Glass fiber reinforced resin soil nailing wall supporting system and construction technology
By using a soil nail wall support system made of glass fiber and resin matrix composite materials, combined with the inflatable consolidation technology of air bags and panels, the problems of traditional soil nail walls are solved, and the problems of large weight and poor corrosion resistance are achieved, achieving more stable and high Strong soil slope support effect.
Patent Information
- Application Number
- CN202411194890.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-15
AI Technical Summary
Traditional soil nail walls have problems with large weight and poor corrosion resistance, which leads to a decrease in support strength over time and makes it difficult to maintain structural stability for a long time.
The earth nail wall support system made of glass fiber and resin matrix composite materials combines stable components and construction technology, including air bags, panels, connecting rods, pressing components and anti-nail pulling, etc., and is inflated and slurry solidified by air bags knot to achieve more stable soil slope support.
It achieves more stable, corrosion-resistant and high-strength soil slope support, avoids the weight and corrosion resistance of the steel bars, and ensures the long-term stability and pull-out resistance of the soil nail wall through the cooperation of air bags and panels.
Smart Images

Figure CN118958310A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of foundation pit construction, and in particular to a glass fiber reinforced resin soil nail wall support system and a construction process. Background Art
[0002] The foundation pit is an earth pit excavated at the foundation design location according to the base elevation and foundation plane dimensions; in order to ensure the stability of structures such as the foundation pit and slopes, soil nail walls are often used as support structures.
[0003] At present, traditional soil nail walls mostly use steel bars or steel pipes as soil nails to improve the stability of support.
[0004] However, although the above-mentioned technology has a certain degree of supporting effect, it has the problems of heavy weight and poor corrosion resistance, so that once time increases, the supporting strength will be greatly reduced. Summary of the invention
[0005] In order to improve the problems existing in the above-mentioned technology, the present application provides a glass fiber reinforced resin soil nail wall support system and construction process.
[0006] In a first aspect, the present application provides a glass fiber reinforced resin soil nail wall support system, which adopts the following technical solution: A glass fiber reinforced resin soil nail wall support system comprises: a plurality of installation heads and hollow soil nails corresponding to the installation heads and arranged in a soil slope, wherein the soil nails are made of a composite material of glass fiber and a resin matrix, the installation heads are provided with installation holes, the soil nails penetrate the installation holes, and the soil nails are threadedly sleeved on installation nuts, and the soil nails are provided with a plurality of grouting holes.
[0007] By adopting the above technical solution, soil nails made of a composite material of glass fiber and resin matrix are used to replace traditional steel bars and steel pipes, so that not only can the soil slope be supported more stably, but also the soil nails are light in weight, have good corrosion resistance and high strength.
[0008] Optionally, it also includes: a stabilizing component, the stabilizing component includes: a stabilizing part and a pressing part, the stabilizing part includes: an air bag and a panel, the air bag is fixed on the panel, and the air bag is in contact with the soil slope, an operating hole is opened on the panel, and the pressing part is arranged between adjacent mounting heads.
[0009] By adopting the above technical solution, after the panel is laid, the air bag is inflated again to prevent space from being left between the panel and the soil slope, so that the panel can bear force together with the soil nails to support the soil slope more stably.
[0010] Optionally, the clamping part includes: a connecting rod and a connecting ear, the connecting rod is pressed onto the panel, a connecting groove is provided on the mounting head, the connecting ear is arranged in the connecting groove, and the connecting ear is fixedly connected to the connecting rod, and a connecting component is arranged between the connecting ear and the mounting head.
[0011] By adopting the above technical solution, the connecting rod can press and fix the panel.
[0012] Optionally, the clamping part also includes: a pressing plate and a clamping nut, the pressing plate is tightly attached to the mounting head, and a through hole is penetrated through the pressing plate, the soil nail is penetrated through the through hole, and the clamping nut is threadedly sleeved on the soil nail.
[0013] By adopting the above technical solution, the pressure plate can prevent the squeezing rod from bulging after the air bag is inflated.
[0014] Optionally, a drainage hole is formed through the mounting head, and the drainage hole extends through the pressing plate.
