Steel pipe pile based on trestle fishing type bridge forming and bridge forming method
Through the design of the cantilever guide frame and hydraulic vibrating hammer with bolts fixed connection, the problem of the difficulty of docking steel pipe piles in the fishing trest construction is solved, the construction efficiency and stability are improved, and the efficient pile sinking of steel pipe piles is realized. Reusable.
Patent Information
- Application Number
- CN202411300732.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2024-11-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the fishing method, it is difficult to connect steel pipe piles in the construction of the trestle, and the environment is located on the water surface, and manual welding is difficult and the risk factor is high, resulting in low construction efficiency.
The steel pipe pile body is fixed by using cantilever guide frame and hydraulic vibrating hammer and crawler crane to sink piles. Through the design of docking grooves and protrusions, the steel pipe pile body is fixedly connected by bolts to avoid manual welding and increase the accuracy and stability of docking. , and facilitate disassembly and reuse after construction is completed.
It reduces the difficulty of docking steel pipe piles, improves construction efficiency, reduces the risk of manual welding, and enhances the stability and reusability of steel pipe piles.
Smart Images

Figure CN118997206A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of trestle construction, in particular to a steel pipe pile based on trestle fishing-type bridge construction and a bridge construction method. Background Art
[0002] A trestle is a bridge structure for locomotives and vehicles to drive onto the ferry. It is composed of piers, abutments, and steel beams. The lower structure of the trestle is concrete or reinforced concrete piers and abutments; the upper structure is steel plate beams or steel truss beams.
[0003] The Chinese invention with publication number CN117552339A discloses a method for constructing a steel temporary bridge across a river based on a combination of a cantilever push-out method and a fishing method, which solves the construction problem of a small-span steel temporary bridge, can reduce the investment in personnel and equipment, and has the advantages of low cost, short construction period and significant economic benefits.
[0004] At present, during the construction of the fishing method trestle, for the construction of trestles of different heights, steel pipe piles need to be transported, hoisted, docked and sunk. During the docking process of the steel pipe piles, the steel pipe piles need to be welded manually. Since the construction environment of the fishing method trestle is located on the water surface, manual welding is difficult, the risk factor is high, and the overall construction efficiency is low. To this end, the present invention proposes a steel pipe pile based on the trestle fishing type bridge and a bridge construction method to solve the above problems. Summary of the invention
[0005] The purpose of the present invention is to provide a steel pipe pile and a bridge construction method based on a pier fishing-type bridge construction, so as to solve the problem of difficulty in connecting steel pipe piles during the fishing-type pier construction proposed in the above background technology.
[0006] To achieve the above object, the present invention provides the following technical solution: a trestle fishing bridge forming method, which specifically comprises the following steps:
[0007] Step 1: Install the cantilever guide frame. The cantilever guide frame is formed into a whole by processing Bailey beam and steel. The end of the cantilever guide frame is pinned to the Bailey beam at the front end of the trestle that has been laid. The front end of the cantilever guide frame is reserved with holes according to the designed pile position and a guide system is set;
[0008] Step 2, steel pipe pile construction, including steel pipe pile transportation, hoisting, docking and pile sinking. When the steel pipe pile is docked, the steel pipe pile is erected by a steel wire rope and a crawler crane, and then hoisted to the installed cantilever guide frame. When the steel pipe pile is sunk, the crawler crane cooperates with the hydraulic vibrating hammer to give the steel pipe pile forced vibration and transmit it to the soil layer in contact with the pile to cause changes in the physical properties of the soil and reduce the friction resistance of the soil around the pile, thereby achieving the purpose of sinking the steel pipe pile;
[0009] Step 3: Bailey beam construction: divided into multiple groups, hoisted and transported to the trestle in sequence, first connected to the completed trestle, and then installed the support frame to complete the splicing between the two groups;
[0010] Step 4: Construction of the bridge deck and its accessories. The accessory facilities include railings, cable ducts, water supply pipes and safety signs. The cable ducts and water supply pipes of the pier are installed on the outside of the pier guardrails.
