Assembling construction method for large steel structure roof
Through the method of assembling and lifting of trusses, the difficulty of assembling and lifting in the construction of large-span steel truss roofs is solved, high-precision and high-efficiency construction is achieved, and the installation quality of steel structure roofs is improved.
Patent Information
- Application Number
- CN202411057305.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-11-15
AI Technical Summary
During the construction of large-span steel truss roofs, there are problems such as assembly and lifting, difficulty in controlling deformation, and difficult to control the accuracy of node installation, which leads to great difficulty in construction technology.
The method of assembling and upgrading of the sub-truss is adopted to partition the sub-truss and floor trusses. Through tire frame elevation control, line control and welding deformation control, the assembly accuracy and efficiency are ensured and connection errors are reduced.
It realizes high-precision and high-efficiency construction of large steel structure roofs, improves the installation quality and accuracy of steel structure roof trusses, and reduces connection errors during assembly.
Smart Images

Figure CN118958695A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of building structures, and in particular relates to an assembling construction method for a large steel structure roof. Background Art
[0002] For the construction of large-scale subway and high-speed rail stations, most of them are currently built by combining steel structure with concrete, which has the advantages of large spatial span, stable structure, and convenient installation and construction. However, when constructing large-span steel truss roofs, the stress conditions of large-span steel truss roof structures are relatively complex, resulting in greater construction process difficulties, and technical difficulties such as difficulty in assembly and hoisting, difficulty in controlling deformation, and difficulty in controlling node installation accuracy.
[0003] Therefore, in view of the above situation, there is an urgent need to provide an assembly construction method for a large steel structure roof to overcome the shortcomings in current practical applications. Summary of the invention
[0004] In view of the above situation, in order to overcome the defects of the prior art, the present invention provides a method for assembling and constructing a large steel structure roof, which effectively solves the problems in the above background technology.
[0005] To achieve the above object, the present invention provides the following technical solution: a method for assembling a large steel structure roof, the method comprising the following steps:
[0006] Step 1: Assemble the secondary truss on the ground;
[0007] The steps of assembling the secondary truss on the ground include:
[0008] S1.1: Secondary truss assembly and scaffolding erection;
[0009] S1.2: Position and install the main chord of the secondary truss;
[0010] S1.3: Positioning and installation of secondary truss web members;
[0011] S1.4: The secondary truss is inspected and welded as a whole;
[0012] Step 2: Assemble the floor trusses;
[0013] The steps of assembling the floor trusses include:
[0014] S2.1: Erection of floor truss assembly scaffolding;
[0015] S2.2: Positioning and installation of main chord members of floor trusses;
[0016] S2.3: Positioning and installation of floor truss web members;
[0017] S2.4: Assembly of peripheral main trusses;
[0018] S2.5: Assemble the secondary trusses using the qualified secondary trusses tested in S1.4;
[0019] S2.6: Assembly of main trusses of roof skylights;
[0020] S2.7: Skylight truss assembly;
[0021] S2.8: Assembly of side span main trusses;
[0022] S2.9: Positioning of secondary trusses between primary trusses;
[0023] S2.10: Assembly of secondary trusses and secondary beams in the other direction;
[0024] S2.11: Assemble the next primary and secondary trusses;
[0025] S2.12: Welding and deformation control of trusses.
[0026] As a further optimization of the technical solution, the specific steps of erecting the secondary truss assembly frame are:
[0027] A template is set up on the tire frame to strictly control the horizontality of the upper end of the tire frame template; a car crane is used to lift the upper tire frame to the chord rod for positioning; a total station and a level are used to accurately measure and position the elevation of the tire frame to ensure that the elevation of the positioning steel plate at the upper end of the tire frame meets the error requirements.
[0028] As a further optimization of the technical solution, the specific steps of positioning and installing the main chord of the secondary truss are:
[0029] According to the plane projection of each member, draw the positioning line, the center line of the upper and lower chords and web members of the truss on the steel platform;
[0030] The specific steps of positioning the secondary truss web are:
[0031] A truck crane is used to hoist and position the straight web, and two supporting frame templates are set under the web. After positioning, the straight web and chord are positioned and welded;
[0032] As a further optimization of the technical solution, the specific steps of the overall detection and welding of the secondary truss are:
[0033] After the assembly is completed, the total station is used to test the overall assembly accuracy. After passing the test, the positioning welds are removed to make the truss segments free, and then the next welding process is carried out. Before the truss assembly welding, welding shrinkage allowance is added to prevent large shrinkage deformation.
