Reinforcing construction technology for pasting steel plate on concrete beam plate
By directly fixing steel plates and concrete with anchors and nail tools, the construction steps are simplified, solving the problem of low construction efficiency in traditional methods, achieving faster construction cycles and higher bonding quality, reducing costs and extending The structure life span.
Patent Information
- Application Number
- CN202411413102.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-11
- Publication Date
- 2024-12-03
AI Technical Summary
In traditional concrete structure reinforcement methods, the construction efficiency is low, resulting in a long construction cycle, which is mainly due to the need to drill, clean holes and wait for chemical agents to solidify, which affects the construction efficiency and cost.
The anchors are used to replace traditional chemical planting bolts, and the steel plate and concrete are directly fixed through nailing tools, which simplifies the construction steps, reduces the use of chemical agents and drills, shortens the curing time, and is carried out through continuous pressure and appropriate structural glue treatment. Improved bonding quality.
It significantly shortens the construction cycle of steel plate adhesion, improves construction efficiency and bonding quality, reduces costs, and extends the service life of concrete structures.
Smart Images

Figure CN119062145A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building structure reinforcement, and in particular to a construction process for reinforcing concrete beams and slabs by gluing steel plates. Background Art
[0002] Concrete structure is the most widely used structure in various industrial and civil buildings, structures, bridges, culverts and tunnels. Due to various reasons, such as aging, damage, and low original design standards of concrete structures, the strength and stiffness of concrete structures cannot meet the normal use requirements. Strengthening existing concrete structures, improving their bearing capacity, and extending their service life have become widely concerned engineering and technical issues.
[0003] At present, the most commonly used fixing method is to stick steel plates on concrete. The traditional steel plate fixing adopts planting chemical bolts. The steps required include: drilling holes, cleaning holes, inserting chemical agent tubes into the holes, drilling bolts, waiting for the curing agent to cure, and then installing washers and nuts for fixing. Although the structure is stable after fixing, the process requires managers to drill and clean holes and wait for the chemical agent to fix, which makes the construction efficiency low and leads to a long construction period. Summary of the invention
[0004] In order to shorten the construction period of bonding concrete and steel plates, the present application provides a concrete beam and slab bonding steel plate reinforcement construction process.
[0005] This application provides a concrete beam-slab reinforcement construction process with steel plates, which adopts the following technical solutions: A concrete beam-slab reinforcement construction process by gluing a steel plate comprises the following steps: S1. Surface cleaning: remove the surface decorative layer of the concrete; S2. Steel plate preparation: cutting and surface grinding of steel plates; S3, gluing and pasting: applying glue to the concrete and the steel plate, and pasting the steel plate to the predetermined position of the concrete; S4. Steel plate fixing: Use anchors to fix the steel plate, so that the anchors directly pass through the steel plate and insert into the concrete; S5. Reinforcement and maintenance: Apply mortar to form a protective layer.
[0006] By adopting the above technical solution, anchors are used to fix the steel plate and concrete, replacing the step of planting chemical bolts in the traditional pasting process, reducing the use of chemical pipes, chemicals, drilling tools, screws and nuts and other parts, saving time waiting for the curing agent to completely cure, thereby shortening the construction period of pasting steel plates.
[0007] Optionally, in step S1, after the decorative layer is removed, the powder particles on the concrete surface are blown away with compressed air, and the holes on the concrete surface are repaired with structural adhesive or mortar.
[0008] By adopting the above technical solution, it can be ensured that there is no loose material on the concrete surface, thereby improving the construction quality.
[0009] Optionally, after scraping off the decorative layer and before using compressed air to blow off the powder particles, use a hard-bristle brush and detergent to brush the component joint surfaces with oil stains on the concrete.
[0010] By adopting the above technical solution, the detergent can decompose the oil stains, thereby reducing the corrosion of the oil stains to the concrete and extending the service life of the concrete.
[0011] Optionally, in step S3, the steel plates are continuously pressed during bonding until the adhesive is squeezed out from between the concrete and the steel plates.
[0012] By adopting the above technical solution, continuous pressure can ensure that the entire steel plate is in full contact with the concrete surface, thereby improving the bonding quality.
[0013] Optionally, the thickness of the structural adhesive applied to the concrete and the steel plate during the gluing process ranges from 1 to 3 mm, and the structural adhesive applied to the predetermined bonding area is thick in the middle and thin at the edges.
