Carbon emission management method and system based on BIM

CN118967402AInactive Publication Date: 2024-11-15WUHAN MODOU CONSTR CONSULTING CO LTD
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202410966214.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-18
Publication Date
2024-11-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology has problems of calculation deviation and management inconvenience in building carbon emission management, especially engineering simplified algorithms, physical model modeling methods and artificial intelligence algorithms are difficult to accurately reflect the actual situation of buildings when predicting building energy consumption and carbon emissions. , there is a lack of effective BIM model to monitor and manage carbon emissions.

Method used

By building a BIM model, classifying nodes and adding category tags, comprehensive carbon emission factors are calculated, including carbon emissions during manufacturing, transportation, installation and operation, and combining real-time energy consumption data to achieve real-time carbon emissions to each node of the building. Monitor and display.

Benefits of technology

It improves the management accuracy and efficiency of carbon emissions, can intuitively reflect the carbon emissions of different construction cycles and energy consumption projects, scientifically and reasonably reduce equipment energy consumption, optimize construction technology, and reduce dust pollution.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118967402A_ABST
    Figure CN118967402A_ABST
Patent Text Reader

Abstract

The invention discloses a BIM-based carbon emission management method and system, and belongs to the technical field of carbon emission management, and the method comprises the steps: building a BIM model of a building, classifying all nodes according to a construction period and an energy consumption type, and adding corresponding class labels; the construction period represents the manufacturing, transportation, installation and operation time of the node, and the energy consumption type represents the energy consumption demand type of the node for water, electricity and / or gas during operation; calculating a comprehensive carbon emission factor of each node; and adding the comprehensive carbon emission factor and the category label of each node to the BIM model so as to display the real-time carbon emission of all nodes of the same construction period and / or the same energy consumption project when a user clicks the category label. According to the application, the carbon emission of each node corresponding to different energy consumption projects in different construction periods can be intuitively reflected through the BIM model, and the carbon emission management precision and efficiency are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of carbon emission management, and specifically to a carbon emission management method and system based on BIM. Background Art

[0002] Issues such as building energy consumption and building carbon emissions have always been hot issues of concern to all countries. The establishment of a building energy consumption and building carbon emissions evaluation system aims to reduce the ecological environmental burden, improve the quality of the building environment, and provide a broader space for future development.

[0003] At present, the most commonly used building energy consumption prediction methods are: engineering simplification algorithm, physical model modeling method, artificial intelligence algorithm, etc. The engineering simplification calculation method is prone to large calculation deviations when comprehensively considering the type and thermal inertia of the building; the physical model modeling method often has cumbersome steps such as the need to establish a complex model separately and manually set a large number of calculation parameters; the artificial intelligence algorithm is separated from the building itself, and is based on existing data for learning and prediction. When predicting different building room types and actual conditions, there are certain limitations, which may cause a large deviation between the prediction results and the actual situation.

[0004] With the rapid development of science and technology today, intelligent buildings are the trend of the future. BIM, as an intelligent building technology, is an information model technology based on a huge database. It can use computers to perform simulation and analysis in the planning, design, construction, operation and maintenance stages of the project. Digital twin technology links buildings and their spaces with their design goals and objectives, and regards digital twins as digital replicas of buildings. BIM and digital twin technology complement each other, and their combination in the life cycle of a building is inevitable. At present, there is still a lack of solutions to effectively monitor and manage carbon emissions based on BIM models. Summary of the invention

[0005] The present application provides a BIM-based carbon emission management method and system, which can solve the technical problem of low carbon emission management level in the prior art.

[0006] In a first aspect, an embodiment of the present application provides a carbon emission management method based on BIM, and the carbon emission management method based on BIM includes:

[0007] Constructing a BIM model of a building, the BIM model including all nodes of the building, classifying all nodes according to construction period and energy consumption type, and adding corresponding category labels; the construction period represents the manufacturing, transportation, installation, and operation time of the node, and the energy consumption type represents the energy consumption demand type of the node for water, electricity, and / or gas during operation;

[0008] Calculate the comprehensive carbon emission factor of each node, the comprehensive carbon emission factor including the first carbon emission amount of the node during manufacturing, transportation, and installation and the second carbon emission amount based on energy consumption during manufacturing, transportation, installation, and operation of the node;

[0009] Add comprehensive carbon emission factors and category labels for each node to the BIM model to display the real-time carbon emissions of all nodes in the same construction period and / or the same energy consumption project when the user clicks on the category label.