[0034] As a further optimization of the technical solution, the specific steps of erecting the floor truss assembly frame are:
[0035] On the floor, according to the actual plane projection coordinates of the roof truss blocks as a whole, the arch value and the longitudinal and transverse welding shrinkage allowance values are added, and the center line of the main chord rod of the truss is marked; an assembly frame is set up, and the assembly frame is set up step by step according to the assembly progress, and is welded and fixed to the embedded parts of the floor;
[0036] The steps for positioning and installing the main chord members of the floor truss are as follows:
[0037] The main chord of the truss is assembled and positioned on the assembly frame. Two support frames are required for each main chord processing segment. After positioning, the limit plate and the frame support template are used to fix the main chord. The main chord is installed symmetrically from the middle to both sides. During installation, the installation gap and the center line of the rod should be ensured to coincide with the center line of the platform.
[0038] The specific steps of positioning and installing the floor truss web are as follows:
[0039] According to the design drawings, the truss web members are installed and positioned. The members must be positioned to coincide with the plane position and center line of the truss nodes. For members with hidden welds, the next web member shall be positioned after the hidden welds are completed. The overall assembly is carried out symmetrically from the middle to both sides.
[0040] As a further optimization of the technical solution, the assembly steps of the peripheral main trusses are:
[0041] After the main trusses of the same span are assembled, the longitudinal main trusses at adjacent positions and the main trusses around the skylight are assembled. Before assembly, the truss frame is positioned and assembled first, and then the truss chords and webs are assembled;
[0042] The specific steps of assembling the secondary truss are:
[0043] When the assembly and positioning of the adjacent longitudinal main trusses and the main trusses around the skylight are completed, the secondary trusses in between, the secondary roof beams and the cross support beams are hoisted and positioned; the secondary trusses are assembled on the ground, and after assembly, they are transported to the vicinity of the installation position by a flatbed truck, and hoisted and positioned by a truck crane; when positioning the rods with hidden welds, the welding and flaw detection of the hidden welds must be completed in advance, and the next rod will be assembled after passing the inspection.
[0044] As a further optimization of the technical solution, the specific steps of assembling the main trusses of the roof skylight are:
[0045] Install adjacent main trusses, main trusses around skylights, secondary trusses, roof secondary beams and cross-bracing beams in sequence;
[0046] The specific steps of assembling the skylight truss are:
[0047] After the skylight trusses are assembled in sections on the ground, they are transported to the vicinity of the installation location, where they are hoisted and positioned in sections by a truck crane, and positioning frames are set up at different locations.
[0048] As a further optimization of the technical solution, the steps of assembling the side span main truss are:
[0049] After the assembly and positioning of the main and secondary trusses of the middle span and the skylight trusses are completed, the main trusses of the side spans are assembled; before assembly, the assembly frame is set up first, and then the assembly and positioning of the truss chords and webs are carried out respectively, starting from the assembled structure and assembling one by one towards the other side;
[0050] The specific steps of positioning the secondary trusses between the main trusses are:
[0051] After the adjacent main trusses are assembled and positioned, the secondary trusses in between are assembled and positioned in sections.
[0052] As a further optimization of the technical solution, the assembly steps of the secondary trusses and secondary beams in the other direction are:
[0053] The truck crane assembles the secondary trusses and secondary beams in the other direction;
[0054] The specific steps of assembling the next main and secondary trusses are:
[0055] A truck crane is used to assemble and position the primary and secondary trusses and secondary roof beams of the next span.
[0056] As a further optimization of the technical solution, the specific steps of welding and deformation control of the truss are:
[0057] Before the truss assembly and welding, add welding shrinkage allowance to prevent large shrinkage deformation; after the trusses between the two axis lines are assembled, the trusses are welded, CO2 gas shielded welding is used, and even numbers of welders are used to weld symmetrically from the center to both sides, and the welding sequence is from bottom to top; first weld the lower layer of rods, then weld the upper layer of rods, and perform flaw detection after welding; after the working surface is ready, the subsequent roof trusses are assembled and welded in sequence.
