Wind power hydrogen production feasibility evaluation model construction method and device, equipment and medium

By constructing a feasibility assessment model for the production of hydrogen by wind power, combining wind speed data and electricity data, the hydrogen generation rate is calculated, and a discount recovery and net present value assessment model is constructed, the feasibility assessment problem of hydrogen production technology in offshore wind farms is solved, and the feasibility assessment problem of hydrogen production technology is achieved. Effective assessment of the economy and sustainability of wind power hydrogen production projects.

CN119027000APending Publication Date: 2024-11-26GUANGZHOU POWER SUPPLY BUREAU GUANGDONG POWER GRID CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411121359.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

How to effectively evaluate the feasibility and economics of hydrogen production technology for special offshore wind farms, considering that wind energy is an intermittent energy and development is limited by the constraints of existing power grids and interconnection, and hydrogen is regarded as ensuring energy security and detachment. Ideal energy carrier for carbon.

Method used

Provide a feasibility assessment model for the production of hydrogen by wind power. By obtaining the wind speed data of offshore wind turbines, calculating the output power of the wind farm, combining the electric energy data of the hydrogen electrolytic plant to calculate the actual generation rate of hydrogen, and based on the system's initial capital expenditure, annual operation and maintenance expenditure and The preset discount rate constructs a discount recycling evaluation model and a net present value evaluation model, considering the value of capital over time.

Benefits of technology

By constructing a discount recovery evaluation model and a net present value evaluation model, the net cash flow of the wind power hydrogen production system can be discounted for each period, and an effective feasibility assessment is carried out, taking into account the economic and sustainability of the wind power hydrogen production project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119027000A_ABST
    Figure CN119027000A_ABST
Patent Text Reader

Abstract

The invention discloses a feasibility evaluation model construction method and device for wind power hydrogen production, equipment and a medium. The method comprises the steps of obtaining wind speed data, and calculating wind power plant output power according to the wind speed data; acquiring electric energy data, and calculating the actual hydrogen generation rate according to the electric energy data and the wind power plant output power; acquiring initial capital expenditure of the system and annual operation and maintenance expenditure of the system, and calculating annual hydrogen production income of the system according to the actual hydrogen generation rate; obtaining a preset discount rate, and constructing a discount recovery evaluation model according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate and the initial capital expenditure of the system; and obtaining the life cycle of the wind power plant, and constructing a net present value evaluation model according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate, the initial capital expenditure of the system and the life cycle of the wind power plant. The two evaluation models constructed by the invention can discount the net cash flow of the system in each period to consider the value of capital along with time, and can effectively evaluate the feasibility of wind power hydrogen production.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of wind power hydrogen production, and in particular to a method, device, equipment and medium for constructing a feasibility assessment model for wind power hydrogen production. Background Art

[0002] In many regions, fuels required for electricity generation, heating and cooling, and transportation account for approximately 20% to 40% of their total energy needs. These regions generate a large amount of electricity from natural gas, but natural gas supplies are currently dependent on other regions and are being depleted. Therefore, regional and regional energy security for electricity generation, heating, and transportation is becoming a pressing issue. Abundant offshore wind resources would enable many regions to achieve their renewable electricity targets without significant adverse impacts on the environment. However, because wind energy is an intermittent energy source, its development is also constrained by existing grids and limited interconnections, which also limits the electrification of the transportation sector.

[0003] Hydrogen is seen as an ideal energy carrier to ensure energy security and decarbonization, making significant contributions in the fields of transportation and thermal energy, and increasing the proportion of renewable energy. In order to unleash the potential of offshore wind energy and achieve decarbonization and energy security in electricity and other fields, offshore wind farms are used for hydrogen production, because these systems can be installed anywhere with good wind conditions, do not require grid connection, and can produce hydrogen without using fossil fuels or emitting greenhouse gases. Therefore, how to effectively evaluate the feasibility and economics of dedicated offshore wind farm hydrogen production technology is an urgent problem to be solved in this field. Summary of the invention

[0004] In view of this, the purpose of the present invention is to overcome the deficiencies in the prior art and to provide a method, device, equipment and medium for constructing a feasibility assessment model for wind power hydrogen production.

[0005] The present invention provides the following technical solutions:

[0006] In a first aspect, the present disclosure provides a method for constructing a feasibility assessment model for wind power hydrogen production, the method comprising:

[0007] Obtain wind speed data of multiple offshore wind turbines, calculate the output power of the corresponding offshore wind turbine according to each of the wind speed data, and aggregate the output power of each of the offshore wind turbines into the wind farm output power;

[0008] Acquiring electric energy data, determining a constraint condition of the wind farm output power according to the electric energy data, and calculating an actual hydrogen generation rate according to the constraint condition, the wind farm output power and the electric energy data;

[0009] Obtaining the initial capital expenditure of the system and the annual operation and maintenance expenditure of the system, and calculating the annual hydrogen production income of the system based on the actual hydrogen generation rate;

[0010] Obtaining a preset discount rate, calculating the average annual income of the system according to the annual operation and maintenance expenditure of the system and the annual hydrogen production income of the system, and constructing a discount recovery evaluation model according to the preset discount rate, the average annual income of the system and the initial capital expenditure of the system;

[0011] The life cycle of the wind farm is obtained, and a net present value evaluation model is constructed according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate, the initial capital expenditure of the system and the life cycle of the wind farm.

