Drainage pipeline of dry dock

By designing the dry dock drainage pipelines of drainage corridors, pump rooms, inverted U-shaped parts and water jet pipes, the problems of docking room flooding and seabed silt affecting the operation of docking doors caused by the jammed one-way valve, and the problem of docking room flooding and seabed silt affecting the operation of docking doors is solved, and the problem of docking room flooding caused by the jammed one-way valve is stuck is solved, and the problem of docking doors is realized. The efficient drainage and dock door cleaning of the dry dock reduce costs and construction difficulties.

CN119058914APending Publication Date: 2024-12-03SINOHYDRO BUREAU 5
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411101829.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-12
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

In traditional dry dock drainage systems, the one-way valve is prone to stuck and causes the dock room to flood, and the seabed silt in the dock door is affected by the operation of the dock door, causing high costs and inconvenience in construction.

Method used

A dry dock drainage pipeline was designed, including a drainage corridor, pump room, first drainage pipe and second drainage pipe. The inverted U-shaped part and vacuum damage valve are used to prevent the siphon effect, and the water spray pipe cleans up the silt and ensure the docking. The door is running normally.

Benefits of technology

Effectively prevent the docking room from flooding, ensure the normal operation and drainage efficiency of the docking door, and reduce the impact on civil structure and seabed.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119058914A_ABST
    Figure CN119058914A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of dock facility engineering equipment, and particularly discloses a dry dock drainage pipeline which is characterized in that a pump room is arranged on one side of a dry dock, and a drainage pump is arranged in the pump room; one end of the drainage gallery is arranged on the bottom plate of the dry dock, and the other end is connected to the drainage pump; the highest point of the inverted-U-shaped part of the first drainage pipe is higher than the sea level, and the highest end of the inverted-U-shaped part is provided with a blowdown pipe which is provided with a vacuum breaking valve; the second drainage pipe and the first drainage pipe are the same in structure, a water spraying pipe is further arranged at the water outlet end, the tail end of the water spraying pipe is closed, the water spraying pipe is provided with a plurality of spraying heads in the axial direction, and the spraying heads face an apron at the bottom of the dock gate. Water in the dry dock is drained into the sea through the drainage gallery, the first drainage pipe, the second drainage pipe and the drainage pump under the siphoning effect, the top end of the U-shaped part is provided with the vacuum breaking valve and the air supplementing pipe to prevent water from flowing backwards, and the dock chamber is prevented from being submerged; and the apron is cleaned by the second drainage pipe, so that the dock gate is convenient to operate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of dock equipment, and in particular to a dry dock drainage pipeline. Background Art

[0002] Dry dock is an essential infrastructure for modern shipyards to manufacture and repair large ships. When the ship to be repaired enters the dry dock and completes positioning, the dock door is closed, and then water is pumped out from the dock chamber to allow the ship to sit steadily on the keel pier of the dock floor. At this time, the ship repair environment changes from water surface construction to land construction, which can greatly improve the efficiency and speed of construction and repair. The system that empties all the water in the dock pool in the above process is the dock drainage system.

[0003] The traditional dock drainage system is mainly composed of a drainage main pump, drainage pipes, check valves, gates and corresponding civil engineering structures. Usually, the drainage pipes are arranged in a straight line after the pump outlet and connected to the external waters. In order to prevent the backflow of seawater outside the dock, drainage gates and one-way valves are often set on the drainage pipes. The drainage gates are convenient for isolating the pump group and the water area from the dock room when the main pump is overhauled. The one-way valve is set upstream of the drainage gate to prevent seawater from backflowing into the main pump unit. When the main pump stops running, there is water in the drainage pipe. However, from actual operating experience, the one-way valve is often stuck due to the change in head caused by the tide, and cannot be closed normally, resulting in flooding of the dock room. At the same time, because the small floating garbage and driftwood in the dock pool are gathered into the main pump suction port with the water flow, they often accumulate in the one-way valve and the drainage gate slot during the drainage process along the drainage pipe, blocking and blocking the gate from opening and closing freely, resulting in the gate often not being able to close normally and failing to achieve the purpose of sealing water.