[0011] Preferably, in the step one, the formed trestle is first used as a rough positioning guide for the steel pipe piles to be constructed, and then the fine-tuning system on the front cantilever guide frame is used to complete the precise positioning of the steel pipe piles. During construction, the guide frame is processed into an integral structure. After the construction of one span of the trestle is completed, the guide frame is hoisted as a whole and connected to the main beam of the trestle by a crawler crane, the pile position is accurately released, and after the position of the guide wheel is adjusted to control the pile position, the crawler crane cooperates with the vibrating hammer to drive the piles along the measured hole position. After a row of steel pipe piles is sunk, the guide frame is removed, the distribution beam, main beam and bridge deck system are laid, and then the construction of the next trestle hole is started.
[0012] Preferably, in the step 2, the steel pipe piles are rolled and welded in the factory using Q235 steel plates, hoisted onto a flatbed truck using a car crane, and transported to the trestle working surface after being firmly fixed, and the steel pipe piles are hoisted from the flatbed truck to the erected trestle using a crawler crane, and fixed measures are taken to prevent them from rolling, and an oxyacetylene flame cutting torch is used to cut a 3 cm diameter hole on the top of the steel pipe pile to install a shackle, and after the steel pipe pile falls to the bottom of the riverbed and the verticality of the steel pipe pile is adjusted to stabilize it, the steel pipe pile sinking operation is carried out, and the operation steps are: using a crawler crane to hoist the hydraulic vibratory hammer to the top of the erected steel pipe pile, operating the hydraulic vibratory hammer so that its hydraulic clamps clamp the steel pipe pile, turning on the vibration switch, and the steel pipe pile vibrates and sinks under the action of the vibration force of the vibratory hammer, and when the steel pipe piles are sunk, ensure that the joints of the steel pipe piles in the same row are staggered to avoid the formation of the most unfavorable cross-section.
[0013] Preferably, the steel pipe pile is composed of a plurality of steel pipe pile bodies butted against each other, a plurality of butt joint grooves distributed in a circular array are opened at the end of the steel pipe pile body, and a protrusion is formed between two adjacent butt joint grooves, the butt joint grooves and the protrusions are both arc-shaped structures and fit each other, and the butt joint grooves and the protrusions at the ends of two adjacent steel pipe pile bodies correspond one to one.
[0014] Preferably, a positioning retaining ring is welded and fixed to the inner wall of the end of the steel pipe pile body, a plurality of connecting sockets distributed in a circular array are provided on the surface of the positioning retaining ring, and the connecting sockets correspond to the docking grooves, a protrusion corresponding to the connecting socket is fixed to the inner wall of the positioning retaining ring, and a thread is provided inside the protrusion.
[0015] Preferably, a positioning hole is formed through the surface of the raised portion. After two adjacent steel pipe pile bodies are butt-jointed, the positioning hole corresponds to the connecting socket. A bolt is passed through the inner cavity of the positioning hole and is fixed to the protrusion after passing through the connecting socket. The two adjacent steel pipe pile bodies are fixedly connected by the bolt, and the two positioning retaining rings are squeezed and fitted against each other.
[0016] Preferably, in the step 2, after the steel pipe piles are sunk, flat joints and diagonal braces are welded and fixed between two adjacent steel pipe piles, a transverse I-beam is arranged at the upper end of the steel pipe pile and is fixedly connected to the upper ends of a plurality of steel pipe pile bodies, a Bailey beam perpendicular to the transverse I-beam is fixedly connected to the upper side of the transverse I-beam, a plurality of Bailey beams are arranged to form a Bailey beam, a patterned steel plate is fixed on the upper side of the Bailey beam, and guardrail frames are arranged on both sides of the patterned steel plate.
[0017] Preferably, in the step three, the Bailey beam is transported by a widened flatbed truck, the upper structure is installed by a 25t truck crane, the Bailey truss longitudinal beam is laid on the load-bearing beam, the Bailey truss is assembled in blocks in advance, transported to the laying position for lifting and installation, and when the Bailey beam is erected, firstly, measurement and layout are carried out on the top cross beam of the lower structure, the exact position of the Bailey frame is determined, and the shock-absorbing rubber sheet is installed, and then the crawler crane is used to lift the unit Bailey beam to connect it to the Bailey beam of the built trestle, and the limiter is welded.
