Method, equipment and product for calculating uncertainty of interpolation wind measurement data of wind power plant
By acquiring and detecting wind measurement data in the wind farm, using Pearson correlation coefficient and data integrity rate to determine the uncertainty, the problem of complex interpolation uncertainty calculation of wind farm wind measurement data in the prior art is solved, and simplified calculation and Improve computing efficiency.
Patent Information
- Application Number
- CN202411144979.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-11-26
AI Technical Summary
The calculation method for uncertainty in wind measurement data interpolation in the prior art is complex and has a large amount of calculation, making it difficult to actually use in engineering.
By obtaining the initial wind measurement data and preset wind measurement data, data detection and interpolation are performed, the upper and lower limits of uncertainty are determined using the Pearson correlation coefficient and data integrity rate, and the non-interpolated wind measurement data is calculated based on the uncertainty table. Determinism, simplifying the calculation process.
The scientific calculation of the uncertainty of wind measurement data of wind farm interpolated wind farms is realized, which reduces the computational complexity and calculation amount, and improves the consideration of the impact of data integrity and correlation on uncertainty.
Smart Images

Figure CN119021834A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of wind power generation, and in particular to a method, device and product for calculating uncertainty of interpolated wind measurement data in a wind farm. Background Art
[0002] Wind energy is one of the most abundant renewable energy sources. In the early development of wind farms, it is necessary to set up wind towers and collect wind measurement data. In the process of wind measurement, wind measurement data may be affected by various factors, resulting in unreasonable and missing data. Therefore, it is necessary to check the wind measurement data, eliminate the unreasonable and missing data, and then use the data from nearby wind towers or meteorological stations to interpolate to improve the completeness of wind measurement data.
[0003] In wind energy resource assessment, it is necessary to calculate the uncertainty caused by interpolation of wind farm wind measurement data in order to evaluate the wind energy resources of the wind farm. However, the current method of fitting and calculating uncertainty using the Gaussian distribution model is relatively complex and computationally intensive, making it inconvenient for actual use in engineering. Summary of the invention
[0004] In view of this, the present invention provides a method, device and product for calculating the uncertainty of interpolated wind measurement data in a wind farm, so as to solve the problem that the uncertainty calculation method is complicated and has a large amount of calculation.
[0005] In a first aspect, the present invention provides a method for calculating the uncertainty of interpolated wind measurement data of a wind farm, the method comprising: obtaining initial wind measurement data and preset wind measurement data, the initial wind measurement data being acquired based on a wind measurement tower of the wind farm, and the preset wind measurement data being acquired based on preset wind measurement equipment; performing data detection on the initial wind measurement data, eliminating defective data, obtaining first wind measurement data, and calculating an initial completeness rate of the first wind measurement data based on the first wind measurement data and the initial wind measurement data; interpolating the first wind measurement data using the preset wind measurement data to obtain interpolated wind measurement data; calculating a Pearson correlation coefficient based on the preset wind measurement data and the first wind measurement data, and determining an upper limit and a lower limit of uncertainty based on the Pearson correlation coefficient and the initial completeness rate; and calculating the uncertainty of the interpolated wind measurement data based on the initial completeness rate, the upper limit of uncertainty, and the lower limit of uncertainty.
[0006] In this implementation, the initial wind measurement data of the wind farm wind tower is interpolated by using the preset wind measurement data of the preset wind measurement equipment, and the uncertainty is determined based on the correlation between the interpolated first wind measurement data and the preset wind measurement data and the data integrity rate. The method of the present application is based on simple calculations and does not use complex calculation models, which can solve the problems of complex calculation methods and large calculation amounts. At the same time, it can consider the influence of data integrity and correlation on uncertainty, and realize scientific calculation of uncertainty.
[0007] In an optional embodiment, obtaining initial wind measurement data includes: obtaining wind farm wind speed data and wind farm wind direction data collected by a wind farm wind measurement tower; calculating the average wind speed and average wind direction within a preset time period based on the wind farm wind speed data and wind farm wind direction data to obtain initial wind measurement data.
[0008] In an optional embodiment, the preset wind measurement equipment includes a target wind measurement tower and a meteorological station, and obtaining the preset wind measurement data includes: obtaining target wind speed data and target wind direction data collected by the target wind measurement tower; obtaining meteorological station wind speed data and meteorological station wind direction data collected by the meteorological station; calculating the average wind speed and average wind direction within a preset time period based on the target wind speed data and target wind direction data to obtain target wind measurement data; calculating the average wind speed and average wind direction based on the meteorological station wind speed data and meteorological station wind direction data to obtain the meteorological station wind measurement data.
[0009] In an optional embodiment, using preset wind measurement data to interpolate the first wind measurement data to obtain interpolated wind measurement data includes: using target wind measurement data to interpolate the first wind measurement data for a first time to obtain target interpolated wind measurement data; using meteorological station wind measurement data to interpolate the target interpolated wind measurement data for a second time to obtain interpolated wind measurement data.
[0010] In this implementation, the present application uses the data of the target wind tower and the meteorological station to interpolate the data of the wind farm wind tower in sequence, thereby improving the interpolation effect.
