Intelligent control system and control method for crane ship
By designing a system for front-end data acquisition, data middle platform and back-end analysis, the problem that the existing technology cannot achieve overall intelligence and expansion of crane ships is solved, comprehensive monitoring and intelligent control of crane ships are realized, and automatic control is improved. Safety and accuracy of ship migration and energy efficiency management.
Patent Information
- Application Number
- CN202410920121.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-10
- Publication Date
- 2024-11-22
AI Technical Summary
The existing intelligent control system for crane ships is limited to lifting mechanisms, ballast systems and anchoring systems, and cannot realize the overall intelligent architecture design of the crane ships, and cannot be expanded to meet the increasing system and intelligent needs.
An intelligent control system for crane ships including front-end system, data middle platform system and back-end system was designed. The front-end system is used for data collection, the data middle platform system is used for data collection and forwarding, and the back-end system is used for data analysis. and develop control recommendations, the system has an open structure that enables the addition of hardware equipment and expands according to requirements.
It has realized comprehensive monitoring and intelligent control of the crane ship, improved the intelligent operation level of the crane ship, adapted to different needs, improved the safety of automatic ship moving and the accuracy of energy efficiency management, and has great promotion value.
Smart Images

Figure CN119002314A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of ship control, and in particular to an intelligent control system and a control method for a crane ship. Background Art
[0002] With the development of marine resource development, the construction of cross-sea bridges continues to increase. The demand for large-scale crane ship construction in large-scale offshore engineering operations has increased significantly, and the crane ships used in construction are becoming larger and larger. At sea, the operation process of a crane ship is a huge and complex system engineering. The lifting function during operation is completed by the crane and electrical transmission control system on the ship. The state of the system changes greatly during the operation process. The operating environment is very complex and costly. Lifting thousands of tons of weight in a short period of time places very high requirements on the ship. The safe operation of the crane plays a major role in the successful completion of offshore operations, and the safety protection of the system faces high requirements.
[0003] For example, the Chinese invention patent with the patent number "CN200810043840.0" and the title "A control system and control method for a self-propelled fully revolving crane ship crane" discloses a control system for a crane ship crane, which includes integrating three control systems, namely a lifting mechanism, a ballast system and an anchoring system, into one system, and performing comprehensive control and safety protection according to the principle of coordinated control; various types of suitable sensor groups are respectively configured in the overall lifting mechanism, ballast system and anchoring system of the self-propelled crane ship, so that the lifting control, ballast control and anchoring control of the self-propelled crane ship form three parallel closed-loop feedbacks; on this basis, a coordination controller is added to calculate the relevant signals collected by the sensor groups of the three subsystems, with the goal of controlling the center of gravity of the crane ship within the safe area of the ship's stability, and the coordination controller is used to supervise and set instructions for the operation and control of the three subsystems, ultimately playing a role in safety protection control. This system can greatly improve the stability of the crane ship during lifting operations, but this crane ship intelligent system only controls the lifting mechanism, ballast system and mooring system. This control system is limited to the intelligence of a certain part or operation process of the crane ship, and there is no design for the overall intelligent architecture of the crane ship. Moreover, this control system cannot be expanded. When new ones are introduced. At present, with the gradual increase of various systems of ships, the gradual improvement of digitalization level, and the continuous increase of intelligent requirements, how to consider a reasonable and scalable crane ship intelligent architecture from the top level is the basis for the smooth implementation of crane ship intelligence. Summary of the invention
[0004] The purpose of the present invention is to solve the deficiencies of the above-mentioned background technology and to provide an intelligent control system and control method for a crane vessel.
[0005] The technical solution of the present invention is: an intelligent control system for a crane vessel, comprising:
[0006] A front-end system, which is used to collect data on the crane, positioning winch, switchboard, liquid level telemetry system, fuel metering system and environmental information of the crane vessel;
[0007] The data middle-end system is used to collect, organize and forward the data collected by the front-end system;
[0008] A back-end system that formulates recommendations for crane operation, ship movement, and energy efficiency management based on data transmitted by the data middle-end system.
[0009] According to an intelligent control system for a crane vessel provided in the present application, the front-end system includes:
[0010] A crane data acquisition module, wherein the crane data acquisition module is used to collect crane operation data;
[0011] A positioning winch data acquisition module, wherein the positioning winch data acquisition module is used to collect positioning winch operation data;
[0012] An environmental monitoring module, which is used to collect environmental parameters of the waters where the crane vessel is located;
[0013] A power monitoring module, which is used to collect the power load status of each equipment on the crane ship;
[0014] A liquid level telemetry module, which is used to collect data on the liquid level of each ballast tank of the crane ship and the hexagonal draft depth of the crane ship;
[0015] A fuel metering module is used to collect fuel metering data of the main diesel engine set and the parked diesel engine set.
[0016] According to an intelligent control system for a crane vessel provided in the present application, the data middle platform system includes:
[0017] The cabin monitoring module is used to receive the data collected by the crane data acquisition module, the positioning winch data acquisition module, the power monitoring module, the liquid level telemetry module, and the fuel metering module, and send the collected data to the intelligent processing unit corresponding to the data.
[0018] According to an intelligent control system for a crane vessel provided in the present application, the back-end system includes:
[0019] An intelligent operation module, the intelligent operation module comprising an intelligent processing unit for formulating crane operation suggestions based on data transmitted by the environmental monitoring module and the cabin monitoring module, an intelligent processing unit for formulating ballast tank adjustment suggestions, and an intelligent processing unit for identifying energy efficiency judgment results;
[0020] An energy efficiency management module, which formulates operation suggestions for the main diesel engine unit and the moored diesel engine unit of the crane ship based on the data transmitted by the engine room monitoring module and the current energy efficiency judgment result transmitted by the intelligent operation module;
[0021] The automatic ship moving module calculates the positioning winch control data based on the data collected by the positioning winch data collection module and the position information, and feeds back the control data to the positioning winch to automatically move the ship.
