Riverway retaining wall template
By using components such as lining plates, steel formwork, channel steel brackets in river retaining wall formwork, and using the cooperation of fixing rods and mounting plates, rapid construction and dismantling are achieved, solving the problem of long disassembly and assembly time in the existing technology, and improving the The formation efficiency of river retaining walls.
Patent Information
- Application Number
- CN202411460968.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-18
- Publication Date
- 2024-12-03
AI Technical Summary
The disassembly and assembly time of existing river retaining wall forms is long, resulting in low efficiency in forming river retaining walls.
Using a structure including lining plate, steel formwork, channel steel bracket, fixing rod, end plate, top rod, mounting plate, connecting piece, drive assembly and limit assembly, the mounting plate and top are pushed through the cooperation between the fixing rod and the mounting plate. The rod moves to make the top rod tightly against the channel steel bracket, achieving rapid construction and removal.
The disassembly and assembly time is shortened, the efficiency of forming river retaining walls is improved, and the operation steps are simplified.
Smart Images

Figure CN119061898A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of river channel construction equipment, and in particular to a river channel retaining wall template. Background Art
[0002] The river retaining wall includes a vertical water-facing surface and an inclined water-receiving surface. The river retaining wall is usually formed by cast-in-place concrete. When casting the river retaining wall, the operator is required to build the retaining wall formwork on site. The common retaining wall formwork includes a liner, steel formwork and channel steel bracket adapted to the water-facing surface of the retaining wall, and a liner, steel formwork and channel steel bracket adapted to the water-receiving surface of the retaining wall. The relative liner, steel formwork and channel steel bracket are connected and limited by tension screws and nuts. The tension screws are arranged in multiple rows, each row is provided with multiple tension screws, and a sleeve is put on the tension screw so that both ends of the sleeve are in contact and fit with the corresponding liner; after the retaining wall maintenance is completed, unscrew the nut, pull the tension screw out of the sleeve, and finally remove the liner, steel formwork and channel steel bracket.
[0003] Since it takes a lot of time to disassemble and assemble the tension screws and nuts, it takes a long time to form the river retaining wall, and the efficiency of forming the river retaining wall is low. Summary of the invention
[0004] In order to improve the efficiency of forming a river retaining wall, the present application provides a river retaining wall template.
[0005] The present application provides a river retaining wall template, which adopts the following technical solution: A river channel retaining wall template, comprising two lining plates arranged opposite to each other, a side of the lining plate away from the other lining plate is provided with corresponding steel templates and channel steel brackets in sequence, and also comprising multiple rows of fixing rods, each row of fixing rods having multiple numbers, the fixing rods passing through all the lining plates, the steel templates and the channel steel brackets, one end of the fixing rod is connected to an end plate, and a sleeve is sleeved on the fixing rod; A limit assembly for limiting the end plate is provided on the channel steel bracket on the water-facing surface; A mounting plate is provided on the outer side of the channel steel bracket on the back water surface, and a connecting piece for connecting the mounting plate is provided on the channel steel bracket on the back water surface, and the connecting piece enables the mounting plate to slide along the thickness direction of the retaining wall; Two sliders are slidably connected to the mounting plate, and the sliders slide along the height direction of the retaining wall. A top rod is hinged on the slider, and the top rod is hinged to the channel steel bracket on the back surface of the water. A limit spring is connected to the slider, and the limit spring is connected to the mounting plate. The limit spring makes the ends of the two top rods close to the slider tilt in a direction away from each other; A driving assembly for driving a top rod to press against the channel steel bracket is also provided on the channel steel bracket on the back surface of the water.
[0006] By adopting the above technical solution, when constructing the retaining wall formwork, the lining plate, the steel formwork and the channel steel bracket are first moved into place, a sleeve is placed at the connection point between the two lining plates, and the fixing rod is inserted into the connection point of the channel steel bracket, the steel formwork and the lining plate. The fixing rod is inserted into the corresponding sleeve, and the end plate is located on the side of the channel steel bracket facing the water.
