Factory-like assembly method for pipe gallery square cabin cluster
Through the factory assembly method of the pipe corridor square cabin cluster, multiple assembly line areas are used to assemble and dock the pipe corridor and square cabin, the difficulties in assembly and manufacturing of subsea data centers are solved and efficient construction of subsea data centers are achieved.
Patent Information
- Application Number
- CN202411317749.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-20
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-09-20
AI Technical Summary
There are difficulties in assembly and manufacturing of pipe corridors and cabins in submarine data centers, and the existing technology has not been effectively solved, and the engineering needs to span multiple manufacturing processes and structures, resulting in less research.
Using the factory assembly method of pipe corridor square cabin cluster, the pipe corridor and the cabin are divided into multiple assembly line areas through the production assembly line, including steel bar binding area, casting area, docking area and outfitting area, so as to realize the assembly of pipe corridor and the cabin The SPMT vehicle is used to synchronously connect the symmetrical cabin, and the installation of ancillary facilities is completed in the installation area.
It effectively deals with the manufacturing and assembly problems of submarine data centers, realizes factory assembly of pipeline cabin clusters, improves the efficiency and quality of the project, and has promotion and application value.
Smart Images

Figure CN118958371A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of submarine data center construction, and in particular to a factory assembly method for a pipe gallery square cabin cluster. Background Art
[0002] Submarine data centers are an important part of the "new infrastructure". When using submarine corridor structures for construction, it is usually necessary to solve the problems of manufacturing and assembly of submarine data center corridors and shelters to realize intelligent manufacturing of corridors and shelters. At present, there is no assembly solution that can completely solve this problem. At the same time, the project needs to span multiple manufacturing processes. The manufacturing and assembly of multiple structures and processes is a major difficulty in engineering construction, and there is relatively little research on this issue.
[0003] Starting from the assembly of pipe gallery square cabin clusters, a factory assembly method for pipe gallery square cabin clusters is studied to solve the difficulties in the assembly and manufacturing of submarine data centers, and a factory assembly method for pipe gallery square cabin clusters is proposed; this method can effectively deal with the problems of manufacturing and assembly of submarine data centers, and has promotion and application value for the construction of submarine data centers. Summary of the invention
[0004] The purpose of the present invention is to overcome the above problems existing in the prior art and greatly improve its technical effect on the basis of the original technology; to this end, the present invention provides a factory assembly method for a cluster of pipe gallery shelters, the method comprising:
[0005] S100, production line; the production line includes a pipe gallery prefabrication line and a shelter docking assembly line;
[0006] S101, the pipe gallery prefabrication line is used to assemble the pipe gallery and dock the assembled pipe gallery with the shelter; the pipe gallery prefabrication line includes: a steel bar binding area, a casting area, a docking area and an outfitting area; the steel bar binding area is used to bind steel bars into a steel cage, and the steel cage is a steel support for the pipe gallery structure; the casting area is used to cast the steel cage; the docking area is used to dock and install the shelter and the pipe gallery; the outfitting area refers to the installation of other ancillary facilities after the pipe gallery and the shelter are docked, and the other ancillary facilities include: the installation of the internal electromechanical system of the pipe gallery, the ventilation and lighting system, the sidewalk and the ladder ancillary facilities;
[0007] S102, the cabin docking assembly line is used to assemble various parts of the cabin and dock the assembled cabin with the pipe gallery; the cabin docking assembly line includes: an assembly area, a docking area and an outfitting area; the assembly area refers to the installation of internal servers, cooling systems and joints in the cabin; the docking area refers to docking the cabin with the pipe gallery; the outfitting area refers to the connection and installation of the cabin's ancillary facilities after the docking is completed, and the cabin's ancillary facilities include: the cabin's internal electromechanical system, ventilation and lighting, and ladder ancillary facilities; the docking area and outfitting area of the pipe gallery prefabrication line are the same as the docking area and outfitting area of the cabin docking assembly line;
[0008] S103. The process of the pipe gallery prefabrication line includes: firstly, tying the steel bars in the steel bar tying area in order, then moving the whole to the pouring area to pour concrete, then after the pouring is completed, moving the whole to the docking area to dock the shelters, and after the docking of the shelters is completed, moving the whole to the outfitting area to outfit other ancillary facilities;
[0009] S104. The process of the container docking assembly line includes: installing the internal server, cooling system and joints of the container in the assembly area; after the assembly in the assembly area is completed, the assembled container is moved to the docking area to dock with the pipe gallery; after the docking of the container and the pipe gallery is completed, the container is moved as a whole to the outfitting area to complete the installation of ancillary facilities.
