Multi-point synchronous construction method for tower beam of large-span cable-stayed bridge

By dividing the main beam of a large span cable-stayed bridge into multiple segments and constructing simultaneously at multiple points, the problems of long construction cycle and high cost of large span cable-stayed bridge are solved, and the construction period is shortened, controllable quality and construction are achieved. Improved safety.

CN118958158APending Publication Date: 2024-11-15CHINA RAILWAY 12TH BUREAU GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411258938.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

During the construction of large-span cable-stayed bridges, the method of first constructing the main tower and then constructing the main beam leads to a long construction cycle, high construction cost, and a long construction cycle of the main beam, which affects the construction period.

Method used

The multi-point synchronous construction method of large-span cable-stayed bridge tower beam is adopted. The main beam is divided into multiple main beam segments, and the construction is synchronously carried out on the construction surface provided by the trestle and bracket, and wet joints are reserved between the main beam segments. The joint and joint sections are synchronized with prestressed tensioning and concrete pouring to ensure synchronous construction and prestressed tensioning of each part.

Benefits of technology

Significantly shorten the construction period, improve construction efficiency, enhance the controllability of construction quality, reduce construction risks, ensure construction safety, and avoid stagnation periods and quality problems in traditional construction methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958158A_ABST
    Figure CN118958158A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of cable-stayed bridge construction, and particularly relates to a multi-point synchronous construction method for tower beams of a large-span cable-stayed bridge. The main beam is divided into a plurality of main beam sections, and the plurality of main beam sections are synchronously constructed on the construction working face provided by the trestle and the support; during the construction period of the main beam section, bridge floor tower column construction is carried out; a wet joint is reserved between the main beam sections, a main beam section prestress tensioning space is formed in the wet joint, and after the main beam sections on the two sides of the wet joint are tensioned, the wet joint is constructed in a cast-in-place mode; a closure section is reserved in the midspan of the main beam, and the closure section is constructed in a cast-in-place mode after the stay cables between the main beam and the bridge floor tower columns are constructed; according to the structural design characteristics of the large-span cable-stayed bridge, the tower beam multi-point synchronous construction method is adopted, the construction progress can be obviously accelerated, the construction period is shortened, the construction efficiency is improved, and the method has the obvious characteristics of being controllable in quality and guaranteeing safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of cable-stayed bridge construction, and in particular relates to a multi-point synchronous construction method for a tower beam of a large-span cable-stayed bridge. Background Art

[0002] A cable-stayed bridge is a type of bridge that uses many cables to directly pull the main beam onto the bridge tower. It is a structural system composed of a pressure-bearing tower, a tensioned cable, and a bending beam. It makes up for the lack of a large span of a continuous beam, has a greater span capacity than a beam bridge, and is one of the most important types of large-span bridges. The construction of a large-span cable-stayed bridge generally involves constructing the main tower first and then the main beam, which results in a long construction period and high construction costs. In addition, the main beam construction mainly uses the cantilever method: the inclined cable of the beam section to be poured is used as the front fulcrum support force of the hanging basket, and the rear end of the hanging basket is anchored on the poured beam section, so that the inclined cable and the poured beam section jointly bear the concrete load of the beam section to be poured. After the concrete reaches the required strength, the connection between the inclined cable and the hanging basket is removed, so that the segment load is transferred to the inclined cable, and then the hanging basket is moved forward. Since the construction work surface is strictly restricted and the construction period of each segment of the main beam is long, it is extremely unfavorable for projects with tight construction periods. Summary of the invention

[0003] The invention aims to solve the problem that the construction of a large-span cable-stayed bridge adopts the method of first constructing the main tower and then constructing the main beam, which results in a long construction period and high construction cost.

[0004] The present invention provides the following technical solutions: a multi-point synchronous construction method for towers and beams of a large-span cable-stayed bridge, wherein a main beam is divided into a plurality of main beam segments, and the plurality of main beam segments are synchronously constructed on a construction work surface provided by a trestle and a support; during the construction of the main beam segments, bridge deck towers are constructed; wet joints are reserved between the main beam segments, and prestressing spaces for the main beam segments are formed in the wet joints, and the wet joints are cast in situ after the tensioning of the main beam segments on both sides of the wet joints is completed; a closure section is reserved in the middle of the main beam span, and the closure section is cast in situ after the construction of the cable-stayed cables between the main beam and the bridge deck towers is completed.

