Charging and discharging automatic waiting test equipment and use method thereof

By designing automatic charging and discharging test equipment in the new energy electric vehicle market, and automatically adjusting the charging and discharging channels using AGV trolleys and multiple sets of charging and discharging equipment, the problem of low power and manual efficiency in battery capacity testing is solved, and the same charging is achieved Spread together to save resources.

CN118980948APending Publication Date: 2024-11-19ANHUI RUILU TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411143712.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

In the new energy electric vehicle market, the battery pack capacity test consumes a lot of electricity and labor, and the plug-and-release time between the equipment and the battery pack cannot be accurately controlled, resulting in low charging and discharging efficiency and wasted resources.

Method used

Design an automatic waiting test device for charging and discharging, and use an AGV car to transport the battery pack between the waiting area, charging and discharging equipment and finished area, and automatically adjust the charging and discharging channels through multiple sets of charging and discharging equipment, according to the remaining time of the battery pack and the equipment The power situation is charged and discharged to reduce manual intervention.

Benefits of technology

It realizes automatic adjustment of the battery pack during charging and discharging, saves electricity and manual intervention time, and improves charging and discharging efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118980948A_ABST
    Figure CN118980948A_ABST
Patent Text Reader

Abstract

The invention discloses charging and discharging automatic waiting test equipment and a use method thereof, and the equipment comprises a waiting area which is internally provided with a series of battery packs; the charging and discharging equipment can charge and discharge the conveyed battery pack; the finished product area can accommodate the processed battery pack; an AGV trolley is arranged on the AGV running track, the AGV trolley can transport the battery packs among the waiting area, the charging and discharging equipment and the finished product area, the charging and discharging channels can be automatically adjusted according to the charging and discharging remaining time of each pack and the equipment load power condition during charging and discharging of the battery packs, simultaneous charging and discharging are achieved, the charging and discharging electric charge is saved, and the charging and discharging efficiency is improved. And the manual intervention time is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of power batteries, and in particular relates to a charging and discharging automatic waiting test device and a use method thereof. Background Art

[0002] In the process of implementing the present invention, the inventors found that the prior art has at least the following problems:

[0003] With the development of the new energy electric vehicle market, the demand for PACK market is gradually increasing.

[0004] In the new energy PACK industry, in order to control the consistency and pass rate of single cells, mainstream PACK manufacturers in the industry conduct 100% capacity testing when shipping. However, during the capacity test, a lot of electricity is consumed, and a lot of manpower is consumed to manually plug and unplug the battery pack and the equipment. In the existing technology, it is impossible to accurately control the plug-in and unplug time between the equipment and the battery pack, and it is impossible to achieve synchronous charging of channels.

[0005] The above problems seriously affect the efficiency of charging and discharging, and waste electricity and labor efficiency.

[0006] CN218331882U-External protection device for power battery pack charge and discharge test and power battery pack charge and discharge test system discloses an external protection device for power battery pack charge and discharge test, the device comprises: a relay array arranged between the battery management system BMS and the power supply; a main control unit, which is connected to the relay array and connected to the battery management system BMS by CAN communication. It also cannot solve the above technical problems. Summary of the invention

[0007] The technical problem to be solved by the present invention is to provide a charging and discharging automatic waiting test device and a method of using the same, so as to solve the problem that the battery pack can automatically adjust the charging and discharging channels according to the remaining charging and discharging time of each pack and the load power of the equipment during charging and discharging, so as to achieve simultaneous charging and discharging, save charging and discharging electricity costs, and save manual intervention time.

[0008] In order to solve the above technical problems, the technical solution adopted by the present invention is: a charging and discharging automatic waiting test device, having:

[0009] A waiting area, wherein a series of battery packs are arranged in the waiting area;

[0010] Charging and discharging equipment, capable of charging and discharging the delivered battery packs;

[0011] Finished product area, which can accommodate processed battery packs;

[0012] The AGV running track has an AGV trolley on it, and the AGV trolley can transport the battery packs between the waiting area, the charging and discharging equipment and the finished product area.

[0013] The charging and discharging equipment area is provided with a plurality of groups of charging and discharging equipment; the number of the charging and discharging equipment is an even number.

[0014] The method for using the above-mentioned automatic waiting test device for charging and discharging comprises the following steps:

[0015] 1) AGV system starts up;

[0016] 2) AGV system trolley transports battery packs;

[0017] 3) Charging and discharging equipment handles battery packs.

