Boiler coal-fired system and control method of boiler coal-fired system

By sifting the ash slag in the boiler coal-fired system and mixing it with high alkali coal to form mixed coal, the problems of slag and contamination in combustion of high alkali coal are solved, the combustion stability and efficiency are improved, and the combustion is reduced Boiler operation risk.

CN118959987APending Publication Date: 2024-11-15XINJIANG TIANCHI ENERGY SOURCES CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411304868.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-14
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

High alkali coal is prone to slag and contamination during burning and use in boilers, affecting the safe and stable operation of the boiler.

Method used

Design a boiler coal-fired system, including a high alkali coal silo, boiler, screening unit and blending unit, and screen the ash slag into primary ash slag particles and secondary ash slag particles, and the high alkali coal is adjusted according to the set proportion. , primary ash slag particles and secondary ash slag particles are mixed to form mixed coal to reduce slag and contamination.

Benefits of technology

By mixing ash slag of different particle sizes and high alkali coal, the mixed coal formed can effectively absorb alkali metals in the flue gas during the combustion process, reduce the risk of coking, improve combustion stability and efficiency, and reduce slag and contamination during the combustion process, thereby reducing slag and pollution. Condition.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118959987A_ABST
    Figure CN118959987A_ABST
Patent Text Reader

Abstract

The invention discloses a boiler coal-fired system and a control method of the boiler coal-fired system. A high-alkali coal bunker in the system is used for storing high-alkali coal. The boiler is provided with a hearth, a coal inlet of the hearth is communicated with the high-alkali coal bunker, and a slag discharge port of the hearth is used for discharging ash generated after combustion of high-alkali coal out of the hearth. The screening unit is used for screening out primary ash particles and secondary ash particles from ash, and the particle size of the primary ash particles is larger than that of the secondary ash particles. The mixing unit is located between the high-alkali coal bunker and the boiler, the high-alkali coal bunker is communicated with the hearth through the mixing unit, and the mixing unit is used for receiving the high-alkali coal, the primary ash particles and the secondary ash particles, mixing the high-alkali coal, the primary ash particles and the secondary ash particles according to a set mixing proportion, inputting the mixed coal into the hearth, and conveying the mixed coal into the boiler. And subsequent combustion is carried out. The boiler coal-fired system can effectively reduce the conditions of slagging and contamination in the combustion process of high-alkali coal.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention specifically relates to a boiler coal-fired system and a control method for the boiler coal-fired system. Background Art

[0002] A large amount of high-alkali coal is mostly mined in open-pits due to its large reserves, so the mining cost is relatively low. Since most high-alkali coals have the characteristics of low sulfur, low ash, medium-high volatile matter and medium-high calorific value, they are a very economical type of thermal coal and are used in power plant boilers inside and outside Xinjiang. However, due to its high alkali metal content, high-alkali coal and medium-alkali coal have serious slagging and contamination during combustion in boilers, affecting the safe and stable operation of boilers.

[0003] Therefore, how to reduce slagging and contamination during the combustion of high-alkali coal in boilers has become a technical problem that needs to be solved urgently. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a boiler coal-fired system and a control method for the boiler coal-fired system in view of the above-mentioned deficiencies in the prior art, wherein the boiler coal-fired system can effectively reduce the slagging and contamination of high-alkali coal during the combustion process.

[0005] According to an embodiment of the first aspect of the present invention, there is provided a boiler coal-fired system, comprising: a high-alkali coal bunker, a boiler, a screening unit and a blending unit. The high-alkali coal bin is used to store high-alkali coal; the boiler is provided with a furnace, and the furnace is provided with a coal inlet and a slag discharge port, the coal inlet is connected with the high-alkali coal bin, the furnace is used to receive and burn high-alkali coal, and the slag discharge port is used to discharge ash generated after the combustion of high-alkali coal out of the furnace; the screening unit is connected with the slag discharge port, and is used to screen the ash and output primary ash particles and secondary ash particles, and the particle size of the primary ash particles is larger than the particle size of the secondary ash particles; the blending unit is located between the high-alkali coal bin and the boiler, and the high-alkali coal bin is connected with the furnace through the blending unit, and the blending unit is also respectively connected with the screening unit, and is used to receive high-alkali coal, primary ash particles and secondary ash particles, and blend the high-alkali coal, primary ash particles and secondary ash particles according to a set blending ratio to obtain blended coal, and the blending unit is also used to input the blended coal into the furnace for subsequent combustion.

[0006] Preferably, the screening unit includes a primary screening machine and a secondary screening machine; the primary screening machine is provided with a first inlet, a first outlet and a second outlet, the first inlet is connected to the slag discharge port, the primary screening machine is used to perform a primary screening on the ash, and discharge primary ash particles and primary bottom ash from the first outlet and the second outlet respectively; the secondary screening machine is provided with a second inlet, a third outlet and a fourth outlet, the second inlet is connected to the second outlet of the primary screening machine, the secondary screening machine is used to perform a secondary screening on the primary bottom ash, and discharge secondary ash particles and waste bottom ash from the third outlet and the fourth outlet respectively.

[0007] Preferably, the blending unit includes a first controller and a weighing unit, and the weighing unit is respectively connected to the outlet of the high-alkali coal bin, the first outlet of the primary screening machine and the third outlet of the secondary screening machine; the blending ratio is pre-stored in the first controller, and the first controller is electrically connected to the weighing unit, and is used to control the weighing unit to weigh the corresponding high-alkali coal, primary ash particles and secondary ash particles according to the blending ratio; the weighing unit is also connected to the furnace, and is used to mix the high-alkali coal, primary ash particles and secondary ash particles weighed according to a preset ratio and transport them to the furnace.

[0008] Preferably, the weighing unit includes a first belt scale, a second belt scale, a third belt scale and a mixing and conveying unit; the first controller is used to pre-store the preset ratio, the first controller is electrically connected to the first belt scale, the second belt scale and the third belt scale, respectively, and the first controller is used to send out a first weight signal, a second weight signal and a third weight signal according to the blending ratio; the first belt scale is connected to the high-alkali coal bin, for receiving the first weight signal, and weighing the corresponding weight of the high-alkali coal according to the first weight signal; the second belt scale is connected to the first outlet of the primary screening machine, for receiving the second weight signal, and weighing the corresponding weight of the primary ash particles according to the second weight signal; the third belt scale is connected to the third outlet of the secondary screening machine, for receiving the third weight signal, and weighing the corresponding weight of the secondary ash particles according to the third weight signal; the mixing and conveying unit is connected to the first belt scale, the second belt scale and the third belt scale, respectively, for conveying the high-alkali coal, the primary ash particles and the secondary ash particles into the furnace.

[0009] Preferably, the mixing unit also includes a primary ash collecting tank and a secondary ash collecting tank; the primary ash collecting tank is located between the primary screening machine and the second belt scale, the inlet of the primary ash collecting tank is connected to the first outlet of the primary screening machine, and the outlet is connected to the second belt scale, and the primary ash collecting tank is used to receive and temporarily store the primary ash particles; the secondary ash collecting tank is located between the secondary screening machine and the third belt scale, the inlet of the secondary ash collecting tank is connected to the third outlet of the secondary screening machine, and the outlet is connected to the third belt scale, and the secondary ash collecting tank is used to receive and temporarily store the secondary ash particles.

[0010] Preferably, the system also includes an ash conveying device and a slag bin, the ash conveying device includes a main feeding unit, a first branch unit and a second branch unit, one end of the main feeding unit is connected to the slag discharge port, and the other end is connected to the first branch unit and the second branch unit; the first branch unit is connected to the screening unit for conveying ash to the screening unit, and the screening unit is also connected to the slag bin for discharging the screened waste bottom ash into the slag bin; the second branch unit is connected to the slag bin for conveying excess ash directly to the slag bin.

