Connecting joint of full-assembly type prefabricated foundation beam and full-assembly type prefabricated foundation column

By setting limit blocks and fit blocks on the connection nodes of prefabricated foundation beams and foundation columns, and adjusting the sliding of limit blocks by using bolts and top contact blocks, the problems of rust and looseness of bolts and nuts in the prior art are solved, and the problem of rust and looseness of bolts and nuts is improved. The stability and firmness of the connection extend the service life of the building.

CN119062003AInactive Publication Date: 2024-12-03XINJIANG ZHONGJING YIYUAN BUILDING MATERIALS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411533591.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-31
Publication Date
2024-12-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing fully-assembled prefabricated foundation beams and prefabricated foundation column connection nodes are ineffective due to the corrosion and looseness of bolts and nuts, which affects the firmness and service life of the building.

Method used

A connection node is designed to ensure that the base beam and the base column are provided with limit blocks and fitting blocks, fitting grooves and plug-in slots are used to adjust the sliding of the limit blocks to ensure that the foundation beam and the The fitting block plug of the foundation column limits the deviation movement of the foundation beam, reduces the use of threaded connections, and avoids rust and looseness.

Benefits of technology

It improves the connection stability between the foundation beam and the foundation column, avoids rust and loosening of the threaded connection, extends the service life of the building, and enhances the firmness of the connection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119062003A_ABST
    Figure CN119062003A_ABST
Patent Text Reader

Abstract

The invention relates to a connecting joint, in particular to a fully-assembled prefabricated foundation beam and fully-assembled prefabricated foundation column connecting joint which is arranged between a foundation column and a foundation beam and comprises a limiting block and an embedding block, and the limiting block is movably arranged on the foundation beam. The embedded blocks and the limiting blocks are arranged on the foundation column and the foundation beam, the limiting blocks are movably arranged on the foundation beam, the embedded grooves matched with the embedded blocks are formed in the limiting blocks, and when the foundation beam is connected with the foundation column, two bolts are used for carrying out jacking adjustment on the other jacking blocks correspondingly; the limiting block can be forced to slide and adjust on the extension column, so that when the extension column integrally poured and formed on the foundation beam is inserted into the extension cylinder integrally poured and formed on the foundation column, one end of the embedding block is inserted into the embedding groove, and the effect that the foundation beam is pulled towards the end away from the foundation column is limited; and the connection between the foundation beam and the foundation column is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a connection node, in particular to a connection node between a fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column. Background Art

[0002] When buildings are assembled through prefabricated parts, the construction period can be greatly shortened. Therefore, prefabricated parts are particularly important in the modern construction industry. Prefabricated foundation beams are a commonly used component in construction projects and are part of prefabricated concrete components. They are mainly used to support the superstructure and transfer loads to the foundation. They have some significant advantages in the construction process. Prefabricated foundation beams are generally used in conjunction with prefabricated foundation columns. Prefabricated foundation columns are important components used to support the superstructure in construction projects. They are usually prefabricated from concrete and have many advantages and wide applications. The connecting node is the connecting component between the prefabricated foundation beam and the prefabricated foundation column, which enables the two to be firmly and stably connected.

[0003] At present, the connection nodes between fully assembled prefabricated foundation beams and fully assembled prefabricated foundation columns are generally connected by bolts and nuts. However, during long-term use, the connection parts between the nuts and bolts may rust or the nuts may loosen on the bolts, resulting in failure of the connection nodes, which will affect the overall firmness of the building constructed with prefabricated parts and indirectly affect the service life of the building. Summary of the invention

[0004] The object of the present invention is to provide a connection node between a fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above purpose, the present invention provides the following technical solutions: A connection node between a fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column, which is arranged between a foundation column and a foundation beam, and comprises a limit block and an interlocking block, wherein the limit block is movably arranged on the foundation beam, and the interlocking block is movably arranged on the foundation column; The limit block is formed with an engaging groove adapted to the engaging block, and the left and right sides and the lower side of the engaging groove are respectively a first inclined surface, a second inclined surface and a first straight surface, and the first inclined surface and the second inclined surface are inclined toward one side of the foundation beam; The left and right sides and the lower side of one end of the engaging block are formed in sequence with a third inclined surface, a fourth inclined surface and a second straight surface which are adapted to the left and right sides and the lower side of the engaging groove.

