Land wind turbine generator layout site selection method and device, storage medium and related equipment

By building a maximum coverage site selection model and optimizing the solution using genetic algorithm, combining multiple factors to determine the optimal site selection point for onshore wind turbines, the problems of site selection accuracy and efficiency in the existing technology are solved, and efficient The accurate layout of wind power units reduces risks and costs and promotes the sustainable development of wind power projects.

CN119026750APending Publication Date: 2024-11-26GUANGZHOU POWER SUPPLY BUREAU GUANGDONG POWER GRID CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411243574.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The existing onshore wind turbine layout site selection methods cannot improve the accuracy and efficiency of site selection, and usually require a large amount of computing resources and time. The parameter setting of the optimization algorithm has a great impact on the results.

Method used

By determining the population distribution, land suitability, road accessibility and onshore wind turbine installation and maintenance costs of the study area, a maximum coverage site selection model is built, and the genetic algorithm is used for optimization and solution to determine the optimal site selection point, comprehensively Consider multiple factors to improve site selection accuracy and efficiency.

Benefits of technology

Improve the utilization rate of wind energy resources, reduce the risks and costs of improper site selection, reduce the calculation and analysis workload, improve site selection efficiency and accuracy, avoid adverse impacts on the environment and society, and realize the economic Win-win situations of benefits and environmental benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119026750A_ABST
    Figure CN119026750A_ABST
Patent Text Reader

Abstract

According to the land wind turbine generator layout site selection method and device, the storage medium and the related equipment provided by the invention, during site selection, the land wind turbine generator demand point of the research area can be determined according to the population distribution condition, the land suitability, the road accessibility and the land wind turbine generator installation and maintenance cost of the research area; therefore, the utilization rate of wind energy resources is improved, and the risk and the cost caused by improper site selection are also remarkably reduced; then, according to the land wind turbine generator facility points and the land wind turbine generator demand points, a land wind turbine generator maximum coverage site selection model can be constructed, and after the land wind turbine generator maximum coverage site selection model is optimized and solved by using a genetic algorithm, an optimal site selection point in the land wind turbine generator facility points is determined according to a solving result. According to the process, the workload of calculation and analysis can be further reduced, and the site selection efficiency and the site selection accuracy can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of energy planning, and in particular to a method, device, storage medium and related equipment for selecting a layout of an onshore wind turbine generator system. Background Art

[0002] As a clean and renewable energy, wind energy is widely used in my country. However, the layout and site selection of onshore wind turbines is a complex and multi-factor comprehensive process, which is directly related to the investment benefits, operating efficiency and environmental impact of wind power projects. Selecting a superior geographical location to build wind turbines according to suitability is of great significance to the use and promotion of wind energy, promoting energy structure transformation and reducing greenhouse gas emissions.

[0003] At present, the layout and site selection methods for onshore wind turbines mainly include traditional site selection methods based on wind energy resource assessment and site selection methods based on optimization algorithms. Traditional site selection methods mainly rely on on-site wind measurement data, topographic analysis, and expert experience. Although they are feasible to a certain extent, they often have problems such as strong subjectivity, low evaluation accuracy, and difficulty in fully considering multiple factors. Site selection methods based on optimization algorithms can improve the accuracy of site selection to a certain extent, but they usually require a lot of computing resources and time, and the parameter settings of the optimization algorithm have a greater impact on the results. Summary of the invention

[0004] The purpose of the present application is to solve at least one of the above-mentioned technical defects, especially the technical defect that the layout and site selection method of onshore wind turbines in the prior art cannot improve the accuracy and efficiency of site selection.

[0005] The present application provides a method for selecting a site for an onshore wind turbine layout, the method comprising:

[0006] Determine the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs, and onshore wind turbine facility locations in the study area;

[0007] Determine the onshore wind turbine demand points in the study area based on the population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs in the study area;

[0008] Constructing a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points;

[0009] A genetic algorithm is used to optimize and solve the maximum coverage site selection model of the onshore wind turbine generator set, and the best site selection point among the onshore wind turbine generator set facility points is determined according to the solution result.

[0010] Optionally, determining the population distribution of the study area includes:

[0011] Obtain population data for the study area;

[0012] Performing raster calculation on the population data to obtain corresponding values, and extracting the values ​​into each fishing net point in the study area;

[0013] The data of each fishing network point is normalized to obtain the population distribution of the study area.

[0014] Optionally, determining the land suitability of the study area includes:

[0015] Obtain land use data for the study area;

[0016] The land use data is input into a pre-configured FLUS model to obtain the land suitability of the study area output by the FLUS model.

[0017] Optionally, determining the road accessibility of the study area includes:

[0018] Obtain road network data for the study area;

[0019] The road density corresponding to the road network data is calculated using a kernel density analysis tool, and the road accessibility of the study area is determined based on the road density.

[0020] Optionally, determining the demand points for onshore wind turbines in the study area according to population distribution, land suitability, road accessibility, and installation and maintenance costs of onshore wind turbines in the study area includes:

[0021] Determine the weights of population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs for each fishing site in the study area;

[0022] Calculate the weight value of each fishing network point based on the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs and corresponding weights of each fishing network point;

[0023] The pre-built onshore wind turbine fitness assessment model is used to assess the comprehensive suitability of each fishing net point according to the weight value of each fishing net point, and the assessment results are obtained;

[0024] According to the evaluation results, fishing net points that do not meet the preset conditions are screened out from various fishing net points, and fishing net points that meet the preset conditions are used as onshore wind turbine demand points in the study area.