[0011] Preferably, the ash conveying device also includes a first flow regulating unit and a second flow regulating unit, the first flow regulating unit is installed on the first branch unit, and the first flow regulating unit is used to control the feeding flow on the first branch unit, thereby controlling the ash flow entering the screening unit; the second flow regulating unit is installed on the second branch unit, and is used to control the feeding flow on the second branch unit.

[0012] Preferably, the ash conveying device also includes a second controller, a first material level detection unit and a second material level detection unit. The first material level detection unit is installed in the primary ash collecting tank of the mixing unit, and is used to detect the material level height of the primary ash particles in the primary ash collecting tank and send out first material level information. The second material level detection unit is installed in the secondary ash collecting tank of the mixing unit, and is used to detect the material level height of the secondary ash particles in the secondary ash collecting tank and send out second material level information. The second controller is electrically connected to the first material level detection unit, the second material level detection unit and the first flow regulating unit and the second flow regulating unit, respectively. The second controller is used to receive the first material level information and the second material level information, and control the opening of the first flow regulating unit and the opening of the second flow regulating unit according to the first material level information and the second material level information.

[0013] Preferably, the second controller pre-stores height threshold parameters of a primary ash collection tank and height threshold parameters of a secondary ash collection tank, the height threshold parameters of the primary ash collection tank include a first height threshold and a second height threshold, the first height threshold is greater than the second height threshold, the height threshold parameters of the secondary ash collection tank include a third height threshold and a fourth height threshold, the third height threshold is greater than the fourth height threshold; the second controller is used to obtain actual material level heights in the primary ash collection tank and the secondary ash collection tank according to the first material level information and the second material level information, and when the actual material level height in the primary ash collection tank exceeds When the actual material level in the primary ash collecting tank exceeds the first height threshold, or the actual material level in the secondary ash collecting tank exceeds the third height threshold, the first flow regulating unit is controlled to cut off the first branch unit to stop the feeding of the screening unit, and the second flow regulating unit is controlled to open the second branch unit to transport the excess ash to the slag bin; the second controller is also used to control the first flow regulating unit to open the first branch unit to feed the screening unit when the actual material level in the primary ash collecting tank is lower than the second height threshold, or the actual material level in the secondary ash collecting tank is lower than the fourth height threshold, to control the first flow regulating unit to open the first branch unit to feed the screening unit, and to control the second flow regulating unit to cut off the second branch unit.

[0014] According to an embodiment of the second aspect of the present invention, a control method for a boiler coal-fired system is provided. The method is applied to the above-mentioned boiler coal-fired system and is characterized by comprising:

[0015] Obtain the load parameters and proportion parameters of the boiler;

[0016] Obtaining a target blending ratio according to the load parameter and ratio parameter of the boiler;

[0017] According to the target blending ratio, controlling the blending unit to blend the high-alkali coal, the primary ash particles and the secondary ash particles to obtain blended coal;

[0018] The blended coal is fed into the furnace of the boiler for combustion.

[0019] Preferably, the load parameters include a set steam output threshold of the boiler and a required steam output value of the boiler;

[0020] The ratio parameters include: a first blending ratio and a second blending ratio, wherein the high-alkali coal ratio in the first blending ratio is lower than the high-alkali coal ratio in the second blending ratio;

[0021] The target blending ratio is obtained according to the load parameter and the ratio parameter of the boiler, specifically including:

[0022] According to the load parameter, determine whether the required steam output value is higher than the set value.

[0023] Steam output threshold:

[0024] If yes, the first blending ratio in the ratio parameter is selected as the target blending ratio; if no, the second blending ratio in the ratio parameter is selected as the target blending ratio.

[0025] The boiler coal-fired system of the present invention obtains blended coal by blending ash of different particle sizes with high-alkali coal, and then burns the blended coal to effectively reduce coking and contamination in the boiler.

[0026] Specifically, the silicon-aluminum compounds in the ash are effective substances for reducing coking, because the silicon-aluminum compounds can well adsorb alkali metals in the flue gas. Moreover, the smaller the particle size of the ash, the better the adsorption effect of the alkali metals in the flue gas. This is because during the combustion process, alkali metals will cause the melting point of the ash to decrease, resulting in coking; when the number of cycles increases, the previously formed small-particle slag will continue to adsorb alkali metals, causing the particle size of the slag to increase while also forming alkali metal enrichment in the ash, and the efficiency of reducing coking is also reduced. Therefore, by screening out small-particle ash, mixing the small-particle ash with high-alkali coal to obtain blended coal, and then burning the blended coal, it can continue to adsorb alkali metals in the flue gas. Moreover, by setting a good blending ratio, high-alkali coal and ash particles of different particle sizes are blended to obtain blended coal with more balanced combustion performance. This blended coal can reduce the combustion fluctuations caused by uneven coal quality during the combustion process and improve the stability and efficiency of combustion.

[0027] Therefore, the coal-fired system of the boiler can effectively reduce the slagging and contamination of high-alkali coal during the combustion process. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a schematic diagram of the structure of a boiler coal-fired system in some embodiments of the present invention.

[0029] In the figure: 1- boiler, 2- first flow regulating unit, 3- second flow regulating unit, 4- coarse screening device, 5- primary screening machine, 6- secondary screening machine, 7- slag bin, 8- primary ash collecting tank, 9- secondary ash collecting tank, 10- second belt scale, 11- third belt scale, 12- high-alkali coal bin, 13- first belt scale, 14- mixed coal belt, 15- coal bin entering the furnace. DETAILED DESCRIPTION

[0030] The following will be combined with the accompanying drawings in the present invention to clearly and completely describe the technical solutions in the invention. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of the present invention.

[0031] In the description of the present invention, it should be noted that the terms "upper", "lower", "upstream", "downstream" and the like indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience and simplification of the description. They do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they should not be understood as limitations on the present invention.

[0032] In the description of the present invention, the terms “first”, “second” and “third” are used for descriptive purposes only and should not be understood as indicating or implying relative importance.

[0033] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "connect", "set", "install", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection, or an integral connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two elements. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0034] First of all, it should be noted that a large amount of high-alkali coal is mostly mined in open-pits due to its large reserves, so the mining cost is relatively low. Since most high-alkali coals have the characteristics of low sulfur, low ash, medium-high volatile matter and medium-high calorific value, they are a very economical type of thermal coal and are used in power station boilers everywhere. However, due to its high alkali metal content, high-alkali coal has serious slagging and contamination during combustion in boilers, affecting the safe and stable operation of boilers.

[0035] Circulating fluidized beds are distributed in most areas due to their wide fuel adaptability, low furnace temperature and low NOx. With the continuous expansion of high-alkali coal in the market outside Xinjiang, it has become a type of coal considered for circulating fluidized beds due to its high cost-effectiveness. At the same time, the center temperature of the furnace can be controlled at around 850-960℃, which greatly alleviates the coking risk of high-alkali coal in the furnace. At the same time, the high calorific value and good combustion stability of high-alkali coal are conducive to ensuring the heat exchange and load-carrying capacity of the fluidized bed.

[0036] However, due to its relatively low ash content, there is often a shortage of circulating bed material during large-proportion blending, which leads to an increase in the temperature in the furnace and an increase in the degree of coking. Therefore, the present invention proposes a process flow to achieve a method of mixing circulating fluidized bed ash with high-alkali coal outside the furnace and then recycling it into the furnace. On the one hand, this process system can reduce the cost of ash treatment. At the same time, since the content of silicon-aluminum compounds in the ash is more than 70%, it can effectively capture the alkali metal gaseous substances volatilized by the high-alkali coal in the furnace, reducing the risk of slagging in the water-cooled wall area of ​​the furnace; in addition, due to the screening process, the bed material entering the furnace is more uniform, which can better control the air distribution and the power field in the furnace, and ensure the safe and stable operation of the circulating fluidized bed boiler.

[0037] Example 1

[0038] See also Figure 1 The present invention discloses a boiler coal-fired system, comprising: a high-alkali coal bunker 12, a boiler 1, a screening unit and a blending unit.

