Construction method of wide non-equal-span continuous arch bridge

By using pier pile foundation and support construction, pre-embedded prestressed steel bundles and temporary hardening to erect a bracket in the construction of non-equal span continuous arch bridges, the problems of high construction difficulty and high cost are solved, and the construction balance and Stability ensures construction quality and cost-effectiveness.

CN119021077APending Publication Date: 2024-11-26中铁建设集团中南建设有限公司 +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411127422.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The construction of non-equal span continuous arch bridges is difficult, the materials are difficult to turn over, the construction period is long, the cost is high, and the segmented construction can easily lead to uneven stress on the pier pile foundation, resulting in deviation.

Method used

The pier pile foundation and bearing construction is adopted, pre-embedded prestressed steel bundles, temporary hardening and erecting brackets, concrete is poured in sections, and horizontal displacement is restrained by friction plates and prestressed steel bundles to ensure the balance and stability of the construction.

Benefits of technology

By temporarily prestressing the displacement of the bearing pile foundation and using friction plates to prevent the displacement of the abutment pile foundation, the conditions for segmented construction are provided, the problems of high construction difficulty and high cost are solved, and the construction quality and cost-effectiveness are ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021077A_ABST
    Figure CN119021077A_ABST
Patent Text Reader

Abstract

A construction method of a wide-width non-equal-span continuous arch bridge comprises the steps that firstly, an abutment pile foundation and a bearing platform are constructed, and an arch support is constructed on the bearing platform; 2, pre-stressed steel beams are pre-buried on skewbacks of side spans and secondary side spans at the two ends of the continuous arch bridge; 3, the site is temporarily hardened, and a support is erected; 4, the single arch is constructed in a left-right mode, and tenons and mortises are arranged on the left-right mode; 5, concrete pouring is conducted, the support is dismantled after solidification, and the step 2 and the step 3 are repeated in the next span; and 6, the side wall is constructed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of bridge construction, and in particular relates to an arch bridge construction method. Background Art

[0002] An arch bridge refers to a bridge that uses an arch as the main load-bearing structural component in a vertical plane. The vertical load is transferred to the arch platform through the curved arch. It was not originally used for garden landscaping, but to meet the purpose of flood discharge and navigation under the bridge in engineering. In the process of formation and development, the bridge body is curved, so it is often called a curved bridge in ancient times. There are single-hole and multi-hole arches in terms of the number of holes. If a multi-hole arch is loaded when a certain hole of the main arch is loaded, it can transfer the load from near to far to other holes of the main arch through the deformation of the pier or the action of the structure on the arch. Such an arch bridge is called a continuous arch bridge. The structure of a continuous arch bridge with different spans of each arch is called a non-equal span.

[0003] During construction, according to the design requirements, non-equal span continuous arch bridges need to be built with full-frame frames, and then poured as a whole at one time. However, in actual construction, if the full-frame frames are built as a whole, there is no room for material turnover, the material cost is high, the frame erection time is long, the amount of concrete poured at one time is too large, the pouring time is long, the pouring quality is difficult to guarantee, and the heat release is huge during the concrete solidification process. The later concrete maintenance is difficult and concrete cracking is prone to occur. In addition, if the whole is poured at one time, the span of the construction site is large, but there is no construction site on site to ensure sufficient access for concrete pump trucks and concrete mixer trucks. Therefore, from the perspective of cost and construction quality, segmented construction is required. However, for the construction of continuous arch bridges, segmented construction is prone to uneven force on both sides of the pier pile foundation, resulting in the displacement of the pier pile foundation. Summary of the invention

[0004] The present invention aims to provide a method for constructing a wide unequal-span continuous arch bridge, so as to solve the technical problem that the construction of the unequal-span continuous arch bridge is difficult.

[0005] In order to solve the above technical problems, the specific technical solutions of the present invention are as follows: A method for constructing a wide unequal span continuous arch bridge, characterized by comprising the following steps: Step 1: Construction of pier pile foundation and cap, and construction of arch seat on the cap; Step 2: Embed prestressed steel strands on the arch seats of the side spans and secondary side spans at both ends of the continuous arch bridge; Step 3: Temporary hardening of the site and setting up of supports; Step 4: The single arch is constructed in left and right sections, and tenons and mortises are set on the left and right sections; Step 5: Concrete pouring, remove the support after solidification, and repeat steps 2 and 3 for the next span; Step 6: Construct the side walls.

[0006] Furthermore, in step 1, a cap is constructed on the pile foundation, abutments are constructed at both ends of the continuous arch bridge, and friction plates are arranged behind the abutments.

[0007] Furthermore, in step 2, the prestressed steel strands embedded in the arch seat are applied with initial stress according to the calculated value during the concrete pouring process.

[0008] Furthermore, in step 3, the site is temporarily hardened, a support is set up, and pre-compression is performed: the pre-compression weight is not less than 120% of the deadweight of the span arch ring, and the strength and stability of the support must be ensured to prevent the support from sinking and eliminate the inelastic deformation of the support.

