Soil nailing wall reinforcing mesh erecting device applied to foundation pit support

By designing the device for steel bar placement bins, ground walking wheels and toothed rail wheels, the problems of low efficiency and safety hazards of steel bar mesh installation in foundation pit slope construction are solved, the automatic laying and stable fixation of steel bars are realized, and the construction is improved Efficiency and safety.

CN119041701AInactive Publication Date: 2024-11-29SHANGHAI GUANGDA FOUND ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411429372.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-14
Publication Date
2024-11-29
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the construction of foundation pit slopes, the erection efficiency of steel bar mesh is low and there are safety risks. The existing technology relies on manual binding to one by one, resulting in low efficiency and safety risks.

Method used

A device including a steel bar placing chamber, a ground walking wheel, a toothed rail and a gear wheel is designed. The automatic laying and fixing of the steel bars through the toothed rail's toothed rail's toothed rail's toothed rail's toothed rail's toothed rail's toothed rail's toothed rail's toothed rail's toothed rail's toothed rail's toothed rail's toothed rail's autoclave and guide sleeve enhance stability.

Benefits of technology

The efficient, stable and safe installation of steel bars has been achieved, construction efficiency has been improved, safety risks have been reduced, and the construction process has been simplified.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041701A_ABST
    Figure CN119041701A_ABST
Patent Text Reader

Abstract

The invention provides a soil nailing wall reinforcing mesh erecting device applied to a foundation pit support, and belongs to the technical field of foundation pit slope construction. The soil nailing wall reinforcing mesh erecting device applied to the foundation pit support comprises a reinforcing steel bar containing bin, a reinforcing steel bar conveying device, a reinforcing steel bar conveying device, a reinforcing steel bar conveying device and a reinforcing steel bar conveying device, the ground walking wheels are arranged on the front side and the rear side of the steel bar containing bin and used for walking on the side slope. The tooth-shaped rails are arranged on the left side and the right side, corresponding to the steel bar containing bin, of the tooth-shaped rails, anchor rods used for being anchored to a side slope are arranged at the ends of the two tooth-shaped rails, the tooth-shaped rails are coaxially installed on the two ground walking wheels located on the same side in the front-back direction, and the tooth-shaped rails are meshed with the tops of the tooth-shaped rails; the steel bar baffles are rotationally arranged on the left side and the right side in the steel bar outlet, circular gears are fixedly installed outside the steel bar baffles, and racks are arranged on the tooth-shaped rails. The method has the advantages of high efficiency, stability and safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation pit slope construction, and in particular to a soil nail wall steel mesh erecting device applied to foundation pit enclosure. Background Art

[0002] In the slope support operation, the installation of steel mesh is a crucial link, and its construction quality and efficiency will directly affect the strength and stability of the support cavity formed after the subsequent shotcrete spraying. At present, the installation of steel mesh is carried out manually in a multi-person cooperation manner, using the method of laying and tying steel bars one by one. At this time, manual labor is required to place, transfer and tie steel bars on the slope surface, which is not only inefficient, but also poses certain safety hazards. In view of this, the present application provides a soil nail wall steel mesh installation device for foundation pit enclosure. Summary of the invention

[0003] In order to solve the above technical problems, the present invention proposes an efficient, stable and safe soil nail wall steel mesh erection device for foundation pit protection.

[0004] The technical solution of the present invention is achieved in this way:

[0005] A soil nail wall steel mesh installation device used for foundation pit protection, comprising:

[0006] The steel bar placement bin is a hollow columnar structure as a whole, and its inner cavity is used to place steel bars. A steel bar outlet is provided at the bottom of the steel bar placement bin;

[0007] Ground walking wheels, arranged on the front and rear sides of the steel bar placement bin, for walking on the slope;

[0008] A toothed rail and a toothed wheel, wherein one toothed rail is provided on each of the left and right sides of the steel bar placement bin, and anchor rods for anchoring to the slope are provided at the ends of the two toothed rails, and the toothed wheel is coaxially mounted on two ground running wheels located on the same side in the front-rear direction, and the toothed wheel is meshed with the top of the toothed rail;

[0009] A steel bar baffle is rotatably arranged on the left and right sides of the steel bar outlet, the steel bar baffle is in a "U" shape, a circular gear is fixedly installed on the outside of the steel bar baffle, a rack is arranged on the toothed rail, and the two ends of the steel bar dropped from the steel bar outlet fall into the tooth grooves of the two toothed rails respectively;

[0010] A travel motor is arranged on both sides of the left and right sides of the steel bar placement bin, and the power shaft of the travel motor is connected to the rack wheel. When the circular gear passes through a rack, it rotates exactly one circle.