[0014] By adopting the above technical solution, an exhaust space can be reserved between the discharged concrete and the steel plate.
[0015] Optionally, when the temperature of the structural adhesive is lower than 10°, the structural adhesive is heated, and when the temperature of the structural adhesive is higher than 30°, the structural adhesive is cooled by blowing compressed air.
[0016] By adopting the above technical solution, the temperature range of the structural adhesive is maintained between 10°-30°, so that the structural adhesive remains active.
[0017] Optionally, the anchor is a nail, and in step S4, the anchor is driven into the steel plate using a nail-driving tool so that the anchor penetrates the steel plate and is driven into the concrete.
[0018] By adopting the above technical solution, the use of nail-shooting tools for construction can improve the convenience of operation, reduce the difficulty of construction, and thus improve the efficiency of steel plate fixing.
[0019] Optionally, the nails are pre-installed in a nail-driving tool for standby use before construction, and before implementing step S4, the surface of the steel plate is marked according to the bolt spacing requirements.
[0020] By adopting the above technical solution, the spare parts loaded into the nail-shooting tool can be increased to reduce construction errors.
[0021] Optionally, in step S2, an angle grinder is used to remove rust from the surface of the steel plate until the surface of the steel plate is polished to have a metallic luster.
[0022] By adopting the above technical solution, the bonding strength between the steel plate and the structural adhesive can be improved after rust removal and grinding, while reducing the possibility of corrosion between the steel plate and the concrete.
[0023] Optionally, in step S5, cement mortar is applied twice to the fixed steel plate and concrete to form a protective bottom layer and a protective surface layer respectively.
[0024] By adopting the above technical solution, additional protection can be provided for the steel plate and concrete, mechanical damage and corrosion can be reduced, and the service life of the steel plate and concrete structure can be extended.
[0025] In summary, the present application includes at least one of the following beneficial technical effects: 1. Use anchors to fix steel plates and concrete, replacing the method of planting chemical bolts in the traditional pasting process, reducing the use of chemical pipes, chemicals, drilling tools, screws and nuts and other parts, saving time waiting for the curing agent to fully cure, thereby shortening the construction period of pasting steel plates; 2. Continuous pressure can ensure that the entire steel plate is in full contact with the concrete surface, improving the bonding quality; 3. Using nail-shooting tools for construction can improve the convenience of operation, reduce the difficulty of construction, and thus improve the efficiency of steel plate fixing. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the construction process in the embodiment of the present application.
[0027] Figure 2 It is a construction schematic diagram of nailing using a nail gun in an embodiment of the present application.
[0028] Figure 3 It is a schematic diagram of the surface state of the steel plate after nailing in the embodiment of the present application. DETAILED DESCRIPTION
[0029] The following is combined with Figure 1 This application is described in further detail.
[0030] The embodiment of the present application discloses a construction process for reinforcing concrete beams and slabs by gluing steel plates.
[0031] Reference Figure 1 , a concrete beam-slab reinforcement construction process with steel plates, comprising the following steps: S1. Surface cleaning: first remove the surface decorative layer of the concrete, and then remove the surface layer of the beam and slab until the dense concrete structure surface is exposed; S2. Steel plate preparation: Cut the steel plate and grind the surface. Use cutting tools to cut the steel plate according to the drawing requirements, and then use grinding tools to grind the surface of the steel plate; S3, gluing and pasting: mix the structural adhesive according to the proportion, apply the structural adhesive to the structural surface after the concrete is cleaned and the surface of the steel plate to be pasted, and then paste the steel plate to the predetermined position of the concrete to make the structural adhesive bond with each other; S4. Steel plate fixing: Use anchors to fix the steel plate, so that one end of the anchor directly passes through the steel plate and is inserted into the concrete; S5. Reinforcement and maintenance: Apply mortar to form a protective surface layer.
[0032] By using anchors to fix the steel plates, the process of drilling holes in the steel plates is eliminated. Firstly, the use of drilling equipment is saved. Secondly, since anchors are used to fix the steel plates and concrete, the step of planting chemical bolts in the traditional pasting process is replaced, and the use of chemical pipes, chemicals, drills, screws and nuts and other parts is reduced, thus saving costs. Since the most important connection method is fixed by physical means, compared with traditional methods, the time required for drilling, cleaning holes, injecting chemicals, and waiting for the curing agent to completely cure is saved, thereby greatly reducing the period of fixing the steel plates and concrete, thereby shortening the construction period of pasting steel plates and reducing costs.
