Gridding power supply service management method and system
Through grid power supply service management methods, real-time monitoring and analysis of power consumption information, combined with industrial production conditions, dynamically adjusting power supply strategies, the problem of power supply imbalance in the existing technology is solved, the power utilization efficiency and system stability are improved, and the power utilization efficiency and system stability are reduced. Cost and economic losses.
Patent Information
- Application Number
- CN202411159080.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-19
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing power supply service management mainly relies on manual inspections, and cannot monitor and solve power supply imbalances in real time and comprehensively, resulting in production interruptions and economic losses.
The grid power supply service management method is adopted to monitor and analyze power consumption information in real time, combine industrial production situations, and dynamically adjust power supply strategies, give priority to ensuring the power supply of emergency production lines, and reduce unnecessary power waste and power outage losses.
Real-time monitoring and precise scheduling of the power supply system are realized, power utilization efficiency is improved, personnel participation and costs are reduced, economic losses caused by power outages are reduced, and the stability of the power system is enhanced.
Smart Images

Figure CN118982261A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of power supply service management, and in particular to a grid-based power supply service management method and system. Background Art
[0002] Electricity is the main energy source for factory production, and a stable and reliable power supply is the key to ensuring the continuity of factory production. Once the power supply system fails, it may cause the production line to stop, seriously affecting production progress and product quality.
[0003] On this basis, it is necessary to provide power supply service management for the factory's electricity. However, the current common power supply service management is only manual inspection to achieve daily inspection and maintenance. This method is time-consuming and labor-intensive. Due to the strong subjectivity of humans, there is no way to ensure that each inspection can achieve the purpose of comprehensive supervision. Therefore, the occurrence of power supply system failures cannot be avoided. Summary of the invention
[0004] The present application provides a grid-based power supply service management method and system to solve the above-mentioned problems.
[0005] In a first aspect, the present application provides a grid-based power supply service management method, comprising: Acquire real-time power consumption information, analyze the real-time power consumption information, and determine whether there is a power supply imbalance at the current moment; If there is a power supply imbalance, obtain and analyze the industrial production situation to determine whether there is any production action in any grid. If so, determine several current production lines based on the grid location; Obtaining the production tasks of each current production line, and determining the production urgency according to the production tasks; According to the production urgency, the power supply strategy is adjusted to solve the power supply imbalance problem.
[0006] Through this solution, real-time monitoring and analysis of real-time power consumption information can be carried out to promptly identify power supply imbalance problems. Combined with the analysis of industrial production conditions, the grids where production actions exist can be accurately located to determine the corresponding production lines. Dynamically adjust the power supply strategy according to the urgency of production, reasonably adjust the power supply strategy, give priority to ensuring the power supply of emergency and important production, ensure the stable operation of key facilities, and reduce economic losses caused by power outages. By rationally allocating power resources, unnecessary waste can be reduced, power utilization efficiency can be improved, and sustainable development can be promoted. Compared with existing technologies, dynamic and real-time monitoring can improve power supply maintenance efficiency, reduce personnel participation, and reduce time and labor costs.
[0007] Optionally, analyzing the real-time power consumption information to determine whether there is a power supply imbalance at the current moment includes: Obtain the production tasks and unit production volume of each current production line; Determine the electricity demand per unit time based on production tasks and unit production volume; According to the production task and the power demand within the unit time, the total power consumption within the preset time period is obtained; Obtaining the unit power supply of the power supply facility, and predicting the power supply within a preset time period based on the unit power supply; Calculate the difference between electricity supply and demand within a preset period based on total electricity consumption and power supply; The power supply and demand difference is compared with a preset supply and demand threshold, and based on the comparison result, it is determined whether there is a power supply imbalance at the current moment.
[0008] Through this solution, the power supply principle and influencing factors of power supply facilities are deeply analyzed. Compared with the existing technology, the power supply in the preset period is predicted more accurately, making the prediction results more realistic. It provides strong support for power dispatching and management, optimizes the use of power resources, and avoids power waste or shortage. It timely discovers and solves potential power supply problems, thereby improving the overall stability of the power system.
[0009] Optionally, predicting the power supply amount within a preset time period according to the unit power supply amount includes: Analyzing the power supply facilities to determine the power supply principle of the power supply facilities; According to the power supply principle, determining factors affecting power supply; Based on the influencing factors, predict the current factory impact information within the preset time period; Analyze the current factory impact information to determine the unit power supply impact within a preset time period; The power supply amount within a preset time period is predicted according to the unit power supply amount and the unit power supply impact.
[0010] Through this solution, the power supply principle and influencing factors of power supply facilities are deeply analyzed. Compared with the existing technology, the power supply in the preset period is predicted more accurately, making the prediction results more realistic. It provides strong support for power dispatching and management, optimizes the use of power resources, and avoids power waste or shortage. It timely discovers and solves potential power supply problems, thereby improving the overall stability of the power system.
[0011] Optionally, determining the production urgency according to the production task includes: Analyze the production tasks and determine the production volume and delivery time of each current production line; According to the production volume and the delivery time, determine the production urgency, refer to the following formula: ; in, Indicates The production urgency of each production task; Indicates The production volume of each production task; Indicates The delivery time of each production task; express The mean of express The standard deviation of express The mean of express The standard deviation of .
[0012] Through this solution, the production tasks are analyzed, the production volume and delivery time of each production line are accurately determined, and the formula is designed based on the production volume and delivery time to determine the production urgency, improve the calculation efficiency, reduce the cost of manual analysis, reduce the subjectivity and uncertainty of human judgment, and make the results more objective and fair. It is convenient to give priority to tasks with high urgency when power supply imbalance occurs in the later stage, ensure that important tasks are completed on time, and make production allocation more flexible to meet production needs.
[0013] Optionally, adjusting the power supply strategy according to the production urgency includes: Obtain production equipment information for each current production line; Determine the rated power of each production equipment according to the production equipment information; According to the power supply in the preset time period, the rated power and the production urgency, the power supply of each current production line in the preset time period is determined to obtain a power supply strategy.
[0014] Through this solution, the rated power determined based on the production equipment information ensures that the power supply based on the production equipment can guarantee the normal operation of the production equipment. In addition, the power supply can be adjusted considering the production urgency, so that the power demand of high-urgency production tasks can be prioritized. This helps enterprises to quickly adjust production plans when facing urgent orders or emergencies, ensure on-time delivery of products, and maintain customer satisfaction.