[0007] During the movement of the fixing rod, after the fixing rod contacts the mounting plate, the fixing rod pushes the mounting plate to move in the direction away from the channel steel bracket; at the same time, the mounting plate drives the sliding block and the push rod to move, thereby causing the push rod to rotate, and the connecting piece limits the mounting plate to prevent the mounting plate and the fixing rod from moving relative to each other along the length direction of the fixing rod. At the same time, the driving assembly pushes the push rod to rotate further, and the ends of the two push rods that are away from each other move toward each other, thereby gradually lengthening the projection length of the push rod on the ground, and the push rod is pressed against the channel steel bracket on the back side of the water. Finally, the end plate is limited by the limiting assembly, so that the end plate is pressed against the channel steel bracket on the front side of the water, and the construction of the retaining wall formwork is completed.
[0008] When removing the retaining wall formwork, the limit assembly is controlled to release the limit on the end plate, and the fixing rod and the end plate are moved to gradually move the end plate away from the channel steel bracket. During this process, the connecting piece works to make the mounting plate move with the fixing rod, and the mounting plate moves toward the direction close to the channel steel bracket. At the same time, the driving assembly works to rotate and reset the top rod, so that the top rod releases the tight contact with the back-water channel steel bracket; finally, the fixing rod is pulled out, and the channel steel bracket, steel formwork and lining plate are removed; this enables the operator to disassemble and assemble the retaining wall formwork more quickly, shortens the time required for disassembling and assembling the retaining wall formwork, and improves the efficiency of forming the river retaining wall.
[0009] Optionally, the mounting plate is provided with sliding grooves corresponding to the sliders one by one, the length direction of the sliding grooves is arranged along the height direction of the corresponding channel steel bracket, and each slider is slidably inserted in the corresponding sliding groove.
[0010] By adopting the above technical solution, the slider cooperates with the slide groove, so that the mounting plate and the slider are slidably matched.
[0011] Optionally, the connecting part includes a hinged rod hinged on the lower side of the mounting plate, the hinged rod is hinged with a hinge block at one end away from the mounting plate, the hinged block is slidably connected to the channel steel bracket on the back water surface, and the hinged block slides along the height direction of the retaining wall, and a limiting spring is connected to the side walls away from each other of the two hinged blocks, and the end of the limiting spring away from the hinged block is fixed to the channel steel bracket on the back water surface.
[0012] By adopting the above technical scheme, in the initial state, the limit spring cooperates with the hinge block and the hinge rod to limit the mounting plate, so that the mounting plate contacts the channel steel template on the back water surface. During the movement of the fixed rod, the fixed rod pushes the mounting plate to move in the direction away from the channel steel template, the mounting plate moves and drives the hinge rod to rotate, so that the ends of the two hinge rods that are away from each other move toward each other, the hinge rod rotates and pulls the hinge block to move, so that the two hinge blocks move toward each other, and at the same time, the hinge block stretches the reset spring; during the rotation of the top rod, the reset spring limits the mounting plate through the hinge block and the hinge rod.
[0013] When the fixing rod is pulled out, the return spring restores its deformation and pushes the hinge block to move. The hinge block pulls the corresponding hinge rod to rotate, so that the end of the hinge rod close to the mounting plate moves toward the direction close to the channel steel bracket, thereby pulling the mounting plate toward the direction close to the channel steel bracket. When the fixing rod is out of contact with the mounting plate, the mounting plate returns to its initial position and contacts the channel steel bracket.
[0014] Optionally, the channel steel bracket on the back water surface is provided with sliding grooves corresponding to the hinge blocks one by one, the length direction of the sliding grooves is arranged along the height direction of the corresponding channel steel bracket, and each hinge block is slidably inserted in the corresponding sliding groove.
[0015] By adopting the above technical solution, the hinge block cooperates with the sliding groove, so that the hinge block and the channel steel bracket on the back water surface are slidably matched.
