Engineering construction project management system and operation method thereof

Through the design of an integrated engineering construction project management system, the problem of unification of the entire process of engineering projects in the existing technology is solved, the management efficiency and safety management level are improved, information sharing and collaboration are promoted, and standardized file management is realized.

CN119005879APending Publication Date: 2024-11-22ANHUI SUN CREATE ELECTRONICS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410953538.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The existing engineering construction project management system cannot achieve unified management and monitoring of the entire process of the project, and lacks an integrated and standardized management system, resulting in inefficiency and poor information flow.

Method used

A project construction project management system was designed, including project management module, task management module, collaborative management module, material management module, safety education management module, working time management module, expense management module, announcement notification module, message management module and report management Modules, through these modules, the entire process management and monitoring of engineering projects are realized.

Benefits of technology

It improves project management efficiency, realizes full-process management, promotes information sharing and communication and cooperation, strengthens security management, realizes standardized file management, and reduces human errors and information improper information problems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119005879A_ABST
    Figure CN119005879A_ABST
Patent Text Reader

Abstract

The invention discloses an engineering construction project management system, which comprises a project management module, a task management module, a collaborative management module, a material management module, a safety education management module, a man-hour management module, a cost management module, an announcement notification module, a message management module and a report management module, the project management module is used for creating, editing, deleting and querying engineering project information and performing classified management and monitoring on a plurality of projects; the task management module is used for distributing, tracking and supervising each task in an engineering project; and the collaborative management module is used for realizing information sharing, communication and collaboration among the members of the project team. By adopting the integrated and standardized management system and method, the project management efficiency can be improved, the whole-process management can be realized, the information sharing and communication cooperation can be promoted, the safety management can be enhanced, the standardized file management can be realized, and the system and the method have a remarkable practical application value and a wide application prospect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of management systems, and in particular to an engineering construction project management system and an operating method of the system. Background Art

[0002] In traditional engineering construction project management, manual management is usually adopted, and project managers use paper documents or Excel spreadsheets to carry out project planning, task allocation, progress supervision, cost control and other management tasks. This method is not only inefficient, but also prone to human errors and information blockages, making it difficult to achieve standardized management of the entire process of the project.

[0003] With the development of information technology, more and more engineering projects are beginning to be managed using information technology. However, the existing engineering construction project management system often only targets certain management needs, such as task management, material management, and time management, but lacks an integrated and standardized management system, making it impossible to achieve unified management and monitoring of the entire process of the project. Summary of the invention

[0004] The purpose of the present invention is to solve the problem that it is impossible to achieve unified management and monitoring of the entire process of an engineering project, and to propose an engineering construction project management system and an operation method of the system.

[0005] The purpose of the present invention can be achieved through the following technical solutions:

[0006] A construction project management system, including a project management module, a task management module, a collaborative management module, a material management module, a safety education management module, a working time management module, a cost management module, a notice module, a message management module, and a report management module:

[0007] The project management module is used to create, edit, delete and query engineering project information, and to classify, manage and monitor multiple projects;

[0008] The task management module is used to assign, track and supervise various tasks in the engineering project;

[0009] The collaborative management module is used to achieve information sharing, communication and collaboration among project team members;

[0010] The material management module is used to implement material procurement and management of engineering projects;

[0011] The safety education management module is used to implement the management of daily safety education for construction units, including the formulation of safety education plans, safety education records and safety inspections;

[0012] The working time management module is used to record and count the working time information of individuals and projects, including working time reporting, review and statistics functions;

[0013] The cost management module is used to formulate and monitor the cost budget and expenditure of the project, and adjust the cost plan;

[0014] The announcement notification module is used to issue the latest status notification of the engineering project;

[0015] The message management module is used to provide expiration reminders and overdue reminders for task plans in engineering projects;

[0016] The report management module is used to record and compile statistics of completed tasks and uncompleted tasks and reasons in the engineering project.

[0017] As a further solution of the present invention: the message management module can issue a task expiration reminder three days before the task end time, and issue an overdue reminder when the task exceeds the end time.