[0005] Furthermore, the main beam is divided into main beam sections at the main tower and other main beam sections with the center lines of the bridge deck towers as the symmetry axes.

[0006] Further, the method comprises the following steps:

[0007] Construction of trestle, piers and supports: construction of steel trestle, construction of piers, installation and preloading of supports;

[0008] Construction of the main beam segment at the main tower: The main beam segment at the main tower is cast-in-place. After the concrete strength, elastic modulus and age of the main beam segment at the main tower meet the design requirements, the main beam segment at the main tower is tensioned longitudinally, transversely and vertically; then the main beam segments at the pier and main tower are temporarily consolidated through a consolidation device consisting of pre-embedded steel bars and sand cylinders on the pier top;

[0009] Bridge deck tower construction: The bridge deck tower is constructed with hydraulic self-climbing formwork. After the steel bars and embedded parts in the bridge deck tower are installed, concrete is poured in layers.

[0010] Cast-in-place construction of other main beam segments: During the construction of the main beam segments at the main tower and the bridge deck tower columns, cast-in-place construction of other main beam segments is carried out simultaneously. After the concrete strength, elastic modulus and age of other main beam segments meet the design requirements, longitudinal, transverse and vertical prestressing is carried out on other main beam segments;

[0011] Wet joint cast-in-place construction: Wet joint cast-in-place construction and bridge deck tower construction are carried out simultaneously; wet joint cast-in-place construction is carried out synchronously from the main beam segment at the main tower to both sides; after each wet joint is constructed on both sides, when the strength, elastic modulus and age of the wet joint concrete meet the design requirements, the main beam segment at the main tower and other main beam segments connected as a whole are longitudinally and transversely prestressed; after completion, the temporary consolidation of the pier beam and the rotation lock of the bearing are released, and the longitudinal lock of the bearing is retained;

[0012] Cable-stayed cable construction: All cables on both sides of the bridge deck towers are installed continuously and symmetrically, and tensioned to the specified value;

[0013] Closure section construction: After installing the temporary rigid connection of the closure section, the concrete pouring construction of the closure section is carried out; when the strength, elastic modulus and age of the closure section reach the design value, the temporary rigid connection is removed and prestressing is carried out at the closure section;

[0014] Dismantling of the trestle and support: After the cable tension test of the entire bridge is completed, the trestle and support are dismantled.

[0015] Furthermore, the length of the main beam segment at the main tower is between 15 and 30 m, the length of other main beam segments is between 30 and 80 m, the length of the wet joint is 2 m, and the length of the joint section is 2 m.

[0016] Furthermore, a full-length steel trestle will be installed on the side of the bridge, which will provide multiple construction work surfaces throughout the bridge, allowing the construction of each pier and support to be carried out simultaneously; the steel trestle consists of a steel panel, Bailey beam, distribution beam, and steel pipe piles from top to bottom, and the steel pipe piles are connected by a channel steel connection system.

[0017] Furthermore, the brackets are divided into main beam segment brackets at the main tower and other main beam segment brackets; the main beam segment brackets at the main tower stand on the top surface of the main pier cap, and the brackets are, from bottom to top, I-beam pads, heavy-duty disc-lock brackets and formwork; other main beam segment brackets are, from bottom to top, open steel pipe piles, longitudinal and transverse pads, steel pipe columns, cross beams, truss beams, I-beam pads, heavy-duty disc-lock brackets and formwork.

[0018] Compared with the prior art, the advantages of the present invention are:

[0019] The present invention adopts a multi-point synchronous construction method in view of the structural design characteristics of a large-span cable-stayed bridge, which can significantly speed up the construction progress, shorten the construction period, improve the construction efficiency, and has the characteristics of obvious quality control and safety assurance. Compared with the traditional construction method, it eliminates the idle period when the main beam cannot be constructed due to the unfinished main tower, and avoids the stagnation period of installing a cable-stayed cable after each section of the main beam is cast. For cable-stayed bridges and similar projects with tight construction periods, the multi-point synchronous construction method of the tower and beam of a large-span cable-stayed bridge has the advantage of significantly shortening the construction period, thereby quickly completing the construction of a large-span cable-stayed bridge. Secondly, the method has good controllability of the construction quality, and the construction efficiency can be further improved by adjusting the number of main beam segments. At the same time, the multi-point synchronous construction of the tower column and the main beam enables the construction of different parts to be carried out in parallel, effectively coordinates the relationship between the various processes, and avoids the occurrence of quality problems. Most importantly, the full-bridge trestle and bracket provide a stable construction platform to provide safety for the entire construction process. Through reasonable support and construction methods, the risk of accidents during construction is reduced, and the safety of construction personnel and the surrounding environment is guaranteed. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 Schematic diagram of main beam segmentation type;