[0010] Specifically, the pipeline corridor prefabrication line includes: first, welding the waterproof bottom plate of the pipeline corridor in the steel bar binding area, then binding the steel bar cage, and binding the pipeline corridor in sections; the steel bar cage includes a bottom plate, side walls, an intermediate layer and a top plate, and the steel bars are positioned by auxiliary positioning steel plates and steel supports, and the inner surface of the steel bar cage is positioned by templates and auxiliary steel supports; the embedded parts of the square cabin support structure are laid out and fixed to the steel bar cage; the casting template is installed, and the casting template includes an outer template and an inner template, and the length of the casting template is the same as the length of the pipeline corridor; then, the segmented pipeline corridor steel bar cage is transferred to the casting area by a synchronously controlled hydraulic trolley, and the next segmented steel bar cage is made in the same way in the steel bar binding area; pouring starts from each section of the pipeline corridor close to the docking area until the corresponding section is poured with concrete as a whole. After pouring and curing to a predetermined strength, the corresponding section is The section pipe gallery is moved to the docking area; if the next section steel cage is completed, the next section steel cage is moved to the casting area for casting in the same way, and the corresponding section pipe gallery that has been cured to the predetermined strength is moved to the docking area; finally, the corresponding section pipe gallery is docked in the docking area, and the cabin docking is installed in a way that the two cabins are docked symmetrically about the section pipe gallery and the two cabins are docked at the same time; after the cabin docking is completed and the current work of other sections is completed, the corresponding section pipe gallery and the cabin that have been docked are moved to the outfitting area as a whole, and the docking work of the next section pipe gallery is carried out until all sections are docked; in the outfitting area, all sections are first connected in sequence to form a complete pipe gallery cabin cluster structure, and then the connected pipe gallery cabin cluster structure is installed including: internal electromechanical system, ventilation and lighting system, sidewalks and ladder ancillary facilities.
[0011] Specifically, the square cabin docking assembly line includes: first, in the assembly area, the square cabin shell is assembled and welded in sections, the electromechanical facilities are laid out, the internal pipes of the cooling system are installed, the internal rack infrastructure of the square cabin is installed, and the server is laid out and the electromechanical facilities of the server are installed, and the embedded parts of the square cabin structure are processed; secondly, the two symmetrical square cabins are moved to the docking area by using the SP MT vehicle, and the corresponding segmented pipe corridors are docked at the positions, and the pipe corridors and the square cabins are bolted together. After the joints are installed, the fixed structure of the square cabin is installed; finally, after the docking of the pipe corridor and the square cabin is completed, the docked pipe corridor and the square cabin cluster is moved to the outfitting area to connect and install the electromechanical ancillary facilities in the pipe corridor and the square cabin.
[0012] Specifically, the square cabin joint consists of two parts, one is the joint fixed to the pipe gallery, and the other is the joint of the square cabin; the joint fixed to the pipe gallery includes a steel cylinder, an internal steel anchor plate, an end connecting circular anchor plate and a waterproof structure; the joint of the square cabin uses bolts to connect the circular anchor plates at both ends of the joint, and installs OMEGA waterstop on the outside and fills with special waterproof glue.
[0013] Specifically, the SPMT vehicle includes: using a special bracket and multiple groups of SPMT vehicles for transportation and installation; first, the special bracket is arranged according to the spacing of the supporting structure of the square cabin on the pipeline corridor, and a double-layer truss structure combination is adopted at the bottom of the special bracket; secondly, a hydraulic jack is configured on the top of each group of SPMT vehicles, and the special bracket is lifted by the hydraulic jack to achieve position adjustment during the docking process; finally, the special bracket structure is supported and moved by multiple groups of SPMT vehicles.
[0014] Specifically, after the docking of the square cabin and the pipe gallery is completed, the whole will be moved to the outfitting area, including: first, after the work of each section is completed, the work of the current stage of the steel cage binding area, casting area, docking area and outfitting area is completed, and the whole can be moved to the next work area; secondly, after the docking of the square cabin and the pipe gallery is completed, the whole will be moved to the outfitting area and transported by two rows of transfer trolleys at the bottom; before the transfer, supports are arranged at the lower part of the predetermined position of the pipe gallery, and the entire pipe gallery structure is supported by a combination of steel plate structure and rubber; during the transfer, all the transfer trolleys are moved to the bottom and the central axis of the trolley is lifted synchronously by the jack for transfer, the trolley moves to the predetermined position of the next work area, the jack is lowered to lower the central axis of the trolley, and the pipe gallery is placed on the arranged support components, and the arranged support components are support structures arranged at the lower part of the predetermined position of the pipe gallery.