[0011] Furthermore, guide sleeves are fixedly installed on both left and right sides of the top of the steel bar placement bin, guide ropes are passed through the guide sleeves, and both ends of the guide ropes are respectively fixed to the top ends of the anchor rods.

[0012] Furthermore, end plates are provided at both left and right ends of the steel bar placement bin, and the end plates are installed in threaded cooperation with the steel bar placement bin.

[0013] Furthermore, the steel bar placement bin includes two relatively distributed bin bodies and a connecting rod assembly connecting the two bin bodies, the connecting rod assembly includes a threaded sleeve located in the middle and a screw rod threadedly connected to both ends of the threaded sleeve, and the end of the screw rod away from the threaded sleeve is fixedly connected to the bin body on the corresponding side.

[0014] Furthermore, a plurality of threaded holes are equidistantly formed on the outer side of the top of the toothed rail, bolts are mounted on the rack, and the rack is bolted to the toothed rail through the cooperation of the bolts and the threaded holes.

[0015] Furthermore, when the circular gear rolls half a circle on the rack, the steel bar baffle is in a state of opening downward, and the steel bar outlet is aligned with one of the tooth grooves of the toothed rail.

[0016] Furthermore, the rack wheel is arranged on the front side of the steel bar placing bin, and the ground running wheel located on the front side of the steel bar placing bin is arranged on the inner side of the rack, and the ground running wheel located on the rear side of the steel bar placing bin is arranged on the outer side of the rack. The cross-section of the rack is an inverted "T" shaped structure, and the rack is installed on the outer side of the top of the rack.

[0017] Furthermore, the toothed rail includes anchor blocks at both ends for connecting anchor rods and toothed units connected in sequence between the two anchor blocks, and two adjacent toothed units slide together in the inward and outward directions. When the ground walking wheel located on the front side of the steel bar placement bin passes through the toothed block, the toothed block is pushed outward to the outermost position. When the ground walking wheel located on the rear side of the steel bar placement bin passes through the toothed block, the toothed block is pushed inward, so that the rack clamps the steel bar.

[0018] Furthermore, a sleeve groove is provided in the middle of the inner side surface of the rack, and the sleeve groove is used to sleeve the end of the steel bar.

[0019] Furthermore, a first guide bevel is provided on both inner and outer sides of the toothed unit, and a second guide bevel adapted to the first guide bevel is provided on the outer side of the ground walking wheel located at the front side of the steel bar placement bin and on the inner side of the ground walking wheel located at the rear side of the steel bar placement bin.

[0020] The present invention has the following beneficial effects:

[0021] 1. Through the coordination of ground walking wheels, toothed rails and toothed rail wheels, the steel bar storage bin can carry a large number of steel bars and move stably in the horizontal and vertical directions of the slope. The tooth grooves on the toothed rails are used as the structure for receiving the steel bars, so that the lowered steel bars are effectively limited, so as to achieve efficient and stable steel bar erection effects.

[0022] 2. Through the cooperation of the ground walking wheels and the toothed units and other structures, the two corresponding toothed units will be moved away before the steel bars are lowered, providing sufficient space for the lowering of the steel bars, ensuring that the steel bars can effectively fall onto the two toothed units, and after the steel bars are lowered, the two toothed units are close to each other, clamping the lowered steel bars from both ends, thereby improving the effect of steel bar laying.