[0006] The fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column connection node as described above: nine first steel bars are evenly spaced and arranged on the foundation column, an extension tube is integrally cast and formed on one side of the foundation column, and a plug-in slot is arranged inside the extension tube; A drop groove is provided on one side of the upper side of the extension tube, and six plug holes are symmetrically provided on the extension tube, and the plug holes are arranged through the foundation column; The drop groove is slidably connected to the engaging block.

[0007] The connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column as described above: an extension column is integrally cast at one end of the foundation beam close to the foundation column, and a limited sliding groove is symmetrically arranged on the extension column along the length direction of the foundation beam, and a sliding groove is symmetrically arranged on one side of the extension column away from the limited sliding groove; The limiting slide groove is movably connected to the limiting block, and the two limiting slide grooves are symmetrically arranged in an L-shape.

[0008] The connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column as described above: six second steel bars are symmetrically arranged on the foundation beam at one end of the extension column, the second steel bars are inserted into the corresponding insertion holes, and the second steel bars are threadedly connected with a nut at one end of the foundation column, and the nut is set in abutment with the foundation column.

[0009] The connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column as described above: a sliding block is symmetrically cast and formed on one side below the limit block, and the two sliding blocks and the limit slide groove are adapted to form a symmetrical L-shaped arrangement; An interfering oblique groove is symmetrically arranged below the limit block, the interfering oblique groove is arranged corresponding to the sliding groove, and the width of the interfering oblique groove is wider than the width of the sliding groove; The limiting block is provided with a plurality of engaging grooves.

[0010] The connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column as described above: the limit block and the extension column are both slidably inserted into the insertion groove provided on the extension tube.

[0011] The connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column as described above: top contact blocks are symmetrically and movably arranged in the two sliding grooves, and a conflict slope is formed on the top of the top contact block, and the conflict slope is arranged to conflict with the inclined surface of the conflicting inclined groove; The bottoms of the two top contact blocks are respectively arranged to abut against the tops of the two bolts.

[0012] The connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column as described above: the two bolts are threadedly connected in two internal threaded cylinders, and the internal threaded cylinders are embedded in the extension cylinder; The diameter of the two bolts is smaller than the width of the two sliding grooves.

[0013] As described above, at the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column: the six second steel bars are staggered with the nine first steel bars on the foundation column.

[0014] Compared with the prior art, the present invention has the following beneficial effects: By arranging an engaging block and a limit block on the foundation column and the foundation beam, the limit block is movably arranged on the foundation beam, and an engaging groove matched with the engaging block is arranged on the limit block. When the foundation beam is connected to the foundation column, the other top contact block is adjusted by two bolts respectively, which can force the limit block to slide and adjust on the extension column, so that when the extension column integrally cast on the foundation beam is inserted into the extension tube integrally cast on the foundation column, one end of the engaging block is inserted into the engaging groove, thereby limiting the effect of pulling the foundation beam away from one end of the foundation column, improving the connection between the foundation beam and the foundation column, and avoiding rust or loosening of the connection due to the use of a large number of threaded connections, which affects the connection stability of the connection node. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a structural schematic diagram of the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0016] Figure 2 It is a structural schematic diagram of the cross-section of the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0017] Figure 3 This is a structural schematic diagram of the front view of the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0018] Figure 4 It is a structural schematic diagram of the foundation column in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0019] Figure 5 It is a structural schematic diagram of the extension tube in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0020] Figure 6 It is a structural schematic diagram of the node foundation beam connecting the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0021] Figure 7It is a structural schematic diagram of the local foundation beam in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0022] Figure 8 This is a structural schematic diagram of the foundation beam in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column, looking up.

[0023] Fig. 9 This is a structural schematic diagram of the limit block in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0024] Fig.10 This is a structural schematic diagram of the limit block in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column when viewed from above.