[0025] Optionally, the constructing a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points includes:

[0026] Determine the facility point locations and facility quantity of the onshore wind turbine facility points, and the demand point locations and demand point quantity of the onshore wind turbine demand points;

[0027] The goal is to cover as many onshore wind turbine demand points as possible with as few onshore wind turbine facility points as possible, and a maximum coverage site selection model for onshore wind turbines is constructed based on the locations of the facility points, the number of facilities, the locations of the demand points and the number of demand points.

[0028] Optionally, the using of a genetic algorithm to optimize and solve the maximum coverage site selection model for the onshore wind turbine generator set, and determining the best site selection point among the onshore wind turbine generator set facility points according to the solution result, includes:

[0029] Determine the number of sites for onshore wind turbines;

[0030] After optimizing and solving the maximum coverage site selection model of the onshore wind turbine generator system using a genetic algorithm, a solution result is obtained;

[0031] According to the solution result and the number of site selections, the best site selection point among the onshore wind turbine facility points is determined.

[0032] The present application also provides an onshore wind turbine layout site selection device, comprising:

[0033] An indicator determination module is used to determine the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs, and onshore wind turbine facility locations in the study area;

[0034] A demand point determination module is used to determine the demand points of onshore wind turbines in the study area according to the population distribution, land suitability, road accessibility, and installation and maintenance costs of onshore wind turbines in the study area;

[0035] A site selection model building module, used to build a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points;

[0036] The site selection result determination module is used to optimize and solve the maximum coverage site selection model of the onshore wind turbine generator set by using a genetic algorithm, and determine the best site selection point among the onshore wind turbine generator set facility points according to the solution result.

[0037] The present application also provides a computer-readable storage medium, in which computer-readable instructions are stored. When the computer-readable instructions are executed by one or more processors, the one or more processors execute the steps of the onshore wind turbine layout and site selection method as described in any of the above embodiments.

[0038] The present application also provides a computer device, comprising: one or more processors, and a memory;

[0039] The memory stores computer-readable instructions, and when the computer-readable instructions are executed by the one or more processors, the steps of the onshore wind turbine layout site selection method as described in any one of the above embodiments are performed.

[0040] It can be seen from the above technical solutions that the embodiments of the present application have the following advantages:

[0041] The onshore wind turbine layout site selection method, device, storage medium and related equipment provided in the present application can first determine the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs, and onshore wind turbine facility points of the study area when selecting a site. In this way, the onshore wind turbine demand points in the study area can be determined based on the population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs of the study area. This process incorporates multiple factors such as wind speed, topography, soil conditions, environmental impacts, and infrastructure access into the site selection evaluation system. Through multi-factor comprehensive weight analysis, the comprehensive suitability of each candidate location is evaluated to determine the optimal layout plan, which not only improves the utilization of wind energy resources The utilization rate is increased, and the risks and costs caused by improper site selection are significantly reduced; then, the present application can construct a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points, and after optimizing and solving the maximum coverage site selection model for onshore wind turbines using a genetic algorithm, the best site selection point among the onshore wind turbine facility points is determined according to the solution results. In this process, the present application can not only efficiently evaluate and optimize a large number of candidate site selection schemes through the guidance of a genetic algorithm, but also because the present application has already determined the onshore wind turbine demand points in advance to quickly screen out candidate locations that do not meet the conditions and narrow the site selection scope, thereby further reducing the workload of calculation and analysis, and improving the site selection efficiency and site selection accuracy. In addition, the present application can effectively avoid adverse effects on the environment and society by comprehensively considering environmental factors such as ecological protection areas, residential areas, and landscape protection during the site selection process; for example, the present application can avoid ecologically fragile areas and densely populated areas during the site selection process, which not only protects the ecological environment, but also reduces noise, visual interference with residents' lives, and promotes the sustainable development of wind power projects. At the same time, this application optimizes the layout of wind turbines through scientific site selection, reduces the waste of land resources, improves land use efficiency, and achieves a win-win situation in economic and environmental benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0043] Figure 1 A schematic diagram of a flow chart of a method for selecting a site for a land-based sub-generator group layout provided in an embodiment of the present application;

[0044] Figure 2 A schematic diagram of a process for determining the demand points of onshore wind turbines in a study area provided in an embodiment of the present application;

[0045] Figure 3 A schematic diagram of the structure of a device for selecting a site for a layout of wind turbines on the road provided in an embodiment of the present application;

[0046] Figure 4 A schematic diagram of the internal structure of a computer device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0047] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0048] In one embodiment, Figure 1 As shown, Figure 1 A schematic diagram of a flow chart of a method for selecting a site for a land-based wind turbine layout provided in an embodiment of the present application; the present application provides a method for selecting a site for a land-based wind turbine layout, which may include:

[0049] S110: Determine the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs, and onshore wind turbine facility locations in the study area.

