Nested steel pipe pile and construction method for nested steel pipe pile

By installing nested steel pipe piles and corresponding construction methods on offshore steel pipe piles, the problems of high construction difficulty and high cost during the removal of steel pipe piles in the prior art are solved, and the update is achieved without pulling piles Steel pipe piles extend the life of offshore projects and reduce construction difficulty.

CN119061879APending Publication Date: 2024-12-03CTG JIANGSU ENERGY INVESTMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411480946.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-22
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

When the service life of existing offshore steel pipe piles ends or are damaged, the construction equipment requirements are high, costly and difficult during the demolition process, making it difficult to achieve efficient renovation or replacement.

Method used

Using nested steel pipe piles and corresponding construction methods, by installing the inner wall slot structure and the outer wall main hanging lug on the old steel pipe piles, the nested steel pipe piles are plugged into the outer layer of the old steel pipe piles by using pile driving technology. The chuck structure is clamped to the main hanging lug for updating and replacing.

Benefits of technology

Updated steel pipe piles without removing old steel pipe piles reduces the construction difficulty and cost of offshore projects, extends the life of offshore projects, and provides more flexible foundation recycling technology.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061879A_ABST
    Figure CN119061879A_ABST
Patent Text Reader

Abstract

The embodiment of the invention provides a nested steel pipe pile and a construction method for the nested steel pipe pile. The nested steel pipe pile comprises a steel pipe pile body, a clamping groove structure is fixed to the inner wall of the steel pipe pile body, the inner diameter of the steel pipe pile body is larger than the outer diameter of an old steel pipe pile, and the clamping groove structure is used for being clamped to a main lifting lug of the old steel pipe pile. The method comprises the steps that a first steel pipe pile is annularly cut; a pile stabilizing platform is built around the first steel pipe piles; positioning, feeding and piling the second steel pipe pile according to the piling mother ship and the pile stabilizing platform until the clamping groove structure on the inner wall of the second steel pipe pile is clamped on the main lifting lug of the first steel pipe pile; wherein the second steel pipe pile is the nested steel pipe pile. The nested steel pipe pile can be connected to the outer layer of the old steel pipe pile in a sleeving mode, and the problem that the old steel pipe pile is difficult to renovate or replace is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of offshore steel pipe piles, and in particular to a nested steel pipe pile and a construction method for the nested steel pipe pile. Background Art

[0002] Steel pipe piles are a commonly used building foundation material, mainly used to support the structure of buildings. They are also important structures in offshore engineering, especially in offshore wind farms, bridges, docks and other marine structures. With the development of the offshore wind power industry, the demand for steel pipe piles is expected to continue to grow in the next few years. Considering the long-term development of offshore projects, how to refurbish or replace offshore steel pipe piles that have reached the end of their service life is an important issue.

[0003] In the prior art, when steel pipe piles need to be replaced at sea due to their service life or degree of damage, the steel pipe piles are generally cut at a certain elevation below the mud surface, and the upper half of the steel pipe piles are lifted out after cutting, or the entire steel pipe pile is pulled out and replaced with a new pile; for example, the patent with publication number "CN117107760A" provides a method for dismantling offshore wind power steel pipe piles. The underwater pile cutting method leaves the main body of the steel pipe pile under the mud surface, leaving hidden dangers for subsequent marine engineering construction. The removal and pulling of piles has extremely high requirements for construction equipment, and its construction is difficult and costly.

[0004] In view of the above-mentioned defects, the present application provides a nested steel pipe pile and a construction method for the nested steel pipe pile. Summary of the invention

[0005] The embodiments of the present application provide a nested steel pipe pile and a construction method for the nested steel pipe pile, which can sleeve the nested steel pipe pile on the outer layer of the old steel pipe pile, thereby solving the problem that the old steel pipe pile is difficult to renovate or replace.

[0006] In a first aspect, the present application provides a nested steel pipe pile, including a steel pipe pile body, a slot structure is fixed on the inner wall of the steel pipe pile body, the inner diameter of the steel pipe pile body is larger than the outer diameter of the old steel pipe pile, and the slot structure is used to be clamped on the main lifting ear of the old steel pipe pile.

[0007] In a possible design, the number of the slot structures is two, the two slot structures are relatively fixed on the inner wall of the steel pipe pile body, and the slot structure is a dovetail slot structure.

[0008] In a possible design, it also includes a pair of main lifting ears, which are fixed on the outer wall of the steel pipe pile body, and the pair of main lifting ears are arranged opposite to each other.

