Bridge web overhauling device

By designing the bridge belly maintenance device, the problem of long and high cost of bridge belly maintenance is solved, rapid and economical bridge maintenance is achieved, and the bridge passage efficiency and maintenance effect are improved.

CN119021093APending Publication Date: 2024-11-26梁龙
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411425886.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-12
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In the prior art, the maintenance of bridge belly of bridges takes a long time and is costly, which affects the long-term maintenance and traffic efficiency of bridges.

Method used

Design a bridge belly maintenance device, including a connecting part, a descending part and a platform part, the connecting part is fixed to the bridge guardrail, the descending part is arranged vertically on the side of the bridge, the platform part is located below the side of the bridge belly, and the workers follow the downing part through safety measures. Down to the platform department for maintenance. The device can be connected to the guardrail on any side of the bridge, which facilitates inspection and maintenance on both sides of the bridge belly.

Benefits of technology

It reduces the cost and installation time of bridge maintenance, improves maintenance efficiency, and reduces maintenance costs, and is suitable for bridge structures with frequent inspections.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021093A_ABST
    Figure CN119021093A_ABST
Patent Text Reader

Abstract

The invention discloses a bridge web maintenance device, relates to the technical field of bridge maintenance, and can solve the problems of long time consumption and high cost of bridge web maintenance of a bridge in the prior art. The bridge web maintenance device comprises a connecting part, a descending part connected to the connecting part and a platform part connected to the end, away from the connecting part, of the descending part and used for bearing workers or maintenance equipment, and the connecting part is used for being connected to a guardrail of a bridge so that the workers or the maintenance equipment can descend to the platform part along the descending part. And the platform part is positioned at the lateral lower part of the bridge web.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of bridge maintenance technology, and in particular to a bridge belly inspection device. Background Art

[0002] Concrete bridges are one of the key infrastructures in urban and highway traffic, with good load-bearing capacity, durability and structural stability. Usually, concrete bridges are composed of bridge decks, piers, abutments, beam structures and concrete guardrails on both sides. The bridge deck bears the traffic load of vehicles and pedestrians, the piers and abutments support the overall weight of the bridge, and the concrete guardrails on both sides play a role in safety protection, preventing vehicles and pedestrians from accidentally rushing out of the bridge.

[0003] The bridge belly is located at the bottom of the bridge, which is exposed above the water all year round and is easily affected by the humid environment. Especially under the influence of rain, moisture, temperature changes and other factors for a long time, cracks and steel corrosion may occur in the bridge belly, which will lead to structural damage or aging and weaken the overall bearing capacity of the bridge. Therefore, the bridge belly needs to be inspected and maintained regularly.

[0004] In the prior art, bridge belly inspection is usually achieved by using a lift or building a scaffolding, and workers use these devices to reach the bridge belly for inspection and maintenance. However, each inspection requires the use of large equipment and professionals to operate the lift, or takes a long time to build a safe and stable scaffolding. Therefore, bridge belly inspection is time-consuming and costly, which is not conducive to the long-term maintenance of bridges. Especially for some bridge structures that require regular and frequent inspections, the high cost of inspection will not only increase the economic burden of maintenance, but may also affect the normal use and traffic efficiency of the bridge. Summary of the invention

[0005] To this end, the present application provides a bridge belly inspection device to solve the problem of long time and high cost in bridge belly inspection of bridges in the prior art.

[0006] In order to achieve the above objectives, this application provides the following technical solutions:

[0007] A bridge belly maintenance device comprises a connecting portion, a descending portion connected to the connecting portion, and a platform portion connected to one end of the descending portion away from the connecting portion and used to carry workers or maintenance equipment, wherein the connecting portion is used to be connected to a guardrail of a bridge so that workers or maintenance equipment can descend along the descending portion to the platform portion, and the platform portion is located at the lower side of the bridge belly.

[0008] Optionally, the connecting portion includes two first support rods and a first cross rod connected between the two first support rods, and the first support rod is bent to form a hook that cooperates with the descending portion to be hooked on a guardrail of a bridge.

[0009] Optionally, the descending part includes two second support rods integrally formed at one end of the first support rod and a plurality of second cross bars connected between the second support rods and used for workers to climb, the two second support rods and the two first support rods corresponding one to one, the two second support rods are respectively connected to the platform part, and the two second support rods are used to support the side of the bridge.