[0025] Fig.11 It is a structural schematic diagram of the interlocking block in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0026] Fig.12 It is a structural schematic diagram of the cross-section of the limit block in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0027] Fig.13 This is a structural schematic diagram of the top contact block in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0028] Fig.14 This is a structural schematic diagram of the internal threaded tube in the connection node between the fully assembled prefabricated foundation beam and the fully assembled prefabricated foundation column.

[0029] In the figure: 1. foundation column; 2. first steel bar; 3. extension tube; 4. drop groove; 5. plug-in hole; 6. extension column; 7. foundation beam; 8. limit slide groove; 9. sliding groove; 10. second steel bar; 11. nut; 12. limit block; 13. sliding block; 14. fitting groove; 15. abutting inclined groove; 16. fitting block; 17. top contact block; 18. abutting slope; 19. bolt; 20. internal thread tube. DETAILED DESCRIPTION

[0030] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0031] See also Figure 1 to Figure 14 In an embodiment of the present invention, a connection node between a fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column is arranged between a foundation column 1 and a foundation beam 7, and includes a limit block 12 and an interlocking block 16, wherein the limit block 12 is movably arranged on the foundation beam 7, and the interlocking block 16 is movably arranged on the foundation column 1.

[0032] The limit block 12 is formed with an engaging groove 14 adapted to the engaging block 16 , and the left and right sides and the lower side of the engaging groove 14 are respectively a first inclined surface, a second inclined surface and a first straight surface, and the first inclined surface and the second inclined surface are inclined toward one side of the foundation beam 7 .

[0033] The left and right sides and the lower side of one end of the engaging block 16 are formed in sequence with a third inclined surface, a fourth inclined surface and a second straight surface corresponding to the left and right sides and the lower side of the engaging groove 14 .

[0034] In this embodiment, when the foundation column 1 and the foundation beam 7 are connected through the connecting node, the engaging block 16 arranged on the foundation column 1 will engage with the engaging groove 14 provided on the limiting block 12 arranged on the foundation beam 7, and the first inclined surface and the second inclined surface on the left and right sides of the engaging groove 14 are inclined toward one side of the foundation beam 7. Therefore, when the foundation beam 7 approaches the foundation column 1 for connection, the engaging block 16 will conflict with the limiting block 12, and the limiting block 12 will rise by contacting the engaging block 16. When the engaging block 16 is engaged with the engaging groove 14, the foundation beam 7 cannot be pulled out to the side away from the foundation column 1 without lifting the engaging block 16. The connection of the foundation beam 7 on the foundation column 1 can be limited. By design, when the foundation column 1 and the foundation beam 7 are connected, the use of threaded connecting parts can be reduced, and rust or loosening between the connecting parts due to threaded connection can be avoided, resulting in connection failure and affecting the firmness of the building built with prefabricated parts.

[0035] As a further solution of the present invention, nine first steel bars 2 are evenly spaced on the foundation column 1, an extension tube 3 is integrally cast on one side of the foundation column 1, and a plug-in groove is provided inside the extension tube 3.

[0036] A drop groove 4 is provided on one side of the upper side of the extension tube 3 , and six plug holes 5 are symmetrically provided on the extension tube 3 , and the plug holes 5 are penetrated through the base column 1 ; the drop groove 4 is slidably connected to the engaging block 16 .

[0037] In this embodiment, the drop groove 4 is also inclined toward one side of the foundation beam 7. When the engaging block 16 is installed inside the drop groove 4, affected by gravity and the inclined design of the drop groove 4, the engaging block 16 can slide down inside the drop groove 4, so that the engaging block 16 is engaged with the engaging groove 14 to meet the positioning connection requirements. When the foundation beam 7 is installed on the foundation column 1, the engaging block 16 is not placed inside the drop groove 4 in advance. After the foundation column 1 and the foundation beam 7 are fully connected, the engaging block 16 is placed inside the drop groove 4 to ensure that the overall installation process will not be interfered with. The plug-in hole 5 is opened on both the extension tube 3 and the foundation column 1.