[0010] In conjunction with the first aspect, in one implementation, the calculating of the comprehensive carbon emission factor of each node specifically includes the following steps:

[0011] Obtaining a bill of quantities for a building, wherein the bill of quantities includes contents of each construction item;

[0012] Obtain the carbon emission factors of the building materials involved in each item in the bill of quantities to obtain a list of carbon emission factors of building materials;

[0013] Based on the bill of quantities and the carbon emission factor list of building materials, calculate the carbon emission factor conversion coefficient corresponding to each construction content;

[0014] According to the carbon emission factor list of building materials and the corresponding carbon emission factor conversion coefficients of various construction contents, the first carbon emission amount expressed by the material carbon emission factor is calculated;

[0015] The second carbon emission is calculated based on the energy consumption data obtained through real-time monitoring;

[0016] The comprehensive carbon emission factor is calculated according to the first carbon emission amount and the second carbon emission amount.

[0017] In combination with the first aspect, in one implementation, the step of calculating the carbon emission factor conversion coefficient corresponding to each construction content based on the bill of quantities and the list of carbon emission factors of building materials specifically includes the following steps:

[0018] Based on the bill of quantities and the list of carbon emission factors for building materials, the carbon emission factor conversion coefficients corresponding to the manufacturing of building materials, transportation of building materials, loss of building materials, construction machinery and personnel activities for each construction content are calculated respectively.

[0019] In combination with the first aspect, in one embodiment, the carbon emission factor conversion coefficient for the manufacture of the building materials is 1.

[0020] In combination with the first aspect, in one embodiment, the carbon emission factor conversion factor corresponding to the transportation of building materials is the ratio of the carbon emission factor of the transportation of building materials to the carbon emission factor of the manufacturing of building materials;

[0021] The carbon emission factor conversion coefficient corresponding to the wasted building materials is the ratio of the carbon emission factor of the wasted building materials to the carbon emission factor of the building materials manufacturing;

[0022] The carbon emission factor conversion coefficient corresponding to the construction machinery is the ratio of the carbon emission factor of the construction machinery to the carbon emission factor of the building materials manufacturing;

[0023] The carbon emission factor conversion coefficient corresponding to the personnel activities is the ratio of the carbon emission factor of personnel activities to the carbon emission factor of building materials manufacturing.

[0024] In a second aspect, an embodiment of the present application provides a BIM-based carbon emission management system, and the BIM-based carbon emission management system includes:

[0025] A preliminary construction module, which is used to construct a BIM model of a building, wherein the BIM model includes all nodes of the building, and all nodes are classified according to the construction period and energy consumption type, and corresponding category labels are added; the construction period represents the manufacturing, transportation, installation, and operation time of the node, and the energy consumption type represents the energy consumption demand type of the node for water, electricity, and / or gas during operation;

[0026] A data calculation module, which is used to calculate the comprehensive carbon emission factor of each node, wherein the comprehensive carbon emission factor includes a first carbon emission amount of the node during manufacturing, transportation, and installation and a second carbon emission amount based on energy consumption during manufacturing, transportation, installation, and operation of the node;

[0027] The model update module is used to add the total carbon emission factor and category label of each node to the BIM model, so as to display the real-time carbon emissions of all nodes in the same construction period and / or the same energy consumption project when the user clicks the category label.

[0028] In conjunction with the second aspect, in one implementation, when calculating the comprehensive carbon emission factor of each node, the data calculation module obtains a bill of quantities of the building, wherein the bill of quantities includes the contents of each construction project;

[0029] Obtain the carbon emission factors of the building materials involved in each item in the bill of quantities to obtain a list of carbon emission factors of building materials;

[0030] Based on the bill of quantities and the carbon emission factor list of building materials, calculate the carbon emission factor conversion coefficient corresponding to each construction content;

[0031] According to the carbon emission factor list of building materials and the corresponding carbon emission factor conversion coefficients of various construction contents, the first carbon emission amount expressed by the material carbon emission factor is calculated;

[0032] The second carbon emission is calculated based on the energy consumption data obtained through real-time monitoring;

[0033] The comprehensive carbon emission factor is calculated according to the first carbon emission amount and the second carbon emission amount.