[0039] Among them, the high-alkali coal bunker 12 is used to store high-alkali coal. The boiler 1 is provided with a furnace, and the furnace is provided with a coal inlet and a slag outlet. The coal inlet is connected to the high-alkali coal bunker 12. The furnace is used to receive high-alkali coal and burn high-alkali coal. The slag outlet is used to discharge the ash produced after the high-alkali coal is burned into the furnace. The screening unit is connected to the slag outlet, and is used to screen the ash and output primary ash particles and secondary ash particles. The particle size of the primary ash particles is larger than the particle size of the secondary ash particles. The blending unit is located between the high-alkali coal bunker 12 and the boiler 1. The high-alkali coal bunker 12 is connected to the furnace through the blending unit. The blending unit is also connected to the screening unit, and is used to receive high-alkali coal, primary ash particles and secondary ash particles, and blend the high-alkali coal, primary ash particles and secondary ash particles according to the set blending ratio to obtain blended coal. The blending unit is also used to input the blended coal into the furnace for subsequent combustion.

[0040] It should be noted that the boiler 1 in this embodiment adopts a circulating fluidized bed boiler 1. The circulating fluidized bed process has the advantages of good fuel adaptability and high combustion efficiency. In the circulating fluidized bed boiler 1, the fuel is fully mixed with oxygen in a fluidized state, the combustion is more complete, and the combustion efficiency is higher. In addition, the circulating combustion process in the boiler 1 also helps to improve the combustion efficiency of the fuel and reduce the loss of unburned fuel.

[0041] Burning high-alkali coal in the circulating fluidized bed boiler 1 will produce ash, and there are unburned carbon particles in the ash, which can be recycled. In addition, by blending ash of different particle sizes with high-alkali coal to obtain blended coal, the coking and contamination in the boiler 1 can be effectively reduced by subsequently burning the blended coal.

[0042] The principle is as follows: the silicon-aluminum compounds in the ash are effective substances for reducing coking, and the silicon-aluminum compounds can adsorb alkali metals in the flue gas very well. Moreover, the smaller the particle size of the ash, the better the adsorption effect on the alkali metals in the flue gas. For example, the alkali metal enrichment in the ash particles with a particle size range of 8-12mm is less than 20%, which can better adsorb the flue gas alkali metals; the fine slag with a particle size range of 4-8mm, the alkali metal enrichment ratio of the ash particles under this particle size is less than 5%, and has a strong adsorption effect on the alkali metals in the flue gas. This is because during the combustion process, alkali metals will cause the melting point of the ash to decrease, causing coking; when the number of cycles increases, the small-particle slag formed previously will continue to adsorb alkali metals, causing the particle size of the slag to increase while also forming alkali metal enrichment in the ash, and the efficiency of reducing coking is also reduced.

[0043] Therefore, small-sized ash can well absorb alkali metals in flue gas. By setting a good blending ratio, high-alkali coal and ash particles of different particle sizes are blended to obtain a blended coal with more balanced combustion performance. This blended coal can reduce combustion fluctuations caused by uneven coal quality during combustion and improve combustion stability and efficiency.

[0044] In this embodiment, the ash is screened into primary ash particles and secondary ash particles by a screening unit, and the ratio of high-alkali coal, primary ash particles and secondary ash particles is selected according to the actual load demand of the boiler 1. Among them, the particle size of the primary ash particles is larger than the particle size of the secondary ash particles. Specifically, the particle size of the primary ash particles is 8-12mm. For example: 8, 9, 10, 11, 12mm. The particle size of the secondary ash particles is 4-8mm, for example: 4, 7, 8mm.

[0045] According to the load of boiler 1, the proportion of blending can be adjusted and controlled. On the one hand, the furnace temperature can be controlled and the risk of coking can be reduced. On the other hand, due to the obvious price advantage of high-alkali coal, costs can be saved by adjusting the proportion. The load of boiler 1 refers to the ability to generate steam per unit time. For example, the steam of boiler 1 is used to drive the steam turbine, and the steam turbine is used to do external work. In this way, boiler 1 is actually doing work. The more work is done per unit time, the greater the load of boiler 1, and vice versa. The actual load of coal-fired boiler 1 is generally 60-100% of the rated evaporation capacity. If it is lower than this range, it is low-load operation. For example: the actual evaporation rate of boiler 1 is 50%, which can be identified as low-load operation; the actual evaporation rate of boiler 1 is 80%, which can be identified as high-load operation. Furthermore, the load of boiler 1 refers to the ability to generate steam per unit time. The lower the load of boiler 1, the less steam there is, and the less heat the furnace requires. At this time, the overall furnace temperature is lower, and the risk of coking is lower.

[0046] In this embodiment, the blending ratio under low load (the following ratios are all high-alkali coal: primary ash particles: secondary ash particles) is (7-10):1:1; the blending ratio under high load is (4-6):1:1. For example, the blending ratio under low load is 8:1:1; the blending ratio under high load is 5:1:1.

[0047] It can be seen that when the boiler 1 is running at low load, the proportion of high-alkali coal needs to be increased. When the boiler 1 is running at high load, the proportion of high-alkali coal needs to be reduced. This is because, under low load, the temperature of the circulating fluidized bed is relatively low overall, and multiple parameters such as the operating conditions of the boiler 1 are unstable. At this time, increasing the proportion of high-alkali coal blending can, on the one hand, maintain the stable combustion capacity of the boiler 1, and it is not easy to cause local heat imbalance due to ash circulation, resulting in the flameout of the boiler 1; on the other hand, the furnace temperature is controlled to be low under low load, and the risk of coking is low, so the proportion of high-alkali coal can be appropriately increased to save costs. Secondly, under high load, the furnace temperature increases. At this time, reducing the proportion of high-alkali coal can still maintain the stable combustion effect of boiler 1, and the probability of coking increases under high load, so it is necessary to control the amount of high-alkali coal to ensure the safe operation of boiler 1.

[0048] In summary, the boiler coal-fired system in this embodiment can effectively reduce the slagging and contamination of high-alkali coal during the combustion process.

[0049] The specific structure of the coal-fired system of this boiler will be further explained below.

[0050] like Figure 1 As shown, in this embodiment, the screening unit includes a primary screening machine 5 and a secondary screening machine 6. The primary screening machine 5 is provided with a first inlet, a first outlet and a second outlet, the first inlet is connected to the slag discharge port, the primary screening machine 5 is used to screen the ash once, and discharge the primary ash particles and the primary bottom slag from the first outlet and the second outlet respectively. The secondary screening machine 6 is provided with a second inlet, a third outlet and a fourth outlet, the second inlet is connected to the second outlet of the primary screening machine 5, the secondary screening machine 6 is used to screen the primary bottom slag twice, and discharge the secondary ash particles and the waste bottom slag from the third outlet and the fourth outlet respectively.

[0051] Specifically, both the primary screening machine 5 and the secondary screening machine 6 can adopt existing screening machines, for example, a 3YK-2456 circular screening machine, the primary screening machine 5 can screen out ash particles with a particle size range of 8-12 mm, and the secondary screening machine 6 can screen out ash particles with a particle size range of 4-8 mm.

[0052] Further, the screening unit also includes a coarse screening device 4. The coarse screening device 4 is located between the slag discharge port of the boiler 1 and the primary screening machine 5, and the slag discharge port is connected to the primary screening machine 5 through the coarse screening device 4. The coarse screening device 4 is used to perform the initial screening of the ash discharged from the furnace. The coarse screening device 4 is equipped with an automatic vibrator to automatically screen the ash particles with a particle size exceeding 2 cm. The coarse screening device 4 can use the existing vibration screening equipment. The outlet of the coarse screening device 4 is connected to the inlet (first inlet) of the primary screening machine 5. The primary screening machine 5 can screen out ash particles with a particle size range of 8-12 mm. The first outlet of the primary screening machine 5 is connected to the inlet of the primary ash collection tank 8 via a belt, and the second outlet is connected to the inlet (second inlet) of the secondary screening machine 6. The secondary screening machine 6 can screen out ash particles with a particle size range of 4-8 mm; the third outlet of the secondary screening machine 6 is connected to the inlet of the ash collection tank via a belt, and the fourth outlet is connected to the slag bin 7. Specifically, the slag bin 7 is used to accommodate waste ash particles with larger particle sizes.

