Air pre-heater sealing structure and boiler system
By adopting floating and gravity sealing devices in the air preloader, the elastic compensation and gravity of the return spring and self-lubricating metal are used to form a gapless seal, which solves the problems of severe wear and short life of mechanical seals, and achieves low air leakage rate and Long-term stable operation.
Patent Information
- Application Number
- CN202410944680.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-12-03
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The mechanical seals in the existing air pre-device sealing devices are severely worn, have short life, and are difficult to adjust the sealing gap, which can easily cause large air leakage during operation.
The floating sealing device and gravity sealing device are adopted. The floating sealing device achieves elastic compensation through return springs and self-lubricating metals. The gravity sealing device relies on its own gravity to form a gapless seal, combining the fan plate and the counterweight block for stable sealing.
Effectively reduce air leakage rate, extend the service life of the sealing device, ensure long-term safe and stable operation of the air preloader, reduce air leakage rate fluctuations, avoid blowing and accumulation of dust from the sealing device, and improve the reliability of the sealing structure.
Smart Images

Figure CN119062760A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of air preheater sealing, and in particular to an air preheater sealing structure and a boiler system. Background Art
[0002] The air preheater is a heat exchanger that uses the waste heat of the exhaust gas of the boiler system to preheat the air entering the boiler system to the required temperature. In order to ensure the sealing of the air preheater, it is necessary to use packing seals on the rotor main shaft of the air preheater near the support bearing. However, during the operation of the air preheater, the packing will wear to varying degrees over time. The air leakage rate is one of the important parameters of the air preheater. The air leakage rate directly affects the economic benefits of the unit and will directly affect the service life of the equipment. The air leakage rate directly affects the operating conditions of the unit and will cause the temperature of the smoke side, the exhaust gas temperature, the hot air temperature, and the heat exchange efficiency to decrease, thereby reducing the temperature of the cold end of the heating surface, accelerating the low-temperature corrosion of the cold end heating surface, and reducing the service life of the equipment.
[0003] At present, the main sealing methods of air preheaters include hard contact mechanical seals, brush seals, hinge spring flexible seals, etc. Among these sealing devices, mechanical seals are severely worn, have a short life and need to be replaced frequently. The sealing gap is difficult to adjust, which easily causes large air leakage during operation. Therefore, in view of the above situation, it is urgent to develop an air preheater sealing structure and boiler system to overcome the shortcomings in current practical applications. Summary of the invention
[0004] The present invention provides an air preheater sealing structure and a boiler system to solve the problems raised by the above background technology: the mechanical seals in the existing sealing devices are severely worn, have a short life and need to be replaced frequently, and the sealing gap is difficult to adjust, which easily causes large air leakage during operation.
[0005] To solve the above technical problems, the present invention discloses an air preheater sealing structure, which includes: a floating sealing device and a gravity sealing device, and the floating sealing device is radially installed at the hot end of the air preheater, and the gravity sealing device is radially installed at the cold end of the air preheater.
[0006] Preferably, the floating sealing device includes: a partition plate 1, a hard sealing plate 1 is provided at the left end of the partition plate 1, a fixed plate 1 is provided at the right end of the partition plate 1, the top end of the fixed plate 1 is in contact with a rotating shaft 1, the rotating shaft 1 is in contact with a moving plate 1, the other end of the moving plate 1 is fixedly installed with a self-lubricating metal 1, the right end of the fixed plate 1 is fixedly installed with a support, the top end of the support is connected to a support rod 1 through a reset spring, the other end of the support rod 1 is movably connected to a support rod 2, and the top end of the support rod 2 is fixedly connected to the moving plate 1.
[0007] Preferably, the gravity sealing device includes: a partition plate 2, a hard sealing plate 2 is arranged at the left end of the partition plate 2, a fixed plate 2 is arranged at the right end of the partition plate 2, the bottom end of the fixed plate 2 is in contact with the movable plate 2, a rotating shaft 2 is arranged inside the movable plate 2, and the other end of the movable plate 2 is fixedly mounted on one end of the self-lubricating metal 2, and the other end of the self-lubricating metal 2 is fixedly connected to the counterweight block.