[0034] In combination with the second aspect, in one embodiment, when the data calculation module calculates the corresponding carbon emission factor conversion coefficients of each construction content based on the bill of quantities and the list of carbon emission factors of building materials, it calculates the carbon emission factor conversion coefficients corresponding to the manufacturing of building materials, transportation of building materials, loss of building materials, construction machinery and personnel activities of each construction content based on the bill of quantities and the list of carbon emission factors of building materials.

[0035] In combination with the second aspect, in one embodiment, the carbon emission factor conversion coefficient for the manufacture of the building materials is 1.

[0036] In conjunction with the second aspect, in one embodiment, the carbon emission factor conversion factor corresponding to the transportation of building materials is the ratio of the carbon emission factor of the transportation of building materials to the carbon emission factor of the manufacturing of building materials;

[0037] The carbon emission factor conversion coefficient corresponding to the wasted building materials is the ratio of the carbon emission factor of the wasted building materials to the carbon emission factor of the building materials manufacturing;

[0038] The carbon emission factor conversion coefficient corresponding to the construction machinery is the ratio of the carbon emission factor of the construction machinery to the carbon emission factor of the building materials manufacturing;

[0039] The carbon emission factor conversion coefficient corresponding to the personnel activities is the ratio of the carbon emission factor of personnel activities to the carbon emission factor of building materials manufacturing.

[0040] The beneficial effects brought by the technical solution provided by the embodiments of the present application include:

[0041] The BIM model can intuitively reflect the carbon emissions of each node corresponding to different energy consumption projects in different construction cycles, thereby improving the accuracy and efficiency of carbon emissions management. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] Figure 1 This is a flow chart of an embodiment of a carbon emission management method based on BIM of the present application;

[0043] Figure 2 This is a schematic diagram of the architecture of an embodiment of a BIM-based carbon emission management system of the present application. DETAILED DESCRIPTION

[0044] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0045] In order to make the objectives, technical solutions and advantages of the present application clearer, the implementation methods of the present application will be further described in detail below in conjunction with the accompanying drawings.

[0046] In a first aspect, an embodiment of the present application provides a carbon emission management method based on BIM.

[0047] In one embodiment, referring to Figure 1 , Figure 1 This is a flow chart of the first embodiment of the carbon emission management method based on BIM in this application. Figure 1 As shown in the figure, BIM-based carbon emission management methods include:

[0048] Step S1: construct a BIM model of the building. The BIM model includes all nodes of the building. All nodes are classified according to the construction period and energy consumption type, and corresponding category labels are added. The construction period represents the manufacturing, transportation, installation, and operation time of the node, and the energy consumption type represents the energy consumption type of the node for water, electricity, and / or gas during operation.

[0049] Step S2: Calculate the comprehensive carbon emission factor of each node, where the comprehensive carbon emission factor includes the first carbon emission of the node during manufacturing, transportation, and installation and the second carbon emission based on energy consumption during manufacturing, transportation, installation, and operation.

[0050] Step S3: Add the comprehensive carbon emission factor and category label of each node to the BIM model, so that when the user clicks the category label, the real-time carbon emissions of all nodes in the same construction period and / or the same energy consumption project are displayed.

[0051] In this embodiment, the first carbon emissions and the second carbon emissions of each node in the BIM model in each construction period are calculated to obtain the total carbon emissions of the node during the construction period, wherein the first carbon emissions are the carbon emissions caused by the manufacturing, transportation and installation of the structural parts corresponding to the node, and the second carbon emissions are the carbon emissions generated by the energy consumption such as water, electricity and gas consumption during the manufacturing, transportation, installation and operation of the structural parts corresponding to the node.