[0023] 3. Through the coordination of structures such as anchor rods, guide sleeves and guide ropes, the walking stability of the steel bar placement bin can be improved, especially when walking longitudinally on the slope, which can effectively prevent the steel bar placement bin from overturning. In addition, the anchor rods are used as the structure for fixing the toothed rails on site, and the construction operation is relatively simple, which can be directly carried out using the anchor rod implantation device on site. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is an overall schematic diagram of the present invention;

[0025] Figure 2 The present invention Figure 1 Enlarged view of point A in the middle;

[0026] Figure 3 The present invention Figure 1 Enlarged view of point B in the middle;

[0027] Figure 4 The present invention Figure 1 Enlarged view of point C in the middle;

[0028] Figure 5 It is a schematic diagram of a warehouse body of the present invention after being cut open;

[0029] Figure 6 It is a schematic diagram of the toothed unit and the rack after being separated from each other;

[0030] Figure 7 The present invention Figure 6 Another perspective of the picture.

[0031] In the figure: 1. Steel bar placement bin; 1.1. Bin body; 1.2. Thread sleeve; 1.3. Screw rod; 2. Ground walking wheel; 3. Toothed rail; 3.1. Anchor block; 3.2. Toothed unit; 4. Rack wheel; 5. Anchor rod; 6. Steel bar baffle; 7. Circular gear; 8. Rack; 9. Tooth groove; 10. Travel motor; 11. Guide sleeve; 12. Guide rope; 13. End plate; 14. Threaded hole; 15. Bolt; 16. Sleeve groove. DETAILED DESCRIPTION

[0032] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0033] like Figures 1 to 7 As shown, the present invention provides a soil nail wall steel mesh installation device for foundation pit protection, comprising:

[0034] The steel bar placement bin 1 is a hollow columnar structure as a whole, and its inner cavity is used to place steel bars. A steel bar outlet is provided at the bottom of the steel bar placement bin 1;

[0035] Ground walking wheels 2 are arranged on the front and rear sides of the steel bar placement bin 1 and are used for walking on the slope;

[0036] A toothed rail 3 and a toothed wheel 4, wherein one toothed rail 3 is provided on each of the left and right sides of the steel bar placement bin 1, and the ends of the two toothed rails 3 are provided with anchor rods 5 for anchoring to the slope, and the toothed wheel 4 is coaxially mounted on two ground running wheels 2 located on the same side in the front-rear direction, and the toothed wheel 4 is meshed with the top of the toothed rail 3;

[0037] The steel bar baffle 6 is rotatably arranged on the left and right sides of the steel bar outlet. The steel bar baffle 6 is "U" shaped. A circular gear 7 is fixedly installed on the outside of the steel bar baffle 6. A rack 8 is arranged on the toothed rail 3. The two ends of the steel bars dropped from the Susou steel bar outlet fall into the tooth grooves 9 of the two toothed rails 3 respectively.

[0038] A travel motor 10 is provided on both sides of the left and right sides of the steel bar placement bin 1, and the power shaft of the travel motor 10 is connected to the rack wheel 4. When the circular gear 7 passes through a rack 8, it rotates exactly one circle.

[0039] The steel bar outlet, the circular gear 7 and the steel bar baffle 6 are all located at the center of the steel bar placement bin 1. The steel bars in the steel bar placement bin 1 will gather to one side of the steel bar outlet under the action of their own weight and enter the steel bar outlet when the steel bar outlet is in an idle state.

[0040] In the initial state, the steel bar baffle 6 is in an upward opening state, and receives the steel bars entering the steel bar outlet. When the circular gear 7 rotates, the steel bar baffle 6 carries the steel bars inside and rotates synchronously. When the steel bar baffle 6 is in an downward opening state, the steel bars inside will fall from the steel bar outlet and fall into the tooth groove 9 located below the steel bar outlet in the toothed rail 3. The tooth groove 9 of the toothed rail 3 is used to limit the lowered steel bars to ensure the accuracy of steel bar laying.

[0041] The anchor rod 5 is used to stably fix the toothed rail 3 on the slope, thereby providing a stable foundation for the movement of the steel bar placement bin 1. The ground walking wheel 2 directly supports the steel bar placement bin 1 on the slope, reduces the pressure of the toothed rail wheel 4 on the toothed rail 3, and thereby ensures that the toothed rail 3 better guides the displacement of the steel bar placement bin 1. The movement of the steel bar placement bin 1 is achieved by the toothed rail wheel 4 rolling on the toothed rail 3, which can make the movement of the two ends of the steel bar placement bin 1 more coordinated.

[0042] Guide sleeves 11 are fixedly installed on both left and right sides of the top of the steel bar placement bin 1 , and guide ropes 12 are passed through the guide sleeves 11 , and both ends of the guide ropes 12 are respectively fixed to the top ends of the anchor rods 5 .