[0010] Optionally, a plurality of guardrails cooperating with the second crossbars are connected between two of the second support rods, and the guardrails and the second crossbars form a guardrail area for workers to pass through, and the plurality of guardrails and the plurality of second crossbars correspond one to one.

[0011] Optionally, the first support rod and the second support rod are integrally formed as a main support rod, the main support rod includes a first sub-support rod and a second sub-support rod, a plurality of first connecting rods are connected between the first sub-support rod and the second sub-support rod, and the first cross rod and a plurality of second cross rods are all connected to the first sub-support rod.

[0012] Optionally, the first cross bar is connected to a plurality of first pulleys for supporting the top surface of the guardrail of the bridge, and the second cross bar is connected to a plurality of second pulleys for supporting the side of the bridge.

[0013] Optionally, the platform portion includes a first support frame connected to the connecting portion and a second support frame connected to the first support frame through a plurality of second connecting rods, the second support frame is connected to a plurality of third connecting rods, the plurality of third connecting rods are connected to support plates for supporting workers or maintenance equipment, and the first support frame, the plurality of second connecting rods, the second support frame and the support plate form a working chamber with an open top surface.

[0014] Optionally, a protective net surrounding the first supporting frame is connected between the plurality of second connecting rods.

[0015] Optionally, a reinforcing diagonal rod is connected between the first supporting frame and the connecting portion.

[0016] Optionally, the connecting portion is connected to the first supporting frame to divide the opening of the working chamber into an entrance opening and a working opening along an extension surface of the connecting portion, and an area of ​​the working opening is larger than an area of ​​the entrance opening.

[0017] Compared with the prior art, this application has at least the following beneficial effects:

[0018] When inspecting the belly of the bridge, the connecting part of the bridge inspection device is fixed on the guardrail of the bridge, and the descending part is arranged vertically on the side of the bridge. Workers can descend along the descending part to the platform part through safety measures (wearing safety belts). Since the platform part is located on the side and lower part of the bridge, workers standing on the platform part can access the inspection position of the bridge belly and carry out inspection work. The bridge belly inspection device can be connected to the guardrail on either side of the bridge, so as to facilitate workers to inspect and repair both sides of the bridge belly. Compared with the method in the prior art that requires the use of elevators or the construction of scaffolding, the inspection device has lower cost and shorter installation time, which greatly improves the efficiency of bridge inspection and reduces maintenance costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more intuitively illustrate the prior art and the present application, several exemplary drawings are given below. It should be understood that the specific shapes and structures shown in the drawings should not generally be regarded as limiting conditions for implementing the present application; for example, those skilled in the art are capable of easily making conventional adjustments or further optimizations to the addition / reduction / attribution division, specific shapes, positional relationships, connection methods, dimensional ratios, etc. of certain units (components) based on the technical concepts and exemplary drawings disclosed in the present application.

[0020] Figure 1 A schematic diagram of the overall structure of a bridge belly inspection device provided in one embodiment of the present application;

[0021] Figure 2 for Figure 1 Another perspective of the picture;

[0022] Figure 3 for Figure 2 A magnified image of point A;

[0023] Figure 4 A schematic diagram of a use status of a bridge belly inspection device provided by one embodiment of the present application;

[0024] Figure 5 A schematic structural diagram of a platform portion of a bridge belly inspection device provided in one embodiment of the present application;

[0025] Figure 6 for Figure 5 Top view of the .

[0026] Description of reference numerals:

[0027] 1. Connecting part; 11. First supporting rod; 12. First cross bar; 13. First pulley; 2. Descending part; 21. Second supporting rod; 22. Second cross bar; 23. Guard bar; 231. Guard area; 24. Second pulley; 3. Platform part; 31. First supporting frame; 311. First section; 312. Second section; 32. Second supporting frame; 33. Second connecting rod; 34. Protective net; 35. Support plate; 36. Working cavity; 361. Entrance; 362. Working opening; 4. First branch supporting rod; 5. Second branch supporting rod; 6. First connecting rod; 7. Guardrail; 8. Bridge belly; 9. Strengthening diagonal rod. DETAILED DESCRIPTION

[0028] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0029] In the description of this application: unless otherwise specified, "plurality" means two or more. The terms "first", "second", "third", etc. in this application are intended to distinguish the objects referred to, and do not have special meanings in terms of technical connotations (for example, they should not be understood as emphasizing the importance or order, etc.). Expressions such as "including", "comprising", "having", etc. also mean "not limited to" (certain units, components, materials, steps, etc.); Figure 4 The arrows in the figure indicate the workers' movement paths.

