Efficient integrated geothermal unit based on middle-deep layer geothermal energy
By designing an efficient integrated geothermal unit including water supply pump, geothermal heat exchange pipe and a combination of multiple pumps, the problems of inadequate grading of medium and deep geothermal energy and insufficient self-priming capacity of water pumps are solved, and the grading of hot water is realized and recirculation heating improve the energy utilization efficiency of the geothermal unit.
Patent Information
- Application Number
- CN202411240822.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
It is difficult for existing geothermal units to temporarily store the medium and deep geothermal energy. The self-priming ability of the water pump when pumping water is insufficient. The lack of a stepped water pump water supply mechanism, so it is impossible to inject water into the water pump to improve the self-priming ability.
An efficient integrated geothermal unit based on medium and deep geothermal heat is designed, including a water supply pump, a geothermal heat exchange tube, a high-temperature resistant water pump, a sub-liquid pump, an insulating box and a liquid extraction assembly, which is used by a combination of a sub-liquid pump and a centrifugal pump. Achieve the grading temporary storage and self-priming enhancement of hot water, and improve the pumping efficiency through the water supply riser and the pumping pump.
It effectively solves the problems of inadequate storage of intermediate and deep geothermal energy grading and insufficient self-priming capacity of water pumps, improves the energy utilization efficiency and pumping efficiency of geothermal units, and realizes the grading temporary storage and recirculation heating of hot water.
Smart Images

Figure CN119022489A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of geothermal units, and in particular relates to a high-efficiency integrated geothermal unit based on mid-deep geothermal heat. Background Art
[0002] Geothermal energy refers to the heat inside the earth, which is transferred to the surface through underground heat sources to form geothermal energy. Geothermal energy is a clean and renewable energy source. According to the depth and temperature of geothermal resources, geothermal energy is usually divided into shallow geothermal, middle geothermal and deep geothermal. Middle and deep geothermal energy mainly comes from heat sources deep underground, with higher temperature and high energy density, and is suitable for large-scale energy supply.
[0003] At present, the ground source heat pump unit in the prior art is a device that uses water circulating in a public pipeline, water drawn from a well, lake or river, or water circulating in an underground coil as a cold (heat) source to produce cold (hot) air or cold (hot) water. However, the geothermal unit in the prior art is difficult to temporarily store medium and deep geothermal energy in a graded manner, the self-priming capacity of the water pump when pumping water is insufficient, and there is a lack of a stepped water pump water supply mechanism, and the water pump cannot be injected with water to improve the self-priming capacity of the water pump.
[0004] Therefore, a high-efficiency integrated geothermal unit based on medium-deep geothermal energy is proposed, which can temporarily store medium-deep geothermal energy in a graded manner and has a stepped water pump water supply mechanism, which can inject water into the water pump to improve the self-priming capacity of the water pump. Summary of the invention
[0005] In order to overcome the problem that geothermal units in the prior art are difficult to temporarily store mid- and deep-layer geothermal energy in a graded manner, the water pump has insufficient self-priming capacity when pumping water, lacks a stepped water pump water supply mechanism, and cannot inject water into the water pump to improve its self-priming capacity.
[0006] The technical solution of the present invention is: a high-efficiency integrated geothermal unit based on medium-deep geothermal heat, including a water supply pump; a water delivery pipeline is fixedly connected to the liquid outlet port of the water supply pump, a geothermal heat exchange pipe is arranged below the water supply pump, the other end of the water delivery pipeline is fixedly connected to the water inlet port of the geothermal heat exchange pipe, a first high-temperature resistant water pump is arranged above the geothermal heat exchange pipe, a first water collecting tank is arranged above the first high-temperature resistant water pump, a first hot water temporary storage tank is connected to the upper end pipeline of the first water collecting tank, a second water collecting tank is arranged above the first hot water temporary storage tank, a second hot water temporary storage tank is arranged above the second water collecting tank, and a A bearing plate is provided, a water storage tank is provided below the bearing plate, a third insulation tank for heat-insulating water is provided below the water storage tank, a return pipe is provided at the lower end of the third insulation tank, the other end of the return pipe passes through the outer wall of the geothermal heat exchange tube and extends to the inner wall of the geothermal heat exchange tube, a liquid extraction port of a first high-temperature resistant water pump is connected to the water outlet port of the geothermal heat exchange tube through a pipeline, a liquid outlet port of the first high-temperature resistant water pump is connected to the water inlet port of the first water collecting tank through a pipeline, a heating component is provided on the second water collecting tank, a second insulation component is provided on the second hot water temporary storage tank, and a second liquid extraction component for extracting liquid is provided on the bearing plate;
[0007] A first liquid pumping assembly is provided on the first water collecting tank, and the first liquid pumping assembly includes a first bracket, a submersible pump, a first drain pipe, a vertical pump, and a second drain pipe; a first bracket is fixedly connected to the upper end of the first water collecting tank, a submersible pump is fixedly connected to the first bracket, a liquid pumping end of the submersible pump is located inside the first water collecting tank, a first drain pipe is fixedly connected to a liquid outlet port of the submersible pump, a vertical pump is provided above the first hot water temporary storage tank, the other end of the first drain pipe is fixedly connected to a liquid pumping port of the vertical pump, a second drain pipe is fixedly connected to a liquid outlet port of the vertical pump, and an upper end of the second drain pipe passes through a lower end of the second water collecting tank and extends to the inside of the second water collecting tank;
[0008] A first insulation component is arranged on the first hot water storage tank, and the first insulation component includes a first insulation box, a first centrifugal pump and a first return pipe; the upper end pipeline of the first water collecting tank is connected to the first hot water storage tank, and the inner wall of the first hot water storage tank is arranged with the first insulation box, the interior of the first insulation box is interconnected with the interior of the first hot water storage tank, and the upper end of the first hot water storage tank is arranged with a first centrifugal pump, the water pumping end pipeline of the first centrifugal pump is connected to the outlet pipeline of the first hot water storage tank, and the first return pipe is fixedly connected to the outlet port of the first centrifugal pump, and the other end of the first return pipe passes through the upper end of the first water collecting tank and extends to the upper inner wall of the first water collecting tank.
