Intelligent analysis method and system for operation state of electric control cabinet

By performing cluster analysis and state fluctuation coefficient assessment on the monitoring data of each control circuit in the electrical control cabinet, the problem of accuracy in the analysis of the operating status of the electrical control cabinet was solved, and more efficient status monitoring and anomaly identification of the electrical control cabinet were achieved.

CN119004387AInactive Publication Date: 2024-11-22WUXI KANGBEI ELECTRONICS EQUIP

Patent Information

Application Number
CN202411464319.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-21
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In existing technologies, the accuracy of operating status analysis of electrical control cabinets is low, especially when electrical equipment experiences short-term load changes, which leads to inaccurate analysis of the fluctuation status of each circuit within the control cabinet and reduces the accuracy of monitoring.

Method used

An intelligent analysis method for the operating status of electrical control cabinets is adopted. By acquiring monitoring data of each control circuit of the electrical control cabinet, clustering algorithm is used to analyze the clustering effect and distribution of the monitoring data, calculate the dispersion and standard deviation, and combine time weight and data changes at adjacent time points to evaluate the status fluctuation coefficient. Finally, the operating status of the electrical control cabinet is evaluated based on the status fluctuation coefficient.

Benefits of technology

This improves the accuracy of electrical control cabinet operation status analysis, enabling more accurate identification of abnormal situations, reducing misjudgments, and ensuring the stable operation of the electrical control cabinet.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119004387A_ABST
    Figure CN119004387A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of electric control cabinet operation monitoring data analysis and processing, in particular to an electric control cabinet operation state intelligent analysis method and system. The method comprises the following steps: firstly, clustering monitoring data at each acquisition moment; obtaining dispersion according to a clustering result, and further obtaining a standard deviation degree of each piece of monitoring data; acquiring a state fluctuation coefficient of each control circuit; and finally evaluating the operation state of the electric control cabinet according to the state fluctuation coefficients of all the control circuits. According to the method, multi-dimensional monitoring data are subjected to fusion analysis through clustering, the abnormal possibility, namely dispersion, of the electric control cabinet at each collection moment is evaluated, and the operation condition of the monitoring data at each collection moment is analyzed by further combining the standard deviation condition of each monitoring data; adjusting the standard deviation degree of monitoring data at a part of acquisition moments, namely under a special operation condition, so as to accurately obtain the state fluctuation coefficient of each control circuit; and the analysis and monitoring accuracy of the operation state of the electric control cabinet is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric control cabinet operation monitoring data analysis and processing, and in particular to an intelligent analysis method and system for the operation status of an electric control cabinet. Background Art

[0002] The electric control cabinet is used to control, protect and distribute the electrical equipment in the power system. The voltage and current required for each circuit are usually determined according to the design requirements of the electrical equipment connected to the circuit. By monitoring the real-time voltage and current data of each circuit in the electric control cabinet, circuit abnormalities such as overload, short circuit, ground fault, etc. can be discovered in time. It can also warn of potential faults and take measures to prevent equipment damage or downtime from causing serious production losses; therefore, intelligent monitoring of the operating status of the electric control cabinet is crucial.

[0003] At present, the operating status of the electric control cabinet is analyzed and evaluated based on the fluctuation of the voltage and current data of each circuit in the electric control cabinet. During normal operation, the voltage and current data usually fluctuate in a small range. When the fluctuation is more severe or deviates from the existing horizontal trend, it can be considered that the operating status is not good. However, the electrical equipment connected to the electric control cabinet may have short-term load changes. For example, the voltage and current at the start of the motor may fluctuate to a certain extent compared with normal operation, which may reduce the accuracy of the analysis of the fluctuation status of each circuit in the electric control cabinet, and then misjudge the operating status of the electric control cabinet, reducing the accuracy of its analysis and monitoring. Summary of the invention

[0004] In order to solve the technical problem that the accuracy of the fluctuation state analysis of each circuit in the electric control cabinet is low, which leads to the low accuracy of the analysis and monitoring of the operation state of the electric control cabinet, the purpose of the present invention is to provide an intelligent analysis method and system for the operation state of the electric control cabinet. The technical solution adopted is as follows: The present invention proposes an intelligent analysis method for the operation status of an electric control cabinet, the method comprising: Obtain all monitoring data on each control circuit of the electric control cabinet during the monitoring period; obtain the clustering results of all the monitoring data at each collection time; At each acquisition moment, according to the clustering effect of the clustering result and the distribution of the monitoring data in each cluster, the discreteness of all the monitoring data at each sampling moment is obtained; according to the difference between each monitoring data and the preset standard data on the control circuit to which it belongs, combined with the discreteness at the corresponding acquisition moment, the standard deviation of the monitoring data on each control circuit at each acquisition moment is obtained; On each control circuit, the state fluctuation coefficient of each control circuit is obtained based on the standard deviation of the monitoring data at all collection moments and the operating conditions at the corresponding collection moments, combined with the difference in the standard deviation of the monitoring data at adjacent collection moments; the operating status of the electric control cabinet is evaluated based on the state fluctuation coefficients of all control circuits.

