By obtaining and processing production request data in the welding and mounting production line, and implementing control strategies to match the order of parts pulling out and pulling in, the problem of parts disordered in multi-model mixed flow production is solved, reducing the footprint and investment of the production line, and improving the production line flexibility and efficiency.
Patent Information
- Application Number
- CN202411188401.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-12-03
AI Technical Summary
In the prior art, during the mixed flow of multiple models, the welding and assembly production line is not matched by the problem of parts being pulled out and pulled in indiscretely during the welding and assembly, resulting in production stoppage, and multiple channels are set up between the line bodies. The buffer area covers a large area and has a large investment.
By obtaining the production request data sent by the workshop central control system, obtaining production order data and finished product launch data, putting it into the task receiving queue in the order of reception, and implementing corresponding control strategies, including normal orders, pull-out orders and finished product launch orders. Ensure that the pull-out and pull-in order of parts matches the order of the model on the production line, avoiding the use of multi-channel cache areas.
It realizes that parts are pulled out and put in in order without using a multi-channel cache area, which reduces the footprint and investment, and improves the flexibility and efficiency of the production line.
Smart Images

Figure CN119065332A_ABST
Abstract
Description
Technical Field
[0001] The invention discloses a method for scheduling a flexible production line of multi-model parts of a body-in-white, and belongs to the field of flexible workshop production and manufacturing. Background Art
[0002] The welding production line is an important part of automobile production, and the welding production line for mixed production of multiple models has become the mainstream. Mixed production of multiple models requires that the models produced by each production line must be sent to the next order for assembly in sequence. For example, if the main welding line produces in the order of A, A, B, B, B, C, C, C, the lower body assembly and the side panel assembly must also be sent to the main welding in the order of A, A, B, B, B, C, C, C, otherwise the lower body assembly and the side panel assembly will not match and the line will be stopped. In the process of body-in-white production, it is necessary to regularly pull out the parts assembly produced by each production line for random inspection and measurement. After the random inspection and measurement are completed, they can be pulled into the production line to continue production. This is called part pulling out and pulling in.
[0003] The pulling out and pulling in of parts affects the order in which the parts are sent to be assembled. For example: the production line has three models of mixed production, A, B, and C. The main welding line is producing in the planned order of A, A, B, B, B, C, C, and C. The lower body assembly and the side panel assembly need to be sent to the main welding in the order of A, A, B, B, B, C, C, and C. If the side panel assembly pulls out the third model B, the order in which the side panel assembly is sent to the main welding line becomes A, A, B, B, C, C, and C, which does not match the order of A, A, B, B, B, C, C, and C of the main welding line. The main welding line is producing the fifth model B, but the side panel assembly is sent to model C, so it cannot be produced. This is called the pull-out and pull-in disorder problem.
[0004] To solve the problem of out-of-order pulling and pulling, car companies usually set up multi-channel buffers between the lines. Parts are first stored in the buffer and then sent to the next process for assembly. In the buffer, parts of the same model exist in the same channel, and the number of parts of any model stored in the buffer is greater than 1. The parts in the buffer are taken out according to the next sequence requirements and sent to the next line for assembly. This layout does not affect the production order of the next process line when pulling in and out of the buffer. However, this method has the problem of large floor space and high investment. Summary of the invention
[0005] In view of the defects of the prior art, the present invention proposes a flexible production line scheduling method, terminal and medium for multi-model parts of white body, which solves the problem of large footprint and high investment in setting up multi-channel buffer areas between lines.
[0006] The technical solution of the present invention is as follows:
[0007] According to a first aspect of an embodiment of the present invention, a method for scheduling a flexible production line of multi-model parts of a body-in-white is provided, comprising:
[0008] When receiving production request data sent by the workshop central control system, obtaining multiple production order data and finished product online data in the production request data;
[0009] Put the multiple production order data into the task receiving queue in the order of receipt, put the finished product online data into the finished product pull-in queue, and execute the corresponding control strategies according to the corresponding production order data and finished product online data in turn until the multiple production order data are completed.
[0010] Preferably, the production order data includes: order type and order information.
[0011] Preferably, the order types include: normal orders, pull orders and finished product online orders.
[0012] Preferably, the order information includes: vehicle type, task type and serial number.
