By adding tracks in the shock wind tunnel and moving the backup shock tube, adjusting the ratio of the drive section to the driven section, the problem of short test time of the shock wind tunnel is solved, and the test time is extended and the data accuracy is improved. in various operating states.

CN119043639APending Publication Date: 2024-11-29CHINA ACAD OF AEROSPACE AERODYNAMICS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411137251.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

The test time of shock wave wind tunnel is extremely short, and the prior art is difficult to effectively extend, and existing methods may increase the problems of airflow erosion and damage to the piston in certain operating conditions.

Method used

By adding a new track next to the shock tube of the wind tunnel body, moving the backup shock tube, and connecting it to the drive section or the driven section through the rail change mechanism, adjusting the ratio of the drive section to the driven section to extend the test time .

Benefits of technology

It achieves the extension of shock wind tunnel test time, is suitable for a variety of operating states, is simple and easy to use, and improves the accuracy and richness of test data.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119043639A_ABST
    Figure CN119043639A_ABST
Patent Text Reader

Abstract

The invention relates to a method for prolonging the test time of a shock tunnel through simple structure change, and the method comprises the steps: additionally arranging a new track beside a shock tube of a wind tunnel body, enabling the new track to be connected with a track of the wind tunnel body through a track transfer mechanism, and placing a standby shock tube on the new track; the film clamping mechanism is loosened, the positions of the driving section, the driven section and the film clamping section are moved, and a placement space is reserved for the standby shock tube; the standby shock tube is moved to the wind tunnel body track from the newly-arranged track through the track transfer mechanism, and the standby shock tube is connected with the driving section or the driven section through the flange; and placing the diaphragm, reconnecting the driving section, the driven section and the diaphragm clamping section, and starting a wind tunnel test. The method can cope with various operation states, and the shock tunnel test time is effectively prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of aerodynamic tests, and relates to a method for increasing the test time of a shock wind tunnel by simple structural changes, and can optimize the operating state of ground equipment of the shock wind tunnel type. Background Art

[0002] A shock wave wind tunnel is a wind tunnel test device that uses the high-temperature and high-pressure gas generated by shock wave compression to expand and accelerate through the nozzle, and obtains a short-term stable high-speed flow field at the nozzle outlet. It is characterized by a wide range of Mach numbers and Reynolds numbers. Depending on the driving method, it can obtain enthalpy values ​​far exceeding those of conventional wind tunnels. It is an important research tool for research in the fields of hypersonic flow and gas non-equilibrium effects. However, its test time is relatively short, generally in the order of milliseconds, which poses a huge challenge to test observation technology.

[0003] The test time of a shock tunnel refers to the time it can provide a stable flow field and the time it can be used to carry out test measurements. It is an important indicator parameter for measuring the performance of a wind tunnel. As the test time increases, the accuracy and richness of the test data can increase. Therefore, how to obtain a longer test time is the continuous pursuit of all shock tunnel designers. Previous researchers have conducted a number of studies on this and achieved corresponding results, such as stitching operation, adding drive balls, etc., but they all have their limitations. For example, stitching operation is a special operating state that needs to meet specific drive parameters and cannot meet the needs of a wide range of test parameters. Moreover, the test time it can obtain is still limited by the wind tunnel structure. Adding drive balls can be seen as a disguised increase in the length of the drive section, but the length space required is small, which can weaken the impact of the slow expansion wave on the test time. However, when operating at a lower Mach number, this structure is a burden. Not only can it not extend the time, but it will increase the scouring of the test piece by the airflow and aggravate the damage to the piston (unique to the gun wind tunnel operation mode). Summary of the invention

[0004] The technical problem solved by the present invention is: to overcome the deficiencies of the prior art and to propose a method for increasing the shock wind tunnel test time by simple structural changes, so as to cope with various operating conditions and increase the shock wind tunnel test time.

[0005] The solution of the present invention is: a method for increasing the shock tunnel test time by simple structural changes, comprising the following steps:

[0006] S1. Add a new track next to the wind tunnel body shock tube, connect the new track with the wind tunnel body track through the track change mechanism, and place the spare shock tube on the new track;

[0007] S2, loosen the film clamping mechanism, move the driving section, driven section, and film clamping section to leave space for the spare shock tube;

[0008] S3, moving the spare shock tube from the newly set track to the wind tunnel main track through the track changing mechanism, and connecting the spare shock tube to the driving section or the driven section through the flange;

[0009] S4. Place the diaphragm, reconnect the driving section, driven section, and diaphragm section, and start the wind tunnel test.