[0005] Furthermore, the method for obtaining the discreteness includes: According to the inter-cluster distances between different clusters, the clustering effect of the clustering results at each collection time is evaluated; According to the total number of monitoring data in each cluster and the cluster area of ​​each cluster, the intra-cluster density of each cluster is obtained; according to the intra-cluster density of all clusters, the density parameter of the clustering result at each collection time is obtained; The discreteness of all the monitoring data at the corresponding collection time is obtained according to the clustering effect and the density parameter.

[0006] Furthermore, the method for obtaining the cluster area includes: The convex hull detection algorithm is used to obtain the cluster area of ​​each cluster.

[0007] Furthermore, the method for obtaining the standard deviation includes: Normalizing the discreteness at each acquisition moment to obtain a relative discreteness at each acquisition moment; Taking the difference between each of the monitoring data and the preset standard data on the corresponding control circuit as the standard deviation; According to the standard deviation and the relative dispersion of each monitoring data, the standard deviation of the monitoring data on each control circuit at each acquisition moment is obtained; the standard deviation and the relative dispersion are both positively correlated with the standard deviation.

[0008] Furthermore, the method for obtaining the state fluctuation coefficient includes: According to the collection time of each monitoring data on each control circuit, obtain the time weight of the standard deviation of the monitoring data on the corresponding circuit branch at the corresponding collection time; according to the time weight, weighted sum of the standard deviation of the monitoring data on the corresponding circuit branch at the corresponding collection time to obtain the first fluctuation parameter of each control circuit; On each control circuit, a second fluctuation parameter is obtained according to the difference of the standard deviation of the monitoring data at all adjacent collection moments; According to the first fluctuation parameter and the second fluctuation parameter, a state fluctuation coefficient of each control circuit is obtained, and the first fluctuation parameter and the second fluctuation parameter are both positively correlated with the state fluctuation coefficient.

[0009] Furthermore, the method for obtaining the time weight includes: A preset number of collection moments after the load startup moment on each control circuit are regarded as special moments; according to the sorting ordinal number of the special moment among all collection moments, the time weight of the standard deviation of the monitoring data at the corresponding special moment is obtained; and the time weight of the standard deviation of the monitoring data at a non-special moment is set to a preset normal number.

[0010] Furthermore, the evaluating the operating state of the electric control cabinet according to the state fluctuation coefficients of all control circuits includes: The control circuit whose state fluctuation coefficient is greater than a preset threshold is regarded as an abnormal circuit, and the ratio of the number of abnormal circuits to the total number of control circuits is regarded as an evaluation parameter. When the evaluation parameter is greater than the preset evaluation threshold, it is determined that the electric control cabinet is in an abnormal operating state.

[0011] Furthermore, the method for obtaining the clustering result includes: The ISODATA clustering algorithm is used for the monitoring data of all control circuits at each collection moment to obtain clustering results.

[0012] Furthermore, the monitoring data is two-dimensional monitoring data constructed by voltage data and current data.

[0013] The present invention also proposes an intelligent analysis system for the operating status of an electric control cabinet, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the steps of the intelligent analysis method for the operating status of an electric control cabinet are implemented.

[0014] The present invention has the following beneficial effects: The present invention obtains all monitoring data on each control circuit of the electric control cabinet within the monitoring period; at each acquisition time, the clustering results of all monitoring data are obtained, and the clustering method comprehensively evaluates the operating status of the electric control cabinet by all monitoring indicators, avoiding the traditional method of analyzing each monitoring indicator one by one, and then combining the correlation between different monitoring indicators for comprehensive evaluation, thereby relatively improving the evaluation efficiency; at each acquisition time, according to the clustering effect of the clustering results and the distribution of monitoring data in each cluster, the discreteness of all monitoring data at each sampling time is obtained, and the discreteness indirectly reflects whether there is an abnormality in the operating status of the electric control cabinet at the sampling time; according to the difference between each monitoring data and the preset standard data on the control circuit to which it belongs, the discreteness of all monitoring data at each sampling time is obtained. The difference is combined with the discreteness at the corresponding acquisition moment to obtain the standard deviation of the monitoring data on each control circuit at each acquisition moment; on each control circuit, according to the standard deviation of the monitoring data at all acquisition moments and the operating conditions at the corresponding acquisition moment, combined with the difference change of the standard deviation of the monitoring data at adjacent acquisition moments, the state fluctuation coefficient of each control circuit is obtained, and the state fluctuation coefficient fully considers that the monitoring data at some acquisition moments may belong to the fluctuation deviation caused by the non-electric control cabinet failure factors, and there may be deviation effects on the abnormal analysis of the circuit, so as to accurately evaluate the state fluctuation of each control circuit; the operating state of the electric control cabinet is evaluated according to the state fluctuation coefficient of all control circuits. The present invention integrates and analyzes the multi-dimensional monitoring data through clustering, evaluates the abnormal possibility of the electric control cabinet at each acquisition moment, that is, the discreteness, and further analyzes the operating conditions of the monitoring data at each acquisition moment in combination with the standard deviation of each monitoring data, so as to adjust the standard deviation of the monitoring data at some acquisition moments, that is, under special operating conditions, so as to accurately obtain the state fluctuation coefficient of each control circuit; improves the accuracy of the analysis and monitoring of the operating state of the electric control cabinet. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the technical solutions and advantages in the embodiments of the present invention or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0016] Figure 1 A flow chart of an intelligent analysis method for the operation status of an electric control cabinet provided by one embodiment of the present invention; Figure 2 A flow chart of a method for obtaining a state fluctuation coefficient provided by an embodiment of the present invention; Figure 3 The present invention is a schematic diagram of the structure of an intelligent analysis system for the operation status of an electric control cabinet provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0017] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the following is a detailed description of the intelligent analysis method and system of the operating status of an electric control cabinet proposed by the present invention, its specific implementation method, structure, features and effects, in combination with the accompanying drawings and preferred embodiments. In the following description, different "one embodiment" or "another embodiment" does not necessarily refer to the same embodiment. In addition, specific features, structures or characteristics in one or more embodiments may be combined in any suitable form.