[0043] By adopting the above scheme, the guide sleeve 11 and the guide rope 12 are utilized to make the steel bar placement bin 1 have stronger stability when walking. At the same time, when the guide rope 12 is in a taut state, it has a limiting effect on the steel bar placement bin 1 both in the height direction and in the horizontal direction. Therefore, combined with the limiting effect of the toothed rail 3 and the toothed wheel 4 on the steel bar placement bin 1, the stability of the steel bar placement bin 1 can be greatly improved.

[0044] Especially when laying transverse steel bars on the slope, the steel bar placement bin 1 moves along the slope surface, and the cooperation between the guide sleeve 11 and the guide rope 12 can effectively prevent the steel bar placement bin 1 from tipping over to the bottom of the slope as a whole, so as to improve its stability.

[0045] The left and right ends of the steel bar placement bin 1 are both provided with end plates 13, and the end plates 13 are threadedly mounted with the steel bar placement bin 1. By directly removing the end plates 13 from the steel bar placement bin 1, new steel bars to be laid can be added into the steel bar placement bin 1.

[0046] The steel bar placement bin 1 includes two relatively distributed bin bodies 1.1 and a connecting rod assembly connecting the two bin bodies 1.1. The connecting rod assembly includes a threaded sleeve 1.2 located in the middle and a screw rod 1.3 threadedly connected to both ends of the threaded sleeve 1.2, and the end of the screw rod 1.3 away from the threaded sleeve 1.2 is fixedly connected to the bin body 1.1 on the corresponding side.

[0047] The above solution not only reduces the overall weight of the steel bar storage bin 1, but also allows the steel bars inside the steel bar storage bin 1 to be directly observed from the outside, so that real-time processing can be performed when the steel bars are stuck, thereby improving the use effect of the device. At the same time, the two bin bodies 1.1 are used to support the two ends of the steel bars respectively, and the distance between the two bin bodies 1.1 can be adjusted according to the length of the steel bars by using the combination of the screw rod 1.3 and the wire sleeve 1.2, so as to be better applied to different on-site construction conditions.

[0048] A plurality of threaded holes 14 are equidistantly formed on the outer side of the top of the toothed rail 3 , bolts 15 are mounted on the rack 8 , and the rack 8 is bolted to the toothed rail 3 through the cooperation between the bolts 15 and the threaded holes 14 .

[0049] By adopting the above scheme, since the position of the rack 8 on the toothed rail 3 determines the position of the steel bar cutting, the position of the steel bar cutting can be adjusted by bolting the rack 8 to the toothed rail 3, and the distance between two adjacent steel bars can also be adjusted to meet the needs of erecting steel meshes on different slopes.

[0050] The rack wheel 4 is arranged on the front side of the steel bar placing bin 1, and the ground running wheel 2 located on the front side of the steel bar placing bin 1 is arranged on the inner side of the rack rail 3, and the ground running wheel 2 located on the rear side of the steel bar placing bin 1 is arranged on the outer side of the rack rail 3. The cross-section of the rack rail 3 is an inverted "T" shaped structure, and the rack 8 is installed on the outer side of the top of the rack rail 3.

[0051] By adopting the above scheme, the distance between the two ground walking wheels 2 located on the front and rear sides of the steel bar placement bin 1 is adapted to the width of the toothed rail 3. Then, the walking direction of the steel bar placement bin 1 is guided by the cooperation between the toothed rail 3 and the ground walking wheels 2 to improve its walking stability and accuracy.

[0052] When the circular gear 7 rolls half a circle on the rack 8, the steel bar baffle 6 is in a downwardly facing state, and the steel bar outlet is aligned with one of the tooth grooves 9 of the toothed rail 3. In this way, when installing the rack 8 according to different steel bar spacings, the middle position of the rack 8 can be directly aligned with the tooth groove 9 in the toothed rail 3 corresponding to the steel bar lowering position, which serves as a position reference when the rack 8 is installed.

