Through real-time monitoring and evaluation, the labor dispatch strategy has been adjusted, and the problem of unreasonable organization and task allocation of labor level groups in traditional landscaping labor dispatch management has been solved, which has improved the efficiency and quality of landscaping maintenance and management, and has improved the work enthusiasm of personnel.
Patent Information
- Application Number
- CN202411455176.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-18
- Publication Date
- 2024-11-19
AI Technical Summary
The traditional landscaping labor dispatch management method lacks reasonable labor level group organization and work task allocation, and cannot dynamically adjust staffing according to landscaping needs. It also lacks real-time monitoring and evaluation feedback mechanisms, resulting in insufficient work efficiency and personnel enthusiasm.
By collecting personnel information and landscaping project needs, forming multiple groups, assigning tasks according to needs, monitoring work progress and completion results in real time, conducting evaluation and feedback to adjust labor dispatch strategies, and formulating incentive and reward and punishment systems to improve work attitude and efficiency.
The reasonable allocation of labor dispatch personnel and tasks on demand have been achieved, the efficiency and quality of landscaping maintenance and management have been improved, and the work enthusiasm and attitude of personnel have been enhanced.
Smart Images

Figure CN118982209A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of personnel management, and in particular to a landscaping labor dispatch management method and system. Background Art
[0002] In the process of landscaping maintenance, labor dispatch is usually needed to ensure sufficient manpower to complete daily pruning, watering, fertilizing, pest control, and planting new varieties. In this way, garden management can flexibly respond to seasonal changes and special project needs, while effectively controlling labor costs. However, labor dispatch also brings some challenges. Traditional labor dispatch management does not reasonably set up labor grade groups based on the information of dispatched personnel, and does not assign work tasks to grade groups on demand according to landscaping needs, and does not evaluate and feedback after the work tasks are completed, and then mobilize the work enthusiasm and work attitude of dispatched personnel through incentive systems.
[0003] In view of the traditional labor dispatch management method, the present invention collects personnel information, forms multiple teams, obtains demand information of landscaping projects, and dispatches teams according to the demand information to immediately decide the direction of the next experimental operation.
[0004] Monitor the work progress and completion results of the labor dispatch team in real time, then evaluate them to get the evaluation results, and finally adjust the labor dispatch strategy based on the evaluation results.
[0005] To sum up, how to reasonably allocate labor dispatch personnel to carry out maintenance and management of landscaping is an issue that needs to be urgently solved and optimized in the landscaping labor dispatch management system. Summary of the invention
[0006] The present invention provides a method and system for managing gardening labor dispatch, which solves the technical problem of how to reasonably allocate labor dispatch personnel to perform maintenance and management on gardening in the related art.
[0007] In order to solve the above technical problems, the present invention provides a landscaping labor dispatch management method and system, and the specific technical scheme is as follows:
[0008] In a first aspect, a landscaping labor dispatch management method comprises the following steps:
[0009] Obtain landscaping project demand information and convert it into executable tasks, including: Repair branches X l ; Watering and fertilization G j ; Planting new varieties Z x ; Treat weeds C l ; Pest control c ;
[0010] Collect personnel information and form multiple teams based on the personnel information, including: pre-organizing n dispatched personnel and marking them as R1, R2, ..., R n , according to the number of personnel and preset information, m groups are set up, and the groups are marked as Z1, Z2, ..., Z m ,Right now ; In the formula, x j i Indicates whether the i-th person is assigned to the j-th group, where i is 1, 2, ..., n, and j is 1, 2, ..., m; by: ; In the formula, d k represents the number of personnel required for the kth service, thereby constraining the number of personnel assigned to different services to be equal to the personnel demand of the service;
[0011] Mapping the executable tasks to each group to allocate gardening demand tasks to each execution group specifically includes: According to the complexity and professional requirements of each executable task, a team with high skill and experience adaptability is selected for docking. In the formula, PD is the adaptability score, Wi is
[0012] is the executable task weight, S ij represents the skill score of the group on the task, and n is the number of groups;
[0013] Real-time monitoring of the work progress and completion results of each group after assignment;
[0014] Evaluate the work progress and completion results to obtain evaluation results;
[0015] Adjust the labor dispatch team personnel based on the evaluation feedback.
[0016] As a further optimization scheme of the present invention, personnel information is collected, multiple groups are formed, and the groups are assigned according to the demand information of the landscaping project, including:
[0017] Collect information about people’s age, size, gender, health, and experience;
[0018] Assign personnel to form teams based on personnel information.
[0019] As a further optimization scheme of the present invention, personnel are assigned to form a team according to personnel information, including:
[0020] The preset weight of experience value is 1; the weight of age is 2; the weight of BMI body mass index is 1;
[0021] By standardizing each weighted feature value and setting the experience score S1, the highest experience is 10 years and the lowest is 1 year, and the score is: ; Set the age score S2, then the scores from high to low for the age range of 30-50 are: ; BMI score S3, the index range is 18.5-24.9 from high to low scores: ;
[0022] Then through: Where S core It is expressed as a score, where W1, W2, and W3 represent the weights of experience value, age, and BMI, respectively, and S1, S2, and S3 represent the standardized thresholds of experience value, age, and BMI of the assigned personnel, which are set between 0 and 1, thereby obtaining the individual score of the personnel;
[0023] After obtaining the scores of each weight, the labor teams are formed in order from high to low according to the scores, namely, senior team, intermediate team, secondary team and primary team;
[0024] Allocations are made based on the formed senior, intermediate, secondary and primary groups according to the landscaping needs.
[0025] As a further optimization scheme of the present invention, the executable tasks are mapped to each group to allocate the gardening demand tasks to each execution group, including:
[0026] According to different types of greening requirements, the group resource matching requirements can be expressed as a four-tuple: ; In the formula, T represents the set of groups participating in the labor service, which is expressed as T={senior group, intermediate group, secondary group, primary group}; VM′ represents the set of greening needs of the garden, which is VM′={X l , G j , Z x , C l , F c}; G represents the preciousness of different plant species required for greening, G={top, advanced, excellent, ordinary}; qos represents the service matching degree set between the labor team and greening needs, expressed as λ={λ1,λ2,…,λ n},λ n Represents the matching of a labor group with landscaping needs.
[0027] As a further optimization scheme of the present invention, real-time monitoring of the work progress and completion effect of each group after assignment includes:
[0028] Break down the team's overall work into multiple subtasks and assign them to each team member. Each subtask has a preset deadline and outcome definition.
[0029] Acquire individual targets through real-time monitoring by deploying monitoring equipment;
[0030] According to the individual goals of the personnel, when executing subtasks, real-time tracking and updating of task status, including: "not started", "in progress", "completed", to obtain real-time progress data;
[0031] Obtain personnel work progress and personnel attendance based on real-time progress data to obtain individual performance data.
[0032] As a further optimization scheme of the present invention, an evaluation is performed according to the work progress and completion effect to obtain an evaluation result, including:
[0033] Based on the individual performance data, quality inspection standards are established, including: punctual completion of assigned tasks, garden vegetation repair effects, reasonable greening layout and environmental maintenance. Quality inspections are conducted after the team's overall work tasks are completed to obtain inspection results;
[0034] According to the inspection results, through: Where S overall is the quality score, n is the number of tasks completed by the personnel; S i The performance summary of i tasks is obtained, and the quality score of individual task completion is obtained to obtain the evaluation result.