[0018] An operation method of an engineering construction project management system, an operation method of a project management module: a user logs in to the system and enters the project management module, the system displays an interface for creating an engineering project information, the user enters information such as the project name, project leader, project schedule and budget on the interface, and the user submits the engineering project information to the system after completing the input; the system verifies and reviews the engineering project information after receiving it; when the review is passed, the system saves the engineering project information into a database and completes the creation of the engineering project information; when the review is not passed, the system prompts the user to modify the relevant information and conduct a new review.

[0019] As a further scheme of the present invention: Task management module operation method: the user enters the task management module, the system displays the task assignment interface, the user creates a task on the interface, and sets the relevant information of the task, task name, task description, task leader, task start time and end time; after the user completes the settings, the task is submitted to the system; after the system receives the task submitted by the user, it assigns the task according to the task schedule; the system assigns the task to the corresponding project team member, and notifies the task leader to start executing the task through message notification or email; after receiving the task, the task leader starts to execute the task and records the progress and status of the task during the execution of the task; during the execution of the task, the system can monitor the execution of the task in real time through the collaborative management module to understand the progress and status of the task; when the task is delayed or abnormal, the system can send a reminder message to the task leader through the message management module to remind the task leader to deal with the problem in time; when the task is completed, the task leader can submit the completion status of the task in the task management module and mark the task as completed.

[0020] As a further scheme of the present invention: Operation method of the collaborative management module: When a user enters the collaborative management module, the system displays a real-time communication interface, including file sharing, online discussion and task collaboration functions; project team members can upload and download project-related files and materials through the file sharing function; users can communicate in real time through the online discussion function to answer questions and exchange opinions; the system records communication records, which can be queried and viewed later; users can assign, execute and supervise tasks through the task collaboration function.

[0021] As a further solution of the present invention: Material management module operation method: the user enters the material management module, the system displays the interface for managing materials, the user creates a material requirement plan on the interface, including the name, quantity, specification, and supplier information of the required materials, and submits the material requirement plan to the system after the user completes the input; after the system receives the material requirement plan submitted by the user, it verifies and reviews it; when the review is passed, the system purchases materials according to the material requirement plan. The system sends a purchase order to the supplier and tracks the arrival of the purchase order; when the material arrives, the system creates a material entry order in the material management module, records the arrival information of the material, including the name, quantity, and specification of the material; when the review fails, the system prompts the user to modify the material requirement plan and re-review it.

[0022] As a further solution of the present invention: operation method of the working time management module: the user enters the working time management module, the system displays the interface for recording and counting working time, the user creates personal and project working time information on the interface, and submits the working time information to the system after the user completes the input. After the system receives the working time information submitted by the user, it verifies and reviews it. When the review is passed, the system saves the working time information into the database and counts the working time of the individual and the project. When the review fails, the system prompts the user to modify the working time information and re-review it.

[0023] As a further solution of the present invention: Message management module operation method: When the user enters the message management module, the system displays the task reminder interface, and performs task expiration reminders and overdue reminders based on the task end time and actual progress. When the task end time reaches three days before the end time, the system will automatically send a task expiration reminder message to remind project team members to pay attention to the task progress and ensure that the task is completed on time. When the task is not completed within the end time, the system will automatically send an overdue reminder message to remind project team members to pay attention to the task progress and solve the problem in time.

[0024] As a further solution of the present invention: Operation method of the report management module: The user enters the report management module, the system displays an interface for recording and counting task completion status, the user enters completed task and unfinished task information on the interface, and the user submits the task completion status to the system after completing the input. After the system receives the task completion status submitted by the user, it verifies and reviews it. When the review is passed, the system saves the task completion status to the database, and counts the completed tasks and unfinished tasks. When the review fails, the system prompts the user to modify the task completion status and re-review it.

[0025] Beneficial effects of the present invention:

[0026] 1. Improve project management efficiency: By integrating various management function modules, the system can quickly and accurately complete various tasks in engineering project management, reduce manual management and human errors, and improve project management efficiency.

[0027] 2. Realize full process management: The system covers the entire process of the project from planning to completion, including project management, task management, collaborative management, material management, safety education management, working time management, cost management and other links, realizing comprehensive management and monitoring of the project.