[0013] Preferably, executing corresponding control strategies according to the corresponding production order data and finished product online data includes:
[0014] When the order type is a normal order, the control strategy is a normal order control strategy, including:
[0015] Determine that the order information is consistent with the model of any order in the finished product online data:
[0016] Yes, implement the finished product online order control strategy;
[0017] No, put the tasks corresponding to the task type into the upper port task queue of the corresponding upper port and the lower port task queue of the corresponding lower port respectively, control the corresponding robots, fixtures, upper port, lower port and process equipment to perform corresponding process operations until the finished parts are placed in the lower port, and send the parts in the lower port to the main welding line of the next process.
[0018] Preferably, executing corresponding control strategies according to the corresponding production order data and finished product online data includes:
[0019] When the order type is a pull order, the control strategy is a pull order control strategy, including:
[0020] Determine that the order information is consistent with the model of any order in the finished product online data:
[0021] Yes, implement the finished product online order control strategy;
[0022] No, put the tasks corresponding to the task type into the upper port task queue corresponding to the upper port and the lower port task queue corresponding to the lower port respectively, and control the corresponding robots, fixtures, upper port, lower port and process equipment to perform corresponding process operations until the completed parts are placed in the lower port and pulled out.
[0023] Preferably, executing corresponding control strategies according to the corresponding production order data and finished product online data includes:
[0024] When the order type is a finished product online order, the control strategy is a finished product online order control strategy, including: placing the task corresponding to the task type into the corresponding downstream task queue, controlling the corresponding robot, fixture and downstream to perform corresponding operations, placing the parts into the downstream, and sending the parts in the downstream to the main welding line of the next process.
[0025] According to a second aspect of an embodiment of the present invention, there is provided a scheduling device for a flexible production line of multi-model parts of a body-in-white, comprising:
[0026] An acquisition module, for acquiring a plurality of production order data and finished product online data in the production request data when receiving the production request data sent by the workshop central control system;
[0027] An execution module is used to place multiple production order data into a task receiving queue in the order of receipt, place the finished product online data into a finished product pull-in queue, and execute corresponding control strategies according to the corresponding production order data and finished product online data in turn until multiple production order data are completed.
[0028] According to a third aspect of an embodiment of the present invention, a terminal is provided, including:
[0029] one or more processors;
[0030] a memory for storing the one or more processor-executable instructions;
[0031] Wherein, the one or more processors are configured to:
[0032] Execute the method described in the first aspect of the embodiment of the present invention.
[0033] According to a fourth aspect of an embodiment of the present invention, a non-temporary computer-readable storage medium is provided. When instructions in the storage medium are executed by a processor of a terminal, the terminal is enabled to execute the method described in the first aspect of the embodiment of the present invention.
[0034] According to a fifth aspect of an embodiment of the present invention, an application product is provided. When the application product is running on a terminal, the terminal executes the method described in the first aspect of the embodiment of the present invention.
[0035] The beneficial effects of the present invention are:
[0036] The present invention provides a scheduling method, terminal and medium for a flexible production line of multi-model parts of a body-in-white. The method obtains multiple production order data and finished product online data in production request data, puts the multiple production order data into a task receiving queue in the order of receipt, puts the finished product online data into a finished product pull-in queue, and executes corresponding control strategies according to the corresponding production order data and the finished product online data in turn until the multiple production order data are completed, thereby meeting the requirement that the pull-in and pull-out are not disordered when there is no multi-channel cache between line bodies.
[0037] It is to be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 The present invention is a flow chart showing a method for scheduling a flexible production line of multi-model body-in-white parts according to an exemplary embodiment.
[0039] Figure 2 It is a schematic diagram of the system structure of an embodiment of a method for scheduling a flexible production line for multi-model parts of a body-in-white according to an exemplary embodiment.
[0040] Figure 3 The present invention is a schematic structural block diagram of a device for scheduling a flexible production line for multi-model parts of a body-in-white according to an exemplary embodiment.
[0041] Figure 4 The present invention is a schematic block diagram of a terminal structure according to an exemplary embodiment. DETAILED DESCRIPTION
[0042] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0043] In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they cannot be understood as limitations on the present invention.
[0044] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0045] An embodiment of the present invention provides a method for scheduling a flexible production line of multi-model parts for a body-in-white. The method is implemented by a terminal, which may be a PLC or an industrial computer, etc. The terminal at least includes a CPU, etc.