[0050] In this step, it is considered that the traditional site selection method for wind turbines usually only considers a single or a few factors, such as wind speed and terrain, and ignores key factors such as soil conditions, environmental impacts, and economic costs, resulting in less than ideal site selection results. The overall efficiency and stability of the wind farm cannot be fully guaranteed. This application adopts a comprehensive suitability assessment method, which incorporates multiple factors such as wind speed, terrain, soil conditions, environmental impacts, and infrastructure access into the site selection assessment system. Through multi-factor comprehensive weight analysis, the comprehensive suitability of each candidate location is evaluated to determine the optimal layout plan. This not only improves the utilization rate of wind energy resources, but also significantly reduces the risks and costs brought about by improper site selection.

[0051] Specifically, when the present application is conducting layout and site selection for onshore wind turbines, the population distribution, land suitability, road accessibility, installation and maintenance costs of onshore wind turbines in the study area can be determined first, and the onshore wind turbine facilities in the study area can be determined. In this way, a comprehensive assessment of the study area can be conducted through a variety of factors, and the demand points for onshore wind turbines in the study area can be determined. Then, combined with the onshore wind turbine facilities, the optimal site selection point can be determined.

[0052] It is understandable that in order to improve the accuracy of site selection, this application comprehensively considers the topography, climate, transportation facilities and other factors of the study area when selecting the site for onshore wind turbines. Among them, the terrain requirements for site selection first need to meet a certain height, for example, this height is designed in the airflow layer with the largest wind speed and wind flow, so as to ensure the operation of the wind turbine; secondly, the requirements for the plane position of the site selection point, which requires that the wind turbine and infrastructure related to the wind turbine be established at this point to ensure subsequent power generation and storage; finally, the site selection point should be avoided from being affected by other obstructions, so as not to reduce the power generation efficiency of the wind turbine and the safety of the wind turbine.

[0053] In addition, the impact of climate on wind turbines is first the annual average wind speed at the site, which directly determines the power generation efficiency of wind turbines; second is the annual rainfall in the area, which affects the maintenance and use time of wind turbines. The demand for transportation facilities is to ensure that the site can be reached smoothly during the construction of wind turbines to complete the transportation of wind turbine equipment. In addition, the supply of electricity required by the infrastructure when the wind turbines are running must be guaranteed; a large amount of water is used for heat dissipation during wind turbine maintenance, and the relationship between site selection and water sources must also be considered to facilitate the acquisition and transportation of water sources.

[0054] This application calculates the installation and maintenance costs of onshore wind turbines. The installation and maintenance costs of wind turbines mainly include equipment procurement, transportation, construction, labor costs, and maintenance material costs. Equipment procurement costs include the procurement costs of major equipment such as wind turbines, towers, blades, transformers, etc. Transportation costs refer to the costs of transporting equipment and materials to the installation site. Construction costs refer to the costs of construction personnel and infrastructure construction. Maintenance costs include regular fault detection, equipment upgrades, and fault repair costs. By constructing a calculation model to calculate the installation and maintenance costs, it can be used as an economic indicator to measure onshore wind turbines.

[0055] In summary, this application can conduct literature research and use population data to analyze population factors, and then determine the population distribution in the study area, so as to ensure the rationality of the layout of wind turbines for population density and distribution; it can also calculate the road network density index of the study area and analyze the traffic network factors to ensure that the layout of wind turbines has good traffic accessibility; it can also conduct a detailed analysis of the current status of land use types based on remote sensing image supervision classification, use the FLUS model to predict land use change trends, and evaluate land suitability to ensure that the layout of wind turbines is consistent with the current land use status and future trends. In addition, this application can also conduct cost factor analysis from aspects such as installation cost and maintenance cost through research data to ensure the economic feasibility of the layout plan. This multi-source big data comprehensive analysis method provides solid data support and theoretical basis for the scientific layout of wind turbines.

[0056] Furthermore, when determining the onshore wind turbine facility points in the study area, the present application can obtain the POI data of the onshore wind turbine through the existing open platform. The POI data includes but is not limited to the address, longitude and latitude of the wind power station, and the construction time. The present application can determine the onshore wind turbine facility points in the study area based on the obtained POI data. In addition, since the open platform is usually maintained by a professional map data provider and has high accuracy and reliability, the present application can more accurately locate the actual position of the wind turbine by calling its interface to obtain the POI data of the onshore wind turbine. Compared with the traditional field survey and manual data collection method, this method can quickly obtain a large amount of onshore wind turbine POI data without investing a lot of manpower and time costs.

[0057] S120: Determine the onshore wind turbine demand points in the study area based on the population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs in the study area.

[0058] In this step, after determining the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs, and onshore wind turbine facility points in the study area through S110, this application can determine the onshore wind turbine demand points in the study area based on the population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs in the study area. This can quickly screen out candidate locations that do not meet the conditions and narrow the site selection range, thereby greatly reducing the workload of calculation and analysis and improving site selection efficiency.