[0012] Optionally, the wind speed data includes a cut-in wind speed, a rated wind speed, a cut-out wind speed, a rated power, a rotor swept area, and an air density at a hub, and the calculating the corresponding offshore wind turbine output power according to each of the wind speed data includes:

[0013] When the real-time wind speed of the offshore wind turbine is less than the corresponding cut-in wind speed, or greater than or equal to the corresponding cut-out wind speed, the output power of the offshore wind turbine is zero;

[0014] When the real-time wind speed of the offshore wind turbine is greater than or equal to the corresponding cut-in wind speed and less than the corresponding rated wind speed, a preset power coefficient is obtained, and the output power of the offshore wind turbine is calculated according to the real-time wind speed of the offshore wind turbine, the air density at the hub, the rotor swept area and the preset power coefficient;

[0015] When the real-time wind speed of the offshore wind turbine is greater than or equal to the corresponding rated wind speed and less than the corresponding cut-out wind speed, the corresponding rated power is used as the output power of the offshore wind turbine.

[0016] Optionally, the constraint condition includes a first constraint condition and a second constraint condition, the electric energy data includes unit electric energy consumption of hydrogen electrolysis, loss electric energy consumption and a preset energy conversion efficiency of the hydrogen electrolysis plant, and the constraint condition for determining the output power of the wind farm according to the electric energy data includes:

[0017] Calculating a theoretical hydrogen generation rate according to the wind farm output power, the unit power consumption of hydrogen electrolysis, the lost power consumption and the preset energy conversion efficiency;

[0018] Calculating the rated power of the hydrogen electrolysis plant according to the theoretical hydrogen generation rate and the unit electric energy consumption of hydrogen electrolysis, and determining the lower limit power of the wind farm according to the rated power of the hydrogen electrolysis plant, and taking the lower limit power of the wind farm as the first constraint condition;

[0019] The second constraint condition is determined according to the rated power of the hydrogen electrolysis plant, the unit power consumption of the hydrogen electrolysis, the lost power consumption and the preset energy conversion efficiency.

[0020] Optionally, the calculating the actual hydrogen generation rate according to the constraint condition, the wind farm output power and the electric energy data includes:

[0021]

[0022] In the formula, is the actual generation rate of hydrogen, P farm (t) is the output power of the wind farm, E elec The electrical energy consumed by the hydrogen electrolysis unit, E pcl The electrical energy consumed for the losses, n conv is the preset energy conversion efficiency, is the rated power of the hydrogen electrolysis plant, P farm,low (t) is the first constraint condition, is the second constraint.

[0023] Optionally, obtaining the system initial capital expenditure and the system annual operation and maintenance expenditure includes:

[0024] Obtaining the capital expenditure of the wind farm, the total capital expenditure of the wind farm equipment, the total capital expenditure of the electrolysis device of the hydrogen electrolysis plant and the total capital expenditure of the hydrogen storage facilities of the hydrogen electrolysis plant, and taking the sum of the capital expenditure of the wind farm, the total capital expenditure of the wind farm equipment, the total capital expenditure of the electrolysis device of the hydrogen electrolysis plant and the total capital expenditure of the hydrogen storage facilities of the hydrogen electrolysis plant as the initial capital expenditure of the system;

[0025] The wind farm operating cost and the total operating cost of the electrolysis device of the hydrogen electrolysis plant are obtained, and the sum of the wind farm operating cost and the total operating cost of the electrolysis device of the hydrogen electrolysis plant is used as the annual operation and maintenance expenditure of the system.

[0026] Optionally, the discounted payback assessment model is:

[0027]

[0028] Where DPB is the discounted payback valuation model, R aa is the average annual income of the system, m is the preset discount rate, and C0 is the initial capital expenditure of the system.

[0029] Optionally, the net present value evaluation model is:

[0030]

[0031] Where, NPV is the net present value evaluation model, M is the life cycle of the wind farm, I1, I2, I N are the annual hydrogen production income of the system in the first year, the second year, and the Nth year, respectively. 1,O&M , C 2,O&M, C N,O&M They are the annual system operation and maintenance expenses in the 1st year, the 2nd year, and the Nth year respectively.