[0046] Embodiment 1
[0047] Figure 1 The flowchart of a method for scheduling a flexible production line of multi-model parts of a body-in-white according to an exemplary embodiment is shown. The method is used in a terminal and includes the following steps:
[0048] Step 101, when receiving the production request data sent by the workshop central control system, obtain multiple production order data and finished product online data in the production request data, the specific content is as follows:
[0049] The present embodiment is a method for pulling in and out parts for mixed production of multiple vehicle models, which is applicable to a body-in-white production line. The body-in-white production line consists of a terminal, an HMI, a robot, a fixture, a loading port, a unloading port, and at least one process equipment. The process equipment includes at least: spot welding equipment, gluing equipment, arc welding equipment, CMT, and the like.
[0050] The terminal is connected to the central control or MES of the workshop through the network and receives the production order from the central control or MES. The production order at least contains vehicle model information. The terminal is connected to the HMI screen, robot, fixture, loading port, unloading port, and process equipment through the network. The HMI screen is used for information display, equipment operation, part pulling in, and part pulling out operations. The terminal preferably uses PLC. After receiving the order information, the LC controls the tooling and equipment of the line body according to the set logic and timing, and produces in sequence according to the vehicle model sequence of the production order and sends them to the next process production line in sequence.
[0051] The above production order data includes: order type and order information. Order types include: normal order, pull order and finished product online order. Order information includes: vehicle model, task type and serial number.
[0052] Step 102, put the multiple production order data into the task receiving queue in the order of receiving, put the finished product online data into the finished product pull-in queue, and execute the corresponding control strategy according to the corresponding production order data and finished product online data in turn until the multiple production order data are completed. The specific content is as follows:
[0053] There are four queues in the PLC program: task receiving queue, loading port task queue, unloading port task queue and finished product pull-in queue. Among them, "task receiving queue", "loading port task queue" and "unloading port task queue" are first-in-first-out queues, that is, the tasks put into the queue first are taken out first.
[0054] Put multiple production order data into the task receiving queue in the order of receipt, put the finished product online data into the finished product pull-in queue, and when the line is in production, the PLC takes out an order from the task receiving queue, determines the type of order, and compares the model of the order in the finished product pull-in queue. Execute the corresponding control strategy according to the corresponding production order data and finished product online data in turn until multiple production order data are completed.
[0055] When the order type is a normal order, the control strategy is the normal order control strategy, including:
[0056] Determine whether the order information is consistent with the model of any order in the finished product online data:
[0057] Yes, implement the finished product online order control strategy;
[0058] No, the tasks corresponding to the task types are respectively placed into the upper port task queue corresponding to the upper port and the lower port task queue corresponding to the lower port, and the corresponding robots, fixtures, upper port, lower port and process equipment are controlled to perform corresponding process operations. That is, according to the vehicle model of the order, the tooling and equipment of the line are controlled to perform automated production according to the set logic and timing, and the robots are controlled to perform processes such as grabbing, gluing, and welding until the finished parts are placed in the lower port, and the parts in the lower port are sent to the main welding line of the next process.
[0059] When the order type is a pull order, the control strategy is the pull order control strategy, including:
[0060] Determine whether the order information is consistent with the model of any order in the finished product online data:
[0061] Yes, implement the finished product online order control strategy;
[0062] No, put the tasks corresponding to the task type into the upper port task queue corresponding to the upper port and the lower port task queue corresponding to the lower port respectively, and control the corresponding robots, fixtures, upper port, lower port and process equipment to perform corresponding process operations until the completed parts are placed in the lower port and pulled out.
[0063] When the order type is a finished product online order, the control strategy is the finished product online order control strategy, including: placing the task corresponding to the task type into the corresponding downstream task queue of the downstream, controlling the corresponding robot, fixture and downstream to perform corresponding operations, placing the parts into the downstream, and sending the parts in the downstream to the main welding line of the next process.
[0064] The unloading port is equipped with a prompting device (feeding port screen, voice speaker) to prompt the manual offline parts or finished products to be put back online, and the model is displayed. The parts pulling out and parts pulling in, that is, the above-mentioned pulling out orders and finished product online orders can also be operated manually by clicking on the HMI screen, that is:
[0065] To pull out parts:
[0066] The HMI screen is equipped with an "Insert Generate Task" button. Manually operate the HMI to click "Insert Generate Task", enter or select the vehicle model, select the order type as "Pull Out Order", select the insertion position (the head of the task receiving queue, the tail of the task receiving queue), and manually click "Generate Insert Order". After manually clicking "Generate Insert Order", the PLC inserts the order into the specified position of the "Task Receiving Queue". Then the line body is produced to the next piece outlet and pulled out.