[0009] In a second aspect, an embodiment of the present application provides a construction method for nested steel pipe piles, comprising:

[0010] Performing a ring cut on the first steel pipe pile, wherein the ring cut is performed at a position where the first steel pipe pile is exposed above the water surface;

[0011] A pile stabilizing platform is built around the first steel pipe pile, and the dragon mouth is coaxially arranged with the first steel pipe pile;

[0012] The second steel pipe pile is positioned, fed and driven according to the piling mother ship and the pile stabilizing platform until the slot structure on the inner wall of the second steel pipe pile is clamped on the main lifting lug of the first steel pipe pile; wherein the second steel pipe pile is the above-mentioned nested steel pipe pile.

[0013] In a possible design, the piling mother ship cooperates with the pile stabilizing platform to position, feed and drive the second steel pipe pile until the ear slot on the inner wall of the second steel pipe pile is clamped on the main ear of the first steel pipe pile; including:

[0014] Sinking a pile stabilizing platform, and arranging the faucet of the pile stabilizing platform coaxially with the first steel pipe pile;

[0015] According to the position of the main lifting lug of the first steel pipe pile, the main lifting lug of the second steel pipe pile is adjusted to be in the same position as the main lifting lug of the first steel pipe pile; wherein the main lifting lug of the nested steel pipe pile and the slot structure are fixed on the same diameter on the same cut plane of the steel pipe pile body;

[0016] The second steel pipe pile is extended and stabilized by the hydraulic jack, and the second steel pipe pile is lowered, and the verticality of the second steel pipe pile is maintained not exceeding a preset verticality according to the total station and the hydraulic jack, until the second steel pipe pile is erected and no longer sinks;

[0017] The second steel pipe pile is driven, and the verticality of the second steel pipe pile is maintained not exceeding a preset verticality according to the total station and the hydraulic jack until the second steel pipe pile sinks to a preset height.

[0018] In a possible design, the total station is used to measure the offset, and the total station includes a first total station and a second total station, the first total station and the second total station are arranged at the edge of the dragon mouth, the measuring direction of the first total station and the measuring direction of the second total station are both toward the axis of the dragon mouth; the measuring direction of the first total station is 90° to the measuring direction of the second total station; the verticality of the second steel pipe pile is maintained not to exceed a preset verticality according to the total station and the hydraulic jack, including:

[0019] determining a first horizontal offset according to the first total station; if the first horizontal offset is greater than a preset offset, obtaining the target oil top according to the first horizontal offset, and controlling the target oil top output until the first horizontal offset is no greater than the preset offset;

[0020] A second horizontal offset is determined according to the second total station; if the second horizontal offset is greater than a preset offset, the target oil top is obtained according to the second horizontal offset, and the target oil top output is controlled until the second horizontal offset is no greater than the preset offset.

[0021] In a possible design, the number of the hydraulic jacks is set to four, the four hydraulic jacks are arranged on the same horizontal plane, the extension and retraction directions of the hydraulic jacks all point to the axis of the dragon mouth, the four hydraulic jacks are evenly distributed around the dragon mouth, the extension and retraction directions of two adjacent hydraulic jacks are 90°, and the first total station and the second total station are respectively arranged on the upper layers of the two adjacent hydraulic jacks; the obtaining of the target oil top according to the first horizontal offset includes:

[0022] According to the first horizontal offset, among the two hydraulic jacks adjacent to the first total station, the hydraulic jack to which the second steel pipe pile is close is determined as the target hydraulic jack.

[0023] In a possible design, acquiring the target oil top according to the second horizontal offset includes:

[0024] According to the second horizontal offset, among the two hydraulic jacks adjacent to the second total station, the hydraulic jack to which the second steel pipe pile is close is determined as the target hydraulic jack.

[0025] In a possible design, before the second steel pipe pile is lifted and positioned at a position coaxial with the first steel pipe pile by the piling mother ship, the method further includes:

[0026] A piling mother ship and a pile transporting ship are docked; wherein the piling mother ship is used to lift the second steel pipe piles, feed and drive the second steel pipe piles; and the pile transporting ship is used to transport the second steel pipe piles.

[0027] In a possible design, before the first steel pipe pile is ring cut, the method further includes:

[0028] The cage of the first steel pipe pile is removed, and the anti-scouring area of ​​the first steel pipe pile is cleaned.