[0015] By adopting the above technical solution, the drainage holes can discharge the water in the earth slope to the outside, so that the earth slope is not easily collapsed due to water accumulation.
[0016] Optionally, the connecting assembly includes: a connecting rod, a fixing rod and a pushing spring, a connecting hole is opened through the connecting groove, one end of the connecting rod is fixed to the connecting ear, and the other end is arranged in the connecting hole, a fixing hole is opened in the connecting hole, and an accommodating hole is opened on the connecting rod, one end of the fixing rod is arranged in the fixing hole, and the other end is arranged in the accommodating hole, and the pushing spring is fixed between the fixing rod and the bottom of the accommodating hole.
[0017] By adopting the above technical solution, the fixing rod can lock the connecting rod so that the connecting rod is not easily separated from the connecting hole, thereby completing the installation of the connecting rod.
[0018] Optionally, the connection assembly further includes: a reinforcement nail, one end of which is arranged in the soil slope, and the other end of which is arranged in the connecting hole.
[0019] By adopting the above technical solution, during the process of inserting the connecting rod into the connecting hole, the connecting rod will push the reinforcing nail so that the reinforcing nail can be inserted into the soil slope, thereby improving the stability of the installation head.
[0020] Optionally, the connecting assembly further comprises: a limit block, a limit groove is provided on the inner wall of the connecting hole, the limit block is slidably disposed in the limit groove, and the limit block is fixedly connected to the reinforcing nail.
[0021] By adopting the above technical solution, the limiting block can prevent the reinforcing nails from being easily separated from the connected holes.
[0022] Optionally, the connecting assembly also includes: an anti-pullout nail, a pushing plate, a support spring and a guide plate, the reinforcing nail is provided with a seating hole, the pushing plate is arranged in the seating hole, the support spring is fixed between the pushing plate and the bottom of the seating hole, the guide plate is fixed to the pushing plate, a clearance hole is penetrated through the inner wall of the seating hole, a connecting hole is penetrated through the soil nail, one end of the anti-pullout nail is arranged in the clearance hole, and the other end passes through the connecting hole and extends into the soil nail.
[0023] By adopting the above technical solution, the anti-pullout nail can improve the pullout resistance of the installation head and the soil nail.
[0024] In a second aspect, the present application provides a construction process for a glass fiber reinforced resin soil nail wall support system, which adopts the following technical solution: A construction process of a glass fiber reinforced resin soil nail wall support system comprises the following steps: S1: Excavate the foundation pit according to the construction requirements to form a soil slope; S2: drilling holes into the soil slope and placing soil nails in the holes; S3: Insert the installation head onto the soil nail and tighten the installation nut; S4: Inflate a small amount of gas into the air bag so that the air bag can maintain its shape and be easily glued to the panel, and then lay the panel on the soil slope; S5: Fix the connecting rod between adjacent mounting heads to press the panel; S6: Insert the pressing plate onto the soil nails and tighten the pressing nut; S7: grouting is performed in the soil nail until the grout flows out through the overflow hole and consolidates with the soil; S8: Fill the air bag with gas again. Through secondary loading and inflation, the panel can bear the force together with the soil nails.
[0025] By adopting the above technical solution, the construction of the soil nail wall can be completed to support the soil slope more stably.
[0026] In summary, the present application includes at least one of the following beneficial effects: 1. Soil nails made of a composite material of glass fiber and resin matrix are used to replace traditional steel bars and steel pipes, which can not only support the soil slope more stably, but also have light weight, good corrosion resistance and high strength.
[0027] 2. After the panel is laid, the air bag is inflated again to prevent space from being left between the panel and the soil slope, so that the panel can bear the force together with the soil nails to support the soil slope more stably.
[0028] 3. The pressure plate can prevent the extrusion rod from bulging after the air bag is inflated. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 is a schematic diagram of the structure according to an embodiment of the present application; Figure 2 yes Figure 1 A schematic front view of Figure 3 is along Figure 2 A schematic cross-sectional view taken along the cutting line AA in FIG. Figure 4 is along Figure 2 A schematic cross-sectional view taken along the cutting line BB in FIG.
