Lassen steel sheet pile cofferdam construction method

Through rotary drilling and grouting technology, the steel sheet piles are ensured to enter the bedrock, and a waist beam and internal support are installed during the excavation of the foundation pit, which solves the penetration and stop of the Lassen steel sheet piles under high groundwater levels. The water problem has achieved significant water stopping effect and construction safety.

CN118997194APending Publication Date: 2024-11-22BEIJING URBAN CONSTRUCTION DESIGN & DEVELOPMENT GROUP CO LIMITED
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411273795.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

Under the conditions of bedrock soil covering with high groundwater levels, the Lassen steel sheet pile cofferdam is difficult to penetrate into the rock formation, resulting in poor water stopping effect and unable to provide a good working environment.

Method used

Using rotary drilling and hole-guiding technology, through hole-guiding replacement and grouting, the steel sheet piles enter the bedrock, and a waist beam and internal support are set up while excavating during the foundation pit to extend the seepage path and enhance structural stability. .

Benefits of technology

The problem of steel sheet piles not being able to penetrate into the rock layer and poor water stopping effect was effectively overcome, and good water stopping effect and safe and simple construction technology were achieved, providing a good working environment for the construction of the main structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997194A_ABST
    Figure CN118997194A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of cofferdam construction, and discloses a Larsen steel sheet pile cofferdam construction method which comprises the steps of field investigation, island building cofferdam filling, survey lofting, lead hole rotary drilling, lead hole replacement filling, steel sheet pile sinking, grouting, foundation pit excavation and drainage, waist beam and inner support installation, construction monitoring, main body structure construction and cofferdam dismantling. When water stop cofferdam construction is conducted under the bed rock earthing condition with the high underground water level, firstly, island building cofferdam construction is conducted, a rotary drilling rig is selected according to the model and specification of Larsen steel sheet piles, and it is guaranteed that the Larsen steel sheet piles enter the bed rock through rotary drilling guide holes; basic constraints are established for temporary stability of the steel sheet pile by taking the penetration of the Larsen steel sheet pile into the bedrock and the backfilling of sandy soil in the rock-entering range as elements; then, a seepage path is prolonged through bottom grouting, and a good water stopping effect is achieved; and finally, according to the excavation depth of the foundation pit, a waist beam and an inner support are arranged while excavation is conducted, water collection and pumping drainage are conducted after excavation is conducted to the bottom, and a good operation environment is provided for main structure construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of cofferdam construction, and more specifically to a Larsen steel sheet pile cofferdam construction method. Background Art

[0002] Larsen steel sheet piles are often used as retaining walls, breakwaters, cofferdams, foundation pit supports, etc. due to their light profile, simple construction, and good water-stopping properties. They are widely used in civil engineering, water conservancy, construction, and municipal engineering.

[0003] When Larsen steel sheet piles are used as cofferdams, the conventional process is to use a pile driver to directly drive the steel sheet piles to the designed elevation, interlock them in pairs until they are connected, and then excavate the pit, pump out the accumulated water, weld the internal supports, and construct the main structure. The main applicable geological conditions include silt, sand, clay, etc. When encountering special soil conditions, such as high-strength rock formations, it will be difficult to penetrate, so that the steel sheet piles can only be driven into the soil-rock interface without any rock penetration depth. As a result, under the condition of bedrock overburden with a high groundwater level, the construction of Larsen steel sheet pile cofferdam has a poor structural water-stopping effect and cannot provide a good working environment for the main structure construction.

[0004] Therefore, it is necessary to propose a Larsen steel sheet pile cofferdam construction method to at least partially solve the problems existing in the prior art. Summary of the invention

[0005] A series of simplified concepts are introduced in the Summary of the Invention, which will be further described in detail in the Detailed Description of the Invention. The Summary of the Invention does not mean to attempt to define the key features and essential technical features of the claimed technical solution, nor does it mean to attempt to determine the scope of protection of the claimed technical solution.

[0006] In order to at least partially solve the above problems, the present invention provides a Larsen steel sheet pile cofferdam construction method, comprising the following steps:

[0007] On-site investigation, island cofferdam filling, surveying and setting out, rotary drilling and guiding holes, hole replacement and filling, steel sheet pile sinking, grouting, foundation pit excavation and drainage, waist beam and internal support installation, construction monitoring, main structure construction and cofferdam removal.