[0035] As a further optimization scheme of the present invention, adjusting the labor dispatch team members according to the evaluation result feedback includes:
[0036] The evaluation results are compared with the preset mass point standards by: ; In the formula, A is the comprehensive deviation score, F is the quality deviation score, and G is the attendance deviation score, in order to obtain the deviation between the actual task completion and the expected result;
[0037] According to the expected deviation, the comparison standard is set: when A is within 10%, it is excellent; when A is 21%-20%, it is good; when A is 21%-30%, it is passing; when A exceeds 31%, it is poor;
[0038] According to the comprehensive deviation scores, they are sorted from high to low, q excellent personnel and h poor personnel are selected, and corresponding incentive and reward and punishment measures are formulated.
[0039] As a further optimization scheme of the present invention, n excellent personnel and n poor personnel are selected according to the comprehensive deviation scores from high to low, and corresponding incentive and reward measures are formulated, including:
[0040] Give bonuses to q outstanding personnel as encouragement and provide career development opportunities: promotion, expansion of responsibilities or participation in higher-level landscaping projects;
[0041] Publicly recognize outstanding personnel and provide opportunities for advanced training or seminars;
[0042] Conduct one-on-one interviews with h poor performers, clearly identify the specific reasons for their poor performance, and negotiate improvement plans;
[0043] For those who have repeatedly failed to make improvements or have a bad attitude, a formal written warning will be issued and they will be informed that they will face salary penalties or dismissal.
[0044] In a second aspect, the system provides an electronic device including a memory, a processor, and a landscaping labor dispatch management method program stored in the memory and executable on the processor, wherein the landscaping labor dispatch management method program implements the steps of the landscaping labor dispatch management method when executed by the processor.
[0045] In a third aspect, a landscaping labor dispatch management system includes:
[0046] Information collection module 201: used to obtain landscaping project demand information;
[0047] On-demand allocation module 202: It is used to collect personnel information, form multiple groups, and assign groups according to the landscaping project demand information; map the executable tasks to each group to allocate the landscaping demand tasks to each execution group;
[0048] Real-time monitoring module 203: used to monitor the work progress and completion effect of each group after assignment in real time;
[0049] The quality assessment module 204 is used to assess the work progress and completion effect to obtain an assessment result;
[0050] Feedback adjustment module 205: It is used to adjust the labor dispatch team members according to the evaluation result feedback.
[0051] The present invention has at least the following beneficial effects: by collecting personnel information and forming multiple groups, the present invention can assign each dispatched personnel to a suitable labor grade group according to their personal information, thus laying a foundation for subsequent on-demand assignment; at the same time, the demand information of the landscaping project is obtained, and the groups are assigned according to the demand information, so that work tasks can be assigned to the labor grade groups according to demand, and the number of personnel in the group can be determined to complete the corresponding tasks;
[0052] By real-time monitoring of the work progress and completion results of the labor dispatch team, evaluation is conducted based on the work progress and completion results to obtain evaluation results. Finally, the labor dispatch strategy is adjusted based on the evaluation results, so that the tasks assigned by the team can be further evaluated and fed back. A corresponding incentive and reward system is formulated to mobilize the enthusiasm and work attitude of the labor dispatch personnel, ensuring the orderly development of landscaping labor dispatch management. BRIEF DESCRIPTION OF THE DRAWINGS
[0053] Figure 1 It is a flow chart of a landscaping labor dispatch management method provided by an embodiment of the present invention;
[0054] Figure 2 It is a schematic diagram of a landscaping labor dispatch management system provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0055] The present application is further described in detail below in conjunction with the accompanying drawings. It is necessary to point out here that the following specific implementation methods are only used to further illustrate the present application and cannot be understood as limiting the scope of protection of the present application. Technical personnel in this field can make some non-essential improvements and adjustments to the present application based on the above application content.
[0056] A landscaping labor dispatch management method and system, the specific implementation methods are as follows:
[0057] like Figure 1 As shown, a landscaping labor dispatch management method includes the following steps:
[0058] Step 1: Obtain landscaping project demand information and convert it into executable tasks, including: Repair branches X l ; Watering and fertilization G j ; Planting new varieties Z x ; Treat weeds C l ; Pest control c ;
[0059] Step 2: Collect personnel information and form multiple teams based on the personnel information, including: pre-organizing n dispatched personnel and marking them as R1, R2, ..., R n , according to the number of personnel and preset information, m groups are set up, and the groups are marked as Z1, Z2, ..., Z m ,Right now ; In the formula, x j i Indicates whether the i-th person is assigned to the j-th group, where i is 1, 2, ..., n, and j is 1, 2, ..., m; by: ; In the formula, d krepresents the number of personnel required for the kth service, thereby constraining the number of personnel assigned to different services to be equal to the personnel demand of the service;
[0060] Step 3, mapping the executable tasks to each group to allocate gardening demand tasks to each execution group, specifically including: According to the complexity and professional requirements of each executable task, a team with high skill and experience adaptability is selected for docking. In the formula, PD is the adaptability score, Wi is the executable task weight, and S ij represents the skill score of the group on the task, and n is the number of groups;
[0061] Step 4: Monitor the work progress and completion results of each group in real time after assignment;
[0062] Step 5, evaluating the work progress and completion effect to obtain an evaluation result;
[0063] Step 6: Adjust the labor dispatch team members based on the evaluation feedback.
[0064] In a preferred embodiment of the present invention, first, after understanding the specific needs of landscaping through step 1 (such as pruning trees, weeding, pest control, vegetation watering, and planting new plant varieties), pre-formed teams are assigned according to these task requirements. Demand information can be obtained from regular garden inspection reports, seasonal plans, or emergencies. Then, use this information to match the corresponding teams and send them to specific task locations. The work tasks and areas of each team will be planned in advance and recorded in the system. According to the task requirements and team skills, the accuracy and applicability of task assignments are ensured, so that teams can be reasonably assigned so that they can efficiently complete landscaping tasks, reduce error rates and waste of resources, and enable the system to clearly assign and record tasks, which helps managers track work progress and task completion in real time;
[0065] Classify and record various problems in the landscaping process through step 2. These problems usually include the following types:
[0066] Repair branches: including pruning branches, removing dead branches, etc.
[0067] Irrigation and fertilization: includes regular watering and fertilization to ensure the healthy growth of plants.
[0068] Planting new varieties: Introduce and plant new plant varieties to increase the diversity of the park's plants.
[0069] Weed control: Remove weeds in the park to prevent them from affecting the normal growth of plants.
[0070] Pest and disease control: Monitor and treat potential pest and disease threats to plants.
[0071] The above-mentioned landscaping needs can be obtained through inspections, sensor data, manual reports, etc., to continuously collect information on greening problems in the park. Mobile devices or sensors can be used to automatically collect problem data and systematically collect different types of greening problems to ensure that various problems in the park can be discovered and handled in a timely manner. Through data collection, a scientific and systematic greening management system is formed to facilitate subsequent analysis and decision-making.
