Optimization adjustment method and device based on virtual power plant

By encrypting and encoding the actual power supply of the virtual power plant, combined with the separation and slicing treatment methods, the problem of insufficient accuracy of the actual power supply in the adjustment of the virtual power plant is solved, and the efficiency of data transmission and storage is improved.

CN119005826APending Publication Date: 2024-11-22TRAINING CENT STATE GRID NINGXIA ELECTRIC POWER
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411142774.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

In the existing virtual power plant regulation technology, the accuracy of the actual power supply is affected by the modification and use of the data transmitted by the smart meter, resulting in inaccurate adjustment.

Method used

By encrypting and encoding the actual power supply, encoded data is formed and decoded using encoding coefficients to improve the reliability and storage efficiency of data transmission, and the storage area is optimized by dividing and slicing treatment methods.

Benefits of technology

It improves the reliability and storage efficiency of data transmission, reduces the reliability risks introduced by the encoding coefficient, improves the efficiency of the storage area, and is suitable for optimization and adjustment of virtual power plants.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119005826A_ABST
    Figure CN119005826A_ABST
Patent Text Reader

Abstract

According to the virtual power plant-based optimization adjustment method and the virtual power plant-based optimization adjustment device, transmission encryption processing is performed on the actual power supply amount during transmission, and corresponding coded data is formed according to the data of the actual power supply amount, so that coding is performed on the actual power supply amount during transmission, and the reliability of data transmission is improved; in addition, reliability hidden dangers introduced by independent coding coefficients can be weakened according to coding data formed by the original data, and in the storage period of the actual power supply quantity, the efficiency of the storage area is improved and storage is facilitated by executing division on the actual power supply quantity and executing different segmentation treatment storage according to different division data.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of virtual power plants, and in particular relates to an optimization and regulation method and device based on virtual power plants. Background Art

[0002] A virtual power plant is a power coordination management system that uses advanced information and communication technologies and software systems to achieve aggregation and coordinated optimization of DERs such as DG, energy storage systems, controllable loads, and electric vehicles, so that it can participate in the power market and power grid operation as a special power plant. The core of the concept of a virtual power plant can be summarized as "communication" and "aggregation". The key technologies of virtual power plants mainly include coordinated control technology, smart metering technology, and information and communication technology. The most attractive function of a virtual power plant is that it can aggregate DERs to participate in the operation of the power market and ancillary service market, and provide management and ancillary services for distribution networks and transmission networks. The solution of "virtual power plant" has a very large market potential in my country, and it is undoubtedly a good choice for China, which is facing the contradiction between "power shortage and low energy efficiency".

[0003] When it comes to regulating virtual power plants, the existing technical solution with patent publication number "CN111463834A" is generally used to perform the regulation. Specifically, it periodically obtains the first difference between the actual power supply of the virtual power plant in the current time period and the predicted power supply in the current time period, so as to perform the regulation of the virtual power plant.

[0004] On the other hand, the actual power supply of the virtual power plant in the current time period is often transmitted by smart meters, which may be modified and misused during transmission, resulting in inaccurate actual power supply. Summary of the invention

[0005] In order to solve the defects existing in the prior art, the present invention proposes an optimization and regulation method and device based on a virtual power plant, which performs transmission encryption processing on the actual power supply during transmission and forms corresponding coded data based on the data of the actual power supply itself. Not only can the actual power supply during transmission be encoded to improve the reliability of data transmission, but the coded data formed based on the own data can also weaken the reliability risks introduced by the separate coding coefficient. In addition, during the storage of the actual power supply, the actual power supply is classified and different segmentation and storage are performed based on different classified data, which improves the efficiency of the storage area and facilitates storage.

[0006] The present invention utilizes the following technical solutions.