[0010] Furthermore, the newly-installed track is parallel to the wind tunnel main body track and is spaced 2 to 5 meters apart from each other; the spare shock tube on the newly-installed track can enter the upstream and downstream of the wind tunnel main body track through a track-changing mechanism.

[0011] Furthermore, the track-changing mechanism realizes structural changes in the following manner: two forks are respectively set upstream and downstream of the newly-established track, and the branched connecting tracks are connected to the wind tunnel main body track. The path curve of the connecting tracks is smooth, and the intersections at both ends are tangent to the wind tunnel main body track and the newly-established track respectively.

[0012] Furthermore, the positions of the mobile driving section, the driven section, and the clamping section are specifically:

[0013] If a higher Mach number test is conducted, the driving section is moved upstream, the driven section and the diaphragm section are moved downstream, and the length of the vacant track left is twice the length of the spare shock tube; if a lower Mach number test is conducted, the driving section and the diaphragm section are moved upstream, and the driven section is moved downstream, and the length of the vacant track left is twice the length of the spare shock tube; the lower Mach number test is a wind tunnel test with a Mach number less than or equal to 8, and the higher Mach number test is a wind tunnel test with a Mach number greater than 8.

[0014] Furthermore, the step of connecting the standby shock tube to the driving section or the driven section is as follows:

[0015] When conducting tests at lower Mach numbers, the spare shock tube is connected to the driven section;

[0016] When conducting tests at higher Mach numbers, a spare shock tube is connected to the drive section.

[0017] Furthermore, the length ΔL of the spare shock tube does not exceed half of the length L1 of the driving section. When the spare shock tube is connected to the driven section, the length ratio of the newly formed driven section to the driving section is 1:3 to 1:3.6; when the spare shock tube is connected to the driving section, the length ratio of the newly formed driving section to the driven section is 1:1 to 3:4.

[0018] Furthermore, for the wind tunnel test at the beginning, for the lower Mach number test condition, the test time is limited by the amount of test gas, and the relationship between the increased test time and the original test time is:

[0019]

[0020] For the test conditions with higher Mach numbers, the test time is affected by the reflected expansion wave. The relationship between the increased test time and the original test time is:

[0021]

[0022] Wherein, t1 is the original available test time of the lower Mach number test condition, t2 is the available test time after the lower Mach number test condition is increased, t3 is the original available test time of the higher Mach number test condition, t4 is the available test time after the higher Mach number test condition is increased, ΔL is the length of the spare shock tube, L1 is the length of the driving section, and L2 is the length of the driven section.

[0023] The beneficial effects of the present invention compared with the prior art are:

[0024] (1) The method proposed by the present invention for increasing the test time of a shock tunnel by simple structural changes is simple, easy to use, and highly adjustable. By changing the ratio of the driving section to the driven section of the shock tunnel, the wave system during the operation of the shock tunnel is optimized, thereby increasing the test time of the shock tunnel.

[0025] (2) The present invention performs variable structure design under higher Mach number test conditions and lower Mach number test conditions respectively, and is effectively applicable to various operating conditions and has strong versatility. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a typical shock wave wind tunnel structure;

[0027] Figure 2 The schematic diagram of the wave system and time extension for the shock tunnel operation;

[0028] Figure 3 It is a schematic diagram of the structural change scheme;

[0029] Figure 4 A flow chart of a method for increasing shock tunnel test time through simple structural changes. DETAILED DESCRIPTION

[0030] The present invention will be further described below in conjunction with the accompanying drawings.

[0031] The structure of a typical shock tunnel is as follows: Figure 1As shown, from upstream to downstream (from left to right) are the driving section, the first clamping section, the driven section, the second clamping section, the nozzle, the test section, and the vacuum tank. The wind tunnel parts except the test section and the vacuum tank are supported by the bracket of the pulley group and are located on the guide rail. The two clamping sections can be loosened and connected by the clamping mechanism, and each section can move left and right within the range allowed by the space. The present invention mainly relates to the driving section, the driven section, and the first clamping section. The clamping section or the clamping mechanism in the text corresponds to the first clamping section. The end of the shock wind tunnel test time is mainly determined by two factors, one is the exhaustion of the test gas, and the other is the arrival of the upstream expansion wave, which destroys the stability of the total pressure in the front chamber. When the state parameters of the driving gas remain unchanged, increasing the volume of the driven section can delay the exhaustion of the test gas (when the diameter of the tube body is constant, it can also be considered as increasing the length), and increasing the length of the driving section can delay the influence of the expansion wave. Therefore, increasing the length of the shock wind tunnel is an effective means to extend its test time.