[0072] Based on the landscaping project information obtained in step 1, the basic information of all dispatched workers, including name, age, skill level, health status, work experience and body type, is collected through step 2. This information is recorded and managed through a spreadsheet or database. Based on the collected information, the personnel are divided into different groups, and each group is set to a different labor level (for example, primary, secondary, intermediate, and senior) according to the skill and experience level of its members. This grouping can be adjusted according to specific task requirements. For example, personnel with special skills are assigned to groups that require these skills, so that by assigning personnel to the most suitable groups, their skills and experience can be fully utilized to improve work efficiency. In addition, the personnel grouping can be flexibly adjusted according to the complexity and particularity of the landscaping project. By reasonably allocating personnel, skill waste can be reduced to ensure that each member plays a role to the maximum extent within their capabilities.
[0073] According to step 1 and step 2, the requirements of the landscaping project are analyzed in detail and split into multiple executable tasks through step 3. Each task requires specific personnel age, body type, gender, health status and experience value. Next, the task is assigned to the most suitable group according to the fitness score, and each task mapping is assigned to the group that can complete the task most efficiently. During the task allocation process, the task allocation needs to be dynamically adjusted according to the actual progress and emergencies of the group. This can be achieved through real-time monitoring tools and adjustment algorithms to ensure the flexibility and responsiveness of the project.
[0074] After assigning the teams according to step 2, use real-time monitoring equipment (such as GPS tracking, mobile applications, RFID, etc.) and management software in step 4 to monitor the work progress and task completion results of each team. The monitoring content includes the start and end time of the task, the actual work progress, and the quality of task completion. These data are automatically recorded and uploaded to the management system for managers to view and analyze, so that they can understand the progress and results of each team in real time, make personnel adjustments in time, avoid task delays or poor execution, ensure that the work quality meets the standards through real-time monitoring, and find and solve problems in time. All progress and completion status are recorded, which increases the transparency and traceability of the work.
[0075] According to step 4, the collected work progress and completion effect data are monitored in real time, and the work performance of each team is evaluated through the evaluation standards and methods preset in step 5. The evaluation content includes the time, quality, and completion rate of the work, and a detailed evaluation report or score is generated. The data-based evaluation can reduce subjective bias, measure the performance of each team fairly and impartially, identify problems and deficiencies through evaluation, provide a basis and direction for future improvements, and help to reward or take improvement measures based on performance, thereby improving the overall work level.
[0076] According to the evaluation results of step 5, adjust the labor dispatch strategy through step 6, including reallocating personnel, adjusting team composition, changing the way tasks are assigned, etc. For teams with excellent performance, more complex tasks can be assigned or rewards can be given; for teams with poor performance, it may be necessary to increase training, reduce the amount of tasks, or adjust the personnel composition. Adjust the strategy according to actual performance and optimize the use of human resources. By continuously adjusting and optimizing the labor dispatch strategy, it will help improve overall work efficiency and the quality of task completion. Rewarding outstanding personnel and teams can motivate the enthusiasm and work attitude of dispatched personnel; improve poor performance to maintain the overall efficient operation of the team.
[0077] In a preferred embodiment of the present invention, the above step 2 further includes:
[0078] Step 21, collect the age, body type, gender, health condition and experience value information of the personnel, specifically including: Age: 30-50 years old;
[0079] Body type: healthy limbs, BMI range of 18.5-24.9;
[0080] Gender: male or female;
[0081] Experience: More than one year of relevant work experience;
[0082] Step 22, assign personnel to form a team based on the personnel-related information in a ratio of "1:2:1".
[0083] In a preferred embodiment of the present invention, the above step 22 further includes:
[0084] Step 221, set the experience value weight: 1; age weight: 2; BMI weight: 1;
[0085] Step 222, by standardizing each weight feature value, so that the weight feature value score is between 0 and 1, specifically including: Experience value score S1 scores the experience value according to the length of working years, when the maximum experience is set to 10 years and the minimum is 1 year, the standardization is: ;
[0086] The age score S2 normalizes and inverts the age, setting the younger scores high: ; The higher the BMI score, the higher the S3 score, the standardized value is: ;
[0087] Step 223, combined with the weights, by: Where S core It is expressed as a score, where W1, W2, and W3 represent the weights of experience value, age, and BMI body mass index, respectively, and S1, S2, and S3 represent the standardized thresholds of experience value, age, and BMI of the assigned personnel, which are set between 0 and 1, thereby obtaining the individual scores of the personnel;
[0088] Step 224, after obtaining the scores of each weight, the labor teams are formed in order of senior team, intermediate team, secondary team and primary team according to the scores from high to low;
[0089] Step 225, according to the formed senior group, intermediate group, secondary group and primary group, allocation is made according to the landscaping needs.
[0090] In the embodiment of the present invention, the following information is collected for each labor dispatch personnel in step 21:
[0091] Age: The screening range is 30-50 years old.
[0092] Body shape: All limbs must be healthy and the BMI should be between 18.5-24.9.
[0093] Gender: Male or Female.
[0094] Health: Ensure you are in good health and able to perform the relevant work.
[0095] Experience: More than one year of relevant work experience is required.
[0096] The data collected must meet the specified standards to ensure that the physical condition and experience of all dispatched workers meet the requirements for forming a team. By collecting and verifying these key data, it can be ensured that the participating personnel have the basic physical conditions and work experience to be competent for the assigned tasks. By screening qualified personnel, a solid foundation can be laid for subsequent group assignments and task arrangements, ensuring the overall work ability and efficiency of the team.
[0097] According to the personnel information collected in step 21, the personnel are assigned in a ratio of "1:2:1" through step 22. This ratio refers to: 1: experience value weight; 2: youth weight; 1: BMI weight. The goal is to form a balanced team, which includes both experienced personnel and young and healthy members, so as to achieve a balance in experience, physical fitness and new creativity and new ideas. By assigning personnel in proportion, it can be ensured that each team achieves a balance in experience, physical fitness and youth, improve the work efficiency and adaptability of the team, and a balanced team performs better when facing complex tasks and can effectively combine experience and physical fitness advantages.
[0098] Based on step 22, a group is formed in proportion, and weights are further assigned to each feature through step 221, where: the weight of experience value is set to 1, which means that the importance of experience value to the overall evaluation is relatively medium; the weight of youth is set to 2, which emphasizes the importance of youth (such as younger age and stronger physical fitness); the weight of BMI body mass index is set to 1, which means that the importance of body shape to the evaluation is also medium.
[0099] The strategic considerations for team composition are reflected through weight setting: older people can more easily cope with physically demanding tasks; experience is important but not the only determining factor. Therefore, by allocating weights reasonably, a team with both experience and physical advantages can be formed; and for tasks that require high physical fitness and vitality, increasing the age weight enables the team to cope better.
[0100] Based on step 221, each eigenvalue collected is normalized through step 222 to limit its range to between 0 and 1. Each weighted eigenvalue can be implemented with the following formula: ; In the formula, x is the original eigenvalue, and x′ is the standardized eigenvalue. The purpose of standardization is to eliminate the dimensional differences between different features and ensure that when calculating the comprehensive score, the impact of each feature on the final result is relatively balanced.
[0101] The standardization process eliminates the scale differences between the eigenvalues, making the various features comparable in the comprehensive score, making the standardized eigenvalues easier to calculate comprehensively, reducing bias, and improving the fairness and accuracy of the score.
