Layered installation dry connection concrete shear wall / special-shaped column structure and construction method

Through the construction method of layered installation of dry-connected concrete shear wall/special column structures, the problem of lack of installation methods of precast concrete special columns and high number of steel bars and high cost is solved, and flexible assembly and efficient construction of the structure are achieved, improving the improvement of the structure It has shock resistance and energy dissipation and shock absorption effects.

CN119062020APending Publication Date: 2024-12-03GUANGZHOU UNIVERSITY +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411355234.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-27
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The existing technology lacks the installation method of precast concrete special-shaped columns, and the number of steel bars of precast shear walls is large, the connection quality is difficult to control, and the connection cost is high. The height of the traditional column connection node is large, and the amount of formwork and wet operations is also used. Larger.

Method used

The construction method of layered installation of dry-connected concrete shear wall/special column structures includes installing the first-layer prefabricated shear wall/special column, connecting the beam bottom longitudinal bars and short steel bars of the prefabricated beam through connectors, and hoisting in place on the upper layer prefabricated Shear wall, adjusting steel support and fixing, prestressed rib casing is installed, surface concrete is poured, and the entire building structure is installed in circulation. The prestressed ribs are tensile on the top of the prefabricated shear wall.

Benefits of technology

Achieve flexible assembly of prefabricated shear walls/special columns, reduce the number of steel bar connections and connectors, concentrate the post-cast concrete area within the slab thickness range, reduce construction costs and wet work amounts, and improve the seismic performance of the structure. and energy dissipation and shock absorption effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119062020A_ABST
    Figure CN119062020A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for installing a dry connection concrete shear wall / special-shaped column structure in a layered mode. The construction method comprises the steps that firstly, a first-layer prefabricated shear wall / special-shaped column is installed; step 2, mounting a precast beam of the current layer, and mounting a precast floor slab bottom plate; 3, hoisting in place and fixing the upper-layer prefabricated shear wall / special-shaped column; 4, connecting prestressed tendons of the upper-layer prefabricated shear wall / special-shaped column and the lower-layer prefabricated shear wall / special-shaped column; sleeves on the peripheries of the prestressed tendons at the connecting parts of the upper and lower prefabricated shear walls / special-shaped columns are mounted; moving an upper moving steel bar of the precast beam to a node area; placing surface layer steel bars of the laminated slab; 5, a formwork is installed; concrete is poured into the floor cover layer and all connecting areas; sixthly, the whole building structure installation is completed in a circulating mode; and the prestressed tendons are tensioned and locked, and then structural construction is completed. Prefabricating is carried out with a single layer as a section, dry connection concrete shear walls / special-shaped columns are installed in a layered mode, the structural flexibility is high, and assembling can be carried out in a layered mode according to requirements.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction, and in particular to a layered installation dry-connected concrete shear wall / special-shaped column structure and a construction method. Background Art

[0002] Reinforced concrete columns are important load-bearing components in concrete structures. Based on their shapes, they can be divided into rectangular columns and special-shaped columns. Special-shaped columns have a variety of forms and are as thick as the building walls. They can organically combine the beauty of the building, the flexibility of the use function, and the reasonable load-bearing performance of the building structure. They are especially suitable for use in low-rise and multi-story residential buildings. Reinforced concrete shear walls have a similar shape to special-shaped columns, but the difference is that the ratio of the length to the thickness of the former is significantly greater than that of the latter.

[0003] In the prior art, CN 105544865 B discloses a prestressed assembled composite special-shaped column. Although prestressed tendons are also set in the special-shaped column, it needs to be cast on site, which takes a long time. The research and development of steel special-shaped column structures and steel special-shaped columns has been relatively mature, and there are some actual projects. The common problem of steel structures is that they require large areas of steel plates, a large number of welding and bolt connections, high costs, and poor fire and corrosion resistance.

[0004] At present, the main method for prefabricating and assembling rectangular columns at home and abroad is grouting sleeve connection. Grouting sleeve connection is achieved by pre-embedding the finished sleeve in the prefabricated concrete component, inserting the steel bar from the sleeve and injecting grouting material to achieve steel bar connection. This technology is also the main method of mechanical connection of vertical steel bars in prefabricated components in China. Its disadvantages are that the number of steel bars is large, the grouting quality is difficult to control, there is a lack of simple, efficient and reliable grouting quality detection methods, and the cost is high. Moreover, the height of the post-cast concrete area of ​​the traditional column connection node is generally within the range of the beam height, the post-casting area is large, and the amount of formwork and wet work is large. It is necessary to propose a more convenient and quicker construction method.