[0028] 3. Promote information sharing and communication and collaboration: The collaborative management module can realize information sharing and communication and collaboration among project team members, avoid problems such as poor information flow and duplication of work, and improve team collaboration efficiency.

[0029] 4. Strengthen safety management: The safety education management module can realize the management of daily safety education of construction units, improve the safety awareness and management level of construction sites, and reduce the occurrence of safety accidents.

[0030] 5. Realize standardized file management: The report management module can record and count the completed and unfinished tasks and reasons in the engineering project, realize standardized management of engineering project files, and facilitate subsequent query and analysis.

[0031] In summary, the invention patent of "A construction project management system and its operation method" can improve project management efficiency, realize whole process management, promote information sharing and communication and collaboration, strengthen safety management, and realize standardized file management by adopting an integrated and standardized management system and method. It has significant practical application value and broad application prospects. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] The present invention will be further described below in conjunction with the accompanying drawings.

[0033] Figure 1 It is a system schematic diagram of the present invention. DETAILED DESCRIPTION

[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] See also Figure 1 As shown, the present invention is a construction project management system, including a project management module, a task management module, a collaborative management module, a material management module, a safety education management module, a working time management module, a cost management module, a notice module, a message management module, and a report management module:

[0036] The project management module is used to create, edit, delete and query engineering project information, and to classify, manage and monitor multiple projects;

[0037] The task management module is used to assign, track and supervise various tasks in the engineering project;

[0038] The collaborative management module is used to achieve information sharing, communication and collaboration among project team members;

[0039] The material management module is used to implement material procurement and management of engineering projects;

[0040] The safety education management module is used to implement the management of daily safety education for construction units, including the formulation of safety education plans, safety education records and safety inspections;

[0041] The working time management module is used to record and count the working time information of individuals and projects, including working time reporting, review and statistics functions;

[0042] The cost management module is used to formulate and monitor the cost budget and expenditure of the project, and adjust the cost plan;

[0043] The announcement notification module is used to issue the latest status notification of the engineering project;

[0044] The message management module is used to provide expiration reminders and overdue reminders for task plans in engineering projects;

[0045] The report management module is used to record and compile statistics of completed tasks and uncompleted tasks and reasons in the engineering project.

[0046] The message management module can issue a task expiration reminder three days before the task end time, and issue an overdue reminder when the task exceeds the end time.

[0047] The specific processing method of the project management module is as follows:

[0048] Project information is created in the project management module, including project name, project leader, project schedule, budget and other information.

[0049] S1. The user logs into the system and enters the project management module.

[0050] S2. In the project management module, the system provides an interface for creating engineering project information, where users can enter information such as project name, project leader, project schedule and budget.

[0051] S3. After the user completes input, click the Submit button to submit the project information to the system.

[0052] S4. After receiving the project information submitted by the user, the system performs verification and review.

[0053] S5. If the review is passed, the system will save the project information into the database and complete the creation of the project information.

[0054] S6. If the review fails, the system will prompt the user to modify the relevant information and re-review it.

[0055] Through the above modules, users can create engineering project information in the project management module, including project name, project leader, project schedule and budget, etc., to facilitate subsequent project management and task allocation operations.

[0056] The specific processing method of the task management module is as follows:

[0057] The task management module assigns tasks and monitors the execution of tasks. The task management module can assign and monitor tasks according to the task schedule to ensure that tasks are completed on time.

[0058] S1. The user enters the task management module.

[0059] S2. In the task management module, the system provides an interface for assigning tasks, on which users can create tasks and set relevant information of the tasks, such as task name, task description, task leader, task start time and end time, etc.

[0060] S3. After the user completes the settings, click the Submit button to submit the task to the system.

[0061] S4. After the system receives the task submitted by the user, it assigns the task according to the task schedule.

[0062] S5. The system assigns the task to the corresponding project team member and notifies the task leader to start executing the task through message notification or email.

[0063] S6. After receiving the task, the task leader starts to execute the task and records the progress and status of the task during the execution of the task.