[0102] Then, in step 223, each standardized feature value is multiplied by the corresponding weight, and then the sum is calculated to obtain the comprehensive score of each person; Through weighted summation calculation, we get the comprehensive score of each person, which is used to measure their priority in team building. By combining the scores of various characteristics, we can comprehensively and objectively evaluate the comprehensive ability of each dispatched worker, thereby ensuring that important characteristics are fully reflected in individual scores, making the scoring results more in line with team needs.
[0103] Finally, all personnel are sorted from high to low according to their comprehensive scores in step 224. Those with high scores have stronger comprehensive abilities and are more suitable for important or complex tasks. According to the score sorting results, the personnel are divided into senior group, intermediate group, secondary group and primary group. The grouping method can be:
[0104] Senior Group: Top X% of the highest scorers;
[0105] Intermediate group: the next highest rate is Y%;
[0106] Secondary group: Z with the next highest score;
[0107] Junior Group: The remaining persons with the lowest scores.
[0108] According to the grouping results, personnel will be assigned to different groups. Each group has different focuses in terms of experience, physical fitness, youth, etc., to adapt to different task requirements. Reasonable grouping is carried out according to the comprehensive scores to ensure that the ability structure of each group is balanced and can cope with different task requirements. By grouping by scores, it is ensured that high-ability personnel are assigned to advanced tasks, and the internal capabilities of the group are complementary, thereby improving overall work efficiency and task completion rate.
[0109] In a preferred embodiment of the present invention, the above step 3 may include:
[0110] Step 31, according to different types of greening requirements, the group resource matching requirements can be expressed as a four-tuple: ; In the formula, T represents the set of groups participating in the labor service, which is expressed as T={senior group, intermediate group, secondary group, primary group}; VM′ represents the set of greening needs of the garden, which is VM′={X l , G j , Z x , C l , F c}; G represents the preciousness of different plant species required for greening, G={top, advanced, excellent, ordinary}; qos represents the service matching degree set between the labor team and greening needs, expressed as λ={λ1,λ2,…,λ n},λ n Represents the matching of a labor group with landscaping needs.
[0111] In the embodiment of the invention, the specific steps of further searching for the best decision λ for specific needs according to step 3 through step 31 are as follows:
[0112] First, a level group α is randomly selected from the task node set T. At this time, the service matching degree λ=Φ, and the required task level group UT=Φ has been found;
[0113] Then, by traversing the virtual node demand task set VM' that can be selected by the current demand task, and selecting the maximum qos match, update the matching degree λ, and then delete the task from the task node set and insert λ into the demand task set that has completed the matching, that is: ;
[0114] When the task node is selected, ∑ i∈C x i,j >1, there is group competition, and the optimal task solution γ is selected through recursive calls and λ is updated, that is, , when T=Φ, the maximum number of matches i has been reached, and the best service matching degree λ is obtained.
[0115] By combining the quadruple with the service matching degree λ, we can match the team with the greening demand tasks to ensure the accuracy and efficiency of task allocation. At the same time, we can reasonably allocate team resources to avoid excessive use of high-skilled teams on simple tasks or low-skilled teams on complex tasks, thereby improving overall work efficiency.
[0116] In a preferred embodiment of the present invention, the above step 4 may include:
[0117] Step 41, decompose the group's overall work task into multiple subtasks and assign them to each team member, and each subtask has a preset deadline and outcome definition;
[0118] Step 42, real-time monitoring and acquisition of individual personnel targets by deploying monitoring equipment;
[0119] Step 43, tracking and updating the task status in real time when executing the subtask according to the individual goal of the personnel, specifically including: "not started", "in progress", "completed", so as to obtain real-time progress data;
[0120] Step 44, obtaining personnel work progress and personnel attendance according to the real-time progress data to obtain individual performance data.
[0121] In the embodiment of the present invention, the overall work task is decomposed into multiple subtasks through step 41. The subdivision criteria can be based on factors such as the nature, complexity, and execution time of the task to ensure that each subtask is operational and manageable, and has clear goals and requirements. In addition, the subdivided subtasks are assigned to the most suitable groups or individuals based on the previously established group structure. The overall work task is decomposed into multiple specific subtasks based on the complexity and time requirements of the task. Each subtask should have clear goals and operation steps, and the decomposition process should consider the logical order and dependencies of the tasks to ensure that the tasks can be effectively connected.
[0122] Assign the decomposed subtasks to appropriate groups or members. Consider the skills, experience and current workload of the members when assigning tasks to ensure that the tasks are reasonably assigned. Record the task assignments through the management system, including the responsible personnel, task content, deadlines and other information. Set a clear deadline for each subtask to ensure that the project is advanced on time. The deadline should be reasonably set according to the workload, complexity and resource availability of the task. When setting the deadline, leave a certain amount of time margin to deal with emergencies. Clearly define the results requirements for each subtask, such as specific work completion standards, acceptance conditions, etc. The results definition should be specific and measurable to facilitate subsequent inspection and acceptance. By decomposing tasks and assigning them to specific personnel or groups, each task has a clear person in charge and goal to reduce uncertainty in task execution. Decomposing tasks, setting deadlines and results standards make each link of the project controllable and manageable, reduce project risks, and ensure that the output of each task meets the expected quality standards through clear results definitions, thereby improving the overall project success rate.
[0123] Then, in step 42, appropriate management and monitoring equipment is selected according to the project requirements. The following factors should be considered when selecting equipment:
[0124] Monitoring range: The equipment should be able to cover the entire working area, or cover key areas as needed.
[0125] Functionality: The equipment should have functions such as real-time monitoring, data collection, and remote control.
[0126] Device type: This can include cameras, sensors, drones, etc., which are used to monitor the environment, task progress, and personnel location, etc.
[0127] Monitoring equipment should be deployed reasonably according to the layout of landscaping and the specific needs of the task, and key task areas or areas with risks should be deployed with emphasis.
[0128] Ensure stable operation of equipment and effective data transmission. For example, cameras can be deployed on trees, buildings or high places to obtain the best monitoring angle. Through the deployment of monitoring equipment, it is possible to understand the progress of tasks, personnel activities and environmental conditions in real time, providing data support for subsequent task management. In addition, monitoring equipment can promptly detect and record abnormal situations during the work process, which is convenient for managers to intervene and adjust in time and reduce risks.
[0129] Then, the task progress of each team member is tracked in real time through step 43. The status of each task is divided into three stages: "not started", "in progress" and "completed".
[0130] When completing each subtask, the team members will update the task status in time and record the status changes in the system. The system will automatically summarize and generate task progress data based on the task status update and provide real-time progress reports. When a task fails to progress as planned (such as overdue or stagnant), the system will send a reminder to the manager or relevant team members to prompt the problem to be solved in time. The overall project progress is intuitively displayed through charts, progress bars, etc., so that managers can quickly understand the current status of the project.
[0131] By updating and tracking task status in real time, managers can keep track of project progress at any time to ensure that the project proceeds as planned. The real-time display and reminder functions of progress data can help to promptly identify problems in task execution and make rapid interventions and adjustments. Through transparent management of task status, team members can collaborate better and reduce information asymmetry and misunderstandings.