[0032] In a second aspect, an embodiment of the present disclosure provides a device for constructing a feasibility assessment model for wind power hydrogen production, which is applied to a wind power hydrogen production system, the system comprising a wind farm and a hydrogen electrolysis plant, and the device comprising:

[0033] A first calculation module is used to obtain wind speed data of multiple offshore wind turbines in the wind farm, calculate the output power of the corresponding offshore wind turbine according to each wind speed data, and aggregate the output power of each offshore wind turbine into the wind farm output power;

[0034] a second calculation module, configured to obtain electric energy data of the hydrogen electrolysis plant, determine the constraint conditions of the wind farm output power according to the electric energy data, and calculate the actual hydrogen generation rate according to the constraint conditions, the wind farm output power and the electric energy data;

[0035] The third calculation module is used to obtain the initial capital expenditure of the system and the annual operation and maintenance expenditure of the system, and calculate the annual hydrogen production income of the system according to the actual hydrogen generation rate;

[0036] The first construction module is used to obtain a preset discount rate, calculate the average annual income of the system according to the annual operation and maintenance expenditure of the system and the annual hydrogen production income of the system, and construct a discount recovery evaluation model according to the preset discount rate, the average annual income of the system and the initial capital expenditure of the system;

[0037] The second construction module is used to obtain the life cycle of the wind farm and construct a net present value evaluation model according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate, the initial capital expenditure of the system and the life cycle of the wind farm.

[0038] In a third aspect, a computer device is provided in an embodiment of the present disclosure, wherein the computer device includes a memory and a processor, wherein the memory stores a computer program, and when the processor executes the computer program, the steps of the method for constructing a feasibility assessment model for wind power hydrogen production described in the first aspect are implemented.

[0039] In a fourth aspect, a computer-readable storage medium is provided in an embodiment of the present disclosure, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the method for constructing a feasibility assessment model for wind power hydrogen production described in the first aspect are implemented.

[0040] Beneficial effects of this application:

[0041] The feasibility assessment model construction method for wind power hydrogen production provided in the embodiment of the present application obtains wind speed data of multiple offshore wind turbines, calculates the corresponding offshore wind turbine output power according to each wind speed data, and summarizes the output power of each offshore wind turbine into the wind farm output power; obtains electric energy data, determines the constraint conditions of the wind farm output power according to the electric energy data, and calculates the actual hydrogen generation rate according to the constraint conditions, the wind farm output power and the electric energy data; obtains the initial capital expenditure of the system and the annual operation and maintenance expenditure of the system, and calculates the annual hydrogen production income of the system according to the actual hydrogen generation rate; obtains a preset discount rate, calculates the average annual income of the system according to the annual operation and maintenance expenditure of the system and the annual hydrogen production income of the system, and constructs a discount recovery assessment model according to the preset discount rate, the average annual income of the system and the initial capital expenditure of the system; obtains the life cycle of the wind farm, and constructs a net present value assessment model according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate, the initial capital expenditure of the system and the life cycle of the wind farm. This application constructs a discounted payback assessment model and a net present value assessment model to discount the net cash flow of the wind power hydrogen production system in each period to consider the value of capital over time and effectively evaluate the feasibility of wind power hydrogen production.

[0042] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and understandable, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work. In each of the drawings, similar components are numbered similarly.

[0044] Figure 1 A flow chart showing a method for constructing a feasibility assessment model for wind power hydrogen production provided in an embodiment of the present application is shown;

[0045] Figure 2 A schematic structural diagram of a device for constructing a feasibility assessment model for producing hydrogen from wind power provided in an embodiment of the present application is shown;

[0046] Figure 3 A schematic diagram of the structure of a computer device provided in an embodiment of the present application is shown. DETAILED DESCRIPTION

[0047] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0048] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. In contrast, when an element is referred to as being "directly on" another element, there is no intermediate element. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.

[0049] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0050] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0051] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein in the specification of the template are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more of the related listed items.

[0052] Example 1

[0053] like Figure 1 As shown, it is a flow chart of a method for constructing a feasibility assessment model for wind power hydrogen production in an embodiment of the present application. The method for constructing a feasibility assessment model for wind power hydrogen production provided in an embodiment of the present application is applied to a wind power hydrogen production system composed of a wind farm and a hydrogen electrolysis plant, and specifically includes the following steps:

[0054] Step S110, obtaining wind speed data of multiple offshore wind turbines in the wind farm, calculating the output power of the corresponding offshore wind turbine according to each wind speed data, and aggregating the output power of each offshore wind turbine into the wind farm output power.

[0055] In this embodiment, the wind farm includes multiple offshore wind turbines. First, wind speed data of the multiple offshore wind turbines are obtained, including the cut-in wind speed v ci , rated wind speed v r , Cut-out wind speed v co , Rated power P r , rotor swept area A r (or diameter D r ) and the air density ρ at the hub. The above data can be collected from an ordinary wind turbine suitable for offshore wind conditions. The specific collection method is not limited in this embodiment.

[0056] The output power P of the i-th offshore wind turbine under the changing real-time wind speed v i (t) Follow the following rule: When the real-time wind speed v of the offshore wind turbine is less than the corresponding cut-in wind speed v ci , or greater than or equal to the corresponding cut-out wind speed v co When the offshore wind turbine output power P i (t) is zero; when the real-time wind speed v of the offshore wind turbine is greater than or equal to the corresponding cut-in wind speed v ci , and is less than the corresponding rated wind speed v r When the preset power coefficient C is obtained tot , according to the real-time wind speed v of the offshore wind turbine, the air density ρ at the hub, and the rotor swept area A r With the preset power coefficient C tot Calculate the output power P of offshore wind turbines i (t); When the real-time wind speed v of the offshore wind turbine is greater than or equal to the corresponding rated wind speed v r , and is less than the corresponding cut-out wind speed v co When the corresponding rated power P r As the output power of offshore wind turbine P i (t), the specific calculation formula is as follows (1):

[0057]

[0058] In the formula, C tot It is a preset power factor, which takes a value between 0.3 and 0.5 and varies with wind speed and offshore wind turbine speed.