[0008] Preferably, in the rotary drilling and boring process: the boring piles are designed as interlocking piles and are constructed in the order of interval holes; assuming that the boring pile diameter is D, the boring pile spacing can generally be 1 / 3D to 1 / 2D; after burying the casing and checking that the verticality and hole position meet the requirements, the rotary drill is put into place for drilling; rotary drilling and soil excavation are carried out alternately until the bottom tube of the casing enters the bedrock by not less than 1 / 2D and not less than 0.5m; the drill residues are loaded onto trucks, covered and transported to the designated slag disposal point; the boring sequence is carried out from upstream to downstream, first facing the water surface side, then the two sides, and finally closing at the downstream point and jumping the piles to bore the holes.

[0009] Preferably, during the hole-drilling and backfilling process: the hole-drilling and backfilling are carried out alternately one by one, and after the hole base is cleaned, backfilling is carried out. Sandy soil is preferably used as the backfill soil, and it is backfilled and compacted in layers of 20 cm to 40 cm until the platform top elevation.

[0010] Preferably, the overall construction sequence of steel sheet pile sinking is: first construct the cofferdams on both sides from upstream to downstream, then construct the upstream steel cofferdam, and finally construct the downstream steel cofferdam. The upstream steel cofferdam and the downstream steel cofferdam are both connected near the river bank.

[0011] Preferably, during grouting: the replacement soil grouting and water-stopping construction adopts the penetration grouting process, and grouting is performed inside and outside each hole along the steel sheet pile, and the construction operation sequence adopts the hole-sequential method; the grouting range is the hole replacement area, wherein the grouting height on the inner side of the steel sheet pile cofferdam is from the bottom of the steel sheet pile to the bottom of the main structure; the grouting height on the outer side of the steel sheet pile cofferdam is 2m above the bottom of the steel sheet pile.

[0012] Preferably, during the excavation and drainage of the foundation pit: during the excavation of the foundation pit, the water level in the cofferdam is kept slightly lower than the elevation of the bottom of the foundation pit so as not to affect the excavation construction. A small excavator is used for excavation. After the foundation pit is excavated to the designed bottom elevation, a collection well and drainage ditch are set in the cofferdam.

[0013] Preferably, during the installation of the waist beam and the inner support: when the cofferdam is excavated and the water level drops to 0.5m below the design elevation of the inner support, the inner support is installed layer by layer, and the next step can be carried out only after the installation of each layer of purlins is completed and the quality inspection is passed; after the water-stopping reinforcement on the inner side of the cofferdam is completed, the corbel triangular bracket is welded on the steel sheet piles, and one is set every 2m. After a section of the waist beam is made into a whole, it is directly hoisted and placed on the corbel triangular bracket, the waist beam and the steel sheet piles are padded and tight, and then welded firmly.

[0014] Preferably, during the installation of the waist beam and the inner support: the inner support of the cofferdam adopts cylindrical steel support; during the excavation of the foundation pit of the pedestal, the water level in the cofferdam is kept slightly lower than the bottom elevation of the foundation pit so as not to affect the excavation construction. When the excavation is 0.5m below the design elevation of the waist beam, the first and second layers of inner support are installed. When installing the inner support, triangular brackets are welded on the side walls of the steel sheet piles as an auxiliary measure.

[0015] Preferably, the construction monitoring contents include: stress of steel sheet piles; stress of cofferdam purlins and supporting structures; horizontal displacement of the top of the cofferdam.

[0016] Preferably, the monitoring points for construction monitoring are arranged as follows:

[0017] A certain number of monitoring points are arranged for the steel sheet pile monitoring points, among which the vertical points are located in the middle of each layer of purlins, and the bottom layer of points are located in the middle of the bottom layer of purlins and the bottom of the foundation pit;

[0018] The purlins and internal supports of each floor are arranged in the same position;

[0019] After the steel sheet piles are sunk, the horizontal and vertical displacement monitoring of the cofferdam is carried out by setting measuring points at the center lines and four corners of the four sides of the entire cofferdam on the top of the steel sheet piles, and collecting data using a total station and fixed prism.