[0032] like Figure 2 As shown, the horizontal axis is position, the vertical axis is time, point O is the diaphragm separating the driving section and the driven section, and is the starting point of the shock wave and expansion wave. Point A is the original upstream end face of the driving section, and the driving section tube length is L1. Point B is the original downstream end face of the driven section, and the driven section tube length is L2. When operating in the low Mach number typical reflection shock wave mode (Mach number ≤ 8), the incident shock wave is reflected at the downstream end face of the driven section (point D), meets the contact surface, and reaches the downstream end face (point E) after the contact surface slows down, that is, the test gas is exhausted. The time t1 between DE is the available test time. If the driven section is extended to B', then the effective test time becomes t2. If the wave velocity attenuation caused by the extended propagation distance is not considered, it can be calculated as follows:

[0033]

[0034] Wherein, ΔL is the length of the spare shock tube.

[0035] When running at a higher Mach number (Mach number>8), the reflected shock wave is stronger, the contact surface decelerates more significantly after the reflected shock wave acts, and finally arrives at the downstream end face later. In this case, the test time depends on the arrival of the reflected expansion wave head. The reflected wave head propagates to the left after starting from point O, propagates to the right after being reflected at the upstream end face (point C), and finally arrives at the downstream end face (point F). The test time is the time difference t3 of DF. Similarly, if the upstream end face is extended to A', the test time is extended to t4. Without considering attenuation, the approximate ones are:

[0036]

[0037] However, in practice, considering the impact of shock wave attenuation and the limitation of building land size, the overall length of the wind tunnel cannot be too long. As mentioned earlier, simply lengthening a certain section is beneficial to some test conditions, but may be harmful to other conditions. Therefore, it is necessary to make rational use of limited space and try to convert it into factors that are beneficial to the test time. Here you can choose to provide a spare shock tube and add it to the driving section or the driven section when needed. Since the shock wind tunnel will have a strong instantaneous recoil during operation, its main body is generally located on a track through rollers. In this case, a railway-like track-changing structure can be used to simply move the spare shock tube to the track of the wind tunnel main structure, thereby completing the structural change, such as Figure 3 As shown. If necessary, multiple spare shock tubes of different lengths can also be prepared.

[0038] Therefore, the present invention proposes a method for increasing the shock tunnel test time by simple structural changes, such as Figure 4 As shown, the following steps are included:

[0039] S1. Add a new track next to the shock tube of the wind tunnel body, connect the new track with the wind tunnel body track through the track changing mechanism, and place the spare shock tube on the new track.

[0040] The newly built track is parallel to the wind tunnel track, with a spacing of 2 to 5 meters. Two forks are set at the upstream and downstream of the newly built track. The branched connecting track is connected to the wind tunnel track. The path curve of the connecting track is smooth, and the intersection at both ends is tangent to the wind tunnel track and the newly built track respectively. The spare shock tube on the newly built track can enter the upstream and downstream of the wind tunnel track through the track change mechanism.

[0041] S2. Loosen the membrane clamping mechanism and move the driving section, driven section and membrane clamping section to leave space for the spare shock tube.

[0042] If a higher Mach number test is conducted, the driving section is moved upstream, the driven section and the clamping section are moved downstream, and the length of the vacant track is twice the length of the spare shock tube.

[0043] If a lower Mach number test is conducted, the driving section and the diaphragm section are moved upstream and the driven section is moved downstream, leaving an empty track length that is twice the length of the spare shock tube.

[0044] S3. Move the spare shock tube from the newly set track to the wind tunnel main track through the track changing mechanism, and connect the spare shock tube to the driving section or the driven section through the flange.

[0045] Among them, when conducting lower Mach number tests, the spare shock tube is connected to the driven section; when conducting higher Mach number tests, the spare shock tube is connected to the driving section.