[0033] In step S1, after the decorative layer is removed, the powder on the concrete surface is blown away with compressed air, and the holes on the concrete surface are repaired with structural adhesive or mortar. The dust and powder on the concrete surface are blown away with compressed air to ensure that there is no loose material on the concrete surface. The concrete surface is then polished to remove the weak layer on the concrete surface and increase the surface roughness of the concrete to improve the bonding effect of the structural adhesive in the subsequent process. After polishing, the concrete surface is cleaned again with compressed air to ensure that no new dust and debris are generated. When there are smaller holes in the cleaned concrete, the holes are repaired with structural adhesive. When there are larger holes, the holes are repaired with polymer repair mortar to reduce the presence of internal voids when bonding steel plates.
[0034] In step S1, after removing the decorative layer and before using compressed air to blow away the powder particles, check whether there is oil or other pollutants on the concrete surface. Use a hard brush and detergent to brush the component joint surface with oil on the concrete. After brushing, let the detergent stay on the concrete surface for a period of time so that the chemical action of the detergent can decompose the oil, thereby reducing the impact of the oil on the bonding effect of the structural adhesive, reducing the corrosion of the concrete by the oil, and extending the service life of the concrete. While waiting for the decomposition, step S2 can be directly performed to unload and grind the steel plate. After the decomposition is completed, rinse the area with detergent with clean water, and then use compressed air to blow away the moisture and loose oil, and at the same time blow away the powder particles on the concrete surface to remove the loose powder particles on the concrete surface.
[0035] In step S3, the structural adhesive is prepared in proportion, and the structural adhesive is applied to the concrete and the steel plate with a spatula. When the steel plates are attached, pressure is continuously applied to the steel plates until the structural adhesive is squeezed out of the gap between the concrete and the steel plates. When applying pressure, uniform pressure is gradually applied outward from the center of the steel plate. Pressure is applied using tools such as a roller or a rubber hammer to ensure that the entire steel plate is in full contact with the concrete surface. Air is discharged through the structural adhesive to ensure that the structural adhesive is evenly distributed between the concrete and the steel plate, which helps to discharge air bubbles in the bonding layer and avoid bubbles during the curing process as much as possible. After the adhesive is squeezed out of the gap, check whether there are air bubbles or gaps between the concrete and the steel plate, and clean up the excess structural adhesive that is squeezed out.
[0036] The thickness of the structural adhesive applied to the concrete and the steel plate during the application of the adhesive is in the range of 1-3mm, and the structural adhesive applied to the predetermined bonding area is thick in the middle and thin at the edge. In this embodiment, the thickness of the structural adhesive in the central area of the pre-bonding area between the concrete and the steel plate is 3mm, and the thickness of the structural adhesive in the edge area is 1mm. The central area and the edge area have a smooth transition to avoid as much as possible the presence of voids in the central area when the steel plate and the concrete are bonded together. At the same time, it is convenient to gradually and evenly apply pressure from the center of the steel plate to the outside during bonding, providing appropriate space for exhausting air.
[0037] Use a thermometer to measure the temperature of the structural adhesive before applying the glue. When the temperature of the structural adhesive is lower than 10°, use an infrared heater to evenly heat the structural adhesive. During the heating process, use a thermometer to regularly measure the temperature of the structural adhesive to avoid overheating. When the temperature of the structural adhesive is higher than 30°, use compressed air to cool it down. During the cooling process, continue to monitor the temperature of the structural adhesive until it drops to a suitable construction temperature to ensure that the temperature range of the structural adhesive is between 10°-30°. Keeping the structural adhesive within this temperature range can increase the activity of the chemical reaction in the structural adhesive, improve its fluidity and bonding properties, and make it easy to apply and operate, thereby improving construction efficiency.
[0038] Reference Figure 1 and Figure 2The anchor is a nail. In step S4, a nail-shooting tool is used to drive the anchor onto the steel plate so that the anchor penetrates the steel plate and is driven into the concrete. In this embodiment, the nail-shooting tool is a direct-drive nail gun, which can directly apply the expanding gas generated by the explosion of gunpowder to the nail, thereby shooting the nail out.