[0038] As a further solution of the present invention, an extension column 6 is integrally cast at one end of the foundation beam 7 close to the foundation column 1, and a limiting slide groove 8 is symmetrically arranged on the extension column 6 along the length direction of the foundation beam 7, and a sliding groove 9 is symmetrically arranged on the side of the extension column 6 away from the limiting slide groove 8; the limiting slide groove 8 is movably connected to the limiting block 12, and the two limiting slide grooves 8 are symmetrically L-shaped.

[0039] In this embodiment, the extension column 6 integrally cast on the foundation beam 7 is used to connect the foundation beam 7 with the foundation column 1. The shorter ends of the two L-shaped limit slots 8 face the two sides of the extension column 6. The sliding grooves 9 symmetrically opened on the extension column 6 are located between the two limit slots 8. The length of the sliding grooves 9 is smaller than the distance between the two limit slots 8. The limit slots 8 and the sliding grooves 9 are both reserved when the extension column 6 is cast to meet the connection requirements.

[0040] As a further solution of the present invention, six second steel bars 10 are symmetrically arranged on the foundation beam 7 at one end of the extension column 6, the second steel bars 10 are inserted into the corresponding insertion holes 5, and the second steel bars 10 are threadedly connected with a nut 11 at one end of the foundation column 1, and the nut 11 is set in conflict with the foundation column 1.

[0041] In this embodiment, the six second steel bars 10 fixedly arranged on the foundation beam 7 are inserted into the insertion holes 5 which are opened through the extension tube 3 and the foundation column 1. A threaded column is welded on the second steel bars 10 which extend to the side of the foundation column 1 away from the extension tube 3. The threaded column is threadedly connected with the nut 11. By tightening the thread of the nut 11, the connection between the foundation beam 7 and the foundation column 1 can be made tighter, thereby ensuring a firm connection effect.

[0042] As a further solution of the present invention, a sliding block 13 is symmetrically cast and formed on one side below the limit block 12, and the two sliding blocks 13 are symmetrically matched with the limit slide groove 8 in an L-shaped arrangement; interference bevel grooves 15 are symmetrically arranged below the limit block 12, and the interference bevel grooves 15 are arranged corresponding to the sliding groove 9, and the width of the interference bevel grooves 15 is wider than the width of the sliding groove 9; and a plurality of interlocking grooves 14 are arranged on the limit block 12.

[0043] In this embodiment, the spacing between two adjacent interlocking grooves 14 among the multiple interlocking grooves 14 is the same as the distance of the width difference between the interfering inclined groove 15 and the sliding groove 9. The limit block 12, the sliding block 13, the interlocking groove 14 and the interfering inclined groove 15 are also prefabricated parts. Through casting, the sliding block 13 slides in the limit slide groove 8. Through the L-shaped sliding block 13 and the limit slide groove 8, the limit block 12 can only be adjusted horizontally on the extension column 6 and cannot be adjusted vertically or tilted, thereby ensuring the connection effect between the limit block 12 and the extension column 6.

[0044] As a further solution of the present invention, the limit block 12 and the extension column 6 are both slidably inserted into the insertion groove provided on the extension tube 3.

[0045] In this embodiment, the limit block 12 is slidably set in the limit slide groove 8 set on the extension column 6 through the sliding block 13. Therefore, when the extension column 6 is plugged into the plug-in groove on the extension tube 3, the limit block 12 will be plugged into the plug-in groove on the extension tube 3 together. The extension column 6 and the foundation beam 7 are cast as one piece, and the extension tube 3 and the foundation column 1 are cast as one piece. The extension column 6 is plugged into the plug-in groove on the extension tube 3, so that the foundation beam 7 and the foundation column 1 can be connected, which is convenient for the later firm positioning.

[0046] As a further solution of the present invention, top contact blocks 17 are symmetrically and movably arranged in the two sliding grooves 9, and a resistance slope 18 is formed on the top of the top contact block 17. The resistance slope 18 is set to resist the inclined surface of the resistance inclined groove 15; the bottoms of the two top contact blocks 17 are respectively set to resist the tops of the two bolts 19.