[0007] An optimization and regulation method based on a virtual power plant, comprising:

[0008] The regulating device periodically obtains the first difference between the actual power supply of the virtual power plant in the current time period and the predicted power supply in the current time period transmitted by the smart meter, thereby performing regulation of the virtual power plant;

[0009] The method for the smart meter to transmit the actual power supply of the virtual power plant in the current time period to the regulating device includes:

[0010] Step 1: Collect different actual power supplies;

[0011] Step 2: Obtain the collected actual power supply, and perform classification processing on the actual power supply according to the collection time of the actual power supply, and then perform transmission analysis on the actual power supply in the simultaneous classification data;

[0012] Step 3: Obtain the transmitted coding parameter value and the selected reference, and perform aggregation processing on them synchronously;

[0013] Step 4: Obtain the transmitted coding coefficient data, and synchronously store the coding coefficient data for decoding the actual power supply after transmission.

[0014] An optimization and regulation device based on a virtual power plant, comprising:

[0015] The smart meter is connected to the regulating device through communication, and the regulating device is also connected to the energy node controller through communication;

[0016] The regulating device is used to regularly obtain the first difference between the actual power supply of the virtual power plant in the current time period and the predicted power supply in the current time period transmitted by the smart meter, so as to perform regulation of the virtual power plant;

[0017] The units running on smart meters include:

[0018] An actual power supply quantity collection unit, used for collecting different actual power supplies;

[0019] The data transmission and analysis unit is used to obtain the collected actual power supply, and perform classification processing on the actual power supply according to the collection time of the actual power supply, and then perform transmission and analysis on the actual power supply in the simultaneous classification data;

[0020] A coding coefficient forming unit, used to obtain the transmitted coding parameter value and the selected reference, and synchronously perform aggregation processing on them;

[0021] The data control export unit is used to obtain the transmitted coding coefficient data, synchronously store the coding coefficient data, and perform decoding processing on the actual power supply after transmission.

[0022] Preferably, the data transmission and analysis unit can also be used to transmit the actual power supply to the redundant data extraction and analysis unit, and then the redundant data extraction and analysis unit performs analysis on the actual power supply;

[0023] The redundant data extraction and analysis unit is used to obtain the actual power supply transmitted, and the actual power supply obtained here is the actual power supply at the same time, and then perform redundancy identification on the actual power supply, and perform classification processing on the actual power supply;

[0024] The method of executing the sub-processing includes:

[0025] Get the total actual power supply j, then determine whether the actual power supply contains redundant data, and the actual power supply determined here represents whether the total actual power supply contains redundant data, if it contains redundant data, the corresponding actual power supply is classified into the first cluster of actual power supplies and registered as p, and p=1,2...n, if it does not contain redundant data, the corresponding actual power supply is classified into the second cluster of actual power supplies and registered as r, and r=1,2...q, thereby forming the corresponding classified data, and transmitting the classified data to the data storage and analysis unit.

[0026] The data storage and analysis unit is used to obtain the sub-data to be transmitted, and to perform segmentation processing on the actual power supply according to the length of the actual power supply corresponding to the actual power supply;

[0027] The methods of segmentation and disposal include:

[0028] The method for performing a splitting process on the actual power supply p of the first cluster includes:

[0029] Get the first cluster actual power supply p of the whole, synchronously get the corresponding redundant data in the first cluster actual power supply p and register it as s, where s = 1, 2...i, and the length of the actual power supply of the synchronously obtained redundant data s is SM r Then calculate the average length SM of the actual power supply of all redundant data q q , and the mean SM here q To remove the decimal part of the integer quantity, and the length of the actual power supply is the average SM q As a basis for equal division;

[0030] Then, the first cluster of actual power supply p is bisected according to the bisecting standard to obtain l segments of first layer data, and the object of bisecting here is the data remaining after the first cluster of actual power supply is extracted from redundant data, and the l segments of first layer data are synchronously stored in mixed order;

[0031] The mixed order storage method comprises: storing the first layer data of the l segments in reverse order according to the serial numbers, thereby forming corresponding storage data, and synchronously transmitting the storage data to the data control export unit;

[0032] The method for performing a splitting process on the actual power supply r of the second cluster includes:

[0033] The entire second cluster actual power supply r is obtained, and the second cluster actual power supply r is equally divided into 16 segments of second layer data according to the length thereof, and the 16 segments of the equally divided second layer data are numbered synchronously, and the order of the numbering is the same as the order of the equally divided data, and then the 16 segments of the second layer data are stored according to the numbering, and the storage method includes:

[0034] Aggregate the first 8 segments of the second layer data among the 16 segments, then aggregate the last 8 segments of the second layer data, then store the aggregated data packets, synchronously form corresponding storage data, and then transmit the storage data to the data control export unit;

[0035] The data control export unit is used to obtain the storage data to be transmitted, and transmit the storage data together with the coding coefficient data after linear encoding to the regulating device. The regulating device uses the coding coefficient data to decode the received linearly encoded data to obtain the actual power supply.

[0036] Preferably, the different actual power supplies are the actual power supplies collected and transmitted by the smart meters in different time periods.

[0037] Preferably, the collected actual power supply is also provided with its corresponding: collection time and length of the actual power supply.

[0038] Preferably, the actual power supply amount acquisition unit is further used to transmit the actual power supply amount to the data transmission and analysis unit.

[0039] Preferably, the method of sub-disposal includes:

[0040] The actual power supply quantity collected is numbered as j, where j = 1, 2...k, and the collection time corresponding to the actual power supply quantity j is numbered as U j , synchronously according to the order of acquisition time, the acquisition time is at the time interval U q The actual power supply in is divided into, that is, into simultaneous distance data, and the simultaneous distance data is numbered b, and b = A, B, C...Z, where the number b represents the category of the simultaneous distance.

[0041] Preferably, the method for transmitting and parsing includes:

[0042] Get the collection time U of the actual power supply j jThe last 4 digits of the value are obtained, and the value of the last 4 digits is used as the selection reference. The bit stream of the actual power supply j is synchronously used as the transformed actual power supply j, and then the bit value of the transformed actual power supply j with the same digit as the selection reference is extracted according to the selection reference.

[0043] Preferably, the data transmission and parsing unit is further used to transmit the coding parameter value and the selection reference to the coding coefficient forming unit. Preferably, the method of performing the aggregation processing includes:

[0044] Obtain the coding parameter value, and identify the integer value of the coding parameter value. When the integer value is an odd number, attach the integer value to the first digit of the selection reference to form a corresponding aggregate value, and then reversely arrange the digits of the aggregate value to form a coding coefficient. When the integer value is an even number, attach the integer value to the last digit of the selection reference to form a corresponding aggregate value, and reversely arrange the digits of the aggregate value to form a coding coefficient, and synchronously transmit the formed coding coefficient data to the data control export unit.

[0045] The beneficial effects of the present invention are that, compared with the prior art, the technical effects of the present invention include:

[0046] By performing transmission encryption processing on the actual power supply during transmission and forming corresponding coded data based on the data of the actual power supply itself, not only the reliability of data transmission can be improved by encoding the actual power supply during transmission, but the reliability risk introduced by a separate coding coefficient can also be weakened by the coded data formed based on the own data. In addition, during the storage of the actual power supply, the actual power supply is classified and different segmentation processing is performed for storage based on different classified data, thereby improving the efficiency of the storage area and facilitating storage. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] Figure 1 is a flow chart of the optimization and regulation method based on the virtual power plant described in the present invention;

[0048] Figure 2 It is a schematic diagram of the architecture of the optimization and regulation device based on the virtual power plant described in the present invention. DETAILED DESCRIPTION

[0049] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely expressed in combination with the drawings in the embodiments of the present invention. The embodiments expressed in this application are only part of the embodiments of the present invention, not all of them. According to the spirit of the present invention, other embodiments obtained by ordinary technicians in this field without creative work are all within the protection scope of the present invention.

