Method and device for determining tunnel maintenance time, terminal and storage medium
By constructing a tunnel constitutive model and Bayesian statistical method that includes mass loss of steel bar corrosion, the problem of lack of systematic evaluation in traditional tunnel maintenance is solved, and more accurate maintenance time prediction and tunnel safety guarantee are achieved.
Patent Information
- Application Number
- CN202410987550.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-11-15
AI Technical Summary
Traditional tunnel maintenance strategies rely on empirical judgment and regular intuitive inspections, lack of systematic assessment, resulting in waste of maintenance resources and untimely detection of key issues, affecting the safety and service life of the tunnel.
By obtaining the constitutive model of the tunnel, a failure probability equation containing the mass loss of steel bar corrosion was constructed, and the deviation factor was updated using Bayesian statistical method to accurately determine the tunnel maintenance time.
It realizes more accurate tunnel maintenance time prediction, ensures timely maintenance and extends the service life of the tunnel.
Smart Images

Figure CN118965971A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel maintenance assessment, and in particular to a method, device, terminal and storage medium for determining tunnel maintenance time. Background Art
[0002] As an important part of transportation infrastructure, tunnel engineering plays a vital role in the economic and social development of modern society. With the continuous advancement of tunnel construction technology and the increasing expansion of its application areas, the stability and safety of tunnel structures have gradually become the focus of attention in the engineering community. Traditional tunnel maintenance strategies often rely on empirical judgment and regular visual inspections, lacking systematic evaluation and scientific decision-making support, which may lead to a waste of maintenance resources or failure to discover key problems in a timely manner, thus affecting the safe operation and service life of the tunnel.
[0003] As the main structural part that bears the surrounding rock pressure and groundwater pressure, the stability of the tunnel lining is directly related to the safety of the entire tunnel. The main failure modes that tunnel linings may face include structural bearing failure, deformation failure, and cracking failure caused by corrosion. The occurrence of these failure modes is often related to multiple factors, such as material performance degradation, environmental erosion, and differences in construction quality, which complicates the stability assessment of tunnel structures and the selection of maintenance strategies.
[0004] In existing technologies, the assessment of tunnel lining stability mostly adopts qualitative or semi-quantitative methods, which makes it difficult to accurately predict the failure probability and maintenance timing of the tunnel. Summary of the invention
[0005] The embodiments of the present invention provide a method, device, terminal and storage medium for determining tunnel maintenance time, so as to solve the problem of determining the time required for tunnel maintenance.
[0006] In a first aspect, an embodiment of the present invention provides a method for determining a tunnel maintenance time, comprising:
[0007] Obtaining a constitutive model of the tunnel; wherein the constitutive model includes steel bar corrosion mass loss;
[0008] constructing a failure probability equation according to the constitutive model;
[0009] The service time of the tunnel is obtained, the deviation factor of the steel bar corrosion mass loss is assigned a normal distribution prior probability distribution, and the tunnel maintenance time is determined according to the failure probability equation;
[0010] Real-time data of the tunnel is obtained, and according to the prior probability distribution, the deviation factor is updated using the Bayesian statistical method to obtain the posterior distribution of the deviation factor, the failure probability equation is updated according to the posterior distribution, and the tunnel maintenance time is recalculated according to the updated failure probability equation.
[0011] In a second aspect, an embodiment of the present invention provides a device for determining tunnel maintenance time, including:
[0012] A constitutive model acquisition module, used to acquire a constitutive model of a tunnel; wherein the constitutive model includes steel bar corrosion mass loss;
[0013] A failure probability equation building module, used to build a failure probability equation according to the constitutive model;
[0014] A maintenance time determination module is used to obtain the service time of the tunnel, assign a deviation factor of the steel bar corrosion mass loss to a normal distribution prior probability distribution, and determine the tunnel maintenance time according to the failure probability equation;
[0015] The maintenance time update module is used to obtain real-time data of the tunnel, update the deviation factor according to the prior probability distribution using the Bayesian statistical method, obtain the posterior distribution of the deviation factor, update the failure probability equation according to the posterior distribution, and recalculate the tunnel maintenance time according to the updated failure probability equation.