[0011] In one implementation, calculating the Pearson correlation coefficient based on preset wind measurement data and first wind measurement data includes: calculating a first completeness rate based on initial wind measurement data and target interpolated wind measurement data; calculating a second completeness rate based on the initial wind measurement data and interpolated wind measurement data; calculating a first Pearson correlation coefficient based on the first wind measurement data and target wind measurement data; calculating a second Pearson correlation coefficient based on the target interpolated wind measurement data and meteorological station wind measurement data; determining a first weight and a second weight based on the initial completeness rate, the first completeness rate and the second completeness rate; and weightedly adding the first Pearson correlation coefficient and the second Pearson correlation coefficient based on the first weight and the second weight to obtain the Pearson correlation coefficient.
[0012] In an optional implementation, determining the first weight based on the initial completeness rate, the first completeness rate, and the second completeness rate includes: Determining the second weight based on the initial completeness rate, the first completeness rate, and the second completeness rate includes: Among them, W1 is the first weight, W2 is the second weight, R0 is the initial complete rate, R1 is the first complete rate, and R1 is the second complete rate; based on the first weight and the second weight, the first Pearson correlation coefficient and the second Pearson correlation coefficient are weighted added to obtain the Pearson correlation coefficient: P=W1P1+W2P2; among them, P1 is the first Pearson correlation coefficient, P2 is the second Pearson correlation coefficient, and P is the Pearson correlation coefficient.
[0013] In this implementation, the correlation between the data after two interpolations and the corresponding reference data and the completeness rate after two interpolations are considered respectively, and the comprehensive correlation is calculated based on this, which can fully consider the impact of data completeness rate and correlation on uncertainty calculation.
[0014] In an optional embodiment, determining the upper limit and lower limit of uncertainty based on the Pearson correlation coefficient and the initial completeness rate includes: obtaining an uncertainty table, the uncertainty table being a relationship table of the Pearson correlation coefficient, completeness rate and uncertainty; obtaining the upper limit and lower limit of the completeness rate of the initial completeness rate in the uncertainty table; obtaining the lower limit of uncertainty corresponding to the upper limit of the completeness rate and the Pearson correlation coefficient, and the upper limit of uncertainty corresponding to the lower limit of the completeness rate and the Pearson correlation coefficient in the uncertainty table.
[0015] In an optional implementation, calculating the uncertainty of the interpolated wind measurement data based on the initial integrity rate, the upper uncertainty limit, and the lower uncertainty limit includes: Among them, U0 is the uncertainty of interpolated wind measurement data, R a is the upper limit of the completeness rate, R b is the lower limit of the completeness rate, U a is the lower limit of uncertainty, U b is the upper limit of uncertainty.
[0016] In this implementation, the upper and lower limits of the completeness rate and the upper and lower limits of the uncertainty are determined by looking up the uncertainty table. Based on this, the calculation method proposed in this application is used to calculate the uncertainty of the interpolated wind measurement data. The table lookup is convenient, the calculation method is simple, and the amount of uncertainty calculation can be reduced. The influence of data completeness rate and correlation on uncertainty calculation is fully considered, so as to realize scientific calculation of the uncertainty caused by interpolating wind measurement data.
[0017] In an optional implementation, calculating the initial completeness rate based on the first wind measurement data and the initial wind measurement data includes: Wherein, R0 is the initial completeness rate, N1 is the number of the first wind measurement data, and N0 is the number of the initial wind measurement data.
[0018] In a second aspect, the present invention provides a computer device, comprising: a memory and a processor, the memory and the processor being communicatively connected to each other, the memory storing computer instructions, and the processor executing the uncertainty calculation method for interpolated wind measurement data of a wind farm according to the first aspect or any corresponding embodiment thereof by executing the computer instructions.
[0019] In a third aspect, the present invention provides a computer-readable storage medium having computer instructions stored thereon, the computer instructions being used to enable a computer to execute the uncertainty calculation method for interpolated wind measurement data of a wind farm according to the first aspect or any corresponding embodiment thereof.
[0020] In a fourth aspect, the present invention provides a computer program product, comprising computer instructions for causing a computer to execute the uncertainty calculation method for interpolated wind measurement data of a wind farm according to the first aspect or any corresponding embodiment thereof. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0022] Figure 1 is a flow chart of a method for calculating uncertainty of interpolated wind measurement data of a wind farm according to an embodiment of the present invention;
[0023] Figure 2 is a flow chart of another method for calculating uncertainty of interpolated wind measurement data of a wind farm according to an embodiment of the present invention;
[0024] Figure 3 is a flowchart of a specific method for calculating uncertainty of interpolated wind measurement data of a wind farm according to an embodiment of the present invention;
[0025] Figure 4 is a structural block diagram of an uncertainty calculation device for interpolating wind measurement data in a wind farm according to an embodiment of the present invention;
[0026] Figure 5 It is a schematic diagram of the hardware structure of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0028] According to an embodiment of the present invention, an embodiment of a method for calculating uncertainty of interpolated wind measurement data in a wind farm is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0029] In actual situations, due to damage to wind tower instruments, data transmission failures, icing, tower collapse, etc., there will be a large amount of problematic data in the wind measurement data. Therefore, in order to objectively reflect the wind resource situation of the wind farm, the wind tower data needs to be cleaned and then completed. Specifically, the reference data is used through interpolation methods to correct the data missing during the wind measurement due to instrument damage, human factors, etc. In this embodiment, a method for calculating the uncertainty of interpolated wind measurement data in a wind farm is provided. Figure 1 FIG. 1 is a flow chart of a method for calculating uncertainty of wind farm interpolation wind measurement data according to an embodiment of the present invention. It should be noted that if there are substantially the same results, this embodiment does not use Figure 1 The process sequence shown is limited. Figure 1 As shown, the process includes the following steps:
[0030] Step S101, obtaining initial wind measurement data and preset wind measurement data.
