Tunnel secondary lining steel bar protection layer thickness detection device and use method

By designing a detection device for tunnels, using cloth trolleys and geological radar scanners to detect the thickness of the tunnel steel bar protective layer, the efficiency and accuracy of traditional detection methods are solved, and fast and accurate detection and labeling are achieved, improving the quality of the traditional detection methods. Construction efficiency and project quality are achieved.

CN118960589APending Publication Date: 2024-11-15CHINA MCC17 GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411223002.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-03
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

Traditional methods cannot achieve rapid, accurate and comprehensive detection of the thickness of the tunnel steel bar protective layer, and there are problems of human error and limited detection range.

Method used

A tunnel two-lined steel bar protective layer thickness detection device including cloth hanging trolley, detection components and fixed components is designed. Using a geological radar scanner and pigment injector, the cloth hanging trolley movement detection array is moved along the tunnel in real time. Detect and mark unqualified parts, upload data to the terminal in real time, providing double detection insurance.

Benefits of technology

It realizes rapid detection and labeling of the thickness of the overall second lining protective layer of the tunnel, improves detection efficiency and engineering quality, reduces manual errors, and ensures the accuracy and comprehensiveness of the detection results.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118960589A_ABST
    Figure CN118960589A_ABST
Patent Text Reader

Abstract

The invention discloses a tunnel secondary lining steel bar protection layer thickness detection device and a use method, and belongs to the technical field of tunnel protection layer construction, and the tunnel secondary lining steel bar protection layer thickness detection device comprises a detection part and a fixing part; the detection part comprises a plurality of shells, scanners and pigment ejectors are arranged in the shells in a matched mode, pigment ejection holes are formed in the peripheries of the shells, connecting pieces are arranged on the sides, close to the support, of the shells, the shells are sequentially in lap joint to form a detection array, the detection array is installed on the support in a covering mode, and signal lines are arranged in the support. One end of the signal line is connected with the detection array, and the other end is connected with a detection terminal which is detachably connected to the cloth hanging trolley; the fixing part comprises a support which is detachably connected to the cloth hanging trolley. The problems of small detection range and large detection result randomness caused by limited labor energy and limited detection distance in traditional detection are solved, and the control terminal is connected with a mobile phone of an accompanying worker through Bluetooth, so that the worker knows problem distribution, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of tunnel protective layer construction, and specifically relates to a device for detecting the thickness of a tunnel secondary lining steel bar protective layer and a method for using the device. Background Art

[0002] The tunnel steel bar protective layer refers to the distance from the outer edge of the outermost steel bar to the concrete surface. It aims to protect the steel bars from rusting while ensuring the durability and functionality of the structure. It is mainly reflected in protecting the steel bars from rusting and withstanding external forces. The thickness of the tunnel steel bar protective layer has an important impact on the performance and safety of the tunnel structure.

[0003] The thickness of the rebar cover is a key factor influencing tunnel structural performance. It not only affects the durability of the rebar and its bond with concrete, but also directly impacts the tunnel's load-bearing capacity and service life. During construction, the thickness of the concrete cover can be affected by factors such as construction errors, the type of sprayed concrete, and environmental factors. After construction is complete, the concrete cover must be measured and uneven areas marked for subsequent correction. Traditional methods require manual sampling and testing, making complete testing impossible.

[0004] After searching, the invention with publication number CN112729198B provides a method for detecting the thickness of concrete steel bar protective layer, which includes a steel bar detector, wherein sliding blocks are fixedly connected on both sides of the steel bar measuring instrument, and clamping blocks are provided on both sides of the steel bar measuring instrument. Suction cups are fixedly connected to the sides of the clamping blocks, and the two clamping blocks are provided with sliding grooves for the sliding blocks to be inserted and slided on the side facing the steel bar detector. Limiting blocks protruding toward the steel bar detector are fixedly connected at the notches at both ends of the sliding grooves; the thickness of the protective layer can only be detected at one place at a time, and a complete detection takes a lot of time. At the same time, there is also the human influence of the construction workers, and it is impossible to ensure that the thickness of the tunnel secondary lining concrete protective layer meets the specifications. Summary of the Invention

[0005] The technical problem to be solved by the present invention is to provide a tunnel secondary lining steel bar protective layer thickness detection device and a use method to solve the problems mentioned in the background technology or achieve better technical effects.