[0005] On the other hand, there is very little research in the industry on precast concrete special-shaped column structures, and no installation method has been proposed so far. Summary of the invention

[0006] In order to solve the installation method problem of prefabricated concrete special-shaped column structure, solve the problems of large number of steel bar connections, difficult connection quality control, high connection cost of existing prefabricated shear wall, and improve the energy dissipation and shock absorption effect of the structure, the present invention provides a construction method for layered installation of dry-connected concrete shear wall / special-shaped column structure.

[0007] The technical solution to achieve the purpose of the present invention is: a construction method for layered installation of dry-connected concrete shear wall / special-shaped column structure, comprising the following steps:

[0008] Step 1: Install the precast shear wall / special-shaped column on the first floor, and install the corbels on the side of the precast shear wall / special-shaped column on the first floor intersecting with the precast beam as temporary support for the precast beam;

[0009] Step 2: Install the precast beams of this layer, connect the bottom longitudinal reinforcement of the precast beams and the short reinforcement bars on the precast shear walls / special-shaped columns through connector 1; install the composite slabs; remove the temporary fixing nuts on the top of the precast shear walls / special-shaped columns;

[0010] Step 3: hoist the upper prefabricated shear wall / special-shaped column into place, so that the screw rod extending from the upper part of the lower prefabricated shear wall / special-shaped column passes through the circular hole of the bottom steel support of the upper prefabricated shear wall / special-shaped column; adjust the bottom steel support and fix it; connect the upper and lower prestressed tendons with connector 2;

[0011] Step 4: Install the sleeves around the prestressed reinforcement at the connection between the upper and lower prefabricated shear walls / special-shaped columns; move the movable reinforcement of the prefabricated beam to the beam shear wall / special-shaped column node area; and place the surface reinforcement of the composite slab;

[0012] Step 5: Install the formwork; pour the surface concrete of the floor slab;

[0013] Step 6: Complete the installation of the entire building structure in a cycle; tension and lock the prestressed tendons at the top of the prefabricated shear wall / special-shaped column at one time to complete the structural construction.

[0014] The present invention also provides a layered installation dry-connected concrete shear wall / special-shaped column structure, comprising a prefabricated shear wall / special-shaped column, a prefabricated beam and a composite slab.

[0015] The prefabricated shear wall / special-shaped column is prefabricated in a single layer, including shear wall / special-shaped column body concrete, ordinary steel bars and a plurality of prestressed bars;

[0016] The top of the precast shear wall / special-shaped column is flush with the lower edge of the floor slab of this layer, and the bottom is flush with the upper edge of the floor slab of the lower layer. The post-cast concrete area of ​​the precast shear wall / special-shaped column connection node is only concentrated within the slab thickness range; the post-cast concrete area of ​​the precast shear wall / special-shaped column connection node is only concentrated within the slab thickness range.

[0017] The shear wall / special-shaped column concrete is provided with a number of holes that penetrate the shear wall / special-shaped column longitudinally to accommodate prestressed tendons.

[0018] Ordinary steel bars include interconnected stirrups and ordinary longitudinal bars. The ordinary steel bars are only set in the shear wall / special-shaped column body, and are cast as a whole with the shear wall / special-shaped column body concrete, and do not pass through the shear wall / special-shaped column segment connection interface.

[0019] The prestressed tendons run longitudinally through the entire length of the component and pass through the shear wall / special-shaped column section connection interface.

[0020] Preferably, a groove or a rough surface is provided at the upper end of the prefabricated shear wall / special-shaped column, and a plurality of screws extending out of the surface are also provided; a raised shear key or a rough surface is provided at the lower end, and a steel support extending out of the surface is also provided; a notch and short steel bars are provided on the side intersecting with the prefabricated beam.

[0021] Preferably, the dry-connected concrete shear wall / special-shaped column structure is L-shaped, T-shaped, cross-shaped, Z-shaped or I-shaped.

[0022] Preferably, each end of the layered dry-connected concrete shear wall / special-shaped column structure is provided with at least one hole, and the hole is arranged to match the prestressed tendons.

[0023] Preferably, the prestressed tendon is arranged coaxially with the hole.

[0024] Preferably, temporary fixing nuts are provided at both ends of the prestressed tendons.