[0018] Preferably, in step 4, a plurality of patterned steel plates are gradually laid as the construction progresses to form a bridge deck, and the guardrail is promptly installed after the construction of each span of the pier deck is completed, and the vertical poles and horizontal poles of the guardrail are painted with red and white warning reflective paint, and the pier is equipped with safety warning lights, life jackets and fire-fighting equipment at specified intervals.
[0019] Compared with the prior art, the present invention has the following beneficial effects:
[0020] The present invention arranges a steel pipe pile to be composed of a plurality of steel pipe pile bodies butted against each other, opens a plurality of butt joint grooves at the end of the steel pipe pile body, forms a convex portion between two adjacent butt joint grooves, and pre-welds a fixed positioning retaining ring on the inner wall of the end of the steel pipe pile body, thereby facilitating butt jointing of two adjacent steel pipe pile bodies. After butt jointing, the two adjacent steel pipe pile bodies can be fixedly connected by bolts without manual welding and fixing, thereby reducing the difficulty of butt jointing of the steel pipe piles, and the piles can be easily disassembled and reused at a later time. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a front schematic diagram of the overall structure of the present invention;
[0022] Figure 2 It is a side schematic diagram of the overall structure of the present invention;
[0023] Figure 3 This is a schematic diagram of the connection of the steel pipe pile body structure of the present invention;
[0024] Figure 4 It is a schematic diagram of the explosion of the steel pipe pile body structure of the present invention.
[0025] In the figure: 1. steel pipe pile body; 11. docking groove; 111. raised part; 112. positioning hole; 12. positioning retaining ring; 13. connecting socket; 14. protrusion; 2. transverse I-beam; 3. Bailey beam; 4. patterned steel plate; 5. guardrail frame; 6. flat joint; 7. diagonal brace. DETAILED DESCRIPTION
[0026] In order to make the purpose and technical solution of the present invention clearly and completely described, and the advantages more clearly understood, the embodiments of the present invention are further described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are part of the embodiments of the present invention, rather than all of the embodiments, and are only used to explain the embodiments of the present invention, and are not used to limit the embodiments of the present invention. All other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0027] In the description of the present invention, it should be noted that the terms "center", "middle", "upper", "lower", "left", "right", "inner", "outer", "top", "bottom", "side", "vertical", "horizontal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "one", "first", "second", "third", "fourth", "fifth", "sixth" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0028] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0029] For the purpose of simplicity and illustration, the principles of the embodiments are mainly described by reference to examples. In the following description, many specific details are proposed to provide a thorough understanding of the embodiments. However, it is obvious that for those of ordinary skill in the art, these embodiments may not be limited to these specific details in practice. In some instances, known methods and structures are not described in detail to avoid making these embodiments unnecessarily difficult to understand. In addition, all embodiments can be used in combination with each other.
[0030] See also Figures 1 to 4 , the present invention provides a technical solution:
[0031] Embodiment 1, a trestle fishing bridge construction method, specifically comprises the following steps:
[0032] Step 1: Install the cantilever guide frame. The cantilever guide frame is formed into a whole by processing Bailey beam and steel. The end of the cantilever guide frame is pinned to the Bailey beam at the front end of the trestle that has been laid. The front end of the cantilever guide frame is reserved with holes according to the designed pile position and a guide system is set;
[0033] The Bailey trusses are assembled into Bailey beams at the back yard, and transported to the front yard by flatbed trucks for assembly and construction. After the Bailey beams and bridge decks are laid on the pile tops, the crawler crane moves forward to drive the next span of steel pipe piles. This method is used step by step.