[0009] Preferably, when in use, a drilling rig is used to drill underground to establish an area where the device can be stored underground, and then the geothermal heat exchange tube is buried near the underground area with geothermal heat, the tap water pipe is connected to the water inlet port of the water supply pump, and then the water supply pump is turned on to allow water to flow into the interior of the geothermal heat exchange tube through the water delivery pipe, and then the first high-temperature resistant water pump is turned on to pump the water in the geothermal heat exchange tube into the first water collecting tank, and then the submersible pump is turned on to pump the hot water in the first water collecting tank into the second water collecting tank. Since excess hot water will enter the first hot water temporary storage tank through the pipe, and then be used by the first insulation box to achieve graded temporary storage of hot water, when it is necessary to inject water into the impeller of the submersible pump to increase its self-priming force, the valve body on the pipe connected to the first water collecting tank is closed, so that only the first return pipe can inject water into the first water collecting tank, and the submersible pump can pump out the water in the first water collecting tank, and then the first separation tank is turned on. The central pump draws the water in the first insulation box into the interior of the first water collecting tank through the first return pipe, squeezes the water in the first water collecting tank, and can squeeze the water to the impeller of the submersible pump, thereby improving the self-priming force of the submersible pump, and then the hot water in the first water collecting tank is pumped into the second water collecting tank through the vertical pump and the submersible pump, and the excess hot water will also enter the second hot water temporary storage tank for temporary storage, and then the second pumping assembly on the supporting plate is opened, the water in the second water collecting tank can be pumped out and discharged into the interior of the water storage tank, and then returned to the geothermal heat exchange pipe through the third insulation box and the return pipe, and can be heated again by the geothermal source near the geothermal heat exchange pipe, which solves the problems in the prior art that geothermal units are difficult to temporarily store medium and deep geothermal energy in stages, the self-priming capacity of the water pump is insufficient when pumping water, and there is a lack of a stepped water pump water supply mechanism, so that the water pump cannot be filled with water to improve the self-priming capacity of the water pump.
[0010] Preferably, the heating component includes a second bracket, a second submersible pump and a water supply riser. The second bracket is fixedly connected to the upper end of the second water collecting tank, and the second bracket is fixedly connected to the second submersible pump. The pumping end of the second submersible pump is located inside the second water collecting tank. The upper end of the second water collecting tank is fixedly connected to the water supply riser. The upper end of the water supply riser passes through the bottom end of the second hot water storage tank and extends to the interior of the second hot water storage tank. The water entering the second water collecting tank will be pumped out by the second submersible pump. The external pipeline is connected to the liquid outlet end of the second submersible pump to supply hot water to the outside. In addition, the hot water in the second water collecting tank can enter the second hot water storage tank through the water supply riser for temporary storage.
[0011] Preferably, the second insulation component includes a second insulation box, a second centrifugal pump and a second return pipe; the inner wall of the second hot water storage box is provided with a second insulation box, and the interior of the second insulation box is communicated with the internal space of the second hot water storage box. When the hot water enters the second hot water storage box through the water supply riser, the second insulation box can temporarily store the hot water after obtaining it.
[0012] Preferably, the second liquid pumping assembly includes a first water pump, a first water pumping pipe, a third drain pipe, a second water pump, a second water pumping pipe, a water supply pipe, a first solenoid valve and a fourth drain pipe; the first water pump and the second water pump are fixedly connected to the upper end of the supporting plate, the first water pump is fixedly connected to the liquid pumping port of the first water pump, the other end of the first water pumping pipe passes through the outer wall of the second water collecting tank and extends to the inner wall of the second water collecting tank, the third drain pipe is fixedly connected to the water outlet port of the first water pump, the other end of the third drain pipe passes through the upper end of the water storage tank and extends to the inside of the water storage tank, the second water pump is fixedly connected to the liquid pumping port of the second water pump, the other end of the second water pumping pipe passes through the upper end of the second water collecting tank and extends to the second water collecting tank Inside the box, a water supply pipe is fixedly connected to the liquid pumping port of the second water pump, and the other end of the water supply pipe penetrates the side wall of the water supply tank and extends to the inside of the water supply tank, and a first solenoid valve is arranged on the water supply pipe, and a fourth drainage pipe is fixedly connected to the liquid outlet port of the second water pump, and the other end of the fourth drainage pipe penetrates the upper end of the water storage tank and extends to the inside of the water storage tank. When the first water pump is turned on, the water in the second water collecting tank can be injected into the inside of the water storage tank through the third drainage pipe, and when the second water pump is turned on, the water in the second water collecting tank can be injected into the inside of the water storage tank. By setting two water pumps, the pumping efficiency can be improved, and when one of the first water pump or the second water pump fails, normal pumping can be guaranteed.
[0013] Preferably, the end of the water supply pipe entering the water supply tank is fifty centimeters away from the inner wall of the water supply tank closest to the supporting plate. The water in the water supply tank can enter the pumping chamber of the second water pump through the water supply pipe, which can avoid the situation where the pumping chamber of the second water pump has insufficient pressure to pump out the water.