[0132] Finally, in step 44, the monitoring data is used to measure the timeliness of task execution and whether it is progressing according to plan through work progress. It is usually measured by the percentage of completed tasks;
[0133] The work completion rate indicates the final completion status of the task, and calculates the ratio of the number of completed tasks to the number of assigned tasks; at the end of the task, the monitoring system is used to confirm whether all tasks have been completed as required; the quality pass rate measures the quality of task completion, indicating whether the task results meet the preset quality standards, and then checks the task results, calculates the ratio of qualified tasks to total tasks, and enters the inspection results into the system as a basis for evaluating the quality pass rate; the attendance rate measures the work participation of personnel, indicating the ratio of the number of attendance days of personnel during the task execution period to the total number of working days, and records the attendance of personnel through the clock-in system and monitoring equipment, and calculates the attendance rate.
[0134] By defining multiple key performance indicators, we can comprehensively measure personnel performance from multiple dimensions to ensure the objectivity and fairness of the evaluation. Performance indicators formulated according to task objectives are more in line with actual work conditions, making it easier for managers and dispatched personnel to focus on the key points of the task. The quantitative definition of key performance indicators makes performance evaluation more specific and operational, providing data support for subsequent quality scoring and personnel incentives.
[0135] In a preferred embodiment of the present invention, the above step 5 may include:
[0136] Step 51, based on the individual performance data, establish quality inspection standards, specifically including: completing the assigned tasks on time, garden vegetation repair effect, reasonable greening layout and environmental maintenance, and conduct quality inspection on the overall work tasks of the group after completion to obtain inspection results;
[0137] Step 52, according to the inspection result, by: Where S overall is the quality score, n is the number of tasks completed by the personnel; S i The performance summary of i tasks is obtained, and the quality score of individual task completion is obtained to obtain the evaluation result.
[0138] In an embodiment of the present invention, according to the nature and requirements of the task, a particle inspection standard is established through step 51. These standards should cover the key quality points of the task to ensure the quality and consistency of the work results. The particle inspection standards may include: checking whether the planting density of the plants meets the design requirements and planting specifications to ensure that the density is moderate and does not affect the growth space of the plants; checking whether the plants are healthy and free of pests and diseases, whether the leaves are complete, and whether there are no yellow leaves, dry leaves, and disease spots; confirming whether the planted seedlings meet the design specifications, including the height, crown width, root system and other indicators of the seedlings; confirming whether the planted plant varieties are consistent with the design drawings to avoid variety confusion or wrong planting; checking whether the soil meets the design requirements, including the nutrient content, pH value, air permeability and other indicators of the soil; checking whether the laying of the planting matrix is uniform and whether the thickness meets the design requirements. Check whether the drainage system is unobstructed and whether there is any water accumulation to ensure good drainage and avoid waterlogging of plant roots; check whether the planting position of plants is consistent with the design drawings to ensure a reasonable and beautiful layout; check whether the planting layers of garden plants are clear, with low in front and high in the back, and staggered to achieve visual beauty; check whether the spacing between plants is appropriate to avoid overcrowding or oversparseness that affects plant growth and aesthetic effects; check whether the material quality and paving methods of hard landscape paving such as garden paths and squares meet the specifications, and whether there are cracks, looseness, etc.; check whether landscape sketches (such as sculptures, water features, flower beds, etc.) are installed in place, whether there are any damage or unstable installation; check Check whether garden facilities and equipment (such as seats, pavilions, lamps, etc.) are installed firmly and whether there are any safety hazards; check the construction quality of basic work such as land preparation, fertilization, and pit digging to ensure that the land is flat, fertilization is even, and the pits are standardized; check whether the transplanting and planting methods of plants meet the specifications to ensure that the root system of the plants is not damaged and the planting depth is appropriate; check whether the support and binding of large trees are firm, and whether the protective measures (such as straw rope wrapping, brackets, etc.) are in place to avoid damage to plants caused by environmental factors such as strong winds; check whether the watering frequency and watering amount meet the requirements to ensure that the plants get enough water and grow healthily; check whether the fertilization frequency, fertilizer type, and fertilizer amount meet the specifications to ensure that the plants get the necessary nutrients; check whether the pest control measures are Check whether the landscaping is in place, whether the type, concentration and spraying frequency of the pesticides used meet the requirements; check whether the pruning and shaping of plants are timely and standardized to ensure that the plants are beautiful in shape and evenly illuminated; check whether there are weeds in the green space, whether the soil is loosened regularly to ensure good soil permeability; check whether the overall layout of the garden meets the design requirements, whether the plant growth is balanced, whether the overall layout is coordinated, check the coordination between the greening project and the surrounding environment, ensure that the color matching and plant species complement the surrounding landscape, evaluate the use effect and satisfaction of the garden through feedback from residents or users, identify potential problems, and make improvements. After each task is completed, check the work results according to the established quality inspection standards.Inspections can be conducted by internal personnel (such as project managers) or external third parties to ensure objectivity and accuracy. The inspection content should cover every key point of the task to ensure that the final results meet the expected quality standards. The inspection results will be entered into the management system as the basis for task acceptance. System records should include: inspector, inspection time, inspection results, existing problems and improvement suggestions.
[0139] By establishing quality inspection standards and strict results inspections, we can effectively ensure the quality of tasks and ensure that the output of each task meets the expected standards. Entering the inspection results into the system will provide a basis for subsequent work improvements, which will help to continuously improve project management levels and work quality. By recording and reporting inspection results, we can improve the transparency and accountability of the project and ensure that all tasks are performed in accordance with the specified quality standards.
[0140] Based on step 51, different weights are set for each key performance indicator according to the actual needs of the project using step 52. For example, if the project has higher quality requirements, the weight of the quality pass rate can be higher than the work progress.
[0141] Set scoring criteria for each KPI. For example:
[0142] Work progress score: Full marks for 100% on-time completion, points may be deducted for less than 80%;
[0143] Work completion rate score: 100% completion will get full marks, and the corresponding score will be reduced for every 10% decrease in completion rate;
[0144] Quality pass rate score: score is given directly based on the quality inspection results;
[0145] Attendance score: Full attendance will get full marks, and each day of absence will reduce the corresponding score.
[0146] Based on the calculated quality score, we can get the comprehensive evaluation results of each person, which can be used as a basis for decision-making in the assessment, promotion, reward, training needs analysis, etc. of dispatched personnel; based on the evaluation results, we can provide specific feedback, point out the strengths of the personnel and areas for improvement. Based on this, we can set the next work goal or personal development plan.
[0147] Through quantitative performance indicators and scientific scoring models, we can objectively and impartially evaluate personnel's work performance and task completion. The clear scoring and evaluation mechanism enables dispatched personnel to understand their own work performance and motivate them to improve work efficiency and quality. The evaluation results provide data support for dispatched personnel management, incentives, training and other decisions, helping managers make more scientific management decisions. Through evaluation results and feedback, dispatched personnel can clearly understand their own improvement directions and promote continuous improvement and development of individuals and teams.
[0148] In a preferred embodiment of the present invention, the above step 6 may include:
[0149] Step 61, compare the evaluation result with the preset mass point standard by: ; In the formula, A is the comprehensive deviation score, F is the quality deviation score, and G is the attendance deviation score, in order to obtain the deviation between the actual task completion and the expected result;
[0150] Step 62, according to the expected deviation, set the comparison standard: when A is within 10%, it is excellent; when A is 21%-20%, it is good; when A is 21%-30%, it is passing; when A exceeds 31%, it is poor;
[0151] Step 63, sorting from high to low according to the comprehensive deviation score, screening out n excellent personnel and n poor personnel, and formulating corresponding incentive and reward measures.