[0034] After the main project is completed and the pier's mission is over, the pier will be dismantled. Before dismantling the pier, the structural safety of the undismantled section of the pier should be checked first. Dismantling construction can only be carried out after ensuring the structural safety;
[0035] During construction, the following construction measurement control technologies and control methods are planned to be used for construction layout, positioning and construction measurement control. Various measurement methods complement and check each other to ensure that the measurement accuracy meets the construction quality requirements:
[0036] ① The domestically produced Huace GPS combined with the Swiss Leica-TS06 total station three-dimensional coordinate positioning technology is used for abutment construction, trestle axis control, superstructure and other construction control;
[0037] ②Accurately position the assembled cantilever guide positioning frame in three dimensions, then drive the steel pipe piles and use a total station to control the verticality;
[0038] ③ The automatic precision level is used for leveling height measurement technology, which is used in the whole process of the trestle construction. The abutment part of this trestle is constructed first, and then the appropriate length is filled to connect with the land access road after the abutment is constructed;
[0039] Step 2, steel pipe pile construction, including steel pipe pile transportation, hoisting, docking and pile sinking. When the steel pipe pile is docked, the steel pipe pile is erected by a steel wire rope and a crawler crane, and then hoisted to the installed cantilever guide frame. When the steel pipe pile is sunk, the crawler crane cooperates with the hydraulic vibrating hammer to give the steel pipe pile forced vibration and transmit it to the soil layer in contact with the pile to cause changes in the physical properties of the soil and reduce the friction resistance of the soil around the pile, thereby achieving the purpose of sinking the steel pipe pile;
[0040] The steel pipe pile is driven by crawler crane and hydraulic vibratory hammer. The process is mainly based on the hydraulic vibratory hammer in the vibration pile driving theory. During the steel pipe pile driving process, its verticality should be monitored. When the verticality deviation exceeds 1%, the pile driving operation should be stopped, and the crawler crane should be directed to correct the verticality of the steel pipe pile, and then the driving should be continued. When the steel pipe pile is driven to 50cm above the guide frame plane, the power supply of the vibratory hammer is turned off, the hydraulic clamp is released, and the hydraulic vibratory hammer is hoisted onto the built trestle bridge deck to dismantle the guide frame.
[0041] After the guide frame is removed, the steel pipe piles are sunk for the second time according to the previous construction steps, and driven to the designed elevation. Considering the consolidation effect of the piles, the pile length is mainly controlled. If the deviation from the designed pile length is large, the construction should be stopped, and the actual situation on site should be studied and solved together with all parties;
[0042] Step 3: Bailey beam construction: divided into multiple groups, hoisted and transported to the trestle in sequence, first connected to the completed trestle, and then installed the support frame to complete the splicing between the two groups;
[0043] When assembling the truss group, the Bailey pieces are connected by pins along the bridge direction and connected by supporting flower racks or scissor braces in the transverse direction. After the Bailey pins are installed, the safety pins must be installed to prevent the Bailey pins from falling off, and the supporting flower racks and Bailey pieces are fixed with bolts;
[0044] Step 4: Construction of the bridge deck and its ancillary facilities, including railings, cable ducts, water supply ducts and safety signage facilities. The cable ducts and water supply ducts of the trestle are set outside the trestle guardrails;
[0045] After the Bailey beam is installed, I-beams are laid at intervals of 40 cm as transverse distribution beams, and are locked with special saddle bolts and the upper chords of the Bailey beams. After the transverse beams are fixed, surface channel steels are laid according to the intervals, and the surface channel steels are intermittently welded and fixed to the transverse beams.
[0046] In order to supplement the construction process of the cantilever guide frame, the present application also has the feature of first using the formed trestle as a rough positioning guide for the steel pipe piles to be constructed, and then using the fine-tuning system on the front cantilever guide frame to complete the precise positioning of the steel pipe piles. During construction, the guide frame is processed into an integral structure. After the construction of one span of the trestle is completed, the guide frame is hoisted as a whole and connected to the main beam of the trestle using a crawler crane. The pile position is accurately released, and after the guide wheel position is adjusted to control the pile position, the crawler crane cooperates with a vibrating hammer to drive the piles along the measured hole position. After a row of steel pipe piles is sunk, the guide frame is removed, the distribution beam, main beam and bridge deck system are laid, and then the construction of the next trestle hole is started.
