Collapsible loess double-row pipeline groove earthwork self-balancing excavation method
Through the self-balancing excavation method of soil in the double-row pipeline trench of wet loess, we excavated in layers in sections and top-down, and reserved the earth and transported directly to the backfill area, which solved the additional bottom and bottom in the excavation of wet soil in the excavation of wet soil The complex problems of sinking and computing improve engineering efficiency and safety and ensure project quality.
Patent Information
- Application Number
- CN202411061968.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-11-19
AI Technical Summary
The existing method of digging loess pipeline trench excavation can easily lead to additional sinking in the digging soil, increasing the safety and stability threat of the project, and has complex calculations, low efficiency and long construction period.
The self-balancing excavation method of earthwork in the double-row pipeline trench of wet loess is adopted. The excavation is divided into sections and top-down layers, and the foundation is reserved to process the earthwork and transport it directly to the backfill area to reduce repeated overloading of the earthwork, and strictly control the design. slope ratio and compaction degree.
It avoids additional sinking, simplifies the earth balance calculation, improves project accuracy and efficiency, shortens construction period, reduces project costs, and ensures project quality and safety.
Smart Images

Figure CN118979505A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of pipeline trench excavation construction, and more specifically, to a self-balancing earthwork excavation method for double-row pipeline trenches in collapsible loess. Background Art
[0002] Collapsible loess is a special type of soil, which is characterized by the destruction of soil structure and significant additional sinking under certain pressure. This phenomenon is called collapsibility. In the fields of civil engineering, geological engineering and pipeline construction, the treatment of collapsible loess is an important topic. Among them, the excavation of pipeline trenches is a key task, and its excavation method directly affects the progress and quality of the project. Solutions of existing technologies: The existing methods for excavating pipeline trenches in collapsible loess mainly use mechanical equipment and manual excavation. The excavated earth is piled on both sides of the trench. After the trench foundation treatment and pipeline installation are completed, the stored backfill soil is transported to the trench for backfilling and rolling. A large amount of digging, transportation, stacking and filling work greatly increases manpower and material resources. The existing technology directly digs to the bottom of the trench, exposing the designed elevation of the bottom of the trench. Repeated rolling by construction machinery can easily cause significant additional sinking of the collapsible loess, affecting the bearing capacity of the foundation. Problems of existing technologies: There are some problems with the existing methods for excavating pipeline trenches in collapsible loess. First, due to the special properties of collapsible loess, additional subsidence may occur during the excavation process, which poses a certain threat to the safety and stability of the project. Secondly, the existing excavation methods often require multiple earthwork balance calculations, which not only increases the complexity of the work, but may also lead to calculation errors and affect the accuracy of the project. Finally, the existing excavation methods may have problems such as long construction period and low efficiency when dealing with large pipeline trenches. Summary of the invention
[0003] The purpose of the present invention is to provide a self-balancing excavation method for double-row pipeline trenches in collapsible loess, which can be used for excavation in collapsible loess areas to prevent additional sinking, while simplifying the complexity of earthwork balance calculations, reducing repeated earthwork transportation, improving the accuracy of the project, improving the efficiency of large-scale pipeline trench excavation, and shortening the construction period.
[0004] In order to achieve these purposes and other advantages of the present invention, a self-balancing excavation method for double-row pipeline trenches in collapsible loess is provided, comprising the following steps:
[0005] The construction site is divided into sections; each section is constructed according to the S1, S2, S3, S4 process. The construction of the next section S1, S2, S3, S4 starts after the construction of the previous section S1, S2, S3, S4 is completed, forming a flow operation. For the first three sections, except for the earth reserved for S2, all the earth is transported to the slag yard. For any other section, except for the earth reserved for S2, the earth excavated from the S1 process is directly transported to the S4 process of the first three sections for backfilling and compaction, and the remaining earth is abandoned and transported to the slag yard;
[0006] The specific steps for construction of each section according to the S1, S2, S3, and S4 procedures are as follows:
[0007] S1. Excavate in layers from top to bottom and reserve soil for foundation treatment. No excavation or transportation is done inside the trench.
[0008] S2, loosen, mix and roll the reserved soil in S1 to make the compaction degree meet the design requirements;
[0009] S3. Hoist the pipe to the groove for installation, welding, and quality inspection. If qualified, proceed to the next process;
[0010] S4. Backfill and roll the earth to make the compaction degree meet the design requirements.
