Power consumption management method considering peak and valley electricity prices

By formulating power supply strategies in the factory based on the power consumption period and reasonably arranging the coordinated work of photovoltaic power generation and energy storage batteries, the problem of failure to effectively utilize electricity in the existing technology is solved, and the effect of reducing power costs and improving energy utilization is achieved. .

CN119029980APending Publication Date: 2024-11-26SUZHOU WEIXUN PHOTOELECTRIC TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411131799.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The existing factory power management method fails to effectively utilize the power of photovoltaic power generation and energy storage batteries during peak and valley periods, resulting in high power costs and low energy utilization.

Method used

Adopt a power consumption management method that considers peak and valley electricity prices, and formulate power supply strategies in peak, flat and valley periods through the management platform, reasonably arrange the coordinated work of photovoltaic power generation and energy storage batteries, and use the remaining power to reduce the use of mains. Excess power is sold and energy storage battery charging is optimized through weather forecasts.

Benefits of technology

It effectively reduces the power costs of factories, improves energy utilization, reduces energy waste, and optimizes the use of photovoltaic power generation and energy storage batteries.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119029980A_ABST
    Figure CN119029980A_ABST
Patent Text Reader

Abstract

The invention discloses a power consumption management method considering peak and valley electricity prices, which comprises the following steps: installing a solar photovoltaic power generation assembly on the roof of a factory, additionally installing an energy storage battery in the factory, considering the electric charge difference in peak and valley periods, and deciding a power supply source and a residual electric quantity purpose according to a peak-time power supply strategy in a power consumption peak period. The electric quantity of the energy storage battery is obtained in real time and a power supply source is decided according to a usual power supply strategy in a power utilization usual period, the electric quantity of the energy storage battery is obtained in real time and the power supply source is decided according to a valley power supply strategy in a power utilization valley period, and whether the energy storage battery is charged or not is further decided by considering the influence of meteorological conditions on photovoltaic power generation through a photovoltaic power generation prediction strategy. The photovoltaic module, the energy storage battery and the mains supply are reasonably utilized to meet the power utilization requirements of factories in different periods, the power utilization cost is reduced, and the energy utilization efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of factory electricity management, and in particular to an electricity management method taking peak and valley electricity prices into consideration. Background Art

[0002] With the continuous rise in energy prices and the improvement of environmental protection requirements, factories and enterprises are paying more and more attention to energy conservation, emission reduction and energy cost control. Photovoltaic power generation, as a clean energy, has significant energy conservation and emission reduction effects, but its intermittent and unstable nature also brings challenges to power supply. At the same time, the peak and valley electricity price policy implemented in the power market has also put forward new requirements for the use and management of electricity by enterprises.

[0003] The invention patent with the existing publication number: CN1 17360308A proposes a power generation, storage and charging management system and method for smart parking lots. The photovoltaic power generation unit, energy storage unit, charging unit and power consumption unit are controlled through a management platform. During the low-power consumption period, the city power is controlled to supply power to the energy storage unit, charging unit and power consumption unit. During the non-low-power period, the power demand is considered, and the photovoltaic power generation unit or the energy storage unit or the city power is switched to supply power to the charging unit and the power consumption unit. In addition, when the photovoltaic power generation power is greater than the charging and power consumption power, power will also be supplied to the energy storage unit.

[0004] The existing management method simply switches the power supply source according to the power demand during the peak and valley periods. When the city power is used to supply electricity, the power of the photovoltaic power generation unit and / or the energy storage unit is not effectively utilized. When the photovoltaic unit supplies the charging unit, the power unit and the energy storage unit, the excess power is wasted. Therefore, the power cost of the existing management method still has room for optimization, and the energy utilization rate is low. Summary of the invention

[0005] The purpose of the present invention is to provide an electricity management method that takes peak and valley electricity prices into consideration, taking into account the difference in electricity charges during peak and valley periods, and coordinating the power supply of photovoltaic power generation, energy storage batteries and city electricity to reduce factory electricity costs and improve energy utilization.

[0006] The technical solution to achieve the purpose of the present invention is:

[0007] A method for electricity management taking into account peak and valley electricity prices, comprising:

[0008] During peak power consumption periods, the management platform decides on the power supply source and the use of the remaining power based on the peak power supply strategy;

[0009] During the power-on period, the management platform obtains the power of the energy storage battery in real time according to the normal power supply strategy and decides the power supply source;

[0010] During the off-peak hours, the management platform obtains the power of the energy storage battery in real time based on the off-peak power supply strategy and decides on the power supply source. If the power supply source is municipal electricity, the photovoltaic power generation prediction strategy is used to further determine whether to charge the energy storage battery.