[0015] Specifically, the docking of the square cabin and the pipe gallery includes: the docking process is: first, the square cabin joints are installed on both sides of the pipe gallery simultaneously and docked, requiring the joint bolts to be installed symmetrically and in the same position, and the preload force of each bolt to be consistent; secondly, at a preset speed, the SPMT vehicles of the two square cabins are released synchronously so that the two symmetrical square cabins are subjected to the same balanced force at the same time; after the deformation remains stable, the deformation and installation of the joints are checked, and re-docking is performed if any abnormality is found; finally, after the joints are installed, OMEGA waterproof glue is injected.
[0016] Specifically, after the square cabin is docked, it is moved as a whole to the outfitting area for outfitting of other ancillary facilities, including: connecting the electromechanical system inside the corridor; installing the ventilation and lighting system in the corridor; paving the road surface of the lane in the corridor; installing ancillary facilities including sidewalks and ladders in the corridor; and installing the steel end shell and sealing door of the corridor.
[0017] Specifically, the completion of the installation of ancillary facilities includes: after the installation of ancillary facilities is completed, the integrated debugging of the corridor cabin is also required, and the steps of the integrated debugging are: first, after the work of all partitions is completed, the corridor cabin is moved to the shallow water area as a whole; secondly, the entrance of the corridor cabin is closed, and when the water depth exceeds the corridor height by 0.5m, the corridor cabin structure is tested for waterproofness and waterproof measures are taken; finally, the external electromechanical system and network are connected, the cabin operation debugging is carried out, and the operating status of the electromechanical, ventilation and lighting ancillary equipment in each cabin and the corridor is checked.
[0018] The beneficial effects of the present invention are:
[0019] The present invention provides a factory assembly method for a pipe gallery and square cabin cluster, which provides a pipe gallery and square cabin cluster assembly method for assembling, docking and debugging pipe gallery and square cabins; the method is used to solve the difficulties and problems in the assembly and manufacturing of submarine data centers, can effectively handle the problems of manufacturing and assembly of submarine data centers, and has promotion and application value for the construction of submarine data centers. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 : A flow chart of a factory assembly method for a pipe gallery shelter cluster of the present invention.
[0021] Figure 2 : Schematic diagram of the partition composition of the pipeline of the present invention. DETAILED DESCRIPTION
[0022] The specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings; it should be understood that the specific embodiments given here are only used to illustrate and explain the present invention and cannot be used to limit the present invention.
[0023] like Figure 1As shown: is a flow chart of a factory assembly method of a pipe gallery and shelter cluster according to the present invention, the flow chart includes: S100, production line; the production line includes a pipe gallery prefabrication line and a shelter docking assembly line; S101, the pipe gallery prefabrication line is used to assemble the pipe gallery and dock the assembled pipe gallery with the shelter; the pipe gallery prefabrication line includes: a steel bar binding area, a casting area, a docking area and an outfitting area; the steel bar binding area is used to bind steel bars into a steel bar cage, and the steel bar cage is a steel bar support of the pipe gallery structure; The casting area is used to cast the steel cage; the docking area is used to dock and install the square cabin and the pipe gallery; the outfitting area refers to the installation of other ancillary facilities after the pipe gallery and the square cabin are docked, and the other ancillary facilities include: the installation of the electromechanical system inside the pipe gallery, the ventilation and lighting system, the sidewalk and the ladder ancillary facilities; S102, the square cabin docking assembly line is used to assemble the various parts of the square cabin and dock the assembled square cabin with the pipe gallery; the square cabin docking assembly line includes: an assembly area, a docking area and an outfitting area; the assembly The installation area refers to the installation of internal servers, cooling systems and joints in the square cabin; the docking area refers to the docking of the square cabin with the pipe gallery; the outfitting area refers to the connection and installation of the square cabin's ancillary facilities after the docking is completed. The ancillary facilities of the square cabin include: the internal electromechanical system of the square cabin, ventilation and lighting, and ladder ancillary facilities; the docking area and outfitting area of the pipe gallery prefabrication line are the same as the docking area and outfitting area of the square cabin docking assembly line; S103, the process of the pipe gallery prefabrication line includes: first, in the steel bar binding area, the steel bars are tied in order. The container is then tied and moved as a whole to the pouring area for concrete pouring. After the pouring is completed, it is moved as a whole to the docking area for docking of the container. After the docking of the container is completed, it is moved as a whole to the outfitting area for outfitting of other ancillary facilities. S104. The process of the container docking assembly line includes: in the assembly area, including: installation of the internal server, cooling system and joints of the container; after the assembly in the assembly area is completed, the assembled container is moved to the docking area for docking with the pipe gallery; after the docking of the container and the pipe gallery is completed, it is moved as a whole to the outfitting area to complete the installation of ancillary facilities.