[0022] According to an intelligent control system for a crane vessel provided in the present application, the automatic ship moving module includes:
[0023] An alarm information judgment module, based on the comprehensive alarm information data collected by the positioning winch data collection module, formulates an instruction not to perform the automatic ship moving operation when the comprehensive alarm is yes, and formulates an instruction to perform the automatic ship moving operation when the comprehensive alarm is no;
[0024] A control state judgment module, based on the control state information data collected by the positioning winch data collection module, the control state judgment module formulates an instruction not to perform the automatic ship moving operation when the positioning winch control state is local control or remote control, and formulates an instruction to perform the automatic ship moving operation when the positioning winch control state is automatic control;
[0025] A brake and clutch judgment module, which, based on the positioning winch brake state and clutch state information data collected by the positioning winch data collection module, formulates an instruction to perform an automatic ship moving operation when the positioning winch brake is in an open state and the clutch is in a closed state, and formulates an instruction not to perform an automatic ship moving operation when the positioning winch brake is in a closed state or the clutch is in an open state;
[0026] A ship moving operation module, wherein the ship moving operation module obtains the current heading and position data of the crane vessel when the alarm information, control status, brake and clutch status are all judged to be capable of automatic ship moving operation, calculates the moving path of the crane vessel based on the target position and target heading of the crane vessel, adjusts the crane vessel by first adjusting the position of the crane vessel and then adjusting the heading, and controls the automatic ship moving based on the collected rope speed and cable tension during the adjustment process, so as to control the crane vessel to move to the target position and target heading.
[0027] According to an intelligent control system for a crane vessel provided in the present application, the ship moving operation module includes:
[0028] An X-direction moving module, wherein the X-direction moving module maintains the current heading unchanged, connects the X-coordinate in the current position information with the X-coordinate in the target position information to form an X-direction connecting line, controls the positioning winch on the side of the X-direction connecting line to collect a unit length along the X-direction connecting line, controls the positioning winch on the opposite side to be in a constant tension cable releasing state, compares the X-coordinate after the movement with the X-coordinate in the target position information, and if the difference between the two is greater than the set X-direction difference, continues to move according to the above mode until the difference between the two is not greater than the set X-direction difference;
[0029] A Y-direction moving module, wherein the Y-direction moving module maintains the current bow direction unchanged after the crane ship moves to its position in the X-direction, connects the Y-coordinate in the current position information with the Y-coordinate in the target position information to form a Y-direction connecting line, controls the positioning winch on the side of the Y-direction connecting line to collect a unit length along the Y-direction connecting line, controls the positioning winch on the opposite side to be in a constant tension cable releasing state, compares the Y-coordinate after the movement with the Y-coordinate in the target position information, and if the difference between the two is greater than the set Y-direction difference, continues to move according to the above mode until the difference between the two is no greater than the set Y-direction difference;
[0030] A bow adjustment module maintains the position of the crane ship unchanged after the crane ship moves into position in the Y direction, controls the two groups of positioning winches on the X-direction line to retract a unit length, and controls the other two groups of positioning winches to be in a constant tension cable-releasing state, and compares the difference between the crane ship's bow after movement and the target bow. If the difference is greater than the set bow difference, continue to adjust according to the above mode until the difference between the two is no greater than the set bow difference.
[0031] According to an intelligent control system for a crane vessel provided in the present application, the ship moving operation module includes:
[0032] The ship moving control module controls the rope speed of the positioning winch not to exceed the rated speed and the cable tension not to exceed the set tension based on the rope speed and cable tension collected by the positioning winch data collection module.
[0033] According to an intelligent control system for a crane vessel provided in the present application, the intelligent operation module includes:
[0034] A state recognition module, wherein the state recognition module recognizes that the crane vessel is in a moored standby state when the crane load is less than a first set load power, the positioning winch load is less than a second set power, and the daily lighting load is not zero; recognizes that the crane vessel is in a ship moving and positioning state when the crane load is less than the first set load power, the main and auxiliary hook lifting motor powers of the crane are zero, and the positioning winch load is not less than a third set power; and recognizes that the crane vessel is in a hoisting state when the crane load is not less than the first set load power, the main and auxiliary hook lifting motor powers of the crane are not zero, and the positioning winch load is less than the second set power.
[0035] According to an intelligent control system for a crane vessel provided in the present application, the energy efficiency management module includes:
[0036] A mooring control module, wherein the mooring control module is used to formulate a suggestion for shutting down the main diesel generator and starting the mooring diesel generator when the state recognition module recognizes that the crane vessel is in a mooring standby state;
[0037] A ship moving control module, the ship moving control module is used to formulate a suggestion to start at least one main diesel generator and shut down the moored diesel generator when the state recognition module recognizes that the crane vessel is in a ship moving positioning state;
[0038] The hoisting control module is used to formulate a suggestion to start at least two main diesel generators and shut down the moored diesel generators when the state identification module identifies that the crane vessel is in the hoisting state.
[0039] According to an intelligent control system for a crane vessel provided in the present application, the intelligent operation module includes:
[0040] An environment over-limit control module, wherein the environment over-limit identification module formulates a suggestion that the environment is over-limit and not suitable for operation when the wind speed, wave height and flow velocity exceed the design working conditions based on the wind speed, wave height and flow velocity data collected by the environment monitoring module;
[0041] A hull motion over-limit control module, wherein the hull motion over-limit identification module formulates a suggestion that the hull motion is over-limit and not suitable for operation when the hull pitch and roll exceed the hull motion limit based on the hull pitch and roll data collected by the liquid level telemetry module;
[0042] The over-limit lifting control module, the over-limit lifting identification module, based on the crane lifting data collected by the crane data collection module, formulates a suggestion that the crane lifting exceeds the lifting limit and is not suitable for operation when the crane lifting exceeds the lifting limit;
[0043] A lifting over-limit control module, wherein the lifting over-limit identification module formulates a suggestion that the lifting over-limit is not suitable for operation when the lifting height of the crane exceeds the lifting limit based on the lifting height data of the crane collected by the crane data collection module;
[0044] The angle over-limit control module, the angle over-limit identification module is based on the crane boom data collected by the crane data collection module, and when the crane boom exceeds the boom limit, it formulates a suggestion that the angle is over-limit and not suitable for operation.
[0045] The present application also provides a method for intelligent control of a crane vessel, the method adopting the above-mentioned intelligent control system of a crane vessel to operate, comprising:
[0046] The front-end system collects data from the crane, positioning winch, switchboard, liquid level telemetry system, and fuel metering system of the crane vessel;
[0047] The data middle-end system collects, organizes and forwards the data collected by the front-end system;
[0048] The back-end system formulates recommendations for crane operation, ship movement, and energy efficiency management based on the data transmitted by the data middle-end system.
