RTO system for oil field and waste gas treatment method
By combining VOCs waste gas and oil field associated gas in the oil field, the heat storage combustion system is used to complete the waste gas treatment without additional fuel gas, the safety and environmental protection problems of VOCs waste gas treatment in the oil field are solved, and efficient waste gas is achieved Removal and cost savings.
Patent Information
- Application Number
- CN202411411497.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-10
- Publication Date
- 2024-11-29
AI Technical Summary
The unorganized emission of associated gas in the oil field or discharged directly into the atmosphere after simple combustion, resulting in small amount of VOCs waste gas, large fluctuations in concentration, lack of collection and treatment measures, and poses safety risks and environmental protection problems.
An RTO system for oil fields is designed, combining VOCs exhaust gas and oil field companion gas for treatment, VOCs gas and first gas are sent through the first intake system, and the second intake system is sent to the oil field companion gas and combustion-assisted air. The exhaust gas treatment is completed without additional fuel gas using a heat storage combustion system.
It realizes efficient treatment of VOCs exhaust gas, reduces safety risks and environmental protection issues, saves investment costs for equipment operation, and solves the problems of unorganized emissions and insufficient combustion of oilfield associated gas.
Smart Images

Figure CN119042646A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to a processing system, and in particular to an RTO system and a processing method for an oil field. Background Art
[0002] Some oilfield associated gas is discharged in an unorganized manner or discharged directly into the atmosphere after simple combustion. The second is the exhaust of the oil tank breathing valve of the oilfield. The VOCs waste gas volume is small and the concentration fluctuates greatly when the oil tanker is loading and unloading oil products. There are no collection and treatment measures for VOCs waste gas, resulting in unorganized emissions. Such treatment has great safety risks and environmental problems. Summary of the invention
[0003] Purpose of the invention: In order to solve the above problems, the present application provides an RTO system and treatment method for oil fields. The RTO system for oil fields of the present application combines VOCs waste gas treatment with oil field associated gas to complete waste gas treatment without using additional fuel gas.
[0004] Technical solution: The RTO system for oil fields in the embodiment of the present application includes a first air intake system, a second air intake system and a thermal storage combustion system; the first air intake system is used to feed VOCs gas and a first gas into the thermal storage combustion system; the second air intake system is used to feed oilfield associated gas and combustion-supporting air into the thermal storage combustion system; the first gas is at least used to purge the thermal storage combustion system.
[0005] In some embodiments, the first air intake system includes a first pipeline for conveying VOCs gas, and a first valve is disposed on the first pipeline;
[0006] The first air intake system further comprises a second pipeline for conveying the first gas, and a second valve is arranged on the second pipeline;
[0007] The outlets of the first pipeline and the second pipeline are respectively communicated with the first fan.
[0008] In some embodiments, the outlets of the first pipeline and the second pipeline are respectively connected to the third pipeline, the outlet of the third pipeline is connected to the first fan; the outlet of the first fan is connected to the fourth pipeline.
[0009] In some embodiments, the second air intake system includes a fifth pipeline, the fifth pipeline is used to feed oilfield associated gas; the fifth pipeline is connected to the burner main fire pipeline and the burner ignition pipeline respectively;
[0010] The second air intake system further includes a sixth pipeline, and the sixth pipeline is used for delivering combustion air.
[0011] In some embodiments, the heat storage combustion system includes a heat storage combustion chamber, which includes a first heat storage chamber, a second heat storage chamber and a combustion chamber, and a burner is arranged at the top of the combustion chamber.
[0012] In some embodiments, the burner is respectively connected to the burner main fire pipeline and the burner ignition pipeline; the burner is also connected to the sixth pipeline.
[0013] In some embodiments, the first heat storage chamber is connected to the fourth pipeline through an eighth pipeline, and the second heat storage chamber is connected to the fourth pipeline through a ninth pipeline; a third valve is provided on the eighth pipeline, and a fourth valve is provided on the ninth pipeline.
[0014] In some embodiments, the RTO system suitable for oil fields further includes a circulation system, which includes a buffer tank; the first heat storage chamber and the second heat storage chamber are respectively provided with a first outlet and a second outlet, and the first outlet and the second outlet are respectively connected to the buffer tank.