[0025] Preferably, the bottom longitudinal reinforcement of the precast beam extends out from the end face. After the precast beam is installed in place, the bottom longitudinal reinforcement of the beam is connected to the short steel bars by a connector. The surface longitudinal reinforcement of the precast beam consists of fixed steel bars located in the middle of the beam and movable steel bars located at both ends of the beam. After the precast beam is installed in place, the movable steel bars are moved horizontally to the beam shear wall / special-shaped column node area.

[0026] Preferably, connector 2 is arranged on the prestressed tendon, and the sleeve is used to wrap the connector 2 and the prestressed tendons exposed in the upper and lower layer connection areas, and the inner diameter of the sleeve is larger than the outer diameter of connector 2 and the diameter of the hole.

[0027] Preferably, after several erected prefabricated shear walls / special-shaped columns are hoisted into place, both ends of the prefabricated beams are supported on the side corbels of the prefabricated shear walls / special-shaped columns, and the composite panels are placed on the prefabricated shear walls / special-shaped columns and prefabricated beams.

[0028] By adopting the above technical scheme, the present invention has the following beneficial effects: (1) The prefabricated shear wall / special-shaped column of the present application is prefabricated in sections of a single layer, and the installation of the dry-connected concrete shear wall / special-shaped column structure is carried out in layers. The structure has strong structural flexibility and can be assembled in layers according to needs, and is suitable for use in low-rise and multi-story residential buildings.

[0029] (2) The structure of the present invention is ingenious. The ordinary steel bars of the component do not pass through the connection interface, and only a small amount of prestressed bars pass through. On site, it is only necessary to hoist the prefabricated component into place, connect the prestressed bars and then tension them. The number of steel bar connections is small, and the number of connectors is greatly reduced. The post-cast concrete area of ​​the prefabricated shear wall / special-shaped column connection node is only concentrated within the slab thickness range, while the height of the post-cast concrete area of ​​the traditional connection node is generally within the beam height range, and the thickness of the beam (i.e., the height) is greater than the thickness of the cast-in-place slab. This solves the problems of the large number of existing prefabricated assembly column steel bar connections, the difficulty in controlling the connection quality, the high connection cost, and the large number of on-site wet operations.

[0030] (3) Under the action of an earthquake, the dry-connected concrete special-shaped columns swing and open along the concave and convex joints at the bottom, which can effectively reduce the impact of the earthquake and play a role in energy dissipation and shock absorption. The structural damage is small, and after the earthquake, gravity and prestressed tendons provide restoring force, so the structure can be quickly restored to use.

[0031] (4) The layered dry-connected concrete shear wall / special-shaped column structure proposed in this invention is simple in construction, easy to install, and has good seismic performance, and has obvious engineering advantages. The shear wall / special-shaped column body concrete is a finished product produced on demand in the factory and does not need to be cast in place during the construction process, which solves the technical problems of high cost and poor fire and corrosion resistance caused by the use of steel special-shaped columns in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to make the content of the present invention more clearly understood, the present invention is further described in detail below according to specific embodiments and in conjunction with the accompanying drawings, wherein

[0033] Figure 1 This is a schematic diagram of the layered installation of dry-connected concrete shear wall / special-shaped column structure of the present invention;

[0034] Figure 2 This is a schematic diagram of the structure of the prefabricated shear wall / special-shaped column of the present invention;

[0035] Figure 3 For the present invention Figure 2 The enlarged schematic diagram at A in the middle;

[0036] Figure 4 For the present invention Figure 2 A magnified schematic diagram of the structure at B in the middle;

[0037] Figure 5 It is the cross-section diagram of prefabricated special-shaped column (L-shaped);

[0038] Figure 6 is the cross section of the precast shear wall (L-shaped);

[0039] Figure 7 It is the cross-section diagram of prefabricated special-shaped column (T-shaped);

[0040] Figure 8 This is the cross-section diagram of the precast shear wall (T-shaped);

[0041] Fig. 9 It is the cross-sectional view of prefabricated special-shaped column (cross shape);

[0042] Fig.10 is the cross section of the precast shear wall (cross shape);

[0043] Fig.11 It is the cross-section diagram of prefabricated special-shaped column (Z-shaped);

[0044] Fig.12 This is the cross-section diagram of the precast shear wall (Z-shaped);

[0045] Fig.13 It is the cross-section diagram of prefabricated special-shaped column (I-shaped);

[0046] Fig.14 It is the cross section of precast shear wall (I-shaped);

[0047] Fig.15 It is a three-dimensional diagram of the precast beam (the movable steel bar 203 has not yet been moved to the beam shear wall / special-shaped column node area);

[0048] Fig.16 for Fig.15 The enlarged schematic diagram at C in the middle;

[0049] Fig.17 for Figure 1 Three-dimensional diagram of the node area at point D in the middle (the movable steel bar 203 has been moved to the beam shear wall / special-shaped column node area).