[0030] refer to Figure 1-6 The present application discloses a bridge belly maintenance device, comprising a connecting portion 1, a descending portion 2 connected to the connecting portion 1, and a platform portion 3 connected to one end of the descending portion 2 away from the connecting portion 1 and used to carry workers or maintenance equipment. The connecting portion 1 is used to be connected to a guardrail 7 of a bridge so that workers or maintenance equipment can descend along the descending portion 2 to the platform portion 3, and the platform portion 3 is located at the lower side of the bridge belly 8.

[0031] When inspecting the bridge belly 8, the connecting part 1 of the bridge belly 8 inspection device is fixed on the guardrail 7 of the bridge, and the descending part 2 is arranged vertically on the side of the bridge. Workers can descend to the platform part 3 along the descending part 2 through safety measures (wearing a safety belt). Since the platform part 3 is located below the side of the bridge belly 8, workers standing on the platform part 3 can access the inspection position of the bridge belly 8 to carry out inspection work. The bridge belly 8 inspection device can be connected to the guardrail 7 on either side of the bridge, so as to facilitate workers to inspect and repair both sides of the bridge belly 8. Compared with the method in the prior art that requires the use of a lift or the construction of a scaffold, the inspection device has lower cost and shorter installation time, greatly improving the efficiency of bridge inspection and reducing maintenance costs.

[0032] It should be noted that the guardrail 7 of the bridge can not only be a common concrete guardrail, but also a guardrail made of other materials (later installed on the concrete guardrail), such as a metal guardrail, a composite material guardrail, etc.

[0033] In some embodiments, the bridge belly 8 maintenance device can also be used to place maintenance equipment, such as unmanned automatic maintenance robots. These devices can perform automated maintenance operations on the platform part 3, or perform precise operations through remote control.

[0034] The connecting part 1 includes two first support rods 11 and a first cross rod 12 connected between the two first support rods 11. The first support rods 11 are bent to form a hook that cooperates with the descending part 2 to be hooked on the guardrail 7 of the bridge. When installing the bridge belly 8 inspection device, it is only necessary to hook the hook formed by bending the two first support rods 11 on the guardrail 7 of the bridge to quickly complete the installation.

[0035] The descending portion 2 includes two second support rods 21 integrally formed at one end of the first support rod 11 and a plurality of second cross bars 22 connected between the second support rods 21 and used for workers to climb. The two second support rods 21 correspond one-to-one to the two first support rods 11, and the two second support rods 21 are respectively connected to the platform portion 3, and the two second support rods 21 are used to support the side of the bridge.

[0036] When the connection part 1 is hooked on the guardrail 7 of the bridge, the two second support rods 21 naturally stick to and support the side of the bridge, providing support for the entire bridge belly 8 inspection device. During the inspection process, the worker can gradually climb down along the multiple second cross bars 22 connected between the second support rods 21 until reaching the platform part 3 for operation. The hook-type design of the connection part 1 combined with the close contact of the second support rods 21 makes the device stable and reliable during use, effectively preventing shaking or deviation, and ensuring the safety of workers when climbing and inspecting.

[0037] A plurality of guard bars 23 cooperating with the second cross bars 22 are connected between the two second support bars 21 , and the guard bars 23 and the second cross bars 22 form a guard area 231 for workers to pass through, and the plurality of guard bars 23 correspond to the plurality of second cross bars 22 one by one.

[0038] When the worker is climbing, a plurality of guardrails 23 surround the worker to form a closed guardrail area 231 to protect the worker. The guardrails 23 cooperate with the second crossbar 22 to ensure that the worker is always in a safe space when climbing, preventing the risk of falling due to slipping or other unexpected situations.

[0039] In some embodiments, the guard bar 23 is bent to form a “C” shape, and the guard bar 23 is flush with the second cross bar 22 .

[0040] The first support rod 11 and the second support rod 21 are integrally formed as a main support rod, and the main support rod includes a first sub-support rod 4 and a second sub-support rod 5. A plurality of first connecting rods 6 are connected between the first sub-support rod 4 and the second sub-support rod 5. The first cross rod 12 and the plurality of second cross rods 22 are all connected to the first sub-support rod 4.