[0053] Continue as Figure 1 As shown, in this embodiment, the blending unit includes a first controller and a weighing unit. The weighing unit is respectively connected to the outlet of the high-alkali coal bin 12, the first outlet of the primary screening machine 5, and the third outlet of the secondary screening machine 6. The first controller has a pre-stored blending ratio, and the first controller is electrically connected to the weighing unit, and is used to control the weighing unit to weigh the corresponding high-alkali coal, primary ash particles, and secondary ash particles according to the blending ratio. The weighing unit is also connected to the furnace, and is used to transport the high-alkali coal, primary ash particles, and secondary ash particles weighed according to the preset ratio to the furnace.

[0054] Specifically, the first controller pre-stores a first blending ratio and a second blending ratio. The first blending ratio is a blending ratio applicable under high load, and the blending ratio under high load is (4-6):1:1. The second blending ratio is a blending ratio under low load, which is (7-10):1:1. Exemplarily, the first blending ratio is 5:1:1; the second blending ratio is 8:1:1.

[0055] The first controller in the blending unit is also used to perform the following steps:

[0056] Obtain the load parameters and proportion parameters of boiler 1.

[0057] According to the load parameter and ratio parameter of the boiler 1, the target blending ratio is obtained.

[0058] According to the target blending ratio, the blending unit is controlled to blend the high-alkali coal, the primary ash particles and the secondary ash particles to obtain blended coal.

[0059] The blended coal is fed into the furnace of the boiler 1 for combustion.

[0060] Specifically, the first controller can be implemented by an industrial computer, or an application-specific integrated circuit (ASIC), or a programmable logic device (PLD). The above PLD can be a complex programmable logic device (CPLD), a field programmable gate array (FPGA), a general array logic (GAL) or any combination thereof.

[0061] The staff inputs the load parameters of the boiler 1 into the first controller, and the first controller pre-stores the ratio parameters. Specifically, the load parameters include the set steam output threshold of the boiler 1 and the required steam output value of the boiler 1. The ratio parameters include: a first blending ratio and a second blending ratio, and the high-alkali coal ratio in the first blending ratio is lower than the high-alkali coal ratio in the second blending ratio.

[0062] The first controller obtains the target blending ratio according to the load parameter and the ratio parameter of the boiler 1, specifically: according to the load parameter, it is judged whether the required steam output value is higher than the set steam output threshold. If yes, the first blending ratio in the ratio parameter is selected as the target blending ratio; if not, the second blending ratio in the ratio parameter is selected as the target blending ratio.

[0063] Further, the weighing unit includes a first belt scale 13, a second belt scale 10, a third belt scale 11 and a mixed conveying unit. The first controller is used to store a preset ratio in advance, and the first controller is electrically connected to the first belt scale 13, the second belt scale 10 and the third belt scale 11 respectively. The first controller is used to send a first weight signal, a second weight signal and a third weight signal according to the blending ratio. The first belt scale 13 is connected to the high-alkali coal bin 12, and is used to receive the first weight signal, and weigh the corresponding weight of high-alkali coal according to the first weight signal. The second belt scale 10 is connected to the first outlet of the primary screening machine 5, and is used to receive the second weight signal, and weigh the corresponding weight of primary ash particles according to the second weight signal. The third belt scale 11 is connected to the third outlet of the secondary screening machine 6, and is used to receive the third weight signal, and weigh the corresponding weight of secondary ash particles according to the third weight signal. The mixed conveying unit is connected to the first belt scale 13, the second belt scale 10 and the third belt scale 11 respectively, and is used to transport high-alkali coal, primary ash particles and secondary ash particles to the furnace.

[0064] Specifically, the first belt scale 13, the second belt scale 10 and the third belt scale 11 can all adopt existing belt scale equipment, for example: high-precision intelligent control electronic belt scale of model YB-GZK-NT / 12. The working principle of the belt scale mainly depends on the weighing sensor and the speed sensor. The weighing feeder detects the weight of the material passing through the belt through the weighing sensor under the weighing scale frame. The feeding controller compares the flow rate with the set flow rate, and the controller outputs a signal to control the speed regulation of the frequency converter to achieve the requirement of quantitative feeding.

[0065] The first controller calculates the weights of high-alkali coal, primary ash particles and secondary ash particles according to the target blending ratio and the total required coal consumption of the boiler 1, and sends a first weight signal, a second weight signal and a third weight signal to the first belt scale 13, the second belt scale 10 and the third belt scale 11 respectively. The first belt scale 13, the second belt scale 10 and the third belt scale 11 weigh the corresponding weights of high-alkali coal, primary ash particles and secondary ash particles respectively. These high-alkali coal, primary ash particles and secondary ash particles are mixed by the mixing and conveying unit and input into the furnace of the boiler 1 for combustion.

[0066] Furthermore, the blending unit further includes a primary ash collecting tank 8 and a secondary ash collecting tank 9. The primary ash collecting tank 8 is located between the primary screening machine 5 and the second belt scale 10, the inlet of the primary ash collecting tank 8 is connected to the first outlet of the primary screening machine 5, and the outlet is connected to the second belt scale 10, and the primary ash collecting tank 8 is used to receive and temporarily store primary ash particles. The secondary ash collecting tank 9 is located between the secondary screening machine 6 and the third belt scale 11, the inlet of the secondary ash collecting tank 9 is connected to the third outlet of the secondary screening machine 6, and the outlet is connected to the third belt scale 11, and the secondary ash collecting tank 9 is used to receive and temporarily store secondary ash particles.

[0067] Specifically, by setting up a primary ash collection tank 8 and a secondary ash collection tank 9, the primary ash particles screened by the primary screening machine 5 and the secondary ash particles screened by the secondary screening machine 6 are collected and temporarily stored respectively. Electric valves are respectively set at the outlets of the primary ash collection tank 8 and the secondary ash collection tank 9, and the discharge of the primary ash collection tank 8 and the secondary ash collection tank 9 is controlled by opening / closing the electric valves. In this way, the discharge of the primary ash particles and the secondary ash particles can be better controlled, thereby improving the accuracy of the blending ratio of high-alkali coal, primary ash particles and secondary ash particles in the blending unit.

[0068] like Figure 1As shown, the system also includes an ash conveying device and a slag bin 7. The ash conveying device includes a main feeding unit, a first branch unit and a second branch unit. One end of the main feeding unit is connected to the slag discharge port, and the other end is connected to the first branch unit and the second branch unit. The first branch unit is connected to the screening unit for conveying ash to the screening unit. The screening unit is also connected to the slag bin 7 for discharging the screened waste bottom ash into the slag bin 7. The second branch unit is connected to the slag bin 7 for conveying excess ash directly to the slag bin 7.

[0069] Furthermore, the ash conveying device also includes a first flow regulating unit 2 and a second flow regulating unit 3. The first flow regulating unit 2 is installed on the first branch unit, and the first flow regulating unit 2 is used to control the feeding flow on the first branch unit, thereby controlling the ash flow entering the screening unit; the second flow regulating unit 3 is installed on the second branch unit, and is used to control the feeding flow on the second branch unit.

[0070] In some embodiments, the main feeding unit, the first branch unit and the second branch unit can transport the ash through a feeding pipeline. The first flow regulating unit 2 and the second flow regulating unit 3 can use control valves to control the flow of ash.

[0071] In some other embodiments, the main feeding unit, the first branch unit and the second branch unit may adopt conveyor belts. The first flow regulating unit 2 and the second flow regulating unit 3 may adopt ash plows.