[0018] Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.

[0019] The specific scheme of the intelligent analysis method and system for the operation status of an electric control cabinet provided by the present invention is described in detail below with reference to the accompanying drawings.

[0020] See also Figure 1 , which shows a flow chart of an intelligent analysis method for the operation status of an electric control cabinet provided by an embodiment of the present invention, specifically comprising: Step S1, obtaining all monitoring data on each control circuit of the electric control cabinet within the monitoring period; obtaining clustering results of all monitoring data at each collection time.

[0021] In one embodiment of the present invention, first, all monitoring data on each control circuit of the electric control cabinet during the monitoring period is obtained. Specifically, a collection device is installed on each control circuit in the electric control cabinet to collect and obtain all monitoring data at a preset sampling frequency, wherein the preset sampling frequency is 3 seconds each time, and the monitoring data includes at least voltage data and current data; at the same time, to facilitate subsequent cluster analysis, the voltage data and the current data are constructed into two-dimensional monitoring data, and the two-dimensional monitoring data is regarded as a monitoring sample.

[0022] It should be noted that, taking into account the different dimensions and numerical expressions of voltage data and current data, in order to avoid affecting subsequent analysis, the embodiment of the present invention further standardizes the monitoring data, specifically adopts the maximum and minimum value normalization method, and standardizes the voltage data and current data respectively, and uniformly maps them to the numerical range of 0 to 1; in other embodiments of the present invention, the implementer may also adopt other standardization processing methods, and the types of monitoring indicators and sampling frequencies in the monitoring data can be adjusted according to actual needs, so as to obtain multi-dimensional monitoring data for subsequent analysis while avoiding dimensional disasters as much as possible and satisfying computing performance.

[0023] It should be noted that, considering that not all electrical equipment on each control circuit in the electrical control cabinet may be in operation, the monitoring data on the control circuit to which the electrical equipment that is not in operation belongs may be significantly different from the monitoring data on the control circuit in operation. Therefore, the monitoring data on the control circuit targeted by the embodiment of the present invention refers to the monitoring data collected when the corresponding electrical equipment is in operation, and the period to be monitored is the period from the start of the equipment operation to the current time.

[0024] Considering that the electrical equipment connected to each control circuit of the electric control cabinet may include different models, the monitoring data of electrical equipment of different models may have certain differences in values, but the corresponding monitoring data of electrical equipment of the same model or working mode may be similar in values. Clustering can be used to evaluate the distribution of monitoring data on all control circuits at each sampling moment, because under normal circumstances, the monitoring data of equipment of similar models may be clustered into one cluster. If the distribution of monitoring data after clustering is relatively discrete, it further indicates that the operating status of the electric control cabinet at the sampling moment may be abnormal. At the same time, by constructing multi-dimensional monitoring data and comprehensively evaluating the operating status of the electric control cabinet with all monitoring indicators, it avoids the traditional method of analyzing each monitoring indicator one by one, and then combining the correlation between different monitoring indicators for comprehensive evaluation, which relatively improves the evaluation efficiency.

[0025] In a preferred embodiment of the present invention, considering that the iterative self-organizing clustering algorithm (ISODATA) can automatically determine the number of clusters and continuously adjust the number and categories of clusters through self-iteration to achieve the optimal clustering effect; therefore, the ISODATA clustering algorithm is used for the monitoring data of all control circuits at each collection moment to obtain the clustering results, which is convenient for the subsequent evaluation of the operating status of the electric control cabinet at each sampling moment.

[0026] In another embodiment of the present invention, the implementer may first count the equipment types, classify electrical equipment with similar operating conditions or the same model into one category, that is, the monitoring data in each category under normal operation has similar numerical performance, obtain all equipment types, take the total number of equipment types as the preset K value, and obtain the clustering results of the monitoring data of all control circuits at each sampling time based on the K-means clustering algorithm. In other embodiments, the implementer may also use other clustering algorithms, which, together with ISODATA clustering and K-means clustering, are prior arts well known to those skilled in the art and will not be described in detail here.