[0039] The operation of nailing with a nailing tool is simple. You only need to align the position and pull the trigger of the nail gun to complete the shooting and fixing of the nails. Using nails instead of chemical bolts can directly save the time required to fix the steel plate and concrete. In terms of flexibility, nails are more flexible when fast fixing or disassembly is required, while chemical bolts are difficult to remove once solidified. Therefore, in terms of fault tolerance, the fault tolerance rate of nail fixing in this embodiment is lower than that of traditional chemical bolt fixing. Also, since no drilling is required, material damage and waste caused by improper drilling are reduced.
[0040] In this embodiment, the anchor is specifically an X-DS steel nail, which has the characteristics of fast construction, no need for welding, and flexible installation. After the anchor is fired, the nail cap can be flat on the surface of the steel plate without secondary hammering or cutting. When nailing, the anchor quickly passes through the steel plate and enters the concrete under the power provided by the nailing tool. The concrete around the nail body is squeezed away, and at the same time, the fast-moving anchor rubs against the concrete, producing a sintering effect, so that the anchor and the concrete are integrated.
[0041] Reference Figure 2 and Figure 3 Before implementing step S4, mark the surface of the steel plate according to the bolt spacing requirements, determine the driving position of the nails, knock the marked position to form a slight depression at the marked position, and install the nails in the nailing tool in advance before implementing step S3.
[0042] The surface marking of the steel plate replaces the traditional drilling process of planting chemical bolts, shortening the construction period. Knocking the steel plate can destroy the surface flatness of the steel plate marking before nailing, making it easier to drive the anchor when nailing, reducing construction errors. The nails are loaded for standby before applying glue in step S3 to ensure the compatibility of the nails with the nail gun, avoiding the situation where the structural glue solidifies prematurely due to the loading of nails after the glue is applied, or avoiding the situation where the steel plates are not fixed evenly and deviate after being attached due to the loading of nails after the steel plates are attached, thereby reducing construction errors.
[0043] The length of the nails used ranges from 14 to 18 mm, and suitable nails are selected according to the thickness of the steel plate.
[0044] In step S2, an angle grinder is used to remove rust from the surface of the steel plate until the surface of the steel plate is polished to a metallic luster. After rust removal and polishing, the bonding strength between the surface of the steel plate and the structural adhesive can be improved, effectively reducing corrosion of the steel plate after pasting and extending its service life.
[0045] In step S5, cement mortar is applied twice to the fixed steel plate and concrete surface to form a coated protective bottom layer and a protective surface layer respectively. The cement mortar is applied using a spatula or spraying equipment. The first application is thick, and the spatula is used to compact and smooth the mortar during the application process to ensure that the mortar fits tightly to the concrete and the steel plate. The second application is performed after the protective bottom layer begins to harden. The second application is shallow, and the mortar is evenly applied to ensure a smooth surface.
[0046] Compared with anchoring by chemical anchors and expansion anchors, the embodiments of the present application not only simplify the construction steps and save the construction period, but also can adapt to a variety of environmental conditions. Construction can be carried out in an environment without power supply, reducing delays in construction due to weather, humidity, temperature, etc., and further reducing costs.
[0047] Compared with the process of gluing with adhesives, the embodiment of the present application can bear loads immediately after nailing, while adhesive gluing requires a certain curing time to reach maximum strength. Under vibration or dynamic load environments, the structure of the solution fixed by nailing in this embodiment is more stable, while adhesive gluing is easily affected by vibration and causes bonding fatigue, affecting the connection stability of the steel plate.
[0048] Compared with the process of anchoring with U-shaped flat steel hoops, the construction process complexity and construction cost of the embodiment of the present application are relatively lower, and blank bullets are usually used for nailing, which has higher safety than welding or other mechanical connection methods used when connecting with U-shaped flat steel hoops. Furthermore, installation with U-shaped flat steel hoops usually requires the use of a certain number of construction equipment, while nailing only requires the use of a nail gun to quickly fix the steel plate without the need for unnecessary mechanical intervention, and has high applicability.
