubricating liquid is driven to the full platform maintenance channel 2 through the rolling of the moving roller 11. Through this device, the running jam of the moving roller 11 in the maintenance channel 2 is reduced, and the smooth operation of the elliptical ring plate 13 is guaranteed, thereby avoiding affecting the staff's maintenance of the cabin driving.
[0035] Embodiment 2 On the basis of the first embodiment, the lubricating brake mechanism includes a triangular pressure block 19, a mounting plate 29, a connecting spring 30 and a lubricating cotton sheet 31. The adjusting cylinder 14 is provided with 38 connected at both ends, and movable grooves 20 connected to 38 are provided on both sides of the top outer wall of the adjusting cylinder 14. The outer wall of one end of the triangular pressure block 19 is fixedly connected to the top of the outer wall of one side of the baffle 17, and the outer wall of the triangular pressure block 19 is movably connected to the inner wall of the movable groove 20. The outer wall of the mounting plate 29 is fixedly connected to the inner wall of 38. The two connecting springs 30 are respectively fixedly connected to the outer walls of both sides of the mounting plate 29, and the outer wall of the connecting spring 30 at one end away from the mounting plate 29 is fixedly connected to the outer wall of one side of the lubricating cotton sheet 31. The outer walls around the lubricating cotton sheet 31 are movably connected to the inner wall of 38. The top outer wall of the lubricating cotton sheet 31 is movably connected to the inclined side outer wall of the triangular pressure block 19, the bottom outer wall of the limiting ring plate 15 is fixedly connected to the limiting retaining frame 21, the bottom outer wall of the elliptical ring plate 13 is fixedly connected with an adjusting card plate 22, the two ends of the outer wall of the adjusting card plate 22 are respectively slidably connected to the inner walls of the two limiting retaining frames 21, the bottom inner wall of the limiting retaining frame 21 is fixedly connected with a resist spring 23, the top outer wall of the resist spring 23 is fixedly connected to the bottom outer wall of the adjusting card plate 22, one side outer wall of the support adjustment plate 8 is movably connected to one side of the top outer wall of the adjusting card plate 22, one side outer wall of the two support adjustment plates 8 are fixedly connected with a retaining hinge 10, and the two support adjustment plates 8 are fixedly connected to the same pressure rod 9 through the retaining hinge 10.
[0036] In the present invention, the supporting pressure of the pressure rod 9 is equal to the gravity of the carrying hanging basket 3. When the staff stands on the carrying hanging basket 3, the supporting pressure of the pressure rod 9 exceeds the amount, resulting in a distance contraction, causing the two supporting adjustment plates 8 to tilt down at a certain angle. At this time, due to the change in angle, the outer wall of the top end of the supporting adjustment plate 8 presses against the outer wall of one side of the adjusting card plate 22, driving the adjusting card plate 22 to press downward, thereby pulling the elliptical ring plate 13 to further pull the adjusting cylinder 14. The adjusting cylinder 14 is loaded with diluted lubricating oil, and the special shape of the triangular pressure block 19 is used to block the lubricating cotton sheet 31 in 38. When the adjusting cylinder 14 is displaced to the placing platform 16, the lubricating cotton sheet 31 loses the pressure of the triangular pressure block 19, and is pushed to the outer wall of one side of the moving roller 11 through the elastic tension of the connecting spring 30. At this time, the lubricating oil adsorbed on the lubricating cotton sheet 31 will stick to the outer wall of the moving roller 11, thereby ensuring the lubrication of the moving roller 11.
[0037] Embodiment 3 On the basis of Example 1, a wheel disc 24 is fixedly connected to the outer wall of one side of the limit retaining frame 21 and the outer wall of the load-bearing shaft 12, and the same connecting belt 25 is rotatably connected between the two wheel discs 24. An adsorption sponge 26 is provided on the outer wall of one side of the wheel disc 24 located at the limit retaining frame 21, and the outer wall of the adsorption sponge 26 is movably connected to the bottom outer wall of the inspection channel 2. A connecting rod 28 is fixedly connected to the outer wall of one side of the wheel disc 24 located at the limit retaining frame 21, and Velcro 27 is fixedly connected to the outer walls around the connecting rod 28 and the inner wall of the adsorption sponge 26. The adsorption sponge 26 is adhered to the connecting rod 28 through the Velcro 27, and a plurality of overflow holes connected to the inner cavity are provided on the bottom outer wall of the inspection channel 2.