[0015] Optionally, the power supply amount of each current production line within the preset time period is determined according to the power supply amount within the preset time period, the rated power and the production urgency, referring to the following formula: ; in, Indicates that within the preset time period The power supply of the current production line; Indicates the number of The power required for the current production line; Indicates The production urgency of each production task; Indicates the power supply within the preset time period.
[0016] Through this solution, the design formula determines the power supply of each current production line within the preset period according to the power supply, rated power and production urgency, ensuring that the distribution of power supply is more reasonable and scientific. Through formula calculation, the power supply can be allocated more accurately to avoid waste and overuse of resources. It also helps to deal with uncertain factors in the production process and ensure that production tasks can be completed on time.
[0017] Optionally, the power supply amount within a preset time period is predicted according to the unit power supply amount and the unit power supply impact, with reference to the following formula: ; in, Indicates the power supply within a preset period of time; Indicates The original power supply capacity of each power supply facility within a preset time period; Indicates the number of influencing factors; Indicates The actual value of each influencing factor; Indicates The weight of the influencing factors; Indicates The unit power supply impact coefficient of each power supply facility.
[0018] Through this scheme, the original power supply capacity of the power supply facilities in the preset period, the number of influencing factors, and the corresponding weights of the influencing factors are considered, and the formula is designed to predict the power supply in the preset period, which can fully reflect the potential impact of various factors on the power supply. In addition, the unit power supply influence coefficient is introduced to more accurately predict the power supply changes of each power supply facility in the preset period, thereby obtaining a more accurate prediction of the overall power supply.
[0019] Optionally, determining the production urgency according to the production volume and the delivery time includes: Determining a power limit level within the preset time period according to the power supply within the preset time period; Get the production records of each current production line; Determine several production processes of each current production line according to the production records; Determine the material preparation status of each current production line according to the production task of each current production line and the unit production volume; Obtain historical operation data of each production process; Analyze the historical operation data to obtain the unit production time of each production process; For each production process, analyze the unit production time of the two production processes closest to any production process to obtain the production efficiency of the two production processes closest to each other; Determine the urgency of running any production process based on the production efficiency; The production urgency is determined according to the power restriction level, the material preparation situation, the operation urgency, the production volume and the delivery time.
[0020] Through this solution, we can conduct an in-depth analysis of the unit production time and production efficiency of each production process to ensure that key and urgent production processes are given priority. Comprehensively consider the power limit level, material preparation, operation urgency, production volume and delivery time, determine the production urgency, optimize the production process and resource allocation, reduce unnecessary waste and waiting time, and help reduce production costs and improve overall profitability.
[0021] Optionally, adjusting the power supply strategy according to the production urgency includes: According to the electricity supply and demand difference, determine the number of production lines to be adjusted at the current moment; Determine whether the number of production lines is greater than 1. If the number of production lines is greater than 1, sort the production urgency of all current production lines, and determine the last production line according to the sorting result; Determining the unit power consumption of the last production line according to the operation data of the last production line; Determine whether stopping the last production line from operating solves the power supply imbalance according to the unit power consumption and the power supply-demand difference; If the problem is not solved, the production urgency of all the remaining current production lines will be re-sorted, and the second last production line will be determined and stopped according to the result of the re-sorting; If the number of the production lines is less than 1, then according to the sorting result, determine the emergency production line with the strongest production urgency, and according to the operation urgency, analyze several production processes of the emergency production line, determine the process characteristics of each production process, and determine the non-stop links of each current production line according to the process characteristics; Determine the non-stoppable process based on the non-stoppable link; and determine the stoppable process based on the non-stoppable process; Obtain the unit start-stop power loss of each process that can be stopped; According to the start-stop power loss, determine the total power loss of each process that can be stopped within a preset time period; According to the non-stoppable links and the total power loss of each stoppable process, the power supply strategy is adjusted to solve the power supply imbalance.
[0022] Through this solution, when the number of production lines is greater than 1, production lines with lower production urgency are stopped first to minimize the impact on the overall production schedule and customer delivery. When the number of production lines is less than 1, the production process and the links that cannot be stopped are analyzed in depth, and the processes that can be stopped are accurately determined to reduce power consumption while ensuring key production. At the same time, based on the analysis of the total power loss of the links that cannot be stopped and each process that can be stopped, a more accurate and effective power supply strategy is formulated to optimize the allocation of power resources. By calculating the unit start-stop power loss and total power loss of each process that can be stopped, unnecessary power loss and economic loss can be minimized when adjusting production.
[0023] In a second aspect, the present application provides a grid-based power supply service management system, including: An imbalance judgment module is used to obtain real-time power consumption information, analyze the real-time power consumption information, and judge whether there is a power supply imbalance at the current moment; The line determination module is used to obtain and analyze the industrial production situation if there is a power supply imbalance, determine whether there is a production action in any grid, and if so, determine several current production lines according to the grid location; A degree analysis module is used to obtain the production tasks of each current production line and determine the production urgency based on the production tasks; A strategy adjustment module is used to adjust the power supply strategy to solve the power supply imbalance problem according to the production urgency 。
[0024] Optionally, the imbalance judgment module is specifically used to: Obtain the production tasks and unit production volume of each current production line; Determine the electricity demand per unit time based on production tasks and unit production volume; According to the production task and the power demand within the unit time, the total power consumption within the preset time period is obtained; Obtaining the unit power supply of the power supply facility, and predicting the power supply within a preset time period based on the unit power supply; Calculate the difference between electricity supply and demand within a preset period based on total electricity consumption and power supply; The power supply and demand difference is compared with a preset supply and demand threshold, and based on the comparison result, it is determined whether there is a power supply imbalance at the current moment.
[0025] Optionally, the imbalance judgment module is specifically used to: Analyzing the power supply facilities to determine the power supply principle of the power supply facilities; According to the power supply principle, determining factors affecting power supply; Based on the influencing factors, predict the current factory impact information within the preset time period; Analyze the current factory impact information to determine the unit power supply impact within a preset time period; The power supply amount within a preset time period is predicted according to the unit power supply amount and the unit power supply impact.
[0026] Optionally, the degree analysis module is specifically used to: Analyze the production tasks and determine the production volume and delivery time of each current production line; According to the production volume and the delivery time, determine the production urgency, refer to the following formula: ; in, Indicates The production urgency of each production task; Indicates The production volume of each production task; Indicates The delivery time of each production task; express The mean of express The standard deviation of express The mean of express The standard deviation of .