[0059] It should be noted that, although the site selection methods based on optimization algorithms in the prior art, such as genetic algorithms, particle swarm algorithms, etc., can improve the accuracy and efficiency of site selection to a certain extent, they usually require a large amount of computing resources and time, and the parameter settings of the optimization algorithm have a greater impact on the results. Based on this, the present application can preliminarily screen the candidate sites in the study area through the obtained multiple factors, which can not only narrow the site selection range, but also reduce the calculation time and cost of the final site selection.

[0060] Specifically, when determining the onshore wind turbine demand points in the study area, the present application can first determine the population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs of each candidate location in the study area, and then explore the impact of the population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs of each candidate location on the wind turbine layout, and quantify the impact size as an indicator for evaluating the suitability of wind turbines. Then, the present application can preliminarily screen out candidate locations with better suitability as onshore wind turbine demand points in the study area based on the impact size of each candidate location, and use the onshore wind turbine demand points and onshore wind turbine facility points to determine the optimal site selection point.

[0061] S130: Construct a maximum coverage site selection model for onshore wind turbines based on onshore wind turbine facility points and onshore wind turbine demand points.

[0062] S140: Using a genetic algorithm to optimize and solve the maximum coverage site selection model for onshore wind turbines, and determining the best site selection point among the onshore wind turbine facility points based on the solution results.

[0063] In the above steps, after the onshore wind turbine demand points in the study area are determined through S120, the present application can construct a maximum coverage site selection model for onshore wind turbines based on the onshore wind turbine facility points and the onshore wind turbine demand points, and optimize and solve the maximum coverage site selection model for onshore wind turbines to determine the final optimal site selection point.

[0064] Specifically, after determining the onshore wind turbine facility points and onshore wind turbine demand points, the present application can construct an onshore wind turbine maximum coverage site selection model based on the facility point locations and facility quantity of the onshore wind turbine facility points, and the demand point locations and demand point quantity of the onshore wind turbine demand points. By optimizing and solving the model, the optimal site selection point can be obtained for covering as many onshore wind turbine demand points as possible with as few onshore wind turbine facility points as possible.

[0065] Among them, when this application uses a genetic algorithm to solve the maximum coverage model problem, the specific steps are as follows:

[0066] 1. Encoding: Each solution (i.e. chromosome) can be represented by a binary string with a length of (i.e. the number of subsets), each gene position corresponds to a subset If the value of a position is 1, it means that the subset is selected; if the value is 0, it means that it is not selected.

[0067] 2. Initialize the population: Randomly generate a set of chromosomes (solutions) to form the initial population, where each chromosome represents a possible solution.

[0068] 3. Fitness function: The fitness function is used to evaluate the quality of each chromosome. For the maximum coverage problem, the fitness function is usually defined as the total number of elements covered by the selected subset. It is necessary to pay attention to the constraint that the number of selected subsets cannot exceed k.

[0069] 4. Selection: Select chromosomes for reproduction based on fitness values. Chromosomes with higher fitness have a greater probability of being selected.

[0070] 5. Crossover: New chromosomes are generated through the crossover operation, which combines two parent chromosomes to produce offspring, which inherit part of the genes of the parent chromosomes.

[0071] 6. Mutation: Randomly mutate chromosomes and change the positions of certain genes. The mutation operation introduces new solution space to prevent the algorithm from falling into local optimality.

[0072] 7. Evolution: Generate a new generation of population and replace the old one, repeat the selection, crossover and mutation steps. After many generations of evolution, the fitness of chromosomes in the population gradually increases.

[0073] 8. Termination condition: When the preset maximum number of iterations is reached or the fitness value in the population no longer increases significantly, the algorithm terminates and the chromosome with the highest fitness in the current population is selected as the final solution to obtain the optimal solution for site selection.

[0074] In a specific implementation method, the present application demonstrates better technical effects and practical application value. For example, in the site selection process of onshore wind farms in Guangdong, the layout site selection method of the present application can be applied for field verification. The results show that the layout scheme of wind turbines selected by suitability assessment and optimization algorithm has increased the power generation efficiency of wind turbines by an average of more than 15% compared with traditional methods. At the same time, due to the more reasonable site selection, the maintenance cost of the wind farm is also significantly reduced. In addition, through comparative analysis, it is found that the wind turbines selected by the layout site selection method of this application have more stable wind speed conditions in the area where they are located, more suitable geological conditions, and less environmental impact, ensuring the long-term and efficient operation of the wind farm.

[0075] In the above embodiment, when selecting a site, the population distribution, land suitability, road accessibility, installation and maintenance costs of onshore wind turbines, and onshore wind turbine facility points of the study area can be determined first. In this way, the onshore wind turbine demand points in the study area can be determined based on the population distribution, land suitability, road accessibility, and installation and maintenance costs of onshore wind turbines in the study area. This process incorporates multiple factors such as wind speed, topography, soil conditions, environmental impacts, and infrastructure access into the site selection evaluation system. Through multi-factor comprehensive weight analysis, the comprehensive suitability of each candidate location is evaluated to determine the optimal layout plan, which not only improves the utilization rate of wind energy resources, but also significantly reduces improper site selection. The risks and costs brought by it; then, the present application can construct a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points, and use the genetic algorithm to optimize and solve the maximum coverage site selection model for onshore wind turbines, and then determine the best site selection point among the onshore wind turbine facility points according to the solution results. In this process, the present application can not only efficiently evaluate and optimize a large number of candidate site selection schemes through the guidance of the genetic algorithm, but also because the present application has already determined the onshore wind turbine demand points in advance to quickly screen out the candidate locations that do not meet the conditions and narrow the site selection scope, thereby further reducing the workload of calculation and analysis, and improving the site selection efficiency and site selection accuracy. In addition, the present application can effectively avoid adverse effects on the environment and society by comprehensively considering environmental factors such as ecological protection areas, residential areas, and landscape protection during the site selection process; for example, the present application can avoid ecologically fragile areas and densely populated areas during the site selection process, which not only protects the ecological environment, but also reduces the interference of noise, vision, etc. on residents' lives, and promotes the sustainable development of wind power projects. At the same time, this application optimizes the layout of wind turbines through scientific site selection, reduces the waste of land resources, improves land use efficiency, and achieves a win-win situation in economic and environmental benefits.