[0049] According to an intelligent control method for a crane vessel provided in the present application, the method for data collection by the front-end system includes: collecting data on the lifting weight, lifting height, boom angle and lifting width of the crane;
[0050] Collect the cable tension, rope speed, rope length and start / stop status data of the positioning winch;
[0051] Collect the power load status data of each equipment on the crane ship;
[0052] Collect data on wind speed, wave height and current velocity in the waters where the crane ship is located;
[0053] Collect the liquid level of each ballast tank of the crane ship, the hexagonal draft of the crane ship, and the pitch and roll data of the crane ship;
[0054] The fuel metering data of the main diesel generator set and the parked diesel generator set are collected.
[0055] According to a method for intelligent control of a crane vessel provided by the present application, the method in which the back-end system formulates crane operation suggestions based on the data transmitted by the data middle-end system includes: analyzing the wind speed, wave height, and flow rate data of the waters where the crane vessel is currently located, and when the wind speed, wave height, and flow rate exceed the design working conditions, formulating suggestions that the environment is out of limit and not suitable for operation;
[0056] Analyze the pitch and roll data of the crane ship. When the pitch and roll data exceed the limit of the hull motion, formulate suggestions on whether the hull motion exceeds the limit and is not suitable for operation;
[0057] Analyze the crane lifting data and formulate suggestions on whether the crane is not suitable for operation when the lifting weight exceeds the lifting limit;
[0058] Analyze the crane lifting height data and formulate suggestions on whether the crane is not suitable for operation if the lifting height exceeds the lifting limit;
[0059] Analyze the crane boom data and formulate recommendations on angle exceeding limit and unsuitable operation when the crane boom exceeds the boom limit.
[0060] According to an intelligent control method for a crane vessel provided by the present application, the method in which the back-end system formulates a ship moving suggestion based on data transmitted by the data middle-end system includes: maintaining the current bow direction unchanged, connecting the X-coordinate in the current position information with the X-coordinate in the target position information to form an X-direction connection line, controlling the positioning winch on the side of the X-direction connection line to collect a unit length along the X-direction connection line, controlling the positioning winch on the opposite side to be in a constant tension cable release state, comparing the X-coordinate after the movement with the X-coordinate in the target position information, if the difference between the two is greater than the set X-direction difference, continuing to move according to the above mode until the difference between the two is not greater than the set X-direction difference;
[0061] After the crane ship moves to the position in the X direction, the current bow direction is maintained unchanged, the Y coordinate in the current position information is connected with the Y coordinate in the target position information to form a Y direction connection line, the positioning winch on the side of the Y direction connection line is controlled to collect a unit length along the Y direction connection line, and the positioning winch on the opposite side is controlled to be in a constant tension cable release state, and the Y coordinate after the movement is compared with the Y coordinate in the target position information. If the difference between the two is greater than the set Y direction difference, the movement continues according to the above mode until the difference between the two is not greater than the set Y direction difference;
[0062] After the crane ship moves into position in the Y direction, the ship's position is maintained unchanged, the two groups of positioning winches on the X-direction line are controlled to retract a unit length, and the other two groups of positioning winches are controlled to be in a constant tension cable-releasing state, and the difference between the crane ship's bow after movement and the target bow is compared. If the difference is greater than the set bow difference, continue to adjust according to the above mode until the difference between the two is no greater than the set bow difference.
[0063] According to an intelligent control method for a crane vessel provided in the present application, during the ship moving process, the rope speed of the positioning winch is controlled not to exceed the rated speed, and the cable tension is controlled not to exceed the set tension.
[0064] According to a method for intelligent control of a crane vessel provided by the present application, the method for the back-end system to formulate energy efficiency management suggestions based on the data transmitted by the data middle-end system includes: analyzing the crane load, the positioning winch load, the daily lighting load, and the crane main and auxiliary hook lifting motor power data, identifying that the crane vessel is in a moored standby state when the crane load is less than a first set load power, the positioning winch load is less than a second set power, and the daily lighting load is not zero, and formulating suggestions for shutting down the main diesel generator and starting the moored diesel generator when the crane vessel is in the moored standby state;
[0065] When the crane load is less than the first set load power, the power of the crane main and auxiliary hook lifting motors is zero, and the positioning winch load is not less than the third set power, it is identified that the crane vessel is in the ship moving and positioning state, and when the crane vessel is in the ship moving and positioning state, a suggestion is made to start at least one main diesel generator and shut down the moored diesel generator;
[0066] When the crane load is not less than the first set load power, the power of the crane's main and auxiliary hook lifting motors is not zero, and the positioning winch load is less than the second set power, it is identified that the crane vessel is in the lifting state. When the crane vessel is in the lifting state, recommendations are made to start at least two main diesel generators and shut down the moored diesel generators.
[0067] The advantages of the present application are as follows: 1. The intelligent control system of the crane vessel of the present application includes three system modules: the front-end system is used for data collection, the data middle-end system is used for data reception and forwarding, and the back-end system is used for data analysis and formulating control suggestions. The system is an open structure, and the corresponding hardware equipment can be added according to actual needs. The corresponding hardware equipment can be connected to the data middle-end system for expansion, and the back-end system can be associated with the data middle-end system for intelligent control operations. Moreover, the system adopted is a portable mode, which can be conveniently applied to various forms of crane vessels. The overall adaptability is excellent and the intelligence is extremely high, which greatly improves the degree of intelligent operation of crane vessels and has great promotion value.