[0067] To pull in parts:
[0068] The HMI screen is equipped with a "Finished Product Pull In" button. Manually operate the HMI and click the "Finished Product Pull In" button, enter or select the model, and click "OK". The PLC will insert an order for the selected model in the "Finished Product Pull In Queue". When the order enters the "Next Part Task Queue", it is the turn of this order to send the parts to the next process production line, pull them in and send them to the next process.
[0069] By adopting the above method, the line body can realize the pulling in and out of parts, and the pulling in and out does not affect the arrangement order of the models sent to the next production line.
[0070] According to the above scheduling method, manual clicking operation is performed on the HMI screen. The specific example is as follows:
[0071] Take a roof assembly production line as an example. It produces two models, Model A and Model B. The roof assemblies of Model A and Model B are both composed of a roof outer panel and a sunroof reinforcement ring. The connection process of the roof assembly includes gluing and CMT welding.
[0072] like Figure 2 As shown, the line network of the top cover assembly production line is connected. The PLC (2) of the top cover assembly production line is connected to the central control (1) of the workshop through the network to receive the production order of the top cover assembly from the central control (1). The production order of the top cover assembly includes information such as vehicle model, task type, serial number, etc. The PLC is connected to the following devices through a network: HMI (3), robot R1 (4), robot R2 (5), robot R3 (6), robot R4 (7), vehicle A fixture (8), vehicle B fixture (9), A sunroof reinforcement ring lower part gripper (19), B sunroof reinforcement ring lower part gripper (20), A roof cover outer panel upper part gripper (17), B roof cover outer panel upper part gripper (18), A roof cover assembly lower part gripper (21), B roof cover assembly lower part gripper (22), A roof cover outer panel upper part opening (10), B roof cover outer panel upper part opening (11), B sunroof reinforcement ring upper part opening (12), A sunroof reinforcement ring upper part opening (23), lower part opening (13), material opening screen (14), glue coating equipment (15), CMT welding equipment (16). Robot R1 (4) performs CMT welding. The robot R2 (5) grabs the top cover outer panel upper part, and the robot R2 (5) is connected to the A vehicle top cover outer panel upper part gripper (17) and the B vehicle top cover outer panel upper part gripper (18) through the gun changing plate. The robot R3 (6) grabs the sunroof reinforcement ring upper part, and the robot R3 (6) is connected to the A sunroof reinforcement ring upper part gripper (19) and the B sunroof reinforcement ring upper part gripper (20) through the gun changing plate. The robot R4 (7) grabs the top cover assembly for the lower part, and the robot R4 (7) is connected to the A vehicle top cover assembly lower part gripper (21) and the B vehicle top cover assembly lower part gripper (22) through the gun changing plate.
[0073] In the PLC program, there are three order types: "normal order", "pull order", and "finished product line order", which are represented by numbers 1, 2, and 3 respectively.
[0074] Order type 1 means "normal order", that is, the top cover assembly of this order is produced normally and sent to the main welding line of the next process.
[0075] Order type 2 means a "pull out order", that is, the top cover assembly of this order is produced normally and pulled out at the unloading port (13).
[0076] Order type 3 indicates "finished product on-line order", that is, the order line does not produce the finished product, and the finished product top cover assembly is directly sent to the main welding line of the next process through the unloading port (13).
[0077] Queues TR1, TR2, TR3, TR4, TR5, TR6, and TR7 are set in the program of PLC (2). Among them, TR1 is the "task receiving queue", TR2 is the "upper part port task queue" of the upper part port of the roof cover outer panel of vehicle A, TR3 is the "upper part port task queue" of the sunroof reinforcement ring of vehicle A, TR4 is the "upper part port task queue" of the upper part port of the roof cover outer panel of vehicle B, TR5 is the "upper part port task queue" of the sunroof reinforcement ring of vehicle B, TR6 is the "lower part port task queue" of the lower part port, and RT7 is the "finished product pulling queue". TR1, TR2, TR3, TR4, TR5, and TR6 are first-in-first-out queues, that is, the task put into the queue first is taken out first.