[0050] like Figure 1 As shown, the optimization and regulation method based on a virtual power plant described in the present invention includes:

[0051] The regulating device periodically obtains the first difference between the actual power supply of the virtual power plant in the current time period and the predicted power supply in the current time period transmitted by the smart meter, so as to perform regulation of the virtual power plant. The method for performing regulation of the virtual power plant is: forming first control information according to the first difference and the predicted power supply in the next time period, and transmitting the first control information to each energy node controller of the virtual power plant, so that the energy node controller adjusts the operation state of the controllable load or energy storage device of the energy node controller in the next time period according to the first control information;

[0052] The method for the smart meter to transmit the actual power supply of the virtual power plant in the current time period to the regulating device includes:

[0053] Step 1: Collect different actual power supplies;

[0054] Step 2: Obtain the collected actual power supply, and perform classification processing on the actual power supply according to the collection time of the actual power supply, and then perform transmission analysis on the actual power supply in the simultaneous classification data;

[0055] Step 3: Obtain the transmitted coding parameter value and the selected reference, and perform aggregation processing on them synchronously;

[0056] Step 4: Obtain the transmitted coding coefficient data, and synchronously store the coding coefficient data for decoding the actual power supply after transmission.

[0057] like Figure 2 As shown, the optimization and regulation device based on a virtual power plant described in the present invention includes:

[0058] The smart meter is connected to the regulating device (the regulating device can be a computer or an industrial computer) by communication, and the regulating device is also connected to the energy node controller by communication;

[0059] The regulating device is used to periodically obtain the first difference between the actual power supply of the virtual power plant in the current time period and the predicted power supply in the current time period transmitted by the smart meter, so as to perform regulation of the virtual power plant. The method for performing regulation of the virtual power plant is: forming first control information according to the first difference and the predicted power supply in the next time period, and transmitting the first control information to each energy node controller of the virtual power plant, so that the energy node controller adjusts the operating state of the controllable load or energy storage device of the energy node controller in the next time period according to the first control information;

[0060] The units running on smart meters include:

[0061] An actual power supply quantity collection unit, used for collecting different actual power supplies;

[0062] In a preferred but non-limiting implementation manner of the present invention, the different actual power supplies are the actual power supplies collected and transmitted by the smart meter in different time periods.

[0063] In a preferred but non-limiting embodiment of the present invention, the collected actual power supply is also provided with its corresponding: collection time and length of the actual power supply.

[0064] In a preferred but non-limiting embodiment of the present invention, the actual power supply amount acquisition unit is further used to transmit the actual power supply amount to the data transmission and analysis unit.

[0065] The data transmission and analysis unit is used to obtain the collected actual power supply, and perform classification processing on the actual power supply according to the collection time of the actual power supply, and then perform transmission and analysis on the actual power supply in the simultaneous classification data;

[0066] In a preferred but non-limiting embodiment of the present invention, the method of treatment comprises:

[0067] The actual power supply quantity collected is numbered as j, where j = 1, 2...k, and the collection time corresponding to the actual power supply quantity j is numbered as U j , synchronously according to the order of acquisition time, the acquisition time is at the time interval U q The actual power supply in is divided into, that is, divided into simultaneous distance data, and the simultaneous distance data is numbered b, and b=A, B, C...Z, where the number b represents the category of the simultaneous distance, just as when b=A, B represents the actual power supply formed in the time interval from 8 o'clock to 9 o'clock, which belongs to the category B to form the category data of the time interval, and the corresponding number j of the actual power supply achieved by the synchronous category does not change.

[0068] The corresponding simultaneous distance belonging data is obtained through the above-mentioned simultaneous distance belonging processing, and then the actual power supply j in the simultaneous distance belonging data is subjected to transmission analysis. In a preferred but non-limiting embodiment of the present invention, the transmission analysis method includes:

[0069] Get the collection time U of the actual power supply j jThe last 4 digits of the transformed actual power j are taken, and the value of the last 4 digits is used as the selection reference. If the acquisition time is 10:24:51, the extracted last 4 digits are 2451. The bit stream of the actual power supply j is synchronously taken as the transformed actual power supply j. Then, according to the selection reference, the bit value of the transformed actual power supply j with the same digit as the selection reference is extracted. If the selection reference is 2451, the bit value of the 2nd bit, the bit value of the 4th bit, the bit value of the 5th bit and the bit value of the 2nd bit in the transformed actual power supply j are extracted accordingly, and aggregation is performed in the extraction order. If the value of the digit with the selection reference is zero, extraction is not performed, and the extracted bit value is used as the coding parameter, and the aggregated coding parameter forms the coding parameter value.