[0068] 2. The front-end system of the present application is used to collect crane data, positioning winch data, environmental data, power equipment data, liquid level telemetry data and fuel metering data in real time, so as to facilitate the subsequent intelligent control operation of the corresponding equipment structure based on the above data. The front-end system can also add other data collection items according to the needs of the crane ship, realize the operation, ship movement and energy efficiency management of the entire crane ship, and achieve the purpose of comprehensive monitoring;
[0069] 3. The data middle platform system of the present application includes a cabin monitoring module. As a data transfer module, the cabin monitoring module can receive all collected data and forward it to the back-end system after corresponding sorting for processing by the back-end system. At the same time, the cabin monitoring module can be connected to other hardware data acquisition modules at any time to facilitate the expansion of the entire system, adapt to the needs of different crane ships, and facilitate the improvement of the intelligent empowerment of crane ships;
[0070] 4. The back-end system of this application can make suggestions on the operation, ship movement and energy efficiency management of the crane ship by analyzing the received data information. It has a very high degree of intelligence and meets the intelligent operation requirements of most crane ships. In addition, the back-end system of this application is a portable software control system, which is convenient for application;
[0071] 5. The back-end system of the present application uses multiple sub-modules to make judgments and identify during the ship moving operation, eliminates factors that do not meet the conditions during the ship moving process, ensures the safety of controlling the crane ship to move automatically, and greatly improves the intelligence and safety of the crane ship's automatic ship moving control;
[0072] 6. The automatic ship moving operation module of the present application is carried out step by step during the ship moving operation, first in the X direction, then in the Y direction, and finally in the bow direction. The adjustment scheme is simple, the safety is excellent, and the efficiency and accuracy of automatic ship moving are extremely high;
[0073] 7. During the ship moving operation of the present application, by analyzing the collected rope speed and cable tension of the positioning winch, safety problems caused by excessive rope speed and excessive cable tension can be avoided, thereby improving the safety of the entire ship moving process;
[0074] 8. The intelligent operation module of the present application will judge the current working condition of the crane ship according to the crane load, positioning winch load, daily lighting load, and the power data information of the crane main and auxiliary hook lifting motors, and automatically identify the state of the crane ship, so as to facilitate the subsequent intelligent control operation according to the state of the crane ship, with a high degree of automation and intelligence;
[0075] 9. This application has formulated different energy efficiency management suggestions for different operating conditions of crane ships. The energy efficiency management is highly targeted, greatly improving the accuracy of energy efficiency management and saving a lot of energy;
[0076] 10. This application makes real-time judgments on environmental data, hull motion data, lifting weight data, lifting height data and boom angle data to eliminate over-limit situations in the lifting operation of the crane ship, avoid the occurrence of safety accidents, and improve the safety of the entire crane ship lifting operation.
[0077] The intelligent control system of the crane vessel of the present application has the function of convenient transplantation and expansion, can be applied to various crane vessels, greatly improves the intelligent automation level of the crane vessel, and has great promotion value. BRIEF DESCRIPTION OF THE DRAWINGS
[0078] Figure 1 : Schematic diagram of the intelligent control system architecture of the crane vessel of this application. DETAILED DESCRIPTION
[0079] The embodiments of the present invention are described in detail below, wherein the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.
[0080] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0081] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0082] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0083] The present application relates to an intelligent control system for a crane vessel, which is mainly used for intelligent control and operation of the crane vessel. The control system of the present application can be expanded and transplanted, that is, the control system of the present application can access the data information of the extended hardware at any time, so as to realize the automatic and intelligent control of the new extended hardware equipment. The control system can also be transplanted to other crane vessels for use, thereby improving the overall intelligence and automation level of the crane vessel.
[0084] The intelligent control system of the crane vessel in this application mainly includes three subsystems, such as Figure 1As shown, the front-end system, the data middle-office system and the back-end system, wherein the front-end system is used to collect data on the crane, positioning winch, distribution board, liquid level telemetry system, fuel metering system and environmental information of the crane ship. The front-end system is a data acquisition system, and the front-end system can add corresponding data acquisition items according to the actual equipment conditions and control requirements of the crane ship; the data middle-office system is used to collect, organize and forward the data collected by the front-end system. The data middle-office system is a data transmission system, and the data middle-office system can access the newly added data acquisition items of the front-end system at any time to collect, organize and forward the newly added data items; the back-end system formulates recommendations for crane operation, ship moving and energy efficiency management based on the data transmitted by the data middle-office system. The back-end system is a data processing system, which analyzes the transmitted data and formulates corresponding control recommendations. The back-end system of the present application is a software module system, so it can be directly transplanted to the corresponding crane ship to improve the intelligence and automation level of the existing crane ship. At the same time, the front-end system involves hardware equipment for data collection, which can also be arranged accordingly according to needs. The data middle-end system is a module for data transmission, and is also equipped with equipment and facilities for data transmission. When it is necessary to configure the intelligent control system of the present application on the crane ship, it is necessary to select the corresponding front-end system, data middle-end system and back-end system according to actual needs.
[0085] When the intelligent control system of the crane ship is actually controlling,
[0086] The front-end system collects data from the crane, positioning winch, switchboard, liquid level telemetry system, and fuel metering system of the crane ship;
[0087] The data middle-end system collects, organizes and forwards the data collected by the front-end system;
[0088] The back-end system formulates recommendations for crane operation, ship movement, and energy efficiency management based on the data transmitted by the data middle-end system.
[0089] In some embodiments of the present application, this embodiment optimizes the above-mentioned front-end system. Specifically, the front-end system includes a crane data acquisition module, a positioning winch data acquisition module, an environmental monitoring module, a power monitoring module, a liquid level telemetry module and a fuel metering module. The crane data acquisition module is used to collect crane operation data, and collects the crane's lifting weight, lifting height, boom angle and lifting width data. Sensors can be installed at corresponding locations to collect the above data; the positioning winch data acquisition module is used to collect positioning winch operation data, and collects the cable tension, rope speed, rope length and start-stop status data of the positioning winch. The positioning winch has four groups located at the four corners of the hull, and a plurality of sensors are installed on the positioning winch to collect the above data; the environmental monitoring module is used to collect the environmental parameters of the waters where the crane ship is located, and collects the wind speed, wave height and flow rate data of the waters where the crane ship is located. Collection; The power monitoring module is used to collect the power load status of each equipment on the crane ship, and collect the power load status data of each equipment on the crane ship. In fact, the above-mentioned power load data information can be obtained through the distribution board on the crane ship; the liquid level telemetry module is used to collect data on the liquid level of each ballast tank of the crane ship and the hexagonal draft of the crane ship. The liquid level of each ballast tank of the crane ship, the hexagonal draft of the crane ship, and the pitch and roll data of the crane ship are collected. The ballast tank liquid level can be monitored in real time through the sensors installed in the ballast tanks. The pitch and roll of the crane ship can be collected through the corresponding equipment. The draft measurement sensors are set on both sides of the bow, both sides of the middle of the ship, and both sides of the stern; the fuel metering module is used to collect the fuel metering data of the main diesel engine set and the moored diesel engine set, and the collection is carried out by installing flow sensors at the fuel inlets of the main diesel engine set and the moored diesel engine set.
[0090] In other embodiments of the present application, this embodiment optimizes the above-mentioned data middle-office system. Specifically, the data middle-office system includes a cabin monitoring module, which is arranged on the hull of the crane ship. It is the data acquisition system and data transmission center of the crane ship, and is used to receive the data collected by the above-mentioned crane data acquisition module, positioning winch data acquisition module, power monitoring module, liquid level telemetry module, and fuel metering module and send the collected data to the intelligent processing unit corresponding to the data.