[0020] Compared with the prior art, the present invention has at least the following beneficial effects:

[0021] The invention provides a Larsen steel sheet pile cofferdam construction method. When water-stop cofferdam construction is carried out under the condition of bedrock covering with a high groundwater level, the island cofferdam construction is first carried out, and a suitable rotary drilling rig is selected in combination with the model and specification of the Larsen steel sheet piles, and the Larsen steel sheet piles are ensured to enter the bedrock through rotary drilling holes; the penetration of the Larsen steel sheet piles into the bedrock and the backfilling of sandy soil within the rock entry range are taken as elements to establish basic constraints for the temporary stability of the steel sheet piles; then the seepage path is extended by bottom grouting, thereby achieving a good water-stopping effect; finally, according to the excavation depth of the foundation pit, waist beams and internal supports are set while digging, and after excavation to the bottom, water is collected and pumped out to provide a good working environment for the main structure construction. This method can effectively overcome the problems that the Larsen steel sheet piles cannot penetrate into the rock and the water-stopping effect of the bottom of the Larsen steel sheet pile cofferdam is not good under the condition of bedrock covering with a high groundwater level. The method has simple process, safe operation and significant water-stopping effect, and can provide a technical reference for the construction of Larsen steel sheet pile cofferdams under similar conditions.

[0022] The Larsen steel sheet pile cofferdam construction method described in the present invention, other advantages, objectives and features of the present invention will be reflected in part through the following description, and in part will be understood by technical personnel in the field through research and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0024] Figure 1 is a process flow chart of the present invention;

[0025] Figure 2 This is a schematic diagram of positioning the lead hole in the measurement and layout of the present invention;

[0026] Figure 3 This is a relationship diagram between the position of the lead hole and the position of the Larsen steel sheet pile in the present invention;

[0027] Figure 4 This is a schematic diagram of a rotary drilling drill in the present invention;

[0028] Figure 5 This is a schematic diagram of the hole introduction sequence in the present invention;

[0029] Figure 6 This is a schematic diagram of backfilling the lead hole in the present invention;

[0030] Figure 7 This is a schematic diagram of the steel sheet pile sinking sequence in the present invention;

[0031] Figure 8 This is a schematic diagram of the steel sheet pile insertion and positioning in the present invention;

[0032] Fig. 9 It is a schematic diagram of the grouting range in the present invention;

[0033] Fig.10 This is a schematic diagram of excavating and taking soil from a foundation pit in the present invention;

[0034] Fig.11 It is a schematic diagram showing the structure of the triangular bracket in the present invention;

[0035] Fig.12 It is a schematic diagram of the inner support structure in the present invention;

[0036] Fig.13 It is a schematic diagram of the arrangement of the stress monitoring points of the surrounding purlin and the inner support in the present invention;

[0037] Fig.14 It is a schematic diagram of the plan and elevation layout of the steel sheet pile monitoring points in the present invention;

[0038] Fig.15 It is a schematic diagram of the arrangement of the monitoring points for the horizontal displacement of the cofferdam in the present invention.

[0039] In the figure: 1. On-site investigation; 2. Island cofferdam filling; 3. Surveying and setting out; 4. Rotary drilling and guiding holes; 5. Guiding hole replacement and filling; 6. Steel sheet pile sinking; 7. Grouting; 8. Foundation pit excavation and drainage; 9. Installation of waist beams and internal supports; 10. Construction monitoring; 11. Main structure construction; 12. Cofferdam removal. DETAILED DESCRIPTION

[0040] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments so that those skilled in the art can implement the invention with reference to the description.

[0041] It should be understood that terms such as “having”, “including” and “comprising” used herein do not exclude the existence or addition of one or more other elements or combinations thereof.

[0042] Embodiment 1:

[0043] like Figure 1 As shown, the present invention provides a Larsen steel sheet pile cofferdam construction method, comprising the following steps:

[0044] On-site investigation 1, island cofferdam filling 2, surveying and setting out 3, rotary drilling and guiding holes 4, guiding hole replacement 5, steel sheet pile sinking 6, grouting 7, foundation pit excavation and drainage 8, waist beam and internal support installation 9, construction monitoring 10, main structure construction 11 and cofferdam removal 12.