[0018] In the above step 1), the AGV system is turned on and the sensors on the AGV cart and each channel of the AGV system are activated.

[0019] The above step 2) includes the following steps:

[0020] a) Self-check whether the battery packs on all AGVs are online;

[0021] b) Check whether the AGV online battery pack capacity and energy status specifications are consistent;

[0022] c) The AGV starts to operate in the running mode and transports the battery pack to the charging and discharging area;

[0023] d) The AGV runs to the charging and discharging area and feeds back signals to the switchboard control system;

[0024] e) The battery pack enters the state of waiting for charging and discharging.

[0025] In step a) of step 2) above, check whether the battery packs on the AGV are online and the number is an even number; if the requirements are met, enter step b) of step 2), if the requirements are not met, the system alarms, uploads error information to the switchboard system, and prohibits system operation.

[0026] In step b) of step 2) above, check whether the capacity and energy of the AGV online battery pack are consistent. If they are consistent, proceed to step c) of step 2). If they are inconsistent, the system alarms, uploads error information to the switchboard system, and prohibits system operation.

[0027] The above step 3) includes the following steps:

[0028] a) The switchboard system sends a signal to activate the discharge system;

[0029] b) Self-check whether the total power of all charging and discharging channels is sufficient;

[0030] c) Self-check whether the number of charge and discharge channels is an even number;

[0031] d) The charging and discharging equipment starts to automatically connect to the battery pack and conduct preparatory charging;

[0032] e) The charging and discharging equipment detects the battery pack information and verifies the battery information and status;

[0033] f) The charging and discharging system enters the charging and discharging state.

[0034] In step b) of step 3) above, self-check whether the total power of the charging and discharging equipment is greater than or equal to the total power of the battery to be tested; in step c) of step 3), self-check whether the charging and discharging channels are even numbers to ensure that one channel is charging and the other channel is discharging.

[0035] In step e) of step 3) above, the charging and discharging equipment automatically docks with the battery pack and communicates with the battery pack, receives battery pack information, and verifies whether the battery pack information is consistent with the status of the information sent by the switchboard. After the information is verified, charging and discharging begin to ensure that one channel is charging and the other channel is discharging, and energy hedging is performed in the charging and discharging equipment.

[0036] One of the above technical solutions has the following advantages or beneficial effects: it solves the problem that the battery pack can automatically adjust the charging and discharging channels according to the remaining charging and discharging time of each pack and the load power of the equipment during charging and discharging, so as to achieve simultaneous charging and discharging, save charging and discharging electricity costs, and save manual intervention time. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 It is a structural schematic diagram of a charge and discharge automatic waiting test device provided in an embodiment of the present invention;

[0038] Figure 2 for Figure 1 Schematic diagram of the automatic waiting test equipment for charging and discharging;

[0039] Figure 3 for Figure 1 Schematic diagram of the automatic waiting test equipment for charging and discharging; DETAILED DESCRIPTION

[0040] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0041] See also Figures 1 to 3, a charging and discharging automatic waiting test equipment, comprising: a waiting area, in which a series of battery packs are arranged; charging and discharging equipment, which can charge and discharge the delivered battery packs; a finished product area, which can accommodate the processed battery packs; an AGV running track, on which an AGV car is arranged, and the AGV car can transport the battery packs between the waiting area, the charging and discharging equipment and the finished product area. The solution is to automatically adjust the charging and discharging channels according to the remaining charging and discharging time of each pack and the load power of the equipment during charging and discharging, so as to achieve the same charging and discharging, save charging and discharging electricity costs, and save manual intervention time.

[0042] There are multiple groups of charging and discharging equipment in the charging and discharging equipment area; the number of charging and discharging equipment is an even number. They can be charged and discharged at the same time, saving charging and discharging electricity costs and saving manual intervention time.

[0043] The method for using the above-mentioned automatic waiting test device for charging and discharging comprises the following steps:

[0044] 1) The AGV system is turned on; 2) The AGV system cart transports the battery pack; 3) The charging and discharging equipment processes the battery pack.

[0045] AVG system operation process description:

[0046] 1) The AGV system is turned on, and the sensors on the AGV car and each channel of the AGV system are activated to detect whether the battery packs on the AGV car are online and the number is even, and whether the capacity and energy of the online battery packs are consistent. When all conditions are met, the AGV car is ready for operation. If the conditions are not met, the AGV system is prohibited from operating and a specific alarm type is issued;

[0047] 2) After the AGV vehicle runs to the charging and discharging area, the AGV vehicle sends a signal to the switchboard control system to remind the switchboard control system that the battery pack has entered the charging state.