[0024] Specifically, the present invention divides the production line into a pipe gallery prefabrication line and a cabin docking assembly line; first, according to the process of the pipe gallery prefabrication line, steel bars are tied in sequence in the steel bar tying area, and then the whole is moved to the pouring area to pour concrete, and then after the pouring is completed, the whole is moved to the docking area; according to the process of the cabin docking assembly line, the internal server, cooling system and joint of the cabin are installed in the assembly area; after the assembly in the assembly area is completed, the assembled cabin is moved to the docking area; then, the tied and assembled pipe gallery and cabin are docked in the docking area, and after the docking is completed, the whole is moved to the outfitting area to install the ancillary facilities of the pipe gallery and cabin.
[0025] S100, production line; the production line includes a pipe gallery prefabrication line and a shelter docking assembly line.
[0026] In the above embodiment, specifically, the factory assembly of the pipe gallery and cabin cluster of the present invention is completed by the pipe gallery prefabrication line and the cabin docking assembly line. After the assembly is completed, debugging work is carried out to check the quality of the pipe gallery and cabin cluster equipped according to the present invention.
[0027] S101. The pipe gallery prefabrication line is used to assemble the pipe gallery and connect the assembled pipe gallery with the shelter. The pipe gallery prefabrication line includes: a steel bar binding area, a casting area, a docking area and an outfitting area. The steel bar binding area is used to bind steel bars into a steel cage, which is a steel support for the pipe gallery structure. The casting area is used to cast the steel cage. The docking area is used to connect and install the shelter and the pipe gallery. The outfitting area refers to the installation of other ancillary facilities after the pipe gallery and the shelter are connected. The other ancillary facilities include: the installation of the internal electromechanical system of the pipe gallery, the ventilation and lighting system, the sidewalk and the ladder ancillary facilities.
[0028] In the above embodiment, specifically, several processes from assembling the pipe gallery to connecting with the shelters are completed in sequence through several partitions of the pipe gallery prefabrication line, thereby completing the pipe gallery prefabrication task of the pipe gallery and shelter cluster work.
[0029] S102, the cabin docking assembly line is used to assemble various parts of the cabin and dock the assembled cabin with the pipe gallery; the cabin docking assembly line includes: an assembly area, a docking area and an outfitting area; the assembly area refers to the installation of internal servers, cooling systems and connectors in the cabin; the docking area refers to docking the cabin with the pipe gallery; the outfitting area refers to the connection and installation of the cabin's ancillary facilities after the docking is completed, and the cabin's ancillary facilities include: the cabin's internal electromechanical system, ventilation and lighting, and ladder ancillary facilities; the docking area and outfitting area of the pipe gallery prefabrication line are the same as the docking area and outfitting area of the cabin docking assembly line.
[0030] In the above embodiment, specifically, several processes from the modular cabin assembly to the connection with the pipe gallery are completed in sequence through several partitions of the modular cabin docking assembly line, thereby completing the modular cabin docking assembly task of the pipe gallery modular cabin cluster work.
[0031] S103. The process of the pipe gallery prefabrication line includes: firstly, tying the steel bars in the steel bar tying area in order, then moving the whole to the pouring area to pour concrete, and then after the pouring is completed, moving the whole to the docking area to dock the shelters, and after the shelters are docked, moving the whole to the outfitting area to outfit other ancillary facilities.