[0045] Specifically:

[0046] On-site investigation 1:

[0047] According to geological surveys, design documents and actual on-site investigations, collect hydrological and meteorological materials, understand local climate characteristics, and grasp the operational time for water-related construction; dig exploration pits, conduct geological surveys on the project site, and verify the accuracy of geological survey data; and handle procedures such as water-related construction permits according to local requirements.

[0048] Island cofferdam filling 2:

[0049] In order to ensure the smooth construction of rotary drilling and accurate and vertical drilling positions, it is necessary to build an island cofferdam operation platform in the Larsen steel sheet pile cofferdam construction area in advance. The island cofferdam construction operation can be combined with the surrounding geological conditions to reasonably select the construction type; in order to reduce the project cost and ecological environmental impact, earth filling is recommended. The filling material for the earth island cofferdam is required to be clay, silty clay or sandy clay with good rolling effect and low permeability. The filling height shall not be less than 0.5m to 0.7m above the maximum water level, the compaction degree shall be ≥92%, and the bearing capacity shall meet the load requirements of construction machinery and materials; waterproof geotextile and a layer of fine mesh shall be laid on the water-facing side of the earth backfill cofferdam to prevent water flow from eroding the cofferdam soil and causing the cofferdam to collapse.

[0050] Measurement and Stakeout 3:

[0051] Be familiar with the drawings in advance, and accurately determine the top elevation of the steel sheet pile cofferdam based on the main structure position and designed cofferdam size, to ensure that the steel sheet piles are laid out above the designed depth.

[0052] Among them, the construction platform should consider the horizontal surface of the steel sheet pile in advance.

[0053] Before the construction of the pilot hole, the plane position of each hole is measured and laid out on the island-building platform by a total station, and marked with positioning stakes. The schematic diagram of the pilot hole positioning is shown in the figure below. Figure 2 shown.

[0054] Rotary drilling guide hole 4:

[0055] The pilot hole pile is designed as a bite pile, the pilot hole drill diameter is φ80cm, the casing is φ85cm×2.5cm, the pilot hole spacing is 55cm, the overlap length is 25cm, the pilot hole depth is 9~11.5m, and the construction is carried out in the order of the interval hole sequence. The relationship between the pilot hole position and the Larsen steel sheet pile position is as follows: Figure 3 shown.

[0056] When burying the casing, the diameter of the casing is 2cm to 10cm larger than the diameter of the lead-in pile; after checking that the verticality and hole position meet the requirements, the rotary drilling drill is put into place for drilling; rotary drilling and soil excavation are carried out alternately until the bottom of the casing enters the bedrock more than 0.5m; the drill residue is loaded onto a truck, covered and transported to a designated dumping point. Figure 4 shown.

[0057] The schematic diagram of the hole introduction sequence is as follows Figure 5 As shown, the sequence of drilling holes is from upstream to downstream (along the direction of water flow), first on the water surface side, then on both sides, and finally at the downstream point, the holes are drilled by jumping piles.

[0058] Lead hole replacement 5:

[0059] Schematic diagram of backfilling the lead hole Figure 6 As shown, the boring and replacement are carried out alternately one by one. After the boring base is cleaned, backfilling is carried out. Sandy soil is preferred for backfilling, and it is backfilled and compacted in 40cm layers until the top elevation of the platform. The compaction of sandy soil can be carried out by using a rotary drilling drill bit; the layer thickness and compaction method can also be determined according to the selection of compaction equipment.

[0060] Steel sheet pile sinking 6:

[0061] Schematic diagram of steel sheet pile sinking sequence Figure 7 As shown in the figure, the overall construction sequence of steel sheet pile sinking is: first construct the cofferdams on both sides from upstream to downstream (along the direction of water flow), then construct the upstream side (water-facing side) steel cofferdam, and finally construct the downstream side steel cofferdam. The upstream side steel cofferdam and the downstream side steel cofferdam are both connected near the river bank.

[0062] The steel sheet pile sinking process adopts the single driving method. Before driving, the inner and outer edges of the steel sheet pile are measured and marked with a wide line or white lime as the positioning line for the steel sheet pile sinking. The schematic diagram of the steel sheet pile driving positioning is as follows Figure 8 shown.