[0072] Taking the conveyor belt as an example, the first branch is connected to the coarse screening unit, the primary screening machine 5 and the secondary screening machine 6 in sequence, and finally connected to the slag bin 7. The second branch is directly connected to the slag bin 7. When the screening unit needs to be fed, the opening of the first branch conveyor belt is controlled by the first ash plow, that is, the feed flow rate of the screening unit is controlled. When the screening unit does not need to be fed (that is, the ash particles in the primary ash collection tank 8 and the secondary ash collection tank 9 reach the height threshold), the first branch can be completely closed by the ash plow unit. At this time, the unscreened ash can directly enter the slag bin 7 through the second branch.

[0073] Furthermore, the first ash plow (first flow regulating unit 2) and the second ash plow (second flow regulating unit 3) can both adopt commercially available coal plows (or plows), for example: an electro-hydraulic coal plow with model number DYTN03F11 G. The coal plow includes a conveyor belt, a plowshare, and a hydraulic drive device. The plowshare includes a first baffle, a second baffle, and a connecting section. The connecting section is located between the first baffle and the second baffle. The first baffle and the second baffle are arranged opposite to each other. The first baffle and the second baffle are both inclined backward (i.e., inclined from the feeding end to the lower feeding end of the conveyor belt). The first baffle is connected to the second baffle by a connecting section, and the entire plowshare is in a herringbone shape. The connecting section of the plowshare faces the feeding direction of the conveyor belt, and is used to intercept and divert the ash on the conveyor belt. The plowshare is located above the conveyor belt, and the driving rod of the hydraulic drive device is connected to the plowshare, which is used to drive the plowshare to rise and fall in the vertical direction.

[0074] The working principle of the coal plow is as follows: the lifting and lowering of the plowshare is controlled by a hydraulic drive device. By adjusting the height position of the plowshare (the height interval between the plowshare and the conveyor belt), the contact area between the plowshare and the conveyor belt can be changed, thereby controlling the discharge flow. When the driving rod of the hydraulic drive device is extended to drive the plowshare down, the lower edge of the plowshare fits tightly with the belt surface, so that all the materials on the conveyor belt can be unloaded, that is, the conveyor belt is blocked and no more materials are conveyed.

[0075] Here, the ash flow is controlled by a coal plow, which has the following advantages: First, the ash particles discharged from the boiler 1 are of different sizes and are uneven, and direct screening is prone to dust and other problems. By adjusting the height of the plow head of the coal plow to control the feed flow, on the one hand, the ash can be leveled and dust can be reduced; on the other hand, the slag blocks with larger particle sizes can be directly plowed and screened. Secondly, the coal plow can also accurately control the discharge flow of the material to ensure that the material is evenly distributed on the conveyor belt, avoiding material accumulation or uneven sparseness, thereby improving the stability and efficiency of the production line.

[0076] Of course, in some other embodiments, the flow control of the screening unit can also be achieved directly through a coal plow. Specifically, the slag discharge port of the furnace is connected to the screening unit through a conveyor belt, and the conveyor belt is used to transport ash to the screening unit. A coal plow is provided on the conveyor belt, and the discharge port of the coal plow is connected to the slag bin 7. When it is necessary to stop feeding, the driving rod of the hydraulic drive device extends to drive the plowshare to descend, so that the lower edge of the plowshare is closely attached to the belt surface, so that all the materials on the conveyor belt are discharged into the slag bin 7. The feeding flow of the transmission belt can also be controlled by adjusting the height interval between the lower edge of the plowshare and the conveyor belt.

[0077] In this embodiment, the ash conveying device also includes a second controller, a first material level detection unit and a second material level detection unit. The first material level detection unit is installed in the primary ash collection tank 8 of the blending unit, and is used to detect the material level height of the primary ash particles in the primary ash collection tank 8, and send out the first material level information. The second material level detection unit is installed in the secondary ash collection tank 9 of the blending unit, and is used to detect the material level height of the secondary ash particles in the secondary ash collection tank 9, and send out the second material level information. The second controller is electrically connected to the first material level detection unit, the second material level detection unit, and the first flow regulating unit 2 and the second flow regulating unit 3, respectively, and the second controller is used to receive the first material level information and the second material level information, and control the opening of the first flow regulating unit 2 and the opening of the second flow regulating unit 3 according to the first material level information and the second material level information.

[0078] Furthermore, the second controller pre-stores the height threshold parameters of the primary ash collection tank 8 and the height threshold parameters of the secondary ash collection tank 9, the height threshold parameters of the primary ash collection tank 8 include a first height threshold and a second height threshold, the first height threshold is greater than the second height threshold, and the height threshold parameters of the secondary ash collection tank 9 include a third height threshold and a fourth height threshold, the third height threshold is greater than the fourth height threshold. The second controller is used to obtain the actual material level heights in the primary ash collection tank 8 and the secondary ash collection tank 9 according to the first material level information and the second material level information, and when the actual material level height in the primary ash collection tank 8 exceeds the first height threshold, or the actual material level height in the secondary ash collection tank 9 exceeds the third height threshold, control the first flow regulating unit 2 to block the first branch unit to stop the feeding of the screening unit, and control the second flow regulating unit 3 to open the second branch unit to transport the excess ash to the slag bin 7. The second controller is also used to control the first flow regulating unit 2 to open the first branch unit to feed the screening unit, and to control the second flow regulating unit 3 to block the second branch unit when the actual material level in the primary ash collecting tank 8 is lower than the second height threshold, or the actual material level in the secondary ash collecting tank 9 is lower than the fourth height threshold.

[0079] Specifically, the first height threshold and the third height threshold are both upper height limits, which are set to 80%-85% of the maximum capacity height of the tank. The second height threshold and the fourth height threshold are both lower height limits, which are set to 20%-25% of the maximum capacity height of the tank.

[0080] Exemplarily, the primary ash collection tank 8 and the secondary ash collection tank 9 are both straight cylindrical tanks, and their heights are both 5000mm. The upper limit of the height is set to 85%, and the lower limit of the height is set to 20%. When the actual ash height in the tank is higher than 4250mm, it is necessary to control the first flow regulating unit 2 (first plow ash slag device) to cut off the first branch conveyor belt, and at the same time, control the plow head of the second flow regulating unit 3 (second plow ash slag device) to lift up to release the second branch conveyor belt; when the actual ash height in the tank is lower than 1000mm, it is necessary to control the second flow regulating unit 3 (second plow ash slag device) to cut off the second branch conveyor belt, and at the same time, control the first flow regulating unit 2 (first plow ash slag device) to release the first branch conveyor belt to transport ash to the screening unit.

[0081] In another example, the upper limit of the height is set to 80%, and the lower limit of the height is set to 25%. When the actual ash height in the tank body is higher than 4000mm, it is necessary to control the first flow regulating unit 2 (first plow ash remover) to cut off the first branch conveyor belt, and at the same time, control the second flow regulating unit 3 (second plow ash remover) to release the second branch conveyor belt; when the actual ash height in the tank body is lower than 1250mm, it is necessary to control the second flow regulating unit 3 (second plow ash remover) to cut off the second branch conveyor belt, and at the same time, control the first flow regulating unit 2 (first plow ash remover) to release the first branch conveyor belt to transport ash to the screening unit.

[0082] Specifically, the second controller can be implemented by an industrial computer, or an application-specific integrated circuit (ASIC), or a programmable logic device (PLD). The above PLD can be a complex programmable logic device (CPLD), a field programmable gate array (FPGA), a general array logic (GAL) or any combination thereof.

[0083] The following will give a detailed description of the working process of the entire boiler coal-fired system:

[0084] Firstly, the boiler coal-fired system can be divided into the ash screening and collection system (part) and the furnace blending system (part).