[0032] In the above embodiment, specifically, first, the waterproof bottom plate of the pipe gallery is welded in the steel bar binding area, and then the steel bar cage is tied, and the pipe gallery is tied in sections; the steel bar cage includes a bottom plate, a side wall, an intermediate layer and a top plate, and the steel bars are positioned by auxiliary positioning steel plates and steel supports, and the inner surface of the steel bar cage is positioned by templates and auxiliary steel supports; the embedded parts of the square cabin support structure are arranged and fixed to the steel bar cage; the casting template is installed, and the casting template includes an outer template and an inner template, and the length of the casting template is the same as the length of the pipe gallery; then, the segmented pipe gallery steel bar cage is transferred to the casting area by a synchronously controlled hydraulic trolley, and the next segmented steel bar cage is made in the same way in the steel bar binding area; pouring starts from each section of the pipe gallery close to the docking area until the corresponding section is poured with concrete as a whole. After pouring and curing to a predetermined strength, the corresponding segmented pipe gallery is The corridor is moved to the docking area; if the next segmented steel cage is completed, the next segmented steel cage is moved to the casting area for casting in the same way, and the corresponding segmented corridor that has been cured to the predetermined strength is moved to the docking area; finally, the corresponding segmented corridor is docked in the docking area, and the cabin docking is installed in a way that the two cabins are docked symmetrically about the segmented corridor and the two cabins are docked at the same time; after the cabin docking is completed and the current work of other sections is completed, the corresponding segmented corridor and the cabin that have been docked are moved to the outfitting area as a whole, and the docking work of the next segmented corridor is carried out until all the segments are docked; in the outfitting area, all the sections are first connected in sequence to form a complete corridor cabin cluster structure, and then the connected corridor cabin cluster structure is installed including: internal electromechanical system, ventilation and lighting system, sidewalks and ladder ancillary facilities.
[0033] S104. The process of the container docking assembly line includes: installing the internal server, cooling system and joints of the container in the assembly area; after the assembly in the assembly area is completed, the assembled container is moved to the docking area to dock with the pipe gallery; after the docking of the container and the pipe gallery is completed, the container is moved as a whole to the outfitting area to complete the installation of ancillary facilities.
[0034] In the above embodiment, specifically, first, in the assembly area, the shell of the container is assembled and welded in sections, the electromechanical facilities are laid out, the internal piping of the cooling system is installed, the basic structure of the rack inside the container is installed, and the server is laid out and the electromechanical facilities of the server are installed, and the embedded parts of the container structure are processed; secondly, the two symmetrical containers are moved to the docking area by using the SPMT vehicle, and the containers are docked with the corresponding segmented pipe corridors, and the pipe corridor and the container joints are bolted together, and after the joints are installed, the fixed structure of the container is installed; finally, after the connection of the pipe corridor and the container is completed, the connected container corridor cluster is moved to the outfitting area, and the electromechanical ancillary facilities in the container corridor are connected and installed; the SPMT vehicle is a self-propelled modular transport vehicle, usually composed of multiple modules, and the modules can be combined into different configurations to accommodate loads of different sizes and weights, and is often used for the transportation of heavy and ultra-heavy goods.
[0035] In the above embodiment, specifically, the square cabin joint is composed of two parts, one part is a joint fixed with the pipe gallery, and the other part is a joint of the square cabin; the joint fixed with the pipe gallery comprises a steel cylinder, an internal steel bar anchor plate, an end connecting ring anchor plate and a waterproof structure; the square cabin joint uses bolts to connect the ring anchor plates at both ends of the joint, and an OMEGA waterstop is installed on the outside and filled with a special waterproof glue;
[0036] In the above embodiment, preferably, before the joints are butt-jointed, the OMEGA waterstop is first put on the joints at the ends of the pipe gallery, then bolted, then the OMEGA waterstop is put on the bolts, and finally waterproof filling glue is poured.
[0037] In the above embodiment, specifically, the SPMT vehicle includes: a special bracket and multiple groups of SPMT vehicles are used for transportation and installation; first, the special bracket is arranged according to the spacing of the supporting structure of the square cabin on the pipeline corridor, and a double-layer truss structure combination is used at the bottom of the special bracket; secondly, a hydraulic jack is configured on the top of each group of SPMT vehicles, and the special bracket is lifted by the hydraulic jack to achieve position adjustment during the docking process; finally, the special bracket structure is supported and transported by multiple groups of SPMT vehicles.
[0038] In the above embodiment, preferably, the dedicated bracket is arranged according to the spacing of the supporting structures of the square cabins on the pipe gallery according to the spacing of two asymmetric adjacent square cabins, so as to support the square cabins during the docking process between the square cabins and the pipe gallery.