[0031] The initial wind measurement data is collected based on the wind tower of the wind farm, and the preset wind measurement data is collected based on the preset wind measurement equipment. The preset wind measurement equipment is other wind measurement equipment other than the wind tower of the wind farm.
[0032] Among them, wind measurement data includes wind speed data and wind direction data.
[0033] Specifically, a plurality of initial wind speed data are continuously acquired using a wind speed sensor of a wind farm wind tower, and a plurality of initial wind direction data are continuously acquired using a wind direction sensor of a wind farm wind tower. A plurality of preset wind speed data are continuously acquired using a wind speed sensor of a preset wind measuring device, and a plurality of preset wind direction data are continuously acquired using a wind direction sensor of a preset wind measuring device.
[0034] Step S102, performing data detection on the initial wind measurement data, eliminating defective data, obtaining first wind measurement data, and calculating the initial completeness rate of the first wind measurement data based on the first wind measurement data and the initial wind measurement data.
[0035] Among them, defective data refers to unreasonable data and data with missing measurements.
[0036] Specifically, multiple initial wind measurement data are tested for rationality and analyzed to determine unreasonable data; multiple initial wind measurement data are tested for data integrity and analyzed to determine missing data. Defective data in the initial wind measurement data are eliminated to obtain the first wind measurement data.
[0037] The number of initial wind measurement data and the number of first wind measurement data are determined, and an initial completeness rate of the first wind measurement data relative to the initial wind measurement data is calculated.
[0038] The initial completeness rate is:
[0039]
[0040] Wherein, R0 is the initial completeness rate, N1 is the number of the first wind measurement data, and N0 is the number of the initial wind measurement data.
[0041] Step S103, interpolating the first wind measurement data using the preset wind measurement data to obtain interpolated wind measurement data.
[0042] The first wind measurement data is interpolated using the preset wind measurement data of the preset wind measurement device as reference data to obtain interpolated wind measurement data, wherein the interpolated wind measurement data includes interpolated wind speed data and interpolated wind direction data.
[0043] The present application does not limit specific interpolation methods, such as linear regression method, orthogonal regression method, matrix time series method, quick sorting method, variance ratio method, wind speed ratio method, vertical stratification algorithm, and Weibull fitting algorithm.
[0044] Step S104: Calculate the Pearson correlation coefficient based on the preset wind measurement data and the first wind measurement data, and determine the upper uncertainty limit and the lower uncertainty limit based on the Pearson correlation coefficient and the initial integrity rate.
[0045] The correlation between the first wind measurement data after interpolation processing and the preset wind measurement data used for interpolation is calculated to obtain the Pearson correlation coefficient.
[0046] Further, an uncertainty table is obtained. The uncertainty table is a relationship table of the Pearson correlation coefficient, the completeness rate and the uncertainty. The completeness rate information in the uncertainty table is a discontinuous discrete value. By querying the uncertainty table, two completeness rate information adjacent to the initial completeness rate are determined, which are the completeness rate upper limit and the completeness rate lower limit, and the completeness rate upper limit and the completeness rate lower limit are used to determine two uncertainties with the Pearson correlation coefficient, respectively, to obtain the uncertainty upper limit and the uncertainty lower limit.
[0047] Step S105, calculating the uncertainty of the interpolated wind measurement data based on the initial completeness rate, the upper uncertainty limit and the lower uncertainty limit.
[0048] Specifically, the uncertainty of the interpolated wind measurement data is calculated based on the initial completeness rate, the upper limit of the completeness rate, the lower limit of the completeness rate, the upper limit of the uncertainty, and the lower limit of the uncertainty. The calculation formula is:
[0049]
[0050] Among them, U0 is the uncertainty of interpolated wind measurement data, R a is the upper limit of the completeness rate, R b is the lower limit of the completeness rate, U a is the upper limit of uncertainty, U b is the lower limit of uncertainty.
[0051] The uncertainty calculation method for interpolating wind measurement data of a wind farm provided in this embodiment interpolates the initial wind measurement data of a wind tower of a wind farm using preset wind measurement data of a preset wind measurement device, and determines the uncertainty based on the correlation between the interpolated first wind measurement data and the preset wind measurement data and the data integrity rate. The method of the present application is based on simple calculations and does not use complex calculation models, and can solve the problems of complex calculation methods and large amount of calculations. At the same time, it can consider the influence of data integrity rate and correlation on uncertainty, and realize scientific calculation of uncertainty.
[0052] In this embodiment, a method for calculating the uncertainty of interpolated wind measurement data of a wind farm is provided. Figure 2 FIG. 1 is a flowchart of another method for calculating uncertainty of wind farm interpolation wind measurement data according to an embodiment of the present invention. It should be noted that if there are substantially the same results, this embodiment does not use Figure 2 The process sequence shown is limited. Figure 2 As shown, the process includes the following steps:
[0053] Step S201, obtaining initial wind measurement data and preset wind measurement data.