[0029] The present application provides a nested steel pipe pile and a construction method for the nested steel pipe pile. The nested steel pipe pile includes a steel pipe pile body. A slot structure is fixed on the inner wall of the steel pipe pile body. The inner diameter of the steel pipe pile body is larger than the outer diameter of the old steel pipe pile. The slot structure is used to be clamped on the main lifting lug of the old steel pipe pile. The present application can sleeve the nested steel pipe pile on the outer layer of the old steel pipe pile, solving the problem that the old steel pipe pile is difficult to renovate or replace. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.

[0031] Figure 1 A schematic diagram of the structure of a nested steel pipe pile provided in an embodiment of the present application;

[0032] Figure 2 A schematic diagram of a use scenario of a nested steel pipe pile provided in an embodiment of the present application Figure 1 ;

[0033] Figure 3 A schematic diagram of a use scenario of a nested steel pipe pile provided in an embodiment of the present application Figure 2 ;

[0034] Figure 4 A schematic diagram of a construction method for nested steel pipe piles provided in an embodiment of the present application Figure 1 ;

[0035] Figure 5 A schematic diagram of a construction method for nested steel pipe piles provided in an embodiment of the present application Figure 2 ;

[0036] Figure 6 A schematic diagram of a construction method for nested steel pipe piles provided in an embodiment of the present application Figure 3 ;

[0037] Figure 7 A schematic diagram of a scene of the hoisting and erection process of a pile stabilizing platform provided in an embodiment of the present application;

[0038] Figure 8 A schematic diagram of the structure of the internal dragon mouth of the pile stabilizing platform provided in an embodiment of the present application.

[0039] The above drawings have shown clear embodiments of the present application, which will be described in more detail later. These drawings and text descriptions are not intended to limit the scope of the present application in any way, but to illustrate the concept of the present application to those skilled in the art by referring to specific embodiments.

[0040] Description of reference numerals:

[0041] 110-steel pipe pile body; 120-fixing piece; 130-main lifting lug; 140-slot structure;

[0042] 210-first steel pipe pile; 220-second steel pipe pile; 230-mud surface; 240-water surface;

[0043] 310-the third steel pipe pile;

[0044] 700-stable pile platform;

[0045] 810-first jack; 820-second jack; 830-third jack; 840-fourth jack;

[0046] 850-the first total station; 860-the second total station; 870-Longkou. DETAILED DESCRIPTION

[0047] Exemplary embodiments will be described in detail herein, examples of which are shown in the accompanying drawings. When the following description refers to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The implementations described in the following exemplary embodiments do not represent all implementations consistent with the present application. On the contrary, they are merely examples of devices and methods consistent with some aspects of the present application as detailed in the attached claims, rather than all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0048] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, or it can be an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0049] In the description of the present application, it should be understood that the terms used include "upper", "lower", "front", "back", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. to indicate orientation or positional relationships. They are based on the orientation or positional relationships shown in the accompanying drawings and are only for the convenience of describing the equipment or method of the present application. They are not used to indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application.

[0050] In the specification and claims of the present application and the above-mentioned drawings, the terms "first", "second", and "third" are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the objects used in this way can be interchanged where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than those illustrated or described herein, for example.

[0051] Description of existing technology:

[0052] Steel pipe piles: Offshore steel pipe piles are one of the commonly used infrastructures in marine engineering, mainly used to provide support and stability to offshore structures, such as offshore platforms, bridges, docks, wind power towers, etc. They are long cylindrical structures made of high-strength steel, which are fixed by being driven or embedded into the seabed soil.

[0053] Pile stabilization platform: The pile stabilization platform is similar to an offshore drilling platform and is mainly used to adjust the verticality of the single pile during the construction of the single pile foundation.

[0054] Specifically, the pile stabilizing platform includes positioning piles at four corners. The four positioning piles are connected to each other through a truss structure to carry the platform body. A dragon mouth for a single pile to pass through is set in the center of the pile stabilizing platform, and multiple hydraulic jacks are arranged in a circular array with the dragon mouth as the center of the circle; when a single pile is set at the dragon mouth, the hydraulic jack drives the top end of the support rod to move toward the single pile, and a roller is set at the end of the hydraulic jack to facilitate rolling along the outer surface of the single pile during the piling process to adjust the verticality of the single pile.