[0059] It should be noted that, in this embodiment, in order to maintain the characteristics of the power curve, especially to ensure that the maximum power generation is P r , assuming C totThe starting value C tot,0 is 0.5, C tot The adjusted value of is estimated as follows:

[0060]

[0061] The output power of each offshore wind turbine is aggregated into the output power of the entire wind farm, which is expressed by the following formula (3):

[0062]

[0063] Where N is the number of offshore wind turbines in the wind farm.

[0064] By real-time monitoring and calculation of the output power of each offshore wind turbine, and then obtaining the total output power of the wind farm, accurate data support can be provided for subsequent model establishment.

[0065] Step S120, acquiring the electric energy data of the hydrogen electrolysis plant, determining the constraint conditions of the wind farm output power according to the electric energy data, and calculating the actual hydrogen generation rate according to the constraint conditions, the wind farm output power and the electric energy data.

[0066] Understandably, the power data of the hydrogen electrolysis plant includes the power consumption E per unit of hydrogen electrolysis. elec (MWh / kg), loss of electric energy E plc (MWh / kg) and preset energy conversion efficiency n conv Among them, the unit electricity consumption of hydrogen electrolysis refers to the electricity consumed in the electrolysis of one unit of hydrogen, and the loss electricity consumption refers to the electricity consumed in water purification, compression of hydrogen from production pressure to storage pressure and other losses.

[0067] The theoretical amount of hydrogen that can be produced per hour by a hydrogen electrolysis plant, i.e., the theoretical hydrogen generation rate, varies with time and can be calculated based on the wind farm output power P. farm (t), unit electricity consumption of hydrogen electrolysis E elec , Loss of electric energy E pcl With the preset energy conversion efficiency n conv Calculated, expressed as The specific calculation formula is as follows (4):

[0068]

[0069] Furthermore, according to the maximum hourly theoretical hydrogen generation rate The electric energy consumed by hydrogen electrolysis unit is E elec To calculate the rated power of the hydrogen electrolysis plant The specific calculation formula is as follows (5):

[0070]

[0071] It should be noted that in order to ensure efficient operation, when the input power of the hydrogen electrolysis plant (i.e. the output power of the wind farm) is too low, the electrolyzer should be shut down. The lower power limit P of the wind farm can be determined farm,low The wind farm's lower power limit P farm,low As the first constraint condition, for example, the lower limit power of the wind farm is selected to be 5% of the rated power of the hydrogen electrolysis plant, as shown in the following formula (6):

[0072]

[0073] It can be understood that, under the rated power of the selected hydrogen electrolysis plant, if the output power of the wind farm is large enough, it can ensure that the hydrogen electrolysis plant operates at the rated power, as shown in the following formula (7):

[0074]

[0075] Among them, the actual amount of hydrogen that a hydrogen electrolysis plant can produce per hour As shown in formula (8):

[0076]

[0077] Substituting equation (8) into equation (7), we can obtain the rated power of the hydrogen electrolysis plant: Hydrogen electrolysis unit power consumption E elec , Loss of electric energy E pcl With the preset energy conversion efficiency n conv The second constraint condition is determined as shown in the following formula (9):

[0078]

[0079] Furthermore, according to the first constraint condition, the second constraint condition, and the combination of equations (6) and (9), the actual hydrogen generation rate is obtained: As shown in the following formula (10):

[0080]

[0081] Where P farm,low (t) is the first constraint, is the second constraint.

[0082] By combining the output power of the wind farm with the electricity demand of the hydrogen electrolysis plant, it helps to improve the reliability and stability of the system, accurately calculate the actual hydrogen generation rate, and provide reliable data support for the system's hydrogen energy industry.

[0083] Step S130, obtaining the system initial capital expenditure and the system annual operation and maintenance expenditure, and calculating the system annual hydrogen production income according to the actual hydrogen generation rate.

[0084] Specifically, obtain the wind farm capital expenditure C 0,wind ; Get the total capital expenditure of wind farm equipment C 0,Equip , including power cables, substations (these are usually required for grid-connected wind farms, but not for dedicated stand-alone wind farms); obtain the total capital expenditure of the electrolysis unit of the hydrogen electrolysis plant Including its platform, installation, water purification system and power supply system; obtain the total capital expenditure of hydrogen storage facilities of hydrogen electrolysis plant C 0,storage , including hydrogen storage tanks and pipeline systems. The sum of the wind farm capital expenditure, the total capital expenditure of wind farm equipment, the total capital expenditure of the hydrogen electrolysis plant electrolysis device and the total capital expenditure of the hydrogen storage facilities of the hydrogen electrolysis plant is taken as the system initial capital expenditure C0, as shown in the following formula (11):