[0052] By labeling each node category in the BIM model, when the user clicks the label corresponding to the construction period, the comprehensive carbon emissions of other nodes in the same construction period as the current node can be displayed. When the user clicks the label corresponding to the energy consumption type, the comprehensive carbon emissions of other nodes with the same energy consumption type as the current node are displayed. For example, if the energy consumption type of this node is water consumption, then when the energy consumption type-related label of this node is clicked, the comprehensive carbon emissions of other nodes with the same energy consumption type of water consumption are displayed. When the user clicks a label associated with both the construction period and the energy consumption type, the comprehensive carbon emissions of all other nodes in the same construction period as the current node and with the same energy consumption type are displayed. Based on the above operations, by clicking on the label of any component in the BIM model, you can view the carbon emission data of all other nodes in the model related to the label of this node, thereby realizing all-round and full-cycle monitoring of the building.

[0053] Furthermore, in one embodiment, the above-mentioned calculation of the comprehensive carbon emission factor of each node specifically includes the following steps:

[0054] Obtain a bill of quantities for the building, which includes the contents of each construction item.

[0055] Obtain the carbon emission factors of the construction materials involved in each item in the bill of quantities to obtain a list of carbon emission factors of construction materials.

[0056] Based on the bill of quantities and the list of carbon emission factors for building materials, calculate the carbon emission factor conversion coefficient corresponding to each construction content.

[0057] According to the carbon emission factor list of building materials and the corresponding carbon emission factor conversion coefficients of various construction contents, the first carbon emission amount expressed by the material carbon emission factor is calculated.

[0058] The second carbon emission amount is calculated based on the energy consumption data obtained through real-time monitoring.

[0059] The above-mentioned comprehensive carbon emission factor is calculated based on the first carbon emission amount and the second carbon emission amount.

[0060] In this embodiment, a standard has been formed in the construction process of the engineering field, that is, which components need to be cast on site, which components can be prefabricated in the factory, which equipment needs to be hoisted, and which equipment needs to be installed manually, and these components and equipment are classified. Factory prefabrication requires the factory to give a certain carbon emission value generated by a certain unit. For on-site casting, hoisting or manual installation, the carbon emission factor method is used for calculation, and then the carbon emission monitoring equipment is installed on site to monitor each type of construction process. After the results are obtained, they are weighted averaged with the results of the carbon emission factor method. The corresponding carbon emissions are calculated during the manufacturing, transportation and installation of each structural component of the building to obtain the first carbon emissions.

[0061] After the building is completed, the water, electricity and gas data generated during the operation and maintenance process will be connected to the platform in real time for monitoring and conversion to obtain the second carbon emissions.

[0062] Based on BIM data and Internet of Things technology, water, electricity and gas equipment in the operation and maintenance phase are monitored in real time to obtain the operation and maintenance energy consumption in each period. The data is then bound to the BIM model components so that the basic information and operation and maintenance data of the component can be viewed by clicking on the component. The real-time carbon emissions are then calculated using the above-mentioned carbon emission calculation method.

[0063] The present invention forms a more accurate methodology for carbon emission calculation methods, which can improve data accuracy. It can also force energy conservation and emission reduction in the operation and maintenance process of the building itself based on the carbon emission results, scientifically and rationally reduce equipment energy consumption, optimize construction technology, and some construction processes with extremely large carbon emission data can be commissioned to factories for prefabrication, thereby reducing the proportion of on-site operations and reducing dust pollution.

[0064] Further, in one embodiment, the above-mentioned calculation of the corresponding carbon emission factor conversion coefficient of each construction content based on the bill of quantities and the list of carbon emission factors of building materials specifically includes the following steps:

[0065] Based on the bill of quantities and the list of carbon emission factors for building materials, the carbon emission factor conversion coefficients corresponding to the manufacturing of building materials, transportation of building materials, loss of building materials, construction machinery and personnel activities for each construction content are calculated respectively.

[0066] Furthermore, in one embodiment, the carbon emission factor conversion coefficient for the manufacture of the above-mentioned building materials is 1.

[0067] Furthermore, in one embodiment, the carbon emission factor conversion coefficient corresponding to the above-mentioned construction material transportation is the ratio of the carbon emission factor of construction material transportation to the carbon emission factor of construction material manufacturing.

[0068] The carbon emission factor conversion coefficient corresponding to the above-mentioned wasted building materials is the ratio of the carbon emission factor of the wasted building materials to the carbon emission factor of the building materials manufacturing.