[0058] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention provides a method for assembling steel structure roof trusses, which performs reasonable partitioning and assembly of trusses by adopting a method for assembling and lifting sub-trusses, and performs frame elevation control, line shape control and welding deformation control on small assembly units, thereby achieving high-precision and high-efficiency construction of large-scale steel structure roof assembly, further reducing the connection errors of various truss components during the assembly process, and improving the installation quality and accuracy of steel structure roof trusses. BRIEF DESCRIPTION OF THE DRAWINGS
[0059] In order to more clearly illustrate the specific implementation of the present invention or the technical solutions in the prior art, the following will briefly introduce the drawings required for the specific implementation or the prior art description. Obviously, the drawings described below are some implementations of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. The drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention.
[0060] In the attached picture:
[0061] Figure 1 It is a flow chart of the present invention.
[0062] Figure 2 It is a schematic diagram of the assembly site layout in the present invention.
[0063] Figure 3 This is a progress diagram of the erection of the secondary truss assembly frame in the present invention.
[0064] Figure 4 It is a schematic diagram of the main truss assembly frame in the present invention.
[0065] Figure 5 It is a schematic diagram of the secondary truss positioning tire frame structure in the present invention.
[0066] Figure 6 This is a construction progress diagram of the secondary truss web member in the present invention.
[0067] Figure 7 This is a construction progress diagram of the diagonal web members of the secondary truss in the present invention.
[0068] Figure 8 This is a diagram showing the overall construction progress of the secondary truss in the present invention.
[0069] Fig. 9 It is a progress diagram of the erection of the floor truss assembly frame in the present invention.
[0070] Fig.10 This is a progress diagram of positioning and installing the main chord members of the floor truss in the present invention.
[0071] Fig.11 This is a progress diagram of the positioning and installation of the web members of the floor truss in the present invention.
[0072] Fig.12 This is a diagram showing the progress of assembling the peripheral main trusses in the present invention.
[0073] Fig.13 This is a diagram showing the progress of secondary truss assembly in the present invention.
[0074] Fig.14This is a progress diagram of the assembly of the main trusses of the roof skylight in the present invention.
[0075] Fig.15 This is a diagram showing the progress of assembling the skylight trusses of the present invention.
[0076] Fig.16 This is a diagram showing the progress of assembling the side span main truss of the present invention.
[0077] Fig.17 This is a construction progress diagram of the positioning of the secondary trusses between the main trusses in the present invention.
[0078] Fig.18 This is a diagram showing the progress of assembling the secondary trusses and secondary beams in the present invention.
[0079] Fig.19 This is a diagram showing the assembly progress of the primary and secondary trusses and the secondary roof beams in the present invention.
[0080] Fig. 20 This is a construction progress diagram of welding and deformation control of the truss of the present invention. DETAILED DESCRIPTION
[0081] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0082] The present invention is further explained below in conjunction with specific implementation modes.
[0083] According to the overall construction deployment, the roof adopts a zoned lifting construction plan. In order to speed up the assembly of the roof, the inverted triangle main trusses are assembled in situ on the elevated floor and the secondary trusses are assembled at an off-site assembly site. After the zoned assembly of the main trusses is completed, the assembled secondary trusses are transported to the elevated floor and assembled with the main trusses to form a lifting unit.
[0084] The weight of the assembled secondary truss is about 5 tons, and the weight of the main truss chord (about 12 meters in length) is about 2 tons. Since the skylight truss assembly distance is far, 50-ton truck crane and 25-ton truck crane are selected as floor assembly machinery to meet the construction requirements. The assembly site is arranged as follows: Figure 2 shown.