[0064] S7. During the task execution process, the system can monitor the execution of the task in real time through the collaborative management module to understand the task progress and status.

[0065] S8. If a task is delayed or encounters an abnormal situation, the system can send a reminder message to the task leader through the message management module to remind the task leader to deal with the problem in a timely manner.

[0066] S9. When the task is completed, the task leader can submit the completion status of the task in the task management module and mark the task as completed.

[0067] Through the above modules, users can assign tasks and monitor the execution of tasks in the task management module to ensure that tasks are completed on time. At the same time, the system can assign and monitor tasks according to the task schedule to improve project management efficiency.

[0068] In the collaborative management module, project team members can communicate in real time through functions such as file sharing, online discussion and task collaboration to avoid information blockage and duplication of work.

[0069] S1. The user enters the collaborative management module.

[0070] S2. In the collaborative management module, the system provides a real-time communication interface, including functions such as file sharing, online discussion and task collaboration.

[0071] S3. Project team members can upload and download project-related files and materials through the file sharing function to avoid duplication of work and information blockage.

[0072] S4. Project team members can communicate in real time through the online discussion function to conduct communication activities such as answering questions and exchanging opinions. The system can record communication records for subsequent query and review.

[0073] S5. Project team members can use the task collaboration function to assign, execute and supervise tasks. The task leader can assign tasks to other members, and other members can collaborate to complete the tasks. At the same time, the system can monitor the progress and status of tasks to avoid duplication of work and information blockage.

[0074] S6. Through the collaborative management module, project team members can communicate in real time, share files, and complete tasks collaboratively, avoiding problems such as poor information flow and duplication of work, and improving team collaboration efficiency.

[0075] Through the above modules, users can perform real-time communication, file sharing, task collaboration and other operations in the collaborative management module to promote information sharing, communication and collaboration among project team members.

[0076] The specific processing methods in the material management module are as follows:

[0077] In the material management module, materials are purchased and managed according to the material requirement plan of the project. The material management module can purchase and manage materials according to the material requirement plan of the project to ensure that the materials arrive and are used on time.

[0078] S1. The user enters the material management module.

[0079] S2. In the material management module, the system provides an interface for managing materials, on which users can create material requirement plans, including the name, quantity, specifications, suppliers and other information of the required materials.

[0080] S3. After the user completes input, click the Submit button to submit the material requirement plan to the system.

[0081] S4. After receiving the material requirement plan submitted by the user, the system will verify and review it.

[0082] S5. If the review is passed, the system will purchase materials according to the material requirement plan. The system will send a purchase order to the supplier and track the arrival of the purchase order.

[0083] S6. When the materials arrive, the system creates a material entry order in the material management module to record the arrival information of the materials, including the name, quantity, specifications, etc. of the materials.

[0084] S7. The system dispatches and manages materials according to the project schedule and actual progress to ensure that materials arrive and are used on time.

[0085] S8. If the review fails, the system will prompt the user to modify the material requirement plan and review it again.

[0086] Through the above modules, users can purchase and manage materials according to the material requirement plan of the project in the material management module to ensure that the materials arrive and are used on time. At the same time, the system can track the arrival of purchase orders, schedule and manage materials, and avoid material shortages or waste.

[0087] The specific processing method of the safety education management module is as follows:

[0088] The safety education management module manages the daily safety education of construction units. The safety education management module can formulate safety education plans, record safety education records, and conduct safety inspections to improve the safety awareness and management level of the construction site.

[0089] S1. Enter the safety education management module.

[0090] S2. In the safety education management module, the system provides an interface for managing safety education, on which users can create safety education plans, including the time, location, content, instructor and other information of safety education.

[0091] S3. After the user completes the settings, click the Submit button to submit the safety education plan to the system.

[0092] S4. After receiving the safety education plan submitted by the user, the system will verify and review it.

[0093] S5. If the review is passed, the system will create and manage safety education records according to the safety education plan. The system can record the time, location, content, lecturer and other information of safety education, and save the safety education records.