[0008] A boiler system comprises: a base, on the top of which an air preheater, a boiler device and an exhaust gas treatment device are fixedly installed in sequence from left to right, and the air preheater and the boiler device are connected by a connecting pipe 1, and the boiler device and the exhaust gas treatment device are connected by a connecting pipe 2.
[0009] Preferably, a heat recovery mechanism is provided in the exhaust gas treatment device, and the heat recovery mechanism includes: a treatment box, the bottom end of the treatment box is fixedly connected to the base, and the bottom end of the treatment box is provided with a liquid storage chamber, the right end of the liquid storage chamber is connected with the water inlet pipe and the water outlet pipe from top to bottom respectively, and the water inlet pipe and the water outlet pipe are respectively fixedly installed with an electromagnetic valve 1 and an electromagnetic valve 2, and the connecting pipe 2 passes through the treatment box and is fixedly connected with the connecting elbow, and the other end of the connecting elbow is connected to the exhaust gas treatment mechanism through a plurality of through holes, and a plurality of reverse flow valves 1 are fixedly installed in the through holes.
[0010] Preferably, the exhaust gas treatment mechanism includes: a cavity 1, which is arranged at the top left side of the treatment box, and the top end of the cavity 1 is connected to the exhaust pipe, and a connecting rod 1 is arranged in the cavity 1, a plurality of push plates are fixedly installed on the left end of the connecting rod 1, and the right end of the connecting rod 1 passes through the cavity 2 arranged at the top right side of the treatment box and is connected to the driving component, and a plurality of nozzles are fixedly installed on the top end of the cavity 1, the nozzle is connected to one end of the connecting pipe 3, the other end of the connecting pipe 3 is connected to the pressurizing chamber, and a reverse flow valve 2 is fixedly installed in the connecting pipe 3, and the bottom end of the pressurizing chamber is connected to one end of the connecting pipe 4, the other end of the connecting pipe 4 is connected to the cavity 1, and a reverse flow valve 3 is fixedly installed in the connecting pipe 4, the piston is slidably connected to the inner wall of the pressurizing chamber up and down, and the top end of the piston is connected to the driving component.
[0011] Preferably, the air preheater is composed of a rotor, a heat storage element, a housing, a transmission device, a sealing device and other components, and the air preheater also includes:
[0012] A flow rate sensor, used to detect the speed of gas passing through the fluid channel of the thermal storage element;
[0013] Temperature sensor 1, used to detect the temperature at the hot end of the fluid channel of the heat storage element in the air preheater when the gas passes through the air preheater;
[0014] Temperature sensor 2, used to detect the cold end temperature of the fluid channel of the heat storage element in the air preheater when the gas passes through the air preheater;
[0015] An alarm and a controller are provided, wherein the alarm and the controller are electrically connected to the flow rate sensor, the first temperature sensor, the second temperature sensor and the alarm.