[0076] In one embodiment, determining the population distribution of the study area in S110 may include:

[0077] S111: Obtain population data for the study area.

[0078] S112: Performing raster calculation on the population data to obtain corresponding values, and extracting the values ​​into each fishing net point in the study area.

[0079] S113: Normalizing the data of each fishing network point to obtain the population distribution of the study area.

[0080] In this embodiment, when determining the population distribution of the study area, the population data of the study area can be obtained first, and then the population data can be raster calculated. When calculating the raster, the type of raster calculation to be performed can be determined first. Common calculation types include arithmetic operations (such as addition, subtraction, multiplication, and division), logical operations (such as AND, OR, and NOT), and statistical operations (such as average, maximum, minimum, standard deviation, etc.). For example, if you want to calculate the sum of two raster data, you can choose addition operations; if you want to determine the number of pixels in a certain area whose raster values ​​are greater than a specific threshold, you can perform logical operations and statistical operations. Then, according to the calculation type and data characteristics, select a suitable raster calculation tool. Common geographic information system software (such as ArcGIS, QGIS, etc.) provides a wealth of raster calculation functions. You can also use programming languages ​​(such as Python's rasterio library, R language's raster package, etc.) to perform customized raster calculations. Then, according to the selected calculation tool and calculation type, set the corresponding calculation parameters, which include but are not limited to the path of the input raster data, the calculation expression, the name and path of the output raster data, etc. Finally, you can use the selected calculation tool to perform raster calculations. During the calculation process, the tool will perform corresponding mathematical operations on the input raster data according to the set parameters and generate output raster data.

[0081] After the output raster data is generated, the raster data can be extracted to points to measure the relative size and obtain the corresponding numerical value. Then, the present application can extract the numerical value to each fishing net point in the study area, and normalize the data of each fishing net point to obtain the population distribution of the study area. Since fishing net points usually represent specific geographical locations or sampling points, extracting raster data to fishing net points can achieve accurate positioning analysis of specific areas. In this way, the specific data value of the location of the fishing net point can be obtained, thereby providing accurate data support for the site selection of onshore wind turbines. Different raster data may have different dimensions and numerical ranges. The present application normalizes the data of each fishing net point to eliminate these dimensional differences and enable different data to be compared and analyzed on the same scale.

[0082] In one embodiment, determining the land suitability of the study area in S110 may include:

[0083] S114: Obtain land use data for the study area.

[0084] S115: Input the land use data into a pre-configured FLUS model to obtain the land suitability of the study area output by the FLUS model.

[0085] In this embodiment, when determining the land suitability of the study area, the land use data of the study area can be obtained first, and then the land use change analysis of the study area is performed based on the FLUS model, and a suitability assessment is performed to determine the land suitability of the study area.

[0086] In a specific implementation, the present application can calibrate the parameters of the FLUS model based on historical data and actual observation results to ensure the accuracy of the model, and then use the FLUS model to simulate and predict future land use changes. The model will generate land use change maps under different scenarios, which can be used to analyze possible future change trends, analyze the simulation results, and compare them with actual observation data to verify the accuracy of the model. In addition, by adjusting the model parameters, the accuracy of the simulation can be further improved. The simulation results of the FLUS model can provide decision-making support for regional land use management and planning, so as to formulate more scientific land use policies and evaluate the site selection of wind turbines based on the corresponding prediction results.

[0087] In one embodiment, determining the road accessibility of the study area in S110 may include:

[0088] S116: Obtain road network data of the study area.

[0089] S117: Calculate the road density corresponding to the road network data using a kernel density analysis tool, and determine the road accessibility of the study area based on the road density.

[0090] In this embodiment, when determining the road accessibility of the study area, the road network data of the study area can be obtained first, and then the kernel density analysis tool is used to calculate the road density corresponding to the road network data, and the road accessibility of the study area is determined based on the road density.

[0091] Specifically, the application can input the acquired road network data into ArcGIS for processing and analysis, and use the kernel density analysis tool to calculate the corresponding road density. In addition, since there is a close relationship between road network density and road accessibility, the higher the road network density, the denser the distribution of roads. A high-density road network helps support a multi-modal transportation system, shortens driving distances, and thus makes roads more accessible. Therefore, the application can use road density as a measure of road accessibility.