[0078] To illustrate the working logic of the line, assume that the workshop central control (1) issues production orders A, B, B, B, A, A, B, B, and the serial numbers are "K001", "K002", "K003", "K004", "K005", "K006", "K007", "K008", and the order types are all 1. After the PLC (2) receives the order information from the workshop central control (1), the orders received by the PLC (2) are placed in the queue TR1 in the order of receipt. Then the order sequence in TR1 is A, B, B, B, A, A, B, B, and the serial numbers are "K001", "K002", "K003", "K004", "K005", "K006", "K007", "K008", and the order types are all 1.
[0079] When the line starts production, the PLC first takes out the order with serial number "K001" from the TR1 queue. In this way, the tasks in TR1 are in the order of B, B, B, A, A, B, B. The serial numbers are "K002", "K003", "K004", "K005", "K006", "K007", "K008", and the order types are all 1.
[0080] Then, the PLC first determines that the model A of the order task with the serial number "K001" is taken out, and the task type is 1, and determines that the queue of RT7 is empty. PLC (1) puts the order into TR2, TR3, and TR6 according to the order model A. Robot R2 (5) switches to the upper part gripper (17) of the roof cover outer panel of vehicle A, and grabs the roof cover outer panel of vehicle A from the upper part opening (11) of the roof cover outer panel of vehicle A. Robot R3 (6) switches to the upper part gripper (19) of the sunroof reinforcement ring of vehicle A, and grabs the sunroof reinforcement ring of vehicle A from the upper part opening (23) of the sunroof reinforcement ring of vehicle A. After the robot successfully grabs the parts, PLC (2) deletes the orders of vehicle A of TR2 and TR3, and the grabbing is completed. Then robots R1 (4), R2 (5), and R3 (6) carry out processes such as loading, gluing, and CMT welding. Then the robot R4 (7) switches to the A car roof assembly unloading gripper (21), grabs the completed A car roof assembly and places it in the unloading port (13). When the A car roof assembly is placed in the unloading port (13), the PLC (2) takes out the "K001" order from the "unloading port task queue" TR6, and by judging that the order type is 1 and the order type is "normal order", the roof assembly in the unloading port (13) is sent to the next process main welding line.
[0081] This completes the production of an order.
[0082] When the PLC generates the second order "K002", the vehicle model is model B. The PLC first takes out the order with serial number "K002" from the TR1 queue. In this way, the tasks in TR1 are in the order of B, B, A, A, B, B, and the serial numbers are "K003", "K004", "K005", "K006", "K007", and "K008", and the order types are all 1. Then the PLC first determines that the vehicle model B and the task type of the taken out order task with serial number "K002" are 1, and determines that the queue of RT7 is empty. PLC (1) puts the order into TR4, TR5, and TR6 according to the order model B. Robot R2 (5) switches to the B car roof cover outer panel upper gripper (18) and grabs the B car roof cover outer panel from the B car roof cover outer panel upper opening (11). Robot R3 (6) switches to the upper part gripper (20) of the sunroof reinforcement ring of vehicle B, and grabs the sunroof reinforcement ring of vehicle A from the upper part opening (12) of the sunroof reinforcement ring of vehicle B. After the robot successfully grabs the part, PLC (2) deletes the order of vehicle A of TR4 and TR5, and the grabbing is completed. Then robots R1 (4), R2 (5), and R3 (6) carry out the processes of loading, gluing, and CMT welding. Then robot R4 (7) switches to the lower part gripper (22) of the roof cover assembly of vehicle B, and grabs and places the completed roof cover assembly of vehicle B to the lower part opening (13). When the roof cover assembly of vehicle B is placed at the lower part opening (13), PLC (2) takes out the "K002" order from the "lower part opening task queue" TR6, judges that the order type is 1, and the order type is "normal order", and sends the roof cover assembly in the lower part opening (13) to the main welding line of the next process.
[0083] If the pull-in and pull-out operations are not performed, the line will complete the production of orders with serial numbers "K003", "K004", "K005", "K006", "K007", and "K008" in the same way as above, and send them to the main welding line. It should be noted that the production in the line body is multi-sequence parallel production.