[0085] Specifically, see Figure 1-Figure 20 The embodiment of the present invention provides a method for assembling a large steel structure roof, the method comprising the following steps:
[0086] Step 1: Assemble the secondary truss on the ground;
[0087] The steps of assembling the secondary truss on the ground include:
[0088] S1.1: Secondary truss assembly and framing; the specific steps of secondary truss assembly and framing are as follows: set up a template on the framing frame, strictly control the horizontality of the upper edge of the framing frame template, and submit the framing frame for acceptance before use; use a car crane to hoist the chord rod to position the framing frame; use a total station and a level to precisely measure and position the framing frame elevation to ensure that the elevation of the framing frame upper edge positioning steel plate meets the error requirements;
[0089] S1.2: Positioning and installing the main chord of the secondary truss; the specific steps of positioning and installing the main chord of the secondary truss are: according to the plane projection of each member, draw the positioning line, the center line of the upper and lower chords and the web of the truss on the steel platform;
[0090] S1.3: Positioning of secondary truss web members; the specific steps of positioning the secondary truss web members are: using a truck crane to hoist and position the straight web members, and setting two supporting frame templates under the web members; after positioning, the straight web members and the chord members are positioned and welded, and at the same time, for the parts with hidden welds, the welds of the hidden parts are welded first; after the welding flaw detection of the hidden welds is completed, the oblique web members are installed and positioned;
[0091] S1.4: Overall inspection and welding of secondary trusses; the specific steps of overall inspection and welding of secondary trusses are: after assembly, use a total station to inspect the overall assembly accuracy. After passing the inspection, remove the positioning welding to make the truss segments free before the next welding process can be carried out; the improved accuracy depends largely on the control of the assembly accuracy of small assembly units. The small assembly and the overall assembly should focus on the control of the frame elevation control, line control and welding deformation control; according to the construction experience and the results of the welding process assessment, before the truss assembly and welding, add the necessary welding shrinkage allowance to prevent large shrinkage deformation;
[0092] Step 2: Assemble the floor trusses;
[0093] The steps of assembling the floor trusses include:
[0094] S2.1: Erection of floor truss assembly scaffolding; the specific steps of the floor truss assembly scaffolding are:
[0095] On the floor, according to the actual plane projection coordinates of the roof truss blocks as a whole, add the arch value and the longitudinal and transverse welding shrinkage allowance values, and draw the center line of the main chord of the truss; set up the assembly frame, and fix the higher frame with diagonal braces. The frame should be submitted for acceptance before use; the assembly frame is set up step by step according to the assembly progress, and welded and fixed with the embedded parts of the floor;
[0096] S2.2: Positioning and installation of main chord members of floor trusses; the steps for positioning and installation of main chord members of floor trusses are as follows:
[0097] The main chord of the truss is assembled and positioned on the assembly frame. Two support frames are required for each main chord processing segment. After positioning, the limit plate and the frame support template are used to fix the main chord. The main chord is installed symmetrically from the middle to both sides. During installation, attention should be paid to the installation gap and the center line of the rod should coincide with the center line of the platform;
[0098] S2.3: Positioning and installation of floor truss web members; the specific steps of positioning and installation of floor truss web members are as follows:
[0099] According to the design drawings, the truss webs are installed and positioned. The rods must be positioned to coincide with the plane position and center line of the truss nodes. For rods with hidden welds, the next web can only be positioned after the hidden welds are completed. The overall assembly is carried out symmetrically from the middle to both sides.