[0085]

[0086] Understandably, in T stack The electrolytic cell needs to be replaced at any time, and the cost is C stack , which is usually less than the total capital expenditure of the electrolyzer in a hydrogen electrolysis plant The operation and maintenance of wind farms and hydrogen electrolysis plants is continuous, so the annual operation and maintenance expenditure of the system is C t,O&M The wind farm operating cost C t,O&M,wind Total operating costs of electrolysis units in hydrogen electrolysis plants (including labor costs, water purification, hydrogen compression and storage device operation and maintenance costs, etc.) as shown in the following formula (12):

[0087]

[0088] Furthermore, in this embodiment, it is assumed that the sale of the actual amount of hydrogen produced by the hydrogen electrolysis plant calculated by equation (10) is the only source of income for the wind power hydrogen production system, and the price of hydrogen is (yuan / kg) (this price includes the subsidy policy), and the additional income from the sale of oxygen by-products is not considered. The annual hydrogen production income of the system is I T As shown in formula (13):

[0089]

[0090] The above method takes into account the decommissioning cost of the electrolysis unit, which helps to more accurately reflect the long-term economic burden of the project, making subsequent modeling more refined, which in turn helps to more comprehensively evaluate the economic and sustainability of the project.

[0091] Step S140, obtaining a preset discount rate, calculating the average annual income of the system according to the annual operation and maintenance expenditure of the system and the annual hydrogen production income of the system, and constructing a discount recovery evaluation model according to the preset discount rate, the average annual income of the system and the initial capital expenditure of the system.

[0092] It should be noted that in the prior art, the economic feasibility assessment model of renewable energy projects based on Simple PayBack (SPB) is usually adopted, which is simply defined as the time (number of cycles) required for the project cash flow to refinance the initial investment. In offshore wind farm projects, SPB is calculated as follows (14):

[0093]

[0094] SPB is often preferred due to its simplicity of calculation. However, its disadvantage is that it ignores the value of economic resources over time, and positive net cash flows in subsequent periods are considered to be generated in the present, which leads to an overweighting of future cash flows, resulting in an overly optimistic valuation. In addition, like any valuation using the payback period method, SPB cannot evaluate cash flows after the payback period, especially in the case of a project with a short payment period but a small net present value over the life of the project.

[0095] Based on the above considerations, this embodiment adopts a discounted payback valuation model (DPB), which takes into account the time value of money. By calculating the present value of future net cash flows caused by the investment, the number of years required to recover the original investment amount from the discounted net cash flows is determined. The economic resources over a period of time are considered by discounting the net cash flows of each period with a discount rate m before adding them up and comparing them with the initial investment, as shown in the following formula (15):

[0096]

[0097] The explicit form of the discounted payback valuation model is derived from equation (15), which is rarely reported in the literature. Its analytical derivation is as follows:

[0098] Assuming that the actual amount of hydrogen produced by the hydrogen electrolysis plant, the selling price, and the system operation and maintenance costs are consistent each year, the average annual income of the system is R aa As shown in formula (16):

[0099] R aa =I1-C 1,O&M =I2-C 2,O&M =…=I DPB -C DPB,O&M (16)

[0100] Substituting equation (16) into equation (15), equation (15) is simplified to the following equation (17):

[0101]

[0102] The payback period of the discounted payback valuation model DPB is calculated as follows (18):

[0103]

[0104] By constructing a discounted recovery valuation model, the time value of money is taken into account, making the valuation results more reasonable.

[0105] Step S150, obtaining the life cycle of the wind farm, and constructing a net present value evaluation model according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate, the initial capital expenditure of the system and the life cycle of the wind farm.

[0106] As can be understood, the discounted payback valuation model has two major limitations: (1) it focuses entirely on variable time but not on possible cash flows after the payback period; (2) it does not properly discount cash flows because it considers the “surplus” of the investment. Therefore, in this example, in order to evaluate the cash flows after the payback period and assess the feasibility of the project, the Net Present Value valuation model (NPV) is used. e The net present value (NPV) model is used together with the discounted cash flow valuation model. The net present value valuation model calculates the present value of future cash flows and compares it with the initial capital expenditure of the system to determine the net present value of the system, as shown in the following formula (19):

[0107]

[0108] Where M is the life cycle of the wind farm.

[0109] By constructing a net present value evaluation model, it can help the system evaluate the profitability of investment projects and provide a basis for enterprises to make scientific investment decisions.