[0014] Preferably, a water supply tank for water supply is provided on the supporting plate, a cylinder is fixedly connected to the side end of the water supply tank, the output shaft of the cylinder passes through the outer wall of the water supply tank and is fixedly connected to a push plate, a liquid level sensor is fixedly connected to one end of the inner wall of the water supply tank close to the supporting plate, a water supply pipe is provided at the upper end of the water supply tank, a second solenoid valve is provided on the water supply pipe, water can be replenished into the water supply tank by opening the second solenoid valve through the water supply pipe, and then the second solenoid valve is closed and the cylinder is opened to push the push plate, so that the water in the water supply tank can be pushed into the interior of the water supply pipe.
[0015] Preferably, the side walls of the push plate are made of hard rubber material, and the center of the push plate is made of stainless steel. The side walls of the push plate are made of hard rubber material, which can easily press the water in the water supply tank into the inside of the water supply pipe.
[0016] Preferably, the third insulation box is provided with an insulation component, which includes a first insulation tube, a second insulation tube, a third insulation tube, a through hole and a cross block; the bottom surface of the inner wall of the third insulation box is fixedly connected with the first insulation tube, the second insulation tube and the third insulation tube, the first insulation tube, the second insulation tube and the third insulation tube are all made of aluminum-iron alloy, and the side walls of the first insulation tube, the second insulation tube and the third insulation tube are penetrated with evenly distributed through holes, when the warm water flows back, it will flow into the interior of the third insulation box, the first insulation tube, the second insulation tube and the third insulation tube can all insulate the water to a certain extent, and the setting of the through holes facilitates the flow of the water.
[0017] Preferably, a cross block is fixed to the bottom surface of the inner wall of the third insulation box, and the four ends of the cross block pass through the third insulation tube and the second insulation tube and are fixed to the inner wall of the first insulation tube. The setting of the cross block can provide stable support for the first insulation tube, the second insulation tube and the third insulation tube.
[0018] Preferably, the cross block is made of stainless steel, the center point of the cross block is located on the central axis of the third insulation box, and each pipeline is provided with a valve body. The cross block is made of stainless steel, has high strength and good stability, and each pipeline is provided with a valve body, which facilitates the control of the water flow in the pipeline.
[0019] Beneficial effects of the present invention:
[0020] 1. Use a drilling rig to drill underground to create an area where the device can be stored underground, then bury the geothermal heat exchange pipe near the underground geothermal area, connect the tap water pipe to the water inlet port of the water supply pump, and then turn on the water supply pump to allow water to flow into the geothermal heat exchange pipe through the water supply pipe, and then turn on the first high-temperature resistant water pump to pump the water in the geothermal heat exchange pipe into the first water collecting tank, and then turn on the first submersible pump to pump the hot water in the first water collecting tank into the second water collecting tank. Since excess hot water will enter the first hot water temporary storage tank through the pipe, and then be used by the first insulation tank to achieve graded temporary storage of hot water, when it is necessary to inject water into the impeller of the first submersible pump to increase its self-priming force, close the valve body on the pipe connected to the first water collecting tank, so that only the first return pipe can inject water into the first water collecting tank, the first submersible pump can pump out the water in the first water collecting tank, and then turn on the first centrifugal pump to The water in the first insulation box is pumped into the interior of the first water collecting tank through the first return pipe, and the water in the first water collecting tank is squeezed to the impeller of the first submersible pump, thereby improving the self-priming force of the first submersible pump, and then the hot water in the first water collecting tank is pumped into the second water collecting tank through the vertical pump and the first submersible pump, and the excess hot water will also enter the second hot water temporary storage tank for temporary storage, and then the second pumping assembly on the carrier plate is opened, the water in the second water collecting tank can be pumped out and discharged into the interior of the water storage tank, and then returned to the geothermal heat exchange pipe through the third insulation box and the return pipe, and can be heated again by the geothermal source near the geothermal heat exchange pipe, which solves the problem that it is difficult for geothermal units in the prior art to temporarily store medium and deep geothermal energy in stages, the self-priming capacity of the water pump is insufficient when pumping water, and there is a lack of a stepped water pump water supply mechanism, so that the water pump cannot be filled with water to improve the self-priming capacity of the water pump;
[0021] 2. The upper end of the water supply riser passes through the bottom end of the second hot water temporary storage tank and extends to the interior of the second hot water temporary storage tank. The water entering the second water collecting tank will be pumped out by the second submersible pump. The external pipe is connected to the liquid outlet end of the second submersible pump to supply hot water to the outside. In addition, the hot water in the second water collecting tank can enter the second hot water temporary storage tank through the water supply riser for temporary storage. When the hot water enters the second hot water temporary storage tank through the water supply riser, the second insulation tank can store the hot water temporarily after obtaining it.