[0027] Step S2, at each collection moment, according to the clustering effect of the clustering results and the distribution of the monitoring data in each cluster, obtain the discreteness of all monitoring data at each sampling moment; according to the difference between each monitoring data and the preset standard data on the corresponding control circuit, combined with the discreteness at the corresponding collection moment, obtain the standard deviation of the monitoring data on each control circuit at each collection moment.

[0028] Taking into account that in the clustering results, the denser the distribution of the monitoring data within each cluster, the more concentrated the monitoring data on the corresponding control circuits of similar-model electrical equipment, and the greater the possibility that the operating status of the electric control cabinet is normal; and considering that the better the clustering effect of the clustering results, the more accurate the analysis of the distribution of the monitoring data within each cluster, the embodiment of the present invention obtains the clustering results at each collection moment, and then evaluates the discreteness of all monitoring data at each sampling moment according to the clustering effect and the distribution of the monitoring data within each cluster; the discreteness indirectly reflects whether there is any abnormality in the operating status of the electric control cabinet at the sampling moment.

[0029] Preferably, in one embodiment of the present invention, considering that if each cluster in the clustering result deviates relatively from other clusters, it means that the greater the degree of separation and distinction between the cluster and other clusters, the better the clustering effect; and considering that the more the number of monitoring data in each cluster, but the smaller the area occupied by the cluster, it means that the distribution of monitoring data in the cluster is relatively dense, the density within the cluster is large, and vice versa; based on this, the method for obtaining the discreteness includes: According to the inter-cluster distances between different clusters, the clustering effect of the clustering results at each collection time is evaluated; According to the total number of monitoring data in each cluster and the cluster area of ​​each cluster, the intra-cluster density of each cluster is obtained; according to the intra-cluster density of all clusters, the density parameter of the clustering result at each collection time is obtained; The discreteness of all monitoring data at the corresponding collection time is obtained according to the clustering effect and density parameters.

[0030] The method for obtaining the cluster area includes: obtaining the cluster area of ​​each cluster using a convex hull detection algorithm. In other embodiments of the present invention, the implementer may also use other minimum circumscribed polygon algorithms to obtain the cluster area. It should be noted that the convex hull detection algorithm and the convex hull detection algorithm are both prior arts well known to those skilled in the art and will not be described in detail here.

[0031] The calculation formula for dispersion is: ; In the formula, For the The discreteness of all monitoring data at a collection time; For the The sequence number of the cluster in the clustering result at the collection time; For the The total number of clusters in the clustering results at each collection moment; For the The clustering results at the collection time are The total number of monitoring data in a cluster; For the The clustering results at the collection time are The cluster area of ​​each cluster; For the The clustering results at the collection time are The intra-cluster density of each cluster; For the The density parameter of the clustering results at each collection moment; For the In the clustering results under the collection time, except for the The sequence numbers of the remaining clusters outside the cluster; For the The clustering results at the collection time are The cluster centers of the clusters are The Euclidean distance between the cluster centers of the clusters; For the The clustering effect of the clustering results at the collection time.

[0032] It should be noted that the cluster center of each cluster can be obtained according to the mean or median of all monitoring data in the cluster, which is an existing technology well known to those skilled in the art and will not be described in detail here.

[0033] In the calculation formula of dispersion, It represents the inter-cluster distance between any two clusters in the clustering results. The larger the inter-cluster distance, the better the clustering effect and the higher the accuracy in evaluating the intra-cluster density. The larger the intra-cluster density, the more clustered the data is and the smaller the corresponding discreteness is. Therefore, the logic is adjusted by performing the inverse operation. Then, the density parameter after the inverse operation is multiplied and combined with the clustering effect to obtain the discreteness.

[0034] In another embodiment of the present invention, the implementer may also evaluate the intra-cluster density by calculating the distance between each monitoring data in the cluster and the center of the cluster, and averaging the distances. The larger the mean distance, the smaller the intra-cluster density and the more discrete the data distribution. The density parameters are then obtained by combining the intra-cluster densities of all clusters. The implementer may also evaluate the clustering effect by the CH index, and then multiply the density parameter after the inverse operation by the clustering effect to obtain the discreteness.

[0035] It should be noted that in other embodiments of the present invention, the implementer may also use the DB index or silhouette coefficient to evaluate the clustering effect, which and the CH index to evaluate the clustering effect are both existing technologies well known to those skilled in the art and will not be described in detail here.