[0016] Optionally, the driving assembly includes a protruding rod connected to the sliding block, the protruding rod is perpendicular to the corresponding channel steel bracket, and a support rod is fixedly connected to the hinge block, and the support rod is fixed to the protruding rod.
[0017] By adopting the above technical scheme, when the fixed rod pushes the mounting plate to move in the direction away from the channel steel bracket, the two hinge blocks move in the direction of approaching each other, and the hinge blocks drive the corresponding support rod and the convex rod to move, so that the convex rod pushes the corresponding sliding block to move, and the sliding block pushes the corresponding end of the push rod to move, so that the two push rods close to the end of the mounting plate move in the direction of approaching each other, and the projection length of the push rod on the ground gradually increases, and the push rod can be pressed tightly against the channel steel bracket on the back water surface; when the fixed rod is pulled out, the two hinge blocks move in the direction of moving away from each other, and the hinge blocks drive the corresponding sliding block to move through the support rod and the convex rod, so that the push rod rotates and resets, and the push rod releases the tight contact with the channel steel bracket.
[0018] Optionally, the limiting assembly includes a U-shaped ring body slidably connected to the channel steel bracket on the water-facing surface, the ring body corresponds to the mounting plate one by one, and a pressure plate is commonly inserted in a row of ring bodies, which presses the mounting plate against the channel steel bracket on the water-facing surface.
[0019] By adopting the above technical scheme, before inserting the fixing rod into the channel steel bracket, the steel formwork and the liner, the ring body is pushed so that the ring body is located on one side of the connection point, so that the fixing rod can be inserted into the channel steel bracket. When the fixing rod is inserted into place, the end plate contacts the channel steel bracket on the water-facing surface, and then the ring body is slid to move the ring body to align with the end plate. Finally, the pressure plate is inserted into a row of ring bodies, and the pressure plate is in contact with the ring body and the end plate. The pressure plate and the ring body cooperate to limit the end plate. When pulling out the fixing rod, the ring body is pushed to move the ring body to one side of the end plate, and then the pressure plate is pulled out. When the end plate is exposed, the fixing rod can be pulled out.
[0020] Optionally, a T-shaped plug-in block is connected to the ring body, and a plug-in groove corresponding to the plug-in block is opened on the channel steel bracket on the water-facing surface. The length direction of the plug-in groove is arranged along the length direction of the retaining wall, and the plug-in groove passes through the channel steel bracket.
[0021] By adopting the above technical solution, the plug-in block cooperates with the plug-in groove, so that the ring body and the channel steel bracket on the water-facing surface are slidably matched.
[0022] Optionally, a sliding rod that passes through the ring body is slidably inserted on the ring body, and the sliding rod is located at the end of the ring body close to the channel steel bracket and is connected to a jacking plate, and the sliding rod is located at the end of the ring body away from the channel steel bracket and is connected to an anti-slip plate, and a jacking spring is provided between the anti-slip plate and the ring body, and the two ends of the jacking spring are respectively fixed to the anti-slip plate and the ring body.
[0023] By adopting the above technical solution, before inserting the pressure plate, pull the anti-slip plate to move, and the anti-slip plate moves in the direction away from the ring body, so that the sliding rod and the jacking plate move, and the movement of the anti-slip plate also stretches the jacking spring; insert the pressure plate into the corresponding ring body, release the anti-slip plate and the jacking spring to restore the deformation so that the jacking plate, pressure plate and end plate are pressed tightly, so that the ring body can limit itself, and the ring body remains aligned with the mounting plate, so that the end plate can better cooperate with the channel steel bracket.
[0024] In summary, the present application includes at least one of the following beneficial technical effects: 1. The efficiency of forming the river retaining wall is improved by setting the lining plate, steel formwork, channel steel bracket, fixing rod, end plate, top rod, mounting plate, connector, driving assembly and limit assembly; 2. By setting the support rod and the convex rod, the top rod can be driven to rotate so that the top rod and the channel steel bracket are tightly pressed; 3. By setting the ring body, pressure plate, jacking plate, sliding rod, anti-slip plate and jacking spring, the end plate can better cooperate with the channel steel bracket. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the overall structure of the retaining wall formwork according to an embodiment of the present application.