[0091] The cabin monitoring module consists of a data acquisition industrial computer and a communication module. The data acquisition industrial computer is used to collect and store data sent by the front-end system; the communication module is used to connect various front-end systems, back-end intelligent systems and the data acquisition industrial computer, convert data of different communication protocols into a unified format and send it to the data acquisition industrial computer, and convert data into different formats and send it to the corresponding back-end intelligent system. A star topology is used between the data acquisition industrial computer and each communication module.
[0092] In a further embodiment of the present application, this embodiment optimizes the above-mentioned back-end system. Specifically, the back-end system includes an intelligent operation module, an energy efficiency management module and an automatic ship moving module. The control of the crane ship involves three aspects, namely lifting operation, automatic ship moving and energy efficiency management. The intelligent operation module of this embodiment includes an intelligent processing unit for formulating crane operation suggestions based on data transmitted by the environment monitoring module and the engine room monitoring module, an intelligent processing unit for formulating ballast tank adjustment suggestions, and an intelligent processing unit for identifying energy efficiency judgment results; the energy efficiency management module formulates operation suggestions for the main diesel engine unit and the moored diesel engine unit of the crane ship based on the data transmitted by the engine room monitoring module and the current energy efficiency judgment results transmitted by the intelligent operation module; the automatic ship moving module calculates the positioning winch control data based on the data collected by the positioning winch data acquisition module and the position information, and feeds back the control data to the positioning winch for automatic ship moving.
[0093] Among them, the automatic ship moving module includes an alarm information judgment module, a control state judgment module, a brake and clutch judgment module and a ship moving operation module. The alarm information judgment module is based on the comprehensive alarm information data collected by the positioning winch data acquisition module. When the comprehensive alarm is yes, it formulates an instruction not to perform the automatic ship moving operation, and when the comprehensive alarm is no, it formulates an instruction to perform the automatic ship moving operation; the control state judgment module is based on the control state information data collected by the positioning winch data acquisition module. When the positioning winch control state is local control or remote control, it formulates an instruction not to perform the automatic ship moving operation, and when the positioning winch control state is automatic control, it formulates an instruction to perform the automatic ship moving operation; the brake and clutch judgment module is based on the positioning winch data acquisition module. The module collects information data on the brake status and clutch status of the positioning winch, and formulates instructions for automatic ship moving when the positioning winch brake is in the open state and the clutch is in the closed state, and formulates instructions not to perform automatic ship moving when the positioning winch brake is in the closed state or the clutch is in the open state; the ship moving operation module obtains the current bow and position data of the crane ship when the alarm information, control status, brake and clutch status are all judged to be capable of automatic ship moving, calculates the moving path of the crane ship based on the target position and target bow of the crane ship, and adjusts the crane ship by first adjusting the position of the crane ship and then adjusting the bow. During the adjustment process, the automatic ship moving is controlled based on the collected rope speed and cable tension, and the crane ship is controlled to move to the target position and target bow.
[0094] The alarm information judgment module, control status judgment module, brake and clutch judgment module are used to judge whether the current state of the crane ship is suitable for automatic ship moving operation. When it is judged to be suitable for automatic ship moving operation, the ship moving operation module will formulate corresponding operation suggestions to control the positioning winch to perform the corresponding automatic ship moving operation.
[0095] The ship moving operation module of this embodiment includes an X-direction moving module, a Y-direction moving module, a bow adjustment module and a ship moving control module. The X-direction moving module maintains the current bow unchanged, connects the X-coordinate in the current position information with the X-coordinate in the target position information to form an X-direction connection line, controls the positioning winch on the side of the X-direction connection line to collect a unit length along the X-direction connection line, controls the positioning winch on the opposite side to be in a constant tension cable release state, compares the X-coordinate after movement with the X-coordinate in the target position information, and if the difference between the two is greater than the set X-direction difference, continues to move according to the above mode until the difference between the two is not greater than the set X-direction difference; the Y-direction moving module maintains the current bow unchanged after the crane ship moves into position in the X-direction, connects the Y-coordinate in the current position information with the Y-coordinate in the target position information to form a Y-direction connection line, controls the positioning winch on the side of the Y-direction connection line to move along the Y-direction The connecting line is collected by a unit length, and the positioning winch on the opposite side is controlled to be in a constant tension cable-releasing state. The Y coordinate after the movement is compared with the Y coordinate in the target position information. If the difference between the two is greater than the set Y-direction difference, the movement continues in the above mode until the difference between the two is not greater than the set Y-direction difference. The bow adjustment module maintains the ship's position unchanged after the crane ship moves into position in the Y direction, controls the two groups of positioning winches on the X-direction connecting line to collect a unit length, and controls the other two groups of positioning winches to be in a constant tension cable-releasing state. The difference between the crane ship's bow after the movement and the target bow is compared. If the difference is greater than the set bow difference, the adjustment continues in the above mode until the difference between the two is not greater than the set bow difference. The ship moving control module controls the rope speed of the positioning winch not to exceed the rated speed and the control cable tension not to exceed the set tension based on the rope speed and cable tension collected by the positioning winch data acquisition module.
[0096] In actual operation, follow the steps below:
[0097] S1: receiving the comprehensive alarm signal of the positioning winch. If the comprehensive alarm is yes, the automatic ship moving process will not be performed; if not, the process will proceed to step S2;
[0098] S2: Receive the control status of the positioning winch. If the control status is local or remote control, do not enter the automatic ship moving process. If the status is automatic ship moving, enter step S3;
[0099] S3: receiving the brake and clutch status of the positioning winch, if the clutch is closed and the brake is open, proceeding to step S4;
[0100] S4: receiving the current position and heading data of the ship, and calculating the moving path of the ship according to the input target position and heading;
[0101] Assume the current ship position (Xa, Ya), heading α; the target ship position (Xb, Yb), heading β; first keep the heading α unchanged, move the ship position from Xa to Xb, connect the X coordinate of the current position, i.e. Xa, with the X coordinate of the target position, Xb, to form an X-direction line, control the winch on the side pointing to the Xb vector direction to reel in a unit length (e.g. 0.1m), and the winch on the opposite side is in a constant tension cable release state, compare the moved ship position Xa' with Xb after the ship is moved, if the difference exceeds 0.1m, continue the above operation; if the difference is less than 0.1m, the ship is moved to the right position in the X direction;
[0102] After the X-axis ship is in place, the ship position is moved from Ya to Yb, and the Y coordinate of the current position, i.e. Ya, is connected with the Y coordinate of the target position, i.e. Yb, to form a Y-axis line. The winch on the side with Ya pointing to the Yb vector direction is controlled to reel in a unit length (e.g. 0.1m), and the winch on the opposite side is in a constant tension cable-releasing state. After the ship is moved, the moved ship position Ya' is compared with Yb. If the difference exceeds 0.1m, the above operation is continued; if the difference is less than 0.1m, the Y-axis ship is in place.