[0054] Specifically, the above step S201 includes:
[0055] Step S2011, obtaining initial wind measurement data.
[0056] A plurality of initial wind speed data are continuously acquired using a wind speed sensor on a wind farm wind tower, and a plurality of initial wind direction data are continuously acquired using a wind direction sensor on a wind farm wind tower. The average wind speed and average wind direction within a preset time period are calculated based on the wind farm wind speed data and the wind farm wind direction data to obtain initial wind measurement data.
[0057] In one implementation, the sampling frequency of the wind speed sensor and the wind direction sensor of the wind farm wind tower is above 1 Hz.
[0058] In one implementation, the preset time period is 10 minutes.
[0059] Step S2012, obtaining preset wind measurement data.
[0060] A plurality of preset wind speed data are continuously obtained using a wind speed sensor of a preset wind measuring device, and a plurality of preset wind direction data are continuously obtained using a wind direction sensor of a preset wind measuring device. The average wind speed and average wind direction in a preset time period are calculated based on the preset wind speed data and the preset wind direction data to obtain the preset wind measurement data.
[0061] In one implementation, the preset wind measurement equipment includes a target wind measurement tower and a meteorological station, wherein the target wind measurement tower is a wind measurement tower near a wind farm wind measurement tower, and the meteorological station is a meteorological station near a wind farm wind measurement tower.
[0062] The target wind speed data and target wind direction data are collected using the wind speed sensor and wind direction sensor of the target wind tower; the wind speed data and wind direction data of the weather station are collected using the wind speed sensor and wind direction sensor of the weather station. The average wind speed and average wind direction are calculated based on the target wind speed data and target wind direction data to obtain the target wind measurement data; the average wind speed and average wind direction are calculated based on the wind speed data and wind direction data of the weather station to obtain the wind measurement data of the weather station.
[0063] In one implementation, the sampling frequencies of the wind speed sensors and wind direction sensors of the target wind tower and the weather station are above 1 Hz.
[0064] In one implementation, the preset time period is 10 minutes.
[0065] Step S202: perform data detection on the initial wind measurement data, remove defective data, obtain first wind measurement data, and calculate the initial completeness rate of the first wind measurement data based on the first wind measurement data and the initial wind measurement data.
[0066] Specifically, the above step S202 includes:
[0067] Step S2021, perform data detection on the initial wind measurement data, eliminate defective data, and obtain first wind measurement data.
[0068] Among them, defective data refers to unreasonable data and data with missing measurements.
[0069] Specifically, multiple initial wind measurement data are tested for rationality and analyzed to determine unreasonable data; multiple initial wind measurement data are tested for data integrity and analyzed to determine missing data. Defective data in the initial wind measurement data are eliminated to obtain the first wind measurement data.
[0070] Step S2022: Calculate the initial completeness rate of the first wind measurement data based on the first wind measurement data and the initial wind measurement data.
[0071] The calculation formula is:
[0072]
[0073] Among them, R0 is the initial completeness rate, N0 is the number of initial wind measurement data, N1 is the number of unreasonable data, and N2 is the number of missing data.
[0074] Step S203, interpolating the first wind measurement data using the preset wind measurement data to obtain interpolated wind measurement data.
[0075] The present application uses the target wind measurement data collected by the target wind measurement tower and the meteorological station wind measurement data collected by the meteorological station to interpolate the first wind measurement data in sequence to obtain interpolated wind measurement data.
[0076] Specifically, the above step S203 includes:
[0077] Step S2031, using the target wind measurement data to perform a first interpolation on the first wind measurement data to obtain target interpolated wind measurement data.
[0078] First, the target wind measurement data is used as reference data to perform the first interpolation on the processed first wind measurement data to obtain the target interpolated wind measurement data after the first interpolation. The target interpolated wind measurement data includes target interpolated wind speed data and target interpolated wind direction data.
[0079] Step S2032, using the meteorological station wind measurement data to perform a second interpolation on the target interpolated wind measurement data to obtain interpolated wind measurement data.
[0080] The wind measurement data of the meteorological station is used as the reference data again, and the target interpolated wind measurement data after the first interpolation is interpolated for the second time to obtain the interpolated wind measurement data after the second interpolation. Among them, the interpolated wind measurement data includes interpolated wind speed data and interpolated wind direction data.
[0081] Among them, the present application uses the data of the target wind tower and the meteorological station to interpolate the data of the wind farm wind tower in sequence to improve the interpolation effect.
[0082] Step S204, calculating the Pearson correlation coefficient based on the preset wind measurement data and the first wind measurement data, and determining the upper uncertainty limit and the lower uncertainty limit based on the Pearson correlation coefficient and the initial integrity rate.
[0083] Specifically, the above step S204 includes:
[0084] Step S2041, calculating the Pearson correlation coefficient based on the preset wind measurement data and the first wind measurement data.
[0085] In some optional implementations, the above step S2041 includes:
[0086] Step a1, calculating a first completeness rate based on initial wind measurement data and target interpolated wind measurement data; calculating a second completeness rate based on the initial wind measurement data and the interpolated wind measurement data.