[0027] Optionally, the policy adjustment module is specifically used to: Obtain production equipment information for each current production line; Determine the rated power of each production equipment according to the production equipment information; According to the power supply in the preset time period, the rated power and the production urgency, the power supply of each current production line in the preset time period is determined to obtain a power supply strategy.
[0028] Optionally, the policy adjustment module is specifically used to: ; in, Indicates that within the preset time period The power supply of the current production line; Indicates the number of The power required for the current production line; Indicates The production urgency of each production task; Indicates the power supply within the preset time period.
[0029] Optionally, the imbalance judgment module is specifically used to: ; in, Indicates the power supply within a preset period of time; Indicates The original power supply capacity of each power supply facility within a preset time period; Indicates the number of influencing factors; Indicates The actual value of each influencing factor; Indicates The weight of the influencing factors; Indicates The unit power supply impact coefficient of each power supply facility.
[0030] Optionally, the degree analysis module is specifically used to: Determining a power limit level within the preset time period according to the power supply within the preset time period; Get the production records of each current production line; Determine several production processes of each current production line according to the production records; Determine the material preparation status of each current production line according to the production task of each current production line and the unit production volume; Obtain historical operation data of each production process; Analyze the historical operation data to obtain the unit production time of each production process; For each production process, analyze the unit production time of the two production processes closest to any production process to obtain the production efficiency of the two production processes closest to each other; Determine the urgency of running any production process based on the production efficiency; The production urgency is determined according to the power restriction level, the material preparation situation, the operation urgency, the production volume and the delivery time.
[0031] Optionally, the policy adjustment module is specifically used to: According to the electricity supply and demand difference, determine the number of production lines to be adjusted at the current moment; Determine whether the number of production lines is greater than 1. If the number of production lines is greater than 1, sort the production urgency of all current production lines, and determine the last production line according to the sorting result; Determining the unit power consumption of the last production line according to the operation data of the last production line; Determine whether stopping the last production line from operating solves the power supply imbalance according to the unit power consumption and the power supply-demand difference; If the problem is not solved, the production urgency of all the remaining current production lines will be re-sorted, and the second last production line will be determined and stopped according to the result of the re-sorting; If the number of the production lines is less than 1, then according to the sorting result, determine the emergency production line with the strongest production urgency, and according to the operation urgency, analyze several production processes of the emergency production line, determine the process characteristics of each production process, and determine the non-stop links of each current production line according to the process characteristics; Determine the non-stoppable process based on the non-stoppable link; and determine the stoppable process based on the non-stoppable process; Obtain the unit start-stop power loss of each process that can be stopped; According to the start-stop power loss, determine the total power loss of each process that can be stopped within a preset time period; According to the non-stoppable links and the total power loss of each stoppable process, the power supply strategy is adjusted to solve the power supply imbalance. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, a brief introduction will be given below to the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.
[0033] Figure 1 A schematic diagram of an application scenario provided for an embodiment of the present application; Figure 2 A flowchart of a grid power supply service management method provided in one embodiment of the present application; Figure 3 A schematic diagram of the structure of a grid-based power supply service management system provided in one embodiment of the present application. DETAILED DESCRIPTION
[0034] In order to make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0035] In addition, the term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article, unless otherwise specified, generally means that the associated objects before and after are in an "or" relationship.
[0036] The embodiments of the present application are further described in detail below in conjunction with the drawings in the specification.
[0037] Electricity is the main energy source for factory production, and a stable and reliable power supply is the key to ensuring the continuity of factory production. Once the power supply system fails, it may cause the production line to stop, seriously affecting production progress and product quality.
[0038] On this basis, it is necessary to provide power supply service management for the factory's electricity. However, the common power supply service management currently only involves manual inspections to achieve daily inspections and maintenance. This method is time-consuming and labor-intensive. Due to the strong subjectivity of humans, there is no way to ensure that each inspection can achieve a comprehensive supervision purpose. Therefore, power supply system failures cannot be avoided. In the prior art, power supply imbalance often occurs. In order to solve the problem of power supply imbalance, the conventional operation is that the power supply department related to the power grid will require the addition of equipment, such as energy storage equipment, to ensure that the normal operation of the factory is not affected when the power supply is unbalanced. However, this method will increase the operating costs of the factory. For electricity users, how to ensure the normal operation of the factory in the case of power supply imbalance without increasing costs is what every factory electricity user hopes to achieve.
[0039] Based on this, the present application provides a grid-based power supply service management method and system to monitor and analyze real-time power consumption information in real time, and promptly discover power supply imbalance problems. Combined with the analysis of industrial production conditions, the grid where production actions exist is accurately located, and the corresponding production lines are determined. Dynamically adjust the power supply strategy according to the urgency of production, reasonably adjust the power supply strategy, give priority to guaranteeing the power supply of emergency and important production, ensure the stable operation of key facilities, and reduce economic losses caused by power outages. By reasonably allocating power resources, unnecessary waste can be reduced, power utilization efficiency can be improved, and sustainable development can be promoted. Compared with the prior art, dynamic and real-time monitoring can improve the efficiency of power supply maintenance, reduce personnel participation, and reduce time and labor costs.
[0040] Figure 1A schematic diagram of an application scenario provided for the present application. When it is necessary to manage the power supply service of the factory, the method provided by the present application can be used. Specifically, the method provided by the present application is applied to any server, and the server interacts with the power supply facilities and the power-consuming equipment. First, the factory area can be divided into grids according to the equipment and location of each production line, so as to achieve targeted management of the production line and facilitate better adjustment. Obtain and analyze the real-time power consumption information of the power-consuming equipment to determine whether there is a power supply imbalance. If so, obtain and analyze the industrial production situation to determine whether there is a production action in each grid. If so, obtain the corresponding current production lines, obtain the corresponding production tasks, analyze the production urgency, and then obtain the current power supply strategy according to the production urgency and send it to the power supply facilities for power supply adjustment to solve the problem of power supply imbalance and avoid the potential safety hazards caused by power supply imbalance. These processes do not require human participation, saving manpower, material resources and time costs.
[0041] For specific implementation methods, please refer to the following embodiments.
[0042] Figure 2 This is a flowchart of a grid power supply service management method provided in an embodiment of the present application. The method of this embodiment can be applied to the server in the above scenario. Figure 2 As shown, the method includes: S201. Acquire real-time power consumption information, analyze the real-time power consumption information, and determine whether there is a power supply imbalance at the current moment.
