Hole periphery backfill grouting construction method
By using the misalignment distribution of grouting holes between the inner and outer tubes and the limit pins and elastic ring mechanisms in the grouting pipe, the foreign fluid problem caused by the open grouting holes of the grouting pipes is solved, and efficient hole backfilling is achieved Grouting construction.
Patent Information
- Application Number
- CN202411201314.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-22
AI Technical Summary
During the grouting and reinforcement process around the tunnel hole, the grouting holes of the embedded grouting pipe are likely to cause foreign fluid to flow into the grouting pipe.
The grouting pipe design adopts a controllable grouting hole, where the grouting holes of the inner and outer pipes do not coincide and dislocation, and the grouting holes are closed or opened through the limiting pins and elastic ring mechanisms to ensure that The grouting pipe is not open when grouting is not allowed to enter foreign fluid.
It effectively prevents foreign fluid from entering the grouting pipe, ensures the safety and quality of the grouting process, and realizes effective injection and curing and reinforcement of high-pressure concrete slurry.
Smart Images

Figure CN118997794A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a backfill grouting construction method around a hole, belonging to the technical field of backfill grouting construction. Background Art
[0002] When grouting reinforcement is performed around the tunnel hole, a grouting pipe for grouting needs to be pre-buried. The existing grouting pipe is provided with a grouting hole for grouting (such as the Chinese patent announcement number CN221002083U). Although the slurry during backfill grouting can be injected into the soil around the tunnel hole through the grouting hole of the grouting pipe, when grouting is not performed, the grouting hole of the pre-buried grouting pipe is open, which easily leads to the problem of foreign fluid flowing into the grouting pipe. Summary of the invention
[0003] In order to solve the above technical problems, the present invention provides a hole perimeter backfill grouting construction method.
[0004] The present invention is achieved through the following technical solutions.
[0005] The invention provides a backfill grouting construction method for tunnel periphery, comprising: using a grouting pipe with controllable grouting holes to be closed or opened to be pre-buried in a soil layer at a tunnel periphery, and then performing backfill grouting.
[0006] The construction process is specifically as follows: the outer tube is inserted into the soil layer at the edge of the tunnel, and then the inner tube is inserted into the outer tube, and the limit pins are symmetrically inserted into the pin holes on both sides of the outer tube; the control push sleeve is screwed into the outside of the outer tube, and the push sleeve pushes the inner tube pressure spring ring downward, and the inner tube slides into the outer tube, until the grouting hole of the inner tube coincides with the grouting hole of the outer tube, the grouting hole path of the grouting tube as a whole is unobstructed to the soil layer at the edge of the tunnel, realizing the process of controllable grouting hole closing or opening in the inner tube and the outer tube, and then injecting slurry to carry out backfill grouting construction around the tunnel, so that the high-pressure concrete slurry flows into the soil layer at the edge of the tunnel through the grouting hole for solidification and reinforcement.
[0007] The grouting pipe comprises: an inner layer pipe and an outer layer pipe both of which are provided with grouting holes. The inner layer pipe can only be slidably inserted into the outer layer pipe. The grouting holes of the inner layer pipe and the outer layer pipe are coaxial, non-overlapping and staggered.
[0008] The outer tube is provided with a pin hole through which a limit pin is installed, and the inner tube is provided with an inwardly concave limit groove. The limit pins are two pin holes on both sides of the outer tube that are symmetrically inserted into the limit groove of the inner tube; the length of the limit groove on the outside of the inner tube is equal to the distance from the grouting hole of the inner tube to the grouting hole of the outer tube until they are offset to overlap.
[0009] The bottom of the outer tube shown is in a cone shape for easy insertion of the bottom of the outer tube into the soil layer at the side of the tunnel.
[0010] An elastic ring made of elastic rubber is installed in the outer tube, and the bottom of the inner tube is against the elastic ring.
[0011] The top of the inner tube protrudes out of the tube opening of the outer tube, and a push sleeve is screwed onto the outer tube, and the push sleeve abuts against the top of the inner tube.