[0047] In order to sink the steel pipe piles, the present application also has the following steps: in step 2, the steel pipe piles are rolled and welded in the factory using Q235 steel plates, hoisted onto a flatbed truck using a car crane, and transported to the trestle working surface after being firmly fixed; a crawler crane is used to lift the steel pipe piles from the flatbed truck to the erected trestle, and fixing measures are taken to prevent them from rolling; an oxyacetylene flame cutting torch is used to cut a 3cm diameter hole on the top of the steel pipe pile to install a shackle; after the steel pipe piles fall to the bottom of the riverbed and the verticality of the steel pipe piles is adjusted to stabilize them, the steel pipe pile sinking operation is carried out, and the operation steps are as follows: a crawler crane is used to lift the hydraulic vibratory hammer to the top of the erected steel pipe pile, the hydraulic vibratory hammer is operated to clamp the steel pipe pile with its hydraulic clamps, the vibration switch is turned on, and the steel pipe piles vibrate and sink under the action of the vibration force of the vibratory hammer, and when the steel pipe piles are sunk, the joints of the steel pipe piles in the same row are ensured to be staggered to avoid the formation of the most unfavorable cross-section.
[0048] In order to facilitate the docking of steel pipe piles, the steel pipe pile of the present application is composed of a plurality of steel pipe pile bodies 1 docked with each other, a plurality of docking grooves 11 distributed in a circular array are opened at the end of the steel pipe pile body 1, and a convex portion 111 is formed between two adjacent docking grooves 11, the docking grooves 11 and the convex portion 111 are both arc-shaped structures and are adapted to each other, and the docking grooves 11 and the convex portions 111 at the ends of two adjacent steel pipe pile bodies 1 correspond to each other one by one, such as Figure 4As shown, when the two steel pipe pile bodies 1 are close to each other for docking, the docking groove 11 and the protrusion 111 can form mutual constraints after splicing, limiting the relative rotation and mutual misalignment of the two steel pipe pile bodies 1, thereby improving the accuracy and stability of docking. In addition, a positioning retaining ring 12 is welded and fixed to the inner wall of the end of the steel pipe pile body 1. When the two steel pipe pile bodies 1 are docked with each other, the two positioning retaining rings 12 can be relatively squeezed to form mutual support, avoiding deformation and damage of the docking end faces of the two steel pipe pile bodies 1 due to excessive pressure, thereby improving the overall strength and stability of the steel pipe pile after docking. A plurality of connecting sockets 13 distributed in a ring array are provided on the surface of the positioning retaining ring 12, and the connecting sockets 13 correspond to the docking grooves 11. A convex block 14 corresponding to the connecting socket 13 is fixed to the inner wall of the positioning retaining ring 12, and a thread is provided inside the convex block 14. The connecting socket 13 can be passed through by bolts, and the thread inside the convex block 14 can be connected and fixed with the bolts.
[0049] In order to facilitate the reuse of steel pipe piles, the present application also has a positioning hole 112 that penetrates the surface of the raised portion 111. After the two adjacent steel pipe pile bodies 1 are butt-jointed, the positioning hole 112 corresponds to the connecting socket 13. A bolt is passed through the inner cavity of the positioning hole 112 and is fixed to the protrusion 14 after passing through the connecting socket 13. The two adjacent steel pipe pile bodies 1 are fixedly connected by the bolt, and the two positioning retaining rings 12 are squeezed and fitted against each other. The two steel pipe pile bodies 1 of the present device can be connected and fixed by bolts. Compared with traditional welding butt-jointing, the steel pipe pile butt-jointing work of the present device is more convenient and labor-saving, and after the steel pipe piles are sunk, they can still be quickly butt-jointed, thereby changing the overall height of the steel pipe piles to adapt to piers of different heights. In addition, since the pier needs to be dismantled after the construction is completed, compared with the welding butt-jointing of traditional steel pipe piles, the steel pipe piles of the present device only need to remove the bolts to separate from each other, thereby greatly improving the reusability.
[0050] In order to improve the stability of the steel pipe piles, the present application also has the following steps: in step 2, after the steel pipe piles are sunk, a flat joint 6 and a diagonal brace 7 are welded and fixed between two adjacent steel pipe piles to connect and fix the multiple steel pipe piles in pairs. A transverse I-beam 2 is arranged at the upper end of the steel pipe pile and is fixedly connected to the upper ends of multiple steel pipe pile bodies 1. A Bailey beam 3 perpendicular to the transverse I-beam 2 is fixedly connected to the upper side of the transverse I-beam 2. A plurality of Bailey beams 3 are arranged to form Bailey beams. A patterned steel plate 4 is fixed to the upper side of the Bailey beam 3. Guardrail frames 5 are arranged on both sides of the patterned steel plate 4.