[0016] Preferably, the controller controls the alarm to work based on the flow rate sensor, the first temperature sensor, and the second temperature sensor, comprising the following steps:
[0017] Step 1: According to formula (1), calculate the flow resistance F in the fluid channel of the thermal storage element: z :
[0018]
[0019] Where λ is the flow rate change adjustment coefficient of the gas passing through the fluid channel, μ is the resistance coefficient along the gas passing through the fluid channel, h is the height of the heat storage element, R is the equivalent diameter of the heat storage element per unit length, ρ g is the mass density of gas entering the heat storage element per unit length, ρ c is the mass density of gas discharged from the unit length of the thermal storage element, m is the gas mass flow rate, S is the installation area of the thermal storage element, and α is the circulation porosity of the thermal storage element;
[0020] Step 2: According to the following formula (2) and the detection values of the flow rate sensor, temperature sensor 1, and temperature sensor 2, the actual air leakage K of the air preheater is calculated. The controller compares the actual air leakage K of the air preheater with the preset air leakage range. When the actual air leakage is higher than the preset air leakage range, the controller controls the alarm to sound an alarm:
[0021]
[0022] in is the gas correction coefficient, β is the gas thermal conductivity, V is the flow rate sensor detection value, χ is the gas kinematic viscosity, Pr is the Prandtl number, δ is the gas leakage coefficient, A is the sealing gap area, F y is the gas output power, ρ is the gas density, T0 is the ambient temperature, T1 is the detection value of temperature sensor 1, and T2 is the detection value of temperature sensor 2. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0024] Figure 1 A schematic structural diagram of a floating sealing device provided in an embodiment of the present invention;
[0025] Figure 2 A schematic diagram of the structure of a gravity sealing device provided in an embodiment of the present invention;
[0026] Figure 3 A schematic diagram of the installation of a boiler system provided in an embodiment of the present invention;
[0027] Figure 4 The embodiment of the present invention provides Figure 3 Schematic diagram of the internal structure of the exhaust gas treatment device.
[0028] Reference numerals:
[0029] 1. Partition 1; 2. Fixed plate 1; 3. Rotating shaft 1; 4. Moving plate 1; 5. Self-lubricating metal 1; 6. Support; 7. Return spring; 8. Support rod 1; 9. Support rod 2; 10. Hard sealing plate 1; 11. Partition 2; 12. Hard sealing plate 2; 13. Fixed plate 2; 14. Moving plate 2; 15. Rotating shaft 2; 16. Self-lubricating metal 2; 17. Counterweight; 18. Fan-shaped plate; 19. Base; 20. Air preheater; 21. Boiler device; 22. Connecting pipe 1; 23. Connecting pipe 2; 24. Processing box; 25. Liquid storage chamber; 26. Water inlet pipe; 27. Water outlet pipe; 28. Solenoid valve 1; 29, solenoid valve 2; 30, connecting elbow; 31, through hole; 32, backflow valve 1; 33, cavity 1; 34, piston; 35, exhaust pipe; 36, connecting rod 1; 37, push plate; 38, nozzle; 39, connecting pipe 3; 40, pressurizing chamber; 41, backflow valve 2; 42, connecting pipe 4; 43, backflow valve 3; 44, cavity 2; 45, driving motor; 46, turntable; 47, short rod 1; 48, rectangular frame; 49, connecting rod 2; 50, short rod 2; 51, rectangular block; 52, slide 1; 53, slide rod; 54, U-shaped rod; 55, slide 2; 56, slider. DETAILED DESCRIPTION
[0030] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0031] In addition, in the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes, and do not specifically refer to the order or sequence, nor are they used to limit the present invention. They are only used to distinguish components or operations described with the same technical terms, and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions and technical features between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.
[0032] The present invention provides the following embodiments
[0033] Example 1
[0034] The embodiment of the present invention provides an air preheater sealing structure, such as Figure 1-2 As shown, the sealing structure includes: a floating sealing device and a gravity sealing device, and the floating sealing device is radially installed at the hot end of the air preheater, and the gravity sealing device is radially installed at the cold end of the air preheater.
[0035] Optionally, the floating sealing device includes: a partition 1, a hard sealing plate 10 is provided at the left end of the partition 1, a fixed plate 2 is provided at the right end of the partition 1, the top end of the fixed plate 2 is in contact with the rotating shaft 3, the rotating shaft 3 is in contact with the moving plate 4, the other end of the moving plate 4 is fixedly installed with a self-lubricating metal 5, the right end of the fixed plate 2 is fixedly installed with a support 6, the top end of the support 6 is connected to the support rod 8 through a reset spring 7, the other end of the support rod 8 is movably connected to the support rod 2 9, and the top end of the support rod 2 9 is fixedly connected to the moving plate 4.