[0016] In a third aspect, an embodiment of the present invention provides a terminal, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the computer program, the steps of the method described in the first aspect or any possible implementation method of the first aspect are implemented.
[0017] In a fourth aspect, an embodiment of the present invention provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the method described in the first aspect or any possible implementation method of the first aspect are implemented.
[0018] The embodiment of the present invention provides a method, device, terminal and storage medium for determining the maintenance time of a tunnel. A failure probability equation is constructed according to a constitutive model, wherein the constitutive model includes steel bar corrosion mass loss, and a deviation factor of the steel bar corrosion mass loss is assigned a normal distribution prior probability distribution. The deviation factor is updated according to the prior probability distribution using a Bayesian method to obtain a posterior distribution of the deviation factor. The posterior distribution of the deviation factor and the service time of the tunnel are input into the failure probability equation, and the failure probability equation outputs the failure probability. The tunnel maintenance time is determined according to the failure probability.
[0019] The deviation factor of the steel bar corrosion quality loss is updated through the Bayesian method to obtain the posterior distribution of the deviation factor. The failure probability equation is updated according to the calculation result of the posterior distribution, and then the tunnel maintenance time is re-determined to make the tunnel maintenance time more accurate. Therefore, the tunnel can be maintained in time according to the tunnel maintenance time, thereby extending the service life of the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0021] Figure 1 is a flow chart of a method for determining tunnel maintenance time provided by an embodiment of the present invention;
[0022] Figure 2 It is a structural schematic diagram of a device for determining tunnel maintenance time provided by an embodiment of the present invention;
[0023] Figure 3 It is a schematic diagram of a terminal for determining tunnel maintenance time provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0024] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present invention. However, it should be clear to those skilled in the art that the present invention may be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present invention.
[0025] In order to make the purpose, technical solutions and advantages of the present invention more clear, specific embodiments will be described below in conjunction with the accompanying drawings.
[0026] Figure 1 A flow chart of a method for determining tunnel maintenance time provided by an embodiment of the present invention. Figure 1 As shown, the details are as follows:
[0027] Step 101: Obtain a constitutive model of the tunnel; wherein the constitutive model includes steel bar corrosion mass loss.
[0028] The tunnel constitutive model is a mathematical model that describes the stress-strain relationship of the tunnel surrounding rock when subjected to external forces. In the design, construction and stability assessment of tunnel engineering, choosing a suitable constitutive model is crucial to ensure the safety and economy of the project.
[0029] According to the basic parameters of the tunnel, a constitutive model of the tunnel is constructed. The constitutive model in this application includes the structural bending bearing failure limit equilibrium equation, the structural deformation failure limit equilibrium equation and the corrosion-induced cracking failure limit equilibrium equation. The above three equilibrium equations are used to determine the failure domain of the failure probability equation.
[0030] The structural bending bearing failure limit equilibrium equation, the structural deformation failure limit equilibrium equation and the corrosion-induced cracking failure limit equilibrium equation all include the steel bar corrosion mass loss. The three equilibrium equations are used to represent the steel bar corrosion mass loss from different angles, so that the subsequent tunnel maintenance time can be more accurate.
[0031] Step 102: Construct a failure probability equation based on the constitutive model.
[0032] The failure domain is determined according to the constitutive model, and the failure probability equation is obtained by integrating the joint probability density function of the basic parameters of the tunnel in the failure domain of the constitutive model of the tunnel.
[0033] The failure domain of the constitutive model is:
[0034] X:G S (S,R,t)∪G D (S,R,t)∪G C (S,R,t)<0 (1)
[0035] In the formula, G S (S, R, t) is the structural bending bearing failure limit equilibrium equation, G D (S,R,t) is the structural deformation failure limit equilibrium equation, G C (S, R, t) is the limit equilibrium equation for crack failure caused by structural corrosion. When at least one of the three equilibrium equations is less than zero, the tunnel no longer meets the requirements, that is, the tunnel fails and needs repair.