[0036] Considering that the electrical equipment on each control circuit in the electric control cabinet has a rated standard, the rated standard represents that the equipment can continue to operate safely and effectively under standard working conditions. During the normal operation of the electrical equipment, the monitoring data usually fluctuates slightly on the basis of the rated standard, but will not deviate from the rated standard to a large extent. When there is a large deviation, it may mean that the equipment may be in an abnormal operating state, and the operating state of the electric control cabinet may also be abnormal; at the same time, the discreteness of the monitoring data at each collection moment also indirectly reflects the possibility of abnormal operation of the electric control cabinet to a certain extent; therefore, the embodiment of the present invention obtains the standard deviation of the monitoring data on each control circuit at each collection moment according to the difference between each monitoring data and the preset standard data on the control circuit to which it belongs, combined with the discreteness at the corresponding collection moment, that is, the standard deviation of each monitoring data.

[0037] Preferably, in one embodiment of the present invention, the method for obtaining the standard deviation includes: Normalize the discreteness at each acquisition moment to obtain the relative discreteness at each acquisition moment; The difference between each monitoring data and the preset standard data on the corresponding control circuit is taken as the standard deviation; According to the standard deviation and relative dispersion of each monitoring data, the standard deviation of the monitoring data on each control circuit at each acquisition moment is obtained; the standard deviation and relative dispersion are positively correlated with the standard deviation.

[0038] It should be noted that, since the monitoring data is standardized to a certain extent in step S1, the method for obtaining the preset standard data is: the rated working voltage of the electrical equipment connected to each control circuit and all voltage monitoring data are synchronously processed using the maximum and minimum value normalization method, and the rated working current is also processed similarly, and the normalized rated working voltage and rated working current are constructed into two-dimensional data to obtain the preset standard data; the specific method for obtaining the standard deviation is: the Euclidean distance between the monitoring data and the preset standard data on the control circuit to which it belongs is used as the corresponding standard deviation.

[0039] The calculation formula for standard deviation is: ; In the formula, For the The next collection time The standard deviation of the monitoring data on the control circuit; The natural constant The exponential function with base ; For the The next collection time Monitoring data on the control circuit; For the Preset standard data on the control circuit; For the The discreteness of all monitoring data at a collection time; is the total number of collection moments in the monitoring period; is the maximum discreteness among all acquisition moments; is the standard deviation; is the relative dispersion.

[0040] In the calculation formula of the standard deviation, the standard deviation and the relative discreteness are multiplied and combined, and then mapped to an exponential function to amplify the numerical value for subsequent analysis and calculation; in other embodiments of the present invention, the implementer may also use basic mathematical operations such as addition or weighted summation or related mapping methods to combine the two, which is a prior art well known to those skilled in the art and will not be elaborated here.

[0041] Step S3, on each control circuit, according to the standard deviation of the monitoring data at all collection moments and the operating conditions at the corresponding collection moments, combined with the difference in the standard deviation of the monitoring data at adjacent collection moments, obtain the state fluctuation coefficient of each control circuit; evaluate the operating status of the electric control cabinet according to the state fluctuation coefficients of all control circuits.

[0042] Taking into account that there may be starting current or starting voltage in the initial startup of electrical equipment, the monitoring data obtained at this time has a large deviation compared to the two-dimensional monitoring data during normal operation, and the corresponding standard deviation is also relatively large; since such deviation is not caused by abnormal operation of the electric control cabinet, it may have a certain deviation effect on the evaluation of the state fluctuation of each control circuit; and considering that the collection time of the monitoring data corresponding to such deviation is usually the initial startup of the electrical equipment; therefore, in the embodiment of the present invention, on each control circuit, according to the standard deviation of the monitoring data at all collection times and the corresponding collection time, combined with the difference in the standard deviation of the monitoring data at adjacent collection times, the state fluctuation coefficient of each control circuit is obtained.

[0043] The state fluctuation coefficient fully considers the possible deviation influence of the monitoring data caused by the initial operation of the control circuit, and at the same time evaluates the operation status of each control circuit in combination with the standard deviation of the monitoring data at all acquisition times on each control circuit; on the basis of adjusting the deviation influence of the initial startup, if there are more acquisition times with deviations and the corresponding standard deviation is larger, it means that the possibility of abnormal fluctuation of the control circuit during the monitoring period is greater; at the same time, the fluctuation change of the corresponding standard deviation of the monitoring data at adjacent acquisition times is also considered. If the fluctuation change is more drastic, it means that the possibility of abnormal fluctuation of the control circuit during the monitoring period is greater.

[0044] Preferably, in one embodiment of the present invention, the method for obtaining the state fluctuation coefficient includes: See also Figure 2 , which shows a flow chart of a method for obtaining a state fluctuation coefficient provided by an embodiment of the present invention: Step S201, according to the collection time of each monitoring data on each control circuit, obtain the time weight of the standard deviation of the monitoring data on the corresponding circuit branch at the corresponding collection time; according to the time weight, weighted sum of the standard deviation of the monitoring data on the corresponding circuit branch at the corresponding collection time is performed to obtain the first fluctuation parameter of each control circuit.

[0045] Due to the possible deviation influence on the standard deviation analysis of the monitoring data at the initial startup, in one embodiment of the present invention, the corresponding time weight is first obtained according to the corresponding collection time, and then the standard deviation is adjusted according to the time weight.