[0030] In the figure: 1. mounting head; 11. mounting hole; 12. connecting groove; 13. connecting hole; 14. fixing hole; 15. limiting groove; 16. drainage hole; 2. soil nail; 21. mounting nut; 22. overflow hole; 23. connecting hole; 3. stabilizing part; 31. air bag; 32. panel; 321. operation hole; 4. clamping part; 41. connecting rod; 42. connecting ear; 43. pressing plate; 431. penetration hole; 44. clamping nut; 5. connecting assembly; 51. connecting rod; 511. accommodating hole; 52. fixing rod; 53. pushing spring; 54. reinforcing nail; 541. placement hole; 52. giving way hole; 55. limiting block; 56. anti-pullout nail; 57. pushing plate; 58. supporting spring; 59. guide plate. DETAILED DESCRIPTION
[0031] The present application provides a glass fiber reinforced resin soil nail wall support system.
[0032] See also Figure 1 A glass fiber reinforced resin soil nail wall support system includes: a plurality of installation heads 1 and hollow soil nails 2 corresponding to the installation heads 1 and arranged in a soil slope 6. In the embodiment of the present application, the soil nails 2 are made of a composite material of glass fiber and resin matrix to replace traditional steel bars and steel pipes, so that they can not only support the soil slope 6, but also have light weight, good corrosion resistance and high strength.
[0033] See also Figure 2 and Figure 3 The installation head 1 is provided with an installation hole 11, and the end of the soil nail 2 away from the soil slope 6 is provided with the installation hole 11. The end of the soil nail 2 away from the soil slope 6 is threaded with an installation nut 21, and the installation nut 21 is tightly abutted against the installation head 1. After the soil nail 2 is placed in the soil slope 6, the installation head 1 is sleeved onto the soil nail 2, and the installation nut 21 is tightened onto the soil nail 2, so that the soil nail 2 can be fixed.
[0034] See also Figure 3 In addition, a plurality of overflow holes 22 are formed through the side wall of the soil nail 2. After the soil nail 2 is placed in the soil slope 6, grouting can be performed into the soil nail 2 until the slurry flows out of the overflow holes 22 and consolidates with the soil, thereby improving the stability of the connection between the soil nail 2 and the soil slope 6 and improving the supporting effect on the soil slope 6.
[0035] See also Figure 1 , Figure 3 and Figure 4 , further, it also includes: a stabilizing component, which can be connected with the soil nails 2 to form a soil nail 2 wall, so that the soil slope 6 can be supported more stably.
[0036] See also Figure 1 , Figure 3 and Figure 4 The stabilizing component includes: a stabilizing part 3 and a pressing part 4.
[0037] See also Figure 1 and see Figure 4 The stabilizing part 3 includes: an air bag 31 and a panel 32. In the embodiment of the present application, the panel 32 is also made of a material composited with glass fiber and a resin matrix. The air bag 31 is glued to the panel 32, and the air bag 31 is in contact with the soil slope 6; an operation hole 321 is provided on the panel 32, and the operation hole 321 is convenient for moving the panel 32; a reserved air hole can also be provided on the panel 32 to inflate and deflate the air bag 31. When fixing, a small amount of gas can be injected into the air bag 31 first, so that the air bag 31 can maintain a certain shape, thereby facilitating the bonding of the air bag 31 and the panel 32.
[0038] See also Figure 1 and see Figure 4 In the embodiment of the present application, the four corners of the panel 32 are all missing, so that the four corners of the panel 32 can fit with the corresponding installation head 1; and there are gaps between adjacent panels 32, so that the panel 32 can be pressed later. Through the arrangement of the panel 32, a soil nail 2 wall is formed between the panel 32 and the soil nail 2 to support the soil slope 6; and after the panel 32 is laid, the air bag 31 is inflated again so that it is not easy to leave space between the panel 32 and the soil slope 6, so that the panel 32 can bear force together with the soil nail 2 to support the soil slope 6 more stably; and the air bag 31 can also prevent problems such as water seepage and slurry leakage.
[0039] See also Figure 1 and see Figure 4 In addition, in the embodiment of the present application, if the construction is completed and there is no need to dismantle the support system, the gas in the air bag 31 can be released and grouting can be performed into the air bag 31 to form a permanent surface layer.