[0070] In a preferred but non-limiting embodiment of the present invention, the data transmission and parsing unit is further used to transmit the coding parameter value and the selected reference to the coding coefficient forming unit.

[0071] A coding coefficient forming unit, used to obtain the transmitted coding parameter value and the selected reference, and synchronously perform aggregation processing on them;

[0072] In a preferred but non-limiting embodiment of the present invention, the method for performing polymerization treatment comprises:

[0073] Obtain the coding parameter value, and identify the integer value of the coding parameter value. When the integer value is an odd number, attach the integer value to the first digit of the selection reference to form a corresponding aggregate value, and then reversely arrange the digits of the aggregate value to form a coding coefficient. When the integer value is an even number, attach the integer value to the last digit of the selection reference to form a corresponding aggregate value, and reversely arrange the digits of the aggregate value to form a coding coefficient, and synchronously transmit the formed coding coefficient data to the data control export unit.

[0074] For example, the obtained coding parameter value is first converted into an integer value through bit rate, and the converted integer value is identified as a whole. Just as the converted integer value is 36, 36 is an even number. Then 36 and the selected reference are aggregated. For example, the selected reference is 2451, and the coding coefficient obtained after the aggregation is 245136. Then, the whole is reversely arranged to obtain 631542, so the corresponding coding coefficient data is the value obtained after the reverse arrangement. If the converted integer value is an odd number, it is placed in the first digit, and then the reverse arrangement is performed to obtain the coding coefficient data.

[0075] The data control export unit is used to obtain the transmitted coding coefficient data, synchronously store the coding coefficient data, and perform decoding processing on the actual power supply after transmission.

[0076] In a preferred but non-limiting embodiment of the present invention, the data transmission and analysis unit can also be used to transmit the actual power supply to the redundant data extraction and analysis unit, and then the redundant data extraction and analysis unit performs analysis on the actual power supply.

[0077] The redundant data extraction and analysis unit is used to obtain the actual power supply transmitted, and the actual power supply obtained here is the actual power supply at the same time, and then perform redundancy identification on the actual power supply, and perform classification processing on the actual power supply;

[0078] The method of executing the sub-processing includes:

[0079] Get the total actual power supply j, then determine whether the actual power supply contains redundant data, and the actual power supply determined here represents whether the total actual power supply contains redundant data, if it contains redundant data, the corresponding actual power supply is classified into the first cluster of actual power supplies and registered as p, and p=1,2...n, if it does not contain redundant data, the corresponding actual power supply is classified into the second cluster of actual power supplies and registered as r, and r=1,2...q, and the corresponding classified data is formed by identifying and classifying the actual power supplies, and the classified data is transmitted to the data storage and analysis unit.

[0080] The data storage and analysis unit is used to obtain the sub-data to be transmitted, and to perform segmentation processing on the actual power supply according to the length of the actual power supply corresponding to the actual power supply;

[0081] The methods of segmentation and disposal include:

[0082] The method for performing a splitting process on the actual power supply p of the first cluster includes:

[0083] Get the first cluster actual power supply p of the whole, synchronously get the corresponding redundant data in the first cluster actual power supply p and register it as s, where s = 1, 2...i, and the length of the actual power supply of the synchronously obtained redundant data s is SM r Then calculate the average length SM of the actual power supply of all redundant data q q , and the mean SM here q To remove the decimal part of the integer quantity, and the length of the actual power supply is the average SM q As a basis for equal division;

[0084] Then, the first cluster of actual power supply p is bisected according to the bisecting standard to obtain l segments of first layer data, and the object of bisecting here is the data remaining after the first cluster of actual power supply is extracted from redundant data, and the l segments of first layer data are synchronously stored in mixed order;