[0053] The rack wheel 4 is arranged on the front side of the steel bar placing bin 1, and the ground running wheel 2 located on the front side of the steel bar placing bin 1 is arranged on the inner side of the rack rail 3, and the ground running wheel 2 located on the rear side of the steel bar placing bin 1 is arranged on the outer side of the rack rail 3. The cross-section of the rack rail 3 is an inverted "T" shaped structure, and the rack 8 is installed on the outer side of the top of the rack rail 3.

[0054] The toothed rail 3 is set in an inverted "T" shape, which can greatly increase its stability and support effect on the toothed rail wheel 4, and at the same time, has a better support effect on the lowered end of the steel bar. The rack 8 is located outside the lowered end of the steel bar, which can prevent the lowered steel bar from being offset, especially in the process of laying the longitudinal steel bars of the slope, after the steel bars fall into the toothed rail 3, the bottom end of the steel bars is supported by the rack 8 located below, so that the bottom ends of all laid steel bars are located on the same horizontal plane.

[0055] The toothed rail 3 includes anchor blocks 3.1 at both ends for connecting the anchor rods 5 and toothed units 3.2 connected in sequence between the two anchor blocks 3.1, and two adjacent toothed units 3.2 slide in the inner and outer directions. When the ground walking wheel 2 located at the front side of the steel bar placement bin 1 passes through the toothed block, the toothed block is pushed outward to the outermost position. When the ground walking wheel 2 located at the rear side of the steel bar placement bin 1 passes through the toothed block, the toothed block is pushed inward, so that the rack 8 clamps the steel bars.

[0056] By adopting the above scheme, before the steel bars are lowered, the ground walking wheel 2 located at the front side of the steel bar placement bin 1 first passes through the corresponding toothed unit 3.2 and pushes the toothed unit 3.2 outward, thereby maximizing the distance between the toothed units 3.2 corresponding to the two ends of the steel bars, so that the steel bars can fall more smoothly into the tooth grooves 9 of the two toothed units 3.2 after falling from the steel bar outlet.

[0057] After the steel bar falls into the two toothed units 3.2, the ground running wheel 2 at the front side leaves the toothed unit 3.2, and the ground running wheel 2 at the rear side pushes the toothed unit 3.2 inwards when passing through the toothed unit 3.2, so that the two ends of the steel bar are clamped by the two toothed units 3.2 respectively. Since the bottom of the toothed unit 3.2 is directly placed on the slope, the friction between the slope ground and the bottom of the toothed unit 3.2 is used to make the two toothed units 3.2 that move to the innermost position maintain an effective clamping effect on the lowered ends of the steel bar, thereby improving the fixing effect on the steel bar.

[0058] Furthermore, a sleeve groove 16 is provided in the middle of the inner side surface of the rack 8, and the sleeve groove 16 is used to cover the end of the steel bar. When the toothed unit 3.2 is pushed inward by the ground walking wheel 2 located at the rear side of the steel bar placement bin 1, the sleeve groove 16 will cover the end of the steel bar to further achieve a stable and effective fixing effect on the steel bar.

[0059] The first guide slope is provided on both the inner and outer sides of the toothed unit 3.2, and the second guide slope matching the first guide slope is provided on the outer side of the ground wheel 2 located at the front side of the steel bar placement bin 1 and the inner side of the ground wheel 2 located at the rear side of the steel bar placement bin 1. The cooperation between the second guide surface and the first guide surface can achieve the purpose of pushing the toothed unit 3.2 to move in the inner and outer directions.

[0060] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A soil nail wall steel mesh installation device used for foundation pit protection, characterized in that: include: The steel bar placement bin (1) is a hollow columnar structure as a whole, and its inner cavity is used to place steel bars. The bottom of the steel bar placement bin (1) is provided with a steel bar outlet; Ground walking wheels (2) are arranged on the front and rear sides of the steel bar placement bin (1) and are used for walking on the slope; A toothed rail (3) and a toothed rail wheel (4), wherein one toothed rail (3) is provided on each of the left and right sides of the steel bar placement bin (1), and the ends of the two toothed rails (3) are provided with anchor rods (5) for anchoring to the slope, and the toothed rail wheel (4) is coaxially mounted on two ground running wheels (2) located on the same side in the front-rear direction, and the toothed rail wheel (4) is meshed with the top of the toothed rail (3); A steel bar baffle (6) is rotatably arranged on the left and right sides of the steel bar outlet, the steel bar baffle (6) is in a "U" shape, a circular gear (7) is fixedly installed on the outside of the steel bar baffle (6), a rack (8) is arranged on the toothed rail (3), and the two ends of the steel bar dropped from the steel bar outlet fall into the tooth grooves (9) of the two toothed rails (3) respectively; A travel motor (10) is provided on both sides of the left and right sides of the steel bar placement bin (1), and the power shaft of the travel motor (10) is connected to the rack wheel (4). When the circular gear (7) passes through a rack (8), it rotates exactly one circle.