[0036] Step 103: Obtain the service time of the tunnel, assign a normal distribution prior probability distribution to the deviation factor of the steel bar corrosion mass loss, and determine the tunnel maintenance time according to the failure probability equation.
[0037] The tunnel itself has a specified service life, similar to the warranty period. The tunnel's service life is shorter than the specified service life.
[0038] The prior probability distribution of the bias factor is a normal distribution with a mean and a standard deviation.
[0039] In a possible implementation, determining the tunnel maintenance time according to the failure probability equation includes:
[0040] The service time is input into the failure probability equation; wherein the mean and standard deviation of the prior probability distribution are used as the initial values of the deviation factor, and the failure probability of the tunnel is output. When the failure probability is greater than or equal to a predetermined threshold, the current service time is determined as the tunnel maintenance time.
[0041] In a possible implementation, the predetermined threshold is a failure probability value set by relevant national standards, which is 0.35%. When the failure probability calculated by the failure probability equation is greater than or equal to 0.35%, the currently input service time is determined as the tunnel maintenance time.
[0042] Due to the uncertainty of measurement errors and model errors in practice, the maintenance time may be a time range rather than a fixed point.
[0043] Step 104: Acquire real-time data of the tunnel, update the deviation factor according to the prior probability distribution using the Bayesian statistical method, obtain the posterior distribution of the deviation factor, update the failure probability equation according to the posterior distribution, and recalculate the tunnel maintenance time according to the updated failure probability equation.
[0044] The prior probability distribution is a normal distribution. The mean and standard deviation of the normal distribution are used as the initial values of the deviation factor. The Bayesian statistical method is used to update the deviation factor based on the initial values to obtain the posterior distribution of the deviation factor. The calculation result of the posterior distribution includes the mean and standard deviation. The mean and standard deviation of the posterior distribution are input into the failure probability equation to update the failure probability equation. Then the service time of the tunnel is input into the updated failure probability equation to output the failure probability. The failure probability is compared with a predetermined threshold. When the failure probability is greater than or equal to the predetermined threshold, the currently input service time is the tunnel maintenance time.
[0045] The deviation factor of the steel bar corrosion mass loss is updated by using the Bayesian statistical method. Since the standard deviation in the posterior distribution represents the error and the standard deviation is a positive difference, a positive number is subtracted from the standard deviation each time the posterior distribution is updated. Therefore, the difference, that is, the standard deviation, will become smaller and smaller, that is, the deviation factor will become smaller and smaller, that is, the error of the calculated steel bar corrosion mass loss will become smaller and smaller, making the calculated steel bar corrosion mass loss more accurate, and the tunnel maintenance time calculated by the corresponding failure probability equation model will become more and more accurate. Therefore, the tunnel can be maintained in time according to the tunnel maintenance time, thereby extending the service life of the tunnel.
[0046] The embodiment of the present invention provides a method, device, terminal and storage medium for determining the maintenance time of a tunnel. A failure probability equation is constructed according to a constitutive model, wherein the constitutive model includes steel bar corrosion mass loss, and a deviation factor of the steel bar corrosion mass loss is assigned a normal distribution prior probability distribution. The deviation factor is updated according to the prior probability distribution using a Bayesian method to obtain a posterior distribution of the deviation factor. The posterior distribution of the deviation factor and the service time of the tunnel are input into the failure probability equation, and the failure probability equation outputs the failure probability. The tunnel maintenance time is determined according to the failure probability.
[0047] The deviation factor of the steel bar corrosion quality loss is updated through the Bayesian method to obtain the posterior distribution of the deviation factor. The failure probability equation is updated according to the calculation result of the posterior distribution, and then the tunnel maintenance time is re-determined to make the tunnel maintenance time more accurate. Therefore, the tunnel can be maintained in time according to the tunnel maintenance time, thereby extending the service life of the tunnel.