[0022] 3. After opening the second solenoid valve, water can be added to the water supply tank through the water supply pipe, and then the second solenoid valve is closed, and the cylinder is turned on to push the push plate, so that the water in the water supply tank can be pushed into the water supply pipe, and the water can enter the pumping chamber of the second water pump, which can avoid the second water pump The pumping chamber pressure is insufficient and cannot pump out the water;
[0023] 4. When the warm water flows back, it will flow into the interior of the third insulation box. The first insulation tube, the second insulation tube and the third insulation tube can all insulate the water to a certain extent. The setting of the through holes facilitates the flow of the water. The setting of the cross block can provide stable support for the first insulation tube, the second insulation tube and the third insulation tube. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 What is shown is a three-dimensional structural schematic diagram of a high-efficiency integrated geothermal unit based on mid-deep geothermal heat of the present invention;
[0025] Figure 2 Shown is a three-dimensional structural schematic diagram of the first water collecting tank and the first hot water temporary storage tank of the high-efficiency integrated geothermal unit based on mid-deep geothermal heat of the present invention;
[0026] Figure 3 Shown is a three-dimensional structural schematic diagram of the second water collecting tank and the second hot water temporary storage tank of the high-efficiency integrated geothermal unit based on mid-deep geothermal heat of the present invention;
[0027] Figure 4 The high-efficiency integrated geothermal unit based on mid-deep geothermal energy of the present invention is shown. Figure 2 Middle A is a partial enlarged schematic diagram of the three-dimensional structure;
[0028] Figure 5 The diagram shows a three-dimensional split structure of the second water collecting tank of the high-efficiency integrated geothermal unit based on mid-deep geothermal heat of the present invention;
[0029] Figure 6 What is shown is a cross-sectional three-dimensional structural schematic diagram of a water supply tank of a high-efficiency integrated geothermal unit based on mid-deep geothermal heat according to the present invention;
[0030] Figure 7 What is shown is the front view of the high-efficiency integrated geothermal unit based on mid-deep geothermal heat of the present invention;
[0031] Figure 8 The schematic diagram of the three-dimensional split structure of the third insulation box of the high-efficiency integrated geothermal unit based on mid-deep geothermal heat of the present invention is shown;
[0032] Fig. 9 What is shown is a three-dimensional structural schematic diagram of the cross block of the high-efficiency integrated geothermal unit based on medium-deep geothermal energy of the present invention.
[0033] The markings in the attached drawings are: 1, water supply pump; 2, water delivery pipeline; 3, geothermal heat exchange pipe; 4, first high temperature resistant water pump; 5, first water collecting tank; 501, first bracket; 502, first submersible pump; 503, first drainage pipe; 504, vertical pump; 505, second drainage pipe; 6, first hot water temporary storage tank; 601, first insulation tank; 602, first centrifugal pump; 603, first return pipe; 7, second water collecting tank; 701, second bracket; 702, second submersible pump; 703, water supply riser; 8, second hot water temporary storage tank; 801, second insulation tank; 802, second centrifugal pump; 803, second return pipe; 9 , bearing plate; 901, first water pump; 902, first water pipe; 903, third drainage pipe; 904, second water pump; 905, second water pipe; 906, water supply pipe; 907, first solenoid valve; 908, fourth drainage pipe; 10, water supply tank; 1001, cylinder; 1002, push plate; 1003, water supply pipe; 1004, second solenoid valve; 1005, liquid level sensor; 11, water storage tank; 12, third insulation box; 1201, first insulation cylinder; 1202, second insulation cylinder; 1203, third insulation cylinder; 1204, through hole; 1205, cross block; 13, return pipe. DETAILED DESCRIPTION
[0034] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0035] See also Figure 1-Figure 9 , the present invention provides three technical solutions:
[0036] Embodiment 1
[0037] See also Figure 1-Figure 9, a high-efficiency integrated geothermal unit based on medium and deep geothermal heat, including a water supply pump 1; a water delivery pipeline 2 is fixedly connected to the liquid outlet port of the water supply pump 1, a geothermal heat exchange pipe 3 is arranged below the water supply pump 1, the other end of the water delivery pipeline 2 is fixedly connected to the water inlet port of the geothermal heat exchange pipe 3, a first high-temperature resistant water pump 4 is arranged above the geothermal heat exchange pipe 3, a first water collecting tank 5 is arranged above the first high-temperature resistant water pump 4, a first hot water temporary storage tank 6 is connected to the upper end pipeline of the first water collecting tank 5, a second water collecting tank 7 is arranged above the first hot water temporary storage tank 6, a second hot water temporary storage tank 8 is arranged above the second water collecting tank 7, a bearing plate 9 is arranged above the second hot water temporary storage tank 8, and a bearing plate 9 is arranged on the bearing plate 9 for A water supply tank 10 for water supply, a water storage tank 11 is arranged below the bearing plate 9, a third insulation tank 12 for heat preservation of water body is arranged below the water storage tank 11, a return pipe 13 is arranged at the lower end of the third insulation tank 12, the other end of the return pipe 13 passes through the outer wall of the geothermal heat exchange tube 3 and extends to the inner wall of the geothermal heat exchange tube 3, the pumping port of the first high temperature resistant water pump 4 is connected to the water outlet port of the geothermal heat exchange tube 3 through a pipeline, the liquid outlet port of the first high temperature resistant water pump 4 is connected to the water inlet port of the first water collecting tank 5 through a pipeline, a heating component is arranged on the second water collecting tank 7, a second insulation component is arranged on the second hot water temporary storage tank 8, and a second pumping component for pumping liquid is arranged on the bearing plate 9;
[0038] A first liquid pumping assembly is provided on the first water collecting tank 5, and the first liquid pumping assembly includes a first bracket 501, a first submersible pump 502, a first drainage pipe 503, a vertical pump 504 and a second drainage pipe 505; the first bracket 501 is fixedly connected to the upper end of the first water collecting tank 5, the first submersible pump 502 is fixedly connected to the first bracket 501, the liquid pumping end of the first submersible pump 502 is located inside the first water collecting tank 5, the first drainage pipe 503 is fixedly connected to the liquid outlet port of the first submersible pump 502, a vertical pump 504 is provided above the first hot water temporary storage tank 6, the other end of the first drainage pipe 503 is fixedly connected to the liquid pumping port of the vertical pump 504, the second drainage pipe 505 is fixedly connected to the liquid outlet port of the vertical pump 504, and the upper end of the second drainage pipe 505 passes through the lower end of the second water collecting tank 7 and extends to the inside of the second water collecting tank 7;
[0039] A first insulation component is arranged on the first hot water temporary storage tank 6, and the first insulation component includes a first insulation box 601, a first centrifugal pump 602 and a first return pipe 603; the upper end pipeline of the first water collecting tank 5 is connected to the first hot water temporary storage tank 6, and the inner wall of the first hot water temporary storage tank 6 is arranged with the first insulation box 601, the interior of the first insulation box 601 is interconnected with the interior of the first hot water temporary storage tank 6, and the upper end of the first hot water temporary storage tank 6 is arranged with a first centrifugal pump 602, and the water pumping end pipeline of the first centrifugal pump 602 is connected to the outlet pipeline of the first hot water temporary storage tank 6, and the first return pipe 603 is fixedly connected to the outlet port of the first centrifugal pump 602, and the other end of the first return pipe 603 passes through the upper end of the first water collecting tank 5 and extends to the upper inner wall of the first water collecting tank 5.