[0004] Traditional dry docks mostly use pontoon-type dock doors, which do not need to be dumped when opened. For dry docks with dumping-type dock doors, when the dock doors are opened, the dock doors need to be dumped onto the treated seabed directly in front of the dock entrance. When the silt on the seabed in this area reaches a certain height, it will seriously affect the normal use of the dumping-type dock doors, requiring divers to manually desilt regularly, which is costly and inconvenient to construct.

[0005] In addition, the seawater disturbance caused by the high-speed water flow at the outlet of the dock drainage system will affect the stability of the dock structure. It will also carry away the silt on the seabed in the outlet area and move it to the area where the tipping dock door lies, causing a certain impact on the operation of the dock door. Summary of the invention

[0006] The purpose of the present invention is to provide a dry dock drainage pipeline to solve the problem that the dock chamber of the dry dock is flooded due to the sticking of the one-way valve, and the existence of silt on the seabed in the area where the dock door is tilted, affecting the operation of the dock door.

[0007] In order to solve the above technical problems, the technical solutions adopted by the present invention are as follows: A dry dock drainage pipeline comprises a drainage gallery, a pump room, a first drainage pipe and a second drainage pipe; A pump room, located on one side of the dry dock, contains a drainage pump; a drainage gallery, one end of which is provided beneath the floor of the dry dock and the other end of which is connected to a drainage pump; The first drainage pipe comprises a water inlet end, an inverted U-shaped portion and a water outlet end; the water inlet end is connected to the drainage pump; one end of the inverted U-shaped portion is connected to the water inlet end, and the other end is connected to the water outlet end, and the water outlet end is connected to the sea; the highest point of the inverted U-shaped portion is higher than the sea level, and an air supply pipe is provided at the highest end, and a vacuum breaking valve is provided on the air supply pipe; The second drain pipe has the same structure as the first drain pipe, and a water spray pipe is also provided at the water outlet. The end of the water spray pipe is closed, and a plurality of spray heads are provided axially on the water spray pipe, and the spray heads face the guard tank at the bottom of the dock door.

[0008] As a further technical solution of the above solution, the water outlet end of the first drain pipe is provided with a large diameter pipe opening.

[0009] As a further technical solution of the above solution, a plurality of first drainage pipes are provided.

[0010] As a further technical solution of the above solution, the drainage corridor is provided with a plurality of water inlets, and trash racks are provided at the water inlets.

[0011] As a further technical solution of the above solution, a blocking plate is provided at the end of the water spray pipe.

[0012] Compared with the prior art, the present invention has the following advantages and beneficial effects: the present invention discharges the water in the dry dock to the sea outside the dock pool through the drainage corridor, the first drainage pipe, the second drainage pipe and the drainage pump; the top of the U-shaped part is provided with a vacuum breaking valve and an air supply pipe to prevent the water in the drainage pipe from flowing back into the dock chamber due to the siphon effect when the main pump stops, thereby preventing the dock chamber from being flooded; and the second drainage pipe cleans the guard tank to facilitate the operation of the dock door. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 Schematic diagram of the connection structure of the first drainage pipe.

[0014] Figure 2 Schematic diagram of the connection structure of the second drainage pipe.

[0015] Figure 3 It is a schematic diagram of the structure of the first drainage pipe and the second drainage pipe.

[0016] Figure 4 It is a schematic diagram of the three-dimensional structure of the first drain pipe and the second drain pipe.

[0017] Figure 5 It is a schematic diagram of the position of the present invention and the dock door.

[0018] The meanings of the numbers in the figure are: drainage gallery-1; pump room-2; drainage pump-21; first drainage pipe-3; water inlet end-31; inverted U-shaped part-32; water outlet end-33; vacuum breaking valve-34; air supply pipe-35; second drainage pipe-4; water spray pipe-41; spray head-42; blocking plate-43; dock door-5; tank guard-6. DETAILED DESCRIPTION

[0019] The technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention, so as to have a further understanding of the concept of the present invention, the technical problems solved, the technical features constituting the technical scheme and the technical effects brought about.