[0041] The first branch strut 4 and the second branch strut 5 are connected by a plurality of first connecting rods 6 to form an integral main strut structure, which improves the supporting strength of the main strut, so that the maintenance device on the bridge belly 8 can more stably carry workers and maintenance equipment. In addition, the gap between the first branch strut 4 and the second branch strut 5 provides space for workers to grasp their hands, so that workers can move the device in the length direction of the bridge guardrail 7, which is convenient for more flexible adjustment of the maintenance position.

[0042] The first cross bar 12 is connected to a plurality of first pulleys 13 for supporting the top surface of the guardrail 7 of the bridge, and the second cross bar 22 is connected to a plurality of second pulleys 24 for supporting the side of the bridge.

[0043] A plurality of first pulleys 13 are supported on the top surface of the guardrail 7 of the bridge, and a plurality of second pulleys 24 are supported on the side of the bridge. Through the design of the pulleys, the entire bridge belly 8 maintenance device can be stably supported on the bridge. When the worker standing on the platform completes the maintenance of a position of the bridge belly 8, the worker standing on the bridge deck can push the maintenance device to move it along the length direction of the guardrail 7 of the bridge. Due to the presence of the pulleys, the device can reduce the friction with the bridge surface during the movement, making the movement process easier and more labor-saving, and improving the efficiency of the maintenance operation.

[0044] In some embodiments, in order to prevent the second pulley 24 on the second cross bar 22 from interfering with the guardrail 7 of the bridge when the maintenance device on the bridge belly 8 is installed, only some of the second cross bars 22 among the multiple second cross bars 22 are connected to the second pulley 24.

[0045] The platform portion 3 includes a first support frame 31 connected to the connecting portion 1 and a second support frame 32 connected to the first support frame 31 through a plurality of second connecting rods 33. The second support frame 32 is connected to a plurality of third connecting rods, and the plurality of third connecting rods are connected to a support plate 35 for supporting workers or maintenance equipment. The first support frame 31, the plurality of second connecting rods 33, the second support frame 32 and the support plate 35 form a working chamber 36 with an open top surface.

[0046] When the worker climbs and descends along the connection part 1, the worker enters the working chamber 36 through the top opening of the working chamber 36 and stands on the support plate 35 to perform maintenance work. Since the working chamber 36 is surrounded by the first support frame 31, multiple second connecting rods 33, the second support frame 32 and the support plate 35, the worker generally extends the upper body out of the working chamber 36 to perform maintenance operations on the bridge belly 8. The first support frame 31 and multiple second connecting rods 33 provide effective enclosure protection when the worker is working, preventing the worker from accidentally falling when working at high altitude.

[0047] In some embodiments, a plurality of third connecting rods may be staggered and connected to form a grid.

[0048] A protection net 34 surrounding the first support frame 31 is connected between the plurality of second connecting rods 33 .

[0049] The protection net 34 surrounds the plurality of second connecting rods 33 of the first support frame 31 , further improving the safety protection effect of the working area. The protection net 34 can effectively prevent small tools, maintenance parts, etc. from falling from the gap between two adjacent second connecting rods 33 .

[0050] A reinforcing diagonal rod 9 is connected between the first supporting frame 31 and the connecting portion 1. The reinforcing diagonal rod 9 improves the connection strength between the first supporting frame 31 and the connecting portion 1.

[0051] The connecting portion 1 is connected to the first supporting frame 31 to divide the opening of the working chamber 36 into an entrance opening 361 and a working opening 362 along the extending surface of the connecting portion 1 . The area of ​​the working opening 362 is larger than that of the entrance opening 361 .

[0052] The connection part 1 divides the opening of the working chamber 36 into an entry opening 361 and a working opening 362. The entry opening 361 is located outside the bridge belly 8, and the working opening 362 is located below the bridge belly 8. The entry opening 361 corresponds to the guard area 231. When a worker descends, he enters the working chamber 36 from the entry opening 361. When working, the worker's upper body extends through the working opening 362. The larger area of ​​the working opening 362 allows it to be closer to the belly of the bridge, making it easier for the worker to perform maintenance operations.

[0053] In some embodiments, the first support frame 31 and the second support frame 32 are quadrilaterals, and the two second support rods 21 are respectively connected to two opposite sides of the first support frame 31, wherein the connection point between the second support rod 21 and the first support frame 31 divides the side of the first support frame 31 into a first section 311 and a second section 312, the first section 311 corresponds to the entrance 361, and the second section 312 corresponds to the working opening 362.