[0046] Preferably, in one embodiment of the present invention, the method for obtaining the time weight includes: The preset number of acquisition moments after the load start-up moment on each control circuit are all regarded as special moments; according to the sorting ordinal number of the special moment under all acquisition moments, the time weight of the standard deviation of the monitoring data at the corresponding special moment is obtained; the time weight of the standard deviation of the monitoring data at non-special moments is set to a preset normal number. The preset number is specifically 3, and the special moments are the first three acquisition moments after the start of acquisition; considering that the fluctuation deviation of the standard deviation of the monitoring data at non-special moments may be caused by real abnormal operation, the preset normal number is 1, that is, the time weight of the non-special moment is set to 1.

[0047] The method for obtaining the time weight of the standard deviation of the monitoring data at a special moment specifically includes: dividing the sorting order of the special moment at all collection moments by the total number of collection moments in the monitoring period to be monitored to obtain the time weight, so that the time weight of the standard deviation of the monitoring data at the corresponding collection moment at the initial start-up of the electrical equipment on each control circuit is obtained.

[0048] In other embodiments of the present invention, implementers may also set their own weights to reduce the weight of the standard deviation of the monitoring data at the special moment corresponding to the initial startup, thereby avoiding misjudging the monitoring data due to normal deviation in the initial startup as abnormal deviation.

[0049] The calculation formula of the first fluctuation parameter is: ; In the formula, For the A first fluctuation parameter of a control circuit; For the The next collection time The standard deviation of the monitoring data on the control circuit; is the serial number of the collection time; is the preset quantity, i.e. the total quantity at a particular moment; For the The sorting ordinal number of a particular moment; is the total number of collection moments in the monitoring period; is a preset positive constant; For the The time weight of the standard deviation of the monitoring data at a specific moment.

[0050] In the calculation formula of the first fluctuation parameter, the standard deviation of the monitoring data at the initial startup is adjusted by time weight to analyze the possible deviation impact, so as to determine the first fluctuation coefficient by combining the standard deviation of the monitoring data at all acquisition moments on each control circuit.

[0051] It should be noted that The number of special moments in the initial startup is much smaller than the total number of acquisition moments, that is, the number of accumulated symbols. Less than .

[0052] Step S202: On each control circuit, a second fluctuation parameter is obtained according to the difference in standard deviations of monitoring data at all adjacent acquisition moments.

[0053] Considering that the electrical equipment on each control circuit operates stably at non-special moments, the monitoring data at different collection moments should fluctuate within a small range, and the corresponding standard deviations should also have small differences. Based on this, the second fluctuation parameter can be evaluated based on the difference fluctuations of the standard deviations of the monitoring data at all adjacent collection moments.

[0054] The calculation formula of the second fluctuation parameter is: ; In the formula, For the a second fluctuation parameter of the control circuit; For the The next collection time The standard deviation of the monitoring data on the control circuit; For the The next collection time The standard deviation of the monitoring data on the control circuit; is the serial number of the collection time; is the preset quantity, i.e. the total quantity at a particular moment; It is the total number of collection moments in the monitoring period.

[0055] In the calculation formula of the second fluctuation parameter, at non-special moments, the absolute values ​​of the differences in the standard deviations corresponding to the monitoring data at all adjacent acquisition moments on each control circuit are summed to evaluate the fluctuation of the standard deviation; in another embodiment of the present invention, the implementer may also evaluate the second fluctuation parameter by the variance or standard deviation of the standard deviations corresponding to all the monitoring data at non-special moments, which is a prior art well known to those skilled in the art and will not be elaborated here.

[0056] Step S203, obtaining the state fluctuation coefficient of each control circuit according to the first fluctuation parameter and the second fluctuation parameter, wherein the first fluctuation parameter and the second fluctuation parameter are both positively correlated with the state fluctuation coefficient.

[0057] In one embodiment of the present invention, the first fluctuation parameter and the second fluctuation parameter are multiplied and combined and then normalized to obtain the state fluctuation coefficient of each control circuit; the maximum and minimum value normalization method is specifically adopted; in other embodiments of the present invention, the implementer may also adopt other basic mathematical operations such as addition or weighted summation or related mapping means to obtain the state fluctuation coefficient, and may also adopt other normalization methods, which are all existing technologies and will not be repeated here.