[0084] To illustrate the pull-out operation, assume that after completing the second order, model A needs to be pulled out manually:
[0085] Manually click the "Insert Generate Task" button set on the HMI (3) screen, manually operate HMI (3) to click "Insert Generate Task", select vehicle type B, select the order type as "pull order", select the head of the task receiving queue at the insertion position, and manually click "Generate Insert Order". After manually clicking "Generate Insert Order", PLC (2) generates a temporary serial number for the order that starts with the character "RX" + 2 digits, such as RX01. And insert the order into the head of the "task receiving queue" TR1. In this way, the order sequence of the "task receiving queue" TR1 is A, B, B, A, A, B, B, and the serial numbers are "RX01", "K003", "K004", "K005", "K006", "K007", and "K008", and the order types are 2, 1, 1, 1, 1, 1, 1. Then, according to the above method, the production of car A with serial number RX01 begins. When PLC (2) takes out the "RX01" order from the "unloading port task queue" TR6, it determines that the order type is 2 and the order type is "pull order", and prompts manual unloading on the material port screen (14). When the manual unloading of the part from the material port, the order is completed. Then, the "K003", "K004", "K005", "K006", "K007", and "K008" orders are produced and sent to the main welding line.
[0086] To illustrate the pull-in operation, assume that after completing the second order, model A needs to be manually pulled in:
[0087] Manually click the "Finished Product Pull In" button on the HMI (2) screen, select vehicle type A, and click "OK". PLC (2) will insert an order with vehicle type A and order type "Finished Product Pull In" in the "Finished Product Pull In Queue" TR7. PLC (2) takes out the "K003" order from the TR1 queue. The vehicle type of the order task is B and the task type is 1, which is inconsistent with the order type in TR7. Order "K003" is produced in the line and sent to the main welding line. Then, PLC (2) takes out the "K004" order from the TR1 queue. The vehicle type of the order task is B and the task type is 1, which is inconsistent with the order type in TR7. Order "K004" is produced in the line and sent to the main welding line. Then, PLC (2) takes out the "K005" order from the TR1 queue. The order task has model A and task type 1, which is consistent with the order type in TR7. Then PLC (2) deletes the order of model A from the "finished product pull-in queue" TR7. PLC (2) changes the type of the "K005" order to "finished product on-line". It only puts the "K005" order into the "download port task queue" TR6 of the download port, and does not put the order into the "upload port task queue" TR2 or TR3. In this way, the production line will not produce the order. Until PLC (2) takes out the "K005" order from the "download port task queue" TR6, prompts manual loading on the material port screen (14), and manually pushes the finished product top cover assembly of model A into the material port, PLC (2) sends the finished product top cover assembly to the next main welding line. Then the line will produce the "K006", "K007", and "K008" orders and send them to the main welding line.
[0088] To sum up, when pulling in and pulling out, the top covers sent to the main welding line are A, B, B, B, A, A, B, B, and the serial numbers are "K001", "K002", "K003", "K004", "K005", "K006", "K007", and "K008" respectively. Pulling in and pulling out will not cause disorder.
[0089] Embodiment 2
[0090] Figure 3 The present invention is a schematic structural block diagram of a device for scheduling a flexible production line for multi-model parts of a body-in-white according to an exemplary embodiment, the device comprising:
[0091] The acquisition module 210 is used to acquire a plurality of production order data and finished product online data in the production request data when receiving the production request data sent by the workshop central control system;
[0092] The execution module 220 is used to put the multiple production order data into the task receiving queue in the order of receipt, put the finished product online data into the finished product pull-in queue, and execute the corresponding control strategy according to the corresponding production order data and finished product online data in turn until the multiple production order data are completed.
[0093] The present invention obtains multiple production order data and finished product online data in the production request data, puts the multiple production order data into the task receiving queue in the order of reception, puts the finished product online data into the finished product pull-in queue, and executes corresponding control strategies according to the corresponding production order data and the finished product online data in turn until the multiple production order data are completed, thereby meeting the requirement that the pulling in and pulling out are not disordered when there is no multi-channel cache between the lines.
[0094] Embodiment 3
[0095] Figure 4 It is a structural block diagram of a terminal provided in an embodiment of the present application, and the terminal may be the terminal in the above embodiment.
[0096] Typically, the terminal includes: a processor 301 and a memory 302 .