[0055] In the prior art, when steel pipe piles need to be replaced at sea due to their service life or degree of damage, they are generally cut at a certain elevation below the mud surface, and the upper part of the steel pipe pile is lifted out after cutting; or the steel pipe pile is completely pulled out and replaced with a new pile. For example, the patent with publication number "CN117107760A" provides a method for removing offshore wind power steel pipe piles. Whether it is the underwater cutting method or the removal and pulling method, the construction equipment is extremely high, and the construction is difficult and costly.

[0056] In view of the above-mentioned defects, the present application provides a nested steel pipe pile and a construction method for the nested steel pipe pile.

[0057] The technical solution of the present application and how the technical solution of the present application solves the above-mentioned technical problems are described in detail below with specific embodiments. The following specific embodiments can be combined with each other, and the same or similar concepts or processes may not be repeated in some embodiments. The embodiments of the present application will be described below in conjunction with the accompanying drawings.

[0058] Figure 1 A schematic structural diagram of a nested steel pipe pile provided in an embodiment of the present application.

[0059] like Figure 1 Used to display the internal structure of a nested steel pipe pile, the present application provides a nested steel pipe pile, including a steel pipe pile body 110, a slot structure 140 is fixed on the inner wall of the steel pipe pile body, the inner diameter of the steel pipe pile body 110 is larger than the outer diameter of the old steel pipe pile, and the slot structure 140 is used to be clamped on the main lifting ear 130 of the old steel pipe pile.

[0060] Specifically, the old steel pipe piles are existing steel pipe piles. When the old steel pipe piles reach the end of their service life or need to be replaced for maintenance reasons, a nested steel pipe pile provided in an embodiment of the present application can be sleeved on the old steel pipe piles for updating.

[0061] Specifically, two slot structures 140 are provided, and the two slot structures 140 are relatively fixed on the inner wall of the steel pipe pile body 110 , and the slot structures 140 are dovetail slot structures.

[0062] Specifically, the slot structure 140 is fixed to the inner wall of the steel pipe pile body 110 through the fixing member 120; optionally, the fixing member 120 is a fixing plate structure supported by multiple steel bars, or can be an arc structure supported by multiple steel bars.

[0063] Specifically, the slot structure 140 can limit the absolute settlement of the nested steel pipe piles and prevent the piles from sliding to a level lower than the designed elevation.

[0064] Specifically, the nested steel pipe pile further includes a pair of main lifting ears 130 , which are fixed on the outer wall of the steel pipe pile body 110 , and the pair of main lifting ears 130 are arranged opposite to each other.

[0065] Optionally, the old steel pipe piles are nested steel pipe piles, or they may be steel pipe piles used in the prior art.

[0066] Optionally, the main lifting lug 130 and the slot structure 140 are fixed on the same cut surface of the steel pipe pile body 110; or, they are arranged on the diameter of the same cut surface to facilitate the implementation of the present application to perform the next layer of nesting.

[0067] The embodiment of the present application provides a nested steel pipe pile, including a steel pipe pile body 110, a slot structure 140 is fixed on the inner wall of the steel pipe pile body, the inner diameter of the steel pipe pile body 110 is larger than the outer diameter of the old steel pipe pile, and the slot structure 140 is used to be clamped on the main lifting lug 130 of the old steel pipe pile. The following effects can be achieved:

[0068] When foundation piles need to be replaced due to replacing small projects with large ones or reaching the end of their life cycle, the nested steel pipe piles provided in the embodiment of the present application are nested in the outer layer of the old steel pipe piles through the piling technology, and the slot structure 140 is clamped on the main lifting lug 130 of the old steel pipe piles; the steel pipe piles can be updated without pulling out the piles, thereby extending the life of the offshore project.

[0069] Furthermore, the nested steel pipe piles provided in the embodiment of the present application can be used as old steel pipe piles and recycled and nested in the next life cycle to further extend the life of the offshore project.

[0070] As a prospect, after nesting, the nested steel pipe piles provided in this embodiment can be used as a fulcrum to pull out the original foundation piles, which can reduce the construction difficulty of offshore pile pulling and provide a new idea for offshore steel pipe pile foundation recovery technology.

[0071] Figure 2 A schematic diagram of a use scenario of a nested steel pipe pile provided in an embodiment of the present application Figure 1 ; It includes a first steel pipe pile 210 and a second steel pipe pile 220. The first steel pipe pile 210 is a foundation pile, and can also be the above-mentioned nested steel pipe pile. The second steel pipe pile 220 is the above-mentioned nested steel pipe pile. When in use, it is necessary to cut the part of the first steel pipe pile 210 above the water surface 240 in a ring, and then sleeve the second steel pipe pile on the outer layer of the first steel pipe pile 210 through the pile driving technology. Under normal working conditions, its main lifting lug is on the mud surface 230.