[0040] See also Figure 3 In the embodiment of the present invention, the heating component includes a second bracket 701, a second submersible pump 702 and a water supply riser 703. The second bracket 701 is fixedly connected to the upper end of the second water collecting tank 7, and the second submersible pump 702 is fixedly connected to the second bracket 701. The pumping end of the second submersible pump 702 is located inside the second water collecting tank 7. The upper end of the second water collecting tank 7 is fixedly connected to the water supply riser 703. The upper end of the water supply riser 703 passes through the bottom end of the second hot water storage tank 8 and extends to the inside of the second hot water storage tank 8.
[0041] See also Figure 3 In the embodiment of the present invention, the second insulation component includes a second insulation box 801, a second centrifugal pump 802 and a second return pipe 803; the inner wall of the second hot water storage tank 8 is provided with a second insulation box 801, and the interior of the second insulation box 801 is communicated with the internal space of the second hot water storage tank 8.
[0042] See also Figure 4 and Figure 5 In the embodiment of the present invention, the second liquid pumping component includes a first water pump 901, a first water pumping pipe 902, a third drainage pipe 903, a second water pump 904, a second water pumping pipe 905, a water supply pipe 906, a first solenoid valve 907 and a fourth drainage pipe 908; the first water pump 901 and the second water pump 904 are fixedly connected to the upper end of the supporting plate 9, the first water pump 901 is fixedly connected to the liquid pumping port with the first water pump 902, the other end of the first water pumping pipe 902 passes through the outer wall of the second water collecting tank 7 and extends to the inner wall of the second water collecting tank 7, the third drainage pipe 903 is fixedly connected to the water outlet port of the first water pump 901, the other end of the third drainage pipe 903 passes through the upper end of the water storage tank 11 and extends to the inside of the water storage tank 11, the second water pump A second water pumping pipe 905 is fixedly connected to the liquid extraction port of 904, and the other end of the second water pumping pipe 905 passes through the upper end of the second water collecting tank 7 and extends to the interior of the second water collecting tank 7. A water supply pipe 906 is fixedly connected to the liquid extraction port of the second water pump 904, and the other end of the water supply pipe 906 passes through the side wall of the water supply tank 10 and extends to the interior of the water supply tank 10. A first solenoid valve 907 is arranged on the water supply pipe 906. A fourth drainage pipe 908 is fixedly connected to the liquid outlet port of the second water pump 904, and the other end of the fourth drainage pipe 908 passes through the upper end of the water storage tank 11 and extends to the interior of the water storage tank 11. The end of the water supply pipe 906 entering the water supply tank 10 is fifty centimeters away from the inner wall of the water supply tank 10 closest to the supporting plate 9, and each pipe is provided with a valve body.
[0043] In the embodiment of the present invention: when in use, a drilling rig is used to drill the soil underground to establish an area where the device can be stored underground, and then the geothermal heat exchange pipe 3 is buried near the area with geothermal heat underground, and the tap water pipe is connected to the water inlet port of the water supply pump 1, and then the water supply pump 1 is turned on to allow water to flow into the inside of the geothermal heat exchange pipe 3 through the water delivery pipe 2, and then the first high-temperature resistant water pump 4 is turned on to pump the water in the geothermal heat exchange pipe 3 into the first water collecting tank 5, and then the first submersible pump 502 is turned on to pump the hot water in the first water collecting tank 5 into the second water collecting tank 7. Since the excess hot water will enter the first hot water temporary storage tank 6 through the pipe, the graded temporary storage of hot water is realized;
[0044] When it is necessary to inject water into the impeller of the first submersible pump 502 to improve its self-priming force, the valve body on the pipeline connected to the first water collecting tank 5 is closed, so that only the first return pipe 603 can inject water into the first water collecting tank 5, and the first submersible pump 502 can pump out the water in the first water collecting tank 5, and then start the first centrifugal pump 602 to pump the water in the first insulation box 601 into the first water collecting tank 5 through the first return pipe 603, and squeeze the water in the first water collecting tank 5 to the impeller of the first submersible pump 502. The self-priming force of the first submersible pump 502 can be improved, and then the hot water in the first water collecting tank 5 is pumped into the second water collecting tank 7 through the vertical pump 504 and the first submersible pump 502, and the excess hot water is also temporarily stored in the second hot water temporary storage tank 8. Then, the second pumping assembly on the supporting plate 9 is opened, and the water in the second water collecting tank 7 can be pumped out and discharged into the water storage tank 11, and then refluxed to the geothermal heat exchange pipe 3 through the third insulation box 12 and the return pipe 13, and can be heated again by the geothermal source near the geothermal heat exchange pipe 3.