[0021] Figure 2 This is a schematic diagram of the construction of the trestle, piers and supports;

[0022] Figure 3 This is a schematic diagram of the construction of the main beam segment at the main tower;

[0023] Figure 4 This is a schematic diagram of the bridge deck tower construction;

[0024] Figure 5 This is a construction diagram of other main beam segments;

[0025] Figure 6 This is a schematic diagram of wet joint construction;

[0026] Figure 7 This is a schematic diagram of the construction of the cable-stayed cable;

[0027] Figure 8 This is a schematic diagram of the construction of the main beam mid-span joint section;

[0028] Fig. 9 Schematic diagram for dismantling the trestle and support;

[0029] Fig.10 This is a structural diagram of a steel trestle;

[0030] Fig.11 This is a schematic diagram of the structure of other main beam segment supports.

[0031] In the figure: 1-bridge pier; 2-bridge tower column; 3-stayed cable; 4-main beam segment bracket at main tower; 5-other main beam segment bracket; 6-steel panel; 7-Bailey beam; 8-distribution beam; 9-channel steel connection system; 10-steel pipe pile; 11-open steel pipe pile; 12-longitudinal and transverse cushion beams; 13-steel pipe column; 14-cross beam; 15-truss beam; 16-I-beam cushion beam; 17-heavy disc buckle bracket; 18-formwork; A0-main beam segment at main tower; A1-other main beam segment of side span No. 1; A2-other main beam segment of side span No. 2; B1-other main beam segment of middle span No. 1; B2-other main beam segment of middle span No. 2; M1-wet joint No. 1; M2-wet joint No. 2; H1-joint section. DETAILED DESCRIPTION

[0032] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0033] like Figure 1 As shown: a multi-point synchronous construction method for towers and beams of a large-span cable-stayed bridge, the main beam is divided into multiple main beam segments, and the multiple main beam segments are synchronously constructed on the construction working surface provided by the trestle and the support; the bridge deck tower column is constructed during the main beam segment construction; wet joints are reserved between the main beam segments, and prestressing spaces for the main beam segments are formed in the wet joints. After the main beam segments on both sides of the wet joints are tensioned, the wet joints are cast in situ; a closure section is reserved in the middle of the main beam span, and the closure section is cast in situ after the construction of the cable-stayed cable between the main beam and the bridge deck tower column is completed.

[0034] The main beam is divided into main beam sections at the main tower and other main beam sections with the center line of each bridge deck tower as the symmetry axis.

[0035] A twin-tower cable-stayed bridge is taken as an example to illustrate the general segmentation principle of the main beam: the main beam is divided into main beam segment A0 at the main tower, other main beam segments A1 at side span No. 1, other main beam segments A2 at side span No. 2, other main beam segments B1 at middle span No. 1, and other main beam segments B2 at middle span No. 2; the main beam segment A0 close to the main tower is the No. 1 wet joint M1, followed by the No. 2 wet joint M2. The length of the main beam segment A0 at the main tower is mainly determined according to the construction period and the requirements of the bridge deck and tower construction working surface, and is generally 15 to 30 meters; the segment length and number of other main beam segments are mainly determined according to the bridge span, construction period and construction capacity, and are generally 30 to 80 meters; the length of the wet joint is generally 2.0 meters; the number of wet joints is determined by the number of segments of other main beam segments; the length of the joint section H1 is generally 2.0 meters, and the number of joint sections is determined by the number of tower columns; among them, the length of each section and the number of sections of other main beam segments are the key factors affecting the construction period. Under the premise of ensuring the quality of the project, the length of each section of other main beam segments should be increased as much as possible and the number of sections should be reduced.

[0036] The specific processes include:

[0037] like Figure 2 , Fig.10 , Fig.11 Shown: Construction of trestle, piers and supports: construction of steel trestle, construction of piers, installation and preloading of supports.