[0039] In the above embodiment, specifically, after the work of each partition is completed, the work of the steel cage binding area, casting area, docking area and outfitting area in the current stage is completed, and the whole unit can be moved to the next work area; wherein, after the docking of the square cabin and the pipe gallery is completed, the whole unit will be moved to the outfitting area and transported by two rows of transfer trolleys at the bottom; before the transport, supports are arranged at the lower part of the predetermined position of the pipe gallery, and the entire pipe gallery structure is supported by a steel plate structure and a rubber combination; during the transport, all the transfer trolleys are moved to the bottom and the central axis of the trolley is synchronously lifted by the jack for transport, the trolley moves to the predetermined position of the next work area, the jack is lowered to lower the central axis of the trolley, and the pipe gallery is placed on the arranged support components, and the arranged support components are support structures arranged at the lower part of the predetermined position of the pipe gallery, that is, support structures of the arranged steel plate structure and rubber combination.
[0040] In the above embodiment, specifically, the process of docking the pipe gallery and the shelter is as follows: first, the shelter joints are installed and docked simultaneously on both sides of the pipe gallery, requiring that the joint bolts are installed symmetrically and in the same position, and the preload force of each bolt is kept consistent; secondly, at a preset speed, the SPMT vehicles of the two shelters are released synchronously so that the two symmetrical shelters are subjected to the same balanced force at the same time; after the deformation remains stable, the deformation and installation of the joints are checked, and if any abnormality is found, the joints are re-docking; finally, after the joints are installed, OMEGA waterproof glue is injected.
[0041] In the above embodiment, specifically, after the docking of the container cabin is completed, it is moved as a whole to the outfitting area for outfitting of other ancillary facilities, including: connecting the electromechanical system inside the corridor; installing the ventilation and lighting system in the corridor; paving the road surface of the lane in the corridor; installing ancillary facilities including sidewalks and ladders in the corridor; and installing the steel end shell and sealing door of the corridor.
[0042] In the above embodiment, specifically, after the installation of the ancillary facilities is completed, the integrated debugging of the corridor cabin is also required, and the steps of the integrated debugging are: first, after the work of all partitions is completed, the corridor cabin is moved to the shallow water area as a whole; all partitions refer to that all partition work of the corridor and the cabin is completed, that is, the entire corridor cabin cluster is assembled; secondly, the entrance of the corridor cabin is closed, and when the water depth exceeds the corridor height by 0.5m, the corridor cabin structure is waterproof tested and waterproof measures are taken; finally, the external electromechanical system and network are connected, the cabin operation debugging is carried out, and the operating status of the electromechanical, ventilation and lighting ancillary equipment of each cabin and the corridor is checked; if the operating status is normal and the various indicators of the corridor cabin cluster are normal, it is proved that the corridor cabin cluster assembled by the present invention is qualified.
[0043] like Figure 2As shown: is a schematic diagram of the partition composition of the assembly line of the present invention; the schematic diagram is composed of a pipe gallery prefabrication assembly line and a square cabin docking assembly line; the pipe gallery prefabrication assembly line includes: a steel bar binding area, a casting area, a docking area and an outfitting area; the square cabin docking assembly line includes: an assembly area, a docking area and an outfitting area; in addition, the docking area and the outfitting area of the pipe gallery prefabrication assembly line and the square cabin docking assembly line are respectively the same partition; through this schematic diagram, the present invention performs factory assembly of pipe gallery square cabin clusters according to this schematic diagram The process is as follows: first, the sections of the corridor are tied and cast in the steel bar tying area and casting area of the corridor prefabrication line, and the cast sections of the corridor are moved to the docking area; at the same time, the internal servers, cooling systems and joints of the cabins are installed in the assembly area of the cabin docking assembly line, and the assembled cabins are also moved to the docking area. After the corridors of different sections are connected in the docking area, the corridor cabins are docked. After the docking is completed, the corridor cabins are moved as a whole to the outfitting area for the installation of ancillary facilities.
[0044] It should be understood that the above-mentioned embodiments are one or more embodiments of the present invention, and there are many other embodiments and variations thereof based on the present invention; the variations and modifications made by ordinary technicians in this industry through the present invention without making pioneering innovations all fall within the scope of protection of the present invention.