[0011] Preferably, in the self-balancing excavation method for collapsible loess double-row pipeline trench earthwork, in S1, each excavated layer is sloped according to the designed slope ratio.
[0012] Preferably, in the self-balancing excavation method for double-row pipeline trenches in collapsible loess, the excavation thickness of each layer does not exceed 3m.
[0013] Preferably, in the self-balancing excavation method for collapsible loess double-row pipeline trench, in S1, when the excavator is used to dig to 0.2-0.3m from the designed elevation of the trench bottom, manual excavation is used to clear the trench bottom elevation.
[0014] Preferably, in the self-balancing excavation method for collapsible loess double-row pipeline trench, the last three sections, through earthwork balance calculation, reduce the amount of abandoned soil transported to the slag yard for the last three sections and the previous sections, or do not abandon the soil, and store the soil on both sides of the trench for use when the last three sections S4 are constructed.
[0015] The present invention has at least the following beneficial effects:
[0016] 1. Optimize the excavation method: The present invention adopts a segmented, top-down layered method for excavation. Through earthwork balance calculation, the excavation depth and earthwork volume of each layer are accurately controlled, thereby avoiding the occurrence of over-excavation and improving the safety and stability of the project. 2. Improve work efficiency: The present invention uses a reasonable excavation sequence and earthwork scheduling to enable the excavation of each layer to be carried out efficiently, greatly reducing the construction period and improving work efficiency. 3. Save resources: The present invention reserves foundation treatment earthwork, and the excavated soil is directly transported to the backfill area, which effectively saves resources and reduces project costs. 4. Ensure project quality: During the excavation process, the present invention strictly controls the designed slope ratio, and at the same time, strictly stores the topsoil and backfill soil according to the designed position and strictly controls the storage height to ensure the safety of the slope and the quality of the project. 5. Strong flexibility and adaptability: The excavation method of the present invention can be adjusted according to actual conditions, has strong flexibility and adaptability, and can be applied under different geological conditions.
[0017] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 is a schematic diagram of a cross-section layering of earth excavation according to an embodiment of the present invention;
[0019] Figure 2 It is a schematic diagram of segmented and layered excavation according to an embodiment of the present invention. DETAILED DESCRIPTION
[0020] The present invention is further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.
[0021] It should be noted that, in the description of the present invention, the terms "lateral", "longitudinal", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc. indicating orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0022] like Figure 1 and Figure 2 As shown, the present invention provides a self-balancing excavation method for double-row pipeline trenches in collapsible loess, comprising the following steps:
[0023] Through scientific earthwork balance calculation, the construction site is divided into sections according to the length of the trench to be dug. In actual construction, the trench is long and often needs to be divided into dozens, hundreds, thousands, or even more sections. The earthwork balance relationship between S1 earthwork excavation, S2 foundation treatment, and S4 backfilling is accurately controlled, and equipment and resources are reasonably invested to ensure that the excavation and backfilling time are consistent; each section is constructed according to the S1, S2, S3, and S4 processes. The construction of the next section S1, S2, S3, and S4 will start after the construction of the previous section S1, S2, S3, and S4 is completed, forming a flow operation. For the first three sections, except for the earthwork reserved for S2, all of it is transported to the slag yard. For any other section, except for the earthwork reserved for S2, the earthwork excavated from the S1 process is directly transported to the S4 process of the first three sections for backfilling and compaction, and the remaining earthwork is abandoned and transported to the slag yard;
[0024] The specific steps for construction of each section according to the S1, S2, S3, and S4 procedures are as follows:
[0025] S1. Excavate in layers from top to bottom, and after earthwork balance calculation, reserve earthwork for foundation treatment. No excavation is done inside the trench and it is transported outside; S1 earthwork excavation.
[0026] S2. Use machinery to loosen, mix and roll the reserved earthwork of S1 to make the compaction degree meet the design requirements; S2 foundation construction.
[0027] S3. Lift the pipeline into the groove for installation, welding and quality inspection. Only after passing the quality inspection can the next process be entered; S3 pipeline installation.
[0028] S4. Backfill and roll the earth to make the compaction degree reach the design requirements; S4 backfill.