[0087] After the first interpolation, the completeness rate of wind farm wind measurement data increases from R0 to R1. The first completeness rate is:
[0088] Among them, R v is the first complete rate, N2 is the target interpolated wind measurement data, and N0 is the initial wind measurement data.
[0089] After the second interpolation, the completeness rate of wind farm wind measurement data increased from R1 to R2. The second completeness rate is:
[0090] Among them, R2 is the first complete rate, N3 is the interpolated wind measurement data, and N0 is the initial wind measurement data.
[0091] Step a2, calculating a first Pearson correlation coefficient based on the first wind measurement data and the target wind measurement data; calculating a second Pearson correlation coefficient based on the target interpolated wind measurement data and the meteorological station wind measurement data.
[0092] Specifically, the correlation between the first wind measurement data and the target wind measurement data is calculated, and the formula for obtaining the first Pearson correlation coefficient is:
[0093]
[0094] Among them, V i and V i ′ are respectively the wind speed data of the first wind measurement data recorded in the ith time and the wind speed data of the target wind measurement data, and n is the total number of wind speed data of the first wind measurement data.
[0095] Specifically, the correlation between the target interpolated wind measurement data and the weather station wind measurement data is calculated to obtain the second Pearson correlation coefficient. The specific calculation method refers to the above formula.
[0096] Step a3: determining a first weight and a second weight based on the initial complete rate, the first complete rate and the second complete rate, and determining a second weight based on the initial complete rate, the first complete rate and the second complete rate.
[0097] The first weight for the first interpolation is:
[0098]
[0099] The second weight for the second interpolation is:
[0100]
[0101] Among them, W1 is the first weight, W2 is the second weight, R0 is the initial completeness rate, R1 is the first completeness rate, and R2 is the second completeness rate.
[0102] Step a4: weighted addition of the first Pearson correlation coefficient and the second Pearson correlation coefficient based on the first weight and the second weight to obtain the Pearson correlation coefficient.
[0103] Among them, the Pearson correlation coefficient is:
[0104] P=W1P1+W2P2.
[0105] Among them, P1 is the first Pearson correlation coefficient, P2 is the second Pearson correlation coefficient, and P is the Pearson correlation coefficient.
[0106] Step S2042, determining the upper uncertainty limit and the lower uncertainty limit based on the Pearson correlation coefficient and the initial completeness rate.
[0107] In some optional implementations, the above step S2042 includes:
[0108] Step b1, obtaining an uncertainty table, which is a relationship table of the Pearson correlation coefficient, the completeness rate and the uncertainty.
[0109] Please refer to Table 1, which is an uncertainty table according to an embodiment of the present invention.
[0110] Table 1 An uncertainty table according to an embodiment of the present invention
[0111]
[0112] As shown in Table 1, the completeness information in the uncertainty table is a discontinuous discrete value.
[0113] Step b2, obtaining the upper limit and lower limit of the completeness rate closest to the initial completeness rate in the uncertainty table.
[0114] Step b3, obtaining the lower limit of uncertainty corresponding to the upper limit of the completeness rate and the Pearson correlation coefficient, and the upper limit of uncertainty corresponding to the lower limit of the completeness rate and the Pearson correlation coefficient in the uncertainty table.
[0115] The upper limit and lower limit of uncertainty are determined by looking up the table twice.
[0116] Step S205, calculating the uncertainty of the interpolated wind measurement data based on the initial completeness rate, the upper uncertainty limit and the lower uncertainty limit.
[0117] Among them, the calculation formula for the uncertainty of interpolated wind measurement data is:
[0118]
[0119] Among them, U0 is the uncertainty of interpolated wind measurement data, R a is the upper limit of the completeness rate, R b is the lower limit of the completeness rate, U a is the lower limit of uncertainty, U b is the upper limit of uncertainty.
[0120] The uncertainty calculation method for interpolated wind measurement data of a wind farm provided in this embodiment uses the preset wind measurement data of a preset wind measurement device to interpolate the initial wind measurement data of the wind farm wind tower, and determines the uncertainty based on the correlation between the interpolated first wind measurement data and the preset wind measurement data and the data integrity rate. The correlation between the data after two interpolations and the corresponding reference data and the integrity rate after two interpolations are considered respectively, and the comprehensive correlation is calculated based on this, which can fully consider the influence of the data integrity rate and correlation on the uncertainty calculation. The upper and lower limits of the integrity rate and the upper and lower limits of the uncertainty are determined by looking up the uncertainty table. Based on this, the calculation method proposed in this application is used to calculate the uncertainty of the interpolated wind measurement data. The table lookup is convenient and the calculation method is simple. It can reduce the amount of uncertainty calculation while realizing scientific calculation of the uncertainty caused by the interpolated wind measurement data.
[0121] In this embodiment, a method for calculating uncertainty of interpolated wind measurement data of a wind farm is provided. In a specific implementation, the method is applied to data of a wind tower in a certain wind farm. Figure 3 FIG. 1 is a flowchart of a specific method for calculating uncertainty of wind farm interpolation wind measurement data according to an embodiment of the present invention. It should be noted that if there are substantially the same results, this embodiment does not use Figure 3 The process sequence shown is limited. Figure 3 As shown, the process includes the following steps:
[0122] Step S301, data collection.