[0092] In one embodiment, Figure 2 As shown, Figure 2A flow chart of determining the demand points of onshore wind turbines in a study area provided in an embodiment of the present application; in S120, determining the demand points of onshore wind turbines in the study area according to the population distribution, land suitability, road accessibility, and installation and maintenance costs of onshore wind turbines in the study area may include:

[0093] S121: Determine the weights of population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs for each fishing site in the study area.

[0094] S122: Calculate the weight value of each fishing network point according to the population distribution, land suitability, road accessibility, installation and maintenance cost of onshore wind turbines and corresponding weights of each fishing network point.

[0095] S123: Using the pre-constructed onshore wind turbine fitness assessment model, the comprehensive suitability of each fishing network point is assessed according to the weight value of each fishing network point, and an assessment result is obtained.

[0096] S124: Screen out fishing net points that do not meet the preset conditions from various fishing net points according to the evaluation results, and use the fishing net points that meet the preset conditions as the onshore wind turbine demand points in the study area.

[0097] In this embodiment, when determining the demand points for onshore wind turbines in the study area, the population distribution, land suitability, road accessibility, and the weights of the installation and maintenance costs of onshore wind turbines for each fishing net point in the study area can be determined first, and then a weighted sum can be performed to obtain the weight value of each fishing net point. The present application can use the weight value of each fishing net point as an indicator for evaluating the suitability of the wind turbine, and construct an onshore wind turbine fitness evaluation model. The onshore wind turbine fitness evaluation model is then used to evaluate the comprehensive suitability of each fishing net point according to the weight value of each fishing net point, and an evaluation result is obtained. Finally, the present application can screen out fishing net points that do not meet the preset conditions from each fishing net point according to the evaluation result, and use the fishing net points that meet the preset conditions as the onshore wind turbine demand points in the study area.

[0098] Among them, when determining the onshore wind turbine demand points in the study area, the present application can pre-set preset conditions, and the preset conditions can be a suitability threshold related to the comprehensive suitability. When the weight value of one or more fishing net points exceeds the suitability threshold, it means that the comprehensive suitability of the fishing net point is relatively high, and it can be used as the onshore wind turbine demand point in the study area; and when the weight value of one or more fishing net points does not exceed the suitability threshold, it means that the comprehensive suitability of the one or more fishing net points is relatively low, and it is not suitable to be the onshore wind turbine demand point in the study area. This can not only narrow the site selection scope, but also reduce the calculation time and calculation cost of the final site selection.

[0099] In one embodiment, constructing a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points in S130 may include:

[0100] S131: Determine the facility point locations and facility quantity of the onshore wind turbine facility points, and the demand point locations and demand point quantity of the onshore wind turbine demand points.

[0101] S132: With the goal of covering as many onshore wind turbine demand points as possible with as few onshore wind turbine facility points as possible, a maximum coverage site selection model for onshore wind turbines is constructed based on the locations of the facility points, the number of facilities, the locations of the demand points, and the number of the demand points.

[0102] In this embodiment, when constructing the maximum coverage site selection model for onshore wind turbines, the respective facility point locations, facility numbers, and demand point locations and demand point numbers can be determined based on the acquired onshore wind turbine facility points and onshore wind turbine demand points. In this way, the goal is to cover as many onshore wind turbine demand points as possible with as few onshore wind turbine facility points as possible, with the facility point locations, facility numbers, demand point locations and demand point numbers as constraints, and the maximum coverage site selection model for onshore wind turbines can be constructed based on the goals and constraints.

[0103] In a specific implementation, the present application constructs a maximum coverage site selection model for onshore wind turbines based on the location and number of onshore wind turbine facility points, the location and number of onshore wind turbine demand points, and the goal of covering as many onshore wind turbine demand points as possible with as few onshore wind turbine facility points as possible. The formula is as follows:

[0104]

[0105]

[0106]

[0107]

[0108] Among them, Q represents the maximum value of the covered onshore wind turbine demand points, I represents the demand point set, and J represents the facility point set; when d ij When ≤R, c ij =1, indicating that facility j can cover demand point i; otherwise, c ij = 0, R is the service radius of the facility point, d ij represents the distance from demand point i to facility point j; K is the number of facilities that can be selected; x jIndicates whether the facility is located at j, where 1 indicates location selection and 0 indicates no location selection; y i Indicates whether demand point i is covered, where 1 indicates coverage and 0 indicates non-coverage.

[0109] In one embodiment, in S140, using a genetic algorithm to optimize and solve the maximum coverage site selection model of the onshore wind turbine generator set, and determining the best site selection point among the onshore wind turbine generator set facility points according to the solution result, may include:

[0110] S141: Determine the number of sites for onshore wind turbines.

[0111] S142: After optimizing and solving the maximum coverage site selection model for the onshore wind turbine generator system using a genetic algorithm, a solution result is obtained.

[0112] S143: Determine the best site selection point among the onshore wind turbine facility points according to the solution result and the number of site selection points.

[0113] In this embodiment, before using the genetic algorithm to optimize and solve the maximum coverage site selection model for onshore wind turbines, the number of sites for onshore wind turbines can be determined first, and then the optimization solution is performed, and then the best site selection point among the onshore wind turbine facility points is determined based on the solution result and the number of sites.