[0072] Figure 3 A schematic diagram of a use scenario of a nested steel pipe pile provided in an embodiment of the present application Figure 2 ;exist Figure 2 On this basis, if the second steel pipe pile 220 needs to be updated, similarly, the nested steel pipe pile provided in the present application can be used as the third steel pipe pile 310 to be sleeved on the second steel pipe pile.

[0073] Figure 4 A schematic diagram of a construction method for nested steel pipe piles provided in an embodiment of the present application Figure 1 .like Figure 4 The method is used to sleeve the second steel pipe pile on the outer layer of the first steel pipe pile, wherein the second steel pipe pile is the above-mentioned nested steel pipe pile, and the method comprises:

[0074] S410, performing circumcision on the first steel pipe pile, wherein the circumcision position is located at the position where the first steel pipe pile is exposed above the water surface.

[0075] Specifically, the first steel pipe pile is a steel pipe pile successfully driven at sea;

[0076] Specifically, the first steel pipe pile can be a foundation pile (ie, a steel pipe pile used in the prior art) or the above-mentioned nested steel pipe pile.

[0077] S420. Sink the pile stabilizing platform and set the faucet of the pile stabilizing platform coaxially with the first steel pipe pile.

[0078] Specifically, the pile stabilizing platform includes positioning piles at four corners, the main function of the positioning piles is to withstand the reaction force when the hydraulic jack adjusts the verticality of the second steel pipe pile; the dragon mouth is located at the top of the pile stabilizing platform, and the dragon mouth is coaxially arranged with the first steel pipe pile. Multiple hydraulic jacks are arranged in a circular array with the center of the dragon mouth semicircle as the center.

[0079] S430, positioning, feeding and driving the second steel pipe pile according to the piling mother ship and the pile stabilizing platform until the slot structure on the inner wall of the second steel pipe pile is clamped on the main lifting lug of the first steel pipe pile; wherein the second steel pipe pile is a nested steel pipe pile.

[0080] Specifically, the diameter of the second steel pipe pile is greater than that of the first steel pipe pile, and the second steel pipe pile is the above-mentioned nested steel pipe pile, and a slot structure is fixed on the inner wall thereof, and the slot structure is used to clamp the main lifting lug of the first steel pipe pile;

[0081] Specifically, the hydraulic jack of the inner stabilizing pile platform adjusts the relative position of the first steel pipe pile and the second steel pipe pile.

[0082] As a technical effect, the present application can sleeve the nested steel pipe piles on the old steel pipe piles to achieve the renewal of the old steel pipe piles and solve the problem that the old steel pipe piles are difficult to renovate or replace.

[0083] Figure 5 A schematic diagram of a construction method for nested steel pipe piles provided in an embodiment of the present application Figure 2 , Figure 6 A schematic diagram of a construction method for nested steel pipe piles provided in an embodiment of the present application Figure 3 ;according to Figure 5 and Figure 6 , the method comprising:

[0084] S510, performing circumcision on the first steel pipe pile, wherein the circumcision position is located at the position where the first steel pipe pile is exposed above the water surface.

[0085] Specifically, the first steel pipe pile is a steel pipe pile successfully driven at sea;

[0086] Specifically, for current offshore projects, the cage of the first steel pipe pile needs to be removed before ring cutting, and the sand blanket, stones, etc. in the anti-scouring area of ​​the first steel pipe pile need to be cleared (riprap protection can take natural scouring into consideration).

[0087] Specifically, the circumferential cutting can be performed by flame cutting, and the circumferential cutting position can be located above the water surface.

[0088] S520. Sink the pile stabilizing platform and set the dragon mouth of the pile stabilizing platform coaxially with the first steel pipe pile.

[0089] Figure 7 The following is a schematic diagram of the process of lifting and building a pile stabilizing platform provided in the embodiment of the present application. Figure 7 , by hoisting the combined pile stabilizing platform 700 to the first steel pipe pile, wherein the dragon mouth is carried on the pile stabilizing platform, the dragon mouth is set at the annular cut of the first steel pipe pile 210, and the first steel pipe pile 210 is coaxially arranged with the dragon mouth, wherein a plurality of hydraulic jacks are arranged in a circular array with the dragon mouth as the center.