[0043] Real-time power consumption information can be understood as the power consumption and power consumption status of the equipment currently using power in the factory, etc. It can be collected through sensors and monitoring equipment.
[0044] Power supply imbalance can be understood as the unbalanced state between power supply and power demand in the power system. It may be caused by too many power-consuming devices, or it may be due to a failure of power supply facilities that causes the power supply to be unable to balance with demand.
[0045] Specifically, smart meters and various sensors are installed at key nodes in the factory to monitor current, voltage, power and other parameters in real time, so as to obtain real-time power consumption information. Then, the real-time power consumption information is cleaned and converted into electrical signals or digital signals to facilitate subsequent data analysis.
[0046] Then, data analysis techniques (such as time series analysis, data mining, machine learning, etc.) are used to conduct in-depth analysis of real-time power consumption data, such as analyzing current load changes, regional power consumption differences in each grid, etc. Based on the above analysis results, it is determined whether power consumption and power generation remain relatively stable. If they can remain relatively stable, it is considered that there is no power supply imbalance. If they cannot remain relatively stable, it can be considered that there is a power supply imbalance.
[0047] S202. If there is a power supply imbalance, obtain and analyze the industrial production situation to determine whether there is any production action in any grid. If so, determine several current production lines based on the grid location.
[0048] The industrial production situation can be understood as the current production status of the factory, which may include which equipment is in production, which equipment is not in operation, information on items being produced, etc.
[0049] Specifically, since the factory has been divided into grids, each grid can be set as a key node in the above steps. At this time, smart meters and various sensors can be set for each grid to determine which devices in the grid are in operation. At this time, if it is determined through the above step S201 that there is a power supply imbalance, the source of the data is determined through the data collected by the devices set in each grid, so as to determine the running devices, and thus determine which grids have production actions. That is, if the devices in the corresponding grid can collect data, it can be considered that there are devices in operation in this grid, and it can also be considered that there are production actions in the grid. Therefore, according to the above grid division method, several production lines in production are determined.
[0050] S203, obtaining the production tasks of each current production line, and determining the production urgency according to the production tasks.
[0051] Production tasks may include information about the items being produced, production volume, delivery time, etc.
[0052] The degree of production urgency can be determined by production volume and delivery time. For example, if the production volume is large and the delivery time is relatively early, it can be considered that the production is more urgent and the degree of production urgency is stronger. If the production volume is small and the delivery time is relatively late, it can be considered that the production is not urgent and, accordingly, the degree of production urgency is weaker.
[0053] S204. According to the production urgency, adjust the power supply strategy to solve the power supply imbalance problem.
[0054] The urgency of production is different, and the urgency of the demand for electricity at the current moment will also be different. Therefore, in order to avoid the safety hazards caused by power supply imbalance, the production lines in each grid can be adjusted according to the production urgency. If the production urgency is weak, it can be stopped at the current moment to ensure that the production line with a strong production urgency can successfully complete the final delivery. In the specific implementation method, if the power supply imbalance is serious, the startup sequence of different processing equipment in the same production line can also be controlled. The above methods can all be considered as different power supply strategies obtained according to the production urgency.
[0055] The power supply strategy is adjusted according to the production urgency to solve the problem of power supply imbalance. In some implementations, the actual power supply capacity of the power supply facilities can also be considered while considering the production urgency, so as to reduce the waste of electric energy and maximize the utilization of energy.
[0056] Through the solution provided by this application, real-time monitoring and analysis of real-time electricity consumption information can be carried out to promptly discover power supply imbalance problems. Combined with the analysis of industrial production conditions, the grids where production actions exist can be accurately located to determine the corresponding production lines. Dynamically adjust the power supply strategy according to the degree of production urgency, reasonably adjust the power supply strategy, give priority to ensuring the power supply of emergency and important production, ensure the stable operation of key facilities, and reduce economic losses caused by power outages. By rationally allocating power resources, unnecessary waste can be reduced, power utilization efficiency can be improved, and sustainable development can be promoted. Compared with the existing technology, dynamic and real-time monitoring can improve the efficiency of power supply maintenance, reduce personnel participation, and reduce time and labor costs.
[0057] In some embodiments, the production tasks and unit production volume of each current production line are obtained; the electricity demand per unit time is determined based on the production tasks and unit production volume; the total electricity consumption within a preset time period is obtained based on the production tasks and the electricity demand per unit time; the unit power supply of the power supply facility is obtained, and the power supply within a preset time period is predicted based on the unit power supply; the electricity supply and demand difference within the preset time period is calculated based on the total power consumption and the power supply; the electricity supply and demand difference is compared with a preset supply and demand threshold, and based on the comparison result, it is determined whether there is a power supply imbalance at the current moment.
[0058] Unit production volume can be understood as the amount of items produced per production line per unit time. For example, if a production line includes loading, manufacturing, and sealing, the unit production volume can include the unit loading volume in the loading process, the unit manufacturing volume in the manufacturing process, and the unit sealing volume in the sealing process.
[0059] The prediction period can be understood as a time period set in advance for power supply and demand analysis and prediction. This time period can be several hours, a day, a week, a month or longer, depending on the purpose and needs of the analysis, and is not limited in this embodiment.
[0060] The preset supply and demand threshold can be understood as a numerical limit set in advance for determining whether the power supply and demand are balanced. When the actual power supply and demand difference exceeds this limit, the power supply status is considered to be unbalanced; otherwise, the power supply status is considered to be balanced or within an acceptable range.
[0061] Specifically, a database is pre-set to store production tasks. When a production task is needed, it can be directly extracted from the database. In the specific implementation method, this database can be dynamically updated. When a production task is completed, it can be deleted according to the delivery time in the production task. For example, after the delivery time is reached, it is determined whether the production task has been delivered. If it has been delivered, it is directly deleted. In the specific implementation method, the production tasks that have been completed can also be transferred. For example, a completed task database is pre-set to store the details of the completed tasks, such as daily task progress, task time and other data.
[0062] The unit production volume of each device in each production line is analyzed through the information stored in the above completed task database. Then, based on the current production tasks of the factory and the unit production volume of each device, the total power consumption of the running equipment per unit time is determined to obtain the power demand per unit time.