[0085] The mixed order storage method comprises: storing the first layer data of the l segments in reverse order according to the serial numbers, thereby forming corresponding storage data, and synchronously transmitting the storage data to the data control export unit;

[0086] The method for performing a splitting process on the actual power supply r of the second cluster includes:

[0087] The entire second cluster actual power supply r is obtained, and the second cluster actual power supply r is equally divided into 16 segments of second layer data according to the length thereof, and the 16 segments of the equally divided second layer data are numbered synchronously, and the order of the numbering is the same as the order of the equally divided data, and then the 16 segments of the second layer data are stored according to the numbering, and the storage method includes:

[0088] The first 8 segments of the second layer data among the 16 segments are aggregated, and then the last 8 segments of the second layer data are aggregated, and then the aggregated data packets are stored, and the corresponding storage data are synchronously formed, and then the stored data is transmitted to the data control export unit.

[0089] For example, the actual power supply of the second cluster is first divided equally according to the capacity, and is divided into 16 segments. The length of the actual power supply of the second layer data after the synchronous division is an integer. The second cluster actual power supply is divided in order from first to last. The second layer data is also numbered in the order of division. The numbers are increased one by one to sixteen, and then numbers one to eight are aggregated as a whole. After aggregation, 2 sections of aggregated data are obtained, and then the aggregated package is stored.

[0090] The data control export unit is used to obtain the storage data to be transmitted, and transmit the storage data together with the coding coefficient data after linear encoding to the regulating device. The regulating device uses the coding coefficient data to decode the received linearly encoded data to obtain the actual power supply.

[0091] The beneficial effects of the present invention are that, compared with the prior art, the technical effects of the present invention include:

[0092] By performing transmission encryption processing on the actual power supply during transmission and forming corresponding coded data based on the data of the actual power supply itself, not only the reliability of data transmission can be improved by encoding the actual power supply during transmission, but the reliability risk introduced by a separate coding coefficient can also be weakened by the coded data formed based on the own data. In addition, during the storage of the actual power supply, the actual power supply is classified and different segmentation processing is performed for storage based on different classified data, thereby improving the efficiency of the storage area and facilitating storage.

[0093] The present disclosure can be a system, method and / or computer program product. The computer program product can include a computer-readable storage medium carrying computer-readable program instructions for causing a processor to implement each aspect of the present disclosure.

[0094] A computer readable storage medium can be a tangible device that can hold and store instructions for use by an instruction execution device. A computer readable storage medium can be, but is not limited to, an electrical storage device, a magnetic storage device, an optical storage device, an electromagnetic storage device, a semiconductor storage device, or any suitable combination of the above. More specific examples (a non-exhaustive list) of computer readable storage media include: a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a static random access memory (SRAM), a portable compact disk read-only memory (CD-ROM), a digital versatile disk (DVD), a memory stick, a floppy disk, a mechanical encoding device, such as a punch card or a raised structure in a groove on which instructions are stored, and any suitable combination of the above. The computer readable storage medium used herein is not to be interpreted as a transient signal itself, such as a radio wave or other freely propagating electromagnetic wave, an electromagnetic wave propagating through a waveguide or other transmission medium (such as a light pulse through a fiber optic cable), or an electrical signal transmitted through a wire.

[0095] The computer readable program instructions described herein can be downloaded from a computer readable storage medium to each computing / processing device, or downloaded to an external computer or external storage device via a network, such as the Internet, a local area network, a wide area network, and / or a wireless network. The network can include copper transmission cables, optical fiber transmission, wireless transmission, routers, firewalls, switches, gateway computers, and / or edge servers. The network adapter card or network interface in each computing / processing device receives the computer readable program instructions from the network and forwards the computer readable program instructions for storage in the computer readable storage medium in each computing / processing device.