[0049] Compared with the process of using anchor bolts and adhesives in combination, the embodiment of the present application simultaneously achieves the effect of lowering the environmental humidity requirements for construction and reducing the use of harmful chemicals, has good safety, and usually has good durability after being fixed with nails, and is not easily affected by ultraviolet rays and environmental corrosion, while anchor bolts and adhesives are prone to aging over time or being affected by environmental factors. The noise generated during the nailing process is also relatively small, which can reduce the impact on the surrounding environment.
[0050] The implementation principle of a construction process for reinforcing concrete beams and slabs by gluing steel plates in an embodiment of the present application is as follows: the traditional method of fixing with chemical bolts is replaced by nailing, thereby saving material costs, eliminating processes such as drilling, cleaning holes, injecting chemicals, and waiting for anchor bolts to solidify, reducing steps such as hole position layout on concrete and hole position layout on steel plates, greatly simplifying the construction process steps, greatly shortening the construction period of gluing steel plates and reducing construction costs, and being easy to fix, requiring only the nail gun to be aimed at the construction position for nailing to complete the fixation, thereby avoiding the tedious work of installing holes in traditional processes; since physical fixation is adopted, disassembly and assembly are more convenient, and while shortening the construction period, the flexibility and fault tolerance of construction can also be improved.
[0051] The above are all preferred embodiments of the present application. The embodiments are only explanations of the present application and do not limit the protection scope of the present application in turn. Therefore, all equivalent changes made according to the structure, shape, and principle of the present application should be covered within the protection scope of the present application.
Claims
1. A concrete beam and slab reinforcement construction process with steel plates, characterized in that: The following steps are involved: S1. Surface cleaning: remove the surface decorative layer of the concrete; S2. Steel plate preparation: cutting and surface grinding of steel plates; S3, gluing and pasting: applying glue to the concrete and the steel plate, and pasting the steel plate to the predetermined position of the concrete; S4. Steel plate fixing: Use anchors to fix the steel plate, so that the anchors directly pass through the steel plate and insert into the concrete; S5. Reinforcement and maintenance: Apply mortar to form a protective layer.
2. A concrete beam and slab reinforcement construction process by gluing steel plates according to claim 1, characterized in that: In step S1, after the decorative layer is removed, the powder particles on the concrete surface are blown away with compressed air, and the holes on the concrete surface are repaired with structural adhesive or mortar.
3. A concrete beam-slab reinforcement construction process by gluing steel plates according to claim 2, characterized in that: After scraping off the decorative layer and before using compressed air to blow off the powder particles, use a hard-bristle brush and detergent to brush the oily joint surfaces of the concrete components.
4. The process for reinforcing a concrete beam and slab by bonding a steel plate according to claim 1 is characterized in that: In step S3, the steel plates are continuously pressed during bonding until the adhesive is squeezed out from between the concrete and the steel plates.
5. A concrete beam-slab reinforcement construction process by gluing steel plates according to claim 4, characterized in that: The thickness of the structural adhesive applied to the concrete and the steel plate during the application of glue is in the range of 1-3 mm, and the structural adhesive applied to the predetermined bonding area is thick in the middle and thin at the edges.
6. The process for reinforcing a concrete beam and slab by bonding a steel plate according to claim 4 is characterized in that: When the temperature of the structural adhesive is lower than 10°, the structural adhesive is heated, and when the temperature of the structural adhesive is higher than 30°, it is cooled by blowing compressed air.
7. The process for reinforcing a concrete beam and slab by bonding a steel plate according to claim 1 is characterized in that: The anchor is a nail. In step S4, the anchor is driven onto the steel plate using a nail tool so that the anchor penetrates the steel plate and is driven into the concrete.
8. The process for reinforcing a concrete beam and slab by gluing a steel plate according to claim 7 is characterized in that: Before construction, the nails are pre-installed in the nail-driving tool for standby use. Before implementing step S4, the surface of the steel plate is marked according to the bolt spacing requirements.
9. The process for reinforcing concrete beams and slabs by gluing steel plates according to claim 1 is characterized in that: In step S2, an angle grinder is used to remove rust from the surface of the steel plate until the surface of the steel plate is polished to have a metallic luster.
10. The process for reinforcing concrete beams and slabs by bonding steel plates according to claim 1, characterized in that: In step S5, cement mortar is applied twice to the fixed steel plate and concrete to form a protective bottom layer and a protective surface layer respectively.