[0085] The ash screening system (part) includes a circulating fluidized bed boiler 1, a first ash plow (i.e., a first flow regulating unit 2), a second ash plow (i.e., a second flow regulating unit 3), a coarse screening device 4, a primary screening machine 5, a secondary screening machine 6, a slag bin 7, a primary ash collecting tank 8, and a secondary ash collecting tank 9. The furnace blending system (part) includes an ash belt scale (a second belt scale 10), an ash belt scale (a third belt scale 11), a high-alkali coal bunker 12, a coal conveying belt scale (a first belt scale 13), and a mixing and conveying unit. The mixing and conveying unit includes a coal mixing belt 14 and a furnace coal bunker 15. The first belt scale 13, the second belt scale 10, and the third belt scale 11 are all connected to the coal mixing belt 14. The high-alkali coal weighed by the first belt scale 13, the primary ash particles weighed by the second belt scale 10, and the secondary ash particles weighed by the third belt scale 11 are all conveyed to the coal mixing belt 14 for blending. The inlet of the coal bunker 15 is connected to the coal mixing belt 14, and the outlet is connected to the furnace of the boiler 1. The coal bunker 15 is used for temporarily storing the mixed coal.

[0086] The bottom slag outlet of the circulating fluidized bed boiler 1 is divided into two branches (i.e., a first branch unit and a second branch unit). The first branch is connected to the inlet of the coarse screening device 4 via the ash plow, and the second branch is connected to the first inlet of the slag bin 7 via the ash plow.

[0087] The first ash slag hopper and the second ash slag hopper can both control the ash slag flow rate by setting the opening by lifting and lowering. Moreover, the first ash slag hopper and the second ash slag hopper can receive the material level alarm of the primary ash slag collection tank 8 and the secondary ash slag collection tank 9, automatically control the lifting and lowering while adjusting the internal opening, and timely replenish the fine slag after screening.

[0088] The coarse screening device 4 is located upstream of the primary screener, and is equipped with a vibrator to automatically screen ash particles with a particle size of more than 2 cm. The outlet of the coarse screening device 4 is connected to the inlet (first inlet) of the primary screener 5, and the primary screener 5 can screen out ash particles with a particle size range of 8-12 mm. The first outlet of the primary screener 5 is connected to the inlet of the primary ash collection tank 8 via a belt, and the second outlet is connected to the inlet of the secondary screener 6 (i.e., the second inlet), and the secondary screener 6 can screen out ash particles with a particle size range of 4-8 mm; the third outlet of the secondary screener 6 is connected to the inlet of the ash collection tank via a belt, and the fourth outlet is connected to the second inlet of the slag bin 7.

[0089] Material level alarms are provided in the primary ash collecting tank 8 and the secondary ash collecting tank 9. When the material level is lower than 25%, the material level alarm is automatically triggered and the opening of the first ash plow is adjusted to replenish the amount of fine slag required for subsequent blending.

[0090] The outlets of the primary ash collection tank 8 and the secondary ash collection tank 9 are connected to the coal mixing belt 14, and the blending amount is accurately controlled by the ash belt scale. The outlets of the (first and second) ash collection tanks are connected to the coal mixing belt 14, and the blending amount is accurately controlled by the ash belt scale (the second belt scale 10 and the third belt scale 11). In addition, the high-alkali coal bunker 12 is connected to the coal mixing belt 14 scale (the first belt scale 13), and the amount of high-alkali coal is controlled by the coal conveying belt scale. The coal mixing belt 14 is connected to the entrance of the furnace coal bunker 15, and is sent to the circulating fluidized bed boiler 1 after re-blending. The blending ratio is fed back in real time by the belt scale, and the amount of ash and high-alkali coal is automatically adjusted.

[0091] The boiler coal-fired system in this embodiment belongs to the field of coking prevention and control of high-alkali coal circulating fluidized bed boiler 1, and specifically relates to a process for co-burning high-alkali coal and ash in a circulating fluidized bed boiler 1. This system can realize the process of co-burning high-alkali coal and ash in a circulating fluidized bed, and its advantage is that it can reuse the ash of the fluidized bed, and after mixing with high-alkali coal, it can not only supplement the bed material, but also reduce the risk of slagging in the furnace after the high-alkali coal is burned, reduce production costs, and ensure the safe and stable operation of the fluidized bed boiler 1.

[0092] In summary, the beneficial results of this system are as follows:

[0093] (1) After cooling, the ash from the slag outlet of the boiler 1 initially reaches the coarse screening device 4. This step will separate 10-20% of the large-particle ash (particle size greater than 2 cm). The alkali metal enrichment ratio in the ash at this particle size reaches 40-60%. After passing through the primary screening machine 5 and the secondary screening machine 6, it reaches the ash collection tank. The opening of the first ash plow and the second ash plow is automatically adjusted according to the material level feedback signal in the ash collection tank to prevent the ash collection tank from being blocked due to overfilling, thereby realizing intelligent adjustment of ash utilization;

[0094] (2) The high-alkali coal is sent to the coal mixing belt 14 through the control of the belt scale, and is mixed with the ash in the primary ash collection tank 8 and the secondary ash collection tank 9 at the same time, wherein the ash amount of the ash collection tank is adjusted according to the uniformity of the bed material in the circulating fluidized bed boiler 1, wherein the first belt scale 13, the second belt scale 10 and the third belt scale 11 are used for monitoring, and the mixing ratio is accurately controlled to adjust the bed material distribution in the furnace;

[0095] (3) This system can recycle the ash 4-6 times. It is also a relatively economical high-alkali coal. The ash is used to fix sodium in the high-alkali coal, which reduces the risk of slagging of the high-alkali coal and reduces the overall production cost of the power plant. The overall process is simple and easy to operate.

[0096] Example 2

[0097] This embodiment is a specific application example of the boiler coal-fired system in Embodiment 1. The boiler 1 in this embodiment is in a low-load operation state.

[0098] The process flow is executed by the boiler coal-fired system in Example 1. Under 50% of the rated load, the bottom ash discharged from the bottom of the circulating fluidized bed boiler 1 is conveyed by a belt through the ash plow into the coarse screening device 4. This step will separate 10-15% of large-size slag blocks (particle size greater than 2 cm). The slag blocks under this particle size are enriched with 40-60% of the alkali metals in the ash and are centrally treated as waste. The remaining bottom ash enters the primary screening machine 5 for the first fine separation, and the slag particles with a particle size range of 8-12 mm are separated and sent to the primary ash collection tank 8 for standby use. The separation efficiency of this link can reach 40%. At the same time, the alkali metal enrichment in the ash under this particle size is less than 20%, which can better adsorb the flue gas alkali metals.

[0099] The remaining ash is further screened out into 4-8mm fine slag in the secondary screening machine 6, and sent to the secondary ash collection tank 9 for standby use. The separation efficiency of this link is 30%, and the alkali metal enrichment ratio of ash particles under this particle size is less than 5%, which has a strong adsorption effect on alkali metals in flue gas. After the screening link is completed, the remaining bottom slag is sent to the slag bin 7 for subsequent treatment. The high-alkali coal coming out of the high-alkali coal bin 12 is conveyed to the mixed coal belt 14 by the coal conveyor belt scale. The primary ash and secondary ash are respectively conveyed to the mixed coal belt 14 after the ash belt scale. The blending ratio is accurately controlled by three belt scales, so that the high-alkali coal: primary ash: secondary ash in the mixed coal is 8:1:1, and the mixed coal is sent to the circulating fluidized bed through the furnace coal bin 15. The blending ratio is the blending ratio under a lower load. At this time, the high-alkali coal ratio can be appropriately increased. Through this process, the number of ash circulations is maintained at 4-6 times, and the ash treatment cost is reduced by 30-40%. Due to the blending of 20% filtered ash, the alkali-acid ratio in the furnace is reduced by 30-50%, and the risk of slagging contamination in the furnace is reduced.

[0100] Example 3

[0101] This embodiment is another specific application example of the boiler coal-fired system in Embodiment 1. The difference from Embodiment 2 is that the boiler 1 in this embodiment is in a high-load operation state.