[0036] Optionally, the gravity sealing device includes: a partition 11, a hard sealing plate 12 is provided at the left end of the partition 11, a fixed plate 13 is provided at the right end of the partition 11, the bottom end of the fixed plate 13 is in contact with a movable plate 14, a rotating shaft 15 is provided in the movable plate 14, and the other end of the movable plate 14 is fixedly installed on one end of a self-lubricating metal 16, and the other end of the self-lubricating metal 16 is fixedly connected to a counterweight 17.
[0037] The working principle and beneficial effects of the above technical solution are as follows: during the operation of the air preheater, once the floating seal device is worn, it will be compensated under the action of the reset spring 7, and the cycle will be repeated. Since the self-lubricating metal 5 material is in close contact with the fan-shaped plate 18, the mushroom-shaped deformation of the rotor and the pressure difference between the air side and the flue gas side can be overcome, so as to effectively prevent the primary and secondary air from leaking into the flue gas. By setting up a floating seal device, the air leakage rate can be effectively reduced, and the air leakage rate increases very little as the operation time increases. Elastic compensation will not cause the air preheater to get stuck or stop, and can ensure the long-term safe and stable operation of the air preheater.
[0038] The gravity-type sealing device is installed on the radial partition plate 11 at the cold end of the air preheater rotor. When the sealing device passes through the fan plate 18, the sealing device rotates backward around the rotating shaft 15, and the sealing device contacts the fan plate 18 to form a gapless seal, and smoothly passes through the fan plate 18 to complete a working cycle. The sealing device completely relies on its own gravity to work, and has stable, safe and reliable operation. The gravity-type seal is easy to install and does not damage the structure of the air preheater, ensuring long-term stable operation. In order to ensure that under special operating conditions, the working limit function set by the gravity-type sealing device can minimize the sealing device from being blown over, and can also prevent dust accumulation on the moving pieces of other structures to ensure that the air preheater leakage rate is long-term stable without large fluctuations or increases. This effectively improves the problems raised by the background technology: the mechanical seals in the existing sealing devices are severely worn, have a short life and need to be replaced frequently, and the sealing gap is difficult to adjust, which easily causes large air leakage during operation.
[0039] Example 2
[0040] Based on Example 1, a boiler system, such as Figure 3-4 As shown, it includes: a base 19, on the top of which an air preheater 20, a boiler device 21 and a waste gas treatment device are fixedly installed in sequence from left to right, and the air preheater 20 and the boiler device 21 are connected by a connecting pipe 1 22, and the boiler device 21 and the waste gas treatment device are connected by a connecting pipe 23.
[0041] Optionally, a heat recovery mechanism is provided in the exhaust gas treatment device, and the heat recovery mechanism includes: a treatment box 24, the bottom end of the treatment box 24 is fixedly connected to the base 19, and the bottom end of the treatment box 24 is provided with a liquid storage chamber 25, the right end of the liquid storage chamber 25 is connected to the water inlet pipe 26 and the water outlet pipe 27 from top to bottom, respectively, and the water inlet pipe 26 and the water outlet pipe 27 are respectively fixedly installed with an electromagnetic valve 1 28 and an electromagnetic valve 2 29, and the connecting pipe 2 23 passes through the treatment box 24 and is fixedly connected to the connecting elbow 30, and the other end of the connecting elbow 30 is connected to the exhaust gas treatment mechanism through a plurality of through holes 31, and a plurality of reverse flow valves 1 32 are fixedly installed in the through holes 31.