[0050] Fig.18 It is a comparison diagram of the pouring area of ​​the prior art and the pouring area of ​​the present application. DETAILED DESCRIPTION

[0051] Embodiment 1

[0052] See Figures 1 to 18 The layered dry-connected concrete shear wall / special-shaped column structure of this embodiment includes a prefabricated shear wall / special-shaped column 1, a prefabricated beam 2 and a composite slab 3.

[0053] The prefabricated shear wall / special-shaped column 1 is prefabricated in a single layer, and includes shear wall / special-shaped column body concrete 101, ordinary steel bars 102 and a plurality of prestressed bars 103;

[0054] The top of the precast shear wall / special-shaped column is flush with the lower edge of the floor slab of the current layer, and the bottom is flush with the upper edge of the floor slab of the lower layer; the post-cast concrete area of ​​the precast shear wall / special-shaped column connection node is only concentrated within the slab thickness range. In the prior art, the precast beam is provided with longitudinal reinforcement, and the precast beam is poured after insertion, so the cast-in-place area (such as the attached Fig.18The casting area is from the bottom of the beam to the top of the floor slab. This casting area is higher, and the template and wet work consumption are relatively large. In this application, the top of the prefabricated dry-connected concrete special-shaped column is flush with the lower edge of the floor slab of this layer, and the bottom is flush with the upper edge of the floor slab of the lower layer. Therefore, the casting area of ​​this application (as shown in the attached Fig.18 As shown in B), the template usage will be reduced, thus improving efficiency.

[0055] The shear wall / special-shaped column concrete 101 is provided with a plurality of holes 110 which penetrate the shear wall / special-shaped column longitudinally and are used to accommodate prestressed tendons.

[0056] The ordinary steel bars 102 include stirrups and ordinary longitudinal bars connected to each other. The ordinary steel bars 102 are only provided in the shear wall / special-shaped column body, and are cast as one with the shear wall / special-shaped column body concrete 101, and do not pass through the shear wall / special-shaped column segment connection interface.

[0057] The prestressed tendons run through the entire length of the component longitudinally and pass through the shear wall / special-shaped column segment connection interface. The present invention proposes a layered installation dry-connected concrete shear wall / special-shaped column structure. The ordinary steel bars of the component do not pass through the connection interface, and only a small amount of prestressed tendons pass through. On site, it is only necessary to hoist the prefabricated component in place, connect the prestressed tendons and then tension them. The number of steel bar connections is small, and the number of connectors is greatly reduced. The problem of the large number of steel bar connections and high connection cost of the existing prefabricated assembly columns is solved. The layered installation dry-connected concrete shear wall / special-shaped column structure has strong flexibility and a rich cross-sectional form. It can not protrude from the wall surface, and solves the problem that the rectangular column is exposed on the wall surface and affects the appearance. Under the action of an earthquake, the dry-connected concrete special-shaped column swings and opens along the bottom joint, which can effectively reduce the impact of the earthquake, play the role of energy dissipation and shock reduction, and has little structural damage. After the earthquake, gravity and prestressed tendons provide restoring force, and it can be quickly restored to use. The layered installation dry-connected concrete shear wall / special-shaped column structure proposed by this invention is simple in structure, easy to install, and has good seismic performance, and has obvious engineering advantages.

[0058] The upper end of the prefabricated shear wall / special-shaped column 1 is provided with a groove 104 or a rough surface, and is also provided with a plurality of screws 106 extending out of the surface;

[0059] A raised shear key 108 or a rough surface is provided at the lower end, and a steel support 109 extending out of the surface is also provided;

[0060] A notch 111 and short steel bars 105 are provided on the side surface intersecting with the precast beam 2 .

[0061] The dry-connected concrete shear wall / special-shaped column structure is L-shaped, T-shaped, cross-shaped, Z-shaped or I-shaped.

[0062] Each end of the layered dry-connected concrete shear wall / special-shaped column structure is provided with at least one hole, and the hole is matched with the prestressed tendons.

[0063] The prestressed tendon 103 and the hole 110 are arranged coaxially.

[0064] Temporary fixing nuts 107 are provided at both ends of the prestressed tendons 103 .