[0040] See also Figure 1 and Figure 3 The pressing part 4 includes: a connecting rod 41 and a connecting ear 42. The connecting rod 41 is pressed against the panel 32 to press and fix the panel 32. In the embodiment of the present application, the cross-section of the connecting rod 41 is in a "T" shape. Therefore, during installation, the bottom of the connecting rod 41 is inserted into the gap between the adjacent panels 32. The connecting rod 41 located between the top of the slope 6 and the slope surface needs to be provided with a curved section to adapt to the angle between the top of the slope and the slope surface.
[0041] See also Figure 1 and Figure 3 A connecting groove 12 is provided on the side of the installation head 1 away from the soil slope 6, and a connecting ear 42 is arranged in the connecting groove 12, and the connecting ear 42 is fixedly connected to the connecting rod 41. A connecting assembly 5 is arranged between the connecting ear 42 and the installation head 1, and the connecting assembly 5 can quickly install the connecting rod 41 to improve the construction efficiency.
[0042] See also Figure 3 The connecting assembly 5 includes: a connecting rod 51, a fixing rod 52 and a pushing spring 53. A connecting hole 13 is formed through the bottom of the connecting groove 12, and a fixing hole 14 is formed on the inner wall of the connecting hole 13. One end of the connecting rod 51 is fixedly connected to the connecting ear 42, and the other end is arranged in the connecting hole 13. A receiving hole 511 is formed on the side wall of the connecting rod 51. The connecting rod 51 can complete the preliminary installation of the connecting rod 41 and the mounting head 1.
[0043] See also Figure 3 One end of the fixing rod 52 is disposed in the receiving hole 511, and the other end is disposed in the fixing hole 14. The fixing rod 52 can lock the connecting rod 51, so that the connecting rod 51 is not easily separated from the connecting hole 13, thereby completing the installation of the connecting rod 41. The pushing spring 53 is fixed between the fixing rod 52 and the bottom of the receiving hole 511, and the pushing spring 53 is used to push the fixing rod 52 to be automatically inserted into the fixing hole 14.
[0044] See also Figure 3 In addition, in the embodiment of the present application, if the support system needs to be disassembled, a pull rope (not shown in the figure) can be additionally provided to be connected to the fixing rod 52 so that the pull rope can be pulled to pull the fixing rod 52 back into the accommodating hole 511, thereby completing the separation of the connecting rod 51 and the mounting head 1.
[0045] See also Figure 3Furthermore, the connection assembly 5 further includes: a reinforcing nail 54 and a limiting block 55. One end of the reinforcing nail 54 is arranged in the connecting hole 13, and the other end is arranged in the earth slope 6. When the connecting rod 51 is inserted into the connecting hole 13, the connecting rod 51 will push the reinforcing nail 54, so that the reinforcing nail 54 can be inserted into the earth slope 6, thereby improving the stability of the installation head 1. The inner wall of the connecting hole 13 is provided with a limiting groove 15. The limiting block 55 is slidably arranged in the limiting groove 15 and slides along the length direction of the limiting groove 15. The limiting block 55 is fixedly connected to the reinforcing nail 54, and the limiting block 55 can prevent the reinforcing nail 54 from being easily separated from the connecting hole 13.
[0046] See also Figure 3 Furthermore, the connection assembly 5 further includes: an anti-pullout nail 56, a push plate 57, a support spring 58 and a guide plate 59. A placement hole 541 is provided at one end of the reinforcement nail 54 away from the soil slope 6, and the push plate 57 is arranged in the placement hole 541; and the connecting rod 51 is arranged in the placement hole 541 and is tightly abutted against the push plate 57. The support spring 58 is fixed between the push plate 57 and the bottom of the placement hole 541, and the support spring 58 is used to push the push plate 57.