[0015] In some embodiments, the buffer tank is connected to a third fan, and an outlet of the third fan is connected to an inlet of the first fan.
[0016] The present invention also provides a method for treating waste gas, comprising the following steps:
[0017] Sending a first gas into the thermal storage combustion system through a first air intake system to purge the thermal storage combustion system;
[0018] After the purging is completed, the oilfield associated gas and the combustion-supporting air are fed into the thermal storage combustion system through the second air intake system, and the oilfield associated gas and the combustion-supporting air are burned in the combustion chamber of the thermal storage combustion system, so that the thermal storage combustion system reaches the temperature for treating the exhaust gas;
[0019] Sending VOCs gas into the regenerator of the regenerative combustion system through the first air intake system, treating the VOCs gas, and discharging the gas after the treatment through the regenerative combustion system;
[0020] The residual VOCs gas in the process of treating the VOCs gas by the thermal storage combustion system is sent back into the thermal storage combustion system through the circulation system.
[0021] In some embodiments, when the concentration of the VOCs gas introduced from the first pipeline is too high, the second valve is opened, and the first gas is introduced from the second pipeline to dilute the VOCs gas, and the diluted VOCs gas is sent to the heat storage combustion chamber for treatment.
[0022] Beneficial effects: The present application provides an RTO system for oil fields, the system comprising a first air intake system, a second air intake system and a thermal storage combustion system; the first air intake system is used to feed VOCs gas and a first gas into the thermal storage combustion system; the second air intake system is used to feed oilfield associated gas and combustion-supporting air into the thermal storage combustion system; the first gas is at least used to purge the thermal storage combustion system. The RTO system for oil fields of the present application combines VOCs waste gas treatment with oilfield associated gas, and completes waste gas treatment without using additional fuel gas. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 This is a schematic diagram of the structure of the RTO system used in the oil field in the embodiment of the present application;
[0024] Figure 2 This is a schematic diagram of the structure of the first air intake system in the embodiment of the present application;
[0025] Figure 3 This is a schematic diagram of the structure of the heat storage combustion system in the implementation of this application;
[0026] Figure 4 Schematic diagram of the structure of the circulation system in the embodiment of the present application. DETAILED DESCRIPTION
[0027] The solution of the present application is further described below in conjunction with the accompanying drawings.
[0028] In some embodiments, the RTO system for oil fields of the present application includes a first air intake system 100, such as Figure 1 and Figure 2 As shown, the first air intake system 100 includes a first pipeline 101 for conveying VOCs gas. The first pipeline 101 is provided with a first valve 102. The first valve 102 serves as a VOCs gas cut-off valve for controlling the opening and closing of the VOCs gas pipeline.
[0029] like Figure 2 As shown, in some embodiments, the first air intake system 100 further includes a second pipeline 103, and the second pipeline 103 is used to introduce a first gas. In some embodiments, the first gas can be any one or a mixture of nitrogen, argon or air. A second valve 104 is provided on the second pipeline 103. The second valve 104 serves as a gas regulating valve, which is used to control the gas input amount and can also control the opening and closing of the second pipeline 103. In some embodiments, the first gas is air. In some embodiments, when the concentration of the VOCs gas introduced from the first pipeline 101 is too high, air needs to be introduced from the second pipeline 103 to dilute the VOCs gas. At this time, the introduced air contains oxygen. When the diluted VOCs gas is sent to the regenerative combustion chamber 30 for treatment, the oxygen in the air can improve the oxidation efficiency of the VOCs gas.
[0030] In some embodiments, the pipeline outlets of the first pipeline 101 and the second pipeline 103 are connected to the first fan 105 at the same time. In other embodiments, the pipeline outlets of the first pipeline 101 and the second pipeline 103 are connected to the third pipeline 106, and the gas delivered by the first pipeline 101 and the second pipeline 102 is delivered to the first fan 105 through the third pipeline 106. The setting of the third pipeline 106 facilitates the maintenance of the overall system and can simplify the pipeline setting. In the present application, the pipeline and the component such as the fan or the pipeline are connected by a flange (the same below), such as the outlet of the third pipeline 106 is connected to the inlet of the first fan 105 by a flange.