[0094] S6. During the safety education process, the system can monitor the progress of safety education in real time through the collaborative management module to understand the progress and status of safety education.

[0095] S7. If an abnormal situation occurs in safety education, the system can send reminder messages to relevant personnel through the message management module to remind them to deal with the problem in a timely manner.

[0096] S8. The system can also conduct safety inspections based on safety education records, evaluate the safety status and safety awareness level of the construction site, and promptly identify and resolve safety hazards.

[0097] Through the above modules, users can manage the daily safety education of construction units in the safety education management module, formulate safety education plans, record safety education records, and conduct safety inspections to improve the safety awareness and management level of the construction site. At the same time, the system can monitor the progress of safety education in real time and promptly discover and resolve safety hazards.

[0098] The specific processing method of the working time management module is as follows:

[0099] S1. Record and count the working hours of individuals and projects in the working hours management module. The working hours management module can realize the functions of reporting, reviewing and counting working hours, which is convenient for project managers to grasp the project progress and personnel work status.

[0100] S2. The user enters the working time management module.

[0101] S3. In the working time management module, the system provides an interface for recording and counting working time. Users can create personal and project working time information on the interface, including working date, time, work content, working hours and other information.

[0102] S4. After the user completes the input, click the Submit button to submit the working time information to the system.

[0103] S5. After receiving the working time information submitted by the user, the system verifies and reviews it.

[0104] S6. If the review is passed, the system will save the working time information into the database and count the working hours of individuals and projects.

[0105] S7. The system can realize the functions of reporting, reviewing and statistics of working hours, which is convenient for project managers to grasp the project progress and personnel work status.

[0106] S8. If the review fails, the system will prompt the user to modify the working time information and re-review it.

[0107] Through the above modules, users can record and count the working hours of individuals and projects in the working hours management module, which is convenient for project managers to grasp the project progress and personnel work status. At the same time, the system can realize the functions of reporting, reviewing and counting working hours, and improve project management efficiency.

[0108] The specific processing method of the expense management module is as follows:

[0109] Module G formulates the cost budget of the project in the cost management module and monitors the cost expenditure. The cost management module can formulate the cost budget, monitor the cost expenditure and adjust the cost plan to avoid cost overruns and budget shortfalls.

[0110] S1. The user enters the expense management module.

[0111] S2. In the expense management module, the system provides an interface for making expense budgets, on which users can input the expense budget information of the project, including the budget amount, source, expenditure time and other information of each expense.

[0112] S3. After the user completes input, click the Submit button to submit the cost budget information to the system.

[0113] S4. After receiving the expense budget information submitted by the user, the system will verify and review it.

[0114] S5. If the review is passed, the system will save the cost budget information into the database as the basis for the project cost.

[0115] S6. During the project implementation, the system can monitor the cost expenditure in real time and compare and analyze it with the cost budget information.

[0116] S7. If there is a cost overrun or budget shortfall, the system can issue a reminder notification to remind project managers to adjust the cost plan in a timely manner.

[0117] S8. Project managers can adjust cost plans based on actual conditions to avoid cost overruns and budget shortfalls.

[0118] Through the above modules, users can formulate the cost budget of the project in the cost management module and monitor the cost expenditure to avoid cost overruns and budget shortfalls. At the same time, the system can monitor the cost expenditure in real time, remind project managers to adjust the cost plan in time, and improve project management efficiency.

[0119] The specific processing method of the announcement notification module is as follows:

[0120] Publish the latest status notifications of engineering projects in the announcement notification module and deliver important information to project team members in a timely manner.

[0121] S1. The user enters the announcement notification module.

[0122] S2. In the announcement notification module, the system provides an interface for publishing notifications, on which users can enter the latest status notifications of the project, including the title, content, release time and other information of the notification.

[0123] S3. After the user completes input, click the Submit button to submit the latest status notification to the system.

[0124] S4. After receiving the latest status notification submitted by the user, the system will conduct verification and review.

[0125] S5. If the review is passed, the system will publish the latest situation notification to the system and deliver important information to the project team members in a timely manner through message notifications or emails.