[0110] The feasibility assessment model construction method for wind power hydrogen production provided in the embodiment of the present application obtains wind speed data of multiple offshore wind turbines, calculates the corresponding offshore wind turbine output power according to each wind speed data, and summarizes the output power of each offshore wind turbine into the wind farm output power; obtains electric energy data, determines the constraint conditions of the wind farm output power according to the electric energy data, and calculates the actual hydrogen generation rate according to the constraint conditions, the wind farm output power and the electric energy data; obtains the initial capital expenditure of the system and the annual operation and maintenance expenditure of the system, and calculates the annual hydrogen production income of the system according to the actual hydrogen generation rate; obtains a preset discount rate, calculates the average annual income of the system according to the annual operation and maintenance expenditure of the system and the annual hydrogen production income of the system, and constructs a discount recovery assessment model according to the preset discount rate, the average annual income of the system and the initial capital expenditure of the system; obtains the life cycle of the wind farm, and constructs a net present value assessment model according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate, the initial capital expenditure of the system and the life cycle of the wind farm. This application constructs a discounted payback assessment model and a net present value assessment model to discount the net cash flow of the wind power hydrogen production system in each period to consider the value of capital over time and effectively evaluate the feasibility of wind power hydrogen production.

[0111] Example 2

[0112] like Figure 2 As shown, it is a structural schematic diagram of a feasibility assessment model construction device 200 for wind power hydrogen production in an embodiment of the present application, and the device is applied to a wind power hydrogen production system composed of a wind farm and a hydrogen electrolysis plant, specifically including:

[0113] A first calculation module 210 is used to obtain wind speed data of multiple offshore wind turbines in the wind farm, calculate the output power of the corresponding offshore wind turbine according to each wind speed data, and aggregate the output power of each offshore wind turbine into the wind farm output power;

[0114] A second calculation module 220 is used to obtain the electric energy data of the hydrogen electrolysis plant, determine the constraint conditions of the wind farm output power according to the electric energy data, and calculate the actual hydrogen generation rate according to the constraint conditions, the wind farm output power and the electric energy data;

[0115] The third calculation module 230 is used to obtain the initial capital expenditure of the system and the annual operation and maintenance expenditure of the system, and calculate the annual hydrogen production income of the system according to the actual hydrogen generation rate;

[0116] A first construction module 240 is used to obtain a preset discount rate, calculate the average annual income of the system according to the annual operation and maintenance expenditure of the system and the annual hydrogen production income of the system, and construct a discount recovery evaluation model according to the preset discount rate, the average annual income of the system and the initial capital expenditure of the system;

[0117] The second construction module 250 is used to obtain the life cycle of the wind farm and construct a net present value evaluation model according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate, the initial capital expenditure of the system and the life cycle of the wind farm.

[0118] The feasibility assessment model construction device for wind power hydrogen production provided in the embodiment of the present application can discount the net cash flow of the wind power hydrogen production system in each period to consider the value of capital over time by constructing a discounted payback assessment model and a net present value assessment model, thereby effectively assessing the feasibility of wind power hydrogen production.

[0119] Example 3

[0120] The present application also provides a computer device. Figure 3 , Figure 3 This is a basic structural block diagram of the computer device in this embodiment.

[0121] The computer device 3 includes a memory 31, a processor 32, and a network interface 33 that are interconnected and communicated through a system bus. It should be noted that the figure only shows a computer device 3 with a memory 31, a processor 32, and a network interface 33, but it should be understood that it is not required to implement all the components shown, and more or fewer components can be implemented instead. Among them, those skilled in the art can understand that the computer device here is a device that can automatically perform numerical calculations and / or information processing according to pre-set or stored instructions, and its hardware includes but is not limited to microprocessors, application specific integrated circuits (ASIC), programmable gate arrays (FPGA), digital signal processors (DSP), embedded devices, etc.

[0122] The computer device may be a computing device such as a desktop computer, a notebook, a PDA, a cloud server, etc. The computer device may interact with a user through a keyboard, a mouse, a remote controller, a touch pad, or a voice control device.

[0123] The memory 31 includes at least one type of readable storage medium, and the readable storage medium includes flash memory, hard disk, multimedia card, card-type memory (for example, SD or D slot compatibility test memory, etc.), random access memory (RAM), static random access memory (SRAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), programmable read-only memory (PROM), magnetic memory, disk, optical disk, etc. In some embodiments, the memory 31 can be an internal storage unit of the computer device 3, such as a hard disk or memory of the computer device 3. In other embodiments, the memory 31 can also be an external storage device of the computer device 3, such as a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (Secure Digital, SD) card, a flash card (Flash Card), etc. equipped on the computer device 3. Of course, the memory 31 can also include both the internal storage unit of the computer device 3 and its external storage device. In this embodiment, the memory 31 is generally used to store the operating system and various application software installed on the computer device 3, such as computer-readable instructions of the slot compatibility test method, etc. In addition, the memory 31 can also be used to temporarily store various types of data that have been output or are to be output.

[0124] The processor 32 may be a central processing unit (CPU), a controller, a microcontroller, a microprocessor, or other wind power hydrogen production feasibility assessment model building chip in some embodiments. The processor 32 is generally used to control the overall operation of the computer device 3. In this embodiment, the processor 32 is used to run the computer-readable instructions stored in the memory 31 or process data, such as running the computer-readable instructions of the slot compatibility test method.

[0125] The network interface 33 may include a wireless network interface or a wired network interface. The network interface 33 is generally used to establish a communication connection between the computer device 3 and other electronic devices.