[0047] In this embodiment, since the whole is equipped with prefabricated modular parts, it is inevitable that there will be deviations when the components are cast and formed. If the limit block 12 is integrally cast and formed on the extension column 6, the engaging block 16 slidably arranged inside the drop groove 4 cannot be accurately inserted and engaged with the engaging groove 14 provided on the limit block 12. Through the design of the top contact block 17 and the bolt 19, after the extension column 6 is completely inserted into the insertion groove provided on the extension tube 3, the engaging block 16 is placed in the drop groove 4. If one end of the engaging block 16 cannot be accurately engaged with the engaging groove 14, the two bolts 19 are rotated and adjusted, and the two bolts 19 respectively contact the bottom of the top contact block 17, so that the top contact block 17 rises inside the sliding groove 9. Since the contact slope 18 set on the top of the top contact block 17 contacts the inclined surface of the contact inclined groove 15, when adjusting the bolt 19, taking the limit block 12 as an example, when the bolt 19 on the right side is rotated and adjusted, the top contact block 17 will be raised inside the sliding groove 9. As the top of the top contact block 17 is raised, the interfering slope 18 at the top of the top contact block 17 will interfere with the inclined surface of the interfering inclined groove 15. Since the width of the interfering inclined groove 15 is wider than that of the top contact block 17, the top contact of the top contact block 17 will cause the limit block 12 to move to the left. As above, when the left bolt 19 is rotated and adjusted, the limit block 12 will move to the right. Through the matching adjustment, the limit block 12 can be adjusted to slide left and right. Since the spacing between the two adjacent fitting grooves 14 is different from the width of the interfering inclined groove 15 and the sliding groove 9, The distance is the same, so when the limit block 12 is adjusted to move left and right, the maximum movement distance is the spacing between two adjacent engaging grooves 14. It should be noted that the deviation of the prefabricated parts exists, but the deviation range is small. Therefore, the movement distance of the limit block 12 can meet the need to make the engaging groove 14 and one end of the engaging block 16 engage and adjust for use. By adjusting, the engaging block 16 can be accurately plugged and engaged with the engaging groove 14, so that the foundation beam 7 cannot deviate from the foundation column 1 when adjusting on the foundation column 1, thereby improving the connection effect.

[0048] As a further solution of the present invention, the two bolts 19 are threadedly connected in two internal threaded tubes 20, and the internal threaded tubes 20 are embedded in the extension tube 3; the diameter of the two bolts 19 is smaller than the width of the two sliding grooves 9.

[0049] In this embodiment, the internal threaded tube 20 is buried and reserved in the casting mold when the extension tube 3 is cast. The connecting ribs arranged at both ends of the internal threaded tube 20 can prevent the internal threaded tube 20 from rotating inside the extension tube 3 when the bolt 19 is threadedly connected and adjusted. After the engaging block 16 is plugged into the engaging groove 14, the two bolts 19 are screwed and adjusted so that the bolts 19 contact the top contact block 17, so that the interference slope 18 is tightly contacted on the inclined surface of the interference inclined groove 15. The two top contact blocks 17 contact the interference inclined groove 15 at the bottom of the limit block 12, so that the limit block 12 loses the effect of moving left and right, and the plug-in engagement between the engaging groove 14 and the engaging block 16 can be improved, thereby improving the connection firmness.

[0050] As a further solution of the present invention, the six second steel bars 10 are staggered with the nine first steel bars 2 on the foundation column 1 .

[0051] In this embodiment, the nine first steel bars 2 on the foundation column 1 are arranged in three rows and three columns, and the six second steel bars 10 on the foundation beam 7 are arranged in two symmetrical rows. The two symmetrical rows of six second steel bars 10 are located between the two outermost rows of first steel bars 2 and are staggered with the first steel bars 2. Through the arrangement, it is possible to ensure that the first steel bars 2 on the foundation column 1 and the second steel bars 10 on the foundation beam 7 maintain integrity, and the connection strength between the foundation column 1 and the foundation beam 7 can be improved. A base with a larger cross-sectional area than the foundation column 1 is provided at the bottom of the foundation column 1. Through the larger base, the support force area can be increased to ensure that the foundation column 1 does not sink due to the smaller force area when it touches the ground.