[0006] A device for detecting the thickness of a protective layer of a secondary lining steel bar in a tunnel, comprising a cloth hanging trolley, wherein the device comprises a detecting component and a fixing component;

[0007] The cloth hanging trolley does not belong to this device, is mainly responsible for the movement and position adjustment of this device, and is a supporting equipment of this device.

[0008] The detection component includes a shell, a scanner and a pigment injector are provided inside the shell, a pigment injection hole is provided on a side of the shell close to the concrete protective layer, and the pigment injection holes are distributed along the four sides, a connector is provided on a side of the shell close to the bracket, the shell includes multiple shells, and the multiple shells are overlapped in sequence to form a detection array, the detection array is covered and installed on the bracket, a signal line is provided inside the bracket, one end of the signal line is connected to the detection array, and the other end is connected to the detection terminal, and the detection terminal is detachably connected to the cloth hanging trolley;

[0009] Furthermore, the fixing component includes a bracket, and the bracket is detachably connected to the cloth hanging trolley; being installed on the cloth hanging trolley reduces the cost of use.

[0010] Furthermore, the bracket can be made of threaded steel, the bracket can be processed in sections and then welded and assembled, the curvature radius of the bracket is calculated based on the curvature of the tunnel secondary lining, long steel bars are used to make the bracket, and the bracket can be detachably connected to the cloth hanging trolley; the bracket is made of materials and manufactured on site, which can better fit the tunnel surface and improve detection accuracy.

[0011] Furthermore, the shell is symmetrically provided with fixing grooves along the center line perpendicular to the direction of the bracket, and the fixing grooves are equipped with fixing parts. The shell is provided with overlapping joints at both ends along the arrangement direction of the detection array. The fixing parts limit left and right movement, and the overlapping joints limit up and down movement while facilitating the installation of components.

[0012] Furthermore, the lap joint includes a protruding lap joint and a recessed lap joint, the recessed lap joint has protrusions on both sides, and the protruding lap joint has grooves on both sides; during installation, the protruding lap joint and the recessed lap joint cooperate with each other to facilitate positioning and installation, and the protrusions and grooves on both sides of the protruding lap joint and the recessed lap joint cooperate with each other to further limit the movement of the shell and avoid dislocation during installation.

[0013] Furthermore, a paint tank is installed on one side of the shell close to the bracket. The paint inside the paint tank is a water-soluble paint. The paint tank stores multiple colors; it can be one, two or more colors. Different paints are used to mark areas where the concrete protective layer is too thick or too thin, which is convenient for subsequent construction. The use of water-soluble paint avoids confusion in subsequent construction marks. The storage of multiple paints can effectively avoid confusion.

[0014] Furthermore, a wear-resistant layer is provided on the side of the shell away from the bracket, and a fluorescent mark is provided on the contact surface between the wear-resistant layer and the shell; the fluorescent mark is used to remind construction workers that the wear-resistant layer is too thin and needs to be replaced in time.

[0015] Furthermore, the shell is provided with installation serial numbers around it; the installation serial numbers are stamped or attached to the shell using a sticker to facilitate construction, installation and positioning.

[0016] Furthermore, the shell is symmetrically mounted with laser lights along a center line perpendicular to the direction of the bracket; the laser lights display whether the current detection position is correct and in contact with the surface of the protective layer.

[0017] Furthermore, the tunnel secondary lining steel bar protective layer thickness detection device is powered by a cable connected to a power source, and the scanner is a geological radar scanner.

[0018] Furthermore, the detection terminal can store and record the data of the thickness of the steel bar protective layer, automatically number the steel bars and identify the steel bar grid. The detection terminal connects to the staff's mobile phone via Bluetooth and uploads construction data; by organizing the data through the terminal, construction personnel can see the thickness of the protective layer more intuitively, understand the distribution of problems and specific locations, better schedule shifts, and improve work efficiency.

[0019] The present invention also discloses a method for using a device for detecting the thickness of a tunnel secondary lining steel bar protective layer, comprising the following steps:

[0020] S1: Make the bracket; Make the bracket in the steel bar processing workshop according to the tunnel curvature;

[0021] S2: Check the cloth hanging trolley; perform corresponding inspections on the cloth hanging trolley according to relevant regulations;

[0022] S3: Install the bracket: hoist the bracket to the middle position of the hanging trolley and connect the corresponding jack to ensure it is firmly installed;

[0023] S4: Assemble the detection array; according to the installation serial number on the housing, install the components to the designated position of the bracket. The components are installed in groups and connected by overlapping joints during installation. After a group is installed, the fixing parts are inserted into the fixing slots. Repeat step S4 until the assembly of the detection array is completed;

[0024] S5: Debugging the detection array; electrically connecting the detection array to the control terminal. The staff uses the control terminal to calibrate the detection array. At the same time, the staff checks the amount of pigment in the pigment tank and the degree of wear of the wear-resistant layer, and replaces it in time.