[0029] The excavation process is as follows: first section earth excavation → first section foundation construction, second section earth excavation → first section pipeline installation, second section foundation construction, third section earth excavation → first section earth backfill, second section pipeline installation, third section foundation construction, fourth section earth excavation → first section construction completion, second section earth backfill, third section pipeline installation, fourth section foundation construction, fifth section earth excavation → second section construction completion, third section earth backfill, fourth section pipeline installation, fifth section foundation construction, sixth section earth excavation, and then continue continuously to form a flow operation.
[0030] From the above, it can be seen that no backfilling was carried out during the excavation of the first, second and third sections, so except for the earth reserved for S2, all the earth was transported to the slag yard.
[0031] like Figure 2As shown in a, when the fourth section is excavating, the first section starts backfilling. After earthwork balance calculation, the earth excavated from the fourth section S1 process is directly transported to the first section S4 process for backfilling and compaction.
[0032] like Figure 2 As shown in b, when the fifth section is excavating, the second section starts backfilling. After earthwork balance calculation, the earth excavated from the fifth section S1 process is directly transported to the second section S4 process for backfilling and compaction.
[0033] like Figure 2 As shown in c, when the sixth section is excavating, the third section starts backfilling. After earthwork balance calculation, the earth excavated from the sixth section S1 process is directly transported to the third section S4 process for backfilling and compaction.
[0034] And so on.
[0035] In another scheme, in the self-balancing earth excavation method for double-row pipeline trenches in collapsible loess, in S1, each excavated layer is sloped according to the designed slope ratio.
[0036] In another embodiment, in the self-balancing excavation method for double-row pipeline trenches in collapsible loess, the excavation thickness of each layer does not exceed 3m.
[0037] In another scheme, in the self-balancing excavation method for collapsible loess double-row pipeline trench, in S1, when the excavator is used to dig to 0.2-0.3m from the designed elevation of the trench bottom, manual excavation is used to clear the trench to the designed elevation.
[0038] In another scheme, in the self-balancing excavation method for collapsible loess double-row pipeline trench, the last three sections, through earthwork balance calculation, reduce the amount of abandoned soil transported to the slag yard in the last three sections and the previous sections, or do not abandon the soil, and store the soil on both sides of the trench until the last three sections S4 are constructed. That is, for the last three sections and the previous sections, in addition to directly transporting the soil excavated in the S1 process to the S4 process of the first three sections for backfilling and rolling, each section reduces the amount of abandoned soil transported to the slag yard or does not abandon the soil, and stores it on both sides of the trench until the last three sections S4 are constructed.
[0039] Example 1
[0040] The construction of the North Trunk Water Pipeline of the Second Phase of the Han-Wei Diversion Project in Shaanxi Province is of the V standard. The steel pipe diameter is DN3400, which is a large-diameter pressure steel pipe, and it is laid in double rows, so the trench excavation is relatively large. This project 1. The self-balancing excavation method of the double-row pipeline trench in collapsible loess is adopted. Through scientific earthwork balance calculation, the earthwork excavation volume is accurately controlled to avoid over-excavation and disturbance of the original foundation, ensuring the safety and stability of the project. 2. The excavation is carried out in layers by using the method of zoning and top-down. The first layer is excavated to the elevation of the horse road. The heights of the second and third layers are 2.85m and 3m respectively; the fourth layer is 1.75m high. After earthwork balance calculation, the earthwork volume is equal to the volume required for the construction of the original soil tamping and cement soil cushion layer, so the fourth layer of earthwork is recycled in the pit. 3. The layer thickness is generally not more than 4m. According to the construction drawings and actual conditions, it can be excavated in three or four layers. The reserved bridleway is divided into four layers, and the non-bridleway is divided into three layers. The first layer is excavated to the bridleway elevation, using 1.6m 3 The backhoe digs the soil directly, calculates the amount of waste soil, and transports it to the waste dump or soil dump area with a 20t dump truck or loader. 4. The second and third layers are 2.85m and 3m high respectively, using 1.6m 3 The soil is excavated with a backhoe and transported to the soil storage area along the slag road in the pit with a 20t dump truck; the fourth layer is 1.75m high. After earthwork balance calculation, the earthwork volume is equal to the volume required for the original soil tamping and cement soil cushion construction, so the fourth layer of soil is recycled in the pit. 5. Excavate one layer at a time according to the designed slope ratio. When brushing the slope, use a slope ruler to strictly control the designed slope ratio. At the same time, the topsoil and backfill soil are stored strictly according to the designed position and the storage height is strictly controlled to ensure the safety of the slope. A 0.3m protective layer is reserved at the bottom of the trench. When the next process is carried out, a small backhoe is used to cooperate with manual cleaning. 6. In order to avoid over-excavation and disturbance of the original foundation, a 30cm trimming margin is reserved near the design line, and manual trimming is used with a backhoe to ensure that the slope ratio and flatness meet the design requirements. Slope cutting should be interspersed with the excavation process of each layer of earthwork to avoid the formation of a slope that is too high to operate and form a major safety hazard. 7. Leave 20 to 30 cm from the bottom of the designed trench (pit), and use machinery in conjunction with manual shoveling to dig. After excavation, measure the excavation side line, center line and elevation to ensure that the excavation elevation and flatness of the trench (pit) bottom meet the design requirements.