[0152] In the embodiment of the present invention, the evaluation result obtained based on step 4 is compared with the preset standard through step 61 to obtain the deviation between the actual task completion and the expected result. Before the task starts, the management will set a set of expected standards or goals. These standards are formulated based on the overall requirements of the project, the difficulty of the specific task and historical data, and represent the expected results of the project.
[0153] According to the quality score in step 52, the task completion evaluation results of each person or team are obtained. The evaluation results are a quantitative reflection of the actual work performance, including comprehensive scores of progress, quality, completion rate and attendance rate. The actual evaluation results are compared with the preset standards to obtain the deviation between the actual task completion and the expected results. It can be understood whether the actual completion of the task is better than, close to or lower than the expected standard, thereby providing a basis for subsequent improvements and adjustments. By comparing the actual results with the expected standards, problems and gaps in the task execution process can be quickly located, which facilitates timely corrective measures. Deviation analysis provides data support for managers, making subsequent management decisions more scientific and reliable.
[0154] In order to better evaluate the task completion status, step 62 is then performed to classify the task completion status into different levels according to the deviation A. The comparison criteria are set as follows:
[0155] A is within 10%, and the task completion is excellent, indicating that the actual results basically meet or exceed the expected standards;
[0156] A is between 21% and 20%, indicating that the task completion is good, indicating that the actual result is slightly lower than the expected standard, but is still relatively satisfactory overall;
[0157] A is between 21% and 30%, indicating that the task completion is acceptable, indicating that the actual result is significantly lower than the expected standard, but still within the acceptable range;
[0158] A exceeds 31%, indicating that the task completion is poor, indicating that the actual results are seriously below the expected standards and need to be paid attention to and improved;
[0159] Application of comparison standards: After the evaluation is completed, the deviation A of each evaluation result will be classified into the above four levels, so that managers can intuitively understand the completion status of each task. By setting clear deviation classification standards, the evaluation of task completion is more objective and consistent, avoiding the interference of subjective judgment. Dispatched personnel can clearly understand the standards they need to achieve and the gap with the expected results, so as to improve their work performance in a targeted manner.
[0160] Finally, the comprehensive deviation score is sorted in step 63: the deviation A of all dispatched personnel or teams is sorted by size, from the smallest to the largest, which means that they are arranged in order from the best to the worst task completion.
[0161] The sorted list can clearly show the relative performance of each dispatched personnel or team in completing the task, making it easier for managers to have a macro control over the overall work status of all personnel.
[0162] Screen out excellent and poor personnel: Screen out the top n excellent personnel (i.e., those with the smallest deviation A) and the bottom n poor personnel (i.e., those with the largest deviation A) from the sorting results.
[0163] Excellent personnel indicated that their actual task completion was closest to or exceeded expectations, while poor personnel indicated that their actual task completion was the most different from expectations and required special attention.
[0164] Formulate incentives and rewards: Give appropriate incentives to outstanding personnel, such as bonuses, commendations, promotion opportunities, training opportunities, etc. These incentives are designed to encourage dispatched personnel to maintain excellent performance and stimulate the competitive awareness of other dispatched personnel.
[0165] Punitive measures: For those with poor performance, appropriate punitive measures will be implemented, such as warnings, salary cuts, bonus deductions, etc. At the same time, additional training or coaching can be arranged to help them improve their work capabilities.
[0166] By screening out personnel with outstanding performance and rewarding them, we can set an example, motivate other dispatched personnel to emulate excellence, and create a positive working atmosphere; by punishing and coaching personnel with poor performance, we can promptly correct mistakes and deficiencies in their work and help them improve and enhance their work performance.
[0167] Improve overall team performance: Through the reward and punishment mechanism, we can promote the continuous improvement of the work efficiency and quality of the entire team, which will help achieve team goals and project success.
[0168] In another preferred embodiment of the present invention, the above step 63 may include:
[0169] Step 631, give bonus encouragement to q outstanding personnel and provide career development opportunities: promotion, expansion of responsibilities or participation in higher-level landscaping projects;
[0170] Step 642, publicly commend outstanding personnel and provide opportunities for them to participate in advanced training or seminars;
[0171] Step 643, conduct one-on-one interviews with the h poor performers, clearly point out the specific reasons for their poor performance, and negotiate improvement plans;
[0172] Step 644: For those who have repeatedly failed to make improvements or have a bad attitude, a formal written warning will be issued and they will be informed that they will face salary penalties or dismissal.
[0173] In the embodiment of the present invention, based on the incentive system formulated in step 63, the n selected excellent personnel are further given bonuses through step 631. The bonus amount can be distributed differently according to the performance score of the dispatched personnel or the size of the project contribution. The bonus incentive is not only an affirmation of the work of the dispatched personnel, but also can enhance their work enthusiasm and loyalty, and provide promotion opportunities for dispatched personnel with particularly outstanding performance. For example, promotion to a higher-level position, assuming more management responsibilities, giving excellent dispatched personnel more responsibilities and challenging tasks, expanding their job scope, such as letting them be responsible for more complex or important projects, enhancing their professional skills and leadership capabilities, and dispatched personnel with outstanding performance can be assigned to higher-level labor groups to increase their experience accumulation and provide them with a platform for career development.
[0174] Bonuses and career development incentives can encourage dispatched personnel to maintain high levels of performance and drive progress for the entire team. Career development opportunities allow dispatched personnel to see future growth paths, which increases their motivation and loyalty to the company. Through promotions and expanded responsibilities, outstanding dispatched personnel can be trained to become leaders of teams or projects, thereby improving the overall quality and management capabilities of the team.
[0175] Then, in step 642, outstanding dispatched personnel are publicly recognized through company announcements, meetings, activities, etc. This is not only an affirmation of the individual, but also a role model for the team. Recognition can be carried out through the issuance of certificates, medals or other forms to enhance the sense of ceremony and honor, and provide outstanding dispatched personnel with opportunities to participate in advanced training courses or industry seminars to help them improve their professional skills and professional qualities.
[0176] Advanced training courses can cover the latest landscaping technology, project management skills, leadership training, etc., to ensure that dispatched personnel stay ahead in their professional fields. Seminars provide opportunities to communicate with industry experts and peers, which helps to broaden horizons and gain new knowledge and insights. Public recognition can set an example effect in the team, inspire other dispatched personnel to learn and improve, and form a good competitive atmosphere. Advanced training and seminars provide dispatched personnel with opportunities for continuous learning and improvement, help them cope with more complex tasks, and promote the further development of their careers. Public recognition is not only a recognition of the individual, but also an affirmation of teamwork, which can enhance team cohesion and a sense of belonging.