[0048] The preferred implementation of each step of this embodiment is described in detail below.
[0049] In one possible implementation, the calculation result of the posterior distribution of the bias factor includes the mean and standard deviation:
[0050] The formula for the average is:
[0051]
[0052] The formula for standard deviation is:
[0053]
[0054] In the formula, ε m =d cor / d cor-p , ε m is the model bias, d cor is the model corrosion value, d cor-p is the actual measured corrosion value, μ ε,0 is the average of the prior probabilities of the bias factors, σ ε,0 is the standard deviation of the prior probability of the bias factor; σ m =σ δ / d cor-p , σ m is the measurement bias, σ δ is the variance of the error between the measured value and the actual value.
[0055] The deviation factor of steel corrosion quality loss is updated by Bayesian method to obtain the posterior distribution of the deviation factor. The failure probability equation is updated according to the standard deviation and mean value of the calculation results of the posterior distribution, and then the tunnel maintenance time is re-determined. Since the standard deviation in the posterior distribution represents the error, and the standard deviation is a positive difference, each time the posterior distribution is updated, a positive number is subtracted from the standard deviation. Therefore, the difference, that is, the standard deviation, will become smaller and smaller, that is, the deviation factor will become smaller and smaller, that is, the error of the calculated steel corrosion quality loss will become smaller and smaller, making the calculated steel corrosion quality loss more accurate, and the corresponding failure probability equation model will calculate the tunnel maintenance time more and more accurately. Therefore, the tunnel can be maintained in time according to the tunnel maintenance time, thereby extending the service life of the tunnel.
[0056] In another possible way, the model bias is calculated as:
[0057] ε m = d cor -d cor-p | (4)
[0058] Where, d cor is the model corrosion value, d cor-p is the actual measured corrosion value;
[0059] The measurement deviation is calculated as:
[0060] σ m = σ δ -d cor-p | (5)
[0061] In the formula, σ δ is the variance of the error between the measured value and the actual value, d cor-p is the actual measured corrosion value.
[0062] In other possible ways, the update of the deviation factor may be performed in other ways. This application mainly uses the Bayesian method to update the deviation factor as an example for explanation.
[0063] In one possible implementation, constructing a failure probability equation based on a constitutive model includes:
[0064] Get the basic parameters of the tunnel;
[0065] Integrate the joint probability density function of the basic parameters; where the integration domain is the failure domain of the constitutive model, the formula is:
[0066]
[0067] Where D f is the failure domain; G S(S, R, t) is the structural bending bearing failure limit equilibrium equation, G D (S,R,t) is the structural deformation failure limit equilibrium equation, G C (S, R, t) is the limit equilibrium equation for crack failure caused by structural corrosion, f z (Z) is the joint probability density function of the basic parameters of the tunnel.
[0068] The basic parameters of the tunnel include the parameters involved in the limit equilibrium equation of structural bending bearing failure, the limit equilibrium equation of structural deformation failure, and the limit equilibrium equation of structural cracking failure caused by corrosion.