[0011] Furthermore, the peak power supply strategy includes the following steps:

[0012] Obtain photovoltaic power generation, energy storage battery power and factory power in real time;

[0013] Determine the relationship between photovoltaic power generation and factory power consumption;

[0014] If the photovoltaic power generation power is greater than or equal to the factory power, photovoltaic modules are used to supply power to the factory;

[0015] Further determine whether the energy storage battery is fully charged;

[0016] If it is fully charged, the remaining power will be sent to the power grid company for sale;

[0017] If it is not fully charged, use the remaining power to charge the energy storage battery;

[0018] If the photovoltaic power generation power is less than the factory power consumption, it is further determined whether the energy storage battery power is exhausted;

[0019] If it is exhausted, the factory will be powered by photovoltaic panels and city electricity;

[0020] If it is not exhausted, photovoltaic panels and energy storage batteries are used to power the factory.

[0021] Furthermore, the normal power supply strategy includes the following steps:

[0022] Obtain the power of the energy storage battery in real time to determine whether the energy storage battery has been exhausted;

[0023] If it is exhausted, use the mains electricity to supply the factory;

[0024] If not exhausted, the energy storage battery is used to power the factory.

[0025] Furthermore, the off-peak power supply strategy includes the following steps:

[0026] Obtain the power of the energy storage battery in real time to determine whether the energy storage battery has been exhausted;

[0027] If it is not exhausted, the energy storage battery is used to power the factory;

[0028] If it is exhausted, the city power is used to power the factory, and the photovoltaic power generation prediction strategy is used to determine whether to use the city power to synchronously charge the energy storage battery.

[0029] Furthermore, the photovoltaic power generation prediction strategy includes the following steps:

[0030] Obtain weather forecast information for the area where the next day is located, and predict the photovoltaic power generation power for the next day based on the weather forecast information, wherein the weather forecast information includes temperature, relative humidity and sunshine intensity;

[0031] The management platform obtains the factory power consumption during the day and at night the next day, and determines whether the power used for energy storage during the day, excluding the power supply to the factory, can meet the power demand of the factory at night;

[0032] If it can be met, the energy storage battery will not be charged with AC power;

[0033] If it cannot be satisfied, the mains electricity is used to charge the energy storage battery according to the first charging amount.

[0034] Optionally, the peak electricity consumption period is 08:00-19:00 on the same day, the level electricity consumption period is 19:00-24:00 on the same day, and the valley electricity consumption period is 00:00-08:00 on the next day. The management platform includes management software, computers, and industrial gateways. The circuit switches are controlled by cooperating with relays. The management software uses communication technology to interact with the inverter of the photovoltaic module, the factory's smart meter and the energy storage battery to obtain real-time photovoltaic power generation power, factory power and energy storage battery power. The communication technology includes wireless communication, network cable, and serial port communication. The management software can also obtain weather forecast information by developing a meteorological data call function.

[0035] Compared with the prior art, the present invention has the following significant advantages:

[0036] 1. Reduce the factory's use of city electricity by rationally arranging the coordinated work of photovoltaic power generation and energy storage batteries, and sell excess electricity to the power grid to reduce electricity costs;

[0037] 2. Optimize the use of photovoltaic power generation and energy storage batteries, and use the remaining electricity after powering the factory to charge the energy storage batteries, reduce energy waste, and improve energy utilization efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is a flow chart of a method for electricity management taking into account peak and valley electricity prices;

[0039] Figure 2 This is a schematic diagram of the connection between the management platform and the mains, power grid, relays, photovoltaic panels, energy storage batteries, mains and factory power. The dotted line indicates the existence of communication interaction, and the real line indicates the existence of cables. DETAILED DESCRIPTION

[0040] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments.

[0041] The present invention provides an embodiment: a method for managing electricity consumption taking into account peak and valley electricity prices, comprising:

[0042] During the peak power consumption period, the management platform compares the size of photovoltaic power generation power P1 and factory power consumption power P2 according to the peak power supply strategy, and decides the power supply source. If there is surplus power, it further decides the use of the surplus power.