[0100] S2.4: Assembly of peripheral main trusses; the assembly steps of the peripheral main trusses are:
[0101] After the main trusses of the same span are assembled, the longitudinal main trusses at adjacent positions and the main trusses around the skylight are assembled. Before assembly, the truss frame must be positioned and assembled first, and then the truss chords and webs are assembled;
[0102] S2.5: Secondary truss assembly; the specific steps of secondary truss assembly are:
[0103] When the assembly and positioning of the adjacent longitudinal main trusses and the main trusses around the skylight are completed, the secondary trusses in between, the secondary roof beams and the cross support beams are hoisted and positioned; the secondary trusses are assembled on the ground, and after the assembly is completed, they are transported to the vicinity of the installation position by a flatbed truck, and hoisted and positioned by a 25-ton truck crane; when positioning the rods with hidden welds, the welding and flaw detection of the hidden welds must be completed in advance, and the next rod assembly can be carried out after passing the inspection;
[0104] S2.6: Assembling the main trusses of the roof skylights; the specific steps of assembling the main trusses of the roof skylights are:
[0105] Install adjacent main trusses, main trusses around skylights, secondary trusses, roof secondary beams and cross-bracing beams in sequence;
[0106] S2.7: Skylight truss assembly; the specific steps of skylight truss assembly are:
[0107] After the skylight trusses are assembled on the ground in sections, they are transported to the vicinity of the installation location, where they are hoisted and positioned in sections by a 25-ton truck crane, and positioning frames are set up at different locations;
[0108] S2.8: Assembly of side span main trusses; the steps of assembling the side span main trusses are:
[0109] After the assembly and positioning of the main and secondary trusses of the middle span and the skylight trusses are completed, the main trusses of the side spans are assembled; before assembly, the assembly frame is set up first, and then the assembly and positioning of the truss chords and webs are carried out respectively, starting from the assembled structure and assembling one by one towards the other side;
[0110] S2.9: Positioning of secondary trusses between main trusses; the specific steps of positioning the secondary trusses between main trusses are:
[0111] After the adjacent main trusses are assembled and positioned, the secondary trusses between them are assembled and positioned in sections;
[0112] S2.10: Assembling the secondary truss and secondary beam in the other direction; the assembly steps of the secondary truss and secondary beam in the other direction are:
[0113] The 25-ton truck crane is used to assemble the secondary trusses and secondary beams in another direction; the other direction refers to the other side where the secondary trusses and secondary beams have been assembled. Fig.18 and attached Fig.19 As shown;
[0114] S2.11: Assembling the next primary and secondary trusses; the specific steps of assembling the next primary and secondary trusses are:
[0115] A 25-ton truck crane is used to assemble and position the primary and secondary trusses and secondary roof beams of the next span;
[0116] S2.12: Welding and deformation control of trusses; the specific steps of welding and deformation control of trusses are:
[0117] According to the construction experience and the results of welding process assessment, before the truss assembly and welding, the necessary welding shrinkage allowance is added to prevent large shrinkage deformation; after the truss between the two axis lines is assembled, the truss is welded, and the welding is carried out by CO 2 Gas shielded welding is used, and an even number of welders are used to perform welding symmetrically from the center to both sides, and the welding sequence is from bottom to top; the lower layer of rods are welded first, and then the upper layer of rods, and flaw detection is performed after welding; after the working surface is ready, the subsequent roof trusses are assembled and welded in sequence.
[0118] In an embodiment of the present invention, a large-scale steel structure roof truss structure is assembled by adopting an inverted triangle main truss assembled on-site on the elevated floor and a secondary truss assembled at an off-site assembly site. After the main truss is assembled in sections, the assembled secondary trusses are transported to the elevated floor and assembled with the main trusses to form a lifting unit. By adopting a method of assembling and then lifting the trusses, the trusses are reasonably divided and assembled, and the frame elevation, line shape and welding deformation of the small assembly units are controlled, thereby achieving high-precision and high-efficiency construction of large-scale steel structure roof assembly, further reducing the connection errors of various truss components during the assembly process, and improving the installation quality and precision of the steel structure roof trusses.
[0119] In one embodiment of the present invention, see Figure 1-Figure 5 In step S10, the step of assembling the tire frame includes:
[0120] S1.1.1: When setting up the hoisting unit assembly frame, temporary fixed embedded parts should be set under the main chord of the main truss and the chord of the skylight truss according to the X and Y projection points after the coordinate transformation of the roof model. They should be embedded before pouring the floor concrete, or connected to form an assembly platform on the floor with I-beams, square tubes, angle steels, etc.;
[0121] S1.1.2: After the embedded parts are set up or the platform is erected, the X and Y projection lines, elevation lines, inspection lines and fulcrum positions are placed to form a rod axis control network, which is submitted for acceptance, and then the tire frame is set according to the elevation at the fulcrum;