[0012] The beneficial effects of the present invention are as follows: the grouting pipe is pre-buried in the soil layer at the side of the tunnel hole, and the grouting holes of the inner pipe and the grouting holes of the outer pipe do not overlap but are staggered, so that the grouting hole path of the grouting pipe as a whole is not in an open state, thereby preventing foreign fluid from flowing from the grouting holes of the outer pipe into the grouting holes of the inner pipe, and solving the problem of foreign fluid flowing into the inside of the grouting pipe. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of the external structure of the present invention;
[0014] Figure 2 It is a cross-sectional view of the grouting holes of the inner layer pipe and the outer layer pipe of the present invention, in which the grouting holes are coaxial and do not overlap;
[0015] Figure 3 It is a coaxially coincident cross-sectional view of the grouting holes of the inner layer pipe and the grouting holes of the outer layer pipe of the present invention;
[0016] In the figure: 1- grouting pipe; 11- grouting hole; 12- inner layer pipe; 13- outer layer pipe; 14- elastic ring; 15- limit pin; 16- push sleeve; 2- soil layer beside the tunnel. DETAILED DESCRIPTION
[0017] The technical solution of the present invention is further described below, but the scope of protection claimed is not limited to the description.
[0018] like Figure 1 shown.
[0019] The present application discloses a backfill grouting construction method for a tunnel, which specifically includes pre-burying a grouting pipe 1 with a controllable grouting hole 11 to close or open the grouting pipe 1 in a soil layer 2 at the side of the tunnel for backfill grouting.
[0020] The grouting pipe 1 comprises: an inner pipe 12 and an outer pipe 13 both of which are provided with grouting holes 11. The inner pipe 12 can only be slidably inserted into the outer pipe 13. The grouting holes 11 of the inner pipe 12 and the grouting holes 11 of the outer pipe 13 are coaxially arranged and do not overlap. Figure 2 shown.
[0021] The outer tube 13 is provided with a pin hole through which a limiting pin 15 is installed, and the inner tube 12 is provided with a concave limiting groove. The limiting pin 15 is symmetrically inserted into the limiting groove of the inner tube 12 from the pin holes on both sides of the outer tube 13, ensuring that the inner tube 12 does not rotate in the outer tube 13 but can only slide, so that the grouting hole 11 of the inner tube 12 and the grouting hole 11 of the outer tube 13 are on the same axis. At the same time, the length of the limiting groove outside the inner tube 12 is equal to the displacement of the grouting hole 11 of the inner tube 12 and the grouting hole 11 of the outer tube 13 to the overlap stroke. After the grouting hole 11 of the inner tube 12 and the grouting hole 11 of the outer tube 13 overlap, the limiting pin 15 is limited by the top edge of the limiting groove.
[0022] The bottom of the outer tube 13 is in a cone shape, which is convenient for the bottom of the outer tube 13 to be inserted into the soil layer 2 at the side of the tunnel.
[0023] An elastic ring 14 made of elastic rubber is installed in the outer tube 13 , and the bottom of the inner tube 12 abuts against the elastic ring 14 .
[0024] The top of the inner tube 12 protrudes from the tube opening of the outer tube 13 , and a push sleeve 16 is screwed onto the outer tube 13 , and the push sleeve 16 abuts against the top of the inner tube 12 .
[0025] After the pushing sleeve 16 is screwed into the outer tube 13 and abuts the limiting pin 15, the top of the limiting groove of the inner tube 12 abuts against the limiting pin 15 for limiting the position, the spring ring 14 of the inner tube 12 is pushed down by the pushing sleeve 16, and the inner tube 12 slides into the outer tube 13. At this time, the grouting hole 11 of the inner tube 12 coincides with the grouting hole 11 of the outer tube 13.
[0026] During the operation and construction of the present application, the outer tube 13 with a cone-shaped bottom is inserted into the soil layer 2 at the edge of the tunnel hole, and then the inner tube 12 is inserted into the outer tube 13. When the limiting groove of the inner tube 12 coincides with the pin hole of the outer tube 13, the pin holes on both sides of the outer tube 13 are symmetrically inserted with limiting pins 15, so that the limiting pins 15 are inserted into the limiting groove of the inner tube 12, so that the grouting holes 11 of the inner tube 12 and the grouting holes 11 of the outer tube 13 are coaxially non-coincidentally staggered. At this time, the grouting tube 1 is pre-buried, as shown in FIG. Figure 2 As shown; because when the grouting pipe 1 is pre-buried, the grouting holes 11 of the inner layer pipe 12 and the grouting holes 11 of the outer layer pipe 13 are not overlapped and are staggered, so that the grouting holes 11 of the grouting pipe 1 as a whole are not in an open state, thereby preventing foreign fluid from flowing from the grouting holes 11 of the outer layer pipe 13 into the grouting holes 11 of the inner layer pipe 12, and solving the problem of foreign fluid flowing into the inside of the grouting pipe.