[0090] S530, hoist the second steel pipe pile by the piling mother ship and bring it to the position of the pile stabilizing dragon mouth, and slowly lower it so that the bottom of the second steel pipe pile sinks to the dragon mouth.

[0091] Specifically, before this step, the method of this embodiment further includes:

[0092] The piling mother ship and the pile transporting ship are docked; the piling mother ship is used to lift the second steel pipe pile, feed and drive the second steel pipe pile; the pile transporting ship is used to transport the second steel pipe pile.

[0093] Specifically, the pile transporting ship is moored beside the piling mother ship, and the pile transporting ship is used to transport the second steel pipe pile; the floating crane is stabilized beside the pile transporting ship, and the floating crane stabilizes the pile transporting ship between the piling mother ship and the floating crane to stabilize the pile transporting ship.

[0094] Specifically, the dragon mouth position is located by the piling mother ship, and the second steel pipe pile is lifted by the crane in cooperation with the main lifting lug; the crane, pile hammer, etc. are carried on the piling mother ship.

[0095] Specifically, the second steel pipe pile can be lifted by a full-slewing crane loaded on the piling mother ship. The advantage of the full-slewing crane is that its boom can rotate 360 ​​degrees, which enables it to operate in different directions, increasing the flexibility and efficiency of the operation.

[0096] S540, according to the position of the main lifting lug of the first steel pipe pile, adjusting the main lifting lug of the second steel pipe pile to be at the same vertical position as the main lifting lug of the first steel pipe pile.

[0097] Specifically, the position of the second steel pipe pile main lifting ear is adjusted by positioning the first steel pipe pile main lifting ear, and the axis of the second steel pipe pile is made to coincide with the axis of the dragon mouth by rotating the boom, so that the orientation of the second steel pipe pile main lifting ear is adjusted to be consistent with the orientation of the first steel pipe pile main lifting ear.

[0098] Specifically, when the position of the adjusted second steel pipe pile main lifting ear is consistent with the position of the first steel pipe pile main lifting ear, it can be determined that when the nested steel pipe pile is driven downward, the slot structure on its inner wall can be snapped onto the main lifting ear of the first steel pipe pile.

[0099] S550. Extend and stabilize the second steel pipe pile through the hydraulic jack, lower the second steel pipe pile, and maintain the verticality of the second steel pipe pile not exceeding the preset verticality according to the total station and the hydraulic jack until the second steel pipe pile is erected and no longer sinks.

[0100] Specifically, the erected pile no longer sinks, which means that the self-sinking of the second steel pipe pile has ended;

[0101] Specifically, when the second steel pipe pile stops sinking, the main hook of the piling mother ship can be unhooked, and the wire rope loop can be gradually separated from the main lifting ear of the second steel pipe pile by rotating the boom.

[0102] Figure 8 This is a schematic diagram of the structure of the internal faucet of the pile stabilization platform provided in the embodiment of the present application. Figure 8 An embodiment of a dragon mouth 870 structure is shown, and the dragon mouth 870 includes an upper U-shaped structure and a lower ring structure connected to each other.

[0103] Specifically, the total station is used to measure the offset, and the total station includes a first total station 850 and a second total station 860. The first total station 850 and the second total station 860 are arranged on the edge of the longkou 870. The measuring direction of the first total station 850 and the measuring direction of the first total station 850 are both toward the axis of the longkou 870; the measuring direction of the first total station 850 and the measuring direction of the second total station 860 are 90°.

[0104] Specifically, the number of hydraulic jacks is set to four, and the four hydraulic jacks are set on the same horizontal plane. The extension and retraction directions of the hydraulic jacks all point to the axis of the dragon mouth 870. The four hydraulic jacks are evenly distributed around the dragon mouth 870, and the extension and retraction directions of two adjacent hydraulic jacks are 90°. The first total station 850 and the second total station 860 are respectively arranged on the upper layers of two adjacent hydraulic jacks.

[0105] Specifically, the verticality of the second steel pipe pile can be determined based on the corresponding horizontal offsets obtained by the total station with the two measuring directions being 90°. Generally, according to the construction requirements and standards, the verticality is required not to be higher than a certain standard, that is, the preset verticality in this article. Similarly, based on the preset verticality, the preset horizontal offset corresponding to the second steel pipe pile under the preset verticality can be obtained. If both the first horizontal offset and the second horizontal offset do not exceed the preset offset, it can be confirmed that the verticality of the second steel pipe pile does not exceed the preset verticality.