[0025] S6: Start working; after checking that everything is correct, start the cloth hanging trolley to enter the tunnel and start testing.

[0026] Compared with the prior art, the present invention can achieve the following technical effects:

[0027] The device is driven to move by the cloth hanging trolley to detect the thickness of the overall secondary lining protective layer of the tunnel. At the same time, the detection data is uploaded to the terminal in real time and sent to the construction personnel at the same time, so that the construction personnel can understand and monitor in real time. When the detection array detects an unqualified concrete protective layer, the terminal uses a paint sprayer to spray different colors of paint to mark the location of the defect according to whether it is too thick or too thin, and records it on the terminal. This solves the problems of limited manual energy and limited detection distance in traditional detection, resulting in a small detection range and random detection results. When the cloth hanging trolley reaches the end point, the data is sorted and retained for comparison in the next construction. The operating status of the cloth hanging trolley and the device is checked. When the repair is completed, the cloth hanging trolley returns to the original route for re-inspection, realizing double detection and double insurance, and further improving the quality of the project.

[0028] The control terminal connects to the mobile phones of accompanying staff via Bluetooth and uploads data to the mobile phones, allowing staff to see the concrete cover thickness test results more intuitively, understand the distribution of problems, and schedule shifts reasonably, further improving construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.

[0030] Figure 1 It is a front view of the present invention;

[0031] Figure 2 It is a side view of the present invention;

[0032] Figure 3 It is a schematic diagram of the shell structure of the present invention;

[0033] Figure 4 It is a side view of the shell structure of the present invention.

[0034] In the figure: 1. bracket, 2. housing, 201. paint injection hole, 202. laser light, 203. paint tank, 204. connector, 205. wear-resistant layer, 206. fixing groove, 207. overlap joint, 208. protrusion, 209. groove, 3. cloth hanging trolley, 301. detection terminal, 302. detection array, 303. jack, 4. concrete protective layer. DETAILED DESCRIPTION

[0035] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0036] The application principle of the present invention will be further described below with reference to the accompanying drawings and specific embodiments.

[0037] Example 1

[0038] like Figure 1-4 As shown:

[0039] The tunnel secondary lining steel bar protective layer thickness detection device includes a detection component and a fixing component;

[0040] The fixing component includes a bracket 1 , which is detachably connected to the cloth hanging trolley 3 .

[0041] The detection component includes a shell 2, a scanner and a paint injector are provided inside the shell 2, paint injection holes 201 are provided around the shell 2, a connector 204 is provided on the side of the shell 2 close to the bracket 1, the shell 2 includes multiple shells, and the multiple shells 2 are overlapped in sequence to form a detection array 302, the detection array 302 is covered and mounted on the bracket 1, a signal line is provided inside the bracket 1, one end of the signal line is connected to the detection array 302, and the other end is connected to the detection terminal 301, and the detection terminal 301 is detachably connected to the cloth hanging trolley 3;

[0042] The bracket 1 is made of threaded steel. The bracket 1 is processed in sections and then welded and assembled. The curvature radius of the bracket 1 is calculated based on the curvature of the tunnel secondary lining. Long steel bars are used in the production of the bracket 1.

[0043] The housing 2 is symmetrically provided with fixing grooves 206 along a center line perpendicular to the bracket 1 . The fixing grooves 206 are equipped with fixing pieces. The housing 2 is provided with overlapping joints 207 at both ends along the arrangement direction of the detection array 302 .

[0044] The overlap joint 207 includes a protruding overlap joint and a recessed overlap joint. The recessed overlap joint has protrusions 208 on both sides, and the protruding overlap joint has grooves 209 on both sides.

[0045] A paint tank 203 is installed on one side of the housing 2 close to the bracket 1. The paint inside the paint tank 203 is a water-soluble paint. The paint tank 203 stores four colors.

[0046] A wear-resistant layer 205 is provided on the side of the housing 2 away from the bracket 1 , and a fluorescent mark is provided on the contact surface between the wear-resistant layer 205 and the housing 1 , and installation serial numbers are provided around the housing 2 .

[0047] The housing 2 is symmetrically mounted with laser lights 202 along a center line perpendicular to the bracket 1 .