[0046] The length ΔL of the spare shock tube does not exceed half of the length L1 of the driving section. When the spare shock tube is connected to the driven section, the length ratio of the newly formed driven section to the driving section is 1:3 to 1:3.6; when the spare shock tube is connected to the driving section, the length ratio of the newly formed driving section to the driven section is 1:1 to 3:4.

[0047] S4. Place the diaphragm, reconnect the driving section, driven section, and diaphragm section, and start the wind tunnel test.

[0048] The method of the present invention can cope with various operating conditions and effectively improve the shock wave wind tunnel test time.

[0049] Although the present invention has been disclosed as above in the form of a preferred embodiment, it is not intended to limit the present invention. Any person skilled in the art may make possible changes and modifications to the technical solution of the present invention by using the methods and technical contents disclosed above without departing from the spirit and scope of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention shall fall within the protection scope of the technical solution of the present invention.

[0050] The contents not described in detail in the specification of the present invention belong to the common knowledge of those skilled in the art.

Claims

1. A method for increasing the test time of a shock tunnel by simple structural changes, characterized in that: The following steps are involved: S1. Add a new track next to the wind tunnel body shock tube, connect the new track with the wind tunnel body track through the track change mechanism, and place the spare shock tube on the new track; S2, loosen the film clamping mechanism, move the driving section, driven section, and film clamping section to leave space for the spare shock tube; S3, moving the spare shock tube from the newly set track to the wind tunnel main track through the track changing mechanism, and connecting the spare shock tube to the driving section or the driven section through the flange; S4. Place the diaphragm, reconnect the driving section, driven section, and diaphragm section, and start the wind tunnel test.

2. The method of increasing the shock tunnel test time by simple structural changes according to claim 1, characterized in that: The newly-installed track is parallel to the wind tunnel main body track and is spaced 2 to 5 meters apart from each other; the spare shock tube on the newly-installed track can enter the upstream and downstream of the wind tunnel main body track through a track-changing mechanism.

3. The method of increasing the shock tunnel test time by simple structural changes according to claim 2, characterized in that: The track-changing mechanism realizes the structural change in the following manner: two forks are respectively set at the upstream and downstream of the newly-established track, and the branched connecting tracks are connected to the wind tunnel main body track. The path curve of the connecting tracks is smooth, and the intersections at both ends are tangent to the wind tunnel main body track and the newly-established track respectively.

4. The method of increasing the shock tunnel test time by simple structural changes according to claim 1, characterized in that: The positions of the mobile driving section, driven section and clamping section are specifically: If a higher Mach number test is conducted, the driving section is moved upstream, the driven section and the diaphragm section are moved downstream, and the length of the vacant track left is twice the length of the spare shock tube; if a lower Mach number test is conducted, the driving section and the diaphragm section are moved upstream, and the driven section is moved downstream, and the length of the vacant track left is twice the length of the spare shock tube; the lower Mach number test is a wind tunnel test with a Mach number less than or equal to 8, and the higher Mach number test is a wind tunnel test with a Mach number greater than 8.

5. The method of increasing the shock tunnel test time by simple structural changes according to claim 4, characterized in that: The step of connecting the standby shock tube to the driving section or the driven section is specifically as follows: When conducting tests at lower Mach numbers, the spare shock tube is connected to the driven section; When conducting tests at higher Mach numbers, a spare shock tube is connected to the drive section.

6. The method of increasing the shock tunnel test time by simple structural changes according to claim 5, characterized in that: The length ΔL of the spare shock tube does not exceed half of the length L1 of the driving section. When the spare shock tube is connected to the driven section, the length ratio of the newly formed driven section to the driving section is 1:3 to 1:3.6; when the spare shock tube is connected to the driving section, the length ratio of the newly formed driving section to the driven section is 1:1 to 3:

4.

7. The method of increasing the shock tunnel test time by simple structural changes according to claim 6, characterized in that: For the wind tunnel test at the beginning, for the lower Mach number test condition, the test time is limited by the test gas volume, and the relationship between the increased test time and the original test time is: For the test conditions with higher Mach numbers, the test time is affected by the reflected expansion wave. The relationship between the increased test time and the original test time is: Wherein, t1 is the original available test time of the lower Mach number test condition, t2 is the available test time after the lower Mach number test condition is increased, t3 is the original available test time of the higher Mach number test condition, t4 is the available test time after the higher Mach number test condition is increased, ΔL is the length of the spare shock tube, L1 is the length of the driving section, and L2 is the length of the driven section.