[0031] In some embodiments, the first air intake system 100 further includes a fourth pipeline 107, and the fourth pipeline 107 is connected to the outlet of the first fan 105. The outlet of the fourth pipeline 107 is respectively connected to two air intake branches, and the two air intake branches are respectively an eighth pipeline 305 and a ninth pipeline 306. The eighth pipeline 305 is connected to the first heat storage chamber 301, and the ninth pipeline 306 is connected to the second heat storage chamber 302. After passing through the fourth pipeline 107, the VOCs gas is respectively sent to the first heat storage chamber 301 and the second heat storage chamber 302 through the eighth pipeline 305 and the ninth pipeline 306.
[0032] like Figure 1 As shown, the second air intake system 200 in the embodiment of the present application includes a fifth pipeline 201, which is used to deliver oilfield associated gas and serves as an oilfield associated gas intake main; the second air intake system 200 also includes a sixth pipeline 202, which is used to deliver combustion-supporting air, and the outlet of the sixth pipeline 202 is connected to the second fan 203, and the outlet of the second fan 203 is connected to the heat storage combustion system 300.
[0033] In some embodiments, the fifth pipeline 201 is connected to the burner main fire pipeline 204 and the burner ignition pipeline 205 respectively. In some embodiments, the fifth pipeline 201 is connected to the burner main fire pipeline 204 and the burner ignition pipeline 205 by a three-way flange.
[0034] In some embodiments, the second air intake system 200 further includes a seventh pipeline 206 , the inlet of the seventh pipeline 206 is connected to the outlet of the second fan 203 , and the outlet of the seventh pipeline 206 is connected to the burner 304 in the heat storage combustion system 300 .
[0035] Regenerative thermal oxidizer is referred to as RTO. Volatile organic matter in the exhaust gas reacts with oxygen in the air in the high temperature environment (above 760℃) in the oxidation furnace to produce water and carbon dioxide, which are discharged into the atmosphere. The intake air is heated by the regenerative ceramics, and the burner is used to heat it to the set temperature for oxidation and decomposition. When it is discharged, the regenerative ceramics absorb most of the heat, and the airflow direction is switched regularly by the airflow switching valve, cyclically absorbing and releasing heat of the regenerative ceramics. The high-temperature gas generated by oxidation flows through a special ceramic regenerative body, causing the ceramic body to heat up and "storage heat". This "heat storage" is used to preheat the subsequent organic waste gas, thereby saving fuel consumption for heating the waste gas. The ceramic regenerative body is divided into two (including two) or more zones or chambers. Each regenerative chamber undergoes the procedures of heat storage-heat release in turn, over and over again, and works continuously.
[0036] During the design and operation of conventional RTO, the equipment usually handles a large air volume, and the fuel gas of the burner is usually natural gas, which requires the configuration of additional natural gas system transportation pipelines, increasing additional primary investment costs and natural gas operation energy consumption costs. This system uses oil field associated gas as fuel, and the RTO system burner only needs to be configured with the corresponding air intake valve group like the conventional RTO, and does not need to be configured with a long transportation pipeline.
[0037] In some embodiments, Figure 3 As shown, the main body of the heat storage combustion system 300 is the heat storage combustion chamber 30, which includes a first heat storage chamber 301, a second heat storage chamber 302 and a combustion chamber 303. The combustion chamber 303 is located in the middle of the two heat storage chambers. The first heat storage chamber 301 and the second heat storage chamber 302 are filled with heat storage ceramics. The first heat storage chamber 301, the second heat storage chamber 302 and the combustion chamber 303 are welded and manufactured as a whole.
[0038] In some embodiments, a burner 304 is provided on the top of the combustion chamber 303, and the burner 304 is connected to the burner main fire pipeline 204 and the burner ignition pipeline 205 respectively. In some embodiments, the burner fire pipeline 204, the burner ignition pipeline 205 and the burner 304 are connected by flanges.
[0039] In some embodiments, the first heat storage chamber 301 is connected to the fourth pipeline 107 via the eighth pipeline 305, and the second heat storage chamber 302 is connected to the fourth pipeline 107 via the ninth pipeline 306. In some embodiments, the eighth pipeline 305 is provided with a third valve 307, and the ninth pipeline 306 is provided with a fourth valve 308.