[0065] The bottom longitudinal reinforcement 201 of the precast beam 2 extends out from the end face. After the precast beam 2 is installed in place, the bottom longitudinal reinforcement 201 and the short steel bar 105 are connected by connector 1 204. The surface longitudinal reinforcement of the precast beam 2 is composed of a fixed steel bar 202 located in the middle of the beam and a movable steel bar 203 located at both ends of the beam. After the precast beam 2 is installed in place, the movable steel bar 203 is moved horizontally to the beam shear wall / special-shaped column node area.

[0066] The second connector 112 is arranged on the prestressed tendon, and the sleeve is used to wrap the second connector 112 and the exposed prestressed tendon 103 in the upper and lower layer connection areas. The inner diameter of the sleeve is larger than the outer diameter of the second connector 112 and the diameter of the hole 110.

[0067] After several erected prefabricated shear walls / special-shaped columns 1 are hoisted into place, both ends of the prefabricated beam 2 are supported on the side brackets 113 of the prefabricated shear walls / special-shaped columns 1, and the composite plate 3 is placed on the prefabricated shear walls / special-shaped columns 1 and the prefabricated beam 2.

[0068] During the implementation process, the construction method of layered installation of dry-connected concrete shear wall / special-shaped column structure includes the following steps:

[0069] Step 1: prefabricate shear walls / special-shaped columns 1, prefabricated beams 2, and composite slabs 3 in a single-layer section and transport them to the area to be constructed;

[0070] Install the prefabricated shear wall / special-shaped column 1 on the first floor, and install the corbel 113 on the side of the prefabricated shear wall / special-shaped column 1 on the first floor intersecting with the prefabricated beam 2 as a temporary support for the prefabricated beam 2;

[0071] Step 2: Install the precast beam 2 of this layer, connect the bottom longitudinal reinforcement 201 of the precast beam and the short reinforcement 105 arranged on the precast shear wall / special-shaped column through the connector 1 204; install the composite plate 3; remove the temporary fixing nut 107 on the top of the precast shear wall / special-shaped column 1;

[0072] Step 3: hoist the upper prefabricated shear wall / special-shaped column 1 in place, so that the screw 106 extending from the upper part of the lower prefabricated shear wall / special-shaped column 1 passes through the circular hole of the bottom steel support 109 of the upper prefabricated shear wall / special-shaped column 1; adjust and fix the bottom steel support 109; connect the upper and lower prestressed tendons 103 with the connector 2 112;

[0073] Step 4: Install the outer casing of the prestressed tendons 103 at the connection between the upper and lower prefabricated shear walls / special-shaped columns 1; move the movable steel bars 203 of the prefabricated beam 2 to the beam shear wall / special-shaped column node area; and place the surface steel bars of the composite slab 3;

[0074] Step 5: Install the formwork; pour the surface concrete of the floor slab;

[0075] Step 6, the whole building structure installation is completed in a cycle; the prestressed tendons 103 are tensioned and locked at the top of the prefabricated shear wall / special-shaped column 1 at one time, and the structural construction is completed.

[0076] The present application solves the installation method problem of prefabricated special-shaped column structures, and at the same time solves the problems of large number of steel bar connections in existing prefabricated shear walls, difficult connection quality control, and high connection costs, thereby playing a role in improving the energy dissipation and shock absorption of the structure.

[0077] The specific embodiments described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A construction method for layered installation of dry-connected concrete shear wall / special-shaped column structure, characterized in that: The steps include: Step 1: Install the prefabricated shear wall / special-shaped column (1) on the first floor, and install a corbel (113) on the side of the prefabricated shear wall / special-shaped column (1) on the first floor intersecting with the prefabricated beam (2) as a temporary support for the prefabricated beam (2); Step 2: Install the precast beam (2) of this layer, connect the bottom longitudinal reinforcement (201) of the precast beam and the short reinforcement (105) arranged on the precast shear wall / special-shaped column through connector 1 (204); install the precast bottom plate of the composite plate (3); remove the temporary fixing nut (107) on the top of the precast shear wall / special-shaped column (1); Step 3: hoist the upper prefabricated shear wall / special-shaped column (1) in place, so that the screw rod (106) extending from the upper part of the lower prefabricated shear wall / special-shaped column (1) passes through the circular hole of the bottom steel support (109) of the upper prefabricated shear wall / special-shaped column (1); adjust the bottom steel support (109) and fix it; connect the upper and lower prestressed tendons (103) with the second connector (112); Step 4: Install the outer casing of the prestressed tendons (103) at the connection between the upper and lower prefabricated shear walls / special-shaped columns (1); move the movable steel bars (203) of the prefabricated beam (2) to the beam shear wall / special-shaped column node area; and place the surface steel bars of the composite slab (3); Step 5: Install the formwork; pour the surface concrete of the floor slab; Step 6, the whole building structure installation is completed in a cycle; the prestressed tendons (103) are tensioned and locked at the top of the prefabricated shear wall / special-shaped column (1) at one time, and the structural construction is completed.