[0097] The processor 301 may include one or more processing cores, such as a 4-core processor, an 8-core processor, etc. The processor 301 may be implemented in at least one hardware form of DSP (Digital Signal Processing), FPGA (Field-Programmable Gate Array), and PLA (Programmable Logic Array). The processor 301 may also include a main processor and a coprocessor. The main processor is a processor for processing data in the awake state, also known as a CPU (Central Processing Unit); the coprocessor is a low-power processor for processing data in the standby state. In some embodiments, the processor 301 may be integrated with a GPU (Graphics Processing Unit), which is responsible for rendering and drawing the content to be displayed on the display screen. In some embodiments, the processor 301 may also include an AI (Artificial Intelligence) processor, which is used to process computing operations related to machine learning.
[0098] The memory 302 may include one or more computer-readable storage media, which may be tangible and non-transitory. The memory 302 may also include high-speed random access memory, and non-volatile memory, such as one or more disk storage devices, flash memory storage devices. In some embodiments, the non-transitory computer-readable storage medium in the memory 302 is used to store at least one instruction, which is used to be executed by the processor 301 to implement a flexible production line scheduling method for multi-model parts of a body-in-white provided in this application.
[0099] In some embodiments, the terminal may further include: a peripheral device interface 303 and at least one peripheral device. Specifically, the peripheral device includes: a radio frequency circuit 304 .
[0100] The peripheral device interface 303 may be used to connect at least one peripheral device related to I / O (Input / Output) to the processor 301 and the memory 302. In some embodiments, the processor 301, the memory 302, and the peripheral device interface 303 are integrated on the same chip or circuit board; in some other embodiments, any one or two of the processor 301, the memory 302, and the peripheral device interface 303 may be implemented on a separate chip or circuit board, which is not limited in this embodiment.
[0101] The radio frequency circuit 304 is used to receive and transmit RF (Radio Frequency) signals, also known as electromagnetic signals. The radio frequency circuit 304 communicates with the communication network and other communication devices through electromagnetic signals. The radio frequency circuit 304 converts electrical signals into electromagnetic signals for transmission, or converts received electromagnetic signals into electrical signals. Optionally, the radio frequency circuit 304 includes: an antenna system, an RF transceiver, one or more amplifiers, a tuner, an oscillator, a digital signal processor, a codec chipset, a user identity module card, and the like. The radio frequency circuit 304 can communicate with other terminals through at least one wireless communication protocol. The wireless communication protocol includes but is not limited to: the World Wide Web, a metropolitan area network, an intranet, various generations of mobile communication networks (2G, 3G, 4G and 5G), a wireless local area network and / or a WiFi (Wireless Fidelity) network. In some embodiments, the radio frequency circuit 304 may also include circuits related to NFC (Near Field Communication), which is not limited in this application.
[0102] Embodiment 4
[0103] In an exemplary embodiment, a computer-readable storage medium is also provided, on which a computer program is stored. When the program is executed by a processor, a flexible production line scheduling method for multi-model parts of a body-in-white is implemented as provided in all the inventive embodiments of the present application.
[0104] Any combination of one or more computer-readable media may be used. A computer-readable medium may be a computer-readable signal medium or a computer-readable storage medium. A computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination thereof. More specific examples (a non-exhaustive list) of computer-readable storage media include: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination thereof. In this document, a computer-readable storage medium may be any tangible medium containing or storing a program that may be used by or in conjunction with an instruction execution system, device, or device.
[0105] Computer-readable signal media may include a data signal propagated in baseband or as part of a carrier wave, which carries a computer-readable program code. Such propagated data signals may take a variety of forms, including, but not limited to, electromagnetic signals, optical signals, or any suitable combination of the above. Computer-readable signal media may also be any computer-readable medium other than a computer-readable storage medium, which may send, propagate, or transmit a program for use by or in conjunction with an instruction execution system, apparatus, or device.
[0106] Program code embodied on a computer readable medium may be transmitted using any appropriate medium, including but not limited to wireless, wireline, optical fiber cable, RF, etc., or any suitable combination of the foregoing.
[0107] Computer program code for performing the operations of the present invention may be written in one or more programming languages or a combination thereof, including object-oriented programming languages such as Java, Smalltalk, C++, and conventional procedural programming languages such as "C" or similar programming languages. The program code may be executed entirely on the user's computer, partially on the user's computer, as a separate software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer may be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or may be connected to an external computer (e.g., via the Internet using an Internet service provider).
[0108] Embodiment 5
[0109] In an exemplary embodiment, an application product is also provided, including one or more instructions, which can be executed by the processor 301 of the above-mentioned device to complete the above-mentioned flexible production line scheduling method for multi-model parts of a white body.