[0052] The above embodiments are exemplary rather than restrictive, so the technical solutions of the present invention that can be implemented in other specific forms without departing from the spirit or basic features of the present invention are all included in the present invention.

Claims

1. A fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column connection node, arranged between a foundation column (1) and a foundation beam (7), It is characterized in that It comprises a limit block (12) and an engaging block (16), wherein the limit block (12) is movably arranged on the foundation beam (7), and the engaging block (16) is movably arranged on the foundation column (1); The limit block (12) is formed with an engaging groove (14) adapted to the engaging block (16); the left and right sides and the lower side of the engaging groove (14) are respectively provided with a first inclined surface, a second inclined surface and a first straight surface; the first inclined surface and the second inclined surface are inclined toward one side of the foundation beam (7); The left and right sides and the lower side of one end of the engaging block (16) are formed in sequence with a third inclined surface, a fourth inclined surface and a second straight surface which are adapted to the left and right sides and the lower side of the engaging groove (14).

2. A fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column connection node according to claim 1, It is characterized in that Nine first steel bars (2) are arranged at equal intervals on the foundation column (1); an extension tube (3) is integrally cast on one side of the foundation column (1); and a plug-in notch is arranged inside the extension tube (3); A drop groove (4) is provided on one side of the upper side of the extension tube (3), and six plug holes (5) are symmetrically provided on the extension tube (3), and the plug holes (5) are provided through the base column (1); The drop groove (4) is slidably connected to the engaging block (16).

3. A connection node between a fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column according to claim 1, It is characterized in that An extension column (6) is integrally cast at one end of the foundation beam (7) close to the foundation column (1); a limit slide groove (8) is symmetrically arranged on the extension column (6) along the length direction of the foundation beam (7); and a sliding groove (9) is symmetrically arranged on one side of the extension column (6) away from the limit slide groove (8); The limiting slide groove (8) is movably connected to the limiting block (12), and the two limiting slide grooves (8) are symmetrically arranged in an L-shape.

4. A fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column connection node according to claim 3, It is characterized in that Six second steel bars (10) are symmetrically arranged on the foundation beam (7) at one end of the extension column (6); the second steel bars (10) are inserted into corresponding insertion holes (5); a nut (11) is threadedly connected to one end of the second steel bar (10) located at the foundation column (1); the nut (11) is arranged to abut against the foundation column (1).

5. A fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column connection node according to claim 4, It is characterized in that A sliding block (13) is symmetrically cast and formed integrally on one side below the limiting block (12), and the two sliding blocks (13) are adapted to be symmetrically L-shaped with the limiting sliding groove (8); A resisting oblique groove (15) is symmetrically arranged below the limit block (12), the resisting oblique groove (15) is arranged corresponding to the sliding groove (9), and the width of the resisting oblique groove (15) is wider than the width of the sliding groove (9); The limiting block (12) is provided with a plurality of engaging grooves (14).

6. A connection node between a fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column according to claim 5, It is characterized in that The limit block (12) and the extension column (6) are both slidably inserted into the insertion groove provided on the extension tube (3).

7. A fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column connection node according to claim 5, It is characterized in that A top contact block (17) is symmetrically and movably arranged in the two sliding grooves (9), and a top of the top contact block (17) is formed with a contact slope (18), and the contact slope (18) is arranged to contact the inclined surface of the contact inclined groove (15); The bottoms of the two top contact blocks (17) are respectively arranged to contact with the tops of the two bolts (19).

8. A fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column connection node according to claim 7, It is characterized in that The two bolts (19) are threadedly connected in two internal threaded barrels (20), and the internal threaded barrels (20) are embedded in the extension barrel (3); The diameter of the two bolts (19) is smaller than the width of the two sliding grooves (9).

9. A fully assembled prefabricated foundation beam and a fully assembled prefabricated foundation column connection node according to claim 4, It is characterized in that The six second steel bars (10) are arranged in a staggered manner with respect to the nine first steel bars (2) on the foundation column (1).