[0126] S6. Project team members can view the latest status notifications through the announcement notification module to understand the latest progress and important information of the project.

[0127] Through the above modules, users can publish the latest status notifications of the engineering project in the announcement notification module, and promptly deliver important information to project team members to ensure that project team members can promptly understand and grasp the latest progress and important information of the engineering project.

[0128] The specific processing method for the message management module is as follows:

[0129] In the message management module, you can provide task expiration reminders and overdue reminders. The message management module can provide task expiration reminders three days before the task end time, and overdue reminders when the task exceeds the end time, reminding project team members to pay attention to the task progress.

[0130] S1. The user enters the message management module.

[0131] S2. In the message management module, the system provides a task reminder interface, which can provide task expiration reminders and overdue reminders based on the task end time and actual progress.

[0132] S3. When the task deadline reaches three days before the deadline, the system will automatically send a task expiration reminder message to remind project team members to pay attention to the task progress and ensure that the task is completed on time.

[0133] S4. If the task is not completed within the end time, the system will automatically send an overdue reminder message to remind project team members to pay attention to the task progress and solve the problem in time.

[0134] S5. The message management module can record and count the task expiration reminders and overdue reminders, making it easier for project managers to understand the task progress and reminders.

[0135] Through the above modules, users can remind project team members of due and overdue tasks in the message management module, reminding them to pay attention to task progress and ensure that tasks are completed on time. At the same time, the system can record and count task reminders, making it easier for project managers to understand task progress and reminders, and improve project management efficiency.

[0136] The specific processing method for the report management module is as follows:

[0137] The report management module records and compiles statistics on completed and unfinished tasks and reasons in the project. The report management module can achieve standardized management of project archives, facilitating subsequent query and analysis.

[0138] S1. The user enters the report management module.

[0139] S2. In the report management module, the system provides an interface for recording and counting task completion status. Users can enter completed and unfinished task information on the interface, including task name, person in charge, completion status, reason and other information.

[0140] S3. After the user completes the input, click the Submit button to submit the task completion status to the system.

[0141] S4. After receiving the task completion status submitted by the user, the system performs verification and review.

[0142] S5. If the review is passed, the system will save the task completion status to the database and count the completed tasks and unfinished tasks.

[0143] S6. The system can realize standardized management of engineering project archives, facilitating subsequent query and analysis.

[0144] S7. If the review fails, the system will prompt the user to modify the task completion status and re-review it.

[0145] Through the above modules, users can record and count the completed and unfinished tasks and reasons in the project in the report management module, realize the standardized management of project archives, and facilitate subsequent query and analysis. At the same time, the system can verify and review the completion of tasks to improve data accuracy and reliability.

[0146] The engineering construction project management system and method of the present invention can realize efficient and standardized management of the entire process of the engineering project, thereby improving the execution efficiency and success rate of the engineering project.

[0147] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made according to the scope of application of the present invention should still fall within the scope of the claims of the present invention.

Claims

1. A construction project management system, It is characterized in that Including project management module, task management module, collaborative management module, material management module, safety education management module, working time management module, expense management module, announcement notification module, message management module, and report management module: The project management module is used to create, edit, delete and query engineering project information, and to classify, manage and monitor multiple projects; The task management module is used to assign, track and supervise various tasks in the engineering project; The collaborative management module is used to achieve information sharing, communication and collaboration among project team members; The material management module is used to implement material procurement and management of engineering projects; The safety education management module is used to implement the management of daily safety education for construction units, including the formulation of safety education plans, safety education records and safety inspections; The working time management module is used to record and count the working time information of individuals and projects, including working time reporting, review and statistics functions; The cost management module is used to formulate and monitor the cost budget and expenditure of the project, and adjust the cost plan; The announcement notification module is used to issue the latest status notification of the engineering project; The message management module is used to provide expiration reminders and overdue reminders for task plans in engineering projects; The report management module is used to record and compile statistics of completed tasks and uncompleted tasks and reasons in the engineering project.

2. According to the construction project management system described in claim 1, It is characterized in that The message management module can issue a task expiration reminder three days before the task end time, and issue an overdue reminder when the task exceeds the end time.