[0122] S1.1.3: The setting of the cradle shall be fully optimized with the corresponding roof design, segment weight and height. In addition, the lowest height of the cradle shall be able to meet the height required for all-position welding. There shall be no obvious shaking after the cradle is erected, and it can only be used after acceptance;
[0123] S1.1.4: After the assembly frame is set up and before assembly begins, the total length, width, height, etc. of the frame are fully measured and calibrated; then a control network is established for the placement of the rods, and then the spatial positions of each point are measured and laid out, and the limits for the placement of the rods are set;
[0124] S1.1.5: Truss arching and deflection control, according to the requirements of Section 3.5.2 of the "Technical Code for Spatial Grid Structures" (JGJ7-2010), "three-dimensional trusses can be pre-arched, and the arching value can be no more than 1 / 300 of the short span."; for the roof trusses in the lifting area, according to the lifting calculation and construction simulation calculation, the maximum deflection of the truss span is about 80mm. Therefore, in the absence of special design requirements for this project, according to the construction simulation verification, the arching value of the main truss mid-span is 80mm, the arching value of the side span is 30mm, and the arching value of the cantilever is 15mm. The trusses at the corresponding positions are assembled synchronously according to the arching value of the trusses at that location; according to the requirements of the main truss arching value, the main trusses are arched and set out during processing and manufacturing; the on-site assembly and installation measurement are carried out according to the elevation after arching;
[0125] S1.1.6: Floor assembly cradle. An assembly cradle is set for the main truss floor assembly. The cradle columns are made of steel pipes with specifications not less than D102×4. When the column height is greater than 4 meters, the steel pipe section is not less than D180×10. Assembly positioning plates are set on the top of the cradle columns to locate the elevation of the truss chord. The lower part of the column is fixed to the elevated floor through embedded parts. The secondary trusses are assembled into sections on the ground and then transported to the floor for assembly. Support frames are set at the section positions. The support frames are in the form of independent pipe supports. Two positioning plates are set on one side of the independent pipe to support the upper and lower chords of the secondary truss. The bottom of the column is fixed through embedded parts or steel platforms.
[0126] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for assembling a large steel structure roof, characterized in that: The method comprises the following steps: Step 1: Assemble the secondary truss on the ground; The steps of assembling the secondary truss on the ground include: S1.1: Secondary truss assembly and scaffolding erection; S1.2: Position and install the main chord of the secondary truss; S1.3: Positioning and installation of secondary truss web members; S1.4: The secondary truss is inspected and welded as a whole; Step 2: Assemble the floor trusses; The steps of assembling the floor trusses include: S2.1: Erection of floor truss assembly scaffolding; S2.2: Positioning and installation of main chord members of floor trusses; S2.3: Positioning and installation of floor truss web members; S2.4: Assembly of peripheral main trusses; S2.5: Assemble the secondary trusses using the qualified secondary trusses tested in S1.4; S2.6: Assembly of main trusses of roof skylights; S2.7: Skylight truss assembly; S2.8: Assembly of side span main trusses; S2.9: Positioning of secondary trusses between primary trusses; S2.10: Assembly of secondary trusses and secondary beams in the other direction; S2.11: Assemble the next primary and secondary trusses; S2.12: Welding and deformation control of trusses.
2. The assembly construction method of a large steel structure roof according to claim 1, characterized in that: The specific steps of erecting the secondary truss assembly frame are: A template is set up on the tire frame to strictly control the horizontality of the upper end of the tire frame template; a car crane is used to lift the upper tire frame to the chord rod for positioning; a total station and a level are used to accurately measure and position the elevation of the tire frame to ensure that the elevation of the positioning steel plate at the upper end of the tire frame meets the error requirements.
3. The assembly construction method of a large steel structure roof according to claim 1 is characterized in that: The specific steps of positioning and installing the secondary truss main chord are: According to the plane projection of each member, draw the positioning line, the center line of the upper and lower chords and web members of the truss on the steel platform; The specific steps of positioning the secondary truss web are: A truck crane is used to hoist and position the straight web, and two supporting frame templates are set under the web. After positioning, the straight web and the chord are positioned and welded.
4. The assembly construction method of a large steel structure roof according to claim 1, characterized in that: The specific steps of the overall inspection and welding of the secondary truss are: After the assembly is completed, a total station is used to test the overall assembly accuracy. After the test is qualified, the positioning welds are removed to make the truss segments free, and then the next welding process is carried out. Before the truss assembly welding, a welding shrinkage allowance is added to prevent shrinkage deformation.