[0106] Further, according to the above principle, a method for maintaining the verticality of the second steel pipe pile not exceeding a preset verticality using a total station and a hydraulic jack can be determined, which specifically includes:

[0107] S551, obtaining a first horizontal offset according to a first total station; if the first horizontal offset is greater than a preset offset, obtaining a target oil top according to the first horizontal offset, and controlling the target oil top output until the first horizontal offset is no greater than the preset offset;

[0108] Specifically, according to the first horizontal offset, among the two hydraulic jacks adjacent to the first total station, the hydraulic jack close to the second steel pipe pile is determined as the target hydraulic jack.

[0109] For example, Figure 8, the four hydraulic jacks are respectively the first jack 810, the second jack 820, the third jack 830 and the fourth jack 840. The first total station 850 is set on the first jack 810, and the second total station 860 is set on the second jack 820. The two hydraulic jacks adjacent to the first total station 850 are respectively the second jack 820 and the fourth jack 840. According to the first horizontal offset, it can be known that the second steel pipe pile is offset to the fourth jack 840, so the fourth jack 840 is determined to be the target oil top.

[0110] S552, obtaining a second horizontal offset according to a second total station; if the second horizontal offset is greater than a preset offset, obtaining a target oil top according to the second horizontal offset, and controlling the target oil top output until the second horizontal offset is no greater than the preset offset.

[0111] Specifically, according to the first horizontal offset, among the two hydraulic jacks adjacent to the first total station, the hydraulic jack close to the second steel pipe pile is determined as the target hydraulic jack.

[0112] For example Figure 8 The two hydraulic jacks adjacent to the second total station 860 are the first jack 810 and the third jack 830. According to the first horizontal offset, it can be known that the second steel pipe pile is offset to the third jack 830, so the third jack 830 is determined as the target oil top.

[0113] S560, driving the second steel pipe pile, and maintaining the verticality of the second steel pipe pile not exceeding a preset verticality by using the total station and the hydraulic jack, until the second steel pipe pile sinks to a preset height.

[0114] Specifically, the second steel pipe pile is driven by a pile driver. During the driving process, the verticality of the second steel pipe pile is kept within a preset verticality by using a total station and a hydraulic jack, and the method is the same as S551-S552, which will not be described in detail here.

[0115] Specifically, the preset height is a height calculated in advance. When the steel pipe pile reaches the preset height, it can be determined that the slot structure inside the second steel pipe pile has been snapped onto the main lifting lug of the first steel pipe pile.

[0116] The embodiment of the present application provides a construction method for nested steel pipe piles, wherein the first steel pipe pile is circumcised, and the position of the circumcision is located at the position where the first steel pipe pile is exposed above the water surface; a pile stabilizing platform is built around the first steel pipe pile, and the dragon mouth is set at the circumcision of the first steel pipe pile and is coaxial with the circumcision; the second steel pipe pile is positioned, fed, and piled according to the pile driving mother ship and the pile stabilizing platform until the slot structure on the inner wall of the second steel pipe pile is clamped on the main lifting lug of the first steel pipe pile; wherein the second steel pipe pile is the above-mentioned nested steel pipe pile. The following technical effects can be achieved:

[0117] When the foundation pile is damaged or reaches the end of its life cycle, the nested steel pipe pile provided in the embodiment of the present application is nested in the outer layer of the old steel pipe pile by piling, and the slot structure is clamped on the main lifting lug of the old steel pipe pile; the steel pipe pile can be updated without pulling out the pile, thereby extending the life of the offshore project.

[0118] Furthermore, the nested steel pipe piles provided in the embodiment of the present application can be used as old steel pipe piles and recycled and nested in the next life cycle to further extend the life of the offshore project.

[0119] As a prospect, after nesting, the nested steel pipe piles provided in this embodiment can be used as a fulcrum to pull out the old steel pipe piles inside, which can effectively reduce the construction difficulty of offshore pile pulling and provide a new idea for offshore pile pulling technology.

[0120] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A nested steel pipe pile, characterized in that: It comprises a steel pipe pile body, on the inner wall of which a slot structure is fixed, the inner diameter of the steel pipe pile body is larger than the outer diameter of the old steel pipe pile, and the slot structure is used for being clipped onto the main lifting lug of the old steel pipe pile.

2. The nested steel pipe pile according to claim 1, characterized in that: The two slot structures are provided with two slot structures, which are relatively fixed on the inner wall of the steel pipe pile body, and the slot structure is a dovetail slot structure.