Claims
1. A factory assembly method for a cluster of pipe gallery shelters. It is characterized in that The method comprises: S100, production line; the production line includes a pipe gallery prefabrication line and a shelter docking assembly line; S101, the pipe gallery prefabrication line is used to assemble the pipe gallery and dock the assembled pipe gallery with the shelter; the pipe gallery prefabrication line includes: a steel bar binding area, a casting area, a docking area and an outfitting area; the steel bar binding area is used to bind steel bars into a steel cage, and the steel cage is a steel support for the pipe gallery structure; the casting area is used to cast the steel cage; the docking area is used to dock and install the shelter and the pipe gallery; the outfitting area refers to the installation of other ancillary facilities after the pipe gallery and the shelter are docked, and the other ancillary facilities include: the installation of the internal electromechanical system of the pipe gallery, the ventilation and lighting system, the sidewalk and the ladder ancillary facilities; S102, the cabin docking assembly line is used to assemble various parts of the cabin and dock the assembled cabin with the pipe gallery; the cabin docking assembly line includes: an assembly area, a docking area and an outfitting area; the assembly area refers to the installation of internal servers, cooling systems and joints in the cabin; the docking area refers to docking the cabin with the pipe gallery; the outfitting area refers to the connection and installation of the cabin's ancillary facilities after the docking is completed, and the cabin's ancillary facilities include: the cabin's internal electromechanical system, ventilation and lighting, and ladder ancillary facilities; the docking area and outfitting area of the pipe gallery prefabrication line are the same as the docking area and outfitting area of the cabin docking assembly line; S103. The process of the pipe gallery prefabrication line includes: firstly, tying the steel bars in the steel bar tying area in order, then moving the whole to the pouring area to pour concrete, then after the pouring is completed, moving the whole to the docking area to dock the shelters, and after the docking of the shelters is completed, moving the whole to the outfitting area to outfit other ancillary facilities; S104. The process of the container docking assembly line includes: installing the internal server, cooling system and joints of the container in the assembly area; after the assembly in the assembly area is completed, the assembled container is moved to the docking area to dock with the pipe gallery; after the docking of the container and the pipe gallery is completed, the container is moved as a whole to the outfitting area to complete the installation of ancillary facilities.
2. According to the factory assembly method of the pipe gallery shelter cluster according to claim 1, It is characterized in that The pipe gallery prefabrication line comprises: first, welding the waterproof bottom plate of the pipe gallery in the steel bar binding area, then binding the steel bar cage, and binding the pipe gallery in sections; the steel bar cage comprises a bottom plate, a side wall, an intermediate layer and a top plate, and the steel bars are positioned by auxiliary positioning steel plates and steel supports, and the inner surface of the steel bar cage is positioned by templates and auxiliary steel supports; the embedded parts of the square cabin support structure are arranged and fixed to the steel bar cage; the casting template is installed, and the casting template comprises an outer template and an inner template, and the length of the casting template is the same as the length of the pipe gallery; then, the steel bar cage of the pipe gallery with sections is transferred to the casting area by a synchronously controlled hydraulic trolley, and the next section steel bar cage is made in the same way in the steel bar binding area; pouring starts from each section of the pipe gallery near the docking area until the corresponding section is poured with concrete as a whole, and after pouring and curing to a predetermined strength, the corresponding section of the pipe gallery is The corridor is moved to the docking area; if the next segmented steel cage is completed, the next segmented steel cage is moved to the casting area for casting in the same way, and the corresponding segmented corridor that has been cured to the predetermined strength is moved to the docking area; finally, the corresponding segmented corridor is docked in the docking area, and the cabin docking is installed in a way that the two cabins are docked symmetrically about the segmented corridor and the two cabins are docked at the same time; after the cabin docking is completed and the current work of other sections is completed, the corresponding segmented corridor and the cabin that have been docked are moved to the outfitting area as a whole, and the docking work of the next segmented corridor is carried out until all the segments are docked; in the outfitting area, all the sections are first connected in sequence to form a complete corridor cabin cluster structure, and then the connected corridor cabin cluster structure is installed including: internal electromechanical system, ventilation and lighting system, sidewalks and ladder ancillary facilities.
3. According to the factory assembly method of a pipe gallery shelter cluster according to claim 1, It is characterized in that The square cabin docking assembly line includes: first, in the assembly area, sequentially assembling and welding the square cabin shell in sections, laying out electromechanical facilities, installing the internal piping of the cooling system, installing the internal rack infrastructure of the square cabin, laying out the server and installing the electromechanical facilities of the server, and processing the embedded parts of the square cabin structure; second, using the SPMT vehicle to move the two symmetrical square cabins to the docking area, and docking them with the corresponding segmented pipe corridors, bolting the pipe corridor and the square cabin joints, and installing the fixed structure of the square cabin after the joints are installed; finally, after the pipe corridor and square cabin docking is completed, the docked pipe corridor and square cabin cluster is moved to the outfitting area, and the electromechanical ancillary facilities in the pipe corridor and square cabin are connected and installed.