[0114] Among them, when determining the number of sites for onshore wind turbines, the present application can use ArcGIS spatial analysis methods and model evaluation to determine the number of sites for onshore wind turbines, and after comparing with the number of existing wind power stations, the number of sites can be assumed to be 30, and experiments with facility numbers of 20 and 40 can be compared. The experimental results show that 30 is the balance point between coverage and number of sites, so the present application can determine 30 as the number of sites for onshore wind turbines.

[0115] Next, this application can use a multi-objective genetic intelligence algorithm to optimize the layout of onshore wind turbines and generate the optimal layout plan, thereby achieving a comprehensive balance between wind resource utilization, environmental protection, and economic benefits. This method combines theoretical analysis with experimental analysis, qualitative analysis with quantitative analysis, to ensure the comprehensiveness of the research method and the reliability of the results. Through suitability assessment and dynamic adjustment mechanisms, the layout plan of wind turbines can be continuously optimized under environmental changes and data updates, ensuring the long-term effectiveness and feasibility of the layout.

[0116] The following is a description of an onshore wind turbine layout site selection device provided in an embodiment of the present application. The onshore wind turbine layout site selection device described below and the onshore wind turbine layout site selection method described above can be referenced to each other.

[0117] In one embodiment, Figure 3 As shown, Figure 3 A schematic diagram of a wind turbine layout site selection device provided in an embodiment of the present application; the present application also provides an onshore wind turbine layout site selection device, which may include an indicator determination module 210, a demand point determination module 220, a site selection model construction module 230, and a site selection result determination module 240, which specifically include the following:

[0118] The indicator determination module 210 is used to determine the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs, and onshore wind turbine facility locations in the study area.

[0119] The demand point determination module 220 is used to determine the demand points of onshore wind turbines in the study area according to the population distribution, land suitability, road accessibility, and installation and maintenance costs of onshore wind turbines in the study area.

[0120] The site selection model building module 230 is used to build a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points.

[0121] The site selection result determination module 240 is used to optimize and solve the maximum coverage site selection model of the onshore wind turbine generator set by using a genetic algorithm, and determine the best site selection point among the onshore wind turbine generator set facility points according to the solution result.

[0122] In the above embodiment, when selecting a site, the population distribution, land suitability, road accessibility, installation and maintenance costs of onshore wind turbines, and onshore wind turbine facility points of the study area can be determined first. In this way, the onshore wind turbine demand points in the study area can be determined based on the population distribution, land suitability, road accessibility, and installation and maintenance costs of onshore wind turbines in the study area. This process incorporates multiple factors such as wind speed, topography, soil conditions, environmental impacts, and infrastructure access into the site selection evaluation system. Through multi-factor comprehensive weight analysis, the comprehensive suitability of each candidate location is evaluated to determine the optimal layout plan, which not only improves the utilization rate of wind energy resources, but also significantly reduces improper site selection. The risks and costs brought by it; then, the present application can construct a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points, and use the genetic algorithm to optimize and solve the maximum coverage site selection model for onshore wind turbines, and then determine the best site selection point among the onshore wind turbine facility points according to the solution results. In this process, the present application can not only efficiently evaluate and optimize a large number of candidate site selection schemes through the guidance of the genetic algorithm, but also because the present application has already determined the onshore wind turbine demand points in advance to quickly screen out the candidate locations that do not meet the conditions and narrow the site selection scope, thereby further reducing the workload of calculation and analysis, and improving the site selection efficiency and site selection accuracy. In addition, the present application can effectively avoid adverse effects on the environment and society by comprehensively considering environmental factors such as ecological protection areas, residential areas, and landscape protection during the site selection process; for example, the present application can avoid ecologically fragile areas and densely populated areas during the site selection process, which not only protects the ecological environment, but also reduces the interference of noise, vision, etc. on residents' lives, and promotes the sustainable development of wind power projects. At the same time, this application optimizes the layout of wind turbines through scientific site selection, reduces the waste of land resources, improves land use efficiency, and achieves a win-win situation in economic and environmental benefits.

[0123] In one embodiment, the present application also provides a computer-readable storage medium, which stores computer-readable instructions. When the computer-readable instructions are executed by one or more processors, the one or more processors execute the steps of the onshore wind turbine layout and site selection method as described in any of the above embodiments.

[0124] In one embodiment, the present application also provides a computer device, including: one or more processors, and a memory.

[0125] The memory stores computer-readable instructions, and when the computer-readable instructions are executed by the one or more processors, the steps of the onshore wind turbine layout site selection method as described in any one of the above embodiments are performed.

[0126] Indicatively, Figure 4 As shown, Figure 4 This is a schematic diagram of the internal structure of a computer device provided in an embodiment of the present application. The computer device 300 may be provided as a server. Figure 4 The computer device 300 includes a processing component 302, which further includes one or more processors, and a memory resource represented by a memory 301, for storing instructions executable by the processing component 302, such as an application. The application stored in the memory 301 may include one or more modules, each corresponding to a set of instructions. In addition, the processing component 302 is configured to execute instructions to perform the onshore wind turbine layout site selection method of any of the above embodiments.