[0069] The carbon emission factor conversion coefficient corresponding to the above-mentioned construction machinery is the ratio of the carbon emission factor of the construction machinery to the carbon emission factor of building materials manufacturing.

[0070] The carbon emission factor conversion coefficient corresponding to the above-mentioned personnel activities is the ratio of the carbon emission factor of personnel activities to the carbon emission factor of building materials manufacturing.

[0071] On the second aspect, the embodiment of the present application also provides a BIM-based carbon emission management system.

[0072] In one embodiment, referring to Figure 2 , Figure 2 This is a functional module diagram of an embodiment of a carbon emission management system based on BIM in this application. Figure 2 As shown in the figure, the BIM-based carbon emission management system includes:

[0073] The preliminary construction module 1 is used to construct a BIM model of a building. The BIM model includes all nodes of the building. All nodes are classified according to the construction period and energy consumption type, and corresponding category labels are added. The construction period represents the manufacturing, transportation, installation, and operation time of the node, and the energy consumption type represents the energy consumption demand type of the node for water, electricity, and / or gas during operation.

[0074] Data calculation module 2 is used to calculate the comprehensive carbon emission factor of each node, which includes the first carbon emission amount of the node during manufacturing, transportation, and installation and the second carbon emission amount based on energy consumption during manufacturing, transportation, installation, and operation.

[0075] The model updating module 3 is used to add the total carbon emission factor and category label of each node to the BIM model, so as to display the real-time carbon emissions of all nodes in the same construction period and / or the same energy consumption project when the user clicks the category label.

[0076] Furthermore, in one embodiment, when calculating the comprehensive carbon emission factor of each node, the data calculation module 2 obtains the bill of quantities of the building, and the bill of quantities includes the contents of each construction project.

[0077] Obtain the carbon emission factors of the construction materials involved in each item in the bill of quantities to obtain a list of carbon emission factors of construction materials.

[0078] Based on the bill of quantities and the list of carbon emission factors for building materials, calculate the carbon emission factor conversion coefficient corresponding to each construction content.

[0079] According to the carbon emission factor list of building materials and the corresponding carbon emission factor conversion coefficients of various construction contents, the first carbon emission amount expressed by the material carbon emission factor is calculated.

[0080] The second carbon emission amount is calculated based on the energy consumption data obtained through real-time monitoring.

[0081] The above-mentioned comprehensive carbon emission factor is calculated based on the first carbon emission amount and the second carbon emission amount.

[0082] Furthermore, in one embodiment, when the data calculation module 2 calculates the corresponding carbon emission factor conversion coefficients of each construction content based on the bill of quantities and the list of carbon emission factors of building materials, it calculates the carbon emission factor conversion coefficients corresponding to the manufacturing of building materials, transportation of building materials, loss of building materials, construction machinery and personnel activities of each construction content based on the bill of quantities and the list of carbon emission factors of building materials.

[0083] Furthermore, in one embodiment, the carbon emission factor conversion coefficient for the manufacture of the above-mentioned building materials is 1.

[0084] Furthermore, in one embodiment, the carbon emission factor conversion coefficient corresponding to the above-mentioned construction material transportation is the ratio of the carbon emission factor of construction material transportation to the carbon emission factor of construction material manufacturing.

[0085] The carbon emission factor conversion coefficient corresponding to the above-mentioned wasted building materials is the ratio of the carbon emission factor of the wasted building materials to the carbon emission factor of the building materials manufacturing.

[0086] The carbon emission factor conversion coefficient corresponding to the above-mentioned construction machinery is the ratio of the carbon emission factor of the construction machinery to the carbon emission factor of building materials manufacturing.

[0087] The carbon emission factor conversion coefficient corresponding to the above-mentioned personnel activities is the ratio of the carbon emission factor of personnel activities to the carbon emission factor of building materials manufacturing.

[0088] Among them, the functional implementation of each module in the above-mentioned BIM-based carbon emission management system corresponds to the various steps in the above-mentioned BIM-based carbon emission management method embodiment, and its functions and implementation processes will not be repeated here one by one.

[0089] It should be noted that the serial numbers of the above-mentioned embodiments of the present application are only for description and do not represent the advantages or disadvantages of the embodiments.