[0009] Furthermore, in step 4, the arch ring is cast in separate holes using a bracket, and adjacent holes are cast symmetrically from the arch foot to the arch top in a symmetrical and balanced manner. During the construction process, the bracket is not allowed to be removed to prevent the bridge pier from being subjected to excessive unidirectional horizontal force.

[0010] Furthermore, in step 5, when the concrete strength reaches the design requirement, the prestressed steel strands are tensioned to the final stress; when the arch ring reaches 100% of the design strength in the concrete, the brackets should be removed strictly in the longitudinal direction and in a symmetrical order for each hole.

[0011] Furthermore, in step 1, after the abutment construction is completed, a portion of the soil should be backfilled first, and the backfilled soil should be compacted layer by layer, and the compaction degree should not be less than 96%, and the internal friction angle should not be less than 35 degrees. The arch ring construction should be carried out simultaneously and symmetrically.

[0012] Furthermore, in step 1, the friction plate is embedded in the support platform.

[0013] The technical solution of the present invention has the following advantages: Temporary prestress is applied to constrain the horizontal displacement of the abutment pile foundation, and the friction plate is used to prevent the horizontal displacement of the abutment pile foundation, providing conditions for segmented construction. This solves the technical problems of the difficulty in constructing non-uniform span continuous arch bridges, the difficulty in turnover of full-frame materials, and the long construction period and high cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the pile foundation structure of the present invention; Figure 2 It is a schematic diagram of the distribution of the side span, secondary side span, middle span and prestressed steel strands of the present invention; Figure 3 It is a schematic diagram of the construction structure of the side span and the secondary side span of the present invention; Figure 4 It is a schematic diagram of the mid-span construction structure of the present invention; Figure 5 It is a structural schematic diagram of the side wall construction of the present invention; Figure 6 This is a schematic diagram of the structure of Embodiment 3 of the present invention; Figure 7 This is a schematic diagram of the structure of Example 2 of the present invention. DETAILED DESCRIPTION

[0015] In order to better understand the purpose, structure and function of the present invention, the technical solution of the present invention is further described in detail below in conjunction with the accompanying drawings.

[0016] Example 1 A method for constructing a wide unequal span continuous arch bridge of the present invention comprises the following steps: Step 1: Construction of pier pile foundation 1 and cap 2, and construction of arch seat 3 on cap 2; Step 2: pre-embed prestressed steel strands 4 on the arch seats 3 of the side span 8 and the secondary side span 9 at both ends of the continuous arch bridge; Step 3: Temporary hardening of the site and erection of support 5; Step 4: The single arch is constructed in left and right sections, and tenons 12 and tenon grooves 13 are provided on the left and right sections; Step 5: concrete pouring, remove support 5 after solidification, and repeat steps 2 and 3 for the next span; Step 6: Construct the side wall 14, and then construct the bridge deck and auxiliary facilities according to the design.

[0017] Specifically, Figure 1 As shown, a cap 2 is constructed on the pile foundation 1, abutments 10 are constructed at both ends of the continuous arch bridge, and friction plates 7 are constructed behind the abutments 10. The friction plates 7 have friction bosses extending into the ground, and the friction bosses are inclined toward the offshore direction, providing better stress conditions and pull-out resistance. After the construction of the abutment 10 is completed, a portion of the soil should be backfilled first, and the backfilled soil should be compacted layer by layer, and the compaction degree should not be less than 96%, and the internal friction angle should not be less than 35 degrees.

[0018] like Figure 2 and Figure 3 As shown, after the construction of the friction plate 7, abutment 10, pedestal 2, and arch seat 3 is completed, the prestressed steel bundle 4 embedded in the arch seat 3 is hardened on the ground line 6, and the bracket 5 is set up, and then the concrete is poured. The initial stress is applied during the concrete pouring process according to the calculated value. The prestressed steel bundle 4 covers the side span 8 and the secondary side span 9 at both ends of the arch bridge, and the prestressed tensioning and the anti-slip force of the friction plate 7 are the same. The tensioning force is the horizontal thrust after the frame is dropped. This state constrains the horizontal displacement of the pedestal 2 and the pile foundation 1 to the middle span 11, and the other end is constrained by the friction plate 7.

[0019] In the specific step 5, the specific demolition work is to remove the three rows of brackets 5 at the arch foot position after the strength of the side span 8 and the secondary side span 9 reaches 100%, apply prestress (the brackets 5 are removed from both ends to the middle), and when the concrete strength reaches the design requirements, tension the prestressed steel strands 4 to the final stress; when the concrete of the arch ring reaches 100% of the design strength, the brackets 5 should be removed strictly in the longitudinal and symmetrical order of each hole.