[0041] The following are the descriptions of the embodiments:
[0042] 1. If there is a bridleway, dig to the bridleway elevation first. If there is no bridleway, directly construct in layers according to the second or third principle.
[0043] 2. 1.6m 3 The maximum vertical excavation depth of a backhoe is generally 5.1m. If the maximum excavation depth is reached, the construction efficiency will be reduced. The optimal state is about 3m, and the excavation depth generally does not exceed 4m. Therefore, the excavation soil layers are divided according to the actual project conditions and the optimal efficiency of the excavator. Therefore, the second and third layers in the case are 2.85m and 3m.
[0044] 3. The fourth layer is the most critical. It is calculated based on the earthwork balance and the earthwork volume is reserved for recycling in the pit, which reduces the construction of excavation, transportation, storage, return and filling, shortens the construction period and reduces investment.
[0045] 4. The balance of the second and third layers of earthwork is also critical, because part of the soil will be backfilled and part will be used in the slag yard. Therefore, the filling volume should be calculated and the rest will be directly dumped in the slag yard to avoid secondary transportation.
[0046] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.
Claims
1. A self-balancing excavation method for double-row pipeline trenches in collapsible loess. It is characterized in that The following steps are involved: The construction site is divided into sections; each section is constructed according to the S1, S2, S3, S4 process. The construction of the next section S1, S2, S3, S4 starts after the construction of the previous section S1, S2, S3, S4 is completed, forming a flow operation. For the first three sections, except for the earth reserved for S2, all the earth is transported to the slag yard. For any other section, except for the earth reserved for S2, the earth excavated from the S1 process is directly transported to the S4 process of the first three sections for backfilling and compaction, and the remaining earth is abandoned and transported to the slag yard; The specific steps for construction of each section according to the S1, S2, S3, and S4 procedures are as follows: S1. Excavate in layers from top to bottom and reserve soil for foundation treatment. No excavation or transportation is done inside the trench. S2, loosen, mix and roll the reserved soil in S1 to make the compaction degree meet the design requirements; S3. Hoist the pipe to the groove for installation, welding, and quality inspection. If qualified, proceed to the next process; S4. Backfill and roll the earth to make the compaction degree meet the design requirements.
2. The self-balancing excavation method for double-row pipeline trenches in collapsible loess as claimed in claim 1, It is characterized in that In S1, each excavated layer is sloped according to the designed slope ratio.
3. The self-balancing excavation method for double-row pipeline trenches in collapsible loess as claimed in claim 1, It is characterized in that The thickness of each excavation layer shall not exceed 3m.
4. The self-balancing excavation method for double-row pipeline trenches in collapsible loess as claimed in claim 1, It is characterized in that In S1, when the excavator is used to dig to 0.2-0.3m from the designed elevation of the trench bottom, manual excavation is used to clear the trench to the designed elevation.
5. The self-balancing excavation method for double-row pipeline trenches in collapsible loess as claimed in claim 1, It is characterized in that For the last three sections, the amount of soil transported to the slag yard for the last three sections and the previous sections is reduced or not discarded through earthwork balance calculation, and the soil is piled on both sides of the trench to be used when the last three sections S4 are constructed.