[0063] Then, based on the production tasks and the electricity demand per unit time, the total electricity consumption within the preset time period is calculated. Through real-time monitoring of the power supply facilities, the unit power supply of the power supply facilities is obtained, and the power supply within the preset time period is predicted based on the unit power supply. Then, the total power consumption and the predicted power supply are combined to obtain the difference between the two, that is, the power supply and demand difference. Then, the power supply and demand difference is compared with the preset supply and demand threshold to determine whether there is a power supply imbalance. In a specific implementation method, if the preset supply and demand threshold is exceeded, it can be considered that there is a power supply imbalance, otherwise, it does not exist.
[0064] Through the solution provided by this embodiment, the production tasks, unit production volume and unit power supply of the production line are obtained in real time, and then the power demand per unit time is calculated in real time, so as to obtain the total power consumption and power supply within the preset time period, and realize real-time monitoring of power supply and demand. The relationship between production tasks, unit production volume and power demand is deeply analyzed to achieve accurate prediction, and the total power consumption and power supply within the preset time period are obtained, providing an accurate basis for power dispatching. The power supply and demand difference within the preset time period is calculated and compared with the preset supply and demand threshold, so as to timely discover power supply imbalance and avoid safety hazards.
[0065] In some embodiments, power supply facilities are analyzed to determine the power supply principle of the power supply facilities; based on the power supply principle, influencing factors affecting power supply are determined; based on the influencing factors, current factory impact information within a preset time period is predicted; current factory impact information is analyzed to determine the unit power supply impact within a preset time period; based on the unit power supply and the unit power supply impact, the power supply within a preset time period is predicted.
[0066] The power supply principle can be understood as the power supply method or power supply system adopted by power supply facilities.
[0067] The factors affecting power supply can be understood as various factors that may affect the power supply during factory operation, including but not limited to weather conditions (such as sunny, cloudy, rainy days), power supply conditions (such as city power stability), equipment operating status (such as equipment failure), etc.
[0068] The unit power supply impact can be understood as the degree of influence of a certain factor on the power supply situation within a unit time. The unit power supply can be understood as the unit power generation of the power supply facility without being affected by the influencing factors within a unit time.
[0069] Specifically, analyze the power supply facilities and conduct in-depth analysis of their internal parts. For example, you can obtain the technical manuals that match the power supply facilities to determine the technical parameters of the power supply facilities and the corresponding power supply principles. Then, based on the power supply principles of the power supply facilities, analyze and determine which factors will affect the power supply of the power supply facilities, such as the operating status of the equipment inside the power supply facilities, environmental factors, etc.
[0070] Then, based on the influencing factors determined above, analyze whether there are corresponding influencing factors in the factory at the current moment. If there are, the actual situation of these influencing factors is used as the current factory impact information. Using these current factory impact information, determine the power supply impact of these impact information per unit time within the above preset period, that is, the unit power supply impact. At this time, combined with the historical power supply records, determine the unit power supply of the power supply facilities when there is no impact, and then combine the unit power supply impact to predict the power supply within the above preset period.
[0071] Through the solution provided by this embodiment, the power supply principle and influencing factors of the power supply facilities are deeply analyzed. Compared with the existing technology, the power supply in the preset period is predicted more accurately, making the prediction result more realistic. It provides strong support for power dispatching and management, optimizes the use of power resources, and avoids power waste or shortage. Potential power supply problems are discovered and resolved in a timely manner, thereby improving the overall stability of the power system.
[0072] In some embodiments, the production tasks are analyzed to determine the production volume and delivery time of each current production line; and the production urgency is determined based on the production volume and delivery time.
[0073] Analyze the production tasks in the database to determine the information therein, such as order details, product specifications, quantity requirements, delivery time, etc. Among them, the delivery time can be considered as the latest delivery time corresponding to this production task, which can be considered to be agreed in advance by the customer when signing the production contract.
[0074] The production volume corresponding to each current production line can be understood as the total production volume of this production line corresponding to this production task.
[0075] Assess the production urgency of each production line based on the rated urgency of the delivery time.
[0076] Through the method provided in this embodiment, production tasks are analyzed, the production volume and delivery time of each production line are accurately determined, and the urgency of the production tasks is evaluated based on the production volume and delivery time. This facilitates giving priority to tasks with high urgency when power supply imbalance occurs in the later stage, ensuring that important tasks are completed on time.
[0077] In some embodiments, the production urgency is determined based on the production volume and the delivery time, referring to the following formula: (1); in, Indicates The production urgency of each production task; Indicates The production volume of each production task; Indicates The delivery time of each production task; express The mean of express The standard deviation of express The mean of express The standard deviation of .
[0078] Specifically, you can use and the duration of the preset period to determine all The production mean within the preset period is obtained ; then use , calculate the mean delivery time, and get .
[0079] Through the solution provided in this embodiment, the design formula determines the production urgency according to the production volume and delivery time, improves the calculation efficiency, reduces the cost of manual analysis, reduces the subjectivity and uncertainty of human judgment, and makes the result more objective and fair. According to the production volume and delivery time, the urgency of each production task is updated in real time, and production allocation can be more flexible to meet production needs.
[0080] In some embodiments, the production equipment information of each current production line is obtained; based on the production equipment information, the rated power of each production equipment is determined; based on the power supply within the preset time period, the rated power and the production urgency, the power supply of each current production line within the preset time period is determined to obtain a power supply strategy.
[0081] The production equipment information can be stored in the corresponding equipment information database together with the above-mentioned power supply facility information, which can be obtained from the purchase records of factory personnel. It can include key information such as equipment model and serial number.
[0082] Specifically, after obtaining the production equipment information, key information is extracted from the production equipment information to determine the rated power of each production equipment. Based on the total power supply, rated power and production urgency within the preset time period obtained above, it is determined which production lines need to be prioritized to ensure normal operation within the preset time period, thereby determining the power supply for each production line within the preset time period.
[0083] Through the solution provided in this embodiment, the rated power determined based on the production equipment information ensures that the power supply based on the rated power can ensure the normal operation of the production equipment. In addition, the power supply can be adjusted considering the production urgency, so as to give priority to the power demand of high-urgency production tasks. This helps enterprises to quickly adjust production plans when facing urgent orders or emergencies, ensure on-time delivery of products, and maintain customer satisfaction.
[0084] In some embodiments, the power supply of each current production line within the preset period is determined according to the power supply within the preset period, the rated power and the production urgency, referring to the following formula: (2); in, Indicates that within the preset time period The power supply of the current production line; Indicates the number of The power required for the current production line; Indicates The production urgency of each production task; Indicates the power supply during the preset time period.