[0069] In one possible implementation, the structural bending bearing failure limit equilibrium equation is calculated by the difference between the lining external load and the lining bending bearing capacity, and its formula is:
[0070] G S (S,R,t)=M(X i )-M u (X i ,t) (7)
[0071]
[0072] Where, X i is a random variable; M(X i ) is the external load of the lining, M u (X i ,t) is the bending bearing capacity of the lining, f cd is the concrete compressive strength; b is the lining section width; x is the height of the compression zone; h0 is the effective height of the lining section; η c (t) is the cross-sectional corrosion rate of the steel bars in the compression zone at time t; A ′ s is the total cross-sectional area of the steel bars in the compression zone; τ cu is the ultimate compressive strain of concrete; a ′ s E is the distance from the edge of the concrete in the compression zone to the outer edge of the steel bar; s ′ is the elastic modulus of the steel bar in the compression zone; β r It is the dimension-one parameter that determines the rectangular equivalent compressive stress diagram and is taken as 0.8095;
[0073] The structural deformation failure limit equilibrium equation is calculated by the difference between the limit lining double-sided horizontal displacement and the lining deformation resistance capacity, and its formula is:
[0074] G D (S, R, t) = Δ limit -Δ(X i ,t) (9)
[0075]
[0076] In the formula, Δ limit is the limit lining double-sided horizontal displacement, Δ is the lining double-sided horizontal displacement, Δ(X i ,t) is the lining deformation resistance, δ h is the unilateral horizontal displacement of the lining; e1 is the horizontal force gradient of the arch top under the consideration of water and soil; e2 is the horizontal force gradient of the arch bottom under the consideration of water and soil; g is the gravitational acceleration; η z is the stiffness reduction factor; EI(t) is the time-varying lining bending stiffness; k is the ground reaction coefficient; R is the tunnel radius, q is the horizontal force gradient of the arch crown and arch bottom under soil and water consideration, EI g is the initial section bending stiffness; η(t) is the steel bar corrosion rate at time t;
[0077] The limit equilibrium equation for cracking failure caused by structural corrosion is calculated by the difference between the limit crack width and the time-varying crack width, and its formula is:
[0078] G C (S,R,t)=w limit -w f (X i ,t) (12)
[0079] w f =0.16415+0.03541η(t) (13)
[0080]
[0081] In the formula, w limit is the limiting crack width, w f (X i ,t) is the time-varying crack width, w f is the crack width, W t is the corrosion mass loss at time t, η(t) is the steel bar corrosion rate at time t, R is the original radius of the steel bar, c is the thickness of the concrete cover, K c is the carbonation coefficient of concrete, D0 is the oxygen diffusion coefficient, ε is the deviation factor, f cuk is the standard value of concrete compressive strength; K1 is the regional influence coefficient, K2 is the indoor and outdoor influence coefficient, and K3 is the curing time influence coefficient;
[0082]
[0083] Where W0 is the mass before corrosion.
[0084] The flexural bearing capacity of the lining will deteriorate over time.
[0085] The external load of the lining mainly comes from the surrounding rock and groundwater pressure, which can be regarded as a constant load and is independent of time. It can be calculated by the finite element method of the continuous medium model or the structural mechanics method of the load structure model.
[0086] The recommended acceptable crack width for concrete is 0.1 to 0.5 mm. For compression-bending members, the maximum crack width for concrete is 0.3 mm.
[0087] The regional influence coefficient is 1.0 in the northern region and 0.5-0.8 in the southern and coastal areas.
[0088] The indoor and outdoor influence coefficients are 1.0 for outdoor and 1.87 for indoor; the curing time influence coefficient is 1.50 for general construction conditions.
[0089] In one possible implementation, the timeliness and effectiveness of tunnel maintenance are evaluated using system resilience, which is negatively correlated with the integral of the failure probability, as shown in the following formula:
[0090]
[0091] In the formula, Re i is the system resilience index, t d is the specified service life of the tunnel, t m1 is the time when the failure probability reaches the value requiring repair, P f,d is the specified probability of failure requiring repair, s i (t) is the evolution of the failure probability after maintenance using the i-th engineering solution.
[0092] The benefits of maintenance measures are evaluated based on comprehensive indicators, and the calculation formula is as follows:
[0093]
[0094] In the formula, Ω i is the i-th engineering benefit index, C i is the cost of the ith engineering solution.
[0095] It should be understood that the order of execution of the steps in the above embodiment does not necessarily mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiment of the present invention.
[0096] The following is an embodiment of the device of the present invention. For details not described in detail therein, reference may be made to the corresponding method embodiment described above.