[0042] Optionally, the exhaust gas treatment mechanism includes: a cavity 33 (a gas treatment liquid is added to the cavity 33), the cavity 33 is arranged at the top of the left side of the treatment box 24, and the top of the cavity 33 is connected to the outlet pipe 35, and a connecting rod 36 is arranged in the cavity 33, and a plurality of push plates 37 are fixedly installed on the left end of the connecting rod 36, and the right end of the connecting rod 36 passes through the cavity 24 arranged at the top of the right side of the treatment box 24 and is connected to the driving component, and the top of the cavity 33 is fixed. A plurality of nozzles 38 are installed, and the nozzles 38 are connected to one end of a connecting pipe three 39, and the other end of the connecting pipe three 39 is connected to a pressurizing chamber 40, and a reverse flow valve two 41 is fixedly installed in the connecting pipe three 39, and the bottom end of the pressurizing chamber 40 is connected to one end of a connecting pipe four 42, and the other end of the connecting pipe four 42 is connected to a cavity one 33, and a reverse flow valve three 43 is fixedly installed in the connecting pipe four 42, and the piston 34 is connected to the inner wall of the pressurizing chamber 40 by sliding up and down, and the top end of the piston 34 is connected to the driving assembly.
[0043] The driving assembly includes: a driving motor 45, the fixed end of the driving motor 45 is fixedly mounted on the rear end inner wall of the cavity 44, and the output end of the driving motor 45 is fixedly mounted with a turntable 46, the front end of the turntable 46 is fixedly mounted with a short rod 47, the short rod 47 is movably connected up and down in a rectangular frame 48, and the left end of the rectangular frame 48 is fixedly connected to the connecting rod 36, the bottom end of the rectangular frame 48 is slidably connected to the slide groove 55 provided at the bottom end of the cavity 44, and the rectangular frame 48 One end of a connecting rod 49 is fixedly installed at the top, and a short rod 50 is fixedly installed at the other end of the connecting rod 49. The other end of the short rod 50 is slidably connected in a slide groove 52 provided in a rectangular block 51, and a slider 56 is fixedly installed at the right end of the rectangular block 51. The slider 56 is slidably connected to the slide rod 53 up and down, and the top of the slide rod 53 is fixedly installed on the inner wall of the top of the cavity 44, and the left end of the rectangular block 51 is fixedly installed at one end of a U-shaped rod 54, and the other end of the U-shaped rod 54 is fixedly installed on the top of the piston 34.
[0044] The working principle of the above technical solution is as follows: when it is necessary to treat the exhaust gas generated by the boiler device 21, first connect the connecting pipe 23 and the connecting elbow 30, then open the electromagnetic valve 1 28, and transport water to the liquid storage chamber 25 through the water inlet pipe 26, and close the electromagnetic valve 1 28 at the same time, so that the residual heat in the exhaust gas is transferred to the water in the liquid storage chamber 25 through the connecting elbow 30. When the water in the liquid storage chamber 25 reaches a certain temperature, open the electromagnetic valve 29, so that the heated water is discharged through the water outlet pipe 27 for use;
[0045] Then, the driving motor 45 is turned on, and the driving motor 45 starts to drive the rotating disk 46 fixedly connected thereto to rotate. The rotating disk 46 rotates and drives the short rod 1 47 to move on the rotating disk 4646. At the same time, the movement of the rotating disk 46 drives the rectangular frame 48 to slide left and right in the slide groove 2 55. When the rectangular frame 48 slides, it drives the connecting rod 1 36 to move left and right. The movement of the connecting rod 1 36 drives the plurality of push plates 37 to move left and right in the cavity 1 33, thereby accelerating the chemical reaction between the gas treatment liquid and the gas discharged from the connecting elbow 30. At the same time, the rectangular frame 48 moves left and right and drives the connecting rod 2 49 and the short rod 2 50 fixedly connected thereto. It moves in the slide groove 52, so that the rectangular block 51 moves up and down on the slide rod 53 accordingly. The up and down movement of the rectangular block 51 drives the U-shaped rod 54 fixedly connected thereto to move up and down accordingly. The up and down movement of the left end of the U-shaped rod 54 drives the piston 34 to move up and down in the pressurizing chamber 40. When the piston 34 moves up, under the action of pressure, the gas treatment liquid in the cavity 33 is transported to the pressurizing chamber 40 through the connecting pipe four 42, and then is sprayed into the cavity 33 through the connecting pipe three 39 and the nozzle 38 when the piston 34 moves down, so that the spray liquid reacts with the gas in the cavity 33 again, and is finally discharged into the air through the outlet pipe 35.