[0103] After the ship is moved into position in the Y direction, keep the ship's position unchanged, move the bow from α to β, the two winches on the diagonal line in the direction of the Xa-Xb vector retract a unit length (such as 0.1m), and the two winches on the other diagonal line are in a constant tension cable-releasing state. After the ship is turned, compare the bow directions α' and β. If the difference is greater than 0.1°, continue the above operation; if the difference is less than 0.1°, turn the ship into position.
[0104] S5: Monitor the rope speed and cable tension during the ship moving process. The rope speed should not exceed the rated speed (the rated speed is the rated speed of the winch), and the cable tension should not exceed the set tension (the set tension is 2 / 3 of the breaking tension of the wire rope) to avoid danger.
[0105] In a preferred embodiment of the present application, this embodiment optimizes the above-mentioned intelligent operation module. Specifically, the intelligent operation module of this embodiment includes a state recognition module and an energy efficiency management module. The state recognition module recognizes that the crane vessel is in a moored standby state when the crane load is less than a first set load power, the positioning winch load is less than a second set power, and the daily lighting load is not zero; recognizes that the crane vessel is in a ship moving and positioning state when the crane load is less than the first set load power, the lifting motor power of the main and auxiliary hooks of the crane is zero, and the positioning winch load is not less than a third set power; recognizes that the crane vessel is in a lifting state when the crane load is not less than the first set load power, the lifting motor power of the main and auxiliary hooks of the crane is not zero, and the positioning winch load is less than the second set power.
[0106] Among them, the energy efficiency management module includes a mooring control module, a ship moving control module and a hoisting control module. The mooring control module is used to formulate a suggestion to shut down the main diesel generator and start the moored diesel generator when the state identification module identifies that the crane vessel is in a moored standby state; the ship moving control module is used to formulate a suggestion to start at least one main diesel generator and shut down the moored diesel generator when the state identification module identifies that the crane vessel is in a ship moving positioning state; the hoisting control module is used to formulate a suggestion to start at least two main diesel generators and shut down the moored diesel generator when the state identification module identifies that the crane vessel is in a hoisting state.
[0107] When actually performing control operations: analyze the crane load, positioning winch load, daily lighting load, and crane main and auxiliary hook lifting motor power data, identify the crane vessel in the mooring standby state when the crane load is less than the first set load power, the positioning winch load is less than the second set power, and the daily lighting load is not zero, and formulate suggestions for shutting down the main diesel generator and starting the mooring diesel generator when the crane vessel is in the mooring standby state;
[0108] When the crane load is less than the first set load power, the power of the crane main and auxiliary hook lifting motors is zero, and the positioning winch load is not less than the third set power, it is identified that the crane vessel is in the ship moving and positioning state, and when the crane vessel is in the ship moving and positioning state, a suggestion is made to start at least one main diesel generator and shut down the moored diesel generator;
[0109] When the crane load is not less than the first set load power, the power of the crane's main and auxiliary hook lifting motors is not zero, and the positioning winch load is less than the second set power, it is identified that the crane vessel is in the lifting state. When the crane vessel is in the lifting state, recommendations are made to start at least two main diesel generators and shut down the moored diesel generators.
[0110] In some embodiments of the present application, this embodiment further optimizes the above-mentioned intelligent operation module. Specifically, the intelligent operation module includes an environment over-limit control module, a hull motion over-limit control module, a hoisting over-limit control module, a lifting over-limit control module and an angle over-limit control module. The environment over-limit identification module is based on the wind speed, wave height and flow rate data collected by the environmental monitoring module. When the wind speed, wave height and flow rate exceed the design conditions, it formulates a suggestion that the environment is over-limit and not suitable for operation; the hull motion over-limit identification module is based on the hull pitch and roll data collected by the liquid level telemetry module (four-corner draft sub-module or six-corner draft sub-module). When the wind speed, wave height and flow rate exceed the design conditions, it formulates a suggestion that the environment is over-limit and not suitable for operation. When the rocking exceeds the limit of the hull movement, suggestions are made that the hull movement is beyond the limit and is not suitable for operation; the over-limit lifting recognition module is based on the crane lifting weight data collected by the crane data acquisition module. When the crane lifting weight exceeds the lifting weight limit, suggestions are made that the lifting weight is beyond the limit and is not suitable for operation; the over-limit lifting recognition module is based on the crane lifting height data collected by the crane data acquisition module. When the crane lifting height exceeds the lifting limit, suggestions are made that the lifting is beyond the limit and is not suitable for operation; the over-limit angle recognition module is based on the crane boom data collected by the crane data acquisition module. When the crane boom exceeds the boom limit, suggestions are made that the angle is beyond the limit and is not suitable for operation.
[0111] Specifically, during the control operation: analyze the wind speed, wave height, and current velocity data of the crane vessel's current waters. When the wind speed, wave height, and current velocity exceed the design conditions, formulate recommendations that the environment is beyond the limit and is not suitable for operation.
[0112] Analyze the pitch and roll data of the crane ship. When the pitch and roll data exceed the limit of the hull motion, formulate suggestions on whether the hull motion exceeds the limit and is not suitable for operation;
[0113] Analyze the crane lifting data and formulate suggestions on whether the crane is not suitable for operation when the lifting weight exceeds the lifting limit;
[0114] Analyze the crane lifting height data and formulate suggestions on whether the crane is not suitable for operation if the lifting height exceeds the lifting limit;
[0115] Analyze the crane boom data and formulate recommendations on angle exceeding limit and unsuitable operation when the crane boom exceeds the boom limit.
[0116] In fact, it means eliminating the above-mentioned over-limit situations and avoiding safety accidents when carrying out lifting operations on a crane ship.