[0047] See also Figure 3 The guide plate 59 is fixed obliquely to the side of the push plate 57 close to the support spring 58. When the connecting rod 41 is not installed, the push plate 57 is located at the opening of the placement hole 541. The inner wall of the placement hole 541 is penetrated with a clearance hole 52, and the side wall of the soil nail 2 is penetrated with a connecting hole 23. One end of the anti-pullout nail 56 is arranged in the clearance hole 52, and the other end is arranged in the connecting hole 23. The end of the anti-pullout nail 56 located in the clearance hole 52 is set as an arc surface. When the connecting rod 41 is not installed, one end of the anti-pullout nail 56 is located in the clearance hole 52, and the other end is located in the placement hole 541 and abuts against the guide plate 59. During the process of inserting the connecting rod 51 into the connecting hole 13, the supporting spring 58 provides sufficient supporting force so that the connecting rod 51 pushes the reinforcing nail 54 to be inserted into the earth slope 6; after the insertion is completed, the connecting rod 51 squeezes the pushing plate 57, and under the action of the guide plate 59, the anti-pullout nail 56 is inserted into the earth slope 6 and extends into the connecting hole 23, thereby improving the pull-out resistance of the installation head 1 and the soil nail 2 to improve stability; and after the soil nail 2 is grouting, the connection between the anti-pullout nail 56 and the soil nail 2 is more stable.
[0048] See also Figure 3 The pressing part 4 further includes: a pressing plate 43 and a pressing nut 44. The pressing plate 43 is sleeved on the soil nail 2 through the through hole 431, and the pressing plate 43 is fitted with the installation head 1. The pressing nut 44 is threadedly sleeved on the soil nail 2, and the pressing nut 44 and the pressing plate 43 are tightly pressed. The pressing plate 43 can prevent the extrusion rod from bulging after the air bag 31 is inflated.
[0049] See also Figure 1Furthermore, a drainage hole 16 is formed on the mounting head 1 and extends through the pressing plate 43. The drainage hole 16 can discharge the water in the earth slope 6 to the outside, so that the earth slope 6 is not easy to collapse due to water accumulation. In the embodiment of the present application, there is no need to pour a concrete surface layer.
[0050] The working principle of a glass fiber reinforced resin soil nail wall support system of the present application when in use is as follows: after the soil nail 2 is placed in the soil slope 6, the installation head 1 is put on the soil nail 2, and the installation nut 21 is tightened onto the soil nail 2, so that the soil nail 2 can be fixed.
[0051] The present application also provides a construction process for a glass fiber reinforced resin soil nail wall support system.
[0052] A construction process of a glass fiber reinforced resin soil nail wall support system comprises the following steps: S1: excavating a foundation pit according to construction requirements to form a soil slope 6; S2: drilling holes in the soil slope 6 and placing soil nails 2 in the holes; S3: Insert the installation head 1 onto the soil nail 2 and tighten the installation nut 21; S4: Inflate a small amount of gas into the air bag 31 so that the air bag 31 maintains its shape and is easy to glue to the panel 32, and then lay the panel 32 on the soil slope 6; S5: Fix the connecting rod 41 between adjacent mounting heads 1 to press the panel 32; S6: insert the pressing plate 43 onto the soil nail 2, and tighten the pressing nut 44; S7: Grouting is performed in the soil nail 2 until the grout flows out through the overflow hole 22 and consolidates with the soil; S8: Fill the air bag 31 with gas again. Through the secondary loading and inflation, the panel 32 can bear the force together with the soil nail 2.
[0053] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A glass fiber reinforced resin soil nail wall support system, characterized in that: include: A plurality of mounting heads (1) and hollow soil nails (2) corresponding to the mounting heads (1) and arranged in a soil slope (6); the soil nails (2) are made of a composite material of glass fiber and a resin matrix; a mounting hole (11) is provided through the mounting head (1); the soil nail (2) passes through the mounting hole (11); the soil nail (2) is threadedly sleeved on a mounting nut (21); and a plurality of grouting holes (22) are provided through the soil nail (2).
2. The glass fiber reinforced resin soil nail wall support system according to claim 1, characterized in that: Also includes: A stabilizing component, the stabilizing component comprising: a stabilizing part (3) and a pressing part (4), the stabilizing part (3) comprising: an air bag (31) and a panel (32), the air bag (31) being fixed on the panel (32), and the air bag (31) being in contact with the soil slope (6), an operating hole (321) being provided on the panel (32), and the pressing part (4) being arranged between adjacent mounting heads (1).