[0102] By executing the process flow of the boiler coal-fired system in Example 1, at a rated load of 80% or more, a large amount of bottom ash discharged from the bottom of the circulating fluidized bed boiler 1 is discharged, and enters the coarse screening device 4 through the first ash plow (i.e., the first flow regulating unit 2). This step separates 15-20% of large-size slag blocks (particle size greater than 2 cm), and the slag blocks are enriched with 40-60% of alkali metals in the ash, which is conducive to the centralized treatment of alkali metals. The remaining bottom ash enters the primary screening machine 5 for the first fine separation, and the ash particles with a particle size range of 8-12 mm are separated and sent to the primary ash collection tank 8 for standby use. The separation efficiency of this link can reach 40%. At the same time, the enrichment of alkali metals in the ash under this particle size is less than 20%, which can better adsorb flue gas alkali metals.

[0103] The remaining ash is further screened out into 4-8mm fine slag in the secondary screening machine 6, and sent to the secondary ash collection tank 9 for standby use. The separation efficiency of this link is 30%, and the alkali metal enrichment ratio of ash particles under this particle size is less than 5%, which has a strong adsorption effect on alkali metals in flue gas. After the screening link is completed, the remaining bottom slag is sent to the slag bin 7 for subsequent treatment. The high-alkali coal coming out of the high-alkali coal bin 12 is conveyed to the mixed coal belt 14 by the coal conveyor belt scale. The primary ash and secondary ash are respectively conveyed to the mixed coal belt 14 after the ash belt scale. The blending ratio is accurately controlled by three belt scales, so that the high-alkali coal in the mixed coal: primary ash: secondary ash is 5:1:1, and the mixed coal is sent to the circulating fluidized bed through the furnace coal bin 15. The blending ratio is the blending ratio under higher load, and the high-alkali coal needs to be appropriately reduced at this time. At this blending ratio, 40% of the circulating ash is required in the circulating fluidized bed, and the circulating ash is controlled below 30%, firstly to ensure that the ash volume of the power plant is sufficient, and secondly to maximize the use of high-alkali coal. Through this process, the ash circulation times are maintained at 4-6 times under higher loads, and the ash treatment cost is reduced by 40-50%. Due to the blending of 28% filtered ash, the alkali-acid ratio in the furnace under high load can be reduced by 20-30%, and the risk of slagging contamination is greatly reduced.

[0104] According to Example 2 and Example 3, it can be seen that the boiler coal-fired system in the present application can effectively reduce the slagging and contamination of high-alkali coal during the combustion process under both high-load operation and low-load operation conditions.

[0105] Moreover, the particle size range of the separated ash particles is 4mm-2cm, and it is not necessary to separate the nano-scale ash particles, and a good adsorption effect of alkali metals in the flue gas can be achieved. This is because the circulating fluidized bed boiler 1 used in this application is different from the pulverized coal boiler 1 in the prior art in terms of operation mode, furnace type and coal powder fineness requirements. The circulating fluidized bed furnace temperature is 850-960℃, and the particle size of the coal entering the furnace is about 10mm, and the fuel and circulating ash particles are fluidized and burned; the furnace temperature of the pulverized coal boiler 1 is about 1500℃, and the coal particle size is 60-80μm, which is suspended and burned in the furnace after mixing with air. Secondly, due to the large particle size in the fluidized bed, the fuel and circulating ash have a long residence time, which can fully adsorb the alkali metal compounds released from the coal. In addition, due to the large amount of circulating ash, it can flush the heating surface to a certain extent, which is conducive to decoking.

[0106] It should also be noted that due to the different loads of the boiler 1 in Example 2 and Example 3, the proportion of large-size slag blocks screened out by the coarse screening device 4 will be different. In Example 2, at a medium and low load of less than 50%, the furnace temperature is low, and the coking of the boiler 1 will be relatively mild, but there will also be some coking in the combustion center area. At this time, the large-size ash produced is relatively low (proportion), and the coarse screening device 4 will separate 10-15% of the large-size slag blocks (particle size greater than 2cm); in Example 3, since the load is above 80%, the furnace temperature is greatly increased at this time, and the high-alkali coal ash has a low melting point, so the coking ratio is large, and there are more large-size slag blocks in the ash. In this process, the large-size slag blocks screened out will increase by 5-10% compared to low loads, that is, the coarse screening device 4 separates 15-20% of the large-size slag blocks (particle size greater than 2cm).

[0107] Example 4

[0108] See also Figure 1 The present invention also discloses a control method for a boiler coal-fired system, which is applied to the boiler coal-fired system in Example 1.

[0109] The method comprises the following steps:

[0110] Obtain the load parameters and proportion parameters of boiler 1.

[0111] According to the load parameter and ratio parameter of the boiler 1, the target blending ratio is obtained.

[0112] According to the target blending ratio, the blending unit is controlled to blend the high-alkali coal, the primary ash particles and the secondary ash particles to obtain blended coal.

[0113] The blended coal is fed into the furnace of the boiler 1 for combustion.

[0114] Further, the load parameter includes a set steam output threshold of the boiler 1 and a required steam output value of the boiler 1. The ratio parameter includes: a first blending ratio and a second blending ratio, and the high-alkali coal ratio in the first blending ratio is lower than the high-alkali coal ratio in the second blending ratio.

[0115] Step: According to the load parameter and proportion parameter of the boiler 1, the target blending ratio is obtained, which specifically includes:

[0116] According to the load parameters, it is determined whether the required steam output value is higher than the set steam output threshold value: if so, the first blending ratio in the ratio parameter is selected as the target blending ratio; if not, the second blending ratio in the ratio parameter is selected as the target blending ratio.

[0117] Specifically, the blending ratio under low load (the following ratios are all high-alkali coal: primary ash particles: secondary ash particles) is (7-10):1:1; the blending ratio under high load is (4-6):1:1. Exemplarily, the blending ratio under low load is 8:1:1; the blending ratio under high load is 5:1:1.

[0118] When the boiler 1 is operating at high load, the proportion of high-alkali coal needs to be reduced. This is because, under low load, the temperature of the circulating fluidized bed is generally low, and multiple parameters such as the operating conditions of the boiler 1 are unstable. At this time, increasing the proportion of high-alkali coal can, on the one hand, maintain the stable combustion capacity of the boiler 1, and it is not easy to cause local heat imbalance due to ash circulation, resulting in the flameout of the boiler 1; on the other hand, the low-load controlled furnace temperature is low, and the risk of coking is low, so the proportion of high-alkali coal can be appropriately increased to save costs. Secondly, under high load, the furnace temperature increases. At this time, reducing the proportion of high-alkali coal can still maintain the stable combustion effect of boiler 1, and the probability of coking increases under high load, so it is necessary to control the amount of high-alkali coal to ensure the safe operation of boiler 1.

[0119] It can be seen that by selecting a more appropriate blending ratio according to the load condition of boiler 1, the slagging and contamination of high-alkali coal during the combustion process can be effectively reduced. At the same time, the stable combustion capacity of boiler 1 can be maintained to avoid flameout of boiler 1, as well as save costs.

[0120] It is to be understood that the above embodiments are merely exemplary embodiments used to illustrate the principles of the present invention, but the present invention is not limited thereto. For those of ordinary skill in the art, various modifications and improvements can be made without departing from the spirit and essence of the present invention, and these modifications and improvements are also considered to be within the scope of protection of the present invention.

Claims

1. A boiler coal-fired system, characterized in that: include: A high-alkali coal bunker (12), a boiler (1), a screening unit and a blending unit; The high-alkali coal bin (12) is used to store high-alkali coal; The boiler (1) is provided with a furnace, the furnace is provided with a coal inlet and a slag outlet, the coal inlet is connected to the high-alkali coal bunker (12), the furnace is used to receive high-alkali coal and burn the high-alkali coal, and the slag outlet is used to discharge ash and slag generated after the high-alkali coal is burned out of the furnace; The screening unit is connected to the slag discharge port, and is used to screen the ash and output primary ash particles and secondary ash particles, wherein the particle size of the primary ash particles is larger than that of the secondary ash particles; The blending unit is located between the high-alkali coal bin (12) and the boiler (1); the high-alkali coal bin (12) is connected to the furnace through the blending unit; the blending unit is also connected to the screening unit, respectively, for receiving high-alkali coal, primary ash particles and secondary ash particles, blending the high-alkali coal, primary ash particles and secondary ash particles according to a set blending ratio to obtain blended coal, and inputting the blended coal into the furnace for subsequent combustion.