[0085] During the preset period The required power supply of the current production line can be obtained by the length of the preset time period and the number of production equipment of this production line.
[0086] Specifically, through and The power supply allocation priority of the production line corresponding to the production task among all production lines can be determined, so that they can be allocated one by one according to the priority to ensure that more urgent tasks can be completed on time.
[0087] Through the solution provided by this embodiment, the design formula determines the power supply of each current production line within the preset period according to the power supply, rated power and production urgency, ensuring that the distribution of power supply is more reasonable and scientific. Through formula calculation, the power supply can be allocated more accurately to avoid waste and excessive use of resources. It also helps to deal with uncertain factors in the production process and ensure that production tasks can be completed on time.
[0088] In some embodiments, within a preset period of time, To calculate the power supply required for the current production line, refer to the following formula: (3); in, Indicates the number of The power required for the current production line; Indicates the length of time for a preset period; Indicates The number of production equipment on the current production line; Indicates The current production line Rated power of each production equipment.
[0089] The number of production equipment can be understood as the total number of equipment corresponding to the production line that has production actions at the current moment.
[0090] Through the scheme provided by this embodiment, the formula is designed to take into account the length of the preset time period, the number of production equipment on the production line, and the rated power of each production equipment, and accurately calculate the power supply required by the production line within the preset time period. The structure is concise and clear, and the calculation process is relatively simple, which is convenient for enterprises to implement and manage. Through the formula calculation, the power supply demand of the production line within the preset time period can be predicted in advance, so as to make power supply plans and preparations in advance and avoid production problems caused by insufficient or excessive power supply.
[0091] In some embodiments, the power supply amount within a preset time period is predicted based on the unit power supply amount and the unit power supply impact, referring to the following formula: ; in, Indicates the power supply within a preset period of time; Indicates The original power supply capacity of each power supply facility within a preset time period; Indicates the number of influencing factors; Indicates The actual value of each influencing factor; Indicates The weight of the influencing factors; Indicates The unit power supply impact coefficient of each power supply facility.
[0092] Through the solution provided by this embodiment, the original power supply capacity of the power supply facility in the preset period, the number of influencing factors, and the weights corresponding to the influencing factors are considered, and a formula is designed to predict the power supply in the preset period, which can fully reflect the potential impact of various factors on the power supply. In addition, the unit power supply influence coefficient is introduced to more accurately predict the change in power supply of each power supply facility in the preset period, thereby obtaining a more accurate prediction of the overall power supply.
[0093] In some embodiments, the power restriction level within a preset time period is determined based on the power supply within a preset time period; the production records of each current production line are obtained; based on the production records, several production processes of each current production line are determined; based on the production tasks and unit production volume of each current production line, the material preparation situation of each current production line is determined; the historical operation data of each production process is obtained; the historical operation data is analyzed to obtain the unit production time of each production process; for each production process, the unit production time of the two production processes closest to any production process is analyzed to obtain the production efficiency of the two closest production processes; based on the production efficiency, the operating urgency of any production process is determined; the production urgency is determined based on the power restriction level, material preparation situation, operating urgency, production volume and delivery time.
[0094] The power restriction level can be understood as the power restriction level set by the power supply department at different time periods to meet the needs of most people. For example, at 2 pm, 2000kw / h is the first level of power restriction; 1000kw / h is the second level of power restriction. These power restriction levels can be set by the power supply department for factories according to the power consumption in different time periods.
[0095] The material preparation situation can be understood as the prediction of how many items this production line can produce on the day based on the unit production volume during the operation of the current production line according to the production task of the current production line, and the material preparation situation.
[0096] Historical operation data may be the operation data of each production process over a period of time in the past, and may include production time, production volume, failure rate, product qualification rate, product failure rate, power consumption during the production process, unit power consumption, etc.
[0097] Operational urgency can be understood as the importance of each production process in the entire production line.
[0098] Specifically, a preset database can be pre-set to store the data generated during the production process of each production line in the factory, including production data and operation data. The production data generated at each start-up can be integrated to form the production record of the day. When it is necessary to call, it can be selected from the preset database according to the needs to obtain the production record of each current production line.
[0099] According to the production records, several production processes of each current production line are determined, and then the material preparation situation of each current production line is determined in combination with the production tasks and unit production volume of each current production line.
[0100] The historical operation data of each production process is obtained from the production records, and the historical operation data is analyzed to obtain the unit production time of each production process. For each production process, the unit production time of the two production processes closest to any production process is analyzed to obtain the production efficiency of the two production processes closest to each other. For example, the production efficiency is calculated using the method of production efficiency = (output / input) * 100%.
[0101] When calculating the operating urgency of a production process, it is possible to consider dividing the operating urgency indicators based on the production characteristics of each production process and the relationship between two adjacent production processes. After determining the production efficiency of the two most adjacent production processes, the operating urgency of any production process can be determined based on the production efficiency of the two most adjacent production processes.
[0102] Then, a deep learning model is established which can reflect the production urgency based on the power restriction level, material preparation status, operation urgency, production volume and delivery time. The power restriction level, material preparation status, operation urgency, production volume and delivery time obtained at the current moment are input into the deep learning model to determine the production urgency.
[0103] Through the solution provided in this embodiment, the unit production time and production efficiency of each production process are deeply analyzed to ensure that key and urgent production processes are given priority. Comprehensively consider the power limit level, material preparation, operation urgency, production volume and delivery time, determine the production urgency, optimize the production process and resource allocation, reduce unnecessary waste and waiting time, and help reduce production costs and improve overall profitability.
[0104] In some embodiments, according to the difference between electricity supply and demand, the number of production lines to be adjusted at the current moment is determined; whether the number of production lines is greater than 1 is determined; if the number of production lines is greater than 1, the production urgency of all current production lines is sorted, and the last production line is determined according to the sorting result; according to the operation data of the last production line, the unit power consumption of the last production line is determined; according to the unit power consumption and the difference between electricity supply and demand, it is determined whether stopping the operation of the last production line can solve the power supply imbalance; if it has not been solved, the production urgency of all remaining current production lines is sorted again, and the second last production line is determined and stopped according to the result of the second sorting; if the number of production lines is less than 1 , then according to the sorting results, determine the emergency production line with the strongest production urgency, and according to the operation urgency, analyze several production processes of the emergency production line, determine the process characteristics of each production process, and according to the process characteristics, determine the non-stoppable links of each current production line; according to the non-stoppable links, determine the non-stoppable processes; and according to the non-stoppable processes, determine the stoppable processes; obtain the unit start-stop power loss of each stoppable process; according to the start-stop power loss, determine the total power loss of each stoppable process within the preset time period; according to the non-stoppable links and the total power loss of each stoppable process, adjust the power supply strategy to solve the power supply imbalance.