[0097] Figure 2A schematic diagram of the structure of a device for determining tunnel maintenance time provided by an embodiment of the present invention is shown. For ease of description, only the part related to the embodiment of the present invention is shown, which is described in detail as follows:
[0098] like Figure 2 As shown, the device 2 for determining the tunnel maintenance time includes:
[0099] A constitutive model acquisition module 21 is used to obtain a constitutive model of the tunnel; wherein the constitutive model includes steel bar corrosion mass loss;
[0100] A failure probability equation building module 22 is used to build a failure probability equation according to the constitutive model;
[0101] The maintenance time determination module 23 is used to obtain the service time of the tunnel, assign the deviation factor of the steel bar corrosion mass loss to a normal distribution prior probability distribution, and determine the tunnel maintenance time according to the failure probability equation;
[0102] The maintenance time update module 24 is used to obtain real-time data of the tunnel, update the deviation factor according to the prior probability distribution using the Bayesian statistical method, obtain the posterior distribution of the deviation factor, update the failure probability equation according to the posterior distribution, and recalculate the tunnel maintenance time according to the updated failure probability equation.
[0103] In a possible implementation, the maintenance time determination module 23 is used to:
[0104] According to the failure probability equation, the tunnel maintenance time is determined by:
[0105] The service time is input into the failure probability equation; wherein the mean and standard deviation of the prior probability distribution are used as the initial values of the deviation factor, and the failure probability of the tunnel is output. When the failure probability is greater than or equal to a predetermined threshold, the current service time is determined as the tunnel maintenance time.
[0106] The embodiment of the present invention provides a method, device, terminal and storage medium for determining the maintenance time of a tunnel. A failure probability equation is constructed according to a constitutive model, wherein the constitutive model includes steel bar corrosion mass loss, and a deviation factor of the steel bar corrosion mass loss is assigned a normal distribution prior probability distribution. The deviation factor is updated according to the prior probability distribution using a Bayesian method to obtain a posterior distribution of the deviation factor. The posterior distribution of the deviation factor and the service time of the tunnel are input into the failure probability equation, and the failure probability equation outputs the failure probability. The tunnel maintenance time is determined according to the failure probability.
[0107] The deviation factor of the steel bar corrosion quality loss is updated through the Bayesian method to obtain the posterior distribution of the deviation factor. The failure probability equation is updated according to the calculation result of the posterior distribution, and then the tunnel maintenance time is re-determined to make the tunnel maintenance time more accurate. Therefore, the tunnel can be maintained in time according to the tunnel maintenance time, thereby extending the service life of the tunnel.
[0108] Figure 3 is a schematic diagram of a terminal provided by an embodiment of the present invention. Figure 3 As shown, the terminal 3 of this embodiment includes: a processor 30, a memory 31, and a computer program 32 stored in the memory 31 and executable on the processor 30. When the processor 30 executes the computer program 32, the steps in the above-mentioned various embodiments of the method for determining tunnel maintenance time are implemented, for example Figure 1 Alternatively, when the processor 30 executes the computer program 32, the functions of the modules in the above-mentioned device embodiments are realized, for example Figure 2 The functions of each module are shown.
[0109] Exemplarily, the computer program 32 may be divided into one or more modules, which are stored in the memory 31 and executed by the processor 30 to implement the present invention. The one or more modules may be a series of computer program instruction segments capable of implementing specific functions, which are used to describe the execution process of the computer program 32 in the terminal 3. For example, the computer program 32 may be divided into Figure 2 The modules shown.
[0110] The terminal 3 may be a computing device such as a desktop computer, a notebook, a PDA, or a cloud server. The terminal 3 may include, but is not limited to, a processor 30 and a memory 31. Those skilled in the art will appreciate that Figure 3 It is only an example of terminal 3 and does not constitute a limitation on terminal 3. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, the terminal may also include input and output devices, network access devices, buses, etc.
[0111] The processor 30 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.
[0112] The memory 31 may be an internal storage unit of the terminal 3, such as a hard disk or memory of the terminal 3. The memory 31 may also be an external storage device of the terminal 3, such as a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the terminal 3. Further, the memory 31 may also include both an internal storage unit of the terminal 3 and an external storage device. The memory 31 is used to store the computer program and other programs and data required by the terminal. The memory 31 may also be used to temporarily store data that has been output or is to be output.