[0038] In the present invention, the rust ash generated in the maintenance channel 2 adheres to the diluted lubricating liquid. After a certain amount of rust ash accumulates on the bottom inner wall of the maintenance channel 2, the rust ash is partially squeezed into the overflow hole under the rolling and squeezing of the moving roller 11. At this time, the adsorption sponge 26 that moves synchronously with the moving roller 11 will adsorb the rust ash in the overflow hole, so that the rust ash and excess lubricating oil can be cleaned synchronously while the maintenance channel 2 of the present invention is running. After the present invention is used for a long time, the adsorption capacity of the adsorption sponge 26 is saturated, and the staff can tear off the adsorption sponge 26 through the Velcro 27 for replacement, thereby ensuring the adsorption efficiency of the device.
[0039] Embodiment 4 On the basis of the second embodiment, the replenishing mechanism includes a lubricating oil filling box 32, a connecting channel 33, a slider 34, a reset spring 35, a first magnet 36 and a second magnet 37. The lubricating oil filling box 32 is fixedly installed inside the gantry hanger 1, the top outer wall of the connecting channel 33 is fixedly connected to the output end of the lubricating oil filling box 32, the outer wall of the slider 34 is movably connected to the inner wall of the connecting channel 33, the top outer wall of the reset spring 35 is fixedly connected to the top inner wall of the connecting channel 33, the bottom outer wall of the reset spring 35 is fixedly connected to the top outer wall of the slider 34, the top outer wall of the slider 34 is provided with a flow hole connected to the outer walls on both sides, the top outer wall of the first magnet 36 is fixedly connected to the bottom outer wall of the slider 34, the bottom outer wall of the second magnet 37 is fixedly connected to the top outer wall of the mounting plate 29, the top outer wall of the adjusting cylinder 14 is provided with a through groove connected to 38, and the first magnet 36 is magnetically connected to the second magnet 37 via the through groove.
[0040] In the present invention, a diluent lubricating liquid is stored in the lubricating oil filling box 32, which is convenient for timely replenishment to the adjusting cylinder 14. The slider 34 is located in the connecting channel 33 by the pulling force of the reset spring 35. When the lubricating brake mechanism moves, the adjusting cylinder 14 will pass through the connecting channel 33 on the groove path. At this time, the first magnet 36 and the second magnet 37 produce magnetic adsorption, and the first magnet 36 drives the slider 34 to move downward. The lubricating oil in the connecting channel 33 flows out through the circulation hole into 38 for replenishment. When the lubricating brake mechanism has completely passed, the first magnet 36 and the second magnet 37 lose their magnetic adsorption, and the slider 34 is retracted into the connecting channel 33 by the pulling force of the reset spring 35.
[0041] The working principle and use process of the present invention are as follows: In the present invention, the staff enters the load-bearing hanging basket 3 and lifts the load-bearing hanging basket 3 to the bottom of the gantry hanger 1 through the electrically controlled winding roller 7, and then uses the moving roller 11 to slide in the maintenance channel 2 to drive the staff to move laterally outside the gantry hanger 1, so that the staff can inspect the gantry hanger 1. In the present invention, the special shape of the elliptical ring plate 13 is used to enable the elliptical ring plate 13 to slide a certain distance on the outer wall of the load-bearing shaft 12. When the elliptical ring plate 13 drives the adjusting cylinder 14 to move downward, the adjusting cylinder 14 will be placed on the placing platform 16. At this time, the outer walls of the two ends of the adjusting cylinder 14 lose the resistance of the baffle 17, and the lubrication device arranged inside the adjusting cylinder 14 can move the moving cylinder 14 through the connecting opening 18. The movable roller 11 is lubricated, and the lubricating fluid is driven to the full platform maintenance channel 2 by the rolling of the movable roller 11. This device reduces the running jam of the movable roller 11 in the maintenance channel 2, ensures the smooth operation of the elliptical ring plate 13, and avoids affecting the maintenance of the cabin driving by the staff. In the present invention, the supporting pressure of the pressure rod 9 is equal to the gravity of the load-bearing hanging basket 3. When the staff stands on the load-bearing hanging basket 3, the supporting pressure of the pressure rod 9 exceeds the amount, resulting in the distance contraction, so that the two support adjustment plates 8 are tilted down by a certain angle. At this time, due to the change in angle, the outer wall of the top end of the support adjustment plate 8 is against the outer wall of one side of the adjustment card plate 22, driving the adjustment card plate 22 to press downward, thereby pulling the elliptical ring plate 13 to further pull the adjustment cylinder 14, and the adjustment cylinder 14 The lubricating cotton sheet 31 is loaded with diluent lubricating oil, and the special shape of the triangular pressing block 19 is used to block the lubricating