[0126] The computer device provided in this embodiment can execute the feasibility assessment model construction method for wind power hydrogen production. The feasibility assessment model construction method for wind power hydrogen production here can be the feasibility assessment model construction method for wind power hydrogen production in each of the above embodiments.

[0127] Example 4

[0128] This embodiment further provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the method for constructing a feasibility assessment model for hydrogen production from wind power in the embodiment are implemented.

[0129] In this embodiment, the computer-readable storage medium includes flash memory, hard disk, multimedia card, card-type memory (for example, SD or DX memory, etc.), random access memory (RAM), static random access memory (SRAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), programmable read-only memory (PROM), magnetic memory, disk, optical disk, etc. In some embodiments, the computer-readable storage medium can be an internal storage unit of a computer device, such as a hard disk or memory of the computer device. In other embodiments, the computer-readable storage medium can also be an external storage device of a computer device, such as a plug-in hard disk equipped on the computer device, a smart memory card (Smart Media Card, referred to as SMC), a secure digital (Secure Digital, referred to as SD) card, a flash card, etc. Of course, the computer-readable storage medium can also include both the internal storage unit of the computer device and its external storage device. In this embodiment, the computer-readable storage medium is generally used to store an operating system and various application software installed on the computer device. In addition, the computer-readable storage medium can also be used to temporarily store various types of data that have been output or are to be output.

[0130] In several embodiments provided in the present application, it should be understood that the disclosed devices and methods can also be implemented in other ways. The device embodiments described above are merely schematic. For example, the flowcharts and structure diagrams in the accompanying drawings show the possible architecture, functions and operations of the devices, methods and computer program products according to multiple embodiments of the present invention. In this regard, each box in the flowchart or block diagram can represent a module, a program segment or a part of a code, and the module, a program segment or a part of a code contains one or more executable instructions for implementing the specified logical function. It should also be noted that in an alternative implementation, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two consecutive boxes can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the structure diagram and / or the flow diagram, and the combination of boxes in the structure diagram and / or the flow diagram, can be implemented with a dedicated hardware-based system that performs a specified function or action, or can be implemented with a combination of dedicated hardware and computer instructions.

[0131] In addition, the functional modules or units in the various embodiments of the present invention may be integrated together to form an independent part, or each module may exist independently, or two or more modules may be integrated to form an independent part.

[0132] If the function is implemented in the form of a software function module and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention is essentially or partly contributed to the prior art or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a smart phone, a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium can be a non-volatile storage medium or a volatile storage medium. For example, the storage medium can be: a U disk, a mobile hard disk, a read-only memory (ROM, Read-Only Memory), a random access memory (RAM, Random Access Memory), a disk or an optical disk, and other media that can store program codes.

[0133] The above description is only a specific implementation mode of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A feasibility assessment model construction method for wind power hydrogen production, It is characterized in that Applied to a wind power hydrogen production system, the system includes a wind farm and a hydrogen electrolysis plant, and the method includes: Obtain wind speed data of multiple offshore wind turbines in the wind farm, calculate the output power of the corresponding offshore wind turbine according to each wind speed data, and aggregate the output power of each offshore wind turbine into the wind farm output power; Acquiring electric energy data of the hydrogen electrolysis plant, determining constraints on the output power of the wind farm according to the electric energy data, and calculating an actual hydrogen generation rate according to the constraints, the output power of the wind farm and the electric energy data; Obtaining the initial capital expenditure of the system and the annual operation and maintenance expenditure of the system, and calculating the annual hydrogen production income of the system based on the actual hydrogen generation rate; Obtaining a preset discount rate, calculating the average annual income of the system according to the annual operation and maintenance expenditure of the system and the annual hydrogen production income of the system, and constructing a discount recovery evaluation model according to the preset discount rate, the average annual income of the system and the initial capital expenditure of the system; The life cycle of the wind farm is obtained, and a net present value evaluation model is constructed according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate, the initial capital expenditure of the system and the life cycle of the wind farm.

2. The feasibility assessment model construction method for wind power hydrogen production according to claim 1, It is characterized in that The wind speed data includes a cut-in wind speed, a rated wind speed, a cut-out wind speed, a rated power, a rotor swept area, and an air density at a hub. The calculation of the corresponding offshore wind turbine output power according to each of the wind speed data includes: When the real-time wind speed of the offshore wind turbine is less than the corresponding cut-in wind speed, or greater than or equal to the corresponding cut-out wind speed, the output power of the offshore wind turbine is zero; When the real-time wind speed of the offshore wind turbine is greater than or equal to the corresponding cut-in wind speed and less than the corresponding rated wind speed, a preset power coefficient is obtained, and the output power of the offshore wind turbine is calculated according to the real-time wind speed of the offshore wind turbine, the air density at the hub, the rotor swept area and the preset power coefficient; When the real-time wind speed of the offshore wind turbine is greater than or equal to the corresponding rated wind speed and less than the corresponding cut-out wind speed, the corresponding rated power is used as the output power of the offshore wind turbine.