[0040] In some embodiments, the first heat storage chamber 301 is also connected to the twelfth pipeline 315, the second heat storage chamber 302 is connected to the thirteenth pipeline 316, the twelfth pipeline 315 and the thirteenth pipeline 316 are connected to the exhaust system 500, and the twelfth pipeline 315 is provided with a sixth valve 313, and the thirteenth pipeline 316 is provided with a seventh valve 314.
[0041] In some embodiments, the RTO system suitable for oil fields further includes a circulation system 400, which includes a buffer tank 401; the first heat storage chamber 301 and the second heat storage chamber 302 are respectively provided with a first outlet 309 and a second outlet 310, and the first outlet 309 and the second outlet 310 are respectively connected to the buffer tank 401.
[0042] In some embodiments, the circulation system 400 includes a third fan 402, which is connected to the buffer tank 401. The third fan 402 is used to send the gas in the buffer tank 401 into the first air intake system 100. In some specific embodiments, the outlet of the third fan 402 is connected to the inlet of the first fan 105, such as the third fan 402 is connected to the third pipeline 106 through the tenth pipeline 403. The first outlet 309 is connected to the buffer tank 401 through the first circulation branch pipe 311, and the second outlet is connected to the buffer tank 401 through the second circulation branch pipe 312; in some embodiments, the first circulation branch pipe 311 and the second circulation branch pipe 312 are connected to the buffer tank 401 through the eleventh pipeline 406. In some embodiments, the eleventh pipeline 406 is provided with a fifth valve 404. In some embodiments, the buffer tank 401 is equipped with a safety valve 405 to adjust the pressure in the box to ensure the safe use of the equipment.
[0043] During the operation of the regenerative combustion system 300, the second fan 203 introduces fresh air at room temperature and oilfield associated gas to form a flame in the burner 304 to maintain the set temperature of the combustion chamber; the two regenerative chambers perform the air intake-air outlet process in turn. The third fan 402 introduces the residual waste gas in the regenerative chamber after the air intake stage is completed into the buffer tank 401 for temporary storage, and finally introduces it into the first pipeline 101 to mix with the VOCs waste gas for further treatment, so as to prevent the regenerative chamber from switching to the air outlet stage and directly discharging the residual untreated VOCs waste gas into the chimney, so as to ensure the high removal efficiency of the RTO equipment.
[0044] From the above description, it can be seen that the fuel gas used in the RTO system for oil fields in this application is oil field associated gas. While solving environmental and safety problems such as unorganized emissions and incomplete combustion of oil field associated gas, no additional fuel gas is put into use, saving equipment operation investment costs. The RTO system uses oil field associated gas as fuel, and at the same time can solve the problem of treating unorganized VOCs waste gas generated by oil tank breathing gas, oil tank truck loading and unloading of oil products, and dirty oil pools, so that it meets emission standards. In addition, the waste gas from oil tank breathing gas, oil tank truck loading and unloading of oil products, and dirty oil pools in oil fields is usually tens of cubic meters or hundreds of cubic meters, and the amount of waste gas is not large. The equipment can be designed as a skid block, and the high degree of integration facilitates transportation to the waste gas generation point, which can solve the problem of scattered waste gas emission sources.
[0045] The embodiment of the present application also provides a method for treating exhaust gas in an RTO system of an oil field, comprising the following steps:
[0046] RTO startup phase:
[0047] When RTO is started, the first valve 102 is closed, the second valve 104 is opened, the third valve 307 and the sixth valve 313, the fourth valve 308 and the seventh valve 314 are switched on and off respectively; fresh air is introduced from the second pipeline 103 through the first fan 105 to the combustion chamber 303, the first heat storage chamber 301, and the second heat storage chamber 302 for purging, which lasts for 5 minutes to 10 minutes.
[0048] After the purge procedure is completed, the combustion air enters the burner 304 through the sixth pipeline 202, the second fan 203 and the seventh pipeline 206, and the oilfield associated gas enters the burner 304 through the fifth pipeline 201, the burner main fire pipeline 204, and the burner ignition pipeline 205. First, a small fire is lit, and then a large fire is lit after the flame is stable. It burns in the combustion chamber 303. After the combustion chamber 303 reaches the set temperature and the RTO is ready to process the exhaust gas, the first valve 102 is opened and the second valve 104 is closed, and the exhaust gas is introduced into the heat storage combustion chamber 30 for processing.