[0177] Then, in step 643, a one-on-one performance interview is conducted with the supervisor or project manager of the dispatched personnel with poor performance. The purpose of the interview is to understand the specific reasons for the poor performance of the dispatched personnel, listen to the feedback and difficulties of the dispatched personnel, and provide them with improvement suggestions. It is ensured that the interview process should be mainly constructive, avoid accusations, and focus more on problem solving and future improvement directions. Through the interview, the supervisor and the dispatched personnel jointly analyze the reasons for poor performance, which may include: insufficient skills, deviation in task understanding, work attitude problems, external interference factors (such as personal problems, team conflicts, etc.), clearly point out the specific areas of poor performance, and analyze them in combination with performance data to ensure that the dispatched personnel understand the problem. The one-on-one interview helps the dispatched personnel understand the specific reasons for their poor performance, ensures the transparency of the problem, and helps the dispatched personnel realize the areas that need improvement. Through direct communication, the dispatched personnel can feel the company's attention to their development, which enhances the dispatched personnel's trust and sense of belonging to the company. The interview provides the dispatched personnel with improvement directions and suggestions, helping them to develop practical action plans, thereby improving subsequent work performance.
[0178] Then, in step 644, a personalized improvement plan is developed for the poor dispatched personnel. Based on the specific problems identified in step 643, the supervisor and the dispatched personnel jointly develop a personalized improvement plan. The plan should clearly define the improvement goals, steps, and timetable, and set specific measurable indicators (such as improving a certain skill, completing tasks on time, etc.). The improvement plan should match the actual work ability and responsibilities of the dispatched personnel, avoid setting goals that are too high or too low, and arrange corresponding training courses based on the skills deficiencies or other problems shown by the dispatched personnel in the interview. The training content can include professional skills training, time management training, communication skills training, etc.
[0179] Training can be conducted in a variety of forms, including internal training, external training, and online learning, to ensure that dispatched personnel can acquire the knowledge and skills needed for actual work. Personalized improvement plans and targeted training help dispatched personnel make up for their inadequacies and improve their performance in tasks. By formulating clear improvement plans, dispatched personnel can gradually improve their work capabilities, increase their self-confidence and work motivation. Continuous training and improvement plans ensure that dispatched personnel will not repeat the same mistakes, and promote their continuous progress and growth.
[0180] Finally, through step 635, we will identify and track the dispatched personnel who have not shown significant improvement after multiple improvement plans and trainings, or who have shown a passive and uncooperative attitude during the improvement process, to see whether they have completed the improvement plan, whether they have improved after training, whether their attitude is correct, etc. For dispatched personnel who are identified as improper or whose improvement is ineffective, we will issue a formal written warning. The warning content should clearly point out the specific reasons why the dispatched personnel did not meet the standards, as well as the possible consequences (such as salary penalties, demotion, and dismissal). The written warning should be filed as a basis for subsequent decision-making, and the dispatched personnel should be informed of the deadline and requirements for improvement.
[0181] If the dispatched personnel still fail to make significant improvements after receiving a written warning, further punitive measures may be taken according to company regulations, such as deducting bonuses, reducing wages, or ultimately dismissing them. These measures are aimed at maintaining team discipline, ensuring the smooth execution of the project, and reminding other dispatched personnel to comply with work requirements. Through written warnings and further punitive measures, the company's zero-tolerance attitude towards poor performance is made clear, team discipline and work efficiency are maintained, and warnings and punitive measures also serve as a warning to other dispatched personnel, prompting them to take their work more seriously. By dealing with uncooperative or persistently poorly performing dispatched personnel, the overall performance of the team is ensured not to be affected by individual personnel, thereby maintaining the quality and progress of the project.
[0182] At present, the evaluation methods for dispatched workers in various fields are diverse but too simple, lacking an effective tracking and feedback mechanism, which leads to performance appraisals often focusing only on results and ignoring processes. This not only wastes the company's human resources, but may also cause resistance from dispatched workers, which is not conducive to the stable development of the company. Although human resource costs continue to rise, the company's overall performance is declining. Many companies attach importance to human resource management, but relatively ignore the performance appraisal of dispatched workers, resulting in a large number of dispatched workers. Through the effective evaluation method in this implementation, it is possible to solve the problem that the current labor dispatch management methods in various fields are too simple, and ensure that dispatched workers can have a specific positive work attitude and receive corresponding labor remuneration.
[0183] like Figure 2 As shown, a landscaping labor dispatch management system includes:
[0184] Information collection module 201: used to obtain landscaping project demand information;
[0185] On-demand allocation module 202: It is used to collect personnel information, form multiple groups, and assign groups according to the landscaping project demand information; map the executable tasks to each group to allocate the landscaping demand tasks to each execution group;
[0186] Real-time monitoring module 203: used to monitor the work progress and completion effect of each group after assignment in real time;
[0187] The quality assessment module 204 is used to assess the work progress and completion effect to obtain an assessment result;
[0188] Feedback adjustment module 205: It is used to adjust the labor dispatch team members according to the evaluation result feedback.
[0189] An embodiment of the present invention further provides an electronic device including a memory, a processor, and a landscaping labor dispatch management method program stored in the memory and executable on the processor based on a landscaping labor dispatch management method and system. When the landscaping labor dispatch management method program is executed by the processor, the steps of the landscaping labor dispatch management method are implemented. All implementation methods in the above method embodiments are applicable to this embodiment and can achieve the same technical effect.
[0190] Those skilled in the art will also appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered beyond the scope of the present invention.
[0191] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0192] In the embodiments provided by the present invention, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0193] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0194] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.
[0195] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art, or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, server, or network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: various media that can store program codes, such as USB flash drives, mobile hard disks, ROM, RAM, magnetic disks, or optical disks.
[0196] In addition, it should be pointed out that in the apparatus and method of the present invention, it is obvious that each component or each step can be decomposed and / or recombined. These decompositions and / or recombinations should be regarded as equivalent schemes of the present invention. Moreover, the steps of performing the above series of processing can naturally be performed in chronological order according to the order of description, but it is not necessary to perform them in chronological order, and some steps can be performed in parallel or independently of each other. For those of ordinary skill in the art, it can be understood that all or any steps or components of the method and apparatus of the present invention can be implemented in hardware, firmware, software or a combination thereof in any computing device (including processors, storage media, etc.) or a network of computing devices, which can be achieved by those of ordinary skill in the art using basic programming skills after reading the description of the present invention.
[0197] Therefore, the purpose of the present invention can also be achieved by running a program or a group of programs on any computing device. The computing device can be a well-known general device. Therefore, the purpose of the present invention can also be achieved by simply providing a program product containing a program code that implements the method or device. That is to say, such a program product also constitutes the present invention, and the storage medium storing such a program product also constitutes the present invention. Obviously, the storage medium can be any well-known storage medium or any storage medium developed in the future. It should also be pointed out that in the device and method of the present invention, it is obvious that each component or each step can be decomposed and / or recombined. These decompositions and / or recombinations should be regarded as equivalent schemes of the present invention. In addition, the steps of performing the above-mentioned series of processing can naturally be performed in chronological order according to the order of description, but it is not necessary to perform them in chronological order. Some steps can be performed in parallel or independently of each other.
[0198] The above describes an embodiment of the present invention, but this embodiment is not limited to the above-mentioned specific implementation mode. The above-mentioned specific implementation mode is merely illustrative and not restrictive. Under the guidance of this embodiment, ordinary technicians in this field can also make more forms of equivalent embodiments, all of which are within the protection of this embodiment.
[0199] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention.