[0020] like Figure 1~Figure 5 As shown, a dry dock drainage pipeline includes a drainage gallery 1, a pump room 2, a first drainage pipe 3 and a second drainage pipe 4; A pump room 2 is arranged at one side of the dry dock, and a plurality of drainage pumps 21 are arranged in the pump room 2; A drainage gallery 1, one end of which is arranged below the bottom plate of the dry dock and the other end of which is connected to the water collection area of ​​the drainage pump 21; The first drainage pipe 3 includes a water inlet end 31, an inverted U-shaped portion 32 and a water outlet end 33; the water inlet end 31 is connected to the drainage pump 21; one end of the inverted U-shaped portion 32 is connected to the water inlet end 31, and the other end is connected to the water outlet end 33, and the water outlet end 33 is connected to the sea; the highest point of the inverted U-shaped portion 32 is higher than the sea level, and an air supply pipe 35 is provided at the highest end, and a vacuum breaking valve 34 is provided on the air supply pipe 35; The second drain pipe 4 has the same structure as the first drain pipe 3, and a water spray pipe 41 is further provided at the water outlet end. The end of the water spray pipe 41 is closed, and a plurality of spray heads 42 are axially provided on the water spray pipe 41, and the spray heads 42 face the tank guard 6 in the bottom area when the lying dock door 5 is in the open state.

[0021] In the present invention, the first drain pipe 3 and the second drain pipe 4 are designed in parallel. First, the drainage pump 21 in the pump room 2 is started. The water inlet elevation of the drainage pump 21 is lower than the elevation of the dock bottom plate. The water in the dry dock is pumped out through the drainage corridor 1 and discharged into the sea outside the dock pool through the first drain pipe 3. The water outlet end of the second drain pipe 4 is aligned with the guard tank 6 at the bottom of the dock door 5 (in the open state). The silt is cleaned by pressurizing the water spray pipe 41 and the spray head 42 to ensure the normal operation of the dock door 5. After the dock is drained, the drainage pump 21 is stopped, and the vacuum breaking valve 34 is started to drive the air supply pipe 35 to supply air to the first drain pipe 3 and the second drain pipe 4, interrupting the siphon effect, preventing seawater from flowing back into the dry dock, and avoiding flooding the dock room.

[0022] like Figure 3 and Figure 4 As shown, as a preferred embodiment, the outlet end of the first drainage pipe 3 is provided with a large diameter pipe opening. In this embodiment, the outlet pipe of the first drainage pipe 3 is trumpet-shaped, which is small inside and large outside, which can reduce the drainage flow rate, allow the water potential energy to offset the free water area outside the dock pool, and reduce the erosion effect on the civil structure and the seabed.

[0023] like Figure 3 and Figure 4 As shown, as a preferred embodiment, a plurality of first drainage pipes 3 are provided. In this embodiment, a plurality of first drainage pipes 3 are provided to work simultaneously to improve drainage efficiency.

[0024] As a preferred embodiment, the drainage gallery 1 is provided with a plurality of water inlets, and trash racks are provided at the water inlets. In this embodiment, a plurality of water inlets are provided on the drainage gallery 1, which improves the drainage efficiency in the dock gate, and trash racks are provided at the water inlets to prevent dirt from entering the drainage system, and the trash racks can be cleaned regularly.

[0025] like Figure 2 As shown, as a preferred embodiment, a blocking plate 43 is provided at the end of the water spray pipe 41. In this embodiment, the blocking plate 43 is provided in the water spray pipe 41 to increase the water pressure, thereby increasing the water outlet speed of the spray head 42.

[0026] The specific drainage and dredging operations are as follows: The drainage pump and the vacuum breaker valve are set for linkage operation. The vacuum breaker valve adopts electric mode and is in a normally open state when there is no drainage. The atmospheric pressure enters the top of the pipeline through the vacuum breaker valve and the air supply pipe.

[0027] When the dry dock needs to be drained, the drainage pump is started and the vacuum breaker valve is also started at the same time. After the vacuum breaker valve is started, it is in a closed state, and the atmospheric pressure cannot enter the pipe. At this time, the drainage pump starts to drain water. The seawater in the dry dock enters the drainage pump through the dry dock drainage gallery, and the drainage pump is used to discharge the water into the sea outside the dock pool through the inverted U-shaped drainage pipe. The outlet of the drainage pipe is trumpet-shaped, which can effectively reduce the scouring effect of water flow on structures such as the seabed and slope protection.