[0105] A non-stop process can be understood as a process that cannot be stopped once it is started in this production process. Once it is stopped, it may result in a large amount of material waste.
[0106] The unit start-stop power loss can be understood as the power loss caused by starting and shutting down each production process per unit time. In the specific implementation method, the startup and shutdown of each electrical equipment will cause a certain amount of power loss.
[0107] The last production line can be understood as the production line at the end of the production urgency ranking.
[0108] Through the solution provided in this embodiment, when the number of production lines is greater than 1, production lines with lower production urgency are stopped first to minimize the impact on the overall production schedule and customer delivery. When the number of production lines is less than 1, the production process and the links that cannot be stopped are analyzed in depth, and the processes that can be stopped are accurately determined to reduce power consumption while ensuring key production. At the same time, based on the analysis of the total power loss of the links that cannot be stopped and each process that can be stopped, a more accurate and effective power supply strategy is formulated to optimize the allocation of power resources. By calculating the unit start-stop power loss and total power loss of each process that can be stopped, unnecessary power loss and economic loss can be minimized when adjusting production.
[0109] Figure 3 A schematic diagram of a grid-based power supply service management system provided in one embodiment of the present application is shown in FIG. Figure 3 As shown, the grid-based power supply service management system 300 of this embodiment includes: an imbalance judgment module 301 , a line determination module 302 , a degree analysis module 303 , and a strategy adjustment module 304 .
[0110] The imbalance judgment module 301 is used to obtain real-time power consumption information, analyze the real-time power consumption information, and judge whether there is a power supply imbalance at the current moment; The line determination module 302 is used to obtain and analyze the industrial production situation if there is a power supply imbalance, determine whether there is a production action in any grid, and if so, determine a number of current production lines according to the grid location; The degree analysis module 303 is used to obtain the production tasks of each current production line and determine the production urgency according to the production tasks; The strategy adjustment module 304 is used to adjust the power supply strategy to solve the power supply imbalance problem according to the production urgency 。
[0111] Optionally, the imbalance judgment module 301 is specifically used to: Obtain the production tasks and unit production volume of each current production line; Determine the electricity demand per unit time based on production tasks and unit production volume; According to the production task and the power demand within the unit time, the total power consumption within the preset time period is obtained; Obtaining the unit power supply of the power supply facility, and predicting the power supply within a preset time period based on the unit power supply; Calculate the difference between electricity supply and demand within a preset period based on total electricity consumption and power supply; The power supply and demand difference is compared with a preset supply and demand threshold, and based on the comparison result, it is determined whether there is a power supply imbalance at the current moment.
[0112] Optionally, the imbalance judgment module 301 is specifically used to: Analyzing the power supply facilities to determine the power supply principle of the power supply facilities; According to the power supply principle, determining factors affecting power supply; Based on the influencing factors, predict the current factory impact information within the preset time period; Analyze the current factory impact information to determine the unit power supply impact within a preset time period; The power supply amount within a preset time period is predicted according to the unit power supply amount and the unit power supply impact.
[0113] Optionally, the degree analysis module 303 is specifically used for: Analyze the production tasks and determine the production volume and delivery time of each current production line; The production urgency is determined based on the production volume and the delivery time.
[0114] Optionally, the degree analysis module 303 is specifically used for: ; in, Indicates The production urgency of each production task; Indicates The production volume of each production task; Indicates The delivery time of each production task; express The mean of express The standard deviation of express The mean of express The standard deviation of .
[0115] Optionally, the policy adjustment module 304 is specifically configured to: Obtain production equipment information for each current production line; Determine the rated power of each production equipment according to the production equipment information; According to the power supply in the preset time period, the rated power and the production urgency, the power supply of each current production line in the preset time period is determined to obtain a power supply strategy.
[0116] Optionally, the policy adjustment module 304 is specifically configured to: ; in, Indicates that within the preset time period The power supply of the current production line; Indicates the number of The power required for the current production line; Indicates The production urgency of each production task; Indicates the power supply within the preset time period.
[0117] Optionally, the grid-based power supply service management system 300 further includes a power supply amount calculation module 305, which is used to: ; in, Indicates the number of The power required for the current production line; Indicates the length of the preset time period; Indicates The number of production equipment on the current production line; Indicates The current production line Rated power of each production equipment.
[0118] Optionally, the imbalance judgment module 301 is specifically used to: ; in, Indicates the power supply within a preset period of time; Indicates The original power supply capacity of each power supply facility within a preset time period; Indicates the number of influencing factors; Indicates The actual value of each influencing factor; Indicates The weight of the influencing factors; Indicates The unit power supply impact coefficient of each power supply facility.
[0119] Optionally, the degree analysis module 303 is specifically used for: Determine the power restriction level within the preset time period based on the power supply within the preset time period; obtain the production record of each current production line; determine several production processes of each current production line based on the production record; determine the material preparation situation of each current production line based on the production task of each current production line and the unit production volume; obtain the historical operation data of each production process; analyze the historical operation data to obtain the unit production time of each production process; for each production process, analyze the unit production time of the two production processes closest to any production process to obtain the production efficiency of the two production processes closest to any production process; determine the operation urgency of any production process based on the production efficiency; determine the production urgency based on the power restriction level, the material preparation situation, the operation urgency, the production volume and the delivery time.
[0120] Optionally, the policy adjustment module 304 is specifically configured to: According to the power supply and demand difference, determine the number of production lines to be adjusted at the current moment; determine whether the number of production lines is greater than 1; if the number of production lines is greater than 1, sort the production urgency of all current production lines, and determine the last production line according to the sorting result; determine the unit power consumption of the last production line according to the operation data of the last production line; determine whether stopping the operation of the last production line can solve the power supply imbalance according to the unit power consumption and the power supply and demand difference; if not, sort the production urgency of all remaining current production lines again, determine the second last production line according to the secondary sorting result and stop it; if the number of production lines is less than 1, then According to the sorting results, the emergency production line with the strongest production urgency is determined, and according to the operation urgency, several production processes of the emergency production line are analyzed to determine the process characteristics of each production process, and according to the process characteristics, the non-stoppable links of each current production line are determined; according to the non-stoppable links, the non-stoppable processes are determined; and according to the non-stoppable processes, the stoppable processes are determined; the unit start-stop power loss of each stoppable process is obtained; according to the start-stop power loss, the total power loss of each stoppable process within a preset time period is determined; according to the non-stoppable links and the total power loss of each stoppable process, the power supply strategy is adjusted to solve the power supply imbalance.