[0049] When the concentration of the VOCs gas introduced from the first pipeline 101 is too high, the second valve 104 is opened, and air is introduced from the second pipeline 103 to dilute the VOCs gas. The diluted VOCs gas is sent from the third pipeline 106 to the heat storage combustion chamber 30 for treatment.
[0050] The RTO goes through a startup phase, at which time the combustion chamber 303 has reached a set temperature. In some embodiments, the set temperature of the combustion chamber 303 is 800°C to 1100°C.
[0051] Phase 1: The first regenerator 301 takes in air and the second regenerator 302 exhausts air. The VOCs waste gas passes through the first pipeline 101 and then through the first fan 105 for boosting, and then passes through the fourth pipeline 107 to enter the first regenerator 301 and then enter the combustion chamber 303. At this time, the third valve 307 and the seventh valve 314 are opened, and the remaining sixth valve 313 and the fourth valve 308 are closed. The VOCs waste gas first passes through the heat storage ceramics of the first regenerator 301 and enters the combustion chamber 303 for oxidation, and then enters the heat storage ceramics of the second regenerator 302 to recover heat, and then passes through the thirteenth pipeline 316 and enters the exhaust main pipe to be discharged as the chimney of the emission system 500.
[0052] Phase 2: The second heat storage chamber 302 takes in air and the first heat storage chamber 301 exhausts air. The VOCs waste gas passes through the first pipeline 101 and then through the first fan 105 to boost pressure and then enter the second heat storage chamber 302 through the fourth pipeline 107. At this time, the fourth valve 308 of the second heat storage chamber 302 is opened, the sixth valve 313 is opened, and the remaining third valves 307 and seventh valves 314 are closed. Before the above switching action is executed, since the first heat storage chamber 301 takes in air in phase 1, some untreated VOCs waste gas will remain at this time and need to be circulated and treated. Before the above valve switching, the fifth valve 404 on the eleventh pipeline 406 is opened, and the remaining waste gas passes through the first circulation branch pipe 311 and then through the eleventh pipeline 406. It is boosted by the third fan 402 and enters the buffer tank 401 for temporary storage and then enters the first pipeline 101 to improve the equipment processing efficiency. The buffer tank 401 equipment is equipped with a safety valve 405 to adjust the pressure in the box to ensure the safe use of the equipment. After the cycle is completed, the exhaust gas is first preheated by the heat storage ceramics in the second heat storage chamber 302 and then enters the combustion chamber 303 for oxidation. Then, it enters the heat storage ceramics in the first heat storage chamber 301 to recover the heat, and then enters the exhaust main pipe after passing through the twelfth pipeline 315 to be discharged through the chimney.
[0053] The above is one cycle of the RTO. The switching time of the switching valve is about 60 to 180 seconds. The fuel gas in all stages of this RTO system uses oilfield associated gas.
[0054] The RTO system of the embodiment of the present application is used to treat VOCs gas. The specific parameters are: the RTO combustion chamber is set at 800°C, the VOCs exhaust gas concentration sent from the inlet of the first pipeline 101 is 3000mg / m 3 The first fan 105 controls the exhaust gas volume at 1000m 3 / h, the valve switching time in the RTO system is 180s. The valve opening and closing time is 1s.
[0055] Stage 1: The exhaust gas enters the first regenerator 301 for treatment, passes through the combustion chamber 303, and finally is discharged through the second regenerator 302. The exhaust gas concentration discharged from the second regenerator 302 is 45 mg / m3 , the equipment processing efficiency can reach 98.5%.
[0056] Phase 2: After running for 180s, the valve starts to switch. The valve switch time of 1s will cause the exhaust gas in the RTO heat storage combustion chamber 30 to leak directly into the chimney without treatment. At this time, the fifth valve 404 in the circulation system 400 is opened in advance when the switching valve (including the third valve 307, the fourth valve 308, the sixth valve 313 and the seventh valve 314) is switched. At this time, the exhaust gas leaked within 1s will enter the buffer tank 401. At this time, the exhaust gas volume flowing into the third fan 402 is about 0.28m 3 The exhaust gas temporarily stored in the buffer tank 401 is pressurized by the third fan 402 and transported to the third pipeline 106, where it is mixed with the front-end exhaust gas sent in from the first pipeline 101 and then enters the RTO equipment for treatment.