[0046] The beneficial effects of the above technical solution are as follows: the present invention, by providing a heat recovery mechanism, is conducive to heating the liquid in the liquid storage chamber 25 through the contact between the gas and the connecting elbow 30, so that the hot liquid in the gas is output to the liquid through heat exchange, so that the heated liquid is provided to the user, thereby improving the utilization rate of the gas; by providing a reverse flow valve 1 32, a reverse flow valve 2 41 and a reverse flow valve 3 43, it is conducive to preventing the backflow of gas and liquid; by providing a short rod 1 47 and a rectangular frame 48, it is conducive to realizing the left and right movement of the connecting rod 1 36 and the push plate 37 under the action of the rotating disk 46, so that the gas and liquid By setting the short rod 2 50 and the rectangular block 51, the rectangular block 51 can be moved up and down during the left and right movement of the rectangular frame 48; by setting the slider 56 and the slide bar 53, it is beneficial to effectively limit the rectangular block 51; by setting the piston 34 and the U-shaped rod 54, it is beneficial to pressurize the liquid; by setting a plurality of connecting pipes 39, it is beneficial to achieve secondary mixing of the gas, thereby further improving the absorption of toxic substances in the gas; by setting the electromagnetic valve 1 28 and the electromagnetic valve 2 29, it is beneficial to realize the switching of the water inlet pipe 26 and the water outlet pipe 27, which is very convenient and practical.
[0047] Example 3
[0048] Based on Embodiment 1 or 2, a boiler system, the air preheater 20 is composed of a rotor, a heat storage element, a housing, a transmission device, a sealing device and other components, and the air preheater 20 also includes:
[0049] A flow rate sensor, used to detect the speed of gas passing through the fluid channel of the thermal storage element;
[0050] Temperature sensor 1, used to detect the temperature of the hot end of the fluid channel of the heat storage element in the air preheater 20 when the gas passes through;
[0051] Temperature sensor 2, used to detect the cold end temperature of the fluid channel of the heat storage element in the air preheater 20 when the gas passes through;
[0052] An alarm and a controller are provided, wherein the alarm and the controller are electrically connected to the flow rate sensor, the first temperature sensor, the second temperature sensor and the alarm.
[0053] Optionally, the controller controls the alarm to work based on the flow rate sensor, the first temperature sensor, and the second temperature sensor, including the following steps:
[0054] Step 1: According to formula (1), calculate the flow resistance F in the fluid channel of the thermal storage element: z :
[0055]
[0056] Where λ is the flow rate change adjustment coefficient of the gas passing through the fluid channel (the value range is 0.5-1), μ is the resistance coefficient along the gas passing through the fluid channel (the value range is 0.26-0.45), h is the height of the heat storage element, R is the equivalent diameter of the heat storage element per unit length, ρ g is the mass density of the gas entering the heat storage element per unit length, ρ c is the mass density of gas discharged from the unit length of the thermal storage element, m is the gas mass flow rate, S is the installation area of the thermal storage element, and α is the circulation porosity of the thermal storage element;
[0057] Step 2: According to the following formula (2) and the detection values of the flow rate sensor, temperature sensor 1, and temperature sensor 2, the actual air leakage K of the air preheater 20 is calculated. The controller compares the actual air leakage K of the air preheater 20 with the preset air leakage range. When the actual air leakage is higher than the preset air leakage range, the controller controls the alarm to sound an alarm:
[0058]
[0059] in is the gas correction coefficient (the range is 0.6-1.0), β is the gas thermal conductivity (the range is 0.024-0.03), V is the flow sensor detection value, χ is the gas kinematic viscosity, Pr is the Prandtl number, δ is the gas leakage coefficient (the range is 0.6-0.9), A is the sealing gap area, F yis the gas output power, ρ is the gas density, T0 is the ambient temperature, T1 is the detection value of temperature sensor 1, and T2 is the detection value of temperature sensor 2.