[0090] The terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned drawings are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but optionally includes steps or units that are not listed, or optionally includes other steps or units inherent to these processes, methods, products or devices. The terms "first", "second" and "third" are used to distinguish different objects, etc., and do not represent a sequence, nor do they limit "first", "second" and "third" to different types.

[0091] In the description of the embodiments of the present application, "exemplary", "for example" or "for example" are used to indicate examples, illustrations or descriptions. Any embodiment or design described as "exemplary", "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "exemplary", "for example" or "for example" is intended to present related concepts in a specific way.

[0092] In the description of the embodiments of the present application, unless otherwise specified, “ / ” means or, for example, A / B can mean A or B; the “and / or” in the text is merely a description of the association relationship of associated objects, indicating that three relationships may exist, for example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone. In addition, in the description of the embodiments of the present application, “multiple” refers to two or more than two.

[0093] In some processes described in the embodiments of the present application, multiple operations or steps that appear in a specific order are included, but it should be understood that these operations or steps may not be executed in the order in which they appear in the embodiments of the present application or in parallel, and the sequence number of the operation is only used to distinguish the different operations, and the sequence number itself does not represent any execution order. In addition, these processes may include more or fewer operations, and these operations or steps may be executed in sequence or in parallel, and these operations or steps may be combined.

[0094] Through the description of the above implementation methods, those skilled in the art can clearly understand that the above-mentioned embodiment methods can be implemented by means of software plus a necessary general hardware platform, and of course by hardware, but in many cases the former is a better implementation method. Based on such an understanding, the technical solution of the present application is essentially or the part that contributes to the prior art can be embodied in the form of a software product, which is stored in a storage medium (such as ROM / RAM, disk, CD) as described above, and includes a number of instructions for a terminal device to execute the methods described in each embodiment of the present application.

[0095] The above are only preferred embodiments of the present application, and are not intended to limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made using the contents of the present application specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present application.

Claims

1. A BIM-based carbon emission management method, It is characterized in that The BIM-based carbon emission management method includes: Constructing a BIM model of a building, the BIM model including all nodes of the building, classifying all nodes according to construction period and energy consumption type, and adding corresponding category labels; the construction period represents the manufacturing, transportation, installation, and operation time of the node, and the energy consumption type represents the energy consumption demand type of the node for water, electricity, and / or gas during operation; Calculate the comprehensive carbon emission factor of each node, the comprehensive carbon emission factor including the first carbon emission amount of the node during manufacturing, transportation, and installation and the second carbon emission amount based on energy consumption during manufacturing, transportation, installation, and operation of the node; Add comprehensive carbon emission factors and category labels for each node to the BIM model to display the real-time carbon emissions of all nodes in the same construction period and / or the same energy consumption project when the user clicks on the category label.

2. The BIM-based carbon emission management method according to claim 1, It is characterized in that The calculation of the comprehensive carbon emission factor of each node specifically includes the following steps: Obtaining a bill of quantities for a building, wherein the bill of quantities includes contents of each construction item; Obtain the carbon emission factors of the building materials involved in each item in the bill of quantities to obtain a list of carbon emission factors of building materials; Based on the bill of quantities and the list of carbon emission factors of building materials, calculate the carbon emission factor conversion coefficient corresponding to each construction content; According to the carbon emission factor list of building materials and the corresponding carbon emission factor conversion coefficients of various construction contents, the first carbon emission amount expressed by the material carbon emission factor is calculated; The second carbon emission is calculated based on the energy consumption data obtained through real-time monitoring; The comprehensive carbon emission factor is calculated according to the first carbon emission amount and the second carbon emission amount.

3. The BIM-based carbon emission management method according to claim 2, It is characterized in that The calculation of the carbon emission factor conversion coefficient corresponding to each construction content based on the bill of quantities and the list of carbon emission factors of building materials specifically includes the following steps: Based on the bill of quantities and the list of carbon emission factors for building materials, the carbon emission factor conversion coefficients corresponding to the manufacturing of building materials, transportation of building materials, loss of building materials, construction machinery and personnel activities for each construction content are calculated respectively.

4. The BIM-based carbon emission management method according to claim 3, It is characterized in that The carbon emission factor conversion coefficient for the manufacture of the building materials is 1.