4. According to the factory assembly method of the pipe gallery shelter cluster according to claim 3, It is characterized in that The square cabin joint consists of two parts, one is the joint fixed to the pipe gallery, and the other is the joint of the square cabin; the joint fixed to the pipe gallery includes a steel cylinder, an internal steel anchor plate, an end connecting circular anchor plate and a waterproof structure; the square cabin joint uses bolts to connect the circular anchor plates at both ends of the joint, and installs OMEGA waterstop on the outside, filled with special filling waterproof glue.
5. According to the factory assembly method of the pipe gallery shelter cluster according to claim 3, It is characterized in that The SPMT vehicle includes: using a special bracket and multiple groups of SPMT vehicles for transportation and installation; first, the special bracket is arranged according to the spacing of the supporting structure of the square cabin on the pipeline corridor, and the bottom of the special bracket adopts a double-layer truss structure combination; secondly, a hydraulic jack is configured on the top of each group of SPMT vehicles, and the special bracket is lifted by the hydraulic jack to achieve position adjustment during the docking process; finally, the special bracket structure is supported and moved by multiple groups of SPMT vehicles.
6. A factory assembly method for a pipe gallery shelter cluster according to claim 1, It is characterized in that After the docking of the square cabin and the pipe gallery is completed, the whole will be moved to the outfitting area, including: first, after the work of each section is completed, the work of the current stage of the steel cage binding area, casting area, docking area and outfitting area is completed, and the whole can be moved to the next work area; secondly, after the docking of the square cabin and the pipe gallery is completed, the whole will be moved to the outfitting area and transported by two rows of transfer trolleys at the bottom; before the transfer, support is arranged at the lower part of the predetermined position of the pipe gallery, and the entire pipe gallery structure is supported by a steel plate structure and a rubber combination; during the transfer, all the transfer trolleys are moved to the bottom and the central axis of the trolley is lifted synchronously by the jack for transfer, the trolley moves to the predetermined position of the next work area, the jack is lowered to lower the central axis of the trolley, and the pipe gallery is placed on the arranged support components, and the arranged support components are support structures arranged at the lower part of the predetermined position of the pipe gallery.
7. According to the factory assembly method of a pipe gallery shelter cluster according to claim 1, It is characterized in that The docking of the square cabin and the pipe gallery includes: the docking process is: first, the square cabin joints are installed on both sides of the pipe gallery simultaneously and docked, requiring that the joint bolts are installed symmetrically and in the same position, and the preload force of each bolt is kept consistent; secondly, the SPMT vehicles of the two square cabins are released synchronously at a preset speed, so that the two symmetrical square cabins are subjected to the same balanced force at the same time; after the deformation remains stable, the deformation and installation of the joint are checked, and the joint is re-docking if abnormalities are found; finally, after the joint is installed, OMEGA waterproof glue is poured.
8. According to the factory assembly method of a pipe gallery shelter cluster according to claim 1, It is characterized in that After the square cabin is docked, it is moved as a whole to the outfitting area for outfitting of other ancillary facilities, including: connecting the electromechanical system inside the corridor; installing the ventilation and lighting system in the corridor; paving the road surface of the lane in the corridor; installing ancillary facilities including sidewalks and ladders in the corridor; and installing the steel end shell and sealing door of the corridor.
9. According to the factory assembly method of a pipe gallery shelter cluster according to claim 1, It is characterized in that The completion of the installation of the ancillary facilities includes: after the completion of the installation of the ancillary facilities, the integrated debugging of the corridor cabin is also required, and the steps of the integrated debugging are: first, after the work of all partitions is completed, the corridor cabin is moved to the shallow water area as a whole; secondly, the entrance of the corridor cabin is closed, and when the water depth exceeds the corridor height by 0.5m, the corridor cabin structure waterproof test is carried out and waterproof measures are taken; finally, the external electromechanical system and network are connected, the cabin operation debugging is carried out, and the operating status of the electromechanical, ventilation and lighting ancillary equipment in each cabin and the corridor is checked.
Citation Information
Patent Citations
Assembly line prefabrication system and method of immersed tube
CN113878704A
Seabed data center of HDPE pipe gallery and construction method
CN118639690A
Data cabin
CN219395323U
Submersible data center mountable on a submersible platform
US20240125078A1