[0058] In another embodiment of the present invention, it is also taken into consideration that the monitoring data is not only affected by the startup of the electrical equipment, but may also be affected by external factors such as unstable main power supply of the electric control cabinet. When the monitoring data fluctuates and deviates due to a fault other than the electric control cabinet, misjudgment may also be caused under this operating condition. Therefore, after obtaining the standard deviation of each monitoring data corresponding to each collection moment on each control circuit, the embodiment of the present invention determines the special time period according to the standard deviation of the monitoring data, that is, the collection time period affected by external factors such as unstable power supply. Considering that when the power supply is unstable, the monitoring data on all control circuits will fluctuate and deviate in the same collection period. Based on this, when all control circuits deviate from the preset deviation threshold at all collection moments, the period at the corresponding collection moment is regarded as a special period; the time weight of the standard deviation of the monitoring data in the special period is set to the preset weight, and the time weight of the standard deviation of the monitoring data in the non-special period is still set to the preset normal number; the preset deviation threshold is set to 0.7, the preset weight is 0.5, and the preset normal number is still 1. The implementer can set the preset deviation threshold and the preset weight by himself; then, according to the time weight, the standard deviation of the monitoring data on the corresponding circuit branch at the corresponding collection moment is weighted and summed to obtain the first fluctuation parameter of each control circuit; at non-special moments, according to the difference in the standard deviation of the monitoring data at all adjacent collection moments, the second fluctuation parameter is obtained; and then the state fluctuation coefficient of each control circuit is obtained by combining the first fluctuation parameter and the second fluctuation parameter. The specific idea of ​​obtaining the state fluctuation coefficient is the same as that of steps S201-S203, which will not be repeated here.

[0059] After obtaining the state fluctuation coefficient of each control circuit in the electric control cabinet, the operating state of the electric control cabinet can be evaluated according to the state fluctuation coefficients of all control circuits.

[0060] Preferably, in one embodiment of the present invention, considering that the electric control cabinet is a device that integrates an electrical control system, if the operating state of the electric control cabinet is abnormal, the operating state of most control circuits will be abnormal; based on this, evaluating the operating state of the electric control cabinet according to the state fluctuation coefficient of all control circuits includes: The control circuit whose state fluctuation coefficient is greater than the preset threshold is regarded as an abnormal circuit, and the ratio of the number of abnormal circuits to the total number of control circuits is regarded as an evaluation parameter. When the evaluation parameter is greater than the preset evaluation threshold, the electric control cabinet is judged to be in an abnormal operating state. The preset threshold is 0.8, and the preset evaluation threshold is 0.9, that is, when the state fluctuation coefficient of the control circuit is greater than 0.8, the control circuit is judged to be an abnormal circuit, and when more than 90% of the control circuits in the electric control cabinet are abnormal circuits, the operating state of the electric control cabinet is judged to be abnormal; in other embodiments of the present invention, the implementer can set the values ​​of the preset threshold and the preset evaluation threshold by himself.

[0061] When the operating status of the electric control cabinet is abnormal, an abnormal warning will be issued to prompt relevant technical personnel to check, repair and maintain the electrical components and circuits inside the abnormal electric control cabinet to ensure that the electric control cabinet is in good operating condition.

[0062] In summary, the embodiment of the present invention first obtains all monitoring data on each control circuit of the electric control cabinet, and clusters all monitoring data at each acquisition time; according to the clustering effect and the distribution of the monitoring data in the cluster, the discreteness of all monitoring data at each sampling time is obtained, and then the standard deviation of each monitoring data is obtained in combination with the difference between each monitoring data and the preset standard data; then, according to the standard deviation of the monitoring data and the corresponding acquisition time, combined with the difference change of the standard deviation of the monitoring data at adjacent acquisition times, the state fluctuation coefficient of each control circuit is obtained; finally, the operation state of the electric control cabinet is evaluated according to the state fluctuation coefficient of all control circuits. The present invention integrates and analyzes the multi-dimensional monitoring data through clustering, evaluates the abnormal possibility of the electric control cabinet at each acquisition time, that is, the discreteness, and further analyzes the operation state of the monitoring data at each acquisition time in combination with the standard deviation of each monitoring data, so as to adjust the standard deviation of the monitoring data at some acquisition times, that is, under special operation conditions, so as to accurately obtain the state fluctuation coefficient of each control circuit; improves the accuracy of analysis and monitoring of the operation state of the electric control cabinet.

[0063] The present invention also proposes an intelligent analysis system for the operation status of an electric control cabinet, see Figure 3 , which shows a structural schematic diagram of an intelligent analysis system for the operating status of an electric control cabinet provided by an embodiment of the present invention. The device includes a memory 301, a processor 302, and a computer program 303 stored in the memory and executable on the processor. When the processor executes the computer program, the steps of the above-mentioned intelligent analysis method for the operating status of an electric control cabinet are performed.

[0064] It should be noted that the sequence of the above embodiments of the present invention is only for description and does not represent the advantages and disadvantages of the embodiments. The processes depicted in the accompanying drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.

[0065] The various embodiments in this specification are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other, and each embodiment focuses on the differences from other embodiments.