[0113] The technicians in the relevant field can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example for illustration. In practical applications, the above-mentioned function allocation can be completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiment can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units and modules are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units and modules in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.
[0114] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0115] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.
[0116] In the embodiments provided by the present invention, it should be understood that the disclosed devices / terminals and methods can be implemented in other ways. For example, the device / terminal embodiments described above are only schematic. For example, the division of the modules or units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0117] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0118] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0119] If the integrated module is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present invention implements all or part of the processes in the above-mentioned embodiment method, and can also be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium. When the computer program is executed by the processor, the steps of the above-mentioned method embodiments for determining the tunnel maintenance time can be implemented. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may include: any entity or device capable of carrying the computer program code, recording medium, U disk, mobile hard disk, magnetic disk, optical disk, computer memory, read-only memory (ROM), random access memory (RAM), electric carrier signal, telecommunication signal and software distribution medium. It should be noted that the content contained in the computer-readable medium can be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, computer-readable media do not include electric carrier signals and telecommunication signals.
[0120] The embodiments described above are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention, and should all be included in the protection scope of the present invention.
Claims
1. A method for determining tunnel maintenance time, characterized in that: include: Obtaining a constitutive model of the tunnel; wherein the constitutive model includes steel bar corrosion mass loss; constructing a failure probability equation according to the constitutive model; The service time of the tunnel is obtained, the deviation factor of the steel bar corrosion mass loss is assigned a normal distribution prior probability distribution, and the tunnel maintenance time is determined according to the failure probability equation; Real-time data of the tunnel is obtained, and according to the prior probability distribution, the deviation factor is updated using the Bayesian statistical method to obtain the posterior distribution of the deviation factor, the failure probability equation is updated according to the posterior distribution, and the tunnel maintenance time is recalculated according to the updated failure probability equation.
2. The method for determining tunnel maintenance time according to claim 1, characterized in that: The calculation results of the posterior distribution of the bias factor include mean and standard deviation: The formula for the average value is: The formula for the standard deviation is: In the formula, ε m =d cor / d cor-p , ε m is the model bias, d cor is the model corrosion value, d cor-p is the actual measured corrosion value, μ ε,0 is the average of the prior probabilities of the bias factors, σ ε,0 is the standard deviation of the prior probability of the bias factor; σ m =σ δ / d cor-p , σ m is the measurement bias, σ δ is the variance of the error between the measured value and the actual value.
3. The method for determining tunnel maintenance time according to claim 1, characterized in that: The constructing of the failure probability equation according to the constitutive model comprises: Get the basic parameters of the tunnel; Integrate the joint probability density function of the basic parameters; where the integration domain is the failure domain of the constitutive model, and the formula is: Where D f is the failure domain; G S (S, R, t) is the limit equilibrium equation for the failure of the structural bending bearing, GD(S, R, t) is the limit equilibrium equation for the failure of the structural deformation, G C (S, R, t) is the limit equilibrium equation for cracking failure caused by structural corrosion, f z (Z) is the joint probability density function of the basic parameters of the tunnel.