[0127] The computer device 300 may further include a power supply component 303 configured to perform power management of the computer device 300, a wired or wireless network interface 304 configured to connect the computer device 300 to a network, and an input / output (I / O) interface 305. The computer device 300 may operate based on an operating system stored in the memory 301, such as Windows Server TM, Mac OS X TM, Unix TM, Linux TM, Free BSD TM, or the like.

[0128] Those skilled in the art will understand that Figure 4 The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.

[0129] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

[0130] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The various embodiments can be combined as needed, and the same or similar parts can refer to each other.

[0131] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A method for selecting a site for an onshore wind turbine layout, characterized in that: The method comprises: Determine the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs, and onshore wind turbine facility locations in the study area; Determine the onshore wind turbine demand points in the study area based on the population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs in the study area; Constructing a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points; A genetic algorithm is used to optimize and solve the maximum coverage site selection model of the onshore wind turbine generator set, and the best site selection point among the onshore wind turbine generator set facility points is determined according to the solution result.

2. The method for selecting the layout and site of an onshore wind turbine generator system according to claim 1, characterized in that: The population distribution of the study area is determined, including: Obtain population data for the study area; Performing raster calculation on the population data to obtain corresponding values, and extracting the values ​​into each fishing net point in the study area; The data of each fishing network point is normalized to obtain the population distribution of the study area.

3. The method for selecting the layout and site of an onshore wind turbine generator system according to claim 1, characterized in that: Determine the land suitability of the study area, including: Obtain land use data for the study area; The land use data is input into a pre-configured FLUS model to obtain the land suitability of the study area output by the FLUS model.

4. The method for selecting the location of onshore wind turbines according to claim 1, characterized in that: Determine the road accessibility of the study area, including: Obtain road network data for the study area; The road density corresponding to the road network data is calculated using a kernel density analysis tool, and the road accessibility of the study area is determined based on the road density.

5. The method for selecting the layout and site of an onshore wind turbine generator system according to claim 1, characterized in that: Determining the onshore wind turbine demand points in the study area based on the population distribution, land suitability, road accessibility, and installation and maintenance costs of onshore wind turbines in the study area includes: Determine the weights of population distribution, land suitability, road accessibility, and onshore wind turbine installation and maintenance costs for each fishing site in the study area; Calculate the weight value of each fishing network point based on the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs and corresponding weights of each fishing network point; The pre-built onshore wind turbine fitness assessment model is used to assess the comprehensive suitability of each fishing net point according to the weight value of each fishing net point, and the assessment results are obtained; According to the evaluation results, fishing net points that do not meet the preset conditions are screened out from various fishing net points, and fishing net points that meet the preset conditions are used as onshore wind turbine demand points in the study area.

6. The method for selecting the layout and site of an onshore wind turbine generator system according to claim 1, characterized in that: The method of constructing a maximum coverage site selection model for onshore wind turbine generator sets according to the onshore wind turbine generator set facility points and the onshore wind turbine generator set demand points includes: Determine the facility point locations and facility quantity of the onshore wind turbine facility points, and the demand point locations and demand point quantity of the onshore wind turbine demand points; The goal is to cover as many onshore wind turbine demand points as possible with as few onshore wind turbine facility points as possible, and a maximum coverage site selection model for onshore wind turbines is constructed based on the locations of the facility points, the number of facilities, the locations of the demand points and the number of demand points.

7. The method for selecting the layout and site of an onshore wind turbine generator system according to claim 1, characterized in that: The method of using a genetic algorithm to optimize and solve the maximum coverage site selection model of the onshore wind turbine generator set, and determining the best site selection point among the onshore wind turbine generator set facility points according to the solution result, includes: Determine the number of sites for onshore wind turbines; After optimizing and solving the maximum coverage site selection model of the onshore wind turbine generator system using a genetic algorithm, a solution result is obtained; According to the solution result and the number of site selections, the best site selection point among the onshore wind turbine facility points is determined.

8. A device for selecting a site for an onshore wind turbine layout, characterized in that: include: An indicator determination module is used to determine the population distribution, land suitability, road accessibility, onshore wind turbine installation and maintenance costs, and onshore wind turbine facility locations in the study area; A demand point determination module is used to determine the demand points of onshore wind turbines in the study area according to the population distribution, land suitability, road accessibility, and installation and maintenance costs of onshore wind turbines in the study area; A site selection model building module, used to build a maximum coverage site selection model for onshore wind turbines according to the onshore wind turbine facility points and the onshore wind turbine demand points; The site selection result determination module is used to optimize and solve the maximum coverage site selection model of the onshore wind turbine generator set by using a genetic algorithm, and determine the best site selection point among the onshore wind turbine generator set facility points according to the solution result.

9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer-readable instructions, and when the computer-readable instructions are executed by one or more processors, the one or more processors execute the steps of the onshore wind turbine layout and site selection method as described in any one of claims 1 to 7.

10. A computer device, characterized in that: include: one or more processors, and memory; The memory stores computer-readable instructions, and when the computer-readable instructions are executed by the one or more processors, the steps of the method for selecting a site for the layout of an onshore wind turbine group as claimed in any one of claims 1 to 7 are performed.