3. The steel pipe pile according to claim 1, characterized in that: It also includes a pair of main lifting ears, which are fixed on the outer wall of the steel pipe pile body, and the pair of main lifting ears are arranged opposite to each other.

4. A construction method for nested steel pipe piles, characterized in that: include: Performing a ring cut on the first steel pipe pile, wherein the ring cut is performed at a position where the first steel pipe pile is exposed above the water surface; Sinking a pile stabilizing platform, and arranging the faucet of the pile stabilizing platform coaxially with the first steel pipe pile; The second steel pipe pile is positioned, fed and driven according to the piling mother ship and the pile stabilizing platform until the slot structure on the inner wall of the second steel pipe pile is clamped on the main lifting lug of the first steel pipe pile; wherein the second steel pipe pile is a nested steel pipe pile according to any one of claims 1-3.

5. The method according to claim 4, characterized in that The method of positioning, feeding and driving the second steel pipe pile according to the piling mother ship and the pile stabilizing platform until the lug groove on the inner wall of the second steel pipe pile is clamped on the main lug of the first steel pipe pile comprises: The second steel pipe pile is lifted by the piling mother ship to the dragon mouth position, and is slowly lowered to allow the bottom of the second steel pipe pile to sink to the dragon mouth; According to the position of the main lifting lug of the first steel pipe pile, the main lifting lug of the second steel pipe pile is adjusted to be in the same position as the main lifting lug of the first steel pipe pile; Extending and stabilizing the second steel pipe pile by means of a hydraulic jack, lowering the second steel pipe pile, and maintaining the verticality of the second steel pipe pile not exceeding a preset verticality by means of a total station and a hydraulic jack until the second steel pipe pile stands upright and no longer sinks; The second steel pipe pile is driven, and the verticality of the second steel pipe pile is maintained not exceeding a preset verticality according to the total station and the hydraulic jack until the second steel pipe pile sinks to a preset height.

6. The method according to claim 5, characterized in that The total station is used to measure the offset, and the total station includes a first total station and a second total station, the first total station and the second total station are arranged at the edge of the dragon mouth, the measuring direction of the first total station and the measuring direction of the second total station are both toward the axis of the dragon mouth; the measuring direction of the first total station is 90° to the measuring direction of the second total station; the verticality of the second steel pipe pile is maintained not to exceed the preset verticality according to the total station and the hydraulic jack, including: Acquire a first horizontal offset according to the first total station; if the first horizontal offset is greater than a preset offset, acquire a target oil top according to the first horizontal offset, and control the target oil top output until the first horizontal offset is no greater than the preset offset; A second horizontal offset is obtained according to the second total station; if the second horizontal offset is greater than a preset offset, the target oil top is obtained according to the second horizontal offset, and the target oil top output is controlled until the second horizontal offset is no greater than the preset offset.

7. The method according to claim 6, characterized in that The number of the hydraulic jacks is set to four, the four hydraulic jacks are arranged on the same horizontal plane, the telescopic directions of the hydraulic jacks are all directed to the axis of the dragon mouth, the four hydraulic jacks are evenly distributed around the dragon mouth, the telescopic directions of two adjacent hydraulic jacks are 90°, and the first total station and the second total station are respectively arranged on the upper layers of two adjacent hydraulic jacks; The acquiring the target oil top according to the first horizontal offset includes: According to the first horizontal offset, among the two hydraulic jacks adjacent to the first total station, the hydraulic jack to which the second steel pipe pile is close is determined as the target hydraulic jack.

8. The method according to claim 7, characterized in that The acquiring the target oil top according to the second horizontal offset includes: According to the second horizontal offset, among the two hydraulic jacks adjacent to the second total station, the hydraulic jack to which the second steel pipe pile is close is determined as the target hydraulic jack.

9. The method according to any one of claims 4 to 8, characterized in that: Before the second steel pipe pile is hoisted and positioned at a position coaxial with the first steel pipe pile by the piling mother ship, the method further comprises: A piling mother ship and a pile transporting ship are docked; wherein the piling mother ship is used to lift the second steel pipe piles, feed and drive the second steel pipe piles; and the pile transporting ship is used to transport the second steel pipe piles.

10. The method according to any one of claims 4 to 8, characterized in that: Before the ring cutting of the first steel pipe pile, the method further comprises: The cage of the first steel pipe pile is removed, and the anti-scouring area of ​​the first steel pipe pile is cleaned.