3. According to the operation method of a construction project management system according to claim 1 or 2, It is characterized in that Operation method of project management module: the user logs in to the system and enters the project management module. The system displays the interface for creating project information. The user enters the project name, project leader, project schedule and budget, etc. on the interface. After the user completes the input, the project information is submitted to the system. The system verifies and reviews the project information submitted by the user. When the review is passed, the system saves the project information to the database, completing the creation of the project information. If the review fails, the system prompts the user to modify the relevant information and re-review it.

4. According to the operation method of a construction project management system according to claim 1 or 2, It is characterized in that Operation method of task management module: when the user enters the task management module, the system displays the task assignment interface, the user creates a task on the interface and sets the relevant information of the task, including task name, task description, task leader, task start time and end time; after the user completes the settings, he / she submits the task to the system; after the system receives the task submitted by the user, it assigns the task according to the task schedule; the system assigns the task to the corresponding project team member and notifies the task leader to start executing the task through message notification or email; after receiving the task, the task leader starts to execute the task and records the progress and status of the task during the execution of the task; during the execution of the task, the system can monitor the execution of the task in real time through the collaborative management module to understand the progress and status of the task; when the task is delayed or abnormal, the system can send a reminder message to the task leader through the message management module to remind the task leader to deal with the problem in time; when the task is completed, the task leader can submit the completion status of the task in the task management module and mark the task as completed.

5. According to the operation method of a construction project management system according to claim 1 or 2, It is characterized in that How to operate the collaborative management module: When a user enters the collaborative management module, the system displays a real-time communication interface, including file sharing, online discussion, and task collaboration functions; project team members can upload and download project-related files and materials through the file sharing function; users can communicate in real time through the online discussion function to answer questions and exchange opinions; the system records communication records, which can be queried and viewed later; Users can assign, execute and supervise tasks through the task collaboration function.

6. According to the operation method of a construction project management system according to claim 1 or 2, It is characterized in that Operation method of material management module: When the user enters the material management module, the system displays the interface for managing materials. The user creates a material requirement plan on the interface, including the name, quantity, specification, and supplier information of the required materials. After the user completes the input, the material requirement plan is submitted to the system. After the system receives the material requirement plan submitted by the user, it verifies and reviews it. When the review is passed, the system will purchase materials according to the material requirement plan. The system will send a purchase order to the supplier and track the arrival of the purchase order; when the material arrives, the system will create a material entry order in the material management module to record the arrival information of the material, including the name, quantity, and specifications of the material; when the review is not passed, the system will prompt the user to modify the material requirement plan and re-review it.

7. According to the operation method of a construction project management system according to claim 1 or 2, It is characterized in that Operation method of working time management module: When the user enters the working time management module, the system displays the interface for recording and counting working time. The user creates personal and project working time information on the interface. After the user completes the input, the working time information is submitted to the system. After the system receives the working time information submitted by the user, it verifies and reviews it. When the review is passed, the system saves the working time information to the database and counts the working time of the individual and project. When the review fails, the system prompts the user to modify the working time information and re-review it.

8. According to the method for operating a construction project management system according to claim 1 or 2, It is characterized in that Operation method of message management module: When the user enters the message management module, the system displays the task reminder interface, and performs task expiration reminders and overdue reminders based on the task end time and actual progress. When the task end time reaches three days before, the system will automatically send a task expiration reminder message to remind project team members to pay attention to the task progress and ensure that the task is completed on time. When the task is not completed within the end time, the system will automatically send an overdue reminder message to remind project team members to pay attention to the task progress and solve the problem in time.

9. According to the operation method of a construction project management system according to claim 1 or 2, It is characterized in that Operation method of the report management module: When the user enters the report management module, the system displays the interface for recording and counting task completion status. The user enters the completed task and unfinished task information on the interface. After the user completes the input, the task completion status is submitted to the system. After the system receives the task completion status submitted by the user, it verifies and reviews it. When the review is passed, the system saves the task completion status to the database and counts the completed and unfinished tasks. When the review fails, the system prompts the user to modify the task completion status and re-review it.