[0045] The second embodiment is different from the first embodiment in that:
[0046] See also Figure 6 In the embodiment of the present invention, a cylinder 1001 is fixedly connected to the side end of the water supply tank 10, and the output shaft of the cylinder 1001 passes through the outer wall of the water supply tank 10 and is fixedly connected to a push plate 1002. A liquid level sensor 1005 is fixedly connected to one end of the inner wall of the water supply tank 10 close to the supporting plate 9. A water supply pipe 1003 is provided at the upper end of the water supply tank 10, and a second solenoid valve 1004 is provided on the water supply pipe 1003. The side wall of the push plate 1002 is made of hard rubber material, and the center of the push plate 1002 is made of stainless steel.
[0047] In the embodiment of the present invention: the second solenoid valve 1004 is opened through the water supply pipe 1003 to replenish water into the water supply tank 10, and then the second solenoid valve 1004 is closed, and the cylinder 1001 is opened to push the push plate 1002, so that the water in the water supply tank 10 can be pushed into the interior of the water supply pipe 906, and the water can enter the pumping chamber of the second water pump 904, which can avoid the second water pump 904 The pumping chamber pressure is insufficient and cannot pump out the water.
[0048] Embodiment 3 is different from Embodiment 1 in that:
[0049] See also Figure 7 , Figure 8 and Fig. 9 In the embodiment of the present invention, the third insulation box 12 is provided with an insulation component, and the insulation component includes a first insulation tube 1201, a second insulation tube 1202, a third insulation tube 1203, a through hole 1204 and a cross block 1205; the bottom surface of the inner wall of the third insulation box 12 is fixedly connected with the first insulation tube 1201, the second insulation tube 1202 and the third insulation tube 1203, and the first insulation tube 1201, the second insulation tube 1202 and the third insulation tube 1203 are all made of aluminum-iron alloy. The side walls of the first insulation tube 1201, the second insulation tube 1202 and the third insulation tube 1203 are all penetrated with evenly distributed through holes 1204, and the bottom surface of the inner wall of the third insulation box 12 is fixed with a cross block 1205. The four ends of the cross block 1205 pass through the third insulation tube 1203 and the second insulation tube 1202 and are fixed to the inner wall of the first insulation tube 1201. The cross block 1205 is made of stainless steel, and the center point of the cross block 1205 is located on the central axis of the third insulation box 12.
[0050] In the embodiment of the present invention: when the warm water flows back, it will flow into the interior of the third insulation box 12, the first insulation tube 1201, the second insulation tube 1202 and the third insulation tube 1203 can all insulate the water to a certain extent, the setting of the through hole 1204 facilitates the flow of the water, and the setting of the cross block 1205 can stably support the first insulation tube 1201, the second insulation tube 1202 and the third insulation tube 1203.
[0051] Working principle: First, when in use, use a drilling rig to drill the soil underground to establish an area where the device can be stored underground, then bury the geothermal heat exchange pipe 3 near the area with geothermal heat underground, connect the tap water pipe to the water inlet port of the water supply pump 1, and then turn on the water supply pump 1 to allow the water to flow into the geothermal heat exchange pipe 3 through the water delivery pipe 2, and then turn on the first high-temperature resistant water pump 4 to pump the water in the geothermal heat exchange pipe 3 into the first water collecting tank 5, and then turn on the first submersible pump 502 to pump the hot water in the first water collecting tank 5 into the second water collecting tank 7. Since the excess hot water will enter the first hot water temporary storage tank 6 through the pipe, the graded temporary storage of hot water is realized;
[0052] When it is necessary to inject water into the impeller of the first submersible pump 502 to improve its self-priming force, the valve body on the pipeline connected to the first water collecting tank 5 is closed, so that only the first return pipe 603 can inject water into the first water collecting tank 5, and the first submersible pump 502 can pump out the water in the first water collecting tank 5, and then start the first centrifugal pump 602 to pump the water in the first insulation box 601 into the first water collecting tank 5 through the first return pipe 603, and squeeze the water in the first water collecting tank 5 to the impeller of the first submersible pump 502. The self-priming force of the first submerged pump 502 can be improved, and then the hot water in the first water collecting tank 5 is pumped into the second water collecting tank 7 through the vertical pump 504 and the first submerged pump 502, and the excess hot water is temporarily stored in the second hot water temporary storage tank 8, and then the second pumping assembly on the bearing plate 9 is opened to pump out the water in the second water collecting tank 7 and discharge it into the water storage tank 11, and then return to the geothermal heat exchange pipe 3 through the third insulation box 12 and the return pipe 13, and can be heated again by the geothermal source near the geothermal heat exchange pipe 3;
[0053] Then, the hot water in the first water collecting tank 5 is pumped into the second water collecting tank 7 through the vertical pump 504 and the first submerged pump 502. The water in the second water collecting tank 7 is pumped out by the second submerged pump 702. The external pipeline is connected to the liquid outlet of the second submerged pump 702, and hot water can be supplied to the outside. In addition, the hot water in the second water collecting tank 7 can enter the second hot water temporary storage tank 8 through the water supply vertical pipe 703 for temporary storage. When the hot water enters the second hot water temporary storage tank 8 through the water supply vertical pipe 703, the second heat preservation tank 801 can obtain the hot water and store it temporarily.