Claims

1. An intelligent analysis method for the operation status of an electric control cabinet, characterized in that: The method comprises: Obtain all monitoring data on each control circuit of the electric control cabinet during the monitoring period; obtain the clustering results of all the monitoring data at each collection time; At each acquisition moment, according to the clustering effect of the clustering result and the distribution of the monitoring data in each cluster, the discreteness of all the monitoring data at each sampling moment is obtained; according to the difference between each monitoring data and the preset standard data on the control circuit to which it belongs, combined with the discreteness at the corresponding acquisition moment, the standard deviation of the monitoring data on each control circuit at each acquisition moment is obtained; On each control circuit, the state fluctuation coefficient of each control circuit is obtained according to the standard deviation of the monitoring data at all collection moments and the operating conditions at the corresponding collection moments, combined with the difference in the standard deviation of the monitoring data at adjacent collection moments; the operating state of the electric control cabinet is evaluated according to the state fluctuation coefficients of all control circuits; The method for obtaining the state fluctuation coefficient includes: According to the collection time of each monitoring data on each control circuit, obtain the time weight of the standard deviation of the monitoring data on the corresponding circuit branch at the corresponding collection time; according to the time weight, weighted sum of the standard deviation of the monitoring data on the corresponding circuit branch at the corresponding collection time to obtain the first fluctuation parameter of each control circuit; On each control circuit, a second fluctuation parameter is obtained according to the difference of the standard deviation of the monitoring data at all adjacent collection moments; According to the first fluctuation parameter and the second fluctuation parameter, a state fluctuation coefficient of each control circuit is obtained, and the first fluctuation parameter and the second fluctuation parameter are both positively correlated with the state fluctuation coefficient.

2. The intelligent analysis method for the operation status of an electric control cabinet according to claim 1 is characterized in that: The method for obtaining the discreteness includes: According to the inter-cluster distances between different clusters, the clustering effect of the clustering results at each collection time is evaluated; According to the total number of monitoring data in each cluster and the cluster area of ​​each cluster, the intra-cluster density of each cluster is obtained; according to the intra-cluster density of all clusters, the density parameter of the clustering result at each collection time is obtained; The discreteness of all the monitoring data at the corresponding collection time is obtained according to the clustering effect and the density parameter.

3. The intelligent analysis method for the operation status of an electric control cabinet according to claim 2 is characterized in that: The method for obtaining the cluster area comprises: The convex hull detection algorithm is used to obtain the cluster area of ​​each cluster.

4. The intelligent analysis method for the operation status of an electric control cabinet according to claim 1 is characterized in that: The method for obtaining the standard deviation includes: Normalizing the discreteness at each acquisition moment to obtain a relative discreteness at each acquisition moment; Taking the difference between each of the monitoring data and the preset standard data on the corresponding control circuit as the standard deviation; According to the standard deviation and the relative dispersion of each monitoring data, the standard deviation of the monitoring data on each control circuit at each acquisition moment is obtained; the standard deviation and the relative dispersion are both positively correlated with the standard deviation.

5. The intelligent analysis method for the operation status of an electric control cabinet according to claim 1 is characterized in that: The method for obtaining the time weight includes: A preset number of collection moments after the load startup moment on each control circuit are regarded as special moments; according to the sorting ordinal number of the special moment among all collection moments, the time weight of the standard deviation of the monitoring data at the corresponding special moment is obtained; and the time weight of the standard deviation of the monitoring data at a non-special moment is set to a preset normal number.

6. The intelligent analysis method for the operation status of an electric control cabinet according to claim 1 is characterized in that: The step of evaluating the operating state of the electric control cabinet according to the state fluctuation coefficients of all control circuits includes: The control circuit whose state fluctuation coefficient is greater than a preset threshold is regarded as an abnormal circuit, and the ratio of the number of abnormal circuits to the total number of control circuits is regarded as an evaluation parameter. When the evaluation parameter is greater than the preset evaluation threshold, it is determined that the electric control cabinet is in an abnormal operating state.

7. The intelligent analysis method for the operation status of an electric control cabinet according to claim 1 is characterized in that: The method for obtaining the clustering result includes: The ISODATA clustering algorithm is used for the monitoring data of all control circuits at each collection moment to obtain clustering results.

8. The intelligent analysis method for the operation status of an electric control cabinet according to claim 1 is characterized in that: The monitoring data is two-dimensional monitoring data constructed by voltage data and current data.

9. An intelligent analysis system for the operation status of an electric control cabinet, characterized in that: It includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the steps of an intelligent analysis method for the operating status of an electric control cabinet as described in any one of claims 1 to 8 are implemented.

Citation Information

Patent Citations

  • Intelligent amusement equipment fault prediction method based on big data

    CN117436353A

  • Dynamic detection method for launch control system

    CN117850403A

  • Intelligent analysis method for monitoring data of disinfection supply center

    CN118051796A

  • Intelligent driving control method of resistor array

    CN118409553A

  • Industrial personal computer data security backup method and system

    CN118519833A

Cited By

  • Method and system for monitoring abnormal running state of high-precision numerical control machine tool

    CN119575876A

  • Intelligent fault diagnosis and alarm system for high-temperature and high-pressure dyeing machine

    CN119781448A

  • Automatic testing method, device and equipment for air conditioner controller

    CN119847119A

  • Automatic testing method, device and equipment for air conditioning controller

    CN119847119B

  • Method and system for monitoring running state of intelligent power grid equipment

    CN119864805A