3. The feasibility assessment model construction method for wind power hydrogen production according to claim 2, It is characterized in that The constraint condition includes a first constraint condition and a second constraint condition, the electric energy data includes the unit electric energy consumption of hydrogen electrolysis, the loss electric energy consumption and the preset energy conversion efficiency of the hydrogen electrolysis plant, and the constraint condition for determining the output power of the wind farm according to the electric energy data includes: Calculating a theoretical hydrogen generation rate according to the wind farm output power, the unit power consumption of hydrogen electrolysis, the lost power consumption and the preset energy conversion efficiency; Calculating the rated power of the hydrogen electrolysis plant according to the theoretical hydrogen generation rate and the unit electric energy consumption of hydrogen electrolysis, and determining the lower limit power of the wind farm according to the rated power of the hydrogen electrolysis plant, and taking the lower limit power of the wind farm as the first constraint condition; The second constraint condition is determined according to the rated power of the hydrogen electrolysis plant, the unit power consumption of the hydrogen electrolysis, the lost power consumption and the preset energy conversion efficiency.

4. The method for constructing a feasibility assessment model for wind power hydrogen production according to claim 3, It is characterized in that The calculating the actual hydrogen generation rate according to the constraint condition, the wind farm output power and the electric energy data comprises: In the formula, is the actual generation rate of hydrogen, P farm (t) is the output power of the wind farm, E elec The electrical energy consumed by the hydrogen electrolysis unit, E pcl The electrical energy consumed for the losses, n conv is the preset energy conversion efficiency, is the rated power of the hydrogen electrolysis plant, P fam,low (t) is the first constraint condition, is the second constraint.

5. The method for constructing a feasibility assessment model for wind power hydrogen production according to claim 4, It is characterized in that The acquisition of the system initial capital expenditure and the system annual operation and maintenance expenditure includes: Obtaining the capital expenditure of the wind farm, the total capital expenditure of the wind farm equipment, the total capital expenditure of the electrolysis device of the hydrogen electrolysis plant and the total capital expenditure of the hydrogen storage facilities of the hydrogen electrolysis plant, and taking the sum of the capital expenditure of the wind farm, the total capital expenditure of the wind farm equipment, the total capital expenditure of the electrolysis device of the hydrogen electrolysis plant and the total capital expenditure of the hydrogen storage facilities of the hydrogen electrolysis plant as the initial capital expenditure of the system; The wind farm operating cost and the total operating cost of the electrolysis device of the hydrogen electrolysis plant are obtained, and the sum of the wind farm operating cost and the total operating cost of the electrolysis device of the hydrogen electrolysis plant is used as the annual operation and maintenance expenditure of the system.

6. The method for constructing a feasibility assessment model for wind power hydrogen production according to claim 1, It is characterized in that The discounted payback valuation model is: Where DPB is the discounted payback valuation model, R aa is the average annual income of the system, m is the preset discount rate, C 0 is the initial capital expenditure for the system.

7. The method for constructing a feasibility assessment model for wind power hydrogen production according to claim 6, It is characterized in that The net present value evaluation model is: Where, NPV is the net present value evaluation model, M is the life cycle of the wind farm, I 1 ,I 2 ,I N are the annual hydrogen production income of the system in the first year, the second year, and the Nth year, respectively. 1,O&M , C 2,O&M , C N,O&M They are the annual system operation and maintenance expenses in the 1st year, the 2nd year, and the Nth year respectively.

8. A device for constructing a feasibility assessment model for wind power hydrogen production. It is characterized in that Applied to a wind power hydrogen production system, the system includes a wind farm and a hydrogen electrolysis plant, and the device includes: A first calculation module is used to obtain wind speed data of multiple offshore wind turbines in the wind farm, calculate the output power of the corresponding offshore wind turbine according to each wind speed data, and aggregate the output power of each offshore wind turbine into the wind farm output power; a second calculation module, configured to obtain electric energy data of the hydrogen electrolysis plant, determine the constraint conditions of the wind farm output power according to the electric energy data, and calculate the actual hydrogen generation rate according to the constraint conditions, the wind farm output power and the electric energy data; The third calculation module is used to obtain the initial capital expenditure of the system and the annual operation and maintenance expenditure of the system, and calculate the annual hydrogen production income of the system according to the actual hydrogen generation rate; The first construction module is used to obtain a preset discount rate, calculate the average annual income of the system according to the annual operation and maintenance expenditure of the system and the annual hydrogen production income of the system, and construct a discount recovery evaluation model according to the preset discount rate, the average annual income of the system and the initial capital expenditure of the system; The second construction module is used to obtain the life cycle of the wind farm and construct a net present value evaluation model according to the annual operation and maintenance expenditure of the system, the annual hydrogen production income of the system, the preset discount rate, the initial capital expenditure of the system and the life cycle of the wind farm.

9. A computer device, It is characterized in that It comprises a memory and a processor, the memory stores a computer program, and the processor implements the steps of the method for constructing a feasibility assessment model for wind power hydrogen production according to any one of claims 1 to 7 when executing the computer program.

10. A computer-readable storage medium, It is characterized in that The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the method for constructing a feasibility assessment model for wind power hydrogen production according to any one of claims 1 to 7 are implemented.