3. The glass fiber reinforced resin soil nail wall support system according to claim 2, characterized in that: The clamping portion (4) comprises: a connecting rod (41) and a connecting ear (42); the connecting rod (41) is clamped on the panel (32); a connecting groove (12) is provided on the mounting head (1); the connecting ear (42) is arranged in the connecting groove (12); and the connecting ear (42) is fixedly connected to the connecting rod (41); and a connecting component (5) is arranged between the connecting ear (42) and the mounting head (1).
4. The glass fiber reinforced resin soil nail wall support system according to claim 3, characterized in that: The clamping part (4) further comprises: a pressing plate (43) and a clamping nut (44); the pressing plate (43) is tightly attached to the mounting head (1); a through hole (431) is formed through the pressing plate (43); the soil nail (2) is penetrated through the through hole (431); and the clamping nut (44) is threadedly sleeved on the soil nail (2).
5. The glass fiber reinforced resin soil nail wall support system according to claim 4, characterized in that: A water leakage hole (16) is formed through the mounting head (1), and the water leakage hole (16) extends through the pressing plate (43).
6. The glass fiber reinforced resin soil nail wall support system according to claim 3, characterized in that: The connecting assembly (5) comprises: a connecting rod (51), a fixing rod (52) and a pushing spring (53); a connecting hole (13) is provided through the connecting groove (12); one end of the connecting rod (51) is fixed to the connecting ear (42) and the other end is arranged in the connecting hole (13); a fixing hole (14) is provided in the connecting hole (13); a receiving hole (511) is provided on the connecting rod (51); one end of the fixing rod (52) is arranged in the fixing hole (14) and the other end is arranged in the receiving hole (511); and the pushing spring (53) is fixed between the fixing rod (52) and the bottom of the receiving hole (511).
7. The glass fiber reinforced resin soil nail wall support system according to claim 6, characterized in that: The connection assembly (5) further comprises a reinforcement nail (54), one end of which is arranged in the soil slope (6) and the other end of which is arranged in the connecting hole (13).
8. The glass fiber reinforced resin soil nail wall support system according to claim 7, characterized in that: The connection assembly (5) further comprises: a limit block (55); a limit groove (15) is provided on the inner wall of the connecting hole (13); the limit block (55) is slidably disposed in the limit groove (15); and the limit block (55) is fixedly connected to the reinforcing nail (54).
9. The glass fiber reinforced resin soil nail wall support system according to claim 8, characterized in that: The connection assembly (5) further comprises: an anti-pullout nail (56), a push plate (57), a support spring (58) and a guide plate (59); a placement hole (541) is provided on the reinforcement nail (54); the push plate (57) is arranged in the placement hole (541); the support spring (58) is fixed between the push plate (57) and the bottom of the placement hole (541); the guide plate (59) is fixed on the push plate (57); a clearance hole (52) is provided through the inner wall of the placement hole (541); a connecting hole (23) is provided through the soil nail (2); one end of the anti-pullout nail (56) is arranged in the clearance hole (52); the other end passes through the connecting hole (23) and extends into the soil nail (2).
10. The construction process of the glass fiber reinforced resin soil nail wall support system according to any one of claims 1 to 9, characterized in that: The following steps are involved: S1: excavating a foundation pit according to construction requirements to form a soil slope (6); S2: drilling holes in the soil slope (6) and placing soil nails (2) in the holes; S3: insert the mounting head (1) onto the soil nail (2), and tighten the mounting nut (21); S4: Inflate a small amount of gas into the air bag (31) so that the air bag (31) maintains its shape and is easy to glue to the panel (32), and then lay the panel (32) on the soil slope (6); S5: fixing the connecting rod (41) between adjacent mounting heads (1) to press the panel (32); S6: inserting the pressing plate (43) onto the soil nail (2), and tightening the pressing nut (44); S7: injecting grout into the soil nail (2) until the grout flows out through the overflow hole (22) and consolidates with the soil; S8: Fill the air bag (31) with gas again. Through the secondary loading and inflation, the panel (32) and the soil nail (2) can bear the force together.