[0123] The wind speed and direction data are obtained based on the 100m high wind speed sensor and wind direction sensor of a wind farm wind tower, with a sampling frequency of more than 1HZ. The wind speed and direction data are obtained based on the 100m high-speed wind speed sensor and wind direction sensor of a nearby wind tower, with a sampling frequency of 1HZ. The wind speed and direction data are obtained based on the 10m high-speed wind speed sensor and wind direction sensor of a nearby meteorological station, with a sampling frequency of more than 1HZ. The average wind speed and wind direction within the set time period of 10 minutes are calculated respectively.
[0124] Step S302, calculating the initial completeness rate.
[0125] The initial wind speed data and initial wind direction data of a wind farm tower were checked and defective data were eliminated to obtain the processed first wind speed data and first wind direction data. The initial completeness rate was calculated as:
[0126]
[0127] Step S303: first interpolation.
[0128] Using the wind speed data of the nearby wind tower as reference data, the first wind speed data of the wind farm is interpolated for the first time to obtain the target interpolated wind speed data and target interpolated wind direction data. After the first interpolation, the completeness rate of the wind farm wind speed data increased from 82% to 88%. The first Pearson correlation coefficient of the first interpolation is calculated as:
[0129]
[0130] Step S304, second interpolation.
[0131] Using the wind speed data from nearby meteorological stations as reference data, the target wind speed data of the wind farm was interpolated for the second time to obtain interpolated wind speed data and interpolated wind direction data. After the second interpolation, the completeness rate of the wind speed data of the wind farm increased from 88% to 100%. The second Pearson correlation coefficient of the second interpolation was calculated to be 0.65.
[0132] Step S305, calculating weights.
[0133] The first weight W1 of the first interpolation is 33% and the second weight W2 of the second interpolation is 67% respectively calculated by the formula, specifically:
[0134]
[0135]
[0136] Step S306, calculating the Pearson correlation coefficient.
[0137] The Pearson correlation coefficient is calculated using the formula:
[0138] P=W1P1+W2P2=33%×0.86+67%×0.65=72%.
[0139] Step S307, look up the table to obtain parameters.
[0140] Among them, the initial completeness rate is 82%. By looking up Table 1, it is determined that the upper limit of the completeness rate closest to the initial completeness rate is 83.33% (missing 2 months of measurement), and the lower limit of the completeness rate closest to the initial completeness rate is 75.00% (missing 3 months of measurement).
[0141] Among them, the Pearson correlation coefficient is 72%, and the interval of the Pearson correlation coefficient is determined to be 0.7≤P<0.8.
[0142] By looking up Table 1, the upper limit of the completeness rate is 83.33% (missing 2 months of measurement) and the Pearson correlation coefficient interval 0.7≤P<0.8, which corresponds to a lower limit of uncertainty of 1.22%. The lower limit of the completeness rate is 75.00% (missing 3 months of measurement) and the Pearson correlation coefficient interval 0.7≤P<0.8, which corresponds to an upper limit of uncertainty of 1.83%.
[0143] Step S308, calculating the uncertainty caused by interpolation of wind farm wind measurement data.
[0144] The uncertainty caused by interpolation of wind farm wind measurement data is calculated using the formula:
[0145]
[0146] It is understandable that calculation errors are allowed due to calculation accuracy.
[0147] In this embodiment, a device for calculating the uncertainty of interpolated wind measurement data of a wind farm is also provided, and the device is used to implement the above-mentioned embodiments and preferred implementation modes, and the descriptions that have been made will not be repeated. As used below, the term "module" can be a combination of software and / or hardware that implements a predetermined function. Although the device described in the following embodiments is preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.
[0148] This embodiment provides a device for calculating the uncertainty of interpolated wind measurement data in a wind farm. Figure 4 , Figure 4 is a structural block diagram of an uncertainty calculation device for interpolating wind measurement data of a wind farm according to an embodiment of the present invention. Figure 4 As shown, including:
[0149] The acquisition module 401 is used to acquire initial wind measurement data and preset wind measurement data. The initial wind measurement data is collected based on the wind farm wind measurement tower, and the preset wind measurement data is collected based on the preset wind measurement equipment.
[0150] The first calculation module 402 is used to perform data detection on the initial wind measurement data, eliminate defective data, obtain first wind measurement data, and calculate the initial completeness rate of the first wind measurement data based on the first wind measurement data and the initial wind measurement data.
[0151] The interpolation module 403 is used to interpolate the first wind measurement data using the preset wind measurement data to obtain interpolated wind measurement data.
[0152] The second calculation module 404 is used to calculate the Pearson correlation coefficient based on the preset wind measurement data and the first wind measurement data, and determine the upper uncertainty limit and the lower uncertainty limit based on the Pearson correlation coefficient and the initial integrity rate.
[0153] The third calculation module 405 is used to calculate the uncertainty of the interpolated wind measurement data based on the initial completeness rate, the upper limit of uncertainty and the lower limit of uncertainty.
[0154] The further functional description of each of the above modules is the same as that of the above corresponding embodiments and will not be repeated here.