cotton sheet 31 in 38. When the adjusting cylinder 14 is displaced to the placement platform 16, the lubricating cotton sheet 31 loses the pressing of the triangular pressing block 19, and is pushed to the outer wall of one side of the moving roller 11 through the elastic tension of the connecting spring 30. At this time, the lubricating oil adsorbed on the lubricating cotton sheet 31 will adhere to the outer wall of the moving roller 11, thereby ensuring the lubrication of the moving roller 11. In the present invention, the rust ash generated in the maintenance channel 2 adheres to the diluent lubricating liquid. After a certain amount of rust ash is accumulated on the bottom inner wall of the maintenance channel 2, the rust ash is partially squeezed into the overflow hole under the rolling and squeezing of the moving roller 11. At this time, the adsorption sponge 2 moves synchronously with the moving roller 11. 6 will absorb the rust and ash in the overflow hole, so that the rust and ash and excess lubricating oil can be cleaned synchronously while the inspection channel 2 of the present invention is running. After the present invention is used for a long time, the adsorption capacity of the adsorption sponge 26 is saturated, and the staff can tear off the adsorption sponge 26 through the Velcro 27 for replacement to ensure the adsorption efficiency of the device. In the present invention, the lubricating oil filling box 32 stores diluting lubricating liquid, which is convenient for timely replenishment to the adjusting cylinder 14. The slider 34 is located in the connecting channel 33 through the pulling force of the reset spring 35. When the lubricating brake mechanism moves, the adjusting cylinder 14 passes through the connecting channel 33 on the path of the groove. At this time, the first magnet 36 and the second magnet 37 produce magnetic adsorption, and the first magnet 36 drives the slider 34 to move downward.The lubricating oil in the connecting channel 33 flows out through the circulation hole into the 38 for replenishment. When the lubricating brake mechanism has completely passed, the first magnet 36 and the second magnet 37 lose their magnetic adsorption, and the slider 34 is retracted into the connecting channel 33 by the pulling force of the return spring 35.
[0042] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A full-travel maintenance channel for a nacelle crane, comprising a gantry hanger (1), characterized in that: The bottom outer wall of the gantry hanger (1) is provided with an inspection passage (2); the bottom outer wall of the gantry hanger (1) is provided with a load-bearing hanging basket (3); pulley blocks (4) are fixedly connected to both sides of the top outer wall of the load-bearing hanging basket (3); the gantry hanger (1) is rotatably connected to a steel cable (5) via the pulley blocks (4); the bottom outer wall of the gantry hanger (1) is provided with a connecting retaining frame (6); an electric-controlled winding roller (7) is fixedly installed on the inner wall of the connecting retaining frame (6); the outer wall of one end of the steel cable (5) away from the gantry hanger (1) is fixedly wound around the electric-controlled winding roller The outer wall position of the connecting retainer (6) is fixedly installed with a connecting hinge on the top inner wall of the connecting retainer (6), and the connecting retainer (6) is fixedly connected to a support adjustment plate (8) through the connecting hinge. The outer wall of one end of the supporting adjustment plate (8) away from the connecting retainer (6) is rotatably connected to a load-bearing shaft (12), and the outer walls of both ends of the load-bearing shaft (12) are fixedly connected to an elliptical ring plate (13), and the outer wall of the elliptical ring plate (13) is movably connected to the inner wall of the maintenance channel (2), and the outer wall of the load-bearing shaft (12) is provided with a regular lubrication mechanism and a replenishing mechanism.
2. The full-travel maintenance passage for the engine room according to claim 1 is characterized by: The periodic lubrication mechanism comprises an elliptical ring plate (13), an adjustment cylinder (14), a limiting ring plate (15), a placement platform (16) and a baffle (17); the inner wall of the elliptical ring plate (13) is movably connected to the outer wall of the load-bearing shaft (12); the bottom outer wall of the adjustment cylinder (14) is fixedly connected to the top outer wall of the elliptical ring plate (13); the inner wall of the limiting ring plate (15) is rotatably connected to the outer wall of the load-bearing shaft (12); one side of the bottom outer wall of the placement platform (16) is rotatably connected to the top outer wall of the limiting ring plate (15); The outer wall of the bottom of the baffle (17) is fixedly connected to the outer wall of the top of the placement platform (16) away from the limiting ring plate (15), the outer walls at both ends of the adjustment cylinder (14) are movably connected to the outer walls of one side of the two baffles (17), the bottom outer walls at both ends of the adjustment cylinder (14) are movably connected to the outer walls of the top of the two placement platforms (16), the bottom outer wall of the baffle (17) is provided with a communicating opening (18), and a lubrication brake mechanism is provided inside the adjustment cylinder (14).