[0026] Figure 2It is a cross-sectional view showing the positional relationship between the fixing rod and the sleeve according to the embodiment of the present application.
[0027] Figure 3 It is a cross-sectional view of the overall structure of the connector according to an embodiment of the present application.
[0028] Figure 4 It is a cross-sectional view showing the connection relationship between the slider and the mounting plate according to an embodiment of the present application.
[0029] Figure 5 It is a cross-sectional view of the structure of the limiting component according to an embodiment of the present application.
[0030] Explanation of the accompanying drawings: 1. Lining plate; 2. Steel formwork; 3. Channel steel bracket; 31. Sliding groove; 32. Pad; 33. Plug-in groove; 4. Fixed rod; 41. End plate; 42. Sleeve; 5. Connector; 51. Articulated rod; 52. Articulated block; 53. Reset spring; 6. Mounting plate; 61. Matching groove; 62. Slide groove; 7. Push rod; 71. Sliding block; 72. Limiting spring; 8. Driving assembly; 81. Protruding rod; 82. Support rod; 9. Limiting assembly; 91. Ring body; 911. Plug-in block; 92. Press plate; 93. Pushing piece; 931. Pushing plate; 932. Sliding rod; 933. Anti-slip plate; 934. Pushing spring. DETAILED DESCRIPTION
[0031] The following is combined with Figure 1-5 This application is described in further detail.
[0032] The present application embodiment discloses a river retaining wall template. Figure 1 , including a lining plate 1 adapted to the water-facing surface of the retaining wall, the lining plate 1 on the water-facing surface is vertical, and the side of the lining plate 1 on the water-facing surface away from the retaining wall is sequentially provided with a steel template 2 adapted to the water-facing surface and a channel steel bracket 3, and the channel steel bracket 3 on the water-facing surface is a channel steel frame with a triangular cross-section. The river channel retaining wall template also includes a lining plate 1 adapted to the back water surface of the retaining wall, the lining plate 1 on the back water surface is inclined, and the side of the lining plate 1 on the back water surface away from the retaining wall is sequentially provided with a steel template 2 adapted to the back water surface and a channel steel bracket 3, and the channel steel bracket 3 on the back water surface is a plurality of channel steels arranged along the length direction of the retaining wall, and the length direction of the channel steel is arranged along the vertical direction of the retaining wall.
[0033] Reference Figure 1 and Figure 2A fixing rod 4 is provided at each connection point of the lining plate 1. The length direction of the fixing rod 4 is arranged along the thickness direction of the retaining wall. The fixing rod 4 passes through all the lining plates 1, the steel formwork 2 and the channel steel bracket 3. An end plate 41 is integrally formed at one end of the fixing rod 4. The diameter of the end plate 41 is larger than the diameter of the fixing rod 4. When the fixing rod 4 cooperates with the channel steel bracket 3, a sleeve 42 is sleeved on the fixing rod 4. The sleeve 42 is located between the two lining plates 1, and both ends of the sleeve 42 are in contact with the corresponding lining plates 1, and the end plate 41 is in contact with the channel steel bracket 3 on the water-facing surface.
[0034] Reference Figure 2 and Figure 3 The channel steel bracket 3 on the back water surface is provided with a connecting piece 5 corresponding to the fixing rod 4 one by one, and is connected to a mounting plate 6 corresponding to the fixing rod 4 one by one through the connecting piece 5; the connecting piece 5 includes a hinged rod 51 hinged on the upper and lower sides of the mounting plate 6, and the hinged rod 51 is hinged to a hinge block 52 at one end away from the mounting plate 6. The channel steel bracket 3 on the back water surface is provided with a sliding groove 31 corresponding to the hinge block 52 one by one, and the length direction of the sliding groove 31 is set along the height direction of the retaining wall, and each hinge block 52 is slidably inserted in the corresponding sliding groove 31.