[0043] During the period of use, the management platform obtains the energy storage battery power Q in real time according to the normal power supply strategy. b , according to Q b Whether the decision-making power supply source is exhausted;

[0044] During the off-peak period, the management platform obtains the energy storage battery power Q in real time according to the off-peak power supply strategy. b , according to Q b The power supply source is exhausted. If the power supply source is the mains, the photovoltaic power generation prediction strategy is used to further determine whether to charge the energy storage battery.

[0045] Furthermore, the peak power supply strategy includes the following steps:

[0046] The management platform obtains photovoltaic power generation power P1 and energy storage battery power Q in real time b and the factory power P2;

[0047] Determine the relationship between photovoltaic power generation power P1 and factory power P2;

[0048] If the photovoltaic power generation power P1 is greater than or equal to the factory power P2, the management platform switches on and off through the relay and uses photovoltaic modules to power the factory;

[0049] Further determine the energy storage battery capacity Q b Rated capacity of energy storage battery size;

[0050] If the energy storage battery capacity is Q b Equal to the rated capacity of the energy storage battery If the energy storage battery is fully charged, the remaining power will be sent to the power grid company for sale;

[0051] If the energy storage battery capacity is Q b Less than the rated capacity of the energy storage battery If the energy storage battery is not fully charged, the remaining power is used to charge the energy storage battery;

[0052] If the photovoltaic power generation power P1 is less than or equal to the factory power P2, the energy storage battery power Q b Battery level threshold The size of , λ is the threshold ratio, which is set to 0.1 in this embodiment;

[0053] If the energy storage battery capacity is Q b Less than or equal to the battery level threshold The energy storage battery is deemed to be exhausted, and the management platform switches on and off through the relay, using photovoltaic modules and city electricity to power the factory. The city electricity is 220V, 50Hz AC.

[0054] If the energy storage battery capacity is Q b Greater than the battery level threshold The management platform performs switching actions through relays and uses photovoltaic panels and energy storage batteries to power the factory.

[0055] Furthermore, the normal power supply strategy includes the following steps:

[0056] The management platform obtains the energy storage battery power Q in real time b , determine the energy storage battery capacity Q b Battery level threshold size;

[0057] If the energy storage battery capacity is Q b Less than or equal to the battery level threshold The energy storage battery is deemed to be exhausted, and the management platform switches on and off through the relay, using the mains electricity to supply power to the factory;

[0058] If the energy storage battery capacity is Q b Greater than the battery level threshold The management platform performs switching actions through relays and uses energy storage batteries to power the factory.

[0059] Furthermore, the off-peak power supply strategy includes the following steps:

[0060] The management platform obtains the energy storage battery power Q in real time b , determine the energy storage battery capacity Q b Battery level threshold size;

[0061] If the energy storage battery capacity is Q b Greater than the battery level threshold The management platform uses relays to switch on and off, and uses energy storage batteries to power the factory;

[0062] If the energy storage battery capacity is Q b Less than or equal to the battery level threshold The energy storage battery is deemed to be exhausted. The management platform switches on and off through the relay, uses the mains power to power the factory, and uses the photovoltaic power generation prediction strategy to determine whether to use the mains power to charge the energy storage battery simultaneously.

[0063] Furthermore, the photovoltaic power generation prediction strategy includes the following steps:

[0064] The management platform calls the data interface of the meteorological bureau website to obtain the weather forecast information of the area for the next day, and predicts the photovoltaic power generation power P3 of the next day based on the weather forecast information, wherein the weather forecast information includes temperature, relative humidity and sunshine intensity;

[0065] The management platform obtains the factory power consumption during the day and at night the next day, and calculates the amount of photovoltaic power used for energy storage, excluding the power supply to the factory. r The specific formula is as follows

[0066]

[0067] Calculate the power demand Q of the plant at night f The specific formula is as follows

[0068]

[0069] If the amount of energy used for energy storage is Q r Greater than or equal to the nighttime power demand Q f If the power supply is 1+λ times of the original power supply, the energy storage battery will not be charged with AC power.

[0070] If the amount of energy used for energy storage is Q r Less than the power demand Q of the plant at night f 1+λ times, then the mains is used according to the first charging amount Q s The energy storage battery is charged, wherein the first charge amount Q s =(1+λ)Q f -Q r .

[0071] Furthermore, predicting the photovoltaic power generation power P3 of the next day based on weather forecast information includes the following steps:

[0072] Get the next day's ambient temperature, relative humidity, and sunshine intensity.