2. The boiler coal-fired system according to claim 1, characterized in that: The screening unit comprises a primary screening machine (5) and a secondary screening machine (6); The primary screening machine (5) is provided with a first inlet, a first outlet and a second outlet, the first inlet is connected to the slag discharge port, the primary screening machine (5) is used to perform a primary screening on the ash, and discharge primary ash particles and primary bottom slag from the first outlet and the second outlet respectively; The secondary screening machine (6) is provided with a second inlet, a third outlet and a fourth outlet, the second inlet is connected to the second outlet of the primary screening machine (5), the secondary screening machine (6) is used to perform secondary screening on the primary bottom ash, and discharge secondary ash particles and waste bottom ash from the third outlet and the fourth outlet respectively.

3. The boiler coal-fired system according to claim 2, characterized in that: The blending unit includes a first controller and a weighing unit, The weighing unit is respectively connected to the outlet of the high-alkali coal bin (12), the first outlet of the primary screening machine (5) and the third outlet of the secondary screening machine (6); The blending ratio is pre-stored in the first controller, and the first controller is electrically connected to the weighing unit, and is used to control the weighing unit to weigh the corresponding high-alkali coal, primary ash particles and secondary ash particles according to the blending ratio; The weighing unit is also connected to the furnace and is used to transport the high-alkali coal, primary ash particles and secondary ash particles weighed according to a preset ratio into the furnace.

4. The boiler coal-fired system according to claim 3, characterized in that: The weighing unit comprises a first belt scale (13), a second belt scale (10), a third belt scale (11) and a mixing conveying unit; The first controller is used to store the preset ratio in advance, the first controller is electrically connected to the first belt scale (13), the second belt scale (10) and the third belt scale (11), and the first controller is used to send out a first weight signal, a second weight signal and a third weight signal according to the blending ratio; The first belt scale (13) is connected to the high-alkali coal bin (12) and is used to receive a first weight signal and weigh a corresponding weight of the high-alkali coal according to the first weight signal; The second belt scale (10) is connected to the first outlet of the primary screening machine (5) and is used to receive the second weight signal and weigh the primary ash particles of corresponding weight according to the second weight signal; The third belt scale (11) is connected to the third outlet of the secondary screening machine (6) and is used to receive a third weight signal and weigh the secondary ash particles of corresponding weight according to the third weight signal; The mixing and conveying unit is respectively connected to the first belt scale (13), the second belt scale (10) and the third belt scale (11), and is used to mix the high-alkali coal, the primary ash particles and the secondary ash particles and convey them to the furnace.

5. The boiler coal-fired system according to claim 4, characterized in that: The blending unit further comprises a primary ash collection tank (8) and a secondary ash collection tank (9); The primary ash collecting tank (8) is located between the primary screening machine (5) and the second belt weigher (10), the inlet of the primary ash collecting tank (8) is connected to the first outlet of the primary screening machine (5), and the outlet is connected to the second belt weigher (10), and the primary ash collecting tank (8) is used to receive and temporarily store the primary ash particles; The secondary ash collecting tank (9) is located between the secondary screening machine (6) and the third belt scale (11); the inlet of the secondary ash collecting tank (9) is connected to the third outlet of the secondary screening machine (6), and the outlet is connected to the third belt scale (11); the secondary ash collecting tank (9) is used to receive and temporarily store the secondary ash particles.

6. The boiler coal-fired system according to any one of claims 1 to 5, characterized in that: It also includes an ash conveying device and a slag bin (7), The ash conveying device comprises a main feeding unit, a first branch unit and a second branch unit, one end of the main feeding unit is connected to the slag discharge port, and the other end is connected to the first branch unit and the second branch unit; The first branch unit is connected to the screening unit and is used to transport ash to the screening unit. The screening unit is also connected to the slag bin (7) and is used to discharge the screened waste bottom slag into the slag bin (7). The second branch unit is connected to the slag bin (7) and is used to directly transport excess ash to the slag bin (7).

7. The boiler coal-fired system according to claim 6, characterized in that: The ash conveying device further comprises a first flow regulating unit (2) and a second flow regulating unit (3); the first flow regulating unit (2) is installed on the first branch unit, and the first flow regulating unit (2) is used to control the feeding flow on the first branch unit, thereby controlling the ash flow entering the screening unit; the second flow regulating unit (3) is installed on the second branch unit, and is used to control the feeding flow on the second branch unit.

8. The boiler coal-fired system according to claim 7, characterized in that: The ash conveying device further includes a second controller, a first material level detection unit and a second material level detection unit. The first material level detection unit is installed in the primary ash collection tank (8) of the blending unit, and is used to detect the material level height of the primary ash particles in the primary ash collection tank (8) and issue first material level information. The second material level detection unit is installed in the secondary ash collection tank (9) of the blending unit, and is used to detect the material level height of the secondary ash particles in the secondary ash collection tank (9) and issue second material level information. The second controller is electrically connected to the first material level detection unit, the second material level detection unit, the first flow regulating unit (2) and the second flow regulating unit (3) respectively, and the second controller is used to receive the first material level information and the second material level information, and control the opening of the first flow regulating unit (2) and the opening of the second flow regulating unit (3) according to the first material level information and the second material level information.

9. The boiler coal-fired system according to claim 8, characterized in that: The second controller pre-stores a height threshold parameter of a primary ash collection tank (8) and a height threshold parameter of a secondary ash collection tank (9), wherein the height threshold parameter of the primary ash collection tank (8) includes a first height threshold and a second height threshold, wherein the first height threshold is greater than the second height threshold, and the height threshold parameter of the secondary ash collection tank (9) includes a third height threshold and a fourth height threshold, wherein the third height threshold is greater than the fourth height threshold; The second controller is used to obtain the actual material level heights in the primary ash collection tank (8) and the secondary ash collection tank (9) according to the first material level information and the second material level information, and when the actual material level height in the primary ash collection tank (8) exceeds the first height threshold, or when the actual material level height in the secondary ash collection tank (9) exceeds the third height threshold, control the first flow regulating unit (2) to block the first branch unit to stop the feeding of the screening unit, and control the second flow regulating unit (3) to open the second branch unit to transport excess ash to the slag bin (7); The second controller is also used to control the first flow regulating unit (2) to open the first branch unit to feed the screening unit, and to control the second flow regulating unit (3) to block the second branch unit when the actual material level in the primary ash collecting tank (8) is lower than the second height threshold, or the actual material level in the secondary ash collecting tank (9) is lower than the fourth height threshold.

10. A control method for a boiler coal-fired system, the method being applied to the boiler coal-fired system according to any one of claims 1 to 9, characterized in that: include: Obtaining load parameters and proportional parameters of the boiler (1); Obtaining a target blending ratio according to a load parameter and a ratio parameter of the boiler (1); According to the target blending ratio, controlling the blending unit to blend the high-alkali coal, the primary ash particles and the secondary ash particles to obtain blended coal; The blended coal is fed into the furnace of a boiler (1) for combustion.

11. The control method of a boiler coal-fired system according to claim 10, characterized in that: The load parameters include a set steam output threshold of the boiler (1) and a required steam output value of the boiler (1); The ratio parameters include: a first blending ratio and a second blending ratio, wherein the high-alkali coal ratio in the first blending ratio is lower than the high-alkali coal ratio in the second blending ratio; The step of obtaining a target blending ratio according to the load parameter and the ratio parameter of the boiler (1) specifically includes: According to the load parameter, it is determined whether the required steam output value is higher than the set steam output threshold: If yes, the first blending ratio in the ratio parameter is selected as the target blending ratio; if no, the second blending ratio in the ratio parameter is selected as the target blending ratio.