[0096] The computer program instructions for performing the operations of the present disclosure can be assembler instructions, instruction set architecture (ISA) instructions, machine instructions, machine-dependent instructions, microcode, firmware instructions, state setting data, or source code or object code written in any combination of one or more programming languages, including object-oriented programming languages ​​such as Smalltalk, C++, etc., and conventional procedural programming languages ​​such as "C" or similar programming languages. The computer readable program instructions can be executed entirely on the controller computer, partially on the controller computer, as a separate software package, partially on the controller computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer can be connected to the controller computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or can be connected to the external computer (such as through the Internet using an Internet service provider). In some embodiments, each aspect of the present disclosure is implemented by personalizing an electronic circuit by utilizing state information of a computer-readable program instruction, such as a programmable logic circuit, a field programmable gate array (FPGA), or a programmable logic array (PLA), which can execute a computer-readable program instruction.

[0097] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents, and any modifications or equivalent replacements that do not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

Claims

1. An optimization and regulation method based on virtual power plant, It is characterized in that include: The regulating device periodically obtains the first difference between the actual power supply of the virtual power plant in the current time period and the predicted power supply in the current time period transmitted by the smart meter, thereby performing regulation of the virtual power plant; The method for the smart meter to transmit the actual power supply of the virtual power plant in the current time period to the regulating device includes: Step 1: Collect different actual power supplies; Step 2: Obtain the collected actual power supply, and perform classification processing on the actual power supply according to the collection time of the actual power supply, and then perform transmission analysis on the actual power supply in the simultaneous classification data; Step 3: Obtain the transmitted encoding parameter value and the selected reference, and perform aggregation processing on them synchronously; Step 4: Obtain the transmitted coding coefficient data, and synchronously store the coding coefficient data for decoding the actual power supply after transmission.

2. An optimization and regulation device based on a virtual power plant, It is characterized in that include: The smart meter is connected to the regulating device through communication, and the regulating device is also connected to the energy node controller through communication; The regulating device is used to regularly obtain the first difference between the actual power supply of the virtual power plant in the current time period and the predicted power supply in the current time period transmitted by the smart meter, so as to perform regulation of the virtual power plant; The units running on smart meters include: An actual power supply quantity collection unit, used for collecting different actual power supplies; The data transmission and analysis unit is used to obtain the collected actual power supply, and perform classification processing on the actual power supply according to the collection time of the actual power supply, and then perform transmission and analysis on the actual power supply in the simultaneous classification data; A coding coefficient forming unit, used to obtain the transmitted coding parameter value and the selected reference, and synchronously perform aggregation processing on them; The data control export unit is used to obtain the transmitted coding coefficient data, synchronously store the coding coefficient data, and perform decoding processing on the actual power supply after transmission.