[0048] In the above step 1), the AGV system is turned on and the sensors on the AGV car and each channel of the AGV system are activated. After the AGV is activated, all sensors on the AGV system need to be activated, which is the first hardware condition for starting this system.

[0049] The above step 2) includes the following steps: a) self-check whether the battery packs on all AGVs are online; b) check whether the capacity and energy status specifications of the online battery packs of the AGVs are consistent; c) the AGV starts the operation mode and starts to transport the battery packs to the charging and discharging area; d) the AGV runs to the charging and discharging area and feeds back the signal to the switchboard control system; e) the battery pack enters the state to be charged and discharged.

[0050] The self-check identifies whether the battery pack on the AGV is online, whether the battery pack capacity and energy are consistent, and uploads the above information to the switchboard system. This is a necessary condition for the AGV to start. If the above conditions are not identified, it may cause the AGV to run to the charging and discharging equipment and find that there is no battery pack to charge or the test battery pack capacity and energy are inconsistent, and charging cannot be formed, affecting the energy imbalance of the entire system.

[0051] In step a) of step 2) above, check whether the battery packs on the AGV are online and the number is an even number; if the requirements are met, enter step b) of step 2), if the requirements are not met, the system alarms, uploads error information to the switchboard system, and prohibits system operation.

[0052] The number of detected battery packs is an even number. The purpose is to charge one pack while the other pack discharges, and put the energy of the discharged battery pack into the charged battery pack. The odd-numbered battery packs cannot form a pair charge, thus realizing energy circulation.

[0053] In step b) of step 2) above, check whether the capacity and energy of the AGV online battery pack are consistent. If they are consistent, proceed to step c) of step 2). If they are inconsistent, the system alarms, uploads error information to the switchboard system, and prohibits system operation.

[0054] The purpose of detecting whether the energy capacity of the battery packs is consistent is to charge one pack while discharging the other pack, and put the energy of the discharged battery pack into the charged battery pack. If the capacity and energy are inconsistent, 100% charging cannot be formed to achieve energy circulation.

[0055] Charging and discharging system operation description:

[0056] 1) After the charging and discharging equipment receives the activation information from the switchboard system (AGV system charging information), it starts to enter the self-test to check whether the total power of the charging and discharging equipment is greater than or equal to the total power of the battery to be tested; and whether the charging and discharging channels are even (one channel must be charged and the other channel must be discharged).

[0057] 2) The charging and discharging equipment automatically connects to the battery pack and communicates with the battery pack, receives the battery pack information, and verifies whether the battery pack information is consistent with the information status sent by the switchboard. After the information is verified, charging and discharging begin to ensure that one channel is charging and the other channel is discharging, and energy hedging is performed in the charging and discharging equipment.

[0058] The above step 3) includes the following steps: a) the PBX system sends a signal to activate the discharge system; b) self-check whether the total power of all charge and discharge channels is met; c) self-check whether the number of charge and discharge channels is an even number; d) the charge and discharge equipment starts to automatically connect to the battery pack and perform preparatory charging; e) the charge and discharge equipment detects the battery pack information and verifies the battery information and status; f) the charge and discharge system enters the charge and discharge state.

[0059] In step b) of step 3) above, self-check whether the total power of the charging and discharging equipment is greater than or equal to the total power of the battery to be tested; in step c) of step 3), self-check whether the charging and discharging channels are even numbers to ensure that one channel is charging and the other channel is discharging.

[0060] The self-test charge and discharge power must be greater than or equal to the total power of the battery pack to be tested and the channels must be an even number. This is a necessary condition to ensure that the battery pack can be charged and discharged normally. The even number of channels is to ensure synchronization with the number of battery packs to be tested.

[0061] In step e) of step 3) above, the charging and discharging equipment automatically docks with the battery pack and communicates with the battery pack, receives battery pack information, and verifies whether the battery pack information is consistent with the status of the information sent by the switchboard. After the information is verified, charging and discharging begin to ensure that one channel is charging and the other channel is discharging, and energy hedging is performed in the charging and discharging equipment.

[0062] The charging and discharging equipment communicates with the battery pack, receives the battery pack information, and checks whether the information is consistent with the switchboard. This step is the last confirmation whether all the information is consistent and is the final test.