[0051] In order to erect the Bailey beam, the present application also has the following characteristics in step three: the Bailey beam is transported by a widened flatbed truck, the upper structure is installed by a 25t truck crane, the Bailey truss longitudinal beam is laid on the load-bearing beam, the Bailey truss is assembled in blocks in advance, transported to the laying position for lifting and installation, and when the Bailey beam is erected, firstly, measurement and layout are carried out on the top crossbeam of the lower structure, the exact position of the Bailey frame is determined, and the shock-absorbing rubber sheet is installed, and then the crawler crane is used to lift the unit Bailey beam and connect it to the Bailey beam of the built trestle, and the limiter is welded.
[0052] In order to construct the ancillary facilities of the bridge deck, the present application also has a step four in which a plurality of patterned steel plates 4 are gradually laid as the construction progresses to form the bridge deck, and the guardrail frame 5 is promptly installed after the construction of each span of the pier deck is completed. The vertical poles and horizontal poles of the guardrail frame 5 are painted with red and white warning reflective paint, and the pier is equipped with safety warning lights, life jackets and fire-fighting equipment at specified intervals.
[0053] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A steel pipe pile based on a trestle fishing bridge, characterized in that: The steel pipe pile is composed of a plurality of steel pipe pile bodies (1) butted against each other, a plurality of butt joint grooves (11) distributed in a ring array are provided at the end of the steel pipe pile body (1), and a convex portion (111) is formed between two adjacent butt joint grooves (11), the butt joint grooves (11) and the convex portion (111) are both arc-shaped structures and are adapted to each other, and the butt joint grooves (11) and the convex portions (111) at the ends of two adjacent steel pipe pile bodies (1) correspond to each other one by one; A positioning retaining ring (12) is welded and fixed to the inner wall of the end of the steel pipe pile body (1), a plurality of connecting holes (13) distributed in a ring array are provided on the surface of the positioning retaining ring (12), and the connecting holes (13) correspond to the docking grooves (11), and a convex block (14) corresponding to the connecting hole (13) is fixed to the inner wall of the positioning retaining ring (12), and a thread is provided inside the convex block (14).
2. The steel pipe pile for bridge-building based on trestle fishing type according to claim 1, characterized in that: A positioning hole (112) is formed through the surface of the raised portion (111). After two adjacent steel pipe pile bodies (1) are butt-jointed, the positioning hole (112) corresponds to the connecting socket (13). A bolt is passed through the inner cavity of the positioning hole (112) and is fixed to the projection (14) after passing through the connecting socket (13). The two adjacent steel pipe pile bodies (1) are fixedly connected by the bolt, and the two positioning retaining rings (12) are pressed and fitted against each other.
3. A pier fishing bridge construction method according to any one of claims 1-2, characterized in that: The specific steps include: Step 1: Install the cantilever guide frame. The cantilever guide frame is formed into a whole by processing Bailey beam and steel. The end of the cantilever guide frame is pinned to the Bailey beam at the front end of the trestle that has been laid. The front end of the cantilever guide frame is reserved with holes according to the designed pile position and a guide system is set; Step 2, steel pipe pile construction, including steel pipe pile transportation, hoisting, docking and pile sinking. When the steel pipe pile is docked, the steel pipe pile is erected by a steel wire rope and a crawler crane, and then hoisted to the installed cantilever guide frame. When the steel pipe pile is sunk, the crawler crane cooperates with the hydraulic vibrating hammer to give the steel pipe pile forced vibration and transmit it to the soil layer in contact with the pile to cause changes in the physical properties of the soil and reduce the friction resistance of the soil around the pile, thereby achieving the purpose of sinking the steel pipe pile; Step 3: Bailey beam construction: divided into multiple groups, hoisted and transported to the trestle in sequence, first connected to the completed trestle, and then installed the support frame to complete the splicing between the two groups; Step 4: Construction of the bridge deck and its accessories. The accessory facilities include railings, cable ducts, water supply pipes and safety signs. The cable ducts and water supply pipes of the pier are installed on the outside of the pier guardrails.