[0035] A return spring 53 is fixedly connected to the side walls of the two hinge blocks 52 that are away from each other. One end of the return spring 53 away from the hinge block 52 is fixed to the groove wall corresponding to the sliding groove 31. The return spring 53 makes the two hinge blocks 52 move away from each other, and the ends of the two hinge rods 51 away from the mounting plate 6 are inclined in a direction away from each other; a pad 32 corresponding to the mounting plate 6 is also fixedly connected to the channel steel bracket 3 on the back water surface, and a hole is opened on the pad 32 for the fixing rod 4 to pass through. When the return spring 53 is not subjected to external force, the return spring 53 presses the mounting plate 6 against the pad 32 through the hinge rod 51.
[0036] Reference Figure 3 and Figure 4 , one side of the mounting plate 6 close to the pad 32 is slidably connected to two sliders 71, and the two sliders 71 are arranged along the height direction of the retaining wall. A slide groove 62 corresponding to the sliders 71 is opened on the side wall of the mounting plate 6 close to the pad 32, and the length direction of the slide groove 62 is arranged along the height direction of the retaining wall, and each slider 71 is slidably inserted in the slide groove 62; a push rod 7 is hinged on the slider 71, and one end of the push rod 7 away from the slide rod 71 is hinged to the pad 32, and the ends of the two push rods 7 close to the pad 32 are inclined in a direction of approaching each other.
[0037] A limiting spring 72 is fixedly connected to the side walls of the two sliders 71 that are away from each other. The end of the limiting spring 72 away from the slider 71 is fixed to the groove wall corresponding to the end of the slide groove 62, and the elastic force of the limiting spring 72 is smaller than the elastic force of the return spring 53. When the return spring 53 is not acted upon by external force, the limiting spring 72 causes the two sliders 71 to move away from each other, and the slider 71 is located at one end of the two slide grooves 62 that are away from each other.
[0038] Reference Figure 3 and Figure 4 A driving assembly 8 for controlling the rotation of the push rod 7 so that the push rod 7 is pressed against the pad 32 is provided on the channel steel bracket 3 on the back water surface. The driving assembly 8 includes a protruding rod 81 fixedly connected to the slider 71, and the protruding rod 81 is perpendicular to the channel steel bracket 3 on the back water surface. A support rod 82 perpendicular to the protruding rod 81 is fixedly connected to the hinge block 52, and the support rod 82 is fixed to the protruding rod 81.
[0039] Reference Figure 2 and Figure 5 A limiting component 9 for limiting the end plate 41 is also provided on the channel steel bracket 3 on the water-facing surface. The limiting component 9 includes a U-shaped ring body 91, which corresponds one-to-one to the end plate 41. The ring body 91 is slidably connected to the channel steel bracket 3 on the water-facing surface, and the opening of the ring body 91 faces the channel steel bracket 3 on the water-facing surface; T-shaped plug-in blocks 911 are connected to the two side walls of the ring body 91 close to the channel steel bracket 3 on the water-facing surface, and plug-in grooves 33 corresponding one-to-one to the plug-in blocks 911 are opened on the channel steel bracket 3 on the water-facing surface. The length direction of the plug-in grooves 33 is set along the length direction of the retaining wall, and each plug-in block 911 is slidably plugged into the corresponding plug-in groove 33, and the plug-in block 911 cooperates with the plug-in groove 33 to make the ring body 91 and the channel steel bracket 3 on the water-facing surface slide and cooperate.