Claims
1. An RTO system for oil fields, characterized in that: The invention comprises a first air intake system (100), a second air intake system (200) and a thermal storage combustion system (300); the first air intake system (100) is used to feed VOCs gas and a first gas into the thermal storage combustion system (300); the second air intake system (200) is used to feed oilfield associated gas and combustion-supporting air into the thermal storage combustion system (300); and the first gas is at least used to purge the thermal storage combustion system (300).
2. The RTO system for oil fields according to claim 1, characterized in that: The first air intake system (100) comprises a first pipeline (101) for conveying VOCs gas, and a first valve (102) is provided on the first pipeline (101); The first air intake system (100) further comprises a second pipeline (103) for conveying the first gas, and a second valve (104) is provided on the second pipeline (103); The outlets of the first pipeline (101) and the second pipeline (103) are respectively connected to the first fan (105).
3. The RTO system for oil fields according to claim 2, characterized in that: The outlets of the first pipeline (101) and the second pipeline (103) are respectively connected to the third pipeline (106); the outlet of the third pipeline (106) is connected to the first fan (105); and the outlet of the first fan (105) is connected to the fourth pipeline (107).
4. The RTO system for oil fields according to claim 3, characterized in that: The second air intake system (200) comprises a fifth pipeline (201), and the fifth pipeline (201) is used to feed oilfield associated gas; the fifth pipeline (201) is respectively connected to the burner main fire pipeline (204) and the burner ignition pipeline (205); The second air intake system (200) further comprises a sixth pipeline (202), wherein the sixth pipeline (202) is used for introducing combustion-supporting air.
5. The RTO system for oil fields according to claim 4, characterized in that: The regenerative combustion system (300) comprises a regenerative combustion chamber (30), wherein the regenerative combustion chamber (30) comprises a first regenerative chamber (301), a second regenerative chamber (302) and a combustion chamber (303), and a burner (304) is arranged at the top of the combustion chamber (303).
6. The RTO system for oil fields according to claim 5, characterized in that: The burner (304) is respectively connected to the burner main fire pipeline (204) and the burner ignition pipeline (205); the burner (304) is also connected to the sixth pipeline (202).
7. The RTO system for oil fields according to claim 5, characterized in that: The first heat storage chamber (301) is connected to the fourth pipeline (107) via an eighth pipeline (305), and the second heat storage chamber (302) is connected to the fourth pipeline (107) via a ninth pipeline (306); a third valve (307) is provided on the eighth pipeline (305), and a fourth valve (308) is provided on the ninth pipeline (306).
8. The RTO system for oil fields according to claim 5, characterized in that: The RTO system suitable for oil fields further comprises a circulation system (400), wherein the circulation system (400) comprises a buffer tank (401); the first heat storage chamber (301) and the second heat storage chamber (302) are respectively provided with a first outlet (309) and a second outlet (310), and the first outlet (309) and the second outlet (310) are respectively communicated with the buffer tank (401).
9. The RTO system for oil fields according to claim 5, characterized in that: The buffer tank (401) is connected to the third fan (402), and the outlet of the third fan (402) is connected to the inlet of the first fan (105).
10. A method for treating waste gas, characterized in that: The following steps are involved: Introducing a first gas into the thermal storage combustion system (300) through a first air intake system (100) to purge the thermal storage combustion system (300); After the purging is completed, oilfield associated gas and combustion-supporting air are introduced into the thermal storage combustion system (300) through the second air intake system (200), and the oilfield associated gas and the combustion-supporting air are burned in the combustion chamber of the thermal storage combustion system (300), so that the thermal storage combustion system (300) reaches a temperature for treating exhaust gas; Sending VOCs gas into a regenerator of a regenerative combustion system (300) through a first air intake system (100), treating the VOCs gas, and discharging the gas treated by the regenerative combustion system (300); The residual VOCs gas in the process of treating the VOCs gas in the thermal storage combustion system (300) is sent back into the thermal storage combustion system (300) through the circulation system (400).