[0054] Next, the first pumping pump 901 is turned on to inject the water in the second water collecting tank 7 into the water storage tank 11 through the third drainage pipe 903, and the second pumping pump 904 is turned on to inject the water in the second water collecting tank 7 into the water storage tank 11. By setting two pumping pumps, the pumping efficiency can be improved, and when one of the first pumping pump 901 or the second pumping pump 904 fails, normal pumping can be guaranteed.
[0055] After the water is drawn out and discharged into the water storage tank 11, it will flow back to the geothermal heat exchange pipe 3 through the third insulation box 12 and the return pipe 13. The first insulation tube 1201, the second insulation tube 1202 and the third insulation tube 1203 can all insulate the water to a certain extent. The through hole 1204 is set to facilitate the flow of the water. Therefore, the water with a certain temperature will be heated again by the geothermal source near the geothermal heat exchange pipe 3, realizing the circulating flow heating of the water. In actual use, multiple insulation boxes are set at a suitable height according to the terrain for temporary storage;
[0056] In addition, when in use, after opening the second solenoid valve 1004, water can be replenished into the water supply tank 10 through the water replenishment pipe 1003, and then the second solenoid valve 1004 is closed, and the cylinder 1001 is opened to push the push plate 1002, so that the water in the water supply tank 10 can be pushed into the interior of the water supply pipe 906, and the water will enter the water pumping chamber of the second water pump 904, which can avoid the second water pump 904 The pumping chamber pressure is insufficient and cannot pump out the water, thereby improving the self-priming ability of the second water pump 904.
[0057] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of those skilled in the art without departing from the spirit of the present invention.
Claims
1. A high-efficiency integrated geothermal unit based on medium-deep geothermal energy, comprising a water supply pump (1); characterized in that: A water delivery pipe (2) is fixedly connected to the liquid outlet of the water supply pump (1), a geothermal heat exchange pipe (3) is arranged below the water supply pump (1), the other end of the water delivery pipe (2) is fixedly connected to the water inlet port of the geothermal heat exchange pipe (3), a first high temperature resistant water pump (4) is arranged above the geothermal heat exchange pipe (3), a first water collecting tank (5) is arranged above the first high temperature resistant water pump (4), an upper end pipe of the first water collecting tank (5) is connected to a first hot water temporary storage tank (6), a second water collecting tank (7) is arranged above the first hot water temporary storage tank (6), a second hot water temporary storage tank (8) is arranged above the second water collecting tank (7), a bearing plate (9) is arranged above the second hot water temporary storage tank (8), a water supply tank (10) for water supply is arranged on the bearing plate (9), and a water supply tank (10) for water supply is arranged on the bearing plate (9). A water storage tank (11) is arranged below the carrier plate (9), a third heat preservation tank (12) for heat preservation of water is arranged below the water storage tank (11), a return pipe (13) is arranged at the lower end of the third heat preservation tank (12), the other end of the return pipe (13) passes through the outer wall of the geothermal heat exchange tube (3) and extends to the inner wall of the geothermal heat exchange tube (3), the liquid extraction port of the first high temperature resistant water pump (4) is connected to the water outlet port of the geothermal heat exchange tube (3) through a pipeline, the liquid outlet port of the first high temperature resistant water pump (4) is connected to the water inlet port of the first water collecting tank (5) through a pipeline, a heating component is arranged on the second water collecting tank (7), a second heat preservation component is arranged on the second hot water temporary storage tank (8), and a second liquid extraction component for extracting liquid is arranged on the carrier plate (9); A first liquid pumping assembly is provided on the first water collecting tank (5), and the first liquid pumping assembly comprises a first bracket (501), a first submersible pump (502), a first drainage pipe (503), a vertical pump (504) and a second drainage pipe (505); A first bracket (501) is fixedly connected to the upper end of the first water collecting tank (5), a first submersible pump (502) is fixedly connected to the first bracket (501), a liquid extraction end of the first submersible pump (502) is located inside the first water collecting tank (5), a first drainage pipe (503) is fixedly connected to the liquid outlet port of the first submersible pump (502), a vertical pump (504) is arranged above the first hot water temporary storage tank (6), the other end of the first drainage pipe (503) is fixedly connected to the liquid extraction port of the vertical pump (504), a second drainage pipe (505) is fixedly connected to the liquid outlet port of the vertical pump (504), the upper end of the second drainage pipe (505) passes through the lower end of the second water collecting tank (7) and extends to The interior of the second water collecting tank (7); A first heat preservation component is arranged on the first hot water temporary storage tank (6), and the first heat preservation component comprises a first heat preservation tank (601), a first centrifugal pump (602) and a first return pipe (603); the upper end pipeline of the first water collecting tank (5) is connected to the first hot water temporary storage tank (6), the inner wall of the first hot water temporary storage tank (6) is arranged with the first heat preservation tank (601), the interior of the first heat preservation tank (601) is interconnected with the interior of the first hot water temporary storage tank (6), the upper end of the first hot water temporary storage tank (6) is arranged with a first centrifugal pump (602), the water pumping end pipeline of the first centrifugal pump (602) is connected to the water outlet pipeline of the first hot water temporary storage tank (6), the first return pipe (603) is fixedly connected to the water outlet port of the first centrifugal pump (602), and the other end of the first return pipe (603) passes through the upper end of the first water collecting tank (5) and extends to the upper inner wall of the first water collecting tank (5).