[0063] The first and second steel sheet piles are driven into the design elevation with the guide beam as the positioning and vertical insertion (the position of the steel sheet piles should be carefully and repeatedly corrected to ensure verticality); the position and direction of the driving should be accurate to serve as a model. The steel sheet piles are measured and corrected once every 1 meter to ensure their verticality and position.

[0064] For the remaining steel sheet piles, the already inserted steel sheet piles shall be used as the standard, and the pile driver shall be used to insert the lock mouth of the previous steel sheet pile and slowly sink it vertically with manual support.

[0065] Among them, in order to ensure the smooth closure of the steel sheet pile cofferdam, the following aspects should be paid attention to:

[0066] (1) The closing position of the steel sheet pile should be preset before driving, and the verticality and width of the closing mouth should be adjusted in advance on both sides of the closing mouth according to the driving conditions;

[0067] (2) Strengthen the verticality control and deviation correction of steel sheet piles during construction, especially when there are 10 piles left on both sides of the joint, strictly control the verticality and gradually correct the accumulated deviation of the verticality of the driven steel sheet piles;

[0068] (3) Strengthen the measurement of joint width and use special-shaped sheet piles when necessary;

[0069] (4) Before driving the joint sheet pile, the heights of the piles on both sides should be different, and the height difference should be controlled within 100-200 mm. In this way, the locking mouth of the joint sheet pile can be easily put on the high pile, and then put on the locking mouth of the low pile.

[0070] Grouting 7:

[0071] The replacement soil grouting water-stopping construction adopts the permeation grouting technology, and the grouting pressure is 0.2~0.6MPa; the grouting time can be determined according to the permeability of the soil and the grouting amount, generally 1~2 hours; the slurry ratio can be determined according to the properties of the soil and the engineering requirements, generally cement: water = 1:0.5~1:1.0. Grouting is carried out inside / outside the steel sheet pile in each hole, and the construction operation sequence should adopt the hole-by-hole sequence method. The interval time of jet grouting of adjacent holes should not be less than 2h, and the grouting fullness is controlled according to the grouting amount, which should not be less than 1.2 times the calculated grouting amount.

[0072] Grouting range diagram Fig. 9 As shown in the figure, the grouting range is the hole replacement area, where the grouting height on the inner side of the steel sheet pile cofferdam is from the bottom of the steel sheet pile to the bottom of the main structure, which can be directly judged by observing whether slurry overflow occurs at the bottom of the foundation pit; the grouting height on the outer side of the steel sheet pile cofferdam is 2m above the bottom of the steel sheet pile, which can be controlled by the grouting amount, generally not less than 1.2 times the calculated grouting amount.

[0073] Foundation pit excavation and drainage 8:

[0074] Schematic diagram of foundation pit excavation and soil extraction Fig.10 As shown,

[0075] During the excavation of the foundation pit, the water level in the cofferdam should be kept slightly lower than the elevation of the bottom of the foundation pit so as not to affect the excavation construction. When the excavation reaches the first waist beam and the inner support position 0.5m, it should be installed in time. The lower layer excavation can only be carried out after the installation is completed.

[0076] A small excavator is used for excavation. The silty clay layer in the cofferdam can be directly excavated. If hard mudstone is encountered, a breaker hammer can be installed on the excavator to break it. The excavated soil is put into the hopper and lifted to the dump truck by a crane.

[0077] After the foundation pit is excavated to the designed bottom elevation, a water collection well and drainage ditch should be set up in the cofferdam. The drainage ditch must not dig through the connection between the cushion layer and the steel sheet pile cofferdam. A water stop wall structure should be built and the drainage should be done by a pump.

[0078] Waist beam and inner support installation 9:

[0079] When excavation is carried out inside the cofferdam and the water level drops to 0.5m below the design elevation of the internal support, the internal support is installed layer by layer. The next step can only be carried out after the installation of each layer of purlins is completed and passed the quality acceptance.

[0080] Among them, the steel sheet pile waist beam should be extended according to the requirements of steel sections with equal strength, and the strength of its welded joint shall not be lower than the strength of the parent material.

[0081] After the water-stop reinforcement on the inner side of the cofferdam is completed, the lifting equipment cooperates with the installation personnel to weld the bracket triangular bracket on the steel sheet pile, and one is set every 2m. The structural diagram of the triangular bracket is as follows Fig.11 As shown. After a section of the waist beam is made into an integral part, it is directly hoisted and placed on the corbel triangular bracket. The waist beam and the steel sheet pile are padded and tight, and then welded firmly.