[0117] When the crane ship of the present application is intelligently controlled, Figure 1As shown, the lifting weight, lifting height, boom angle and lifting amplitude data of the crane are collected; the cable tension, rope speed, rope length and start-stop status data of the positioning winch are collected; the power load status data of each equipment of the crane ship are collected; the wind speed, wave height and flow rate data of the waters where the crane ship is located are collected; the liquid level of each ballast tank of the crane ship, the hexagonal draft depth of the crane ship, and the pitch and roll data of the crane ship are collected; the fuel metering data of the main diesel engine set and the moored diesel engine set are collected;
[0118] Control the lifting operation of the crane ship, analyze the wind speed, wave height and current speed data of the current waters of the crane ship, and formulate suggestions that the environment is beyond the limit and is not suitable for operation when the wind speed, wave height and current speed exceed the design conditions; analyze the pitch and roll data of the crane ship's hull, and formulate suggestions that the hull movement is beyond the limit and is not suitable for operation when the pitch and roll data exceed the hull movement limit; analyze the crane lifting weight data, and formulate suggestions that the lifting weight is beyond the limit and is not suitable for operation when the crane lifting weight exceeds the lifting weight limit; analyze the crane lifting height data, and formulate suggestions that the lifting is beyond the limit and is not suitable for operation when the crane lifting height exceeds the lifting limit; analyze the crane boom data, and formulate suggestions that the angle is beyond the limit and is not suitable for operation when the crane boom exceeds the boom limit;
[0119] Carry out energy efficiency management and control of crane vessels, analyze the crane load, positioning winch load, daily lighting load, and crane main and auxiliary hook lifting motor power data, identify the crane vessel in the mooring standby state when the crane load is less than the first set load power, the positioning winch load is less than the second set power, and the daily lighting load is not zero, and formulate suggestions to shut down the main diesel generator and start the mooring diesel generator when the crane vessel is in the mooring standby state; identify the crane vessel in the ship moving and positioning state when the crane load is less than the first set load power, the crane main and auxiliary hook lifting motor power is zero, and the positioning winch load is not less than the third set power, and formulate suggestions to start at least one main diesel generator and shut down the mooring diesel generator when the crane vessel is in the ship moving and positioning state; identify the crane vessel in the hoisting state when the crane load is not less than the first set load power, the crane main and auxiliary hook lifting motor power is not zero, and the positioning winch load is less than the second set power, and formulate suggestions to start at least two main diesel generators and shut down the mooring diesel generator when the crane vessel is in the hoisting state;
[0120] The automatic ship moving control of the crane vessel is performed according to the following steps: S1: receiving the comprehensive alarm signal of the positioning winch, if the comprehensive alarm is yes, then the automatic ship moving is not performed; if it is no, then the step S2 is performed;
[0121] S2: Receive the control status of the positioning winch. If the control status is local or remote control, do not enter the automatic ship moving process. If the status is automatic ship moving, enter step S3;
[0122] S3: receiving the brake and clutch status of the positioning winch, if the clutch is closed and the brake is open, proceeding to step S4;
[0123] S4: receiving the current position and heading data of the ship, and calculating the moving path of the ship according to the input target position and heading;
[0124] Assume the current ship position (Xa, Ya), heading α; the target ship position (Xb, Yb), heading β; first keep the heading α unchanged, move the ship position from Xa to Xb, connect the X coordinate of the current position, i.e. Xa, with the X coordinate of the target position, Xb, to form an X-direction line, control the winch on the side pointing to the Xb vector direction to reel in a unit length (e.g. 0.1m), and the winch on the opposite side is in a constant tension cable release state, compare the moved ship position Xa' with Xb after the ship is moved, if the difference exceeds 0.1m, continue the above operation; if the difference is less than 0.1m, the ship is moved to the right position in the X direction;
[0125] After the X-axis ship is in place, the ship position is moved from Ya to Yb, and the Y coordinate of the current position, i.e. Ya, is connected with the Y coordinate of the target position, i.e. Yb, to form a Y-axis line. The winch on the side with Ya pointing to the Yb vector direction is controlled to reel in a unit length (e.g. 0.1m), and the winch on the opposite side is in a constant tension cable-releasing state. After the ship is moved, the moved ship position Ya' is compared with Yb. If the difference exceeds 0.1m, the above operation is continued; if the difference is less than 0.1m, the Y-axis ship is in place.
[0126] After the ship is moved into position in the Y direction, keep the ship's position unchanged, move the bow from α to β, the two winches on the diagonal line in the direction of the Xa-Xb vector retract a unit length (such as 0.1m), and the two winches on the other diagonal line are in a constant tension cable-releasing state. After the ship is turned, compare the bow directions α' and β. If the difference is greater than 0.1°, continue the above operation; if the difference is less than 0.1°, turn the ship into position.
[0127] S5: Monitor the rope speed and cable tension during the ship moving process. The rope speed should not exceed the rated speed (the rated speed is the rated speed of the winch), and the cable tension should not exceed the set tension (the set tension is 2 / 3 of the breaking tension of the wire rope) to avoid danger.
[0128] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. An intelligent control system for a crane vessel, characterized in that: include, A front-end system, which is used to collect data on the crane, positioning winch, switchboard, liquid level telemetry system, fuel metering system and environmental information of the crane vessel; The data middle-end system is used to collect, organize and forward the data collected by the front-end system; A back-end system that formulates recommendations for crane operation, ship movement, and energy efficiency management based on data transmitted by the data middle-end system.
2. The intelligent control system for a crane vessel according to claim 1, characterized in that: The front-end system comprises: A crane data acquisition module, wherein the crane data acquisition module is used to collect crane operation data; A positioning winch data acquisition module, wherein the positioning winch data acquisition module is used to collect positioning winch operation data; An environmental monitoring module, which is used to collect environmental parameters of the waters where the crane vessel is located; A power monitoring module, which is used to collect the power load status of each equipment on the crane ship; A liquid level telemetry module, which is used to collect data on the liquid level of each ballast tank of the crane ship and the hexagonal draft depth of the crane ship; A fuel metering module is used to collect fuel metering data of the main diesel engine set and the parked diesel engine set.
3. The intelligent control system for a crane vessel according to claim 2, characterized in that: The data middle platform system includes: The cabin monitoring module is used to receive the data collected by the crane data acquisition module, the positioning winch data acquisition module, the power monitoring module, the liquid level telemetry module, and the fuel metering module, and send the collected data to the intelligent processing unit corresponding to the data.
4. The intelligent control system for a crane vessel according to claim 3, characterized in that: The backend system includes: An intelligent operation module, the intelligent operation module comprising an intelligent processing unit for formulating crane operation suggestions based on data transmitted by the environmental monitoring module and the cabin monitoring module, an intelligent processing unit for formulating ballast tank adjustment suggestions, and an intelligent processing unit for identifying energy efficiency judgment results; An energy efficiency management module, which formulates operation suggestions for the main diesel engine unit and the moored diesel engine unit of the crane ship based on the data transmitted by the engine room monitoring module and the current energy efficiency judgment result transmitted by the intelligent operation module; The automatic ship moving module calculates the positioning winch control data based on the data collected by the positioning winch data collection module and the position information, and feeds back the control data to the positioning winch to automatically move the ship.