[0155] The uncertainty calculation device for interpolating wind measurement data of a wind farm in this embodiment is presented in the form of a functional unit, where the unit refers to an ASIC (Application Specific Integrated Circuit) circuit, a processor and memory that executes one or more software or fixed programs, and / or other devices that can provide the above functions.
[0156] The embodiment of the present invention also provides a computer device having the above Figure 4 The uncertainty calculation device for interpolating wind measurement data in a wind farm is shown.
[0157] See also Figure 5 , Figure 5 is a schematic diagram of the structure of a computer device provided by an optional embodiment of the present invention, such as Figure 5As shown, the computer device includes: one or more processors 10, a memory 20, and interfaces for connecting various components, including high-speed interfaces and low-speed interfaces. Various components are connected to each other using different buses for communication, and can be installed on a common mainboard or installed in other ways as needed. The processor can process the instructions executed in the computer device, including instructions stored in or on the memory to display the graphical information of the GUI on an external input / output device (such as, a display device coupled to the interface). In some optional embodiments, if necessary, multiple processors and / or multiple buses can be used together with multiple memories and multiple memories. Similarly, multiple computer devices can be connected, and each device provides some necessary operations (for example, as a server array, a group of blade servers, or a multi-processor system). Figure 5 A processor 10 is taken as an example.
[0158] The processor 10 may be a central processing unit, a network processor or a combination thereof. The processor 10 may further include a hardware chip. The hardware chip may be a dedicated integrated circuit, a programmable logic device or a combination thereof. The programmable logic device may be a complex programmable logic device, a field programmable gate array, a general purpose array logic or any combination thereof.
[0159] The memory 20 stores instructions executable by at least one processor 10, so that the at least one processor 10 executes the method shown in the above embodiment.
[0160] The memory 20 may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created according to the use of the computer device, etc. In addition, the memory 20 may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some optional embodiments, the memory 20 may optionally include a memory remotely arranged relative to the processor 10, and these remote memories may be connected to the computer device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0161] The memory 20 may include a volatile memory, such as a random access memory; the memory may also include a non-volatile memory, such as a flash memory, a hard disk or a solid state drive; the memory 20 may also include a combination of the above types of memory.
[0162] The computer device also includes an input device 30 and an output device 40. The processor 10, the memory 20, the input device 30 and the output device 40 may be connected via a bus or other means. Figure 5 The example of connecting through bus is taken in the following.
[0163] The input device 30 can receive input digital or character information, and generate key signal input related to the user settings and function control of the computer device, such as a touch screen, a keypad, a mouse, a track pad, a touch pad, an indicator bar, one or more mouse buttons, a trackball, a joystick, etc. The output device 40 may include a display device, an auxiliary lighting device (e.g., an LED) and a tactile feedback device (e.g., a vibration motor), etc. The above-mentioned display device includes but is not limited to a liquid crystal display, a light emitting diode, a display and a plasma display. In some optional embodiments, the display device can be a touch screen.
[0164] The embodiment of the present invention also provides a computer-readable storage medium. The method according to the embodiment of the present invention can be implemented in hardware, firmware, or can be implemented as a computer code that can be recorded in a storage medium, or can be implemented as a computer code that is originally stored in a remote storage medium or a non-temporary machine-readable storage medium and will be stored in a local storage medium through a network download, so that the method described herein can be stored in such software processing on a storage medium using a general-purpose computer, a dedicated processor, or programmable or dedicated hardware. Among them, the storage medium can be a magnetic disk, an optical disk, a read-only storage memory, a random access memory, a flash memory, a hard disk or a solid-state hard disk, etc.; further, the storage medium can also include a combination of the above types of memories. It can be understood that a computer, a processor, a microprocessor controller, or programmable hardware includes a storage component that can store or receive software or computer code. When the software or computer code is accessed and executed by a computer, a processor, or hardware, the method shown in the above embodiment is implemented.
[0165] A part of the present invention may be applied as a computer program product, such as a computer program instruction, which, when executed by a computer, can call or provide the method and / or technical solution according to the present invention through the operation of the computer. Those skilled in the art should understand that the existence of the computer program instruction in a computer-readable medium includes, but is not limited to, a source file, an executable file, an installation package file, etc., and accordingly, the way in which the computer program instruction is executed by the computer includes, but is not limited to: the computer directly executes the instruction, or the computer compiles the instruction and then executes the corresponding compiled program, or the computer reads and executes the instruction, or the computer reads and installs the instruction and then executes the corresponding installed program. Here, the computer-readable medium may be any available computer-readable storage medium or communication medium accessible to the computer.
[0166] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.
Claims
1. A method for calculating uncertainty of interpolated wind measurement data in a wind farm, characterized in that: The method comprises: Acquire initial wind measurement data and preset wind measurement data, wherein the initial wind measurement data is collected based on a wind measurement tower in a wind farm, and the preset wind measurement data is collected based on preset wind measurement equipment; Performing data detection on the initial wind measurement data, eliminating defective data, obtaining first wind measurement data, and calculating an initial completeness rate of the first wind measurement data based on the first wind measurement data and the initial wind measurement data; interpolating the first wind measurement data using the preset wind measurement data to obtain interpolated wind measurement data; Calculating a Pearson correlation coefficient based on the preset wind measurement data and the first wind measurement data, and determining an upper uncertainty limit and a lower uncertainty limit based on the Pearson correlation coefficient and the initial integrity rate; The uncertainty of the interpolated wind measurement data is calculated based on the initial completeness rate, the upper uncertainty limit and the lower uncertainty limit.