[0048] The tunnel secondary lining steel bar protective layer thickness detection device is powered by a cable connected to a power source, and the scanner is a geological radar scanner.

[0049] The detection terminal 301 stores and records the steel bar protective layer thickness data, automatically numbers the steel bars and identifies the steel bar grid. The detection terminal 301 connects to the staff's mobile phone via Bluetooth and uploads construction data.

[0050] A method for using a device for detecting the thickness of a tunnel secondary lining steel bar protective layer comprises the following steps:

[0051] S1: manufacturing support 1; manufacturing support 1 in a steel bar processing workshop according to the curvature of the tunnel;

[0052] S2: Check the cloth hanging trolley; perform corresponding inspections on the cloth hanging trolley according to relevant regulations;

[0053] S3: Install the bracket: hoist the bracket 1 to the middle position of the cloth hanging trolley 3 and connect the corresponding jack 303 to ensure that it is firmly installed;

[0054] S4: Assemble the detection array; according to the installation serial number on the shell 2, install the components to the specified position of the bracket 1, and install the components in groups. When installing, connect them through the overlap joint 207. When installing, the staff selects the corresponding shell 2 according to the digital mark. When installing the shell 2, install it from low to high and from left to right. After fixing the initial shell 2 on the bracket 1, the protruding overlap joints and the recessed overlap joints at both ends of the shell 2 are installed in accordance with the array assembly direction. At the same time, the protrusions 208 and grooves 209 on both sides of the overlap joint 207 cooperate with each other to prevent the shell from being misaligned. After a group of installation is completed, insert the fixing parts into the fixing groove 206 to connect a group of shells 2 into a whole. Repeat step S4 until the assembly of the detection array is completed;

[0055] S5: Debugging the detection array; electrically connecting the detection array to the control terminal. The staff uses the control terminal to calibrate the detection array. At the same time, the staff checks the amount of pigment in the pigment tank 203 and the degree of wear of the wear-resistant layer 205, and replaces them in time.

[0056] S6: Start working; after checking that everything is correct, start the cloth hanging trolley 3 to enter the tunnel and start testing.

[0057] When the equipment starts working, the construction workers follow the cloth hanging trolley to observe whether the device is working properly. For areas with large pigment markings, the staff can use a handheld detector to re-inspect to determine whether the thickness of the concrete protective layer 4 in the area is qualified. If it is determined to be unqualified, it means that the device is working properly. If the handheld detector is qualified, the cloth hanging trolley will stop moving forward. At the same time, the construction workers will locate the pigment injection hole 201 on the shell 2 according to the spraying position to see if it is damaged. If damaged, the nozzle will be repaired in time and the error mark will be flushed with water. If it is not damaged, the device will be calibrated and returned for re-inspection.

[0058] Working principle:

[0059] The detection array 302 is driven by the cloth hanging trolley 3 and moves along the predetermined track in the tunnel. During the movement, multiple scanners inside the detection array 302 work together to record the thickness data of the concrete protective layer 4. The laser lights on both sides of the shell 2 indicate the scanning working range. When the scanner detects that the thickness of the concrete protective layer at the scanning location is unqualified, the detection terminal 301 records the concrete thickness at this location and compares it with the concrete thickness specification to determine whether it is too thick or too thin. According to the thickness, the pigment injection hole 201 sprays pigments of different colors to facilitate repairs by construction workers. Then the cloth hanging trolley 3 continues to move along the track until the entire tunnel section is inspected, and then the damaged parts of the device are inspected and replaced. After the construction workers have repaired the marked position, they return along the original track and conduct another inspection until the tunnel concrete protective layer is completely qualified.

[0060] The control terminal 301 is connected to the mobile phone of the accompanying staff via Bluetooth and uploads the data to the mobile phone, so that the staff can see the thickness detection results of the concrete cover 4 more intuitively, understand the distribution of problems, and further improve the construction efficiency.

[0061] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the invention can be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. Therefore, the embodiments should be considered in all respects as illustrative and non-restrictive, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations that come within the meaning and range of equivalents of the claims be embraced therein.

[0062] In addition, it should be understood that although this specification is described in terms of implementation methods, not every implementation method contains only one independent technical solution. This narrative method of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment can also be appropriately combined to form other implementation methods that can be understood by those skilled in the art.