[0054] It should be noted that the working opening 362 does not need to extend to the center of the bridge belly 8. The worker's upper body extends out of the working opening 362 and he can carry some tools to work near the center of the bridge belly 8. For the maintenance of the bridge belly 8, the positions near the two sides of the bridge belly 8 are easily eroded by the environment or damaged by external forces, that is, the positions near the two sides of the bridge belly 8 are the focus of maintenance.

[0055] In the present application, the first cross bar 12 and the second cross bar 22 are welded to the first branch strut 4, the two ends of the first connecting rod 6 are respectively welded to the first branch strut 4 and the second branch strut 5, the guardrail 23 is welded to the second branch strut 5, the first branch strut 4 and the second branch strut 5 are respectively welded to the first support frame 31, the two ends of multiple second connecting rods 33 are respectively welded to the first support frame 31 and the second support frame 32, and multiple third connecting rods are welded to the second support frame 32; the above structures can all be made of steel, other metal materials or alloy materials.

[0056] The technical features of the above embodiments may be arbitrarily combined (as long as there is no contradiction in the combination of these technical features). To make the description concise, not all possible combinations of the technical features in the above embodiments are described; these embodiments that are not explicitly written should also be considered to be within the scope of this specification.

[0057] The above is a relatively specific and detailed description of the present application through general description and specific embodiments. It should be understood that, based on the technical concept of the present application, several conventional adjustments or further innovations can be made to these specific embodiments; however, as long as they do not deviate from the technical concept of the present application, the technical solutions obtained by these conventional adjustments or further innovations also fall within the scope of protection of the claims of the present application.

Claims

1. A bridge belly inspection device, characterized in that: It includes a connecting part, a descending part connected to the connecting part, and a platform part connected to one end of the descending part away from the connecting part and used to carry workers or maintenance equipment. The connecting part is used to be connected to the guardrail of the bridge so that workers or maintenance equipment can descend along the descending part to the platform part, and the platform part is located on the lower side of the bridge belly.

2. The bridge belly inspection device according to claim 1, characterized in that: The connecting portion includes two first support rods and a first cross rod connected between the two first support rods. The first support rod is bent to form a hook that cooperates with the descending portion to be hooked on the guardrail of the bridge.

3. The bridge belly inspection device according to claim 2, characterized in that: The descending part includes two second support rods integrally formed at one end of the first support rod and a plurality of second cross bars connected between the second support rods and used for workers to climb, the two second support rods and the two first support rods corresponding one to one, the two second support rods are respectively connected to the platform part, and the two second support rods are used to support the side of the bridge.

4. The bridge belly inspection device according to claim 3, characterized in that: A plurality of guardrails cooperating with the second crossbars are connected between the two second support bars. The guardrails and the second crossbars form a guarding area for workers to pass through. The plurality of guardrails and the plurality of second crossbars correspond one to one.

5. The bridge belly inspection device according to claim 3, characterized in that: The first support rod and the second support rod are integrally formed as a main support rod, the main support rod includes a first sub-support rod and a second sub-support rod, a plurality of first connecting rods are connected between the first sub-support rod and the second sub-support rod, and the first cross rod and a plurality of second cross rods are all connected to the first sub-support rod.

6. The bridge belly inspection device according to claim 3, characterized in that: The first cross bar is connected to a plurality of first pulleys for supporting the top surface of the guardrail of the bridge, and the second cross bar is connected to a plurality of second pulleys for supporting the side of the bridge.

7. The bridge belly inspection device according to claim 1, characterized in that: The platform portion includes a first support frame connected to the connecting portion and a second support frame connected to the first support frame through a plurality of second connecting rods, the second support frame is connected to a plurality of third connecting rods, and the plurality of third connecting rods are connected to support plates for supporting workers or maintenance equipment, and the first support frame, the plurality of second connecting rods, the second support frame and the support plates form a working chamber with an open top surface.

8. The bridge belly inspection device according to claim 7, characterized in that: A protective net surrounding the first supporting frame is connected between the plurality of second connecting rods.

9. The bridge belly inspection device according to claim 7, characterized in that: A reinforcing diagonal rod is connected between the first supporting frame and the connecting portion.

10. The bridge belly inspection device according to claim 7, characterized in that: The connecting portion is connected to the first supporting frame to divide the opening of the working chamber into an entrance opening and a working opening along an extending surface of the connecting portion, and an area of ​​the working opening is larger than an area of ​​the entrance opening.