3. The optimization and regulation device based on virtual power plant according to claim 2, It is characterized in that The data transmission and analysis unit can also be used to transmit the actual power supply to the redundant data extraction and analysis unit, and then the redundant data extraction and analysis unit performs analysis on the actual power supply; The redundant data extraction and analysis unit is used to obtain the actual power supply transmitted, and the actual power supply obtained here is the actual power supply at the same time, and then perform redundancy identification on the actual power supply, and perform classification processing on the actual power supply; The method of executing the sub-processing includes: Get the total actual power supply j, then determine whether the actual power supply contains redundant data, and the actual power supply determined here represents whether the total actual power supply contains redundant data, if it contains redundant data, the corresponding actual power supply is classified into the first cluster of actual power supplies and registered as p, and p=1,2...n, if it does not contain redundant data, the corresponding actual power supply is classified into the second cluster of actual power supplies and registered as r, and r=1,2...q, thereby forming the corresponding classified data, and transmitting the classified data to the data storage and analysis unit. The data storage and analysis unit is used to obtain the sub-data to be transmitted, and to perform segmentation processing on the actual power supply according to the length of the actual power supply corresponding to the actual power supply; The methods of segmentation and disposal include: The method for performing a splitting process on the actual power supply p of the first cluster includes: Get the first cluster actual power supply p of the whole, synchronously get the corresponding redundant data in the first cluster actual power supply p and register it as s, where s = 1, 2...i, and the length of the actual power supply of the synchronously obtained redundant data s is SM r Then calculate the average length SM of the actual power supply of all redundant data q q , and the mean SM here q To remove the decimal part of the integer quantity, and the length of the actual power supply is the average SM q As a basis for equal division; Then, the first cluster of actual power supply p is bisected according to the bisecting standard to obtain l segments of first layer data, and the object of bisecting here is the data remaining after the first cluster of actual power supply is extracted from redundant data, and the l segments of first layer data are synchronously stored in mixed order; The mixed order storage method comprises: storing the first layer data of the l segments in reverse order according to the serial numbers, thereby forming corresponding storage data, and synchronously transmitting the storage data to the data control export unit; The method for performing a splitting process on the actual power supply r of the second cluster includes: The entire second cluster actual power supply r is obtained, and the second cluster actual power supply r is equally divided into 16 segments of second layer data according to the length thereof, and the 16 segments of the equally divided second layer data are numbered synchronously, and the order of the numbering is the same as the order of the equally divided data, and then the 16 segments of the second layer data are stored according to the numbering, and the storage method includes: Aggregate the first 8 segments of the second layer data among the 16 segments, then aggregate the last 8 segments of the second layer data, then store the aggregated data packets, synchronously form corresponding storage data, and then transmit the storage data to the data control export unit; The data control export unit is used to obtain the storage data to be transmitted, and transmit the storage data together with the coding coefficient data after linear encoding to the regulating device. The regulating device uses the coding coefficient data to decode the received linearly encoded data to obtain the actual power supply.

4. The optimization and regulation device based on virtual power plant according to claim 3, It is characterized in that Different actual power supplies are the actual power supplies collected by smart meters in different time periods.

5. The optimization and regulation device based on virtual power plant according to claim 4, It is characterized in that The actual power supply collected is also accompanied by its corresponding: collection time and length of the actual power supply.

6. The optimization and regulation device based on virtual power plant according to claim 5, It is characterized in that The actual power supply amount acquisition unit is also used to transmit the actual power supply amount to the data transmission and analysis unit.

7. The optimization and regulation device based on virtual power plant according to claim 6, It is characterized in that The methods of disposal include: The actual power supply quantity collected is numbered as j, where j = 1, 2...k, and the collection time corresponding to the actual power supply quantity j is numbered as U j , synchronously according to the order of acquisition time, the acquisition time is at the time interval U q The actual power supply in is divided into, that is, into simultaneous distance data, and the simultaneous distance data is numbered b, and b = A, B, C...Z, where the number b represents the category of the simultaneous distance.

8. The optimization and regulation device based on virtual power plant according to claim 7, It is characterized in that The method of transmitting the analysis includes: Get the collection time U of the actual power supply j j The last 4 digits of the actual power supply j are obtained, and the value of the last 4 digits is used as the selection reference, and the bit stream of the actual power supply j is synchronously used as the conversion actual power supply j.

9. The optimization and regulation device based on virtual power plant according to claim 8, It is characterized in that The method of transmitting the analysis includes: Then, according to the selected reference, the bit value of the same digit as the actual power supply j and the selected reference is extracted.

10. The optimization and regulation device based on virtual power plant according to claim 9, It is characterized in that The data transmission and analysis unit is also used to transmit the coding parameter value and the selection reference to the coding coefficient forming unit. Preferably, the method of performing the aggregation processing includes: Obtain the coding parameter value, and identify the integer value of the coding parameter value. When the integer value is an odd number, attach the integer value to the first digit of the selection reference to form a corresponding aggregate value, and then reversely arrange the digits of the aggregate value to form a coding coefficient. When the integer value is an even number, attach the integer value to the last digit of the selection reference to form a corresponding aggregate value, and reversely arrange the digits of the aggregate value to form a coding coefficient, and synchronously transmit the formed coding coefficient data to the data control export unit.

Citation Information

Cited By

  • Detection data processing system and method for hydraulic hammer power system

    CN120234323A