3. The full-travel maintenance passage for the engine room according to claim 2 is characterized by: The lubricating brake mechanism comprises a triangular pressure block (19), a mounting plate (29), a connecting spring (30) and a lubricating cotton sheet (31); the adjusting cylinder (14) is provided with two ends connected to each other (38); both sides of the top outer wall of the adjusting cylinder (14) are provided with movable grooves (20) connected to (38); the outer wall of one end of the triangular pressure block (19) is fixedly connected to the top of the outer wall of one side of the baffle (17); the outer wall of the triangular pressure block (19) is movably connected to the inner wall of the movable groove (20); The outer wall of the mounting plate (29) is fixedly connected to the inner wall of (38), the two connecting springs (30) are respectively fixedly connected to the outer walls on both sides of the mounting plate (29), the outer wall of one end of the connecting spring (30) away from the mounting plate (29) is fixedly connected to the outer wall of one side of the lubricating cotton sheet (31), the outer walls around the lubricating cotton sheet (31) are movably connected to the inner wall of (38), and the top outer wall of the lubricating cotton sheet (31) is movably connected to the inclined side outer wall of the triangular pressing block (19).
4. The full-travel maintenance passage for the engine room according to claim 2 is characterized by: The bottom outer wall of the limiting ring plate (15) is fixedly connected to the limiting retaining frame (21), the bottom outer wall of the elliptical ring plate (13) is fixedly connected to an adjusting clamping plate (22), the outer wall ends of the adjusting clamping plate (22) are respectively slidably connected to the inner walls of the two limiting retaining frames (21), the bottom inner wall of the limiting retaining frame (21) is fixedly connected to a resisting spring (23), the top outer wall of the resisting spring (23) is fixedly connected to the bottom outer wall of the adjusting clamping plate (22), one side outer wall of the supporting adjusting plate (8) is movably connected to one side of the top outer wall of the adjusting clamping plate (22), one side outer walls of the two supporting adjusting plates (8) are fixedly connected to a retaining hinge (10), and the two supporting adjusting plates (8) are fixedly connected to the same pressure rod (9) through the retaining hinge (10).
5. The full-travel maintenance passage for the engine room according to claim 4 is characterized by: A wheel disc (24) is fixedly connected to an outer wall of one side of the position-limiting retaining frame (21) and an outer wall of the load-bearing shaft (12); a connecting belt (25) is rotatably connected between the two wheel discs (24); an adsorption sponge (26) is provided on an outer wall of one side of the wheel disc (24) located at the position-limiting retaining frame (21); and an outer wall of the adsorption sponge (26) is movably connected to an outer wall of the bottom of the inspection channel (2).
6. The full-travel maintenance passage for the engine room according to claim 5 is characterized by: A connecting rod (28) is fixedly connected to an outer wall of one side of the wheel disc (24) located at the position limiting retaining frame (21), and the outer walls around the connecting rod (28) and the inner wall of the adsorption sponge (26) are fixedly connected to Velcro (27), and the adsorption sponge (26) is adhered to the connecting rod (28) via the Velcro (27), and a plurality of overflow holes communicating with the inner cavity are provided on the bottom outer wall of the inspection channel (2).
7. The full-travel maintenance passage for the engine room according to claim 2 is characterized by: The replenishing mechanism comprises a lubricating oil filling box (32), a connecting channel (33), a slider (34), a return spring (35), a first magnet (36) and a second magnet (37). The lubricating oil filling box (32) is fixedly installed inside the gantry hanger (1); the top outer wall of the connecting channel (33) is fixedly connected to the output end of the lubricating oil filling box (32); the outer wall of the slider (34) is movably connected to the inner wall of the connecting channel (33); the top outer wall of the reset spring (35) is fixedly connected to the top inner wall of the connecting channel (33); the bottom outer wall of the reset spring (35) is fixedly connected to the top outer wall of the slider (34); the top outer wall of the slider (34) is provided with a flow hole connected to the outer walls on both sides; the top outer wall of the first magnet (36) is fixedly connected to the bottom outer wall of the slider (34); the bottom outer wall of the second magnet (37) is fixedly connected to the top outer wall of the mounting plate (29); the top outer wall of the adjusting cylinder (14) is provided with a through slot connected to (38); the first magnet (36) is magnetically connected to the second magnet (37) by means of the through slot.
8. A maintenance method for a full-travel maintenance channel of a cabin crane, characterized in that: The invention comprises any one of the cabin driving full-travel maintenance passages described in claims 1 to 7 above, and the maintenance method is as follows: Step 1: A worker enters the load-bearing hanging basket (3) and lifts the load-bearing hanging basket (3) to the bottom of the gantry hanger (1) through the electrically controlled winding roller (7), so as to facilitate the worker to inspect and repair the gantry hanger (1); Step 2: Using the moving roller (11) to slide in the inspection channel (2) to drive the staff to move horizontally outside the gantry hanger (1); Step 3: The staff regularly replenishes lubricating oil into the lubricating oil filling box (32) and replaces the adsorption sponge (26).
Citation Information
Patent Citations
Special hanging basket for overhauling cabin crane
CN115675791A
Cited By
Light guide plate laminating equipment and method capable of enhancing atomization display effect
CN120057585A
Light guide plate laminating device and method capable of enhancing atomized display effect
CN120057585B