[0040] The limiting assembly 9 also includes a pressing plate 92 inserted in a row of ring bodies 91, and the pressing plate 92 cooperates with the ring body 91 to limit the end plate 41 and the fixing rod 4; the limiting assembly 9 also includes a jacking piece 93 that makes the pressing plate 92 and the end plate 41 tightly pressed, and the jacking piece 93 includes a jacking plate 931 located in the ring body 91, and the jacking plate 931 is located on the side of the pressing plate 92 away from the channel steel bracket 3, and the side wall of the jacking plate 931 away from the pressing plate 92 is fixedly connected with a jacking plate that penetrates the ring body 91 and is connected to the ring The slide rod 932 is slidably inserted into the ring body 91, and one end of the slide rod 932 located outside the ring body 91 is fixedly connected to the anti-slip plate 933. The slide rod 932 is provided with a push-in spring 934 located between the ring body 91 and the anti-slip plate 933. One end of the push-in spring 934 is fixed to the ring body 91, and the other end of the push-in spring 934 is fixed to the anti-slip plate 933. When the push-in spring 934 is not subjected to external force, the push-in spring 934 makes the anti-slip plate 933 abut against the channel steel bracket 3 on the water-facing surface.
[0041] When constructing the river channel retaining wall template, all the lining plates 1, steel templates 2 and channel steel brackets 3 are put in place, and then the ring body 91 is pushed to move so that the ring body 91 moves to one side of the connection point, and a fixing rod 4 is inserted into each connection point so that the end plate 41 is located on the side facing the water, and a sleeve 42 is put on the fixing rod 4, and both ends of the sleeve 42 are in contact and fit with the corresponding lining plate 1; in the process of plugging in the fixing rod 4, the fixing rod 4 contacts with the mounting plate 6 and pushes the mounting plate 6 to move, so that the mounting plate 6 moves away from the channel steel bracket 3. In order to make the mounting plate 6 move more smoothly, a matching groove 61 that is adapted to the fixing rod 4 is opened on the side wall of the mounting plate 6 close to the pad 32. The fixing rod 4 cooperates with the matching groove 61, so that the fixing rod 4 can guide the mounting plate 6 to reduce the displacement of the mounting plate 6 when moving.
[0042] The mounting plate 6 drives the hinge rod 51 to rotate, so that the ends of the two hinge rods 51 that are away from each other move toward each other, thereby driving the corresponding hinge block 52 to move, so that the two hinge blocks 52 move toward each other, and the hinge block 52 compresses the return spring 53; at the same time, the mounting plate 6 also drives the push rod 7 to rotate, so that the ends of the two push rods 7 that are away from each other rotate toward each other.
[0043] The hinge block 52 moves and drives the support rod 82, the protruding rod 81 and the corresponding slider 71 to move, so that the two sliders 71 move in the direction of approaching each other, the slider 71 compresses the limit spring 72, and the slider 71 drives the push rod 7 to further rotate; at the same time, the reset spring 53 limits the mounting plate 6 through the hinge rod 51, and the mounting plate 6 limits the corresponding end of the push rod 7. The slider 71 moves to push the push rod 7 to continue to rotate, so that the push rod 7 is pressed against the pad 32. The pad 32 makes the force transmitted from the push rod 7 to the channel steel bracket 3 more uniform, thereby reducing the deformation of the channel steel bracket 3 due to stress concentration.
[0044] When the end plate 41 contacts the channel steel bracket 3 on the water-facing surface, the fixing rod 4 moves into place, and at this time the ring body 91 is moved to align the ring body 91 with the corresponding end plate 41, and the jacking plate 931 is pushed to move the jacking plate 931, the sliding rod 932 and the anti-slip plate 933. The movement of the anti-slip plate 933 also stretches the jacking spring 934; when the distance between the jacking plate 931 and the end plate 41 can accommodate the pressure plate 92, the pressure plate 92 is inserted into the corresponding ring body 91, and at this time the jacking spring 934 restores its deformation to make the jacking plate 931, the pressure plate 92 and the end plate 41 press tightly, so that the ring body 91 can limit itself, and the ring body 91 remains aligned with the mounting plate 6, so that the end plate 41 can better cooperate with the channel steel bracket 3, and the end plate 41 presses tightly against the channel steel bracket 3 on the water-facing surface, completing the limiting and fixing of the lining plate 1, steel formwork 2 and channel steel bracket 3 on the water-facing surface and the back water surface.