2. A layered dry-connected concrete shear wall / special-shaped column structure, characterized in that: It comprises a prefabricated shear wall / special-shaped column (1), a prefabricated beam (2) and a composite slab (3). The prefabricated shear wall / special-shaped column (1) is prefabricated in a single layer, and comprises shear wall / special-shaped column body concrete (101), ordinary steel bars (102) and a plurality of prestressed bars (103); The top of the precast shear wall / special-shaped column is flush with the lower edge of the floor slab of the current layer, and the bottom is flush with the upper edge of the floor slab of the lower layer. The post-cast concrete area of ​​the precast shear wall / special-shaped column connection node is only concentrated within the slab thickness range; The shear wall / special-shaped column concrete (101) is provided with a plurality of holes (110) which penetrate the shear wall / special-shaped column longitudinally and are used to accommodate prestressed tendons. The common steel bars (102) include stirrups and common longitudinal bars connected to each other. The common steel bars (102) are only arranged in the shear wall / special-shaped column body, and are cast as one with the shear wall / special-shaped column body concrete (101), and do not pass through the shear wall / special-shaped column segment connection interface. The prestressed tendons run longitudinally through the entire length of the component and pass through the shear wall / special-shaped column section connection interface.

3. The layered installation dry-connected concrete shear wall / special-shaped column structure according to claim 2 is characterized by: The upper end of the prefabricated shear wall / special-shaped column (1) is provided with a groove (104) or a rough surface, and is also provided with a plurality of screws (106) extending out of the surface; A raised shear key (108) or a rough surface is provided at the lower end, and a steel support (109) extending out of the surface is also provided; A notch (111) and short steel bars (105) are arranged on the side surface intersecting with the prefabricated beam (2).

4. The layered installation dry-connected concrete shear wall / special-shaped column structure according to claim 2 is characterized by: The dry-connected concrete shear wall / special-shaped column structure is L-shaped, T-shaped, cross-shaped, Z-shaped or I-shaped.

5. The layered installation dry-connected concrete shear wall / special-shaped column structure according to claim 2 is characterized by: Each end of the layered dry-connected concrete shear wall / special-shaped column structure is provided with at least one hole, and the hole is matched with the prestressed tendons.

6. The layered installation dry-connected concrete shear wall / special-shaped column structure according to claim 2 is characterized in that: The prestressed tendon (103) and the hole (110) are arranged coaxially.

7. The layered installation dry-connected concrete shear wall / special-shaped column structure according to claim 2 is characterized by: Temporary fixing nuts (107) are provided at both ends of the prestressed tendon (103).

8. The layered installation dry-connected concrete shear wall / special-shaped column structure according to claim 2 is characterized by: The bottom longitudinal reinforcement (201) of the precast beam (2) extends out from the end face. After the precast beam (2) is installed in place, the bottom longitudinal reinforcement (201) and the short reinforcement (105) are connected by connector 1 (204). The surface longitudinal reinforcement of the precast beam (2) is composed of fixed reinforcement (202) located in the middle of the beam and movable reinforcement (203) located at both ends of the beam. After the precast beam (2) is installed in place, the movable reinforcement (203) is horizontally moved to the beam shear wall / special-shaped column node area.

9. The layered installation dry-connected concrete shear wall / special-shaped column structure according to claim 8, characterized in that: The second connector (112) is arranged on the prestressed tendon, and the sleeve is used to wrap the second connector (112) and the prestressed tendon (103) exposed in the upper and lower layer connection areas, and the inner diameter of the sleeve is larger than the outer diameter of the second connector (112) and the diameter of the hole (110).

10. The layered installation dry-connected concrete shear wall / special-shaped column structure according to claim 8, characterized in that: After a number of erected prefabricated shear walls / special-shaped columns (1) are hoisted in place, both ends of the prefabricated beam (2) are supported on the side brackets (113) of the prefabricated shear walls / special-shaped columns (1), and the composite slab (3) is placed on the prefabricated shear walls / special-shaped columns (1) and the prefabricated beam (2).