4. A trestle fishing bridge construction method according to claim 3, characterized in that: In the step 1, the formed trestle is first used as a rough positioning guide for the steel pipe piles to be constructed, and then the fine-tuning system on the front cantilever guide frame is used to complete the precise positioning of the steel pipe piles. During construction, the guide frame is processed into an integral structure. After the construction of a span of the trestle is completed, the guide frame is hoisted as a whole and connected to the main beam of the trestle by a crawler crane, the pile position is accurately released, and after the position of the guide wheel is adjusted to control the pile position, the crawler crane cooperates with the vibrating hammer to pile along the measured hole position. After a row of steel pipe piles is sunk, the guide frame is removed, the distribution beam, the main beam and the bridge deck system are laid, and then the next hole of the trestle construction is started.
5. A trestle fishing bridge construction method according to claim 4, characterized in that: In the step 2, the steel pipe pile is formed by rolling and welding Q235 steel plates in the factory, and is hoisted onto a flatbed truck by a car crane, fixed firmly, and then transported to the trestle working surface, and the steel pipe pile is hoisted from the flatbed truck to the erected trestle by a crawler crane, and fixed measures are taken to prevent it from rolling, and an oxyacetylene flame cutting torch is used to cut a 3cm diameter hole on the top of the steel pipe pile to install a shackle, and after the steel pipe pile falls to the bottom of the riverbed and the verticality of the steel pipe pile is adjusted to be stable, the steel pipe pile is sunk. The operation steps are: using a crawler crane to hoist the hydraulic vibratory hammer to the top of the erected steel pipe pile, operating the hydraulic vibratory hammer to clamp the steel pipe pile with its hydraulic clamp, turning on the vibration switch, and the steel pipe pile vibrates and sinks under the action of the vibration force of the vibratory hammer. When the steel pipe pile is sunk, ensure that the joints of the steel pipe piles in the same row are staggered to avoid the formation of the most unfavorable section.
6. A trestle fishing bridge construction method according to claim 5, characterized in that: In the step 2, after the steel pipe piles are sunk, a flat joint (6) and a diagonal brace (7) are welded and fixed between two adjacent steel pipe piles, a transverse I-beam (2) is arranged at the upper end of the steel pipe pile and is fixedly connected to the upper ends of a plurality of steel pipe pile bodies (1), a Bailey beam (3) perpendicular thereto is fixedly connected to the upper side of the transverse I-beam (2), a plurality of Bailey beams (3) are arranged to form Bailey beams, a patterned steel plate (4) is fixed to the upper side of the Bailey beam (3), and guardrail frames (5) are arranged on both sides of the patterned steel plate (4).
7. A trestle fishing bridge construction method according to claim 6, characterized in that: In the step three, the Bailey beam is transported by a widened flatbed truck, and the upper structure is installed by a 25t truck crane. The Bailey truss longitudinal beam is laid on the load-bearing beam. The Bailey truss is assembled in blocks in advance and transported to the laying position for lifting and installation. When the Bailey beam is erected, first measure and lay out on the top crossbeam of the lower structure, determine the exact position of the Bailey frame and install the shock-absorbing rubber sheet, then use a crawler crane to lift the unit Bailey beam and connect it to the Bailey beam of the built trestle, and weld the limiter.
8. A trestle fishing bridge construction method according to claim 7, characterized in that: In the step 4, a plurality of patterned steel plates (4) are gradually laid as the construction progresses to form a bridge deck, and a guardrail frame (5) is promptly installed after the construction of each span of the trestle bridge deck is completed. The vertical poles and horizontal poles of the guardrail frame (5) are painted with red and white warning reflective paint, and safety warning lights, life jackets and fire-fighting equipment are installed on the trestle at specified intervals.
Citation Information
Patent Citations
Multi-terrain cast-in-place bridge steel trestle, platform and cofferdam combined construction method
CN115110419A
Steel-pipe pile basis combination steel trestle
CN204530433U
Reinforced concrete hollow square pile connecting device
CN208293572U