[0038] like Figure 3 As shown: Construction of main beam segment at main tower: The main beam segment at main tower is cast-in-place. After the concrete strength, elastic modulus and age of the main beam segment at main tower reach the design requirements, the main beam segment at main tower is tensioned longitudinally, transversely and vertically. After that, the main beam segment at pier and main tower is temporarily consolidated by a consolidation device composed of pre-embedded steel bars and sand cylinders on the pier top.

[0039] like Figure 4 As shown: Bridge deck tower construction: The bridge deck tower is constructed with hydraulic self-climbing formwork. After the steel bars and embedded parts in the bridge deck tower are installed, the concrete is poured in layers. When pouring the bridge deck tower, the concrete is placed and vibrated in layers, and the concrete is pumped into the mold.

[0040] like Figure 5 As shown: Cast-in-place construction of other main beam segments: During the construction of the main beam segments at the main tower and the bridge deck tower columns, cast-in-place construction of other main beam segments is carried out simultaneously. After the concrete strength, elastic modulus and age of other main beam segments meet the design requirements, longitudinal, transverse and vertical prestressing is carried out on other main beam segments.

[0041] like Figure 6As shown: Wet joint cast-in-place construction: Wet joint cast-in-place construction and bridge deck tower column construction can be carried out simultaneously. Wet joint cast-in-place construction is carried out synchronously from the main beam segment at the main tower to both sides; after each wet joint is constructed on both sides, when the strength, elastic modulus and age of the wet joint concrete meet the design requirements, the main beam segment at the main tower and other main beam segments connected as a whole are longitudinally and transversely prestressed; after completion, the temporary consolidation of the pier beam and the rotation lock of the bearing are released, and the longitudinal lock of the bearing is retained.

[0042] That is, first cast the No. 1 wet joint M1 on both sides of the main beam segment A0 at the main tower. When the concrete strength, elastic modulus and age of the No. 1 wet joint M1 meet the design requirements, the main beam segment A0 at the main tower, other main beam segments A1 of the side span No. 1, and other main beam segments B1 of the middle span No. 1 are prestressed as a whole; after the No. 2 wet joint M2 is cast and the concrete strength, elastic modulus and age of the No. 2 wet joint M2 meet the design requirements, the main beam segment A0 at the main tower, other main beam segments A1 of the side span No. 1, other main beam segments B1 of the middle span No. 1, other main beam segments A2 of the side span No. 2, and other main beam segments B2 of the middle span No. 2 are prestressed as a whole.

[0043] like Figure 7 Shown: Cable-stayed cable construction: All cables on both sides of the bridge deck tower are installed continuously and symmetrically, and tensioned to the specified value.

[0044] like Figure 8 As shown: Construction of the closure section: After installing the temporary rigid connection of the closure section, the concrete pouring construction of the closure section shall be carried out; the pouring of the concrete of the closure section H1 should be carried out at night when the temperature is low. When the strength, elastic modulus and age of the closure section reach the design values, the temporary rigid connection shall be removed and the prestressing shall be carried out at the closure section; the temporary closure steel bundles of the top and bottom plates shall be tensioned to form a three-span continuous beam, and the longitudinal cables of the middle span shall be tensioned, among which the temporary steel bundles are tensioned to the designed tonnage; the tensioning order of the steel bundles is: long bundles first, then short bundles.

[0045] like Fig. 9 Shown: Removal of the trestle and support: After the cable tension test of the entire bridge is completed, the trestle and support are removed.

[0046] like Fig.10 As shown: the steel trestle is composed of 10mm thick steel panel 6, Bailey beam 7, 2HM588×300 type distribution beam 8, Ф630×10 steel pipe pile 10 from top to bottom, and 28a type channel steel connection system 9 is connected before the steel pipe pile 10. The trestle deck is 8m wide and has handrails.

[0047] The brackets are divided into main beam segment brackets at the main tower and other main beam segment brackets. The construction of the main beam segment brackets at the main tower and other main beam segment brackets can be carried out simultaneously; the main beam segment brackets at the main tower stand on the top surface of the main pier cap, and the brackets are composed of I-beam pad beams, heavy-duty disc brackets and formwork from bottom to top.

[0048] like Fig.11 As shown: the other main beam segment supports are, from bottom to top, Ф630 open steel pipe piles 11, I55b longitudinal and transverse cushion beams 12, Ф630 steel pipe columns 13, HN700 cross beams 14, truss beams 15, I10 I-beam cushion beams 16, heavy-duty disc brackets 17 and formwork 18.