[0110] Although the embodiments of the present invention have been disclosed above, they are not limited to the applications listed in the specification and the embodiments. It can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily realized. Therefore, without departing from the general concept defined by the claims and equivalent scope, the present invention is not limited to the specific details and the illustrations shown and described here.
Claims
1. A method for scheduling a flexible production line for multi-model body-in-white parts, characterized in that: include: When receiving production request data sent by the workshop central control system, obtaining multiple production order data and finished product online data in the production request data; Put the multiple production order data into the task receiving queue in the order of receipt, put the finished product online data into the finished product pull-in queue, and execute the corresponding control strategies according to the corresponding production order data and finished product online data in turn until the multiple production order data are completed.
2. The method for scheduling a flexible production line for multi-model body-in-white parts according to claim 1, characterized in that: The production order data includes: order type and order information.
3. The method for scheduling a flexible production line for multi-model body-in-white parts according to claim 2 is characterized in that: The order types include: normal orders, pull orders and finished product online orders.
4. The method for scheduling a flexible production line for multi-model body-in-white parts according to claim 3 is characterized in that: The order information includes: vehicle type, task type and serial number.
5. The method for scheduling a flexible production line for multi-model body-in-white parts according to claim 4, characterized in that: The executing corresponding control strategies according to the corresponding production order data and finished product online data includes: When the order type is a normal order, the control strategy is a normal order control strategy, including: Determine that the order information is consistent with the model of any order in the finished product online data: Yes, implement the finished product online order control strategy; No, put the tasks corresponding to the task type into the upper port task queue of the corresponding upper port and the lower port task queue of the corresponding lower port respectively, control the corresponding robots, fixtures, upper port, lower port and process equipment to perform corresponding process operations until the finished parts are placed in the lower port, and send the parts in the lower port to the main welding line of the next process.
6. The method for scheduling a flexible production line for multi-model body-in-white parts according to claim 4, characterized in that: The executing corresponding control strategies according to the corresponding production order data and finished product online data includes: When the order type is a pull order, the control strategy is a pull order control strategy, including: Determine that the order information is consistent with the model of any order in the finished product online data: Yes, implement the finished product online order control strategy; No, put the tasks corresponding to the task type into the upper port task queue corresponding to the upper port and the lower port task queue corresponding to the lower port respectively, and control the corresponding robots, fixtures, upper port, lower port and process equipment to perform corresponding process operations until the completed parts are placed in the lower port and pulled out.
7. The method for scheduling a flexible production line for multi-model body-in-white parts according to claim 4, characterized in that: The executing corresponding control strategies according to the corresponding production order data and finished product online data includes: When the order type is a finished product online order, the control strategy is a finished product online order control strategy, including: placing the task corresponding to the task type into the corresponding downstream task queue, controlling the corresponding robot, fixture and downstream to perform corresponding operations, placing the parts into the downstream, and sending the parts in the downstream to the main welding line of the next process.
8. A flexible production line scheduling device for multi-model body-in-white parts, characterized in that: include: An acquisition module, for acquiring a plurality of production order data and finished product online data in the production request data when receiving the production request data sent by the workshop central control system; An execution module is used to place multiple production order data into a task receiving queue in the order of receipt, place the finished product online data into a finished product pull-in queue, and execute corresponding control strategies according to the corresponding production order data and finished product online data in turn until multiple production order data are completed.
9. A terminal, characterized in that: include: one or more processors; a memory for storing the one or more processor-executable instructions; Wherein, the one or more processors are configured to: Execute a flexible production line scheduling method for multi-model body-in-white parts as described in any one of claims 1 to 7.
10. A non-transitory computer-readable storage medium, characterized in that: When the instructions in the storage medium are executed by the processor of the terminal, the terminal is enabled to execute the method for scheduling a flexible production line for multi-model parts of a body-in-white as described in any one of claims 1 to 7.
Citation Information
Patent Citations
Final-assembly flexible production system and method
CN109263762A
Dynamic scheduling method for getting repaired vehicle online again in welding workshop
CN113238531A
Method for dynamically scheduling multiple off-line repaired vehicles in welding workshop to get on line again
CN113341898A
Workshop comprehensive scheduling system based on order management and rolling optimization production scheduling
CN115471133A
Multi-variety small-batch mixed line machining flexible manufacturing scheduling and executing method and system
CN115826545A