[0028] When the seawater in the dry dock is almost drained, the drainage pump stops running and the vacuum breaker valve stops working. At this time, since the drainage pipe is full of water, in order to prevent the water from the surrounding sea area from flowing back into the dock pool through the drainage pipe, water pump and drainage gallery under the siphon effect, the vacuum breaker valve should stop running immediately, the vacuum breaker valve returns to the normally open state and immediately replenishes air into the pipe to interrupt the siphon, so that the water level in the pipe is lowered under the action of gravity and cannot climb over the top of the inverted U-shaped pipe slope, preventing the external water area from flowing back into the dock pool and impacting the pump impeller blades.

[0029] At the same time, during the drainage process of the drainage system, a special drainage pipe extends directly to the dock structure of the tank guard area in front of the dock gate (in the open state). The end of the drainage pipe is blocked by a blocking plate, and the water can only be discharged through the jet pipes evenly and equidistantly arranged on the drainage pipe. The jet pipes will form a powerful water flow to blow and remove the silt and debris on the tank guard, preparing for the opening of the dock gate.

[0030] The jet flushing device can also be used for the dock structure of an ordinary pontoon-type dock door to flush away sand, gravel, particles, garbage and other debris on the dock sill to ensure that the sealing surface is clean, thereby meeting the water-stopping requirements.

[0031] A sump is set in front of the bell of the drainage pump to improve the water absorption efficiency of the water pump; after the siphon is interrupted, the water in the drainage pipe falls back into the sump and reversely flushes the sump trash rack to achieve a self-cleaning effect; at the same time, the drainage pipe is set into an inverted U shape, so that when the drainage pump stops unexpectedly, water hammer will not occur, causing damage to the structure and the water pump.

[0032] The terms “connection” and “fixation” mentioned in the description of the present invention may refer to fixed connection, processing and forming, welding or mechanical connection. The specific meanings of the above terms in the present invention shall be understood according to the specific circumstances.

[0033] In the description of the present invention, the terms "center", "upper", "lower", "horizontal", "inside", "outside", etc., which indicate the orientation or position relationship, are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying a specific orientation that the device or element referred to must have, and therefore cannot be understood as a limitation on the present invention.

[0034] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments can still be modified, or some or all of the technical features therein can be replaced by equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A dry dock drainage pipeline, characterized in that: It comprises a drainage gallery (1), a pump room (2), a first drainage pipe (3) and a second drainage pipe (4); A pump room (2) is arranged on one side of the dry dock, and a drainage pump (21) is arranged in the pump room (2); A drainage gallery (1), one end of which is arranged on the bottom plate of the dry dock and the other end of which is connected to a drainage pump (21); The first drainage pipe (3) comprises a water inlet end (31), an inverted U-shaped portion (32) and a water outlet end (33); the water inlet end (31) is connected to the drainage pump (21); one end of the inverted U-shaped portion (32) is connected to the water inlet end (31), and the other end is connected to the water outlet end (33), and the water outlet end (33) is connected to the sea; the highest point of the inverted U-shaped portion (32) is higher than the sea level, and an air supply pipe (35) is provided at the highest end, and a vacuum breaking valve (34) is provided on the air supply pipe (35); The second drainage pipe (4) has the same structure as the first drainage pipe (3), and is further provided with a water spray pipe (41) at the water outlet end. The end of the water spray pipe (41) is closed, and the water spray pipe (41) is provided with a plurality of spray heads (42) along the axial direction, and the spray heads (42) are directed toward the guard tank (6) at the bottom of the dock door (5).

2. A dry dock drainage pipeline according to claim 1, characterized in that: The water outlet end of the first drainage pipe (3) is provided with a large diameter pipe opening.

3. A dry dock drainage pipeline according to claim 1, characterized in that: A plurality of the first drainage pipes (3) are provided.

4. A dry dock drainage pipeline according to claim 1, characterized in that: The drainage gallery (1) is provided with a plurality of water inlets, and trash racks are provided at the water inlets.

5. A dry dock drainage pipeline according to claim 1, characterized in that: A blocking plate (43) is provided at the end of the water spray pipe (41).