[0045] When removing the channel steel bracket 3, the steel formwork 2 and the lining plate 1, the ring body 91 is pushed to move, so that the ring body 91 and the jacking plate 931 are moved to one side of the end plate 41, and the pressure plate 92 is pulled out. After the pressure plate 92 is out of contact with the jacking plate 931, the jacking spring 934 restores its deformation and pushes the anti-slip plate 933, the sliding rod 932 and the jacking plate 931 to move until the jacking plate 931 abuts against the channel steel bracket 3; when the pressure plate 92 is out of contact with the mounting plate 6, the reset spring 53 restores its deformation and drives the corresponding hinge block 52 to move and reset, so that the two hinge blocks 52 move away from each other, and the two hinge rods 51 move away from the mounting plate 6 at one end in a direction away from each other, and the hinge rod 51 rotates and pulls the mounting plate 6 to move in a direction close to the channel steel bracket 3.
[0046] The hinged rod 51 moves and drives the support rod 82, the protruding rod 81 and the corresponding slider 71 to move. The limit spring 72 also restores its deformation and pushes the slider 71 to move. The movement of the slider 71 drives the push rod 7 to rotate, so that the push rod 7 rotates and gradually resets. When the reset spring 53 returns to its initial state, the limit spring 72 also returns to its initial state. The mounting plate 6, the hinged rod 51 and the push rod 7 all return to their initial positions. Then the operator pulls out the fixing rod 4, and finally removes the lining plate 1, the steel formwork 2 and the channel steel bracket 3. When disassembling and assembling the retaining wall formwork, compared with the fixing method of bolts and nuts, it is fixed by the cooperation of the fixing rod 4, the push rod 7, the ring body 91 and the jacking plate 931, so that the operating steps when disassembling and assembling the retaining wall formwork are reduced, thereby improving the efficiency of forming the river retaining wall.
[0047] The implementation principle of a river retaining wall formwork in an embodiment of the present application is as follows: put the lining plates 1, steel formworks 2 and channel steel brackets 3 on the water-facing and water-retaining surfaces in place, move the ring body 91 so that the ring body 91 is located on one side of the connection point, insert the fixing rod 4 into all the lining plates 1, steel formworks 2 and channel steel brackets 3, and at the same time, the fixing rod 4 pushes the mounting plate 6 to move, and the mounting plate 6 rotates the top rod 7 through the hinged rod 51, the support rod 82 and the protruding rod 81, and the top rod 7 is pressed against the pad 32; when the end plate 41 contacts the channel steel bracket 3, move the ring body 91 so that the ring body 91 is aligned with the end plate 41, pull the anti-slip plate 933, and insert the pressure plate 92 into a row of ring bodies 91. When removing the lining plate 1, the steel formwork 2 and the channel steel bracket 3, move the ring body 91 until the ring body 91 is located on one side of the end plate 41, and pull out the pressure plate 92. When the pressure plate 92 is out of contact with the end plate 41, the reset spring 53 and the limit spring 72 restore their deformation and reset the mounting plate 6 and the top rod 7, and finally pull out the fixing rod 4.