Claims
1. A landscaping labor dispatch management method, It is characterized in that The following steps are involved: Obtain landscaping project demand information and convert it into executable tasks, including: Repair branches X l ; Watering and fertilization G j ; Planting new varieties Z x ; Treat weeds C l ; Pest control c ; Collect personnel information and form multiple teams based on the personnel information, including: pre-organizing n dispatched personnel, marking each person as R 1 , R 2 , …, R n , according to the number of personnel and preset information, m groups are set up, and the groups are marked as Z 1 , Z 2 , …, Z m ,Right now ; In the formula, x j i Indicates whether the i-th person is assigned to the j-th group, where i is 1, 2, ..., n, and j is 1, 2, ..., m; pass: ; In the formula, d k represents the number of personnel required for the kth service, thereby constraining the number of personnel assigned to different services to be equal to the personnel demand of the service; Mapping the executable tasks to each group to allocate gardening demand tasks to each execution group specifically includes: According to the complexity and professional requirements of each executable task, a team with high skill and experience adaptability is selected for docking. In the formula, PD is the adaptability score, Wi is is the executable task weight, S ij represents the skill score of the group on the task, and n is the number of groups; Real-time monitoring of the work progress and completion results of each group after assignment; Evaluate the work progress and completion results to obtain evaluation results; Adjust the labor dispatch team personnel based on the evaluation feedback.
2. A landscaping labor dispatch management method according to claim 1, It is characterized in that Collect personnel information and form multiple groups based on the personnel information, including: Collect information about people’s age, size, gender, health, and experience; Assign personnel to form teams based on personnel information.
3. A landscaping labor dispatch management method according to claim 2, It is characterized in that Assign personnel to form teams based on personnel information, including: The preset weight of experience value is 1; the weight of age is 2; the weight of BMI body mass index is 1; By standardizing each weighted feature value and setting the experience score S1, the highest experience is 10 years and the lowest is 1 year, and the score is: ; Set the age score S2, then the scores from high to low for the age range of 30-50 are: ; BMI score S3, the index range is 18.5-24.9 from high to low scores: ; Then through: Where S core Expressed as a score, W 1 ,W 2 ,W 3 Represents the weights of experience value, age, and BMI body mass index, S 1 ,S 2 ,S 3 The standardized thresholds representing the experience value, age and BMI of the assigned personnel are set between 0 and 1, thereby obtaining the individual scores of the personnel; After obtaining the scores of each weight, the labor teams are formed in order from high to low according to the scores, namely, senior team, intermediate team, secondary team and primary team; Allocations are made based on the formed senior, intermediate, secondary and primary groups according to the landscaping needs.
4. A landscaping labor dispatch management method according to claim 3, It is characterized in that Map the executable tasks to each group to assign gardening demand tasks to each execution group, including: According to different types of greening requirements, the group resource matching requirements can be expressed as a four-tuple: ; In the formula, T represents the set of groups participating in the labor service, which is expressed as T={senior group, intermediate group, secondary group, primary group}; VM′ represents the set of greening needs of the garden, which is VM′={X l , G j , Z x , C l , F c }; G represents the preciousness of different plant species required for greening, G={top, advanced, excellent, ordinary}; qos represents the service matching degree set between the labor team and greening needs, expressed as λ={λ 1 ,λ 2 ,…,λ n },λ n Represents the matching of a labor group with landscaping needs.
5. A landscaping labor dispatch management method according to claim 4, It is characterized in that Real-time monitoring of the work progress and completion results of each group after assignment, including: Break down the team's overall work into multiple subtasks and assign them to each team member. Each subtask has a preset deadline and outcome definition. Acquire individual targets through real-time monitoring by deploying monitoring equipment; According to the individual goals of the personnel, when executing subtasks, the task status is tracked and updated in real time, including: "not started", "in progress", "completed", so as to obtain real-time progress data; Obtain personnel work progress and personnel attendance based on real-time progress data to obtain individual performance data.
6. A landscaping labor dispatch management method according to claim 5, It is characterized in that Evaluate the work progress and completion results to obtain evaluation results, including: Based on the individual performance data, quality inspection standards are established, including: punctual completion of assigned tasks, garden vegetation repair effects, reasonable greening layout and environmental maintenance. Quality inspections are conducted after the team's overall work tasks are completed to obtain inspection results; According to the inspection results, through: Where S overall is the quality score, n is the number of tasks completed by the personnel; S i The performance summary of i tasks is obtained, and the quality score of individual task completion is obtained to obtain the evaluation result.
7. A landscaping labor dispatch management method according to claim 6, It is characterized in that Adjust the labor dispatch team members based on the evaluation results, including: The evaluation results are compared with the preset mass point standards by: ; In the formula, A is the comprehensive deviation score, F is the quality deviation score, and G is the attendance deviation score, in order to obtain the deviation between the actual task completion and the expected result; According to the expected deviation, the comparison standard is set: when A is within 10%, it is excellent; when A is 21%-20%, it is good; when A is 21%-30%, it is passing; when A exceeds 31%, it is poor; According to the comprehensive deviation scores, they are sorted from high to low, q excellent personnel and h poor personnel are selected, and corresponding incentive and reward and punishment measures are formulated.
8. A landscaping labor dispatch management method according to claim 7, It is characterized in that According to the comprehensive deviation score, the ranking is from high to low, n excellent personnel and n poor personnel are selected, and corresponding incentive and reward measures are formulated, including: Give bonuses to q outstanding personnel as encouragement and provide career development opportunities: promotion, expansion of responsibilities or participation in higher-level landscaping projects; Publicly recognize outstanding personnel and provide opportunities for advanced training or seminars; Conduct one-on-one interviews with h poor performers, clearly identify the specific reasons for their poor performance, and negotiate improvement plans; For those who have repeatedly failed to make improvements or have a bad attitude, a formal written warning will be issued and they will be informed that they will face salary penalties or dismissal.
9. A landscaping labor dispatch management system, It is characterized in that The system sets up an electronic device including a memory, a processor and a landscaping labor dispatch management method program stored in the memory and executable on the processor. When the landscaping labor dispatch management method program is executed by the processor, the steps of the landscaping labor dispatch management method as described in any one of claims 1-8 are implemented.
10. A landscaping labor dispatch management system according to claim 9, It is characterized in that The system includes: Information collection module: It is used to obtain landscaping project demand information; On-demand allocation module: It is used to collect personnel information, form multiple teams, and assign teams according to the demand information of the landscaping project; map the executable tasks to each team to allocate the gardening demand tasks to each execution team; Real-time monitoring module: It is used to monitor the work progress and completion results of each group in real time after assignment; Quality assessment module: used to assess the work progress and completion effect to obtain assessment results; Feedback adjustment module: It is used to adjust the labor dispatch team members according to the evaluation results.
Citation Information
Patent Citations
Labor dispatch data information management method and system and storage medium
CN115204839A
Cucumber substrate cultivation implementation personnel task assignment management algorithm
CN116468245A
Cleaning labor dispatch data information management method and system and storage medium
CN118552007A
Car insurance claim settlement repairman intelligent dispatching method based on multivariate factor decision algorithm
CN118747683A
Cited By
Construction labor service human resource management method and system
CN119623983A
Human resource management method and system
CN119919012A
Intelligent personnel scheduling method and system based on multi-factor comprehensive scoring
CN121436595A