4. The method for determining tunnel maintenance time according to claim 3, characterized in that: The structural bending bearing failure limit equilibrium equation is calculated by the difference between the lining external load and the lining bending bearing capacity, and its formula is: G S (S,R,t)=M(X i )-M u (X i ,t) Where, X i is a random variable; M(X i ) is the external load of the lining, M u (X i , t) is the bending bearing capacity of the lining, f cd is the concrete compressive strength; b is the lining section width; x is the height of the compression zone; h0 is the effective height of the lining section; η c (t) is the cross-sectional corrosion rate of the steel bars in the compression zone at time t; A′ s is the total cross-sectional area of the steel bars in the compression zone; τ cu is the ultimate compressive strain of concrete; a′ s is the distance from the edge of the concrete in the compression zone to the outer edge of the steel bar; E′ s is the elastic modulus of the steel bar in the compression zone; β r It is the dimension-one parameter that determines the rectangular equivalent compressive stress diagram and is taken as 0.8095; The structural deformation failure limit equilibrium equation is calculated by the difference between the limit lining bilateral horizontal displacement and the lining deformation resistance, and its formula is: G D (S,R,t)=Δ limit -Δ(X i ,t) In the formula, Δ limit is the limit lining double-sided horizontal displacement, Δ is the lining double-sided horizontal displacement, Δ(X i , t) is the deformation resistance of the lining, δ h is the unilateral horizontal displacement of the lining; e1 is the horizontal force gradient of the arch top under the consideration of water and soil; e2 is the horizontal force gradient of the arch bottom under the consideration of water and soil; g is the acceleration of gravity; η z is the stiffness reduction factor; EI(t) is the time-varying lining bending stiffness; k is the ground reaction coefficient; R is the tunnel radius, q is the horizontal force gradient of the arch crown and arch bottom under soil and water consideration, EI g is the initial section bending stiffness; η(t) is the steel corrosion rate at time t; The limit equilibrium equation for cracking failure caused by structural corrosion is calculated by the difference between the limit crack width and the time-varying crack width, and its formula is: G C (S,R,t)=w limit -w f (X i ,t) w f =0.16415+0.03541η(t) In the formula, w limit is the limiting crack width, w f (X i , t) is the time-varying crack width, w f is the crack width, W t is the corrosion mass loss at time t, η(t) is the steel bar corrosion rate at time t, R is the original radius of the steel bar, c is the thickness of the concrete cover, K c is the carbonation coefficient of concrete, D0 is the oxygen diffusion coefficient, ε is the deviation factor, f cuk is the standard value of concrete compressive strength; K1 is the regional influence coefficient, K2 is the indoor and outdoor influence coefficient, and K3 is the curing time influence coefficient; Where W0 is the mass before corrosion.
5. The method for determining tunnel maintenance time according to claim 1, characterized in that: Determining the tunnel maintenance time according to the failure probability equation includes: The service time is input into the failure probability equation; wherein the mean value and standard deviation of the prior probability distribution are used as initial values of the deviation factor, and the failure probability of the tunnel is output. When the failure probability is greater than or equal to a predetermined threshold, the current service time is determined as the tunnel maintenance time.
6. The method for determining tunnel maintenance time according to claim 1, characterized in that: The timeliness and effectiveness of tunnel maintenance are evaluated by using system resilience, which is negatively correlated with the integral of the failure probability, as shown in the following formula: In the formula, Re i is the system resilience index, t d is the specified service life of the tunnel, t m1 is the time when the failure probability reaches the value requiring repair, P f,d is the specified probability of failure requiring repair, s i (t) is the evolution of the failure probability after maintenance using the i-th engineering solution.
7. The method for determining tunnel maintenance time according to claim 6, characterized in that: The benefits of maintenance measures are evaluated based on comprehensive indicators, and the calculation formula is as follows: In the formula, Ω i is the i-th engineering benefit index, C i is the cost of the ith engineering solution.
8. A device for determining tunnel maintenance time, characterized in that: include: A constitutive model acquisition module, used to acquire a constitutive model of a tunnel; wherein the constitutive model includes steel bar corrosion mass loss; A failure probability equation building module, used to build a failure probability equation according to the constitutive model; A maintenance time determination module is used to obtain the service time of the tunnel, assign a deviation factor of the steel bar corrosion mass loss to a normal distribution prior probability distribution, and determine the tunnel maintenance time according to the failure probability equation; The maintenance time update module is used to obtain real-time data of the tunnel, update the deviation factor according to the prior probability distribution using the Bayesian statistical method, obtain the posterior distribution of the deviation factor, update the failure probability equation according to the posterior distribution, and recalculate the tunnel maintenance time according to the updated failure probability equation.
9. A terminal comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 7 are implemented.
10. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 7 are implemented.