[0082] The schematic diagram of the internal support structure is as follows Fig.12 As shown in the figure, the inner support of the cofferdam is made of cylindrical steel. During the excavation of the foundation pit, the water level in the cofferdam is kept slightly lower than the bottom elevation of the foundation pit, which does not affect the excavation construction. When the excavation is 0.5m below the design elevation of the waist beam, the first and second layers of inner support are installed. When installing the inner support, a triangular bracket is welded on the side wall of the steel sheet pile as an auxiliary measure.

[0083] The installation of waist beams and internal supports should be synchronized with the excavation of the foundation pit according to the design requirements until all installation is completed.

[0084] Construction monitoring 10:

[0085] The construction monitoring contents mainly include: the stress of steel sheet piles; the stress of purlins and supporting structures; and the horizontal displacement of the top of the cofferdam.

[0086] The arrangement of stress monitoring points for purlins and internal supports is as follows: Fig.13 As shown, the purlins and internal supports of each layer are arranged in the same position.

[0087] The plan and elevation diagram of the steel sheet pile monitoring point layout is as follows: Fig.14 As shown, the vertical distribution points are located in the middle of each layer of purlins, and the lowest layer of distribution points are located in the middle of the lowest layer of purlins and the bottom of the foundation pit.

[0088] Schematic diagram of the arrangement of monitoring points for cofferdam horizontal displacement Fig.15 As shown in the figure, after the steel sheet piles are sunk, the horizontal and vertical displacement monitoring of the cofferdam is completed. Measuring points are arranged at the center lines and four corners of the four sides of the entire cofferdam on the top of the steel sheet piles, and data are collected using a total station and a fixed prism.

[0089] During the main structure construction 11:

[0090] After the cofferdam construction is completed, in order to facilitate the main construction, a steel inclined ladder should be set at the midpoint of the long side of the steel cofferdam for personnel to go up and down. The main structure construction is strictly in accordance with the design and specification requirements.

[0091] Cofferdam removal 12:

[0092] After the main structure construction is completed, the steel sheet piles can be pulled out and reused.

[0093] First, clamp the end of the steel sheet pile with a pile driver and vibrate it for 1 to 2 minutes to loosen the soil around the steel sheet pile, produce "liquefaction" to reduce the friction of the soil on the pile, and then slowly vibrate and pull it out. If it is difficult to pull it up, stop pulling the pile, vibrate it for 1 to 2 minutes, then hammer it down 0.5 to 1.0 meters and then vibrate and pull it up.

[0094] When pulling out piles, try to separate the lower part of the steel sheet pile from the concrete before pulling out the piles. Pull up all the steel sheet piles by 1 to 2 meters in sequence to loosen them, and then pull them out one by one. For piles with curled pile tips and deformed locks, increase the pulling force and pull out the adjacent piles together.

[0095] The following points should be noted during operation: (1) To prevent adjacent sheet piles from being pulled out at the same time, the sheet piles and reinforced supports should be removed one by one; (2) The piles should be pulled out in the opposite order to the order in which the sheet piles were driven; (3) The sheet piles should be driven again to overcome the friction of the soil; (4) The pulled-out sheet piles should be cleaned of soil and sand and coated with grease; sheet piles with large deformation should be straightened, and intact sheet piles should be transported out of the construction site in a timely manner and stacked on a flat site.

[0096] The working principle and beneficial effects of the above technical solution are:

[0097] The technological principle of a Larsen steel sheet pile cofferdam construction method is that when constructing a water-stop cofferdam under the condition of bedrock covering with a high groundwater level, first carry out island cofferdam construction, and select a suitable rotary drilling rig in combination with the model and specification of the Larsen steel sheet piles, and ensure that the Larsen steel sheet piles can enter the bedrock through rotary drilling holes; the penetration of the Larsen steel sheet piles into the bedrock and the backfilling of sandy soil within the rock entry range are used as elements to establish basic constraints for the temporary stability of the steel sheet piles; then the seepage path is extended by bottom grouting, thereby achieving a good water-stopping effect; finally, according to the excavation depth of the foundation pit, waist beams and internal supports are set while digging, and after excavating to the bottom, water is collected and pumped out to provide a good working environment for the main structure construction.