[0063] After adopting the above solution, the battery pack can automatically adjust the charging and discharging channels according to the remaining charging and discharging time of each pack and the load power of the equipment during charging and discharging, so as to achieve simultaneous charging and discharging, save charging and discharging electricity costs, and save manual intervention time.

[0064] In the description of the present invention, it is necessary to understand that the terms "coaxial", "bottom", "one end", "top", "middle", "the other end", "upper", "one side", "top", "inside", "front", "center", "both ends" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0065] In the present invention, unless otherwise clearly stipulated and limited, the terms such as "installation", "setting", "connection", "fixation" and "screw-on" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. Unless otherwise clearly defined, ordinary technicians in this field can understand the specific meanings of the above terms in the present invention according to the specific circumstances.

[0066] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A charging and discharging automatic waiting test equipment, It is characterized in that have: A waiting area, wherein a series of battery packs are arranged in the waiting area; Charging and discharging equipment, capable of charging and discharging the delivered battery packs; Finished product area, which can accommodate processed battery packs; The AGV running track has an AGV cart on it, and the AGV cart can transport the battery packs between the waiting area, the charging and discharging equipment and the finished product area.

2. The automatic waiting test device for charging and discharging as claimed in claim 1, It is characterized in that The charging and discharging equipment area is provided with a plurality of groups of charging and discharging equipment; the number of the charging and discharging equipment is an even number.

3. A method for using the automatic charging and discharging waiting test device as claimed in claim 1 or 2, It is characterized in that The steps include: 1) AGV system starts up; 2) AGV system trolley transports battery packs; 3) Charging and discharging equipment handles battery packs.

4. The method for using the automatic waiting test device for charging and discharging as claimed in claim 3, It is characterized in that In the above step 1), the AGV system is turned on and the sensors on the AGV cart and each channel of the AGV system are activated.

5. The method for using the automatic waiting test device for charging and discharging as claimed in claim 4, It is characterized in that The above step 2) includes the following steps: a) Self-check whether the battery packs on all AGVs are online; b) Check whether the AGV online battery pack capacity and energy status specifications are consistent; c) The AGV starts to operate in the running mode and transports the battery pack to the charging and discharging area; d) The AGV runs to the charging and discharging area and feeds back signals to the switchboard control system; e) The battery pack enters the state of waiting for charging and discharging.

6. The method for using the automatic waiting test device for charging and discharging as claimed in claim 5, It is characterized in that In step a) of step 2) above, check whether the battery packs on the AGV are online and the number is an even number; if the requirements are met, enter step b) of step 2), if the requirements are not met, the system alarms, uploads error information to the switchboard system, and prohibits system operation.

7. The method for using the automatic waiting test device for charging and discharging as claimed in claim 6, It is characterized in that In step b) of step 2) above, check whether the capacity and energy of the AGV online battery pack are consistent. If they are consistent, proceed to step c) of step 2). If they are inconsistent, the system alarms, uploads error information to the switchboard system, and prohibits system operation.

8. The method for using the automatic waiting test device for charging and discharging as claimed in claim 7, It is characterized in that The above step 3) includes the following steps: a) The switchboard system sends a signal to activate the discharge system; b) Self-check whether the total power of all charging and discharging channels is sufficient; c) Self-check whether the number of charge and discharge channels is an even number; d) The charging and discharging equipment starts to automatically connect to the battery pack and conduct preparatory charging; e) The charging and discharging equipment detects the battery pack information and verifies the battery information and status; f) The charging and discharging system enters the charging and discharging state.

9. The method for using the automatic waiting test device for charging and discharging as claimed in claim 8, It is characterized in that In step b) of step 3) above, self-check whether the total power of the charging and discharging equipment is greater than or equal to the total power of the battery to be tested; in step c) of step 3), self-check whether the charging and discharging channels are even numbers to ensure that one channel is charging and the other channel is discharging.

10. The method for using the automatic waiting test device for charging and discharging as claimed in claim 3, It is characterized in that In step e) of step 3) above, the charging and discharging equipment automatically docks with the battery pack and communicates with the battery pack, receives battery pack information, and verifies whether the battery pack information is consistent with the status of the information sent by the switchboard. After the information is verified, charging and discharging begin to ensure that one channel is charging and the other channel is discharging, and energy hedging is performed in the charging and discharging equipment.