Claims

1. A device for detecting the thickness of the secondary lining steel bar protective layer of a tunnel, comprising a cloth hanging trolley (3), characterized in that: It includes a detection component and a fixing component; The fixing component comprises a bracket (1), and the bracket (1) is detachably connected to the cloth hanging trolley (3); The detection component comprises a shell (2), a scanner and a paint injector are provided inside the shell (2), paint injection holes (201) are provided around the shell (2), a connector (204) is provided on the side of the shell (2) close to the bracket (1), the shell (2) comprises a plurality of shells (2), the plurality of shells (2) are overlapped in sequence to form a detection array (302), the detection array (302) is covered and installed on the bracket (1), a signal line is provided inside the bracket (1), one end of the signal line is connected to the detection array (302), and the other end is connected to the detection terminal (301), and the detection terminal (301) is detachably connected to the cloth hanging trolley (3).

2. A tunnel secondary lining steel bar protective layer thickness detection device according to claim 1, characterized in that: The support (1) is made of threaded steel. The support (1) is processed in sections and then welded and assembled. The curvature radius of the support (1) is calculated based on the curvature of the tunnel secondary lining. Long steel bars are used to manufacture the support (1).

3. A tunnel secondary lining steel bar protective layer thickness detection device according to claim 1, characterized in that: The housing (2) is symmetrically provided with fixing grooves (206) along a center line perpendicular to the direction of the bracket (1); the fixing grooves (206) are matched with fixing pieces; and overlapping joints (207) are provided at both ends of the housing (2) along the arrangement direction of the detection array (302).

4. A tunnel secondary lining steel bar protective layer thickness detection device according to claim 3, characterized in that: The overlapping joint (207) comprises a protruding overlapping joint and a recessed overlapping joint, the recessed overlapping joint has protrusions (208) on both sides, the protruding overlapping joint has grooves (209) on both sides, and the contact surfaces of the protrusion (208) and the groove (209) are arc-shaped.

5. The device for detecting thickness of the secondary lining steel bar protective layer of a tunnel according to claim 3 is characterized by: A paint tank (203) is installed on one side of the housing (2) close to the bracket (1); the paint inside the paint tank (203) is a water-soluble paint; and the paint tank (203) stores a variety of colors.

6. A tunnel secondary lining steel bar protective layer thickness detection device according to claim 5, characterized in that: A wear-resistant layer (205) is provided on the side of the outer shell (2) away from the bracket (1), a fluorescent mark is provided on the contact surface between the wear-resistant layer (205) and the outer shell (1), and the outer shell (2) includes installation serial numbers around its periphery.

7. A tunnel secondary lining steel bar protective layer thickness detection device according to claim 6, characterized in that: The housing (2) is symmetrically mounted with a laser lamp (202) along a center line perpendicular to the support (1).

8. The device for detecting thickness of the secondary lining steel bar protective layer of a tunnel according to claim 1, characterized in that: The tunnel secondary lining steel bar protective layer thickness detection device is powered by a cable connected power source, and the scanner is a geological radar scanner.

9. A tunnel secondary lining steel bar protective layer thickness detection device according to claim 1, characterized in that: The detection terminal (301) stores and records the steel bar protection layer thickness data, automatically numbers the steel bars and identifies the steel bar grid. The detection terminal (301) is connected to the worker's mobile phone via Bluetooth and uploads the construction data.

10. A method for using a tunnel secondary lining steel bar protective layer thickness detection device, comprising a tunnel secondary lining steel bar protective layer thickness detection device according to any one of claims 1 to 9, characterized in that: The following steps are involved: S1: manufacturing a support (1); manufacturing the support (1) in a steel bar processing workshop according to the curvature of the tunnel; S2: Check the cloth hanging trolley; perform corresponding inspections on the cloth hanging trolley according to relevant regulations; S3: Install the bracket: hoist the bracket (1) to the middle position of the cloth hanging trolley (3) and connect the corresponding jack (303) to ensure that the installation is firm; S4: Assembling the detection array; according to the installation serial number on the housing (2), the components are installed at the designated positions of the bracket (1), and the components are installed in groups. During installation, they are connected by overlapping joints (207). After a group is installed, the fixing parts are inserted into the fixing grooves (206), and step S4 is repeated until the assembly of the detection array is completed. S5: Debugging the detection array; the detection array is electrically connected to the control terminal, and the staff uses the control terminal to calibrate the detection array. At the same time, the staff checks the amount of pigment in the pigment tank (203) and the degree of wear of the wear-resistant layer (205), and replaces them in time; S6: Start working; after checking that everything is correct, start the cloth hanging trolley (3) to drive the device into the tunnel to start testing.