[0048] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A river retaining wall template, comprising two lining plates (1) arranged opposite to each other, wherein a corresponding steel template (2) and a channel steel bracket (3) are sequentially arranged on a side of the lining plate (1) away from the other lining plate (1), characterized in that: It also includes a plurality of rows of fixing rods (4), each row of fixing rods (4) having a plurality of fixing rods (4), the fixing rods (4) passing through all the lining plates (1), the steel formwork (2) and the channel steel brackets (3), one end of the fixing rod (4) being connected to an end plate (41), and a sleeve (42) being sleeved on the fixing rod (4); A limiting assembly (9) for limiting the position of the end plate (41) is provided on the channel steel bracket (3) on the water-facing surface; A mounting plate (6) is provided on the outer side of the channel steel bracket (3) on the back water surface, and a connecting piece (5) for connecting the mounting plate (6) is provided on the channel steel bracket (3) on the back water surface, wherein the connecting piece (5) enables the mounting plate (6) to slide along the thickness direction of the retaining wall; Two sliders (71) are slidably connected to the mounting plate (6). The sliders (71) slide along the height direction of the retaining wall. A top rod (7) is hingedly connected to the slider (71). The top rod (7) is hingedly connected to the channel steel bracket (3) on the back surface of the water. A limit spring (72) is connected to the slider (71). The limit spring (72) is connected to the mounting plate (6). The limit spring (72) causes the ends of the two sliders (7) close to the slider (71) to tilt in a direction away from each other. A driving assembly (8) for driving a top rod (7) to press against the channel steel bracket (3) is also provided on the back surface of the water.
2. A river retaining wall template according to claim 1, characterized in that: The mounting plate (6) is provided with a slide groove (62) corresponding to the sliders (71) one by one. The length direction of the slide groove (62) is arranged along the height direction of the corresponding channel steel bracket (3). Each slider (71) is slidably inserted in the corresponding slide groove (62).
3. A river retaining wall template according to claim 1 or 2, characterized in that: The connecting member (5) comprises a hinged rod (51) hinged on the upper and lower sides of the mounting plate (6); one end of the hinged rod (51) away from the mounting plate (6) is hinged with a hinged block (52); the hinged block (52) is slidably connected to the channel steel bracket (3) on the back water surface, and the hinged block (52) slides along the height direction of the retaining wall; a limit spring (72) is connected to the side walls of the two hinged blocks (52) away from each other; one end of the limit spring (72) away from the hinged block (52) is fixed to the channel steel bracket (3) on the back water surface.
4. A river retaining wall template according to claim 3, characterized in that: The channel steel bracket (3) on the back water surface is provided with sliding grooves (31) corresponding to the hinge blocks (52) one by one. The length direction of the sliding grooves (31) is arranged along the height direction of the corresponding channel steel bracket (3). Each hinge block (52) is slidably inserted in the corresponding sliding groove (31).
5. A river retaining wall formwork according to claim 3, characterized in that: The driving assembly (8) comprises a protruding rod (81) connected to the sliding block (71), the protruding rod (81) being perpendicular to the corresponding channel steel bracket (3), and a supporting rod (82) being fixedly connected to the hinge block (52), the supporting rod (82) being fixed to the protruding rod (81).
6. A river retaining wall formwork according to claim 1, characterized in that: The position limiting assembly (9) comprises a U-shaped ring body (91) slidably connected to the channel steel bracket (3) on the water-facing surface, the ring bodies (91) corresponding to the mounting plates (6) one by one, and a pressing plate (92) is commonly inserted into a row of ring bodies (91), and the pressing plate (92) causes the mounting plate (6) to press against the channel steel bracket (3) on the water-facing surface.
7. A river retaining wall template according to claim 6, characterized in that: A T-shaped plug-in block (911) is connected to the ring body (91), and a plug-in groove (33) corresponding to the plug-in block (911) is provided on the channel steel bracket (3) on the water-facing surface. The length direction of the plug-in groove (33) is arranged along the length direction of the retaining wall, and the plug-in groove (33) passes through the channel steel bracket (3).
8. A river retaining wall formwork according to claim 6, characterized in that: The ring body (91) is slidably connected with a slide bar (932) which passes through the ring body (91); one end of the slide bar (932) located on the ring body (91) close to the channel steel bracket (3) is connected to a jacking plate (931); one end of the slide bar (932) located on the ring body (91) away from the channel steel bracket (3) is connected to an anti-slip plate (933); a jacking spring (934) is provided between the anti-slip plate (933) and the ring body (91); and both ends of the jacking spring (934) are respectively fixed to the anti-slip plate (933) and the ring body (91).