[0098] The main purpose of the island cofferdam 2 is to provide a working platform for the Larsen steel sheet pile construction. The hydrological survey results of the construction area should be combined to ensure that the platform top elevation should be 0.5 to 0.7 m greater than the maximum water level elevation of the construction area; low-permeability materials are preferred for island cofferdam filling materials; geotextiles or dense mesh are laid on the water-facing surface to reduce water scouring.

[0099] The purpose of the rotary drilling guide hole 4 is to drill into the bedrock to provide basic conditions for the Larsen steel sheet pile to enter the rock; the two adjacent guide holes should be interlocked with each other. Assuming that the diameter of the guide hole pile is D, the distance between the guide hole piles can generally be 1 / 3D~1 / 2D; the depth of the guide hole entering the bedrock is not less than 1 / 2D; in case of hole collapse, full casing can be used for follow-up.

[0100] The purpose of filling sandy soil within the rock range of Larsen steel sheet piles is to provide constraints for their temporary stability through the base filling of the steel sheet piles; at the same time, it is convenient for bottom filling and grouting, and by extending the seepage path, it has a good water-stopping effect.

[0101] After the Larsen steel sheet pile cofferdam is formed, it is excavated in layers according to the depth of the foundation pit. According to the structural design, waist beams and internal supports are set while excavating. After excavating to the bottom of the foundation pit, the accumulated water in the foundation pit is pumped out to provide a relatively good working environment for the construction of the main structure.

[0102] This method of pile can effectively overcome the problem that Larsen steel sheet piles cannot penetrate into rocks, and the poor water-stopping effect at the bottom of Larsen steel sheet pile cofferdam under the condition of bedrock overburden with high groundwater level. It has simple process, safe operation and significant water-stopping effect. It can provide technical reference for the construction of Larsen steel sheet pile cofferdam under similar conditions, and has the following technical advantages:

[0103] Reliable quality: Through drilling and replacement filling, and compaction grouting after the steel sheet piles are penetrated, the bottom of the steel sheet pile cofferdam can be effectively sealed and compacted, effectively extending the seepage path, with significant water-stopping effects and greatly improved quality reliability.

[0104] Safe and controllable: The penetration of Larsen steel sheet piles is carried out by mechanical construction, and the construction process is safe and controllable; by drilling holes into the rock, the connection between the Larsen steel sheet pile cofferdam foundation and the bedrock is strengthened, the overall stability is enhanced, and the cofferdam structure is safe and controllable.

[0105] Construction period saving: In the construction process, it is difficult to install Larsen steel sheet piles in hard geological areas, and the construction period of water-stop curtain is long. The combination of steel sheet pile construction with hole grouting is adopted. The rotary drilling hole speed is fast and the steel sheet piles are easy to insert, thus effectively shortening the construction period.

[0106] Energy saving and environmental protection: The combined Larsen steel sheet pile cofferdam construction with hole grouting can use local materials for the cofferdam filling, the Larsen steel sheet piles can be recycled and reused, and the use of original soil can greatly reduce the impact on the surrounding water ecology, which is energy-saving and environmentally friendly.

[0107] Cost saving: The hole-drilling and filling replacement scheme can reduce the use of concrete while achieving a better water-stopping effect; it can avoid material waste while improving the construction efficiency of the cofferdam structure.

[0108] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0109] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0110] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation methods. They can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.

Claims

1. A Larsen steel sheet pile cofferdam construction method, characterized in that: The steps include: On-site investigation (1), island cofferdam filling (2), surveying and setting out (3), rotary drilling and hole drilling (4), hole replacement and backfilling (5), steel sheet pile sinking (6), grouting (7), foundation pit excavation and drainage (8), waist beam and internal support installation (9), construction monitoring (10), main structure construction (11) and cofferdam removal (12).