[0020] Specifically, two side spans 8 and a secondary side span 9 are constructed simultaneously, and the prestressed steel strands 4 are embedded in the arch seat 3, and the initial stress is applied during the concrete pouring process according to the calculated value. When the concrete strength reaches the design requirements, it is tensioned to the final stress and the bracket 5 is removed. The purpose of applying temporary prestress is to restrict the horizontal displacement of the pile foundations of the ①, ②, ⑤, ⑥③ abutments, and the function of the friction plate 7 is to prevent the horizontal displacement of the pile foundations of the abutment 10.

[0021] Specifically, during the construction process, in step 3, the site is temporarily hardened, and after the support 5 is erected, the support 5 needs to be pre-pressed. The pre-pressing weight is not less than 120% of the deadweight of the span arch ring, and the strength and stability of the support 5 must be ensured to prevent the support 5 from sinking and eliminate the inelastic deformation of the support 5.

[0022] Specifically during the construction process, Figure 3 and Figure 4 As shown, in step 4, the arch ring is cast in holes using bracket 5. The arch rings at both ends of the bridge should be constructed symmetrically at the same time, and then the brackets are rotated to the arch ring in the middle span. The adjacent holes should be symmetrically constructed and cast symmetrically from the arch foot to the arch top. During the construction process, bracket 5 is not allowed to be removed to prevent the bridge pier from being subjected to excessive unidirectional horizontal force.

[0023] Example 2 In this embodiment, if Figure 7 As shown, when the left and right sides of the arch ring are constructed, tenons 12 and tenons 13 are respectively arranged at the center of the arch ring to effectively transfer the load and enhance the integrity and stability of the structure. At the same time, the turnover space of the bracket 5 is guaranteed, and the quality problems caused by excessive single pouring of concrete are avoided.

[0024] Example 3 like Figure 6 As shown, in this embodiment, the friction plate 7 is embedded in the support platform 2 to prevent the friction plate 7 from lateral displacement.

[0025] It is to be understood that the present invention is described by some embodiments, and it is known to those skilled in the art that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. In addition, under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. Therefore, the present invention is not limited by the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of this application are within the scope of protection of the present invention.

Claims

1. A method for constructing a wide unequal span continuous arch bridge, characterized in that: The steps include: Step 1: constructing the pier pile foundation (1) and the cap (2), and constructing the arch seat (3) on the cap (2); Step 2: pre-embed prestressed steel strands (4) on the arch seats (3) of the side spans (8) and the secondary side spans (9) at both ends of the continuous arch bridge; Step 3: Temporary hardening of the site and erection of supports (5); Step 4: The single arch is constructed in left and right sections, and tenons (12) and tenon grooves (13) are provided on the left and right sections; Step 5: Concrete pouring, after solidification, remove the support (5), and repeat steps 2 and 3 for the next span; Step 6: Construction of the side walls (14).

2. The method for constructing a wide unequal span continuous arch bridge according to claim 1, characterized in that: In the step 1, a cap (2) is constructed on the pile foundation (1), abutments (10) are constructed at both ends of the continuous arch bridge, and friction plates (7) are arranged behind the abutments (10).

3. The method for constructing a wide unequal span continuous arch bridge according to claim 2, characterized in that: In the step 2, the prestressed steel strands (4) embedded in the arch seat (3) are subjected to initial stress according to the calculated value during the concrete pouring process.

4. The method for constructing a wide unequal span continuous arch bridge according to claim 3, characterized in that: In step 3, the site is temporarily hardened, the support (5) is erected and pre-pressed, and the pre-pressing weight is not less than 120% of the deadweight of the span arch ring, and the strength and stability of the support (5) must be ensured to prevent the support (5) from sinking and eliminate the inelastic deformation of the support (5).

5. The method for constructing a wide unequal span continuous arch bridge according to claim 4, characterized in that: In step 4, the arch ring is cast in holes using a bracket (5), and adjacent holes are cast symmetrically from the arch foot to the arch top in a symmetrical and balanced manner. During the construction process, the bracket (5) is not allowed to be removed to prevent the bridge pier from being subjected to excessive unidirectional horizontal force.

6. The method for constructing a wide unequal span continuous arch bridge according to claim 5, characterized in that: In step 5, when the concrete strength reaches the design requirement, the prestressed steel strand (4) is tensioned to the final stress; when the arch ring reaches 100% of the design strength in the concrete, the bracket (5) should be removed strictly in the longitudinal direction and in a symmetrical order for each hole, and the arch ring construction should be carried out symmetrically at the same time.

7. The method for constructing a wide unequal span continuous arch bridge according to claim 6, characterized in that: In the step 1, after the construction of the abutment (10) is completed, a portion of the soil should be backfilled first. The backfilled soil should be compacted layer by layer, and the compaction degree should not be less than 96%, and the internal friction angle should not be less than 35 degrees.

8. The method for constructing a wide unequal span continuous arch bridge according to claim 7, characterized in that: In step 1, the friction plate (7) is embedded in the support platform (2).