2. The high-efficiency integrated geothermal unit based on mid-deep geothermal heat according to claim 1 is characterized by: The heating component comprises a second bracket (701), a second submersible pump (702) and a water supply riser (703); the second bracket (701) is fixedly connected to the upper end of the second water collecting tank (7); the second submersible pump (702) is fixedly connected to the second bracket (701); the pumping end of the second submersible pump (702) is located inside the second water collecting tank (7); the upper end of the second water collecting tank (7) is fixedly connected to the water supply riser (703); the upper end of the water supply riser (703) passes through the bottom end of the second hot water temporary storage tank (8) and extends to the inside of the second hot water temporary storage tank (8).
3. The high-efficiency integrated geothermal unit based on mid-deep geothermal energy according to claim 1 is characterized in that: The second heat preservation component comprises a second heat preservation box (801), a second centrifugal pump (802) and a second return water pipe (803); the second heat preservation box (801) is arranged on the inner wall of the second hot water temporary storage box (8), and the interior of the second heat preservation box (801) is communicated with the internal space of the second hot water temporary storage box (8).
4. The high-efficiency integrated geothermal unit based on mid-deep geothermal energy according to claim 1 is characterized in that: The second liquid pumping assembly comprises a first water pump (901), a first water pumping pipe (902), a third drainage pipe (903), a second water pump (904), a second water pumping pipe (905), a water supply pipe (906), a first solenoid valve (907) and a fourth drainage pipe (908); the first water pump (901) and the second water pump (904) are fixedly connected to the upper end of the bearing plate (9); the first water pumping pipe (902) is fixedly connected to the liquid pumping port of the first water pump (901); the other end of the first water pumping pipe (902) passes through the outer wall of the second water collecting tank (7) and extends to the inner wall of the second water collecting tank (7); the third drainage pipe (903) is fixedly connected to the water outlet port of the first water pump (901); the other end of the third drainage pipe (903) passes through the water storage tank (1 The upper end of the second pump (904) extends to the interior of the water storage tank (11); a second pumping pipe (905) is fixedly connected to the pumping port of the second pump (904); the other end of the second pumping pipe (905) passes through the upper end of the second water collecting tank (7) and extends to the interior of the second water collecting tank (7); a water supply pipe (906) is fixedly connected to the pumping port of the second pump (904); the other end of the water supply pipe (906) passes through the side wall of the water supply tank (10) and extends to the interior of the water supply tank (10); a first solenoid valve (907) is provided on the water supply pipe (906); a fourth drainage pipe (908) is fixedly connected to the liquid outlet port of the second pump (904); the other end of the fourth drainage pipe (908) passes through the upper end of the water storage tank (11) and extends to the interior of the water storage tank (11).
5. The high-efficiency integrated geothermal unit based on mid-deep geothermal energy according to claim 4 is characterized in that: The end of the water supply pipe (906) entering the water supply box (10) is fifty centimeters away from the inner wall of the water supply box (10) closest to the supporting plate (9).
6. The high-efficiency integrated geothermal unit based on mid-deep geothermal energy according to claim 1 is characterized in that: A cylinder (1001) is fixedly connected to the side end of the water supply tank (10); an output shaft of the cylinder (1001) passes through the outer wall of the water supply tank (10) and is fixedly connected to a push plate (1002); an inner wall of the water supply tank (10) close to one end of the supporting plate (9) is fixedly connected to a liquid level sensor (1005); a water supply pipe (1003) is provided at the upper end of the water supply tank (10); and a second solenoid valve (1004) is provided on the water supply pipe (1003).
7. The high-efficiency integrated geothermal unit based on mid-deep geothermal energy according to claim 6 is characterized by: The side wall of the push plate (1002) is made of hard rubber material, and the center of the push plate (1002) is made of stainless steel.
8. The high-efficiency integrated geothermal unit based on mid-deep geothermal energy according to claim 1 is characterized by: The third heat preservation box (12) is provided with a heat preservation component, which includes a first heat preservation cylinder (1201), The second heat-insulating tube (1202), the third heat-insulating tube (1203), the through hole (1204) and the cross block (1205); the bottom surface of the inner wall of the third heat-insulating box (12) is fixedly connected with the first heat-insulating tube (1201), the second heat-insulating tube (1202) and the third heat-insulating tube (1203); the first heat-insulating tube (1201), the second heat-insulating tube (1202) and the third heat-insulating tube (1203) are all made of aluminum-iron alloy; the side walls of the first heat-insulating tube (1201), the second heat-insulating tube (1202) and the third heat-insulating tube (1203) are all penetrated with evenly distributed through holes (1204).
9. The high-efficiency integrated geothermal unit based on mid-deep geothermal energy according to claim 8 is characterized in that: A cross block (1205) is fixedly connected to the bottom surface of the inner wall of the third heat-insulating box (12), and the four ends of the cross block (1205) pass through the third heat-insulating tube (1203) and the second heat-insulating tube (1202) and are fixedly connected to the inner wall of the first heat-insulating tube (1201).
10. The high-efficiency integrated geothermal unit based on mid-deep geothermal energy according to claim 9, characterized in that: The cross block (1205) is made of stainless steel, the center point of the cross block (1205) is located on the central axis of the third insulation box (12), and each pipeline is provided with a valve body.
Citation Information
Patent Citations
Multilayer-sleeve-formed temperature gradient control structure for crystal growth and method thereof
CN103243378A
Light multifunctional industrial kiln wall structure with composite layers
CN103423998A
Reverse slope tunnel construction drainage system
CN110410143A
Ball float valve type automatic sealed water tank water filling equipment for pump station
CN202250890U
Geothermal energy gradient utilization circulating device
CN220135760U