[0060] The beneficial effects of the above technical solution are as follows: the controller calculates the resistance along the fluid channel of the heat storage element based on the formula (1), and comprehensively considers the flow rate change adjustment coefficient of the gas passing through the fluid channel, the resistance coefficient along the fluid channel of the gas, the height of the heat storage element, the equivalent diameter of the heat storage element per unit length, the mass density of the gas entering the heat storage element per unit length, the mass density of the gas discharged from the heat storage element per unit length, the gas mass flow rate, the installation area of the heat storage element, and the circulation porosity of the heat storage element, so that the calculation result is more accurate and reliable;
[0061] Then, according to formula (2) and the detection values of the flow rate sensor, temperature sensor 1, temperature sensor 2, gas correction coefficient, gas thermal conductivity, gas kinematic viscosity, Prandtl number, gas leakage coefficient, sealing gap area, gas output power, gas density, and ambient temperature, the actual air leakage of the air preheater 20 is calculated, so that the calculation result is more accurate and reliable;
[0062] The controller controls the alarm based on the flow rate sensor, temperature sensor 1 and temperature sensor 2. The controller compares the actual air leakage of the air preheater 20 with the preset air leakage range. When the actual air leakage is higher than the preset air leakage range, the controller controls the alarm to sound, reminding the staff to inspect or replace the air preheater 20 in time, so that it can operate normally, thereby meeting the user's needs for this type of air preheater sealing structure and boiler system.
[0063] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. An air preheater sealing structure, characterized in that: The sealing structure comprises: a floating sealing device and a gravity sealing device, and the floating sealing device is radially installed at the hot end of the air preheater, and the gravity sealing device is radially installed at the cold end of the air preheater.
2. The air preheater sealing structure according to claim 1, characterized in that: The floating sealing device comprises: a partition plate (1), a hard sealing plate (10) is arranged at the left end of the partition plate (1), a fixed plate (2) is arranged at the right end of the partition plate (1), the top end of the fixed plate (2) contacts with a rotating shaft (3), the rotating shaft (3) contacts with a moving plate (4), the other end of the moving plate (4) is fixedly mounted with a self-lubricating metal (5), the right end of the fixed plate (2) is fixedly mounted with a support (6), the top end of the support (6) is connected to a support rod (8) through a return spring (7), the other end of the support rod (8) is movably connected to a support rod (9), and the top end of the support rod (9) is fixedly connected to the moving plate (4).
3. The air preheater sealing structure according to claim 1, characterized in that: The gravity sealing device comprises: a partition plate 2 (11), a hard sealing plate 2 (12) is arranged at the left end of the partition plate 2 (11), a fixed plate 2 (13) is arranged at the right end of the partition plate 2 (11), the bottom end of the fixed plate 2 (13) is in contact with a movable plate 2 (14), a rotating shaft 2 (15) is arranged inside the movable plate 2 (14), and the other end of the movable plate 2 (14) is fixedly mounted on one end of a self-lubricating metal 2 (16), and the other end of the self-lubricating metal 2 (16) is fixedly connected to a counterweight block (17).
4. A boiler system, characterized in that: The boiler system comprises an air preheater sealing structure as described in any one of claims 1 to 3, and the boiler system comprises: a base (19), an air preheater (20), a boiler device (21) and a waste gas treatment device are fixedly installed on the top of the base (19) in sequence from left to right, and the air preheater (20) and the boiler device (21) are connected by a connecting pipe 1 (22), and the boiler device (21) and the waste gas treatment device are connected by a connecting pipe 2 (23).