2. The soil nail wall steel mesh installation device for foundation pit protection as claimed in claim 1, characterized in that: Guide sleeves (11) are fixedly installed on both left and right sides of the top of the steel bar placement bin (1), a guide rope (12) is inserted into the guide sleeve (11), and both ends of the guide rope (12) are respectively fixed to the top of the anchor rod (5).

3. The soil nail wall steel mesh installation device for foundation pit protection as claimed in claim 1, characterized in that: End plates (13) are provided at both left and right ends of the steel bar placement bin (1), and the end plates (13) are threadedly mounted on the steel bar placement bin (1).

4. The soil nail wall steel mesh installation device for foundation pit protection as claimed in claim 1, characterized in that: The steel bar placement bin (1) comprises two bin bodies (1.1) that are relatively distributed and a connecting rod assembly connecting the two bin bodies (1.1); the connecting rod assembly comprises a threaded sleeve (1.2) located in the middle and a threaded rod (1.3) threadedly connected to both ends of the threaded sleeve (1.2); and one end of the threaded rod (1.3) away from the threaded sleeve (1.2) is fixedly connected to the bin body (1.1) on the corresponding side.

5. The soil nail wall steel mesh installation device for foundation pit protection as claimed in claim 1, characterized in that: A plurality of bolts (14) are equidistantly provided on the outer side of the top of the toothed rail (3), a bolt (15) is installed on the toothed rack (8), and the toothed rack (8) is bolted to the toothed rail (3) through the cooperation of the bolt (15) and the threaded hole (14).

6. The soil nail wall steel mesh installation device for foundation pit protection as claimed in claim 1, characterized in that: When the circular gear (7) rolls half a circle on the rack (8), the steel bar baffle (6) is in a state of opening downward, and the steel bar outlet is aligned with one of the tooth grooves (9) of the toothed rail (3).

7. The soil nail wall steel mesh installation device for foundation pit protection as claimed in claim 1, characterized in that: The rack wheel (4) is arranged at the front side of the steel bar placement bin (1), and the ground running wheel (2) located at the front side of the steel bar placement bin (1) is arranged on the inner side of the rack rail (3), and the ground running wheel (2) located at the rear side of the steel bar placement bin (1) is arranged on the outer side of the rack rail (3), the cross section of the rack rail (3) is an inverted "T"-shaped structure, and the rack (8) is installed on the outer side of the top of the rack rail (3).

8. The soil nail wall steel mesh installation device for foundation pit protection as claimed in claim 7, characterized in that: The toothed rail (3) comprises anchor blocks (3.1) at both ends for connecting anchor rods (5) and toothed units (3.2) connected in sequence between the two anchor blocks (3.1), and two adjacent toothed units (3.2) are slidably matched in the inner and outer directions. When the ground running wheel (2) located at the front side of the steel bar placement bin (1) passes the toothed block, the toothed block is pushed outward to the outermost position. When the ground running wheel (2) located at the rear side of the steel bar placement bin (1) passes the toothed block, the toothed block is pushed inward, so that the rack (8) clamps the steel bar.

9. The soil nail wall steel mesh installation device for foundation pit protection as claimed in claim 8, characterized in that: A sleeve groove (16) is provided in the middle of the inner side surface of the rack (8), and the sleeve groove (16) is used to sleeve the end of the steel bar.

10. The soil nail wall steel mesh installation device for foundation pit protection as claimed in claim 8, characterized in that: The toothed unit (3.2) is provided with a first guide bevel on both the inner and outer sides, and a second guide bevel matched with the first guide bevel is provided on the outer side of the ground running wheel (2) located at the front side of the steel bar placement bin (1) and the inner side of the ground running wheel (2) located at the rear side of the steel bar placement bin (1).