[0027] When backfill grouting is required, the control push sleeve 16 is screwed into the outside of the outer tube 13, and the push sleeve 16 pushes the inner tube 12 to push the spring ring 14 downward, and the inner tube 12 slides into the outer tube 13, until the grouting hole 11 of the inner tube 12 coincides with the grouting hole 11 of the outer tube 13, the grouting hole 11 of the grouting tube 1 as a whole is unobstructed to the soil layer 2 at the edge of the tunnel, realizing the process of closing or opening the controllable grouting hole 11 in the inner tube 12 and the outer tube 13, and then injecting slurry to carry out backfill grouting construction around the tunnel, so that the high-pressure concrete slurry flows into the soil layer 2 at the edge of the tunnel through the grouting hole 11 for solidification and reinforcement.
Claims
1. A method for backfilling grouting around a hole. It is characterized in that include: The invention relates to a construction process in which a grouting pipe (1) which is closed or opened using a controllable grouting hole (11) is pre-buried in a soil layer (2) at the side of a tunnel and then backfilled with grout.
2. The hole backfill grouting construction method as claimed in claim 1, It is characterized in that The construction process is specifically as follows: the outer tube (13) is inserted into the soil layer (2) at the side of the tunnel hole, and then the inner tube (12) is inserted into the outer tube (13), and the pin holes on both sides of the outer tube (13) are symmetrically inserted with limit pins (15); the control push sleeve (16) is screwed into the outside of the outer tube (13), and the push sleeve (16) pushes the inner tube (12) to push the spring ring (14) downward, and the inner tube (12) slides into the outer tube (13) until the inner tube (13) is After the grouting holes (11) of the inner layer pipe (12) and the grouting holes (11) of the outer layer pipe (13) overlap, the grouting holes (11) of the grouting pipe (1) as a whole are unobstructed to the soil layer (2) at the edge of the tunnel hole, and the process of controlling the grouting holes (11) to be closed or opened in the inner layer pipe (12) and the outer layer pipe (13) is realized, and then the grouting is injected to carry out the backfill grouting construction around the tunnel hole, so that the high-pressure concrete slurry flows into the soil layer (2) at the edge of the tunnel hole through the grouting holes (11) to be solidified and reinforced.
3. The hole backfill grouting construction method according to claim 1 or 2, Features: The grouting pipe (1) comprises: an inner layer pipe (12) and an outer layer pipe (13) both of which are provided with grouting holes (11); the inner layer pipe (12) can only be slidably inserted into the outer layer pipe (13); the grouting holes (11) of the inner layer pipe (12) and the grouting holes (11) of the outer layer pipe (13) are coaxially non-overlapping and staggered.
4. The hole backfill grouting construction method as claimed in claim 3, Features: The outer tube (13) is provided with a pin hole penetrating therethrough for installing a limiting pin (15); the inner tube (12) is provided with an inwardly concave limiting groove; the limiting pin (15) is symmetrically inserted into the limiting groove of the inner tube (12) from two pin holes on both sides of the outer tube (13); the length of the limiting groove on the outer side of the inner tube (12) is equal to the distance between the grouting hole (11) of the inner tube (12) and the grouting hole (11) of the outer tube (13) being offset to overlap.
5. The hole backfill grouting construction method as claimed in claim 3, Features: The bottom of the outer layer pipe (13) is in a cone shape to facilitate the bottom of the outer layer pipe (13) to be inserted into the soil layer (2) at the side of the tunnel.
6. The hole-surrounding backfill grouting construction method as claimed in claim 3, Features: An elastic ring (14) made of elastic rubber is installed inside the outer tube (13), and the bottom of the inner tube (12) abuts against the elastic ring (14).
7. The hole-surrounding backfill grouting construction method as claimed in claim 6, Features: The top of the inner tube (12) protrudes from the tube mouth of the outer tube (13), and the outer tube (13) is screwed with a propulsion sleeve (16), which abuts against the top of the inner tube (12).