2. A Larsen steel sheet pile cofferdam construction method according to claim 1, characterized in that: In the rotary drilling and hole guiding (4): the guiding piles are designed as interlocking piles and are constructed in the order of the holes. The casing is buried and the verticality and hole position are checked to meet the requirements. The rotary drilling is then put into place and drilled. The rotary drilling and soil excavation are carried out alternately until the bottom of the casing enters the bedrock more than 0.5m. The drill residue is loaded onto a truck, covered and transported to a designated waste disposal point. The hole guiding sequence is from upstream to downstream, first facing the water surface side, then the two sides, and finally the joint is closed at the downstream point, and the piles are jumped to guide the hole.

3. A Larsen steel sheet pile cofferdam construction method according to claim 1, characterized in that: In the process of hole digging and backfilling (5), the digging and backfilling are carried out alternately one by one. After the bottom of the hole is cleaned, backfilling is carried out. Sandy soil is preferably used as backfill soil. The backfill is backfilled and compacted in layers of 20 cm to 40 cm until the top elevation of the platform is reached.

4. A Larsen steel sheet pile cofferdam construction method according to claim 1, characterized in that: The overall construction sequence of steel sheet pile sinking (6) is: first construct the cofferdams on both sides from upstream to downstream, then construct the upstream steel cofferdam, and finally construct the downstream steel cofferdam. The upstream steel cofferdam and the downstream steel cofferdam are both connected near the river bank.

5. The Larsen steel sheet pile cofferdam construction method according to claim 1 is characterized in that: In grouting (7): the replacement soil grouting and water-stopping construction adopts the penetration grouting technology, and grouting is carried out along the inside and outside of each hole along the steel sheet pile. The construction operation sequence adopts the hole-by-hole sequence method; the grouting range is the lead-in hole replacement area, among which the grouting height on the inner side of the steel sheet pile cofferdam is from the bottom of the steel sheet pile to the bottom of the main structure; the grouting height on the outer side of the steel sheet pile cofferdam is 2m above the bottom of the steel sheet pile.

6. The Larsen steel sheet pile cofferdam construction method according to claim 1, characterized in that: During the excavation of the foundation pit, the water level in the cofferdam is kept slightly lower than the bottom elevation of the foundation pit, so as not to affect the excavation construction. A small excavator is used for excavation. After the foundation pit is excavated to the designed bottom elevation, a water collection well and drainage ditch are set up in the cofferdam.

7. The Larsen steel sheet pile cofferdam construction method according to claim 1 is characterized in that: During the installation of the waist beam and inner support (9): after the excavation in the cofferdam is completed and the water level drops to 0.5m below the design elevation of the inner support, the inner support is installed layer by layer. The next step can be carried out only after the installation of each layer of purlins is completed and the quality inspection is passed; after the water-stopping reinforcement on the inner side of the cofferdam is completed, the corbel triangular bracket is welded on the steel sheet pile, and one is set every 2m. After a section of the waist beam is made into an integral part, it is directly hoisted and placed on the corbel triangular bracket, and the waist beam and the steel sheet pile are padded and tightly connected, and then welded firmly.

8. A Larsen steel sheet pile cofferdam construction method according to claim 7, characterized in that: During the installation of the waist beam and internal support (9), cylindrical steel supports are used for the internal support of the cofferdam. During the excavation of the foundation pit, the water level in the cofferdam is kept slightly lower than the bottom elevation of the foundation pit so as not to affect the excavation construction. When the excavation is 0.5m below the design elevation of the waist beam, the first and second layers of internal support are installed. When installing the internal support, triangular brackets are welded on the side walls of the steel sheet piles as an auxiliary measure.

9. A Larsen steel sheet pile cofferdam construction method according to claim 8, characterized in that: Construction monitoring (10) includes: stress of steel sheet piles; stress of cofferdam purlins and supporting structures; horizontal displacement of cofferdam top.

10. A Larsen steel sheet pile cofferdam construction method according to claim 9, characterized in that: The monitoring point arrangement for construction monitoring (10) is as follows: A certain number of monitoring points are arranged for the steel sheet pile monitoring points, among which the vertical points are located in the middle of each layer of purlins, and the bottom layer of points are located in the middle of the bottom layer of purlins and the bottom of the foundation pit; The purlins and internal supports of each floor are arranged in the same position; After the steel sheet piles are sunk, the horizontal and vertical displacement monitoring of the cofferdam is carried out by setting measuring points at the center lines and four corners of the four sides of the entire cofferdam on the top of the steel sheet piles, and collecting data using a total station and fixed prism.