2. The uncertainty calculation method for interpolating wind measurement data of a wind farm according to claim 1 is characterized in that: The obtaining of initial wind measurement data comprises: Obtaining wind speed data and wind direction data of the wind farm collected by the wind farm wind measurement tower; The average wind speed and average wind direction in a preset time period are calculated based on the wind farm wind speed data and the wind farm wind direction data to obtain the initial wind measurement data.
3. The uncertainty calculation method for interpolating wind measurement data of a wind farm according to claim 1 is characterized in that: The preset wind measurement equipment includes a target wind measurement tower and a weather station, and obtaining the preset wind measurement data includes: Obtain target wind speed data and target wind direction data collected by the target wind tower; obtain weather station wind speed data and weather station wind direction data collected by the weather station; The average wind speed and the average wind direction within a preset time period are calculated based on the target wind speed data and the target wind direction data to obtain the target wind measurement data; the average wind speed and the average wind direction are calculated based on the meteorological station wind speed data and the meteorological station wind direction data to obtain the meteorological station wind measurement data.
4. The uncertainty calculation method for interpolating wind measurement data of a wind farm according to claim 3 is characterized in that: The interpolating the first wind measurement data using the preset wind measurement data to obtain the interpolated wind measurement data comprises: Using the target wind measurement data, interpolating the first wind measurement data for the first time to obtain target interpolated wind measurement data; The target interpolated wind measurement data is interpolated for a second time using the weather station wind measurement data to obtain the interpolated wind measurement data.
5. The uncertainty calculation method for interpolating wind measurement data of a wind farm according to claim 4 is characterized in that: The calculating of the Pearson correlation coefficient based on the preset wind measurement data and the first wind measurement data comprises: Calculate a first completeness rate based on the initial wind measurement data and the target interpolated wind measurement data; calculate a second completeness rate based on the initial wind measurement data and the interpolated wind measurement data; Calculate a first Pearson correlation coefficient based on the first wind measurement data and the target wind measurement data; calculate a second Pearson correlation coefficient based on the target interpolated wind measurement data and the weather station wind measurement data; determining a first weight and a second weight based on the initial complete rate, the first complete rate, and the second complete rate; The first Pearson correlation coefficient and the second Pearson correlation coefficient are weightedly added based on the first weight and the second weight to obtain the Pearson correlation coefficient.
6. The uncertainty calculation method for interpolating wind measurement data of a wind farm according to claim 5, characterized in that: The determining a first weight based on the initial complete rate, the first complete rate, and the second complete rate comprises: The determining the second weight based on the initial complete rate, the first complete rate, and the second complete rate comprises: Wherein, W1 is the first weight, W2 is the second weight, R0 is the initial complete rate, R1 is the first complete rate, and R2 is the second complete rate; The step of weighted addition of the first Pearson correlation coefficient and the second Pearson correlation coefficient based on the first weight and the second weight to obtain the Pearson correlation coefficient comprises: P=W1P1+W2P2; Wherein, P1 is the first Pearson correlation coefficient, P2 is the second Pearson correlation coefficient, and P is the Pearson correlation coefficient.
7. The uncertainty calculation method for interpolating wind measurement data of a wind farm according to claim 1, characterized in that: The determining of the upper uncertainty limit and the lower uncertainty limit based on the Pearson correlation coefficient and the initial integrity rate includes: Obtaining an uncertainty table, wherein the uncertainty table is a relationship table of Pearson correlation coefficient, completeness rate and uncertainty; Obtaining the upper limit and lower limit of the initial completeness rate in the uncertainty table; The uncertainty lower limit corresponding to the upper limit of the complete rate and the Pearson correlation coefficient, and the uncertainty upper limit corresponding to the lower limit of the complete rate and the Pearson correlation coefficient are obtained in the uncertainty table.
8. The uncertainty calculation method for interpolating wind measurement data of a wind farm according to claim 7, characterized in that: The calculation of the uncertainty of the interpolated wind measurement data based on the initial completeness rate, the upper uncertainty limit and the lower uncertainty limit includes: Wherein, U0 is the uncertainty of the interpolated wind data, and R a is the upper limit of the completeness rate, and the R b is the lower limit of the completeness rate, and the U a is the lower limit of uncertainty, the U b is the upper limit of uncertainty.
9. The uncertainty calculation method for interpolating wind measurement data of a wind farm according to claim 1, characterized in that: The calculating the initial completeness rate based on the first wind measurement data and the initial wind measurement data comprises: Among them, R0 is the initial completeness rate, N1 is the number of the first wind measurement data, and N0 is the number of the initial wind measurement data.
10. A computer device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the uncertainty calculation method for interpolated wind measurement data of a wind farm according to any one of claims 1 to 9 by executing the computer instructions.
11. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a computer to execute the uncertainty calculation method for interpolated wind measurement data of a wind farm according to any one of claims 1 to 9.
12. A computer program product, characterized in that The method comprises computer instructions, wherein the computer instructions are used to enable a computer to execute the uncertainty calculation method for interpolated wind measurement data of a wind farm according to any one of claims 1 to 9.