5. A boiler system according to claim 4, characterized in that: The waste gas treatment device is provided with a heat recovery mechanism, the heat recovery mechanism comprising: a treatment box (24), the bottom end of the treatment box (24) is fixedly connected to the base (19), and the bottom end of the treatment box (24) is provided with a liquid storage chamber (25), the right end of the liquid storage chamber (25) is respectively connected to the water inlet pipe (26) and the water outlet pipe (27) from top to bottom, and the water inlet pipe (26) and the water outlet pipe (27) are respectively fixedly installed with an electromagnetic valve 1 (28) and an electromagnetic valve 2 (29), and the connecting pipe 2 (23) passes through the treatment box (24) and is fixedly connected to the connecting elbow (30), and the other end of the connecting elbow (30) is connected to the waste gas treatment mechanism through a plurality of through holes (31), and a plurality of reverse flow valves 1 (32) are fixedly installed in the through holes (31).
6. A boiler system according to claim 5, characterized in that: The waste gas treatment mechanism comprises: a cavity (33), wherein the cavity (33) is arranged at the top left side of the treatment box (24), and the top of the cavity (33) is connected to the exhaust pipe (35), and a connecting rod (36) is arranged in the cavity (33), and a plurality of push plates (37) are fixedly installed at the left end of the connecting rod (36), and the right end of the connecting rod (36) passes through the cavity (44) arranged at the top right side of the treatment box (24) and is connected to the driving component, and a plurality of nozzles (38) are fixedly installed at the top of the cavity (33), The nozzle (38) is connected to one end of the connecting pipe three (39), the other end of the connecting pipe three (39) is connected to the pressurizing chamber (40), and a reverse flow valve two (41) is fixedly installed in the connecting pipe three (39), and the bottom end of the pressurizing chamber (40) is connected to one end of the connecting pipe four (42), the other end of the connecting pipe four (42) is connected to the cavity one (33), and a reverse flow valve three (43) is fixedly installed in the connecting pipe four (42), the piston (34) is connected to the inner wall of the pressurizing chamber (40) in an up-and-down sliding manner, and the top end of the piston (34) is connected to the driving assembly.
7. A boiler system according to claim 4, characterized in that: The air preheater (20) is composed of a rotor, a heat storage element, a housing, a transmission device, a sealing device and other components. The air preheater (20) also includes: A flow rate sensor, used to detect the speed of gas passing through the fluid channel of the thermal storage element; Temperature sensor 1, used for detecting the temperature at the hot end of the fluid channel of the heat storage element in the air preheater (20) when the gas passes through the air preheater; Temperature sensor 2, used for detecting the temperature at the cold end of the fluid channel of the heat storage element in the air preheater (20) when the gas passes through the air preheater; An alarm and a controller are provided, wherein the alarm and the controller are electrically connected to the flow rate sensor, the first temperature sensor, the second temperature sensor and the alarm.
8. A boiler system according to claim 7, characterized in that: The controller controls the alarm to work based on the flow rate sensor, the first temperature sensor, and the second temperature sensor, including the following steps: Step 1: According to formula (1), calculate the flow resistance F in the fluid channel of the thermal storage element: z : Where λ is the flow rate change adjustment coefficient of the gas passing through the fluid channel, μ is the resistance coefficient along the gas passing through the fluid channel, h is the height of the heat storage element, R is the equivalent diameter of the heat storage element per unit length, ρ g is the mass density of gas entering the heat storage element per unit length, ρ c is the mass density of gas discharged from the unit length of the thermal storage element, m is the gas mass flow rate, S is the installation area of the thermal storage element, and α is the circulation porosity of the thermal storage element; Step 2: According to the following formula (2) and the detection values of the flow rate sensor, the temperature sensor 1 and the temperature sensor 2, the actual air leakage K of the air preheater (20) is calculated, and the controller compares the actual air leakage K of the air preheater (20) with the preset air leakage range. When the actual air leakage is higher than the preset air leakage range, the controller controls the alarm to sound an alarm: in is the gas correction coefficient, β is the gas thermal conductivity, V is the flow rate sensor detection value, χ is the gas kinematic viscosity, Pr is the Prandtl number, δ is the gas leakage coefficient, A is the sealing gap area, F y is the gas output power, ρ is the gas density, T0 is the ambient temperature, T1 is the detection value of temperature sensor 1, and T2 is the detection value of temperature sensor 2.