5. The BIM-based carbon emission management method according to claim 3, It is characterized in that The carbon emission factor conversion factor corresponding to the transportation of building materials is the ratio of the carbon emission factor of the transportation of building materials to the carbon emission factor of the manufacturing of building materials; The carbon emission factor conversion coefficient corresponding to the wasted building materials is the ratio of the carbon emission factor of the wasted building materials to the carbon emission factor of the building materials manufacturing; The carbon emission factor conversion coefficient corresponding to the construction machinery is the ratio of the carbon emission factor of the construction machinery to the carbon emission factor of the building materials manufacturing; The carbon emission factor conversion coefficient corresponding to the personnel activities is the ratio of the carbon emission factor of personnel activities to the carbon emission factor of building materials manufacturing.

6. A BIM-based carbon emission management system, It is characterized in that The BIM-based carbon emission management system includes: A preliminary construction module, which is used to construct a BIM model of a building, wherein the BIM model includes all nodes of the building, and all nodes are classified according to the construction period and energy consumption type, and corresponding category labels are added; the construction period represents the manufacturing, transportation, installation, and operation time of the node, and the energy consumption type represents the energy consumption demand type of the node for water, electricity, and / or gas during operation; A data calculation module, which is used to calculate the comprehensive carbon emission factor of each node, wherein the comprehensive carbon emission factor includes a first carbon emission amount of the node during manufacturing, transportation, and installation and a second carbon emission amount based on energy consumption during manufacturing, transportation, installation, and operation of the node; The model update module is used to add the total carbon emission factor and category label of each node to the BIM model, so as to display the real-time carbon emissions of all nodes in the same construction period and / or the same energy consumption project when the user clicks the category label.

7. The BIM-based carbon emission management system according to claim 6, It is characterized in that When calculating the comprehensive carbon emission factor of each node, the data calculation module obtains the bill of quantities of the building, and the bill of quantities includes the contents of each construction project; Obtain the carbon emission factors of the building materials involved in each item in the bill of quantities to obtain a list of carbon emission factors of building materials; Based on the bill of quantities and the list of carbon emission factors of building materials, calculate the carbon emission factor conversion coefficient corresponding to each construction content; According to the carbon emission factor list of building materials and the corresponding carbon emission factor conversion coefficients of various construction contents, the first carbon emission amount expressed by the material carbon emission factor is calculated; The second carbon emission is calculated based on the energy consumption data obtained through real-time monitoring; The comprehensive carbon emission factor is calculated according to the first carbon emission amount and the second carbon emission amount.

8. The BIM-based carbon emission management system according to claim 7, It is characterized in that When the data calculation module calculates the corresponding carbon emission factor conversion coefficients of each construction content based on the bill of quantities and the list of carbon emission factors of building materials, it calculates the carbon emission factor conversion coefficients corresponding to the manufacturing of building materials, transportation of building materials, loss of building materials, construction machinery and personnel activities of each construction content based on the bill of quantities and the list of carbon emission factors of building materials.

9. The BIM-based carbon emission management system according to claim 8, It is characterized in that The carbon emission factor conversion coefficient for the manufacture of the building materials is 1.

10. The BIM-based carbon emission management system according to claim 8, It is characterized in that The carbon emission factor conversion factor corresponding to the transportation of building materials is the ratio of the carbon emission factor of the transportation of building materials to the carbon emission factor of the manufacturing of building materials; The carbon emission factor conversion coefficient corresponding to the wasted building materials is the ratio of the carbon emission factor of the wasted building materials to the carbon emission factor of the building materials manufacturing; The carbon emission factor conversion coefficient corresponding to the construction machinery is the ratio of the carbon emission factor of the construction machinery to the carbon emission factor of the building materials manufacturing; The carbon emission factor conversion coefficient corresponding to the personnel activities is the ratio of the carbon emission factor of personnel activities to the carbon emission factor of building materials manufacturing.

Citation Information

Cited By

  • Building carbon emission monitoring system based on BIM

    CN120706704A

  • BIM-based building carbon emission monitoring system

    CN120706704B

  • Method for automatically calculating carbon emissions from mrt projects

    TWI939284B