[0121] The system of this embodiment can be used to execute the method of any of the above embodiments. The implementation principles and technical effects are similar and will not be described in detail here.
Claims
1. A grid-based power supply service management method, characterized in that: include: Acquire real-time power consumption information, analyze the real-time power consumption information, and determine whether there is a power supply imbalance at the current moment; If there is a power supply imbalance, obtain and analyze the industrial production situation to determine whether there is any production action in any grid. If so, determine several current production lines based on the grid location; Obtaining the production tasks of each current production line, and determining the production urgency according to the production tasks; According to the production urgency, the power supply strategy is adjusted to solve the power supply imbalance problem.
2. The method according to claim 1, characterized in that The analyzing the real-time power consumption information to determine whether there is a power supply imbalance at the current moment includes: Obtain the production tasks and unit production volume of each current production line; Determine the electricity demand per unit time based on production tasks and unit production volume; According to the production task and the power demand within the unit time, the total power consumption within the preset time period is obtained; Obtaining the unit power supply of the power supply facility, and predicting the power supply within a preset time period based on the unit power supply; Calculate the difference between electricity supply and demand within a preset period based on total electricity consumption and power supply; The power supply and demand difference is compared with a preset supply and demand threshold, and based on the comparison result, it is determined whether there is a power supply imbalance at the current moment.
3. The method according to claim 2, characterized in that The predicting the power supply amount within a preset time period according to the unit power supply amount includes: Analyzing the power supply facilities to determine the power supply principle of the power supply facilities; According to the power supply principle, determining factors affecting power supply; Based on the influencing factors, predict the current factory impact information within the preset time period; Analyze the current factory impact information to determine the unit power supply impact within a preset time period; The power supply amount within a preset time period is predicted according to the unit power supply amount and the unit power supply impact.
4. The method according to claim 3, characterized in that Determining the production urgency according to the production task includes: Analyze the production tasks and determine the production volume and delivery time of each current production line; According to the production volume and the delivery time, determine the production urgency, refer to the following formula: ; in, Indicates The production urgency of each production task; Indicates The production volume of each production task; Indicates The delivery time of each production task; express The mean of express The standard deviation of express The mean of express The standard deviation of .
5. The method according to claim 2, characterized in that: The adjusting the power supply strategy according to the production urgency includes: Obtain production equipment information for each current production line; Determine the rated power of each production equipment according to the production equipment information; According to the power supply in the preset time period, the rated power and the production urgency, the power supply of each current production line in the preset time period is determined to obtain a power supply strategy.
6. The method according to claim 5, characterized in that The power supply amount of each current production line within the preset time period is determined according to the power supply amount within the preset time period, the rated power and the production urgency, referring to the following formula: ; in, Indicates that within the preset time period The power supply of the current production line; Indicates the number of The power required for the current production line; Indicates The production urgency of each production task; Indicates the power supply within the preset time period.
7. The method according to claim 4, characterized in that The power supply amount within the preset time period is predicted based on the unit power supply amount and the unit power supply impact, referring to the following formula: ; in, Indicates the power supply within a preset period of time; Indicates The original power supply capacity of each power supply facility within a preset time period; Indicates the number of influencing factors; Indicates The actual value of each influencing factor; Indicates The weight of the influencing factors; Indicates The unit power supply impact coefficient of each power supply facility.
8. The method according to claim 4, characterized in that The determining of the production urgency according to the production volume and the delivery time includes: Determining a power limit level within the preset time period according to the power supply within the preset time period; Get the production records of each current production line; Determine several production processes of each current production line according to the production records; Determine the material preparation status of each current production line according to the production task of each current production line and the unit production volume; Obtain historical operation data of each production process; Analyze the historical operation data to obtain the unit production time of each production process; For each production process, analyze the unit production time of the two production processes closest to any production process to obtain the production efficiency of the two production processes closest to each other; Determine the urgency of running any production process based on the production efficiency; The production urgency is determined according to the power restriction level, the material preparation situation, the operation urgency, the production volume and the delivery time.
9. The method according to claim 8, characterized in that The adjusting the power supply strategy according to the production urgency includes: According to the electricity supply and demand difference, determine the number of production lines to be adjusted at the current moment; Determine whether the number of production lines is greater than 1. If the number of production lines is greater than 1, sort the production urgency of all current production lines, and determine the last production line according to the sorting result; Determining the unit power consumption of the last production line according to the operation data of the last production line; Determine whether stopping the last production line from operating solves the power supply imbalance according to the unit power consumption and the power supply-demand difference; If the problem is not solved, the production urgency of all the remaining current production lines will be re-sorted, and the second last production line will be determined and stopped according to the result of the re-sorting; If the number of the production lines is less than 1, then according to the sorting result, determine the emergency production line with the strongest production urgency, and according to the operation urgency, analyze several production processes of the emergency production line, determine the process characteristics of each production process, and determine the non-stop links of each current production line according to the process characteristics; Determine the non-stoppable process based on the non-stoppable link; and determine the stoppable process based on the non-stoppable process; Obtain the unit start-stop power loss of each process that can be stopped; According to the start-stop power loss, determine the total power loss of each process that can be stopped within a preset time period; According to the non-stoppable links and the total power loss of each stoppable process, the power supply strategy is adjusted to solve the power supply imbalance.
10. A grid-based power supply service management system, characterized in that: include: An imbalance judgment module is used to obtain real-time power consumption information, analyze the real-time power consumption information, and judge whether there is a power supply imbalance at the current moment; The line determination module is used to obtain and analyze the industrial production situation if there is a power supply imbalance, determine whether there is a production action in any grid, and if so, determine several current production lines according to the grid location; A degree analysis module is used to obtain the production tasks of each current production line and determine the production urgency based on the production tasks; The strategy adjustment module is used to adjust the power supply strategy according to the production urgency to solve the power supply imbalance problem.