[0049] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A multi-point synchronous construction method for tower and beam of a long-span cable-stayed bridge, characterized in that: The main beam is divided into multiple main beam segments, and multiple main beam segments are constructed simultaneously on the construction working surface provided by the trestles and supports; the bridge deck tower column is constructed during the main beam segment construction; wet joints are reserved between the main beam segments, and prestressing space for the main beam segments is formed in the wet joints. After the main beam segments on both sides of the wet joints are tensioned, the wet joints are cast in situ; a closure section is reserved in the middle of the main beam span, and the closure section is cast in situ after the construction of the inclined cables between the main beam and the bridge deck tower column is completed.

2. A method for multi-point synchronous construction of tower and beam of a long-span cable-stayed bridge according to claim 1, characterized in that: The main beam is divided into main beam sections at the main tower and other main beam sections with the center line of each bridge deck tower as the symmetry axis.

3. The method for multi-point synchronous construction of tower and beam of a long-span cable-stayed bridge according to claim 2, characterized in that: Including the following processes: Construction of trestle, piers and supports: construction of steel trestle, construction of piers, installation and preloading of supports; Construction of the main beam segment at the main tower: The main beam segment at the main tower is cast-in-place. After the concrete strength, elastic modulus and age of the main beam segment at the main tower meet the design requirements, the main beam segment at the main tower is tensioned longitudinally, transversely and vertically; then the main beam segments at the pier and main tower are temporarily consolidated through a consolidation device consisting of pre-embedded steel bars and sand cylinders on the pier top; Bridge deck tower construction: The bridge deck tower is constructed with hydraulic self-climbing formwork. After the steel bars and embedded parts in the bridge deck tower are installed, concrete is poured in layers. Cast-in-place construction of other main beam segments: During the construction of the main beam segments at the main tower and the bridge deck tower columns, cast-in-place construction of other main beam segments is carried out simultaneously. After the concrete strength, elastic modulus and age of other main beam segments meet the design requirements, longitudinal, transverse and vertical prestressing is carried out on other main beam segments; Wet joint cast-in-place construction: Wet joint cast-in-place construction and bridge deck tower construction are carried out simultaneously; wet joint cast-in-place construction is carried out synchronously from the main beam segment at the main tower to both sides; after each wet joint is constructed on both sides, when the strength, elastic modulus and age of the wet joint concrete meet the design requirements, the main beam segment at the main tower and other main beam segments connected as a whole are longitudinally and transversely prestressed; after completion, the temporary consolidation of the pier beam and the rotation lock of the bearing are released, and the longitudinal lock of the bearing is retained; Cable-stayed cable construction: All cables on both sides of the bridge deck towers are installed continuously and symmetrically, and tensioned to the specified value; Closure section construction: After installing the temporary rigid connection of the closure section, the concrete pouring construction of the closure section is carried out; when the strength, elastic modulus and age of the closure section reach the design value, the temporary rigid connection is removed and prestressing is carried out at the closure section; Dismantling of the trestle and support: After the cable tension test of the entire bridge is completed, the trestle and support are dismantled.

4. The method for multi-point synchronous construction of a tower and beam of a long-span cable-stayed bridge according to claim 2, characterized in that: The length of the main beam segment at the main tower is between 15 and 30m, the length of other main beam segments is between 30 and 80m, the length of the wet joint is 2m, and the length of the joint section is 2m.

5. The method for multi-point synchronous construction of tower and beam of a long-span cable-stayed bridge according to claim 3, characterized in that: A full-length steel trestle will be set up on the side of the bridge, which will provide multiple construction work surfaces throughout the bridge, so that the construction of each pier and support can be carried out simultaneously; the steel trestle is composed of steel panels, Bailey beams, distribution beams, and steel pipe piles from top to bottom, and the steel pipe piles are connected with a channel steel connection system.

6. The method for multi-point synchronous construction of tower and beam of a long-span cable-stayed bridge according to claim 1, characterized in that: The brackets are divided into main beam segment brackets at the main tower and other main beam segment brackets; the main beam segment brackets at the main tower stand on the top surface of the main pier cap, and the brackets are composed of I-beam pads, heavy-duty disc-lock brackets and formwork from bottom to top; the other main beam segment brackets are composed of open steel pipe piles, longitudinal and transverse pads, steel pipe columns, cross beams, truss beams, I-beam pads, heavy-duty disc-lock brackets and formwork from bottom to top.