5. The intelligent control system for a crane vessel according to claim 4, characterized in that: The automatic ship moving module comprises: An alarm information judgment module, based on the comprehensive alarm information data collected by the positioning winch data collection module, formulates an instruction not to perform the automatic ship moving operation when the comprehensive alarm is yes, and formulates an instruction to perform the automatic ship moving operation when the comprehensive alarm is no; A control state judgment module, based on the control state information data collected by the positioning winch data collection module, the control state judgment module formulates an instruction not to perform the automatic ship moving operation when the positioning winch control state is local control or remote control, and formulates an instruction to perform the automatic ship moving operation when the positioning winch control state is automatic control; A brake and clutch judgment module, which, based on the positioning winch brake state and clutch state information data collected by the positioning winch data collection module, formulates an instruction to perform an automatic ship moving operation when the positioning winch brake is in an open state and the clutch is in a closed state, and formulates an instruction not to perform an automatic ship moving operation when the positioning winch brake is in a closed state or the clutch is in an open state; A ship moving operation module, wherein the ship moving operation module obtains the current heading and position data of the crane vessel when the alarm information, control status, brake and clutch status are all judged to be capable of automatic ship moving operation, calculates the moving path of the crane vessel based on the target position and target heading of the crane vessel, adjusts the crane vessel by first adjusting the position of the crane vessel and then adjusting the heading, and controls the automatic ship moving based on the collected rope speed and cable tension during the adjustment process, so as to control the crane vessel to move to the target position and target heading.
6. The intelligent control system for a crane vessel according to claim 5, characterized in that: The ship moving operation module includes: An X-direction moving module, wherein the X-direction moving module maintains the current heading unchanged, connects the X-coordinate in the current position information with the X-coordinate in the target position information to form an X-direction connecting line, controls the positioning winch on the side of the X-direction connecting line to collect a unit length along the X-direction connecting line, controls the positioning winch on the opposite side to be in a constant tension cable releasing state, compares the X-coordinate after the movement with the X-coordinate in the target position information, and if the difference between the two is greater than the set X-direction difference, continues to move according to the above mode until the difference between the two is not greater than the set X-direction difference; A Y-direction moving module, wherein the Y-direction moving module maintains the current bow direction unchanged after the crane ship moves to its position in the X-direction, connects the Y-coordinate in the current position information with the Y-coordinate in the target position information to form a Y-direction connecting line, controls the positioning winch on the side of the Y-direction connecting line to collect a unit length along the Y-direction connecting line, controls the positioning winch on the opposite side to be in a constant tension cable releasing state, compares the Y-coordinate after the movement with the Y-coordinate in the target position information, and if the difference between the two is greater than the set Y-direction difference, continues to move according to the above mode until the difference between the two is no greater than the set Y-direction difference; A bow adjustment module maintains the position of the crane ship unchanged after the crane ship moves into position in the Y direction, controls the two groups of positioning winches on the X-direction line to retract a unit length, and controls the other two groups of positioning winches to be in a constant tension cable-releasing state, and compares the difference between the crane ship's bow after movement and the target bow. If the difference is greater than the set bow difference, continue to adjust according to the above mode until the difference between the two is no greater than the set bow difference.
7. The intelligent control system for a crane vessel according to claim 4, characterized in that: The intelligent operation module includes: A state recognition module, wherein the state recognition module recognizes that the crane vessel is in a moored standby state when the crane load is less than a first set load power, the positioning winch load is less than a second set power, and the daily lighting load is not zero; recognizes that the crane vessel is in a ship moving and positioning state when the crane load is less than the first set load power, the main and auxiliary hook lifting motor powers of the crane are zero, and the positioning winch load is not less than a third set power; and recognizes that the crane vessel is in a hoisting state when the crane load is not less than the first set load power, the main and auxiliary hook lifting motor powers of the crane are not zero, and the positioning winch load is less than the second set power.
8. The intelligent control system for a crane vessel according to claim 7, characterized in that: The energy efficiency management module includes: A mooring control module, wherein the mooring control module is used to formulate a suggestion for shutting down the main diesel generator and starting the mooring diesel generator when the state recognition module recognizes that the crane vessel is in a mooring standby state; A ship moving control module, the ship moving control module is used to formulate a suggestion to start at least one main diesel generator and shut down the moored diesel generator when the state recognition module recognizes that the crane vessel is in a ship moving positioning state; The hoisting control module is used to formulate a suggestion to start at least two main diesel generators and shut down the moored diesel generators when the state identification module identifies that the crane vessel is in the hoisting state.
9. The intelligent control system for a crane vessel according to claim 4, characterized in that: The intelligent operation module includes: An environment over-limit control module, wherein the environment over-limit identification module formulates a suggestion that the environment is over-limit and not suitable for operation when the wind speed, wave height and flow velocity exceed the design working conditions based on the wind speed, wave height and flow velocity data collected by the environment monitoring module; A hull motion over-limit control module, wherein the hull motion over-limit identification module formulates a suggestion that the hull motion is over-limit and not suitable for operation when the hull pitch and roll exceed the hull motion limit based on the hull pitch and roll data collected by the liquid level telemetry module; The over-limit lifting control module, the over-limit lifting identification module, based on the crane lifting data collected by the crane data collection module, formulates a suggestion that the crane lifting exceeds the lifting limit and is not suitable for operation when the crane lifting exceeds the lifting limit; A lifting over-limit control module, wherein the lifting over-limit identification module formulates a suggestion that the lifting over-limit is not suitable for operation when the lifting height of the crane exceeds the lifting limit based on the lifting height data of the crane collected by the crane data collection module; The angle over-limit control module, the angle over-limit identification module is based on the crane boom data collected by the crane data collection module, and when the crane boom exceeds the boom limit, it formulates a suggestion that the angle is over-limit and not suitable for operation.
10. A method for intelligent control of a crane vessel, characterized in that: The control method is operated by using an intelligent control system for a crane vessel as described in any one of claims 1 to 9. Including, the front-end system collects data from the crane, positioning winch, switchboard, liquid level telemetry system, and fuel metering system of the crane ship; The data middle-end system collects, organizes and forwards the data collected by the front-end system; The back-end system formulates recommendations for crane operation, ship movement, and energy efficiency management based on the data transmitted by the data middle-end system.