[0073] Obtain the nominal power generation P of the photovoltaic module. The nominal power generation refers to the power generation of the photovoltaic module under standard operating temperature, standard relative humidity and standard light intensity. In this embodiment, the standard operating temperature, standard relative humidity and standard light intensity are 25°C, 0.6 and 1000W / m 2 ;

[0074] Predict the photovoltaic power generation power P3 of the photovoltaic module the next day. The formula is as follows

[0075] P3=P·[1-(T-25)·0.004]·[1-(H-0.6)·A]·(L / 1000)

[0076] Among them, A selects different values ​​according to the type of photovoltaic modules, 0.003 for monocrystalline modules and 0.01 for polycrystalline modules.

[0077] Optionally, the peak electricity consumption period is 08:00-19:00 of the same day, the average electricity consumption period is 19:00-24:00 of the same day, and the valley electricity consumption period is 00:00-08:00 of the next day.

[0078] Optionally, the management platform includes management software, computers, and industrial gateways, which control circuit switches by cooperating with relays. The management software uses communication technology to interact with the inverter of the photovoltaic module, the factory's smart meter and energy storage batteries to obtain real-time photovoltaic power generation, factory power and energy storage battery power. The communication technology includes wireless communication, network cable, and serial port communication. The management software can also obtain weather forecast information by developing a meteorological data call function.

[0079] The present invention identifies power consumption time periods and configures corresponding power supply strategies according to different power consumption time periods. Based on the power supply strategies, photovoltaic power generation and energy storage batteries are scheduled for collaborative power supply, reducing the factory's use of city electricity, and selling excess electricity to reduce electricity costs. The use of photovoltaic power generation and energy storage batteries is optimized, and the remaining electricity after powering the factory is used to charge the energy storage batteries, thereby reducing energy waste and improving energy utilization efficiency.

[0080] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.

Claims

1. A method for electricity management taking into account peak and valley electricity prices, characterized in that: include: Identify power consumption periods, configure power supply strategies according to power consumption periods, and adjust power consumption based on power supply strategies; During peak power consumption periods, the power supply source and the use of remaining power are determined based on the peak power supply strategy; During the power-on period, the battery power is obtained in real time according to the normal power supply strategy, and the power supply source is determined; During the off-peak hours, the power level of the energy storage battery is obtained in real time according to the off-peak power supply strategy to decide the power supply source. If the power supply source is the mains, the photovoltaic power generation prediction strategy is used to determine whether to charge the energy storage battery.

2. The method for electricity management taking into account peak and valley electricity prices as claimed in claim 1, characterized in that: The off-peak power supply strategy includes obtaining the power of the energy storage battery in real time, selecting the energy storage battery or the mains power to power the factory according to the power of the energy storage battery, and determining whether to charge the energy storage battery synchronously when the mains power is used through the photovoltaic power generation prediction strategy.

3. A method for electricity management taking into account peak and valley electricity prices as claimed in any one of claims 1 to 2, characterized in that: The photovoltaic power generation prediction strategy includes obtaining weather forecast information for the area where the next day is located, obtaining the factory power consumption during the day and at night on the next day, predicting the photovoltaic power generation power of the next day based on the weather forecast information, and deciding whether to use the city power to charge the energy storage battery based on whether the photovoltaic power generation can meet the factory power consumption during the day and at night.

4. The method for electricity management considering peak and valley electricity prices as claimed in claim 1, characterized in that: The peak power supply strategy includes real-time acquisition of photovoltaic power generation and factory power consumption, and judging whether the photovoltaic components can independently supply power to the factory based on the photovoltaic power generation and factory power consumption; if it can supply power independently, deciding the use of excess power based on the power of the energy storage battery; if it cannot supply power independently, selecting energy storage batteries or AC power to assist photovoltaic components to supply power to the factory based on the power of the energy storage batteries.

5. The method for electricity management considering peak and valley electricity prices as claimed in claim 1, characterized in that: The normal power supply strategy obtains the power of the energy storage battery in real time, and decides whether to use the energy storage battery or the mains to supply power to the factory according to the power of the energy storage battery.

6. The method for electricity management considering peak and valley electricity prices as claimed in claim 1, characterized in that: The peak electricity consumption period is 08:00-19:00 of the same day, the average electricity consumption period is 19:00-24:00 of the same day, and the valley electricity consumption period is 00:00-08:00 of the next day.