5. The assembly construction method of a large steel structure roof according to claim 4 is characterized in that: The specific steps of erecting the floor truss assembly frame are as follows: On the floor, according to the actual plane projection coordinates of the roof truss blocks as a whole, the arch value and the longitudinal and transverse welding shrinkage allowance values are added, and the center line of the main chord rod of the truss is marked; an assembly frame is set up, and the assembly frame is set up step by step according to the assembly progress, and is welded and fixed to the embedded parts of the floor; The steps for positioning and installing the main chord members of the floor truss are as follows: The main chord of the truss is assembled and positioned on the assembly frame. Two support frames are required for each main chord processing segment. After positioning, the limit plate and the frame support template are used to fix the main chord. The main chord is installed symmetrically from the middle to both sides. During installation, the installation gap and the center line of the rod should be ensured to coincide with the center line of the platform. The specific steps of positioning and installing the floor truss web are as follows: According to the design drawings, the truss web members are installed and positioned. The members must be positioned to coincide with the plane position and center line of the truss nodes. For members with hidden welds, the next web member shall be positioned after the hidden welds are completed. The overall assembly is carried out symmetrically from the middle to both sides.
6. The assembly construction method of a large steel structure roof according to claim 5, characterized in that: The assembly steps of the peripheral main truss are: After the main trusses of the same span are assembled, the longitudinal main trusses at adjacent positions and the main trusses around the skylight are assembled. Before assembly, the truss frame is positioned and assembled first, and then the truss chords and webs are assembled; The specific steps of assembling the secondary truss are: When the assembly and positioning of the adjacent longitudinal main trusses and the main trusses around the skylight are completed, the secondary trusses in between, the secondary roof beams and the cross support beams are hoisted and positioned; the secondary trusses are assembled on the ground, and after assembly, they are transported to the vicinity of the installation position by a flatbed truck, and hoisted and positioned by a truck crane; when positioning the rods with hidden welds, the welding and flaw detection of the hidden welds must be completed in advance, and the next rod will be assembled after passing the inspection.
7. The assembly construction method of a large steel structure roof according to claim 6, characterized in that: The specific steps of assembling the main truss of the roof skylight are: Install adjacent main trusses, main trusses around skylights, secondary trusses, roof secondary beams and cross-bracing beams in sequence; The specific steps of assembling the skylight truss are: After the skylight trusses are assembled in sections on the ground, they are transported to the vicinity of the installation location, where they are hoisted and positioned in sections by a truck crane, and positioning frames are set up at different locations.
8. The assembly construction method of a large steel structure roof according to claim 7, characterized in that: The steps of assembling the side span main truss are: After the assembly and positioning of the main and secondary trusses of the middle span and the skylight trusses are completed, the main trusses of the side spans are assembled; before assembly, the assembly frame is set up first, and then the assembly and positioning of the truss chords and webs are carried out respectively, starting from the assembled structure and assembling one by one towards the other side; The specific steps of positioning the secondary trusses between the main trusses are: After the adjacent main trusses are assembled and positioned, the secondary trusses in between are assembled and positioned in sections.
9. The assembly construction method of a large steel structure roof according to claim 8, characterized in that: The assembly steps of the secondary truss and the secondary beam in the other direction are: The truck crane assembles the secondary trusses and secondary beams in the other direction; The specific steps of assembling the next main and secondary trusses are: A truck crane is used to assemble and position the primary and secondary trusses and secondary roof beams of the next span.
10. The assembly construction method of a large steel structure roof according to claim 9, characterized in that: The specific steps of welding and deformation control of the truss are: Before assembling and welding the trusses, add welding shrinkage allowance to prevent shrinkage deformation; after the trusses between the two axis lines are assembled, the trusses are welded. CO2 gas shielded welding is used. An even number of welders are used to weld symmetrically from the center to both sides. The welding sequence is from bottom to top; the lower layer of rods are welded first, and then the upper layer of rods. After welding, flaw detection is carried out; after the working surface is available, the subsequent roof trusses are assembled and welded in sequence.
Citation Information
Patent Citations
Safe and stable steel structure building
CN106906902A
Construction method of 120m-span prestressed triangular steel pipe truss girder
CN113463768A
Cable-beam composite large-span cable support arch shell and construction method thereof
CN116025095A
Construction method of large-span truss net deformed steel roof structure
CN118361111A
Double-curved arc-shaped large-span steel truss and manufacturing method thereof
WO2